No Acts & Articles mentioned in this case
2024:MHC:1290OSA (CAD) NOS.150 AND 154 OF 2021
IN THE HIGH COURT OF JUDICATURE AT MADRAS
JUDGMENT RESERVED ON
24 / 01 / 2024
JUDGMENT DELIVERED ON
14 / 03 / 2024
CORAM :
THE HONOURABLE MR. JUSTICE R.SUBRAMANIAN
AND
THE HONOURABLE MR. JUSTICE R.SAKTHIVEL
OSA (CAD) NOS.150 AND 154 OF 2021
AND
CMP NO.21109 OF 2021 IN OSA (CAD) NO.150 OF 2021
AND CMP NO.21249 OF 2021 IN OSA (CAD) NO.154 OF 2021
Accudyne Industries India Private Limited
Represented by its Authorised Signatory
Mr.Sridhar Jawahar
No.4, Rajarajan Street, Visalakshi Nagar,
Ekkaduthangal, Chennai – 600 097. ... Appellant in both OSAs'
(Cause title accepted vide order
dated 10.11.2021)
Vs.
M/s.R.P.Rajarajan Enterprises
Represented by its Managing Partner
R.Parthiban S/o. K.A.Rishikesavam
Having its office at No.39, Habibullah Road,
T.Nagar, Chennai – 600 017. ... Respondent in both OSAs'
1/42
https://www.mhc.tn.gov.in/judis
OSA (CAD) NOS.150 AND 154 OF 2021
PRAYER IN OSA (CAD) NO.154 OF 2021: Original Side Appeal filed
under Order 36 Rule 1 of Original Side Rules read with Section 13 of the
Commercial Courts Act, 2015, praying to set aside the Judgment and
Decree dated 19.02.2021 passed in C.S.No.692 of 2012 and dismiss the
judgment and decree to the extent of directing the appellant to pay a sum
of Rs.1,40,14,080/- (Rupees One Crore Forty Lakh Fourteen Thousand and
Eighty only) along with intererst at the rate of 12% from 29.10.2008 to the
respondent.
PRAYER IN OSA (CAD) NO.150 OF 2021: Original Side Appeal filed
under Order 36 Rule 1 of Original Side Rules read with Section 13 of the
Commercial Courts Act, 2015, praying to set aside the Judgment and
Decree dated 19.02.2021 passed in C.S.No.692 of 2012 to the extent of
dismissal of the counter-claim filed by the appellant, and allow the
counter-claim by directing the respondent to pay a sum of Rs.1,18,43,273/-
(One Crore Eighteen Lakh Forty Three Thousand Two Hundred and
Seventy Three only) along with interest at the rate of 24% from 29.11.2007
till the date of payment.
For Appellant : Mr. P. H. Aravindh Pandian
(in both OSAs' ) Senior Counsel for
Mr. Thriyambak J. Kannan
For Respondent : Mr. V. Anand
(in both OSA's)
2/42 https://www.mhc.tn.gov.in/judis
OSA (CAD) NOS.150 AND 154 OF 2021
COMMON JUDGMENT
R.SAKTHIVEL, J.
By this common Judgment, the following appeals are being
disposed of :
(i)OSA (CAD) NOS.154 of 2021 preferred assailing the
Judgment and Decree dated 19.02.2021 passed in C.S.No.692 of 2012, by
the defendant therein, praying to set aside the same.
(ii)OSA (CAD) NOS.150 of 2021 preferred assailing the
rejection of the counter-claim in Judgment and Decree dated 19.02.2021
passed in C.S.No.692 of 2012, by the defendant therein, praying to allow
the counter-claim.
2.For the sake of convenience, henceforth, the parties will be
referred to as per their array in the suit i.e., ‘appellant’ and the ‘respondent
herein’ will be referred to as ‘defendant’ and ‘plaintiff’ respectively.
