As per case facts, a construction company completed bridge work for the State but faced non-payment of outstanding bills and cost escalation claims, despite assurances and a legal notice. This ...
1
Serial No. 02
Regular List
HIGH COURT OF MEGHALAYA
AT SHILLONG
WP(C) No. 30 of 2023
Reserved Date: 17.06.2026
Pronouncement Date: 14.09.2026
M/s. Ashima Projects Pvt. Ltd.,
Through its Director, Shri. Upendra Nath Saha,
having its registered office at : Room No. 6,
Council Building, Tura Bazar, P.O. & P.S.
Tura, West Garo Hills, Meghalaya-794001.
…… Petitioner
- Vs-
1. State of Meghalaya through its Chief Secretary,
Government of Meghalaya.
2. The Chief Engineer (NH), P.W.D. (Roads),
Government of Meghalaya.
3. The Executive Engineer, P.W.D. (Roads),
Baghmara NH Division, Baghmara,
South Garo Hills, Meghalaya
4. The Regional Officer
Ministry of Surface, Road & Highways,
Rajgarh Road, Guwahati – 781003.
……… Respondents
Coram:
Hon’ble Mr. Justice W. Diengdoh, Judge.
Appearance:
For the Petitioner/Appellant(s) : Mr. D. Sahu, Adv.
Mr. P.R. Paske, Adv.
For the Respondent(s) : Mr. N.D. Chullai, AAG with
Ms. R. Colney, GA. for R 1-3. 2026:MLHC:1032
2
Dr. N. Mozika, DSGI with
Ms. K. Gurung, Adv. for R 4.
i) Whether approved for reporting in Yes/No
Law journals etc.:
ii) Whether approved for publication
in press: Yes/No
JUDGMENT AND ORDER
1. Pleadings found in this petition reveals that the petitioner is a private
limited construction company, registered under the Indian Companies Act. 1956.
It is also registered as a Class-I Government Contractor of a number of
government departments, e.g., PWD, PHED, MePDCL.
2. In the year 2007-2008, a tender was floated for construction of a
High-Level Bridge across the river Dabua at Gasuapara in KM 187 on NH-62,
including approaches in South Garo Hills District of Meghalaya. The petitioner
having participated in the said bidding process, was accordingly awarded the
contract vide Final Work Order No. PW/TB/BR/74/2005/Pt/13 dated 01.10.2007
for the amount of ₹ 3,00,35,800/- (Rupees Three Crore, Thirty-Five Thousand,
Eight Hundred) only. Then, after completing the work in the year 2014, the
petitioner raised the total bill of ₹ 3,04,62,164/- (Rupees Three Crore, Four Lakh,
Sixty-Two Thousand, One Hundred and Sixty-Four) only.
3. It is stated in the petition that on completion of the said contract
work/project in the year 2014, on being satisfied thereof, the respondent 2026:MLHC:1032
3
authority took charge of the same by issuing a completion certificate to the
petitioner.
4. The petitioner was assured by the concerned department that the final
bill will be cleared soon, he waited for the same for a few months, however,
inspite of such assurance, the said bills have not been paid till date.
5. That in the meantime, the relevant respondent sought for undertaking
of some additional/supplementary work pertaining to CC wearing coat at bridge
No. 186/8 for which the working estimates have been prepared and duly
approved by the Office of the Additional Chief Engineer, PWD (Roads) Western
Zone, the total amount of which comes to ₹ 4,31,000/- (Rupees Four Lakh,
Thirty-One Thousand) only. In this regard, a Tender Process was also carried
out for the said work and the petitioner being the successful bidder, a preliminary
work order vide letter No. PW/WZ/CS-4/NH-62/2017-18/2 dated 07.07.2017
was also issued in favour of the petitioner. The Final Work Order was eventually
issued by the Office of the Additional Chief Engineer, PWD (Roads) Western
Zone, Tura, Government of Meghalaya, vide letter dated 10.07.2017.
6. The department having failed to fulfil to settle the said outstanding
bills, the petitioner issued several letters to the Executive Engineer, PWD
(Roads), Baghmara NH Division ranging from 25.02.2014 to 23.03.2021, the
respondent department has failed to clear the outstanding bills amounting to ₹
3,04,62,164/- (Rupees Three Crore, Four Lakh, Sixty-Two Thousand, One 2026:MLHC:1032
4
Hundred and Sixty-Four) only.
