As per case facts, the appellant challenged a Commercial Court order that dismissed their Section 34 challenge against an arbitration award. The arbitration concerned a bridge construction contract which was ...
1
IN THE HIGH COURT AT CALCUTTA
CIVIL APPELLATE JURISDICTION
COMMERCIAL DIVISION
APPELLATE SIDE
Present:
The Hon’ble Justice Debangsu Basak
And
The Hon’ble Justice Aryak Dutt
FMAT (ARBAWARD) 35 of 2022
State of West Bengal
Vs.
M/s. A.J. Sarkar & Co.
For the Appellant : Mr. Abhishek Banerjee, Adv.
For Respondent : Mr. Priyankar Saha, Adv.
Ms. Srijani Mukherjee, Adv.
Hearing Concluded on : August 27, 2026
Judgment on : September 22, 2026
DEBANGSU BASAK, J.: -
1. Appellant has assailed the judgment and order dated
March 30, 2022 passed by the learned Commercial Court at
Asansol in Misc. Arbitration Case No. 1 of 2019.
2. By the impugned judgment and order, learned Judge
has dismissed the challenge under Section 34 of the
Arbitration and Conciliation Act, 1996 directed against the
award dated February 18, 2019.
2
3. Learned Advocate appearing for the appellant has
contended that, the learned Arbitrator erred in granting some
of the claims made by the respondent.
4. Referring to the impugned award, learned Advocate
appearing for the appellant has contended that, learned
Arbitrator relied upon documents which were not proved in
accordance with the law. He has contended that, the appellant
was denied any opportunity to inspect the original documents
relied upon by the respondent. The appellant had denied the
genuineness, factum, validity and contents of the documents
as such documents were third party document s. He has
contended that, the respondent was called upon to prove such
documents by adducing cogent evidence as they were third
party documents. He has pointed out that, in absence of
examination of the authors of such documents, none of such
documents were admissible in evidence.
5. Learned Advocate for the appellant has submitted that
the learned Arbitrator had recorded submissions of the
respective parties made in every sitting of the arbitration
proceeding in extenso. He has pointed out that the basis of
the claims of the respondent, being Annexure C-21 of the
3
statement of claim, is essentially a cost analysis and nothing
more. He has contended that, cost analysis amounts to
nothing and cannot be a substitute of actual proof. In support
of his contention he has relied upon 1994 Volume 1
Arbitration Law Reporter 269 (Kochar Construction
Versus Union of India and Another)
6. Relying upon 2015 (2) Bom CR 697 (Rashmi Housing
Private Limited Versus Pan India Infraprojects Private
Limited) learned advocate appearing for the appellant has
contended that, although, Evidence Act has no application
before any arbitration nonetheless the principles thereto are
applicable.
7. Learned Advocate appearing for the appellant has
contended that, although a document can be proved by
examining the person who has seen the original nonetheless
the contents of such documents has to be proved by the
author of such document. In support of such contention he
has relied upon AIR 54 Bom 305 (Madholal Sindhu Versus
Asian Assurance Co. Ltd and Others )
8. Relying upon 2011 (2) SCC 532 (Kalyan Kumar
Gogoi Versus Ashutosh Agnihotri and Another ) learned
4
advocate appearing for the appellant has contended that,
evidence which is hearsay in nature is to be ignored and
discarded outright.
9. Learned Advocate appearing for the appellant has
contended that, events occurring subsequent to the contract
had made the execution of the project impossible. He has
pointed out there were litigations regarding the land and of
there were problems with regard to the availability of the site.
He has relied upon 1953 (2) SCC 437 (Satyabrata Ghose
Versus Mugneeram Bangur and Company and Another ) for
the proposition that, the contract stood terminated by reason
of frustration of the contract and/or impossibility in execution
of the contract.
10. Relying upon 2025 SCC OnLine SC 2857 (Ramesh
Kumar Jain Versus Bharat Aluminium Company Limited)
learned Advocate appearing for the appellant has contended
that, the learned Arbitrator ignored binding precedents and
therefore, the award stands vitiated by reason of patent
illegality.
11. Learned Advocate appearing for the appellant has
contended that, while allowing claims No. 1 and 2 made by
5
the appellant, learned Arbitrator reproduced the arguments
made by the respondent in the 21
st sitting.