3/42 https://www.mhc.tn.gov.in/judis
OSA (CAD) NOS.150 AND 154 OF 2021
3. Case of the Plaintiff in brief
3.1.The plaintiff owns lands admeasuring 1.67 Acres in
S.Nos.60/11C, 60/12, 61/17C, 61/18, 61/19 and 61/20B at Old No.101,
New No.55, Thandalam Village, Sriperumpudur Taluk. The defendant
proposed a built-to-suit lease arrangement. After discussions, a registered
Lease Deed was executed on 29.11.2007. It was agreed that the plaintiff as
lessor would construct an industrial shed with approximately 30,000 sq.ft
of factory space and 7,000 sq.ft of office space and hand it over to the
defendant as lessee within six months from the date of execution of the
lease deed. As per the agreement, necessary building construction
permissions and licenses had to be obtained by the plaintiff and other
permissions relating to running the industry had to be obtained by the
defendant.
4/42 https://www.mhc.tn.gov.in/judis
OSA (CAD) NOS.150 AND 154 OF 2021
3.2.At a subsequent meeting, the said period had been altered
and the date of commencement was changed to 01.04.2008 owing to the
delay primarily attributable to the defendant, who changed the construction
specifications frequently, and also owing to the delay on account of
rainfall. The construction commenced and proceeded till the roof level
under regular supervision of the defendant through its Managing Director
and representatives. Further, the defendant was dependent on a Multi
National French company for its business. The industrial shed had to be
constructed according to the needs of the foreign company and therefore,
the specifications kept changing. Though the plaintiff incurred additional
expenses, the changes desired by the defendant’s side were carried out duly
by the plaintiff.
3.3.The issue of construction of toilet for the office space
generated a dispute between the plaintiff and the defendant and this was
resolved in a meeting held on 26.08.2008. It was resolved that the
5/42 https://www.mhc.tn.gov.in/judis
OSA (CAD) NOS.150 AND 154 OF 2021
construction of the toilets for the office space would be carried out with no
additional charges on the defendant. The other specifications regarding
roof height and flooring level were agreed to be uniform. It was further
agreed that the plans from the municipality should be obtained by the
plaintiff and only after the defendant approves the drawings and plans,
construction should be commenced by the plaintiff; that the revised
drawings approved by the municipality should be handed over to the
defendant by 30.10.2018; and that the entire construction should be
completed on or before 30.12.2008.
3.4.The agreement arrived at in the aforementioned meeting
brought about substantial variation in the terms and conditions of the
registered Lease Deed dated 29.11.2007. The changes in the construction
were on account of additional open space of 6698 sq.ft required in addition
to the originally agreed 6400 sq.ft of open space mentioned in the Lease
Deed.
6/42 https://www.mhc.tn.gov.in/judis
OSA (CAD) NOS.150 AND 154 OF 2021
3.5.Further, owing to the drop of export potential of the
defendant in July 2008 and other difficulties faced by the defendant, the
plaintiff was blamed by the defendant for deviation from the agreed plan
and approved drawing by letter dated 02.08.2008. The plaintiff by letter
dated 07.08.2008 set out the details of the requirement of the defendant
and sought clarification regarding the location of the toilets for resuming
construction. It had been also stated that the period fixed for completing
construction namely 30.12.2008 should be extended further.
3.6.The defendant had also taken up the issue of additional
rent for the additional space vide letter dated 02.08.2008 which was refuted
by the plaintiff by letter dated 07.08.2008. The plaintiff had made clear
that many modifications have been sought by the defendant and there were
also many deviation in the approved plan. The plaintiff claimed they had
spent more than Rs.1.5 Crores towards construction and that the ground
level was raised for the entire lease area.
7/42 https://www.mhc.tn.gov.in/judis
OSA (CAD) NOS.150 AND 154 OF 2021
3.7.Further, the defendant by letter dated 29.10.2008
terminated the lease exercising Clause No.5.2 and Clause No.8.5 of the
registered Lease Deed dated 29.11.2007. The defendant alleged that the
construction had not been done in accordance with the specifications and
the drawings. The plaintiff had issued a reply on 02.11.2008 stating that a
huge amount of money had been spent on construction. The plaintiff also
pointed out that there was no delay on their part in the construction.