7. Inspite of a number of letters sent to the department, the said
outstanding bills not being paid, the petitioner was compelled to issue a Legal
Notice dated 23.04.2021. Such action of the respondent department
demonstrating lack of interest, the same being arbitrary, illegal and tantamount
to violation of Article 14 of the Constitution and other legal rights of the
petitioner which permits the approach before this Court with this instant petition
under Article 226 of the Constitution.
8. Mr. D. Sahu, learned counsel for the petitioner has submitted that
during the construction period, the petitioner has raised 3 Nos. of AR (Running)
Bills bearing Nos. CC-I for ₹ 30,03,580/- (Rupees Thirty Lakh, Three Thousand,
Five Hundred Eighty) only; CC-II for ₹ 41,20,081/- (Rupees Forty One Lakh,
Twenty Thousand, Eighty One) only and CC-III for ₹ 60,92,538/- (Rupees Sixty
Lakh, Ninety Two Thousand, Five Hundred Thirty Eight) only (Total AR Bills
raised for ₹1,32,16,199/-). The respondent has released payment against the
three running bills amounting to ₹ 1,18,25,724/- (Rupees One Crore, Eighteen
Lakh, Twenty-Five Thousand, Seven Hundred Twenty-Four) only after
deducting ₹ 11,89,475/-.
9. It is further submitted that the petitioner has submitted the final bill
bearing No. FCC-IV/243BGNH dated 15.12.2014 for ₹ 3,00,36,148/- out of
which ₹ 1,33,88,983/- was released to the petitioner through running bills and 2026:MLHC:1032
5
the remaining amount of ₹ 1,66,47,165/- against the final bill has not been paid
yet.
10. Demand was also raised as regard cost escalation during the material
period for which the petitioner has raised demand for cost escalation bill dated
05.01.2015 amounting to ₹ 1,19,83,919/- and that the total outstanding amount
entitled to by the petitioner is ₹ 2,86,31,084/-.
11. The learned counsel has also submitted that, by not releasing the
petitioner’s legitimate dues, the same is violative of Article 14 of the
Constitution, arbitrariness being apparent in such act of unreasonableness. As
such, this Court exercising jurisdiction under Article 226 of the Constitution can
direct the respondents to release the outstanding dues of the petitioner. The case
of M/s Gvpr Engineers Ltd. v. The Managing Director, Karnataka Neevari
Nigam Ltd. [WP(C) No. 8182 of 2022], reported in 2024 Supreme (Kar) 210
has been referred to in support of this contention.
12. The learned counsel for the petitioner has also submitted that for the
delay in payment of the dues of the petitioner, therefore, interest on such delayed
payment till final release of the said dues has to be made to the petitioner. The
case of State of Kerala v. P. Edward John, 2015 (Supreme Online (Ker),
46582, para 17 & 22 has been cited in this regard.
13. On the issue of limitation, the learned counsel has submitted that the 2026:MLHC:1032
6
provisions of the Limitation Act are not applicable to reliefs sought for on an
application under Article 226. Though it is admitted that it was incumbent upon
the petitioner to approach the court within a reasonable time period, however,
the same depends on the facts and circumstances of each case. The case of Shri
Vallabh Glass Works Ltd. & Anr v. Union of India & Ors, (1984) 3 SCC
362, para 9 as well as the case of Sachindra Nath Sen Gupta v. General
Manager, NEF Railway, 1973 AIR (Gua) 108, para 4 was referred to, to
sustain this contention.
14. Finally, the learned counsel has argued that in a writ petition
involving disputed question of facts or for a monetary claim, the same is
maintainable in exercise of the discretionary powers of the court. The case of
ABL International Ltd. V. Export Credit Guarantee Corporation of India
Ltd., (2004) 3 SCC 553 has been put into service in this connection.
