As per case facts, Appellants (promoters) failed to deliver possession of a flat in their "Waterways" project to Respondents (allottees) by the agreed deadline. MahaRERA initially ordered a refund with ...
k 1/28 SA (St) 8825 of 2025 with IA
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CIVIL APPELLATE JURISDICTION
SECOND APPEAL (STAMP) NO.8825 OF 2025
1. Sanklecha Constructions Pvt. Ltd.
2. Vijay Kachardas Sanklecha
3. Dilip Kachardas Sanklecha
4. Puneet Ajit Sanklecha ....Appellants
V/S
1. Nitin Madhukar Shewale
2. Shital Nitin Shewale
3. Bhimashankar Laxman Janmali
4. Shrikrishna Laxman Janmali
5. Sitabai Laxman Janmali
6. Pushpa Jaggannath Janmali
7. Devemdra Jaggannath Janmali
8. Anil Laxman Janmali
9. Dinkar Laxman Janmali ....Respondents
WITH
INTERIM APPLICATION NO.7869 OF 2025
IN
SECOND APPEAL (STAMP) NO.8825 OF 2025
(FOR STAY)
1. Sanklecha Constructions Pvt. Ltd.
2. Vijay Kachardas Sanklecha
3. Dilip Kachardas Sanklecha
4. Puneet Ajit Sanklecha ....Applicants
V/S
1. Nitin Madhukar Shewale
2. Shital Nitin Shewale
3. Bhimashankar Laxman Janmali
4. Shrikrishna Laxman Janmali
5. Sitabai Laxman Janmali
6. Pushpa Jaggannath Janmali
katkam Page No. 1 of 28
2026:BHC-AS:39337
k 2/28 SA (St) 8825 of 2025 with IA
7. Devemdra Jaggannath Janmali
8. Anil Laxman Janmali
9. Dinkar Laxman Janmali ....Respondents
_________
Mr. Abhishek Pungaliya for the Appellants/Applicants.
Mr. Akshay R. Kapadia for Respondent Nos.1 and 2.
__________
CORAM : SANDEEP V. MARNE, J.
RESERVED ON : 17 SEPTEMBER 2026.
PRONOUNCED ON : 28 SEPTEMBER 2026.
J U D G M E N T
THE CHALLENGE
1.This Appeal is filed under provisions of Section 58 of the Real
Estate (Regulation and Development) Act, 2016 (RERA) by the
Appellants—Promoters, challenging the judgment and order dated 7
November 2023 and Review Order dated 28 November 2024 passed by
the Maharashtra Real Estate Appellate Tribunal, Mumbai, (Appellate
Tribunal) partly allowing the Appeal preferred by the allottees and
modifying the order dated 24 August 2021 passed by the Maharashtra
Real Estate Regulatory Authority (MahaRERA). By the impugned Order,
the Appellate Tribunal has withdrawn the option granted to them by
MahaRERA to return the paid consideration to the allottees alongwith
interest after obtaining occupation certificate (OC) for the project.
2.The Appeal involves the Appellants-Promoters being aggrieved by
the ultimate direction for refund of the entire amount to the allottees
katkam Page No. 2 of 28
k 3/28 SA (St) 8825 of 2025 with IA
along with interest thereon with effect from 1 January 2018. Since the
ultimate direction contemplates immediate return of amounts with
interest to the allottees and since option of returning the amount at the
time of securing OC is deleted, the Appellants have filed the present
Appeal.
3.It must be observed at the very outset that the Appellate Tribunal
has rather passed confusing orders posing challenge to comprehend the
same. Initially, MahaRERA had granted option to the promoter to refund
the paid consideration to the allottee along with interest after securing
OC for the project. By the main judgment and order dated 7 November
2023, the Appellate Tribunal withdrew that option by directing deletion
of portion of direction from MahaRERA’s Order and directed that the
promoter must refund the paid consideration with interest from the
dates of receipt of payments within 23 days of the Order. The main Order
is later reviewed by the Appellate Tribunal deleting the direction for
payment of interest from the date of receipt of payments. Thus, the net
effect of the Order passed by MahaRERA as modified twice by the
Appellate Tribunal is that the promoter needs to ‘forthwith’ refund the
paid consideration with interest w.e.f. 1 January 2018.
4.Appellants are not aggrieved per se by the direction for return of
amount and interest to the allottees. They are willing to return the
amount with interest, however, after obtaining the OC for the project.
The Appeal is filed contending that there are mitigating circumstances
beyond the control of the Promoters which have resulted in delay in
katkam Page No. 3 of 28
k 4/28 SA (St) 8825 of 2025 with IA
completion of the project and they desire that option of returning the
amount with interest after obtaining OC for the project must be made
available to them. Thus, the limited scope of inquiry in the Appeal is
whether the Appellate Tribunal was justified in withdrawing the option
made available to the Appellants to return the amount with interest to
the allottees after obtaining the OC for the project.
