As per case facts, the petitioner submitted bids for two packages and was identified as the lowest tenderer. However, the respondent TIDCL did not issue a Letter of Acceptance, and ...
No Acts & Articles mentioned in this case
TRHC010009542026
Page 1 of 24 2026:THC:933-DB
HIGH COURT OF TRIPURA
AGARTALA
WP(C) No.374 of 2026
R & C Infraengineers Pvt. Ltd., a company, incorporated under the Companies
Act, 2013, having its Head Office at B-2/151, Type-B, opposite Summit
Building, Vishesh Khand, Gomati Nagar, Lucknow, Uttar Pradesh, Pin-
226010. Represented by its Project Manager, namely, Sri Rohit Kumar Singh,
son of Ram Badan Singh, having his Office at Jail Ashram Road, near
Purbasha, P.O.-Agartala, P.S.-East Agartala, District-West Tripura, Pin-
799001.
……… Petitioner(s).
V E R S U S
1. The State of Tripura, represented by the Commissioner & Secretary to the
Department of Industries & Commerce, Government of Tripura, New
Secretariat Complex, Gurkhabasti, Agartala, P.O.-Kunjaban, P.S.-New Capital
Complex, Sub-Division-Sadar, District-West Tripura.
2. The Commissioner & Secretary to the Public Works Depart (R & B),
Government of Tripura, New Secretariat Complex, Gurkhabasti, Agartala,
P.O.-Kunjaban, P.S.-New Capital Complex, Sub-Division-Sadar, District-
West Tripura.
3. Tripura Industrial Development Corporation Ltd. (TIDCL), to be
represented by its Project Director, Government of Tripura, Shilpa Nigam
Bhawan, Khejur Bagan, P.O.-Kunjaban, Agartala, District-West Tripura, Pin-
799006.
4. AXIS Bank Limited, Agartala Branch, to be represented by its Branch
Manager, Banik Tower, HGB Road, Agartala, District-West Tripura, Pin-
799001.
………Respondent(s).
For Petitioner(s) : Mr. Somik Deb, Sr. Advocate,
Mr. Koomar Chakraborty, Advocate.
For Respondent(s) : Mr. B.N. Majumder, Sr. Advocate,
Mr. Karnajit De, Addl. G.A.,
Mr. Kousik Roy, Advocate,
Mr. Rajib Saha, Advocate,
Mr. Ritwick Bhuyan, Advocate,
Mr. Yash Ahuja, Advocate.
HON’BLE THE CHIEF JUSTICE MR. M.S. RAMACHANDRA RAO
HON’BLE MR. JUSTICE BISWAJIT PALIT
CAV reserved on : 06.07.2026.
Judgment delivered on : 20.07.2026.
Whether fit for reporting : YES
TRHC010009542026
Page 2 of 24 2026:THC:933-DB
JUDGMENT & ORDER
(M.S. Ramachandra Rao, C.J.)
1) The issue in this Writ petition relates to validity of invocation by
the Tripura Industrial Corporation Ltd ( for short „TIDCL‟) (respondent no.3)
on 25.5.2026 of 2 Bank Guarantees given as Bid security totalling
Rs.94,24,000/- by petitioner in connection with 2 packages (Packages 11 and
12) under a tender dt.12.9.2025 issued by TIDCL.
2) These Bank guarantees were issued by the Axis Bank Ltd,
Agartala branch.
3) There is no dispute that petitioner submitted it‟s bids under the
above tender for these two packages on 3.11.2025, and the petitioner was
found to be the lowest tenderer, but no Letter of Acceptance was issued to it.
4) Clause 18.1 of the Instructions to Bidders (ITB) /Tender states
that the Bids shall remain valid for the bid validity period specified in the Bid
Data Sheet. The said Bid data Sheet mentions the bid validity period to be 180
days. So these bids of the petitioner were valid under clause 18.1 of the
Tender for 180 days i.e., upto 2.5.2026 only.
5) However the tender contemplates a situation where the bid
validity can also be extended. Clause 18.2 of the ITB provides that:
“in exceptional circumstances, prior to the expiration of the
bid validity period, the Employer may request Bidders to extend the
period of validity of their Bids. The request and the responses shall
be made in writing…. A bidder may refuse the request without
forfeiting it‟s bid security. A bidder granting the request shall not
be required or permitted to modify it‟s bid.”
TRHC010009542026
Page 3 of 24 2026:THC:933-DB
6) In the instant case, admittedly there was no request by TIDCL to
petitioner to extend the bid validity period for the two packages. Therefore the
bids of the petitioner lapsed on 2.5.2026.