12. Relying upon 2022 (3) SCC 121 (I-Pay Clearing
Services Private Limited Versus ICICI Bank Limited )
learned Advocate appearing for the appellant has contended
that, non-consideration of the binding precedents cited on
behalf of the appellant constitutes patent illegality.
13. Relying upon 2026 (4) SCC 392 (Lancor Holdings
Limited Versus Prem Kumar Menon and Others ) learned
Advocate appearing for the appellant has contended that, time
in excess of two years elapsed between the date of conclusion
of the hearing and the passing of the award. On that ground
alone, the award should be set aside.
14. Learned Advocate appearing for the respondent has
contended that, the appellant floated the tender for
construction of box sales bridge and both side project over
Gomani Khal in between 6
th Km and 7
th Km of Goas-Goraipur
Road under Murshidabad Highway Division No. 1 in the
district Murshidabad under tender No. 7/B of 2010/2011. He
has contended that, the respondent participated in the tender
and become a successful bidder. Appellant had issued the
6
acceptance cum work order by a letter dated November 15,
2010.
15. Learned Advocate appearing for the respondent has
contended that, in terms of the acceptance cum work order
the work was to be completed within ten months that is
September 21, 2011. He has pointed out that immediately
after the receipt of the acceptance cum work order the
respondent mobilised itself and progressed with the work.
16. Learned Advocate appearing for the respondent has
contended that, by a writing dated June 17, 2011 , the
appellant asked the respondent not to execute any further
work till such problem was solved. Thereafter on September 9,
2011 the respondent had requested for extension of time
since, the work could not be completed due to suspension of
the work. By a letter dated September 20, 2011, the appellant
had informed the respondent that the dispute was ongoing,
the work cannot be started and directed the respondent to
wait for a month with the hope that the matter will be resolved
within such time. Thereafter, the respondent had by letters
dated September 11, 2011, November 11, 2011, November 29,
2011, December 7, 2011 and March 23, 201 2 informed the
7
appellant of the losses suffered by the respondent due to such
prolonged suspension of the work.
17. Learned Advocate appearing for the respondent has
submitted that, by a letter dated Mar ch 28, 2012 the
appellant asked the respondent to submit the bills for the
works executed before the suspension of the work in terms of
clause 8 of the conditions of contract.
18. Learned Advocate appearing for the respondent has
contended that, his client co-wrote several letters to the
appellant detailing the losses and damages suffered by
prolonged suspension of work and non-payment of the dues.
He has pointed out that, by a letter dated June 24, 2013
respondent had submitted its assessed losses up to June 17,
2013 amounting to ₹ 1, 59, 53, 853 along with interest to the
appellant. By a letter dated December 13, 2016, the appellant
had confirmed that since an arbitrator was appointed, the job
was formerly treated as closed.
19. Learned Advocate for the respondent has contended
that, before the learned arbitrator, the respondent had made 5
heads of claim. He has pointed out that, the first claim related
to amount payable for work done and others used as detailed
8
in the letters dated June 24, 2013 and September 13, 2013
amounting ₹ 1, 59, 53, 853. The 2
nd head of claim had been
premised on compensation and/for damages on account of
prevention of the performance of the work which was assessed
at ₹ 8,00,000/- Under the 3
rd head of claim, the respondent
had claimed interest at the rate of 18% per annum from June
24, 2013 till payment. On the 4
th head of claim, the
respondent had claimed any amount which may be found t o
in terms of the contract and/or in law has accrued. On the 5
th
of claim, the respondent had claimed cost of arbitration on
actual basis.
20. Learned Advocate appearing for the respondent had
contended that, parties had adduced evidence before the
learned arbitrator by filing affidavit of evidence. Respondent
had produced a documents in part 1 which has details of the
measurement of the work done by the claimant, bills, money
receipts, quantum of artwork in execution, a apron filling,
dewatering, bamboo piling, wooden plank filing, etc. He has
pointed out that, the witness of the respondent ha d been
cross-examined in details.
9
21. Learned Advocate appearing for the respondent has
contended that, the award is dated February 18, 2019.