15. Mr. N.D. Chullai, learned AAG assisted by Ms. R. Colney, learned
GA appearing for the State respondents No. 1-3, in his response has submitted
that admittedly, the work for reconstruction of the High-Level Bridge over the
river Dabua at Gasuapara, is a project sanctioned by the Ministry of Road
Transport and Highways (MoRTH), Government of India.
16. However, in the instant case, no fund towards payment of the
contractual dues have been released by the sanctioning authority to the
Government Department (PWD) for disbursement of the same to the 2026:MLHC:1032
7
contractor/petitioner.
17. The first objection raised by the learned AAG is on the issue of
maintainability of this petition. It is the contention of the learned AAG that
through this writ, the petitioner seeks enforcement of contractual dues arising
from works contracts. As such, dispute involving payment of dues etc. are in the
realm of private law remedy which the petitioner ought to have resorted to and
not by way of a writ petition. To this contention, the case of Union of India &
Ors. v. Puna Hinda, (2021) 10 SCC 690, para 18 & 24 was referred to by the
learned AAG in support of his case.
18. The next contention of the learned AAG is with regard to the fact
that though, in the contract agreement, there is an arbitration clause which
provides for settlement of disputed contractual claims through the medium of
arbitration, this alternative remedy being available, the petitioner is therefore
precluded to seek redressal of his alleged grievance by way of a writ petition
under Article 226 of the Constitution. To this, the case of Joshi Technologies
International INC. v. Union of India and Ors. (2015) 7 SCC 728, para 55, 59,
69.2 has been cited.
19. The next point of contention raised by the learned AAG is on the
issue of delay and laches where it was said that the petitioner for alleged failure
of the concerned department to clear his contractual dues relevant for the year
2014, he has approached this Court by way of this writ petition only in the year 2026:MLHC:1032
8
2023, knowing fully well that, if he had proceeded by the regular process by
approaching the civil court, his claim would be hit by limitation as per the
provisions of the Limitation Act, therefore, to skirt such process, he has come
before this Court with this instant petition. The action of the petitioner in this
respect cannot be condoned, as such, this petition being hit by delay and laches,
the same ought to be dismissed in limine, submits the learned AAG. On this, the
case of State of Maharashtra v. Digambar, (1995) 4 SCC 683, para 14; has
been referred to.
20. Dr. N. Mozika, learned DSGI assisted by Ms. K. Gurung, learned
appearing for the respondent No. 4/Regional Officer (MoRTH), Guwahati in his
argument, has raised similar contentions as was done by the learned AAG for
the State respondent as far as the issue of disputed question of facts is concerned
and also on the point of an alternate remedy being available to the petitioner.
That the petitioner has suppressed the fact that there was an arbitration clause in
the Contract agreement, vis-a-vis reference of dispute arising out of the contract
to arbitration was also another contention brought forth by the learned DSGI
while presenting his argument in favour of the respondent No. 4. Finally, that
there was delay and laches on the part of the petitioner in preferring this petition
before this Court, therefore, the same ought to be dismissed on this ground too,
is also the submission of the learned DSGI.
21. It is also the submission of the learned DSGI that under the contract 2026:MLHC:1032
9
there is no provision for price escalation, as such, the amount of ₹1,19,83,919/-
(Rupees One Crore, Nineteen Lakh, Eighty-Three Thousand, Nine Hundred
Nineteen) only submitted to the respondent No. 3 herein was not received by the
respondent No. 4.
22. Therefore, in view of such disputed factual situation, this petition is
liable to be dismissed on this ground alone, since the petitioner has an alternate
redressal forum in the form of a civil court of competent jurisdiction, submits
the learned DSGI.
23. This Court, on consideration of the submission made by the learned
counsel for the parties herein, has also looked into the contents of the petition as
well as the counter-affidavit filed by the State respondents No. 1, 2 & 3 and also
respondent No. 4 respectively. The rejoinder to the said affidavit has also been
taken note of.