7) Both the Bank Guarantees state that the Public Works
Department (R &B) of Govt. of Tripura (respondent no.2) and the TIDCL
(respondent no.3) were the „beneficiary‟ of the Bank Guarantees and they
further state as under:
“At the request of the bidder, we Axis Bank …………hereby
irrevocably undertake to pay you sum not exceeding Rs.……… upon
receipt by us of your first demand in writing accompanied by a
written statement stating that the bidder is in breach of it‟s
obligations under the bid conditions , because the Bidder :
(a) Has withdrawn its Bid during the period of bid validity
specified by the Bidder in the Letter of Technical bid and Letter of
price Bid; or
(b) Does not accept the correction of errors in accordance with
the Instructions to Bidders ( for short „ITB‟) ;
(c) Having been notified of the acceptance of it‟s bid by the
employer during the period of bid validity, (i) fails or refuses to
execute the contract Agreement, or (ii) fails or refuses to furnish the
performance security, in accordance with the ITB , or (iii) fails or
refuses to furnish the domestic preference security , if required.
This guarantee will expire (a) if the bidder is the successful
Bidder, upon receipt of copies of the contract Agreement signed by
the bidder and the Performance security issued to you upon the
instruction of the Bidder; and (b) if the bidder is not successful
Bidder, upon earlier of (i) our receipt of a copy of your notification
to the Bidder of the name of the successful Bidder, or (ii) 28 days
after the expiration of the Bidder‟s bid (c) or till 26.11.2026 ( claim
expiry date) , whichever is earlier.”
TRHC010009542026
Page 4 of 24 2026:THC:933-DB
8) Admittedly vide letter dt.29.4.2026 (Annexure-G), the TIDCL
wrote to petitioner that petitioner had quoted low prices and also no rate/cost
for many items in the two packages, that it had examined the reasons cited by
petitioner in it‟s Letter dt.23.4.2026, and it „may accept‟ the bid prices quoted
by petitioner with the condition that the amount of Performance Security be
increased at the expense of the petitioner to 10% of the contract price for
Package 11 and 7% for Package 12, all other terms and conditions remaining
unchanged. Petitioner was asked to communicate it‟s acceptance of the
condition within 2.5.2026 for further necessary action at it‟s end.
9) The petitioner wrote a letter dt.2.5.2026 (Annexure- H) to the
TIDCL .In that letter it made a counter offer stating that instead of 10%
performance security, it is willing to offer only 5% performance security. It‟s
letter states as under:
“ … we reiterate that the bid prices were determined based
on prevailing market conditions and a competitive pricing
approach. Further , our ongoing project in Agartala has enabled us
to optimise resources and logistics, allowing us to operate with
reduced margins while ensuring efficient execution.
In view of the above, we kindly request your consideration
to permit submission of Performance Security @ 5% without any
additional increment, which will help us maintain adequate cash
flow and facilitate timely project execution.
However, we hereby confirm that in the event the Authority
does not acceded to our above request, we shall comply and submit
the performance Security along with Additional performance
security, strictly in accordance with the directions of the
Authority.”
TRHC010009542026
Page 5 of 24 2026:THC:933-DB
10) To this response of petitioner, TIDCL replied vide letter dt.
5.5.2026 (Annexure – I) disagreeing with petitioner‟s proposal to offer only
5% performance security without additional increment. It directed petitioner to
submit the requisite Additional Performance Security Bank Guarantee over
and above the standard Performance Security/Bank guarantee as per it‟s terms
and conditions communicated earlier.
11) However, in the meantime, the bid validity of petitioner‟s bid
expired on 2.5.2026, as stated supra.
12) Petitioner then wrote letter dt.12.5.2026 (Annexure -3) to TIDCL
stating that it had submitted it‟s bid on 3.11.2025 as per the then prevailing
conditions, that Financial evaluation of tenders was declared on 30.3.2026
showing it as L-1 for both packages, but Letter of Acceptance had not been
issued to it, that due to ongoing war situation and it‟s consequential impact on
the market, the present market conditions have deteriorated significantly,
which is entirely beyond it‟s control. It contended that as per clause ITB 18.1
of Section 2 BDS, since the bid validity period has been stipulated as 180 days
and the validity of it‟s bids had expired on 2.5.2026, it is not willing to grant
any further extension of it‟s bid validity period. It therefore sought return of
it‟s 2 Bank Guarantees for the two packages for which it had submitted bids.
13) The TIDCL then invoked the two Bid Security Bank Guarantees
by writing Annexure letter dt.25.5.2026 (Annexure-4) to the Axis Bank. The
said Letter states :
“3. M/s R & C Infraengineers Pvt.Ltd participated in the
above tenders and submitted bids accordingly. Subsequently, vide
Letter dt.12.5.2026, despite being L-1 , the bidder has expressed its
TRHC010009542026
Page 6 of 24 2026:THC:933-DB
unwillingness to continue in the bid process and requested release
of the aforesaid bank guarantees.
4. In this regard, it is stated that the bid submitted by the
bidder remained valid during the stipulated bid validity period and
the bidder, being the L-1 bidder, was under obligation to honour
the bid conditions during the currency of the bid process. The
communication received from the bidder conveying unwillingness
to continue with the bid process has been treated as withdrawl /
non-complicance with the tender conditions and has adversely
affected the procurement process.