Learned arbitrator had allowed claim numbers 1, 2 and 5
along with interest at the rate of 9% from June 24, 2013 till
payment, by the award. He has contended that, the award
contains detailed reasons. Learned arbitrator has dealt with
every fact and evidence placed before him.
22. Learned Advocate appearing for the respondent has
contended that, the learned arbitrator relied upon 1984 (4)
SCC 59 (A.T. Brij Paul Singh Versus State of Gujarat ) for
awarding 10 percent compensation on the proportion of work
which could not be done due to land acquisition problem
under the 2
nd claim.
23. On the scope of judicial intervention in an appeal
under section 37 of the act of 1996, learned Advocate
appearing for the respondent has relied upon 2026 SCC
OnLine SCC 1001 (Madhya Pradesh Road Development
Corporation Versus Jabalpur Corridor Private Lim ited)
and 2026 (3) SCC 186 (Jan De Nul Dredging India Private
Limited Versus Tuticorin Port Trust ).
10
24. Learned Advocate appearing for the respondent has
submitted that the arbitrator is the ultimate master of the
quality and quantity of evidence to be relied upon while
passing the award. In support of such contention, he has
relied upon 2015 (3) SCC 49 (Associate Builders Versus
Delhi Development Authority).
25. Relying upon 2026 (4) SCC 392 (Lancor Holdings
Limited Versus Prem Kumar Menon and Others ), learned
Advocate appearing for the respondent has contended that,
delay in passing the award does not per se affect the award.
Moreover, the same is also not a ground under section 34 of
the Act of 1996 to set aside the award.
26. Appellant had floated a tender for cons truction.
Respondent had participated in such tender and became
successful therein. Appellant had issued an Acceptance-cum-
Work order dated November 15, 2010 in favour of the
respondent. Under the Acceptance-cum-work order, the
contract had to be completed within 10 months from
November 22, 2010, that is, till September 21, 2011.
11
27. Apparently, execution of the contract had been stalled
due to problems at the site. The parties had gone to
arbitration with regard to the contract and its execution.
28. Parties have raised issues with regard to the delay in
making and publishing the award. It appears from the records
that, the first meeting of the arbitration had been held on
January 30, 2014. In aggregate, there have been 36 sittings of
the arbitration.
29. On the last sitting of the arbitration, that is the 36
th
sitting, held on February 18, 2019, learned arbitrator had
made and published the award and made over signed copies
of the award to the parties.
30. The 35
th sitting of the arbitration had been held on
June 15, 2017 where, the learned Arbitrator has recorded
that, both sides filed their respective notes an argument and
that the same were taken on record. Learned Arbitrator has
recorded that neither of the sides had any further
submissions to make. He has al so recorded that the
respondent submitted non-judicial Stamp paper and that, the
appellant requested for further time to do so. Prayer of the
appellant to put in the non-judicial Stamp paper had been
12
allowed. The learned arbitrator has recorded that the
arbitration stands concluded.
31. From the records made available to us therefore,
conclusion of hearing in the arbitration had taken place on
June 15, 2017. Learned arbitrator had passed the award on
February 18, 2019. There has therefore been a gap in excess
of 1 year 8 months from the date when, the hearing in the
arbitration proceedings stood concluded.
32. Lancor Holdings Ltd (supra) has answered the issue
as to what is the effect of undue and unexplained delay in the
pronouncement of an arbitral award upon its validity. It has
held as follows: –
“87.1.1. Delay in the delivery of an arbitral award, by
itself, is not sufficient to set aside that award. However, each
such case would have to be examined on its own individual
facts to ascertain whether that delay had an adverse impact
on the final decision of the Arbitral Tribunal, whereby that
award would stand vitiated due to the lapses committed by
the Arbitral Tribunal owing to such delay. It is only when the
effect of the undue delay in the delivery of an arbitral award
is explicit and adversely reflects on the findings therein, such
delay and, more so, if it remains unexplained, can be
construed to result in the award being in conflict with the
public policy of India, thereby attracting Section 34(2)(b)(ii) of
the 1996 Act or Section 34(2-A) thereof, as it may also be
vitiated by patent illegality. Further, it would not be necessary
13
for an aggrieved party to invoke the remedy under Section
14(2) of the 1996 Act as a condition precedent to lay a
challenge to that delayed and tainted award under Section 34
thereof.”