3.8.The defendant then issued a legal notice dated 08.12.2008,
and for the first time, allegations were raised against the plaintiff. The
plaintiff issued a reply through their advocate on 18.12.2008. The plaintiff
claimed that the amount alleged to have been incurred by the defendant to
a sum of Rs.1,43,54,324/- was not sustainable. The defendant issued a re-
joinder to the notice of the plaintiff. The plaintiff replied through their
counsel on 05.01.2009. The plaintiff claimed that they had spent a sum of
Rs.3.75 Crores on construction. The rent agreed was Rs.9,73,200/- per
8/42 https://www.mhc.tn.gov.in/judis
OSA (CAD) NOS.150 AND 154 OF 2021
month. They also estimated that they would have realized rent up to
Rs.8,31,69,504/- for the six-year lock-in period. The plaintiff therefore is
entitled to a total amount of Rs.12,06,69,504/- which consists of the rent
and construction cost. However, the plaintiff claimed the rents payable by
the defendant only for three years namely, from 30.12.2008 to 29.12.2011
while reserving their right to claim rent for the rest of the lock-in period.
3.9.The plaintiff had therefore filed a Civil Suit for a
declaration that the termination of the Lease Deed by the Defendant vide
letter dated 29.10.2008 is illegal; for recovery of a sum of Rs.3,85,89,216/-
together with interest from the date of termination of the lease i.e.,
29.10.2008 till the date of realization; and also for costs, before the
Hon’ble Single Judge of this Court.
9/42 https://www.mhc.tn.gov.in/judis
OSA (CAD) NOS.150 AND 154 OF 2021
4. Case of the defendant in brief and counter claim
4.1.The defendant filed their written statement, in which they
claimed that the suit is barred by law of limitation as the period of
limitation expired on 29.10.2011. The defendant also questioned the
authority of the person who verified the plaint. The defendant also stated
that the plaintiff was not a registered partnership firm and hence, the suit
was not maintainable.
4.2.Further stated that, the plaintiff was to start construction
on 20.03.2008 and to complete the same within a period of six months;
that the plaintiff was required to develop, construct, and lease to the
defendant, the office and factory building at the said place; that the
defendant had paid to the plaintiff a total sum of Rs.1,17,02,840/-; and that,
however, the plaintiff deviated, did not carry out the construction as per the
terms agreed, failed to complete the construction and handover the
10/42 https://www.mhc.tn.gov.in/judis
OSA (CAD) NOS.150 AND 154 OF 2021
possession within six months from 29.11.2007. Therefore, the defendant
terminated the Lease Deed dated 29.11.2007 on 29.10.2008 and sought
return of Rs.1,17,02,840/- which had been paid by the defendant to the
plaintiff as advance in terms of the registered Lease Deed dated
29.11.2007 together with interest at 24% per annum from the date of
payment i.e., 29.11.2007 till the date of filing counter-claim and further
claimed subsequent interests on counter-claim. The defendant therefore
prayed to dismiss the suit with costs and allow the counter-claim.
5.A reply statement was filed by the plaintiff denying the
averments stated in the written statement including the counter-claim and
reiterating a few plaint averments.
6.Based on the above pleadings, the Hon'ble Single Judge
framed the following issues:
“1.Whether the plaint has been validly signed and
verified?
11/42 https://www.mhc.tn.gov.in/judis
OSA (CAD) NOS.150 AND 154 OF 2021
2.Whether the present suit is maintainable on account of
the plaintiff being an unregistered partnership?
3.Is the suit barred by limitation?
4.Is the Shed subject matter of the lease was delayed in
construction due to the variations required by the defendant?
5.Whether the termination of the lease by the defendant
through letter dated 29.10.2008 is valid?
6.Is the plaintiff entitled to recover money from the
defendant for the entire term of the lease under the lease deed
dated 29.11.2007, including the lock-in period?
7.To what relief the plaintiff is entitled?”