FACTS
5.The case of the Complainants/Allottees, as set out in their
Complaint, is that they booked Flat No.702 in Building No.C-1 in the
project named “Waterways” situate at Anusaya Nagar, Tapovan Road,
Dwarka, Nashik. Petitioner No.1-Sanklecha Constructions Private
Limited is the developer/promoter, who undertook construction of the
‘Project’. Appellant Nos. 2 to 4 are the directors of Appellant No. 1. Flat
No.702 in Building No. C-1 of the Project was booked by the Allottees for
total consideration of Rs.43,13,200/- and they paid part consideration of
Rs.22,58,178/- to the Promoter. Agreement for Sale dated 16 May 2016
was executed between the Promoter and Allottees, in which it was
agreed that the Promoter shall deliver possession of the flat on or before
31 December 2017, subject to reasonable extension of time based on
certain force majeure events. It appears that the Promoter was unable to
deliver possession of the flat within the agreed timeline. Therefore,
Allottees approached MahaRERA by filing a Complaint under Section 31
of RERA, which was registered as Complaint No.CC001000000000102. It
appears that the Appellants did not file any reply opposing the
katkam Page No. 4 of 28
k 5/28 SA (St) 8825 of 2025 with IA
Complaint. It appears that another Complaint was filed by other allottees
in respect of the same project.
6.MahaRERA proceeded to jointly hear both the Complaints and
decided them by passing common order dated 24 August 2021.
MahaRERA permitted the Allottees to withdraw from the project and
held them entitled to refund of the entire amount paid by them with
interest with effect from 1 January 2018 along with interest at the rate as
prescribed in Rule 18 of the Maharashtra Real Estate (Regulation and
Development) (Registration of Real Estate Projects, Registration of Real
Estate Agents, Rate of Interest and Disclosures on Website) Rules, 2017
(Rules of 2017). However, MahaRERA took into consideration the
mitigating circumstances beyond the control of the Promoter and
ensured that the project is not jeopardized due to outflow of finances
and is completed keeping in mind the interest of other buyers in the
project. Accordingly, MahaRERA directed that the amount of refund and
interest can be paid by the Promoter to the Allottees upon the Promoter
obtaining OC for the project. However, an option was left open to the
Promoter to pay the amount of refund and interest before obtaining OC.
7.The Allottees/Respondent Nos.1 and 2 got aggrieved by order
dated 24 August 2021 passed by MahaRERA and filed Appeal No.
AT006000000053455 of 2021 before the Appellate Tribunal. This time,
the Promoter appeared before the Appellate Tribunal and opposed the
Appeal. By judgment and order dated 7 November 2023, the Appellate
Tribunal partly allowed the Appeal filed by Complainants / Respondent
katkam Page No. 5 of 28
k 6/28 SA (St) 8825 of 2025 with IA
Nos.1 and 2 and modified order dated 24 August 2021 passed by
MahaRERA. The Appellate Tribunal directed deletion of portion of
operative part of MahaRERA’s order which gave option to the Promoter
to refund the amount with interest upon obtaining OC for the project.
Instead, the Appellate Tribunal directed the Promoter to refund the
entire amount to the allottees within 23 days along with interest from
the date of receipt of the payments at Marginal Cost of Lending Rate
(MCLR) of State Bank of India plus 2%, failing which the Promoter is
directed to pay interest at the directed rate on the total amount due and
outstanding as on 30 November 2023 till its complete refund.
8.Appellant No.1-Promoter preferred Review Application No.14 of
2023 before the Appellate Tribunal seeking review of judgment and order
dated 7 November 2023. By order dated 28 November 2024, the Appellate
Tribunal has partly allowed the Review Application. It has set aside
direction No.15(b)(ii) of the judgment and order dated 7 November 2023.
Thus, the final effective direction against the Appellants/Promoter is for
refund of entire payment received by them to Respondent Nos.1 and 2
with interest from 1 January 2018 as per the Rules of 2017.
9.Appellants/Promoters are aggrieved by the main judgment and
order dated 7 November 2023 as well as by the review order dated 28
November 2024 and have accordingly filed the present Second Appeal.
10.The Second Appeal has been admitted by order dated 17
September 2026, by framing the following substantial questions of law:
katkam Page No. 6 of 28
k 7/28 SA (St) 8825 of 2025 with IA
1) Whether the obligation for the Promoter to return to the
allottee the amount received by him with interest on demand
made by the allottee under Section 18(1) of the Real Estate
(Regulation and Development) Act, 2016 (RERA Act) is absolute
and unqualified or whether the Real Estate Regulatory Authority
and/or the Appellate Tribunal has discretion to take into
consideration any mitigating circumstances or genuine efforts
made by the Promoter in completing the project in time for the
purpose of claiming any relaxation either in respect of period of
interest or rate of interest or the date on which the refund is to be
made?
2) Whether the observations made by the Hon’ble Apex Court in
paragraph 25 of the judgment in Newtech Promoters and
Developers Private Limited vs. State of U.P. & Ors. Etc.
1
are
obiter dicta and whether the findings recorded by Division Bench
of this Court in paragraph 137 of the judgment in Neelkamal
Realtors Suburban Pvt. Ltd. and Anr. vs. Union of India and
Ors.
2
shall continue to operate even after observations made by
the Hon’ble Apex Court in paragraph 25 of the judgment in
Newtech Promoters and Developers Pvt. Ltd.?
3) Whether it is permissible for the Real Estate Regulatory
Authority and/or the Appellate Tribunal to direct that return of
1
IV (2021) CPJ 21 (SC) : 2021 SCC OnLine SC 1044
2
2017 SCC OnLine Bom 9302
katkam Page No. 7 of 28
k 8/28 SA (St) 8825 of 2025 with IA
the amount with interest shall be only after securing occupation
certificate of the project and not upon demand by the allottee
under provisions of Section 18(1) of the RERA Act?
11.After framing of substantial questions of law, the learned counsel
appearing for the respective parties have been heard on those questions.