33. In Lancor Holdings Limited (supra) learned
Arbitrator had reserved the arbitral award on July 28, 2012
and pronounced it on March 16, 2016 , that is, nearly three
years and eight months after reserving the decision. Moreover
no explanation had been offered for the delay. Supreme Court
has held that, the award did not resolve the disputes between
the parties. Supreme Court has invoked Article 142 of the
Constitution of India to grant reliefs to the parties.
34. A Court exercising jurisdiction under Section 34 of the
Act of 1996 would necessarily have to evaluate whether there
was delay in making and publishing the award and whether
such delay remained unexplained. The Court will also have to
evaluate whether the delay has an adverse impact on the final
decision of the Arbitral Tribunal thereby vitiating the award
owing to such delay or not.
35. In the facts and circumstances of the present case,
there is a delay of more than 1 year 8 months from the date of
conclusion of the hearing of the arbitration proceeding till the
date of making and publishing the award which has not been
14
explained. We now have to evaluate as to whether such
unexplained delay in making and publishing the award had
an adverse impact on the final decision of the arbitrator or
not.
36. Records disclosed before us have established that, the
learned Arbitrator made elaborate notes of the proceedings on
each day. Respective submissions of the Advocates appearing
for the respective parties have been recorded in the minutes
by the learned Arbitrator.
37. Jan De Nul Dredging India Private Limited (supra)
has noticed the limited scope of the interference with the
award of Court exercising powers under Sections 34 and 37 of
the Act of 1996. It has held that, powers of a Court under
Section 37 of the Act of 1996 are even more restricted than
the powers under Section 34. Appellate powers under Section
37 of the Act of 1996 has been held to be exercisable only to
find out if the Court exercising powers under Section 34 of the
Act of 1996 has acted within its limits as prescribed
thereunder or has exceeded or failed to exercise the powers so
conferred. The Appellate Court exercising powers under
Section 37 of the Act of 1996 has no authority of law to
15
consider the matter in dispute before the Arbitral Tribunal on
merits so as to hold as to whether the award is right or wrong.
Appellate Court has no power as a court of appeal to re-
appreciate the evidence and record a contrary finding.
38. Madhya Pradesh Road Development Corporation
(supra) has held that, the architecture of appeal under
Section 37 of the Act of 1996 is restrictive. It has observed
that, jurisdiction under Sections 34 and 37 of the Act of 1996
cannot be equated with mandatory appellate jurisdiction. The
Appellate Court under Section 37 of the Act of 1996 does not
sit as a Court of Appeal on the merits of the Arbitral Tribunal.
Its role is confined to examine whether the Court under
Section 34 of the Act of 1996 has acted within the limits
prescribed by law or not. Interference is permissible only
where the Section 34 Court has exceeded its jurisdiction or
failed to exercise it within the confines of Section 34 and not
merely because another view of the facts or interpretation of
the contract may appear preferable.
39. Having noted the periphery of the jurisdiction under
Section 37 of the Act of 1996 as enunciated in Madhya
Pradesh Road Development Corporation (supra) and Jan
16
De Nul Dredging India Private Limited (sup ra) the
contentions of the respective parties have to be assessed on
the merits of the matter.
40. Associate Builders (supra) has held that, the
Arbitrator is the sole Judge of the quantity and quality of
evidence when he delivers the Arbitral Award. Powers under
Section 34 of the Act of 1996 cannot be exercised to set aside
an award merely because the award is based on little evidence
or on evidence which does not measure up in quality to a
trained legal mind. In the event, it is established that, the
approach of the Arbitrator to the issues is neither arbitrary
nor capricious then no interference is called for on facts.
41. In Kochar Construction (supra) Supreme Court
however has disallowed claim for escalation on the ground
that no evidence had been led in support of such claim. It has
noted that, no evidence at all was led by the claimant on the
point except filing of the chart containing cost analysis. This
chart containing cost analysis has been held to be of no
evidence at all.
42. In Madholal Sindhu (supra) the Single Bench of the
Bombay High Court has held that, mere proof of the
17
signatures or the handwriting of the persons who signed or
wrote the various documents without calling the persons who
could depose as to the correctness of the contents of such
documents, amounts to no evidence at all.