24. What is apparent is that there was a contract agreement executed
between the petitioner and the relevant respondent authorities for construction
of the High-Level Bridge across the river Dabua at Gasuapara in KM 187 on
NH-62, including approaches in South Garo Hills District of Meghalaya. The
petitioner has however stated at para 4 of this petition that the total bill amount
raised and submitted to the respondent is ₹ 3,04,62,164/- (Rupees Three Crore,
Four Lakh, Sixty-Two Thousand, One Hundred Sixty-Four) only which was not
disputed by the respondent department. 2026:MLHC:1032
10
25. As have been noticed hereinabove, the learned counsel for the
petitioner, in course of argument, have mentioned an amount of ₹ 4,31,000/-
(Rupees Four Lakh, Thirty-One Thousand) only, being the total amount for
carrying out additional/supplementary work in the year 2017 pertaining to CC
wearing coat at Bridge No. 186/8 (High-Level Bridge across the river Dabua at
Gasuapara).
26. The petitioner has also stated in his written argument that out of the
total bill of ₹ 3,00,36,148/- (Rupees Three Crore, Thirty-Six Lakh, One Hundred
Forty-Eight) only ₹ 1,33,88,983/- (Rupees One Crore, Thirty-Three Lakh,
Eighty-Eight Thousand, Nine Hundred Eighty-Three) only have been released
to the petitioner through running bills. The outstanding amount to be realized by
the petitioner comes to ₹ 1,66,47,165/- (Rupees One Crore, Sixty-Six Lakh,
Forty-Seven Thousand, One Hundred Sixty-Five) only. However, it is also the
argument of the petitioner that there is a cost escalation bill dated 05.01.2015
raised by the petitioner for ₹ 1,19,83,919/-, the total outstanding amount due and
payable to the petitioner being ₹ 2,86,31,084/- only.
27. It is the observation of this Court that the detailed claim made by the
petitioner is not found in the petition. No mention of the amount of the bill for
price escalation has been stated in the petition. As such, this aspect of the matter
cannot be countenanced by this Court in the absence of clear and precise
pleadings, since the petitioner has advanced argument beyond the pleadings and 2026:MLHC:1032
11
has introduced facts which were not found in the petition.
28. Even otherwise, on a wholesome consideration of the facts and
circumstances of the case of the parties, there is no doubt that disputed question
of facts is involved herein. In this regard, the authority cited by the learned AAG
that is, the case of Puna Hinda (supra), para 18 and 24 which is relevant is quoted
herein below:
“18. Mr Nataraj also placed reliance on the judgment of this
Court reported as Joshi Technologies International Inc. v. Union of
India, (2015) 7 SCC 728 wherein the following was held: (SCC pp.
757-58 & 766, paras 55, 59 & 69)
“55. Law in this aspect has developed through a
catena of judgments of this Court and from the reading of
these judgments it would follow that in pure contractual
matters the extraordinary remedy of writ under Article 226
or Article 32 of the Constitution cannot be invoked.
However, in a limited sphere such remedies are available
only when the non-Government contracting party is able to
demonstrate that it is a public law remedy which such party
seeks to invoke, in contradistinction to the private law
remedy simpliciter under the contract. Some of the case law
to bring home this cardinal principle is taken note of
hereinafter.
59. On the basis of these facts, this Court observed that
the aforesaid observations of the High Court, (1986 SCC
OnLine All 110) relying upon Ramana Dayaram Shetty case,
(1979) 3 SCC 489 were not correct. Thus observed the Court,
speaking through Ratnavel Pandian, J.: (Ajai Pal Singh case,
(1989) 2 SCC 116, SCC pp. 125-26, paras 21-22)
‘21. This finding in our view, is not correct in
the light of the facts and circumstances of this case
because in Ramana Dayaram Shetty case, (1979) 3
SCC 489, there was no concluded contract as in this
case. Even conceding that the BDA has the trappings 2026:MLHC:1032
12
of a State or would be comprehended in "other
authority" for the purpose of Article 12 of the
Constitution, while determining price of the
houses/flats constructed by it and the rate of monthly
instalments to be paid, the "authority" or its agent
after entering into the field of ordinary contract acts
purely in its executive capacity. Thereafter the
relations are no longer governed by the constitutional
provisions but by the legally valid contract which
determines the rights and obligations of the parties
inter se. In this sphere, they can only claim rights
conferred upon them by the contract in the absence of
any statutory obligations on the part of the authority
(i.e. BDA in this case) in the said contractual field.