It would be apt to record the gist of submissions canvassed by the
learned counsel appearing for the rival parties.
SUBMISSIONS
12.Mr. Pungaliya, the learned counsel appearing for Appellants
submits that the Appellate Tribunal has erroneously withdrawn the
option made available to the Appellants to refund amount with interest
to the allottees upon securing Occupation Certificate for the project.
That the impugned orders direct the Promoters to refund the received
amount with interest immediately. That Promoter is willing to refund
the received amount with interest upon receipt of OC for the project. He
submits that prior to the judgment of the Apex Court in Newtech
Promoters and Developers Private Limited (supra), the Regulatory
Authority as well as the Appellate Tribunal used to exercise the
discretion of molding the relief. That the observations made by the Apex
Court in paragraph 25 of the judgment in Newtech Promoters are being
misread by the Appellate Tribunal to mean as if the same constitutes
declaration of law. That the observations made in paragraph 25 of the
judgment in Newtech Promoters are mere obiter dicta having no
relevance for deciding the five questions framed in paragraph 31 of the
katkam Page No. 8 of 28
k 9/28 SA (St) 8825 of 2025 with IA
judgment. Mr. Pungaliya further submits that even if the entire
observations in paragraph 25 of the judgment in Newtech Promoters are
removed, the same would have no consequence on conclusions/answers
rendered by the Apex Court on the issues involved in the case. That
therefore the observations in paragraph 25 of the judgment in Newtech
Promoters will have to be necessarily treated as a mere obiter. He relies
on the judgment of the Apex Court in Career Institute Educational
Society v. Om Shree Thakurjee Educational Society
3
. That in the present
case, the Appellate Tribunal has committed the same mistake by treating
that observation in paragraph 25 of the judgment in Newtech Promoters
is a ratio decidendi or constitutes binding precedent. By misreading the
observations in paragraph 25 of the judgment in Newtech Promoters,
the Appellate Tribunal has refused to take into consideration the
mitigating circumstances put forth by the Appellants resulting in delay
in project completion and accordingly, the Appellate Tribunal has
erroneously withdrawn the molded relief granted by MahaRERA in the
order dated 24 August 2021.
13.Mr. Pungaliya further submits that MahaRERA had correctly
permitted Appellants to refund the amount and interest after obtaining
the occupation certificate by taking into consideration the mitigating
circumstances beyond the control of the Appellants. He relies on the
judgment of the Division Bench of this Court in Neelkamal Realtors
(supra) in support of his contention that it is permissible for courts to
take into consideration mitigating circumstances, where the developer
3
SLP (C) Nos.7455–7456 of 2023
katkam Page No. 9 of 28
k 10/28 SA (St) 8825 of 2025 with IA
makes genuine efforts to complete the project. He submits that it is
necessary to protect a promoter making genuine efforts to complete the
project within agreed timelines. That a balanced approach needs to be
adopted in the facts of the present case. That in the present case, two of
the five buildings of the Waterways project are 95% complete, and one
building is 85% complete. That even Building C-1, in which the flat was
booked by Respondent Nos.1 and 2, is also 70% complete. That in such
circumstances, forcing the developer to refund the entire received
amount with interest at this stage would seriously prejudice the fund
flow and harm the interests of more than hundred other flat buyers.
14.Mr. Pungaliya further submits that Section 18 of RERA came into
force in May 2017, whereas the Waterways project was registered on 19
August 2017 under MahaRERA. However, the registered Agreement for
Sale was executed on 16 May 2016. That since the Agreement for Sale
was executed before coming into effect of Section 18 of RERA and prior
to the registration of the project, the contractual obligation to hand over
possession had occurred prior to coming into force of Section 18 of
RERA. That therefore observations made in paragraph 137 of the
judgment in Neelkamal Realtors (supra) would apply to the present
case. That the possession date of 31 December 2017 was always
understood to be a tentative date. That mitigating circumstances were
totally ignored by the Appellate Tribunal. Mr. Pungaliya accordingly
prays for setting aside the impugned orders passed by the Appellate
Tribunal.
katkam Page No. 10 of 28
k 11/28 SA (St) 8825 of 2025 with IA
15.The Appeal is opposed by Mr. Kapadia, the learned counsel
appearing for Respondent Nos.1 and 2. He submits that MahaRERA had
grossly erred in giving option to the Promoter to refund the amount
after securing OC for the project. That once allottees are permitted to
withdraw from the project, they must receive their payments alongwith
interest without having to wait for securing the OC. He submits that
provisions of Section 18 of RERA are clear and unambiguous, which do
not permit withholding of amount by the promoter and makes the
allottee entitled to receive the entire amount along with interest on
making a demand. He submits that the findings recorded by the Apex
Court in Newtech Promoters in paragraph 25 of the judgment are not
obiter dicta, as erroneously sought to be suggested by the Appellants.
That the same constitute declaration of law. He also relies on several
other findings recorded by the Apex Court in Newtech Promoters in
support of his contention that the Apex Court has laid down a law that
the allottee has an unqualified right to secure a refund of the entire
amount alongwith interest by mere making of a demand. Mr. Kapadia
accordingly prays for dismissal of the Appeal.