6.1.On 28.08.2019, the following additional issues were
framed:
“1.Whether the plaintiff is in breach of its obligations as
contained in the agreement dated 29.11.2007 entered into with
the defendant?
2.Whether the construction was completed, and
possession was delivered to the defendant by the plaintiff within
the period mutually agreed on by the parties?.
3.Whether the defendant is entitled to receive from the
plaintiff a sum of Rs.1,18,43,274/- including an interest of
Rs.1,40,434/- on the principal amount of Rs.1,17,02,840/- paid
as advance in terms of the lease deed dated 29.11.2007?”
12/42 https://www.mhc.tn.gov.in/judis
OSA (CAD) NOS.150 AND 154 OF 2021
6.2.To prove the case, Mr. R. Parthiban, Managing Partner of
the plaintiff firm was examined as P.W.1 and Ex-P.1 to Ex-P.12 were
marked on the plaintiff's side. On the defendant side, J. Sridhar, Finance
Controller of the defendant company, was examined as D.W.1, and Ex-D.1
to Ex-D.11 were marked. Notably, the defendant side marked Ex-D.1
through cross-examination of P.W.1.
6.3.After considering the rival submissions and the evidence
on record, the Hon’ble Single Judge held that the plaint has been duly
verified by the Managing Partner of the plaintiff firm; that the plaintiff is a
registered firm; that the plaint was presented on 28.10.2011 which is well
within the period of limitation; and that therefore, the suit is maintainable.
Accordingly, the Hon’ble Single Judge answered Issue Nos. 1, 2 and 3 in
favour of the plaintiff.
6.4.With regard to Issue 4 and Additional Issue No.1, the
Hon’ble Single Judge held that the construction was delayed due to the
13/42 https://www.mhc.tn.gov.in/judis
OSA (CAD) NOS.150 AND 154 OF 2021
changes sought by the defendant, and the plaintiff was not in breach of Ex-
P.2 – Lease Deed dated 29.11.2007.
6.5.With regard to Issue No.5, the Hon’ble Single Judge held
that the termination is invalid as it is premature. With regard to Additional
Issue No.2, Hon’ble Single Judge held that, as a consequence of the
decision on Issue No.5, the Additional Issue No.2 pales into insignificance.
6.6.With regard to Issue 6, the Hon’ble Single Judge held that
the plaintiff is entitled only to the base rent for a period of three years at
the rate of 3,89,280 per month and accordingly, directed the defendant to
pay a sum of Rs.1,40,14,080/-.
6.7.With regard to Additional Issue No.3, the Hon’ble Single
Judge held that, since the termination was held invalid, the defendant is not
entitled to the counter-claim raised.
14/42 https://www.mhc.tn.gov.in/judis
OSA (CAD) NOS.150 AND 154 OF 2021
6.8.With regard to Issue No.7, the Hon’ble Single Judge held
as extracted hereunder:
“115.The suit is partly decreed.
(a).The termination of the lease deed by the defendant
by letter dated 29.10.2008 is declared as illegal.
(b).The defendant is directed to pay a sum of
Rs.1,40,14,080/- together with interest at 12% per
annum from 29.10.2008 till date of realisation.
(c).The counter claim of the defendant is dismissed.
(d).The plaintiff is entitled for costs of the suit.”
7.Feeling aggrieved with the Judgement and Decree dated
19.02.202 and the rejection of the counter-claim, the defendant has
preferred these two appeals.
8. Arguments
8.1.Mr.P.H.Aravindh Pandian, the learned Senior Counsel
appearing for the appellant / defendant would argue that the defendant was
ready and willing to perform their part of the contract. In accordance with
15/42 https://www.mhc.tn.gov.in/judis
OSA (CAD) NOS.150 AND 154 OF 2021
Ex-P.2 – Lease Deed, the defendant obtained the necessary permissions
from the Tamil Nadu Pollution Control Board to establish the industry and
the same was communicated to the plaintiff on 08.01.2008 vide Ex-D.1.