22. There is a line of decisions where the
contract entered into between the State and the
persons aggrieved is non-statutory and purely
contractual and the rights are governed only by the
terms of the contract, no writ or order can be issued
under Article 226 of the Constitution of India so as to
compel the authorities to remedy a breach of contract
pure and simple - Radhakrishna Agarwal v. State of
Bihar, (1977) 3 SCC 457, Premji Bhai Parmar v.
DDA, (1980) 2 SCC 129 and Divl. Forest Officer v.
Bishwanath Tea Co. Ltd. (1981) 3 SCC 238.
69. The position thus summarised in the aforesaid
principles has to be understood in the context of discussions
that preceded which we have pointed out above. As per this,
no doubt, there is no absolute bar to the maintainability of
the writ petition even in contractual matters or where there
are disputed questions of fact or even when monetary claim
is raised. At the same time, discretion lies with the High
Court which under certain circumstances, it can refuse to
exercise. It also follows that under the following
circumstances, “normally”, the Court would not exercise
such a discretion:
69.1. The Court may not examine the issue unless the
action has some public law character attached to it.
69.2. Whenever a particular mode of settlement of 2026:MLHC:1032
13
dispute is provided in the contract, the High Court would
refuse to exercise its discretion under Article 226 of the
Constitution and relegate the party to the said mode of
settlement, particularly when settlement of disputes is to be
resorted to through the means of arbitration.
69.3. If there are very serious disputed questions of
fact which are of complex nature and require oral evidence
for their determination.
69.4. Money claims per se particularly arising out of
contractual obligations are normally not to be entertained
except in exceptional circumstances.”
“24. Therefore, the dispute could not be raised by way of a writ
petition on the disputed questions of fact. Though, the jurisdiction of
the High Court is wide but in respect of pure contractual matters in
the field of private law, having no statutory flavour, are better
adjudicated upon by the forum agreed to by the parties. The dispute
as to whether the amount is payable or not and/or how much amount
is payable are disputed questions of facts. There is no admission on
the part of the appellants to infer that the amount stands crystallised.
Therefore, in the absence of any acceptance of joint survey report by
the competent authority, no right would accrue to the writ
petitioner only because measurements cannot be undertaken after
passage of time. Maybe, the resurvey cannot take place but the
measurement books of the work executed from time to time would
form a reasonable basis for assessing the amount due and payable to
the writ petitioner, but such process could be undertaken only by the
agreed forum i.e. arbitration and not by the writ court as it does not
have the expertise in respect of measurements or construction of
roads.”
29. Similarly, the case of Joshi Technologies International Inc.(supra),
para 55, 59, 69.2 being relevant is reproduced herein below as:
“55. Law in this aspect has developed through catena of
judgments of this Court and from the reading of these judgments it
would follow that in pure contractual matters the extraordinary
remedy of writ under Article 226 or Article 32 of the Constitution
cannot be invoked. However, in a limited sphere such remedies are 2026:MLHC:1032
14
available only when the non-Government contracting party is able to
demonstrate that it is a public law remedy which such party seeks to
invoke, in contradistinction to the private law remedy simpliciter
under the contract. Some of the case law to bring home this
cardinal principle is taken note of hereinafter.
59. On the basis of these facts, this Court observed that the
aforesaid observations of the High Court relying upon Ramana
Dayaram Shetty case, (1979) 3 SCC 489, were not correct. Thus
observed the Court, speaking through Ratnavel Pandian. J.: (Ajai
Pal Singh case, (1989) 2 SCC 116, SCC pp. 125-26, paras 21-22)
“21. This finding in our view, is not correct in the light
of the facts and circumstances of this case because in Ramana
Dayaram Shetty case (1979) 3 SCC 489 there was no concluded
contract as in this case. Even conceding that the BDA has the
trappings of a State or would be comprehended in 'other authority'
for the purpose of Article 12 of the Constitution, while determining
price of the houses/flats constructed by it and the rate of monthly
instalments to be paid, the 'authority' or its agent after entering into
the field of ordinary contract acts purely in its executive capacity.