CONSIDERATION OF SUBMISSIONS
16.The case involves non-completion of project by the Appellants-
Promoter. Respondent Nos.1 and 2 (allottees) booked Flat No.702 in
Building C-1 in the project ‘Waterways’ on 14 January 2015. Thereafter,
an Agreement for Sale was executed and registered on 16 May 2016. The
agreed consideration for the flat was Rs.43,13,200/-. Out of the agreed
katkam Page No. 11 of 28
k 12/28 SA (St) 8825 of 2025 with IA
amount of consideration, the allottees have paid an amount of
Rs.22,58,178/- to the Appellants from time to time.
17.The Appellants were required to hand over possession of the flat
to the allottees by 31 December 2017. However, admittedly, the Project
has not been completed by the Appellants even till date. After waiting
for a substantial time, Respondent Nos.1 and 2 approached MahaRERA
in 2019 and lodged a Complaint. While allowing the Complaint,
MahaRERA issued a rather confusing direction. It would be apposite to
reproduce the operative part of MahaRERA's order dated 24 August
2021:
Thus, the present complaints are allowed to withdraw from the said Project
and the Complainants are entitled to refund of the entire amount paid by
them with interest from 01.07.2021 for complaint No.CC001000000000100 and
from 01.01.2018 complaint No.CC001000000000102 at the rate as presribed
under Rule 18 of the Maharashtra Real Estate (Regulation and Development)
(Registration of Real Estate Projects, Registration of Real Estate Agents, Rate of
Interest and Disclosures on website) Rules 2017. However, in view of the
mitigating circumstances beyond the control of the Respondent and also to
ensure that the said Project is not jeopardised due to the outflow of finances
and is completed keeping in mind the interest of the other buyers of the said
Project at large, it is directed that the amounts of refund and the interest
thereupon shall be paid by the Respondent to the Complainant upon the
Respondent obtaining occupation certificate (OC) for the said Project.
However, in case the Respondent so desires to pay the same before obtaining
OC the period of interest calculation shall be from 07.07.2021 for complaint
No.CC001000000000100 and from 01.01.2018 complaint
No.CC001000000000102 up to date of refund of the entire amount together
with interest as aforesaid.
(underlining added)
18.As observed above, two Complaints have been simultaneously
decided by MahaRERA, and Respondent Nos.1 and 2 were Complainants
in Complaint No.CC001000000000102. Thus, the final order passed by
MahaRERA allowed Respondent Nos.1 and 2 to withdraw from the
katkam Page No. 12 of 28
k 13/28 SA (St) 8825 of 2025 with IA
Project and also held that they are entitled to a refund of the entire
amount paid by them along with interest with effect from 1 January 2018
at the rate as prescribed under the Rules of 2017. However, in the
subsequent part of operative directions, the MahaRERA gave two
options to the Appellants/Promoters. Under the first option, the refund
and interest was payable upon obtaining OC for the project. The second
option was to make immediate payment of the amount with interest.
Thus, MahaRERA left it to the Promoter to decide when to grant the
refund along with interest. Though the Promoter was granted the option
to refund the received amount upon obtaining the OC for the project,
the Promoter was required to bear the interest burden up to the date of
actual payment. The directions were apparently issued with a view to
ensure that the flow of funds for the project is not disturbed and the
direction to return the amount with interest does not result in the
promoter getting incapacitated to complete the remaining project,
thereby affecting other flat purchasers.
19.Respondent Nos.1 and 2 / allottees got aggrieved by the option
given to the Promoter to refund the amount after obtaining the OC, and
accordingly, filed an Appeal before the Appellate Tribunal. As if the
confusion created by MahaRERA was not enough, the Appellate Tribunal
added its share of confusion while passing two orders. In the original
order dated 7 November 2023, the Appellate Tribunal directed deletion
of the portion (underlined below) which granted two options to the
Promoter for making a refund of the amount and interest. Instead, the
Appellate Tribunal directed the Promoter to refund the entire paid
katkam Page No. 13 of 28
k 14/28 SA (St) 8825 of 2025 with IA
amount together with interest ‘from the date of receipt of the
payments’, along with interest, within a period of 23 days. The operative
part of the order dated 7 November 2023 passed by the Appellate
Tribunal reads thus:
a) Appeal is partly allowed.
b) Impugned order dated 24th August 2021 passed in Complaint No. CC
006000000000102 is modified as hereunder.
i. Following directions / observations provided in para 13 [final order] in the
operative part of the impugned order dated 24th August 2021 providing
options to promoters for refund of the paid amounts to allottees are quashed,
set aside and accordingly stands deleted; -
“ in view of the mitigating circumstances beyond the control of the Respondent and
also to ensure that the said project is not jeopardised due to the outflow of
finances and is completed keeping in mind the interest of the other buyers of the
said project at large, it is directed that the amounts of refund and the interest
thereupon shall be paid by the Respondent to the Complainant upon the
Respondent obtaining occupation certificate (OC) for the said Project. However, in
case the Respondent so desires to pay the same before obtaining OC the period of
interest calculation shall be from 01.01.2018 up to date of refund of the entire
amount together with interest as aforesaid. ”
ii. Respondent Promoter is directed to refund the entire paid amounts within
23 days to Appellants allottees together with interest from the date of receipt
of the payments at the rate of highest marginal cost of lending rate of State
Bank of India plus 2%, failing which, promoter will pay interest at this rate on
the total amount due and outstanding as on 30th November 2023 till its
complete refund/ realisation of these outstanding amounts along with
interest.
c) No order as to costs.
d) In view of the provisions of Section 44(4) of the Act of 2016, a copy of this
order shall be sent to the parties and to MahaRERA.