5. Accordingly, as per the terms and conditions governing
the bid security/ bank Guarantee submitted by the bidder, TIDCL
has decided to invoke the aforesaid Bank guarantees furnished
toward the Bid Security.”
6. You are, therefore, requested to invoke the above bank
Guarantees and remit the proceeds to the following bank Account
of TIDCL…” (emphasis supplied)
14) The instant Writ Petition has been filed on 26.5.2026 by the
petitioner to restrain the respondents from acting on the letter dt.25.5.2026
issued by TIDCL, to quash it and to direct the TIDCL to return both Bank
guarantees. Interim relief was also sought to restrain the respondents from
acting in furtherance of the letter dt.25.5.2026.
15) It is stated by both sides that the Axis Bank processed the said
letter dt.25.5.2026 on the same day and paid the amounts covered by both
Bank Guarantees to TIDCL.
16) Petitioner contends that under Clause 24.3 of the ITB of the
Tender documents, no bid may be withdrawn between the deadline for
submission of Bids and the expiration of the period of bid validity i.e.,
between 3.11.2025 and 2.5.2026 only; that there is therefore no restriction to
TRHC010009542026
Page 7 of 24 2026:THC:933-DB
withdraw bids after 2.5.2026; that there was no request for extension of bid
validity by TIDCL or it‟s acceptance in writing by petitioner; that the TIDCL ,
having deliberately abstained from invoking Clause 18.2 , cannot now invoke
the Bank Guarantees as if a bid validity extension had been refused or a
withdrawal has occurred.
17) It is further contended that clause 43.1 of the ITB states that prior
to the expiration of the period of bid validity, the employer shall transmit the
notification of award through issuance of Letter of Acceptance; that
admittedly, no Letter of Acceptance had been issued to petitioner by TIDCL
before 2.5.2026; and so petitioner was entitled to write the letter dt.12.5.2026 ,
after the bid validity expired, to TIDCL to return the Bank Guarantees.
Consequently, TIDCL‟s action in invoking both Bank Guarantees, is arbitrary,
illegal and violates Art.14 and 300-A of the Constitution of India.
18) Petitioner contends that the respondents‟ cannot penalise the
petitioner for their own failure to discharge their mandatory obligation to issue
Letter of Acceptance within the bid validity period.
19) It is also contended that though the financial evaluation results
were declared on 30.3.2026, the TIDCL waited till 29.4.2026 to ask the
petitioner to enhance the Performance Security Guarantee, and then gave time
to petitioner till 2.5.2026 to respond to it. It is contended that the respondent
TIDCL cannot take advantage of it‟s own wrong and penalise the petitioner. It
is further contended that after petitioner‟s bid lapsed on 2.5.2026, the TIDCL
had no authority on 5.5.2026 to demand the enhanced Performance security. It
is also pointed out that as per clause 45.1 of ITB, the obligation to furnish
Performance Security is triggered only “within 28 days of receipt of
TRHC010009542026
Page 8 of 24 2026:THC:933-DB
notification of award through issuance of Letter of Acceptance from the
Employer”, and since LOA was never issued, no obligation to furnish the
Performance Security ever arises.
20) It is further contended that the Bank Guarantees were conditional
Bank Guarantees and none of the conditions precedent for invoking the bank
Guarantee exist in the instant case. There is no withdrawal of bid during the
bid validity period, no issue of correction of errors arose, there was no
notification of acceptance of bid during the period of validity because the
TIDCL demanded extra 10% Performance Security on 29.4.2026, to which the
petitioner made a counter offer on 2.5.2026 offering 5% Performance
Security, and till 5.5.2026, TIDCL had not responded, and in the meantime, on
2.5.2026, the bid validity ended.
21) We find force in the contentions of petitioner.
22) As the TIDCL admits, upon completion of the financial
evaluation process, mere declaration of petitioner as the Lowest Evaluated
Substantially Responsive Bidder does not automatically culminate in the
issuance of the Letter of Acceptance or the formation of a concluded contract
( Para 5.6 an 5.7 of the Counter filed by TIDCL).
23) There was admittedly no issuance of Letter of Acceptance to
petitioner before 2.5.2026 or even thereafter.
24) As per clause 43.1 of the Tender, prior to expiry of the period of
bid validity, the TIDCL shall transmit the Notification of the Award through
issuance of Letter of Acceptance. Under clause 43.3, until a formal contract is
prepared and executed, the notification of award through issuance of Letter of
TRHC010009542026
Page 9 of 24 2026:THC:933-DB
Acceptance shall constitute a binding contract. So after 2.5.2026, it cannot
issue the Letter of Acceptance or create a binding contract.
25) The crucial question in this case relates to the validity of the
petitioner‟s bid.