43. Another Single Bench of the Bombay High Court in
Rashmi Housing Private Limited (supra) has held that,
although, Evidence Act, 1872 is not applicable in an
arbitration proceedings, nonetheless, an Arbitral Tribunal is
bound to consider the principles of the Evidence Act, 1872.
44. Kalyan Kumar Gogoi (supra) has dealt with the
Evidence Act, 1872 in the context of hearsay evidence. It has
held that, idea of best evidence is implicit in the Evidence Act,
1872. It has noted that, in the case of oral evidence, only that
person who has actually perceived something by senses
through which he is capable of perception who should make
the statement about it and no one else. If it is documentary
evidence, then, ordinarily the original thereof be produced
because a copy may contain commission of mistake of a
deliberate or accidental nature.
45. Satyabrata Ghose (supra) has noted the distinction
between frustration of a contract and repudiation thereof. It
18
has noted that, frustration of a contract occurs automatically.
It has noted that, termination of a contract on the ground of
repudiation or breach is dependent upon choice or election of
either of the parties to the contract.
46. Ramesh Kumar Jain (supra) has explained the
phrase patent illegality appearing in Section 34 of the Act of
1996. It has noted various authorities on the subject and held
that, patent illegality goes to the root of the award and
includes an award deciding matters outside the scope of the
arbitration, an award contradicting the substantive law of
India or the Act of 1996 itself, an award against the terms of
the contract and award so unreasoned or irrational that it
manifest an error on its face.
47. I-Pay Clearing Services Private Limited (supra) has
considered the scope and ambit of Section 34(4) of the Act of
1996. It has held that, powers under Section 34(4) of the Act
of 1996 are discretionary and may be exercised where there is
inadequate reasoning in the award or to fill up the gaps in the
reasoning in support of the findings which are already
recorded in the award.
19
48. A.T. Brij Paul Singh (supra) has considered claims
on account of damages in the context of Section 73 of the Act
of 1872. It has held that, where, a contractor claimed
damages on the Government committing breach by improperly
rescinding the contract, the Court should make a broad
evaluation instead of entering into minute details.
49. Respondent had filed the statement of claim containing
five heads of claim which are as follows:-
List of Claims/Disputes
Sl. No.
Due
Description of Item Amount
1. Amount payable for works done and
other dues as detailed in my Client’s
letter dated 24
th
June, 2013 and also
Letter dated 13
th
September, 2013
Rs. 1,59,53,853.00
2. Compensation and/or damages on
account of prevention of our
performance by the Department for
which the work could not be completed
depriving us from the expected profit
which remained unexecuted. Assessed
10% of the value of work which
remained unexecuted.
Rs. 8,00,000.00
3. Interest @ 18% p.a from 24.06.2013 till
payment.
As accrued.
4. Any other claim and/or amounts
which may be found due to us in terms
of the Contract and/or in law.
As may be found due.
5. Cost of Arbitration On actual.
20
50. Learned Arbitrator in his Award has noted that claim
no. 1 comprised of amounts payable for work done and other
dues as detailed in the letters dated June 24, 2013 and
September 16, 2013 of the respondent herein.
51. In the body of the Award, Learned Arbitrator has noted
the Assessment of Claims which has 19 heads. Head numbers
1 to 11 under the Assessment of Claims had added upto Rs.
28,67,812/-. Respondent had added compound interest
@1.5% per month for 24 months aggregating to Rs.
40,99,545/-. Likewise, respondent has added compound
interest for 24 months @1.5% per month to head no.
13,14,15,16,17,18,19. Significantly, by adding interest at the
compound rate of 1.5% for 24 months for such heads under
claim no. 1, interest component has exceeded the principal
claim on each of the heads.
52. Respondent has claimed a sum of Rs. 1,59,53,853/-
under claim no. 1 which included the compound rate of
interest. Learned Arbitrator has allowed it in its entirety.
53. Our attention has not been drawn to any agreement
for interest far less in position of interest at the compound
rate.