Thereafter the relations are no longer governed by the
constitutional provisions but by the legally valid contract which
determines the rights and obligations of the parties inter se. In this
sphere, they can only claim rights conferred upon them by the
contract in the absence of any statutory obligations on the part of
the authority (i.e. BDA in this case) in the said contractual field.
22. There is a line of decisions where the contract
entered into between the State and the persons aggrieved is non-
statutory and purely contractual and the rights are governed only
by the terms of the contract, no writ or order can be issued under
Article 226 of the Constitution of India so as to compel the
authorities to remedy a breach of contract pure and simple -
Radhakrishna Agarwal v. State of Bihar (1977) 3 SCC 457, Premji
Bhai Parmar v. DDA (1980) 2 SCC 129 and Divl. Forest Officer v.
Bishwanath Tea Co. Ltd. (1981) 3 SCC 238"
69.2. Whenever a particular mode of settlement of dispute is
provided in the contract, the High Court would refuse to exercise its
discretion under Article 226 of the Constitution and relegate the
party to the said mode of settlement, particularly when settlement of 2026:MLHC:1032
15
disputes is to be resorted to through the means of arbitration.”
30. Based on the authorities referred to herein above, the principle has
also been adverted to by this Court in the case of Smti. Priyanchi R. Marak
(supra), the relevant para being noted herein below as para 37, 38 and 39:
37. Venturing to ignore such a situation repleted with disputed
question of facts would reduce this Court to a trial court wherein
evidence has to be looked into and appreciated, which is not a duty
cast upon a constitutional Court, considering the facts and
circumstances of this instant case. In this regard, the observations of
a Division Bench of this Court in the case of Adarsh Saraswati
Mahila Shiksha and Gramin Vikas Samiti v. State of Meghalaya &
Ors. in MC(WA) No. 16/2023 in W.A. No. 22/2023, at para 7 of
Judgment dated 19.07.2023, is found relevant to the factual situation
of this instant case, wherein it was observed as follows:
“7. For the wealth of reasons indicated in the order
impugned, the writ court held that the writ petition was liable
to be dismissed as not maintainable. Indeed, notwithstanding
the wide authority available to a Constitutional Court under
Article 226 of the Constitution, there is an element of self-
restraint that is exercised. Since writ proceedings are
decided on affidavit evidence and on summary procedure,
disputed questions of fact which require proof are not
entertained. In any event, at the end of the day, the real
grievance of the petitioner is that the petitioner has been
unfairly treated and has been deprived of the profits that the
petitioner was entitled to upon successful completion of the
work. Such grievance sounds in money and the relief that the
petitioner should pursue should be by way of a suit for
damages.”
38. This Court having convinced itself that there appears to be
question of disputed facts to be looked into, the relevant authorities
cited in this regard may not be off the mark. In the case of Poona
Hinda(supra) at para 24 the Hon’ble Supreme Court has held that
“…Though, the jurisdiction of the High Court is wide but in respect
of pure contractual matters in the field of private law, having no
statutory flavour, are better adjudicated upon by the forum agreed to 2026:MLHC:1032
16
by the parties. The dispute as to whether the amount is payable or
not and/or how much amount is payable are disputed questions of
facts.”
39. In the case of Joshi Technologies International Inc.(supra) at
para 69 of the same, the Hon’ble Supreme Court has observed that
though there is no bar to the maintainability of a writ petition in a
contractual matter where there are disputed questions of fact or even
when monetary claim is raised, however discretion is bestowed upon
the High Court to refuse to exercise such jurisdiction, when there are
serious disputed questions of fact and money claims arising out of
contractual obligations are normally not to be entertained, the fact
being that there is proper forum for determination of the parties’
right, for example a civil court of competent jurisdiction.
31. In view of the above, this Court is of the opinion that the grievance
of the petitioner can only be remedied by an approach before the civil court of
competent jurisdiction. Considering the fact that the proceedings before this
Court has travelled a long distance since the year 2023, therefore, provided the
petitioner approach such civil court within a period of 60 days from the date of
this order, the period spent before this Court is hereby condoned as far as the
rigors of the provisions of the Limitation Act is concerned.
32. In the final analysis, this petition is hereby disposed of in the terms
hereinabove set out. No costs.
Judge
2026:MLHC:1032
Legal Notes
Add a Note....