26) TIDCL‟s plea in para 5.10 of it‟s counter is that petitioner‟s
continued correspondence prior to and also on 2.5.2026 indicated that
petitioner was actively participating in the post qualification and evaluation
process and unequivocally demonstrated it‟s intention to continue with the
procurement process.
27) We may point out that in it‟s letter dt.29.4.2026 sent to
petitioner, TIDCL stated that in terms of Clause 38.4, it „may accept „ the bid
prices for Packages 11 and 12 with the condition that amount of performance
security be increased to 10% and 7% of the contract price. The words „may
accept‟ used in the said Letter show that it still retained the choice „not to
accept‟ even if petitioner were to agree for it‟s new conditions. There is no
„unequivocal‟ statement in this letter that TIDCL „will accept‟ the petitioner‟s
price bids if the petitioner gives the enhanced Performance Security it wants.
28) The contents of the Letter dt.2.5.2026 written by petitioner to the
TIDCL, in reply to the Letter dt.29.4.2026 of TIDCL, have to be therefore
understood keeping in mind that TIDCL itself had not given a clear, definite
and final decision that if petitioner agrees to the new conditions proposed by
it, it will accept petitioners bids.
29) In the Letter dt.2.5.2026 written by petitioner to the TIDCL,
petitioner had objected to the demand of the TIDCL to give 10% and 7 %
TRHC010009542026
Page 10 of 24 2026:THC:933-DB
Performance Security for each of the packages and made a counter offer of
only 5% Performance Security.
30) So the TIDCL cannot contend that petitioner‟s Letter shows an
„unequivocal‟ intention to continue the procurement process. No doubt
petitioner did say in the last para of the said letter as under:
“However, we hereby confirm that in the event the Authority
does not acceded to our above request, we shall comply and submit
the performance Security along with Additional performance
security, strictly in accordance with the directions of the
Authority.” (emphasis supplied)
31) We are of the view that parties were still negotiating at that stage
(i.e., on 2.5.2026) whether they can agree on a middle ground or not and the
petitioner was awaiting the response of the TIDCL to it‟s counter offer (of
only 5 % increase in Performance security).
32) Even according to the TIDCL, the last day of the bid validity
period was 2.5.2026. It is undisputed that it never sought extension of bid
validity from petitioner under clause 18.2. The TIDCL responded only on
5.5.2026, after the bid validity expired.
33) The TIDCL cannot contend that the bid validity stood extended
by the conduct of petitioner because the ITB specifically states in Clause 18.2
that if the TIDCL wants a bid extension, it has to make a request to petitioner
in writing, and the petitioner has to agree to it also in writing. As there was no
such extension of bid validity sought by TIDCL before 2.5.2026, petitioner‟s
bid lapsed on 2.5.2026 notwithstanding the petitioner writing the Letter
dt.2.5.2026 and TIDCL cannot interpret the said Letter as extending the bid
validity contrary to the ITB clause 18.2.
TRHC010009542026
Page 11 of 24 2026:THC:933-DB
34) The plea of TIDCL that the assurance of petitioner quoted above
is unequivocal, unconditional and binding on it and that it created a legitimate
and bonafide expectation in it‟s favor that petitioner intended to honor it‟s bid
and proceed with the execution of the works, cannot therefore be
countenanced.
35) The Court can also take judicial notice also of the fact that the
market conditions on the basis of which the petitioner submitted it‟s bid in
November, 2025 changed after the Iran-USA Middle East war which started
in February, 2026 and is still continuing in July, 2026.
36) So the petitioner was entitled to mention this in it‟s letter
dt.23.4.2026 (Annexure-F) where it stated that the „present market situation
has deteriorated significantly‟, which it again reiterated in it‟s letter
dt.2.5.2026 to oppose the demand of TIDCL for the increase to 10% / 7%
Performance of contract value while making it‟s counter offer of only 5%.
37) The action of the TIDCL in insisting that the petitioner should
stick to it‟s quoted prices for the two packages even in such a situation is
arbitrary, unreasonable and cannot be countenanced.
38) We can view the issue from another angle i.e, whether the
invocation of the Bank guarantees by TIDCL is valid in law?
39) It is settled law that invocation of the Bank guarantee will have
to be in accordance with the terms of the Bank Guarantee or else, the
invocation itself will be bad. (see Hindustan Construction Co. Ltd v. State of
Bihar
1
.)
1
(1999) 8 SCC 436
TRHC010009542026
Page 12 of 24 2026:THC:933-DB
40) So we shall examine the terms of the Bank Guarantees and see
whether TIDCL has invoked them as per their terms or not.