(underlining added)
20.Deletion of only underlined portion from operative direction of
MahaRERA’s order resulted in conflicting directions in the retained
katkam Page No. 14 of 28
k 15/28 SA (St) 8825 of 2025 with IA
portion of MahaRERA’s order and new direction issued in Para 15(b) (ii)
by the Appellate Tribunal. the retained/portion of MahaRERA’s order
contemplated payment of interest from ‘1 January 2018’, whereas
direction in Para 15(b)(ii) of the Appellate Authority’s order
contemplated payment of interest from ‘the date of receipt of payments’
i.e. from 2015-2016.
21.The Promoter applied for a review of the order dated 7 November
2023, and the Review Application has been partly allowed by the
Appellate Tribunal by passing the following operative directions:
a) Captioned review application stands partly allowed.
b) The direction to the applicant promoter in para no. 15(b) (ii) of the
judgment dated 7
th
November 2023, stands deleted.
c) Parties to bear their own costs.
Thus, the direction in paragraph 15(b)(ii) of the judgment and order
dated 7 November 2023 is now deleted.
22.This Court does not appreciate the manner in which the Appellate
Tribunal has given operative directions, which are unclear and capable
of causing confusion. One has to undertake a complex exercise to
comprehend the exact final direction which the Promoter is expected to
comply. It took some time for this Court to understand what exactly the
final direction is, which the Promoter is expected to comply/implement.
This Court was required to repeatedly go back and forth between the
orders passed by MahaRERA, the main order passed by the Appellate
Tribunal, and the review order passed by the Appellate Tribunal. With
some degree of effort, this Court has finally understood the exact
katkam Page No. 15 of 28
k 16/28 SA (St) 8825 of 2025 with IA
purport and final outcome of the litigation between the parties. Now, the
only direction which is capable of being implemented is the direction of
MahaRERA allowing Respondent Nos.1 and 2 to withdraw from the
Project and direction to the Promoter to refund the entire amount paid
by Respondent Nos.1 and 2 alongwith interest from 1 January 2018 as
per the rate prescribed in Rule 18 of the Rules of 2017.
23.If clear and unambiguous directions were to be issued by the
Appellate Tribunal, the time spent by this Court in comprehending the
exact nature of directions would have been saved. Be that as it may. Now
I proceed to decide whether there is any interference warranted in the
final direction given to the Promoter for refund of entire amount
alongwith interest from 1 January 2018.
24.As observed above, Appellants are not averse to refunding the
amount received from the allottees. They are also not averse to paying
interest at the rate prescribed in Rule 18 of the Rules of 2017. They are
only aggrieved by withdrawal of the option given to them by MahaRERA
to pay the amount and interest after obtaining OC for the Project. I
proceed to examine whether withdrawal of the said option by the
Appellate Tribunal is in order or not.
Question Nos. 1, 2 and 3
25.Since all the questions are interconnected, the same are taken up
for decision together.
katkam Page No. 16 of 28
k 17/28 SA (St) 8825 of 2025 with IA
26.The first question formulated is whether the obligation of the
Promoter to return to the allottee the amount received by him alongwith
interest on demand made by the allottee under Section 18(1) of RERA is
absolute and unqualified or whether the Regulatory Authority or the
Appellate Tribunal has any discretion to take into consideration the
mitigating circumstances or genuine efforts made by the Promoter in
completing the project for granting some relaxation either in respect of
period of interest or the rate of interest or the date on which the refund
is to be made. This question is interconnected with question No.2. Since
it is sought to be suggested by and on behalf of the Appellants that
observations made by the Hon’ble Apex Court in paragraph 25 of the
judgment in Newtech Promoters (supra) are in the obiter, it is also
sought to be suggested by the Appellants that the finding recorded by
Division Bench of this Court in Neelkamal Realtors (supra) can be
followed and and it is open for the Regulatory Authority and/or the
Appellate Tribunal to take into consideration genuine efforts of a
promoter and grant relaxation while issuing directions under Section
18(1) of RERA. It is therefore contended on behalf of the Appellants that
MahaRERA was right in granting option to the Promoter to refund the
amount and interest only after securing OC for the project.
27.To answer the questions, it would be necessary to take into
consideration the provisions of Section 18 of RERA, which provides thus:
18. Return of amount and compensation.—
(1) If the promoter fails to complete or is unable to give possession of
an apartment, plot or building,—
katkam Page No. 17 of 28
k 18/28 SA (St) 8825 of 2025 with IA
(a) in accordance with the terms of the agreement for sale or, as the
case may be, duly completed by the date specified therein; or
(b) due to discontinuance of his business as a developer on account of
suspension or revocation of the registration under this Act or for any
other reason,
he shall be liable on demand to the allottees, in case the allottee wishes to
withdraw from the project, without prejudice to any other remedy available, to
return the amount received by him in respect of that apartment, plot, building,
as the case may be, with interest at such rate as may be prescribed in this
behalf including compensation in the manner as provided under this Act:
Provided that where an allottee does not intend to withdraw from the
project, he shall be paid, by the promoter, interest for every month of delay, till
the handing over of the possession, at such rate as may be prescribed.
(2) The promoter shall compensate the allottees in case of any loss
caused to him due to defective title of the land, on which the project is being
developed or has been developed, in the manner as provided under this Act,
and the claim for compensation under this subsection shall not be barred by
limitation provided under any law for the time being in force.