21
54. On Claim No. 1, learned Arbitrator has held as
follows:-
“The Claim No. 1 is subject matter in both during
examination in chief and also Cross-examination. It is
a fit case when the Claimant is entitled to full Award in
respect of Claim No. 1. There has been no defence at
all by the Respondent against Claim No. 1 either in
their Statement of Defence or during cross-examination
of the Claimant’s witness. The Claim No. 1, the
Claimant is entitled to full Award, which I decide
unhesitatingly and the same is decided on
consideration of evidence.”
55. No document in support of the work that the
respondent had actually executed at the site was tendered in
evidence. What had been tendered in evidence by t he
respondent in support of the claim of the quantum of work are
statements unilaterally noted by an engineer appointed at the
behest of the respondent. Appellant did not accept such
measurements. The quantum work claimed to have been done
has not been corroborated by any other evidence apart from
the unilateral measurement of the engineer of the respondent.
56. Learned Arbitrator did not give any reason as to why
he was relying upon such measurement details and why he
did not call for the measurement book which is required to be
maintained in a construction work of this nature.
22
57. Associate Builders (supra) and Kochar
Construction (supra) have laid down that, although, the
Arbitrator is the sole Judge of the quantity and quality of
evidence, nonetheless, if the award is based on no evidence at
all, then, a Court exercising jurisdiction under Section 34 of
the Act of 1996 is obliged to set aside such award, on the
ground of patent illegality.
58. By the award, the learned Arbitrator has i ncluded
component of compound rate of interest of every heads of
claim under Claim No. 1. He has proceeded to award the
interest independently while allowing interest at the rate of 9%
under claim no. 3. Essentially, the learned Arbitrator has
awarded compound interest up to a given stage and thereafter
simple interest on the sum waived at after adding interest at
the compound rate. Learned Arbitrator has not ascribed any
reason as to why compound rate of interest has been allowed
by him for a period of time while simple interest has been
allowed subsequently.
59. The award as it stands today contains interest at
compound rate. The amount arrived after calculating interest
at compound rate will carry further interest at the rate of 9%
23
per annum. In effect the appellant has to pay interest on
compound rate of interest.
60. The nature of the contract is a social welfare measure
which a State is required to discharge. The contract is of
construction of a bridge. It is not a project from which the
appellant is expected to earn or generate revenue. Award of
interest at compound rate and thereafter interest on interest
would render the award as shocking to the conscience of the
Court.
61. An inference that the, passage of time between the
date when the learned Arbitrator reserved the award for
decision and its ultimate publication affected the decision on
such an aspect is plausible.
62. Significantly, claim no. 1 has sub heading which
relates to the claim on account of refund of security deposit.
On such sub heading also, claim no. 1 included compound
interest as also alleged loss of business for withholding such
security deposit. Learned Arbitrator has however allowed
refund of security deposit as an independent claim under the
heading claim no. 2. The award therefore suffers from non-
application of mind.
24
63. Under the contract, the date of commencement had
been fixed at November 22, 2010 with completion being fixed
at September 21, 2011. By a letter dated June 17, 2011
appellant had called upon the respondent not to execute
further work till the land problem issue was solved. Records
made available have established the respondent was aware of
the land acquisition problem.
64. By a letter dated September 9, 2011 the respondent
had requested for extension of time to complete the contract.
By letter dated September 20, 2011 appellant had requested
the respondent to wait for a month.
65. Respondent had not taken any steps to mitigate the
loses to be recovered or claimed, at least none has been
pleaded or established before the learned Arbitrator. Arbitral
Tribunal has also failed to take into consideration the issue of
frustration of the contract due to supervening impossibility.
The contract was for construction of a bridge. The requisite
land for such construction was not available. This factor had
to be taken into consideration by the learned Arbitrator which
he did not do.
25
66. In such circumstances, learned Judge erred in
correctly evaluating the award in terms of Section 34 of the
Act of 1996 and failed to exercise jurisdiction vested upon to
in law.
67. Consequently, the impugned judgment and order
dated March 30, 2022 is set aside. The award dated February
18, 2019 is set aside. FMAT (ARBAWARD) 35 of 2022 is
disposed of without any order as to costs.
[DEBANGSU BASAK, J.]
68. I agree.
[ARYAK DUTT, J.]
Legal Notes
Add a Note....