41) The following are the terms of the Bank Guarantees terms:
“At the request of the bidder, we Axis Bank …………hereby
irrevocably undertake to pay you sum not exceeding Rs.……… upon
receipt by us of your first demand in writing accompanied by a
written statement stating that the bidder is in breach of it‟s
obligations under the bid conditions , because the Bidder :
(a) Has withdrawn its Bid during the period of bid validity
specified by the Bidder in the Letter of Technical bid and Letter of
price Bid; or
(b) Does not accept the correction of errors in accordance with
the Instructions to Bidders ( for short „ITB‟) ;
(c) Having been notified of the acceptance of it‟s bid by the
employer during the period of bid validity, (i) fails or refuses to
execute the contract Agreement, or (ii) fails or refuses to furnish the
performance security, in accordance with the ITB , or (iii) fails or
refuses to furnish the domestic preference security , if required.”
42) No doubt if the TIDCL makes demand, the Axis Bank has to pay
the amount covered by the Bank Guarantee if the TIDCL gives written
statement that one or other events mentioned therein have occurred. The Bank
cannot question it.
43) But even according to TIDCL, during the period of bid validity,
the petitioner had not withdrawn it‟s bid. The withdrawal of the bid was
admittedly on 13.5.2026, long after the bid validity expired on 2.5.2026. So
clause (a) of the Bank Guarantees, is inapplicable.
44) There is also no issue of correction of errors. So clause (b) of the
Bank Guarantees, has no relevance.
TRHC010009542026
Page 13 of 24 2026:THC:933-DB
45) Coming to clause (c) (i) of the Bank Guarantees, admittedly the
acceptance by TIDCL of bids of petitioner in it‟s letter dt.29.4.2026 was not
definite (It had used the words „may accept‟) and it was further subject to
condition of the petitioner agreeing to it‟s demand to increase the
Performance Security to 10% of the contract price for one package and 7%
for another package.
As a matter of law, when there is variance between the offer and
the acceptance in respect of any material term, acceptance cannot be said to
be absolute and unqualified and the same will not result in the formation of a
legal contract.
Moreover TIDCL itself on 29.4.2026 gave time to petitioner up
to 2.5.2026 to communicate it‟s acceptance of increase in Performance
Security knowing fully well that the said date is the last date of bid validity of
petitioner‟s bid. It did not bother to seek extension of bid validity in writing
under clause 18.2.
On 2.5.2026, petitioner objected to it‟s demand and made a
counter offer of 5% increase of Performance Security only. It stated that only
if the TIDCL does not agree to it, petitioner will act as per demand of TIDCL.
Instead of sending it‟s response on 2.5.2026, TIDCL delayed it‟s
response till 5.5.2026. By that date, the bid validity had expired.
We hold that there was no consensus ad idem between the parties
during the period of bid validity i.e before or on 2.5.2026 , and that was why
Letter of Acceptance was also not issued to petitioner by TIDCL. Thus, it
cannot be said that during the period of bid validity, petitioner failed or
TRHC010009542026
Page 14 of 24 2026:THC:933-DB
refused to execute the contract Agreement. So clause (c) (i) condition was not
fulfilled.
46) Further as per cause (c)(ii), during the period of bid validity, the
petitioner should have failed or refused to furnish the performance security, in
accordance with the ITB.
Admittedly, the Petitioner was willing to furnish the Performance
Security indicated in the ITB , but the TIDCL wanted the Performance
Security to be more i.e., increased to 10% and 7% respectively. So clause
(c)(ii) is also not attracted.
47) Consequently, the statement in the letter dt.25.5.2026 issued by
TIDCL to the Axis Bank invoking the Bank Guarantees that:
“In this regard, it is stated that the bid submitted by the
bidder remained valid during the stipulated bid validity period and
the bidder, being the L-1 bidder, was under obligation to honour
the bid conditions during the currency of the bid process. The
communication received from the bidder conveying unwillingness
to continue with the bid process has been treated as withdrawal /
non-compliance with the tender conditions and has adversely
affected the procurement process”
cannot be accepted firstly, because the petitioner is not bound by the bid after
2.5.2026 because there was no valid bid extension beyond it; secondly,
because it had not withdrawn the bid during the validity of the period of the
bid before 2.5.2026; and thirdly, the term „currency of bid process‟ has no
meaning after 2.5.2026, and there cannot be continuation of the bid process
after the bid validity expired.
48) TIDCL is permitted to invoke the Bid Security Guarantees only
on fulfillment of conditions mentioned therein. When none of those
TRHC010009542026
Page 15 of 24 2026:THC:933-DB
conditions were fulfilled, it cannot invoke them. In these circumstances, we
hold that by invoking them without valid justification, it had acted arbitrarily,
unreasonably and illegally violating Art.14 and Art.300-A of the Constitution
of India. It cannot in law be permitted to retain the same.
49) In Techno Power Enterprises (P) Ltd. v. Food Corpn. of
India
2
, a case which is similar to instant case on facts, it was held:
“12. It is apparent from the above that the bid security
could be forfeited if the petitioner had withdrawn its bid during the
period of bid validity as specified in the RFP. The RFP provided for
the bid validity period of one hundred and twenty days. Admittedly,
there is no provision in the RFP which provides for a bid validity
period for more than one hundred and twenty days from the bid due
date. Thus, there can be no dispute that the petitioner had not
withdrawn its bid during the validity period as specified in the RFP.