(3) If the promoter fails to discharge any other obligations imposed on
him under this Act or the rules or regulations made thereunder or in
accordance with the terms and conditions of the agreement for sale, he shall
be liable to pay such compensation to the allottees, in the manner as provided
under this Act.
28.A plain reading of Section 18(1) of RERA would indicate that
promoter has an obligation to return the amount received by him
alongwith interest on demand by the allottee. Section 18(1) of RERA
does not leave any option or discretion about the timeline at which
refund is to be made. Once the promoter fails to complete the project or
is unable to give possession of the apartment within the timeline agreed,
allottee has a right to demand refund of amount paid by him, and the
promoter has an obligation to fulfill that demand by refunding the
amount received by him alongwith interest immediately on making such
demand. In that sense, there is an unqualified right created in favour of
the allottee to seek the refund under Section 18(1) of RERA.
katkam Page No. 18 of 28
k 19/28 SA (St) 8825 of 2025 with IA
29.Section 18 of RERA talks of two amounts viz. (i) amount received
by the promoter from the allottee, and (ii) compensation to be recovered
by the allottee from the promoter. A plain reading of Section 18(1) and
18(2) of RERA would indicate that return of amount and interest thereon
is the bare minimum which the allottee must receive from the Promoter.
If the allottee is in a position to prove cause of loss and entitlement to
receive compensation, the same can be pressed before the Adjudicating
Authority under Section 18(2) of RERA. Thus, while payment of
compensation amount may await adjudication, return of amount
received by the Promoter and interest thereon must be paid immediately
on raising of a demand. Section 18(1) of RERA thus does not leave any
discretion for the Promoter or to the Regulatory Authority or to the
Appellate Tribunal to delay return of the paid amount or to direct that
the refund can be made only after obtaining OC for the project.
30.Thus, on plain reading of Section 18 of RERA, in my view, the right
to seek return of amount with interest is absolute and unqualified. The
right cannot be diluted by the Regulatory Authority or by the Appellate
Authority or even by the High Court by giving any concession to the
promoter to return the amount only after securing OC for the project.
31.The issue of unqualified nature of allottee’s right to seek refund is
also recognised by the Apex Court in Newtech Promoters (supra). In that
case, the Apex Court essentially took up for consideration the issue as to
whether RERA is retrospective or retroactive in operation. The Apex
katkam Page No. 19 of 28
k 20/28 SA (St) 8825 of 2025 with IA
Court also took up for consideration the issue as to whether the
Regulatory Authority had jurisdiction to direct return/refund of the
amount or whether such jurisdiction lies exclusively with the
Adjudicating Officer. The issue before the Apex Court was also whether a
single member of the Authority can hear complaints instituted under
Section 31 of RERA. The fourth issue for consideration before the Apex
Court was whether condition of pre-deposit under proviso to Section
43(5) of RERA for entertaining substantive right of appeal was
sustainable in law. The last issue for consideration was whether
Regulatory Authority has power to issue Recovery Certificate for
recovery of principal amount under Section 40(1) of RERA. The issues
taken up for consideration are listed in paragraph 31 of the judgment of
Apex Court in Newtech Promoters (para 30 of SCC Report). Relying on
the list of five issues, it is sought to be contended by Mr. Pungaliya that
the Apex Court did not take up for consideration the issue as to whether
Regulatory Authority and/or the Appellate Tribunal has any discretion to
grant relaxation to a promoter making genuine efforts to complete the
project or whether they have the power of molding the relief. This
argument on behalf of the Appellant is necessitated on account of the
fact that in paragraph 25 of the judgment (Paragraph 24 in SCC Report),
the Apex Court has held that right of the allottee to seek refund under
Section 18(1) of RERA is absolute and not dependent on any
contingencies or stipulations. For the sake of convenience, paragraph
number ‘24’ of judgment in Newtech Promoters of the SCC report is
referred. In paragraph 24 of the judgment the Apex Court held as under:
katkam Page No. 20 of 28
k 21/28 SA (St) 8825 of 2025 with IA
24. The unqualified right of the allottee to seek refund referred under Section
18(1)(a) and Section 19(4) of the Act is not dependent on any contingencies or
stipulations thereof. It appears that the legislature has consciously provided
this right of refund on demand as an unconditional absolute right to the
allottee, if the promoter fails to give possession of the apartment, plot or
building within the time stipulated under the terms of the agreement
regardless of unforeseen events or stay orders of the court/tribunal, which is in
either way not attributable to the allottee/homebuyer, the promoter is under
an obligation to refund the amount on demand with interest at the rate
prescribed by the State Government including compensation in the manner
provided under the Act with the proviso that if the allottee does not wish to
withdraw from the project, he shall be entitled for interest for the period of
delay till handing over possession at the rate prescribed.
32.Since the findings recorded in paragraph 24 of the judgment do
not leave any discretion for the Regulatory Authority and/or the
Appellate Tribunal to grant any relaxation to promoters making genuine
efforts to complete the project, it is sought to be suggested by Mr.