There is no allegation that the petitioner had engaged in any
corrupt, fraudulent, coercive, undesirable or restrictive practices as
specified in Clause 4 of the RFP documents.
13. In view of the above, there is no ground for the FCI to
retain the bid security (bank guarantees) furnished by the
petitioner.
14. The decision in the case of Gujarat Maritime Board
(supra) is of little assistance to the petitioner. There is no dispute
that a bank guarantee constitutes a separate agreement between the
bank and the beneficiary and the courts would not interdict
invocation of the bank guarantees except in cases of egregious
fraud and irretrievable injuries. In the present case, there is no
dispute with regard to the invocation of the bank guarantees. The
principal controversy relates to the validity of the petitioner‟s bid.
Concededly, if it is accepted that the validity of the petitioner‟s bid
(offer) had expired or was withdrawn after the bid validity period
2
2018 SCC OnLine Del 9740 : AIR 2019 (NOC 260) 86
TRHC010009542026
Page 16 of 24 2026:THC:933-DB
as specified in the RFP, the impugned letters accepting the offer
would be of no consequence. It is also not disputed that in the
circumstances, the FCI would be obliged to refund the bid
security.” (emphasis supplied)
50) Similar view was also taken by the Bombay High Court in Great
Eastern Energy Corporation ltd. v. Jain Irrigation Systems Ltd
3
.
51) We fail to understand why the TIDCL, after issuing the tender on
12.9.2025 dragged it‟s feet till 30.3.2026 to complete the financial evaluation
of the various bids, and even thereafter waited till 29.4.2026 to conditionally
accept petitioner‟s bids, gave time to petitioner to respond till 2.5.2026, and
even thereafter waited till 5.5.2026 to take action.
52) Coming to the tenuous objection raised by TIDCL about
maintainability of the Writ Petition because it allegedly relates to contractual
matters, we may refer to the decision of the Supreme Court in Unitech Ltd. v.
Telangana State Industrial Infrastructure Corpn.
4
.
In that case, the Supreme Court has held that recourse to the
jurisdiction under Article 226 of the Constitution is not excluded altogether in
a contractual matters where the State or it‟s instrumentality has acted
arbitrarily , unfairly or unreasonably in that arena. A public law remedy is
available for enforcing legal rights subject to well-settled parameters. It
declared:
“38……However, to clear the ground, it is necessary to
postulate that recourse to the jurisdiction under Article 226 of the
Constitution is not excluded altogether in a contractual matter. A
3
(2010) SCC ONLINE BOM 248
4
(2021) 16 SCC 35, at page 59 :
TRHC010009542026
Page 17 of 24 2026:THC:933-DB
public law remedy is available for enforcing legal rights subject to
well-settled parameters.
39. A two-Judge Bench of this Court in ABL International
Ltd. v. Export Credit Guarantee Corpn. of India Ltd.
5
[ABL
International] analysed a long line of precedent of this Court15 to
conclude that writs under Article 226 are maintainable for
asserting contractual rights against the State, or its
instrumentalities, as defined under Article 12 of the Indian
Constitution.
39.1. Speaking through N. Santosh Hegde, J. the Court held
: (ABL International case14, SCC p. 572, para 27)
“27. … the following legal principles emerge as to the
maintainability of a writ petition:
(a) In an appropriate case, a writ petition as against a State
or an instrumentality of a State arising out of a contractual
obligation is maintainable.
(b) Merely because some disputed questions of fact arise for
consideration, same cannot be a ground to refuse to entertain a writ
petition in all cases as a matter of rule.
(c) A writ petition involving a consequential relief of
monetary claim is also maintainable.”
This exposition has been followed by this Court, and has
been adopted by the three-Judge Bench decisions of this Court in
State of U.P. v. Sudhir Kumar Singh
6
and Popatrao Vyankatrao
Patil v. State of Maharashtra
7
.
39.2. The decision in ABL International, cautions that the
plenary power under Article 226 must be used with circumspection
when other remedies have been provided by the contract. But as a
statement of principle, the jurisdiction under Article 226 is not
excluded in contractual matters.
5
(2004) 3 SCC 553
6
(2021) 19 SCC 706
7
(2020) (19) SCC 241
TRHC010009542026
Page 18 of 24 2026:THC:933-DB
39.3. Article 23.1 of the development agreement in the
present case mandates the parties to resolve their disputes through
an arbitration. However, the presence of an arbitration clause
within a contract between a State instrumentality and a private
party has not acted as an absolute bar to availing remedies under
Article 22618.
39.4. If the State instrumentality violates its constitutional
mandate under Article 14 to act fairly and reasonably, relief under
the plenary powers of Article 226 of the Constitution would lie. This
principle was recognised in ABL International : (ABL
International case, SCC p. 572, para 28)
“28. However, while entertaining an objection as to the
maintainability of a writ petition under Article 226 of the
Constitution of India, the court should bear in mind the fact that the
power to issue prerogative writs under Article 226 of the
Constitution is plenary in nature and is not limited by any other
provisions of the Constitution. The High Court having regard to the
facts of the case, has a discretion to entertain or not to entertain a
writ petition. The Court has imposed upon itself certain restrictions
in the exercise of this power. (See Whirlpool Corpn. v. Registrar of
Trade Marks19.) And this plenary right of the High Court to issue
a prerogative writ will not normally be exercised by the Court to
the exclusion of other available remedies unless such action of the
State or its instrumentality is arbitrary and unreasonable so as to
violate the constitutional mandate of Article 14 or for other valid
and legitimate reasons, for which the Court thinks it necessary to
exercise the said jurisdiction.”
(emphasis supplied)
39.5. Therefore, while exercising its jurisdiction under
Article 226, the Court is entitled to enquire into whether the action
of the State or its instrumentalities is arbitrary or unfair and in
consequence, in violation of Article 14. The jurisdiction under
TRHC010009542026
Page 19 of 24 2026:THC:933-DB
Article 226 is a valuable constitutional safeguard against an
arbitrary exercise of State power or a misuse of authority.
39.6. In determining as to whether the jurisdiction should
be exercised in a contractual dispute, the Court must, undoubtedly
eschew, disputed questions of fact which would depend upon an
evidentiary determination requiring a trial. But equally, it is well
settled that the jurisdiction under Article 226 cannot be ousted only
on the basis that the dispute pertains to the contractual arena. This
is for the simple reason that the State and its instrumentalities are
not exempt from the duty to act fairly merely because in their
business dealings they have entered into the realm of contract.
Similarly, the presence of an arbitration clause does (sic not) oust
the jurisdiction under Article 226 in all cases though, it still needs
to be decided from case to case as to whether recourse to a public
law remedy can justifiably be invoked.
39.7. The jurisdiction under Article 226 was rightly invoked
by the Single Judge and the Division Bench of the Andhra Pradesh
High Court in this case, when the foundational representation of
the contract has failed. TSIIC, a State instrumentality, has not just
reneged on its contractual obligation, but hoarded the refund of the
principal and interest on the consideration that was paid by
Unitech over a decade ago. It does not dispute the entitlement of
Unitech to the refund of its principal.”
53) We therefore reject the plea of the TIDCL that petitioner had
sought to give an artificial Constitutional colour to what is essentially a purely
contractual dispute arising out of the terms and conditions of a commercial
tender and the invocation of an unconditional Bid Security Bank Guarantee,
and that it‟s allegations of violation of Art.14, 21 and 300-A of the
Constitution are misconceived and that no fundamental or Constitutional right
of petitioner has been infringed,.
TRHC010009542026
Page 20 of 24 2026:THC:933-DB
54) There is also no merit in the contention raised by TIDCL about
suppression of facts in para 6.1 of it‟s counter affidavit.
The letter dt.27.10.2025 of petitioner‟s Technical bid has no
relevance.
The Letter dt.2.5.2026 of petitioner has been filed as Annexure
H.
The Bank Guarantee copies having been filed, there cannot be
said to be a suppression of actual validity and claim period of the bank
Guarantees.
When the ITB in it‟s entirety has been filed by petitioner on
9.6.2026, to say that clause 19.7 has been suppressed, is ridiculous.
The subsequent letter dt.13.5.2026 of petitioner has not been
filed, but this loses it‟s significance because it is an event long after 2.5.2026
when the bid validity expired. The TIDCL has filed it anyway.
55) The reliance of TIDCL on clause 19.7 permitting forfeiture of
bid security by TIDCL is of no avail because
(i) petitioner had not withdrawn it‟s bid during the period of
bid validity,
(ii) and no contract was offered for petitioner to sign by
TIDCL.
(iii) The question of petitioner failing to furnish performance
security in accordance with ITB 45 does not arise because the
said clause provides for furnishing it within 28 days of receipt of
notification of award through issuance of Letter of acceptance
TRHC010009542026
Page 21 of 24 2026:THC:933-DB
from the TIDCL. Such Letter of Acceptance, never having been
issued, this does not apply.
56) There is also no merit in the plea of TIDCL in para 7.4 that mere
declaration of petitioner as Lowest Evaluated Substantially Responsive
Bidder (L-1) for the two packages creates a corresponding obligation to
honour it‟s bid.
This plea contradicts it‟s own plea in para 5.7 that declaration of
petitioner as Lowest Evaluated Substantially Responsive Bidder (L-1) for the
two packages does not automatically culminate in the formation of a
concluded contract.
Unless a concluded contract comes into existence, there is no
obligation of petitioner to honour it‟s bid, after the bid‟s validity expired.