Pungaliya that those observations are mere obiter dicta as they have no
connection with the five issues taken up for consideration by the Hon’ble
Apex Court. I am unable to agree. The Apex Court was equally concerned
with the interpretation of provisions of Section 18 of RERA. In paragraph
72 of the judgment, the Apex Court has held that refund and
compensation are two distinct rights under the Act and cannot be
conflated. The Apex Court, while deciding the issue as to whether the
Regulatory Authority has jurisdiction to direct return/refund, has held in
paragraphs 71, 72 and 74 of the judgment as under:
71. Thus, refund and compensation are two distinct rights under the Act and
cannot be conflated. The manner in which the two are to be determined would
require a different process and involve different considerations. According to
her, the determination of compensation involves a full-fledged adjudicatory
process which is more complex than that involved in determining refund. To
do so, it would tantamount to regressing into the very malaise that the
legislature intended to liberate the allottees-homebuyers from. The result of
katkam Page No. 21 of 28
k 22/28 SA (St) 8825 of 2025 with IA
conflating the rights and/or relegating the allottees to the adjudicating officer
would amount to a compromise of the timeliness of the right to refund on
demand. It would also deter and daunt allottees from seeking compensation
because in the process the remedies would be clubbed and the availability of
refund would get relatively delayed as compensation requires a more elaborate
adjudication process (even though the same is required to be completed in 60
days). The Authority to determine a claim for refund on demand while the
adjudicating officer to determine the claim for compensation.
72. The expression “on demand” which follows the right to “return of amount”
is indicative of the priority, immediacy and expediency which is accorded to
the right to refund. Thus, according to her, the expressions “refund” and
“return of amount” is an act of restitution, and the obligation to restitute lies
on the person or the Authority that has received unjust enrichment or unjust
benefit.
74. The legislature in its wisdom has made a specific provision delineating
power to be exercised by the Regulatory Authority/adjudicating officer.
“Refund of the amount” and “compensation” are two distinct components
which the allottee or the person aggrieved is entitled to claim if the promoter
has not been able to hand over possession with a nature of enquiry and
mechanism provided under the Act. So far as the claim with respect to refund
of amount on demand under Sections 18(1) and 19(4) of the Act is concerned,
it vests within the jurisdiction of the Regulatory Authority. Section 71 carves
out the jurisdiction of the adjudicating officer to adjudge compensation under
Sections 12, 14, 18 and 19 after holding enquiry under Section 71(3) of the Act
keeping in view the broad contours referred to under Section 72 of the Act.
33.Thus, it cannot be said by any stretch of imagination that what is
observed by the Apex Court in paragraph 24 of the judgment in Newtech
Promoters (supra) is a mere obiter. The Apex Court in Newtech
Promoters lays down a law that there is a priority, immediacy and
expediency accorded to the right of the allottee to seek refund. The Apex
Court has interpreted the expression “on demand” appearing in Section
18(1) of RERA. Therefore, observations of the Hon’ble Apex Court in
paragraph 24 of the judgment are also required to be read in conjunction
with the findings recorded in paragraphs 71, 72 and 74 of the judgment.
Merely because the findings in paragraph 24 precede the formulation of
katkam Page No. 22 of 28
k 23/28 SA (St) 8825 of 2025 with IA
questions/issues in paragraph 30, it would be erroneous to assume that
the observations made in paragraph 24 are mere obiter. The Apex Court
has declared a law in Newtech Promoters (supra) that an allottee has an
unqualified right to seek refund under Section 18(1) of RERA and if the
promoter fails to give possession of the apartment within time
stipulated under the terms of agreement, regardless of unforeseen
events or stay orders of Court/Tribunal (not attributable to the allottee),
the promoter is under obligation to refund the amount on demand with
interest.
34.Mr. Pungaliya has strenuously relied on the judgment of Division
Bench of this Court in Neelkamal Realtors (supra), in which the
constitutional validity of certain provisions of RERA were challenged.
While questioning the constitutional validity of provisions of Section 18
of RERA, it was sought to be suggested that Section 18 of RERA did not
contemplate taking into consideration genuine efforts made by the
Promoter to complete the project. While dealing with the argument, this
Court held in paragraph 137 as under:
137. The another plea raised is as to why a promoter shall pay interest for the
past contractual rights, in case of failure to complete the project after
registration under RERA, till the possession is handed over. Under the scheme
of the RERA it is clear by now that a promoter has to self assess and declare
time period during which he would complete the project. But in case, inspite of
making genuine efforts, a promoter fails to complete the project, then the
concerned authorities, adjudicators, forums, tribunals would certainly look
into genuine cases and mould their reliefs accordingly. We do not find that on
that count the provisions of Section 18(1)(a) are to be declared as contrary and
violative of Articles 14 and 19(1)(g). Considering the scheme of the RERA and
the provisions of Section 18(1)(b), we are of the view that the same are not
contrary to Articles 14 and 19(1)(g) of the Constitution. The provisions cannot
be struck down on the ground of challenge that its operation is retroactive in
katkam Page No. 23 of 28
k 24/28 SA (St) 8825 of 2025 with IA
nature. Neither the provisions of Section 18(1)(a) and (b) violate Article 20 of
the Constitution. The payment of interest under Section 18 is compensatory in
nature [Abati Bezbaruah v. Director General, Geological Survey of India-(2003) 3
SCC 148 (para 18) and Alok Shanker Pandey v. UOI-(2007) 3 SCC 545 (para 9)].