57) Coming to plea of TIDCL in para 7.5 of the counter affidavit,
merely because the validity of the bank Guarantees was extended by 28 days
beyond bid validity period under clause 19.3 of ITB, the TIDCL cannot
violate the terms of the ITB and insist that validity of bid stands extended
beyond 2.5.2026, and claim that it can invoke the bank Guarantees even
though no condition specified for it‟s invocation is fulfilled, as explained
above.
58) We also do not agree with the plea of the TIDCL in para 7.6 and
7.8 that Bid security does not become automatically refundable upon the
expiry of the Bid Validity period.
Once the bid of petitioner lapsed on 2.5.2026, there is no bid of
petitioner in existence in the eye of law which can be accepted to create a
contract.
TRHC010009542026
Page 22 of 24 2026:THC:933-DB
So it was the obligation of TIDCL to conclude the contract by
issuing Letter of Acceptance during the period of bid validity, and having
failed to do so, it cannot fall back on clause 19.3 or clause 19.7. So it was
obligated to return both Bank Guarantees to petitioner.
59) Whatever be the justification offered in para 7.7 of the counter
affidavit for the delay in TIDCL‟s slowness in taking action, it could have
speeded up it‟s actions knowing that it has only 6 months to complete the
process. Alternatively, it could have asked in writing under Clause 18.2 for a
bid validity extension and got the bid validity extended if it felt that some
more time is required and it cannot finalise the award./contract by 2.5.2026.
It has only itself to blame for the situation.
60) There is also no merit in the plea raised in para 8.6 of the counter
affidavit that clause 19.7 (a) states “notwithstanding clause 24.3” and so the
bid security can be forfeited, if the bidder withdraws it‟s bid during the bid
validity period specified by the bidder. In the instant case, there was no
withdrawal of petitioner‟s bid before 2.5.2026, the last date of expiry of bid
validity, and so clause 19.7 has no application.
61) The further plea in para 8.8. of the counter affidavit that the
procurement process remained active and ongoing after 2.5.2026 cannot be
countenanced because if the bid validity extension was not sought under
clause 18.2 in writing by TIDCL, and not agreed to in writing by petitioner
before 2.5.2026, there was no scope of TIDCL keeping the procurement
process active after 2.5.2026 as a matter of law, and acting on petitioner's bid
by TIDCL after 2.5.2026.
TRHC010009542026
Page 23 of 24 2026:THC:933-DB
62) We do not agree with plea of TIDCL in para 8.10 that
petitioner‟s letter dt.2.5.2026 contained an unequivocal undertaking that it
would comply with enhanced performance security arrangements if such
relaxation was not granted because it also said it will agree only to 5%
enhancement and not 7% or 10% as sought by TIDCL.
63) With regard to stand of TIDCL that the bank guarantee is
„unconditional‟ we agree since it asks the Axis bank to pay on first demand.
64) But that is different from saying that TIDCL could have invoked
it when conditions contained in them to be fulfilled before their invocation do
not exist. TIDCL cannot be permitted to mislead the Bank as to fulfilment of
conditions therein, invoke them and then retain the amount paid by the Bank
to it. That would be a travesty of justice.
65) All other contentions raised by the TIDCL also have no merit for
the aforesaid reasons.
66) It is true that the petitioner had sought to restrain the Axis Bank
to make payment to TIDCL after the Bank Guarantees were invoked on
25.5.2026 in this Writ Petition filed on 26.5.2026. But, merely because the
amount covered by the Bank Guarantees has been paid on 25.5.2026, this
court is not helpless and it is entitled as a Constitutional Court to mould relief
appropriately to do complete justice.
67) In Vashist Narayan Kumar v. State of Bihar
8
, the Supreme
Court held :
“25. …. A writ court has the power to mould the relief.
Justice cannot be forsaken on the altar of technicalities.”
8
(2024) 11 SCC 785, at page 791
TRHC010009542026
Page 24 of 24 2026:THC:933-DB
68) In M. Sudakar v. V. Manoharan
9
, also the Supreme Court
declared:
“4. The power to mould relief is always available to the
court possessed with the power to issue high prerogative writs. In
order to do complete justice it can mould the relief, depending upon
the facts and circumstances of the case. In the facts of a given case
a writ petitioner may not be entitled to the specific relief claimed by
him but this itself will not preclude the writ court to grant such
other relief which he is otherwise entitled.”
69) Accordingly, we allow the Writ Petition and direct the TIDCL
(respondent no.3) to pay to the petitioner the amount of Rs.94,24,000/- (which
the Axis Bank has paid it on 25.5.2026 under the two Bank Guarantees) with
interest at 12% p.a on the said amount from 25.5.2026 till actual payment
within 4 weeks from today. The TIDCL shall also pay costs of Rs.25,000/- to
petitioner within 4 weeks from today.
70) All pending Miscellaneous applications shall stand disposed of.
(BISWAJIT PALIT, J) (M.S. RAMACHANDRA RAO, CJ)
9
(2011) 1 SCC 484
Legal Notes
Add a Note....