35.By relying on findings recorded by this Court in paragraph 137 of
the judgment in Neelkamal Realtors (supra), it is sought to be suggested
by Mr. Pungaliya that the Regulatory Authority as well as the Appellate
Tribunal has power to take into consideration genuine cases and mould
the reliefs accordingly. In my view, findings recorded by the Division
Bench of this Court in Neelkamal Realtors (supra) in paragraph 137 of
the judgment cannot be read to mean as if any relaxation is permissible
when it comes to return of the amount received by the promoter from
the allottee along with interest. The right would always continue to
remain absolute and unqualified. Right to seek refund of what is paid to
the promoter is the bare minimum which an allottee must receive under
any circumstances. Even if the promoter may not be at fault in not
completing the project within the agreed timeline, the minimum that he
must do is to return the amount received by him from the allottee
together with interest. In a given case, an allottee may suffer other
losses. He may have to bear the burden of paying rent or interest to
banks and housing loan companies. In a given case, a home buyer may
have to bear a double whammy of paying loan installments as well as
rent. In such circumstances, an allottee may suffer consequences of sale
of his/her assets on account of inability to repay loan installments, and
may suffer mental torture as well as financial losses. In such
circumstances, the allottee can prove cause of loss and claim
damages/compensation from the promoter. If a promoter makes genuine
katkam Page No. 24 of 28
k 25/28 SA (St) 8825 of 2025 with IA
efforts to complete the project and is not at all responsible for delay, in
such circumstances, the Adjudicating Authority, Tribunal, or the Court
may relieve the promoter from liability to compensate the allottee.
However, return of amount received by the promoter from the allottee
together with interest is the bare minimum which the promoter must
perform in every case, including a case where the promoter has made
genuine efforts to complete the project within the agreed timeline. In
my view therefore, the judgment of the Division Bench of this Court in
Neelkamal Realtors (supra) cannot be read to mean as if any relaxation
is permissible for a promoter on a case-to-case basis in respect of
liability to return the amount received from the allottee along with
interest.
36.Reliance by Mr. Pungaliya on order passed by the Apex Court in
Career Institute Educational Society (supra) in support of his contention
that observations in paragraph 24 of the judgment in Newtech
Promoters (supra) are obiter, is clearly misplaced. In Career Institute
Educational Society, the Apex Court has underscored the distinction
between an obiter dicta and a ratio decidendi in a judgment. Referring to
its judgments in State of Gujarat and Others v. Utility Users’ Welfare
Association
4
and Jayant Verma and Others v. Union of India and
Others
5
, the Apex Court has discussed “the inversion test”, which
contemplates removal of the proposition from the text of the judgment
and to examine whether the conclusion of the case would still remain
the same. In such circumstances, the removed proposition cannot be
4
(2018) 6 SCC 21
5
(2018) 4 SCC 743
katkam Page No. 25 of 28
k 26/28 SA (St) 8825 of 2025 with IA
treated as ratio decidendi. In Jayant Verma, the Apex Court has held that
only the statements of principle of law applicable to the legal problems
disclosed by the facts would operate as a precedent. It is held that not
everything said by a judge when giving the judgment would constitute a
precedent. However, in the present case, the findings recorded by the
Apex Court in paragraph 24 of the judgment in Newtech Promoters
(supra), when read in conjunction with other findings recorded at
paragraphs 71, 72, and 74 make it clear that the Apex Court was
concerned with the interpretation of provisions of Section 18 of RERA,
and interpretation made by it would constitute a binding precedent to be
followed by all Courts in India. Therefore, I am unable to accept the
contention of Mr. Pungaliya that the findings recorded in paragraph 24
of the judgment in Newtech Promoters (supra) is an obiter by any stretch
of imagination.
ANSWERS TO THE QUESTIONS FORMULATED
37.Thus, in view of the above discussion, the questions of law are
answered as under:
i)The obligation of a promoter to return to the allottee the amount
received by him with interest on demand made by the allottee
under Section 18(1) of RERA is absolute and unqualified. The
Regulatory Authority and/or the Appellate Tribunal does not have
discretion to take into consideration any mitigating circumstances
or genuine efforts made by the promoter in completing the project
katkam Page No. 26 of 28
k 27/28 SA (St) 8825 of 2025 with IA
in time for the purpose of granting any relaxation, either in
respect of the period during which interest is payable, or in the
rate of interest or the date on which refund is to be made.
ii)The observations made by the Hon’ble Apex Court in paragraph 24
of the judgment in Newtech Promoters (supra) are not obiter dicta
and they constitute ratio decidendi. Findings recorded by the
Division Bench of this Court in paragraph 137 of the judgment in
Neelkamal Realtors (supra) cannot be read to mean as if any
discretion exists with the Regulatory Authority or with the
Appellate Tribunal in granting any relaxation to the promoter,
who makes genuine efforts in completing the project in time in
the matter of either period during which interest is payable or in
the rate of interest or the date on which refund is to be made.
iii)It is impermissible for the Regulatory Authority and/or the
Appellate Tribunal to direct that return of amount with interest
shall only be after securing Occupation Certificate of the project
and not upon demand made by the allottee under Section 18(1) of
RERA.
38.In view of the above answers to the questions formulated, in my
view, the ultimate direction given to the Appellants-Promoter to refund
the entire amount received by them from the allottees alongwith
interest at the rate prescribed under Rule 18 of Rules of 2017 with effect
from 1 January 2018 is valid and does not warrant any interference.
katkam Page No. 27 of 28
k 28/28 SA (St) 8825 of 2025 with IA
ORDER
39.Resultantly, the Second Appeal is dismissed. In the facts and
circumstances of the case, there shall be no order as to costs.
40.In view of the disposal of the Second Appeal, nothing would
survive in the Interim Application for stay and the same is also
accordingly disposed of.
(SANDEEP V. MARNE, J.)
katkam Page No. 28 of 28
Legal Notes
Add a Note....