Thereafter, the defendant required open space of 6698 sq.ft in addition to
the open space indicated in Ex-P.1 and the same was communicated to the
plaintiff on 20.03.2008 vide Ex-P.12 / Ex-D.4. In Ex-P.12 / Ex-D.4, both
parties have agreed in writing that the date of commencement of
construction shall be 01.04.2008 and both parties have also signed therein.
This would imply that the plaintiff had to complete the construction by
30.09.2008. The plaintiff raised some issues regarding the construction
cost of toilets which was already included and specified in the original
contract. In the meeting held on 26.08.2008, the issue regarding toilets was
resolved and further, the plaintiff agreed to provide facility to the
defendant for fit-outs by 15.11.2008. However, the plaintiff failed to
perform their part of the contract. Hence, on 29.11.2008, the defendant
terminated the contract by exercising Clause No.5.2 and Clause No.8.5 of
16/42 https://www.mhc.tn.gov.in/judis
OSA (CAD) NOS.150 AND 154 OF 2021
Ex-P.2 - Lease Deed and sought for refund of the advance amount of
Rs.1,17,02,284/- along with 24% interest from 29.11.2007 till the date of
filing counter-claim, along with subsequent interest. Thereafter, after
exchange of notices, the plaintiff filed the aforementioned Civil Suit.
8.2.The learned Senior Counsel would further argue that, the
Hon’ble Single Judge without properly appreciating the evidence on
record, partly decreed the Suit and dismissed the counter-claim of the
defendant. The defendant filed a complaint before consumer forum and the
same was dismissed as not maintainable. However, the defendant’s
counter-claim is maintainable in law. The Hon’ble Single Judge failed to
consider the fact that the entire construction was executed out of the
advance money paid by the defendant and the plaintiff failed to execute the
construction as required by the defendant. Further, the plaintiff did not
deliver possession of the industrial area within the stipulated time. Hence,
awarding base rent to the plaintiff would amount to unjust enrichment. He
17/42 https://www.mhc.tn.gov.in/judis
OSA (CAD) NOS.150 AND 154 OF 2021
accordingly prayed to allow these appeals, set aside the Judgement and
Decree passed by the Hon’ble Single Judge and allow the counter-claim of
the defendant.
9.Per contra, Mr.V.Anand, the learned counsel for the plaintiff
would argue that the plaintiff was ready and willing to perform their part of
the contract. The defendant had not fulfilled their part of the contract in
accordance with Ex-P.2- Lease Deed. Ex-P.12 / Ex-D.4 document would
show that the construction was to commence only from 01.04.2008 and the
delay in commencement is primarily attributable to the defendant. The
defendant in the month of July 2008 asked the plaintiff to hold on the
construction until further notice. There was a delay of 13 days on account
of rainfall. Then, since the defendant did not confirm the location of the
toilets in the factory and office area, there occurred a delay. The
construction was completed up to the roof level under the supervision of
the defendant. The defendant was frequently changing the specifications
18/42 https://www.mhc.tn.gov.in/judis
OSA (CAD) NOS.150 AND 154 OF 2021
for construction. The plaintiff carried out the desired changes of the
defendant duly. In the meeting held on 26.08.2008, the issue of
construction of toilet was resolved and both parties orally agreed to extend
the construction deadline till 30.12.2008 considering the 13 days rain
period and the delay caused by the defendant. As the export potential of
the defendant dropped in July 2008, the defendant wanted to wriggle out of
the contract. All of a sudden, before the deadline, the defendant terminated
Ex-P.2 – Lease Deed which is illegal and arbitrary. The plaintiff spent
about 3.75 Crores on the construction. The rent agreed per month was
Rs.9,73,200/-. The plaintiff would have realized rent up to
Rs.8,31,69,504/- for the six-year lock-in period. However, the plaintiff
claimed the rents payable by the defendant only for three years namely,
from 30.12.2008 to 29.12.2011 while reserving their right to claim rent for
the rest of the lock-in period. The Hon’ble Single Judge awarded only base
rent for three years to a tune of Rs. 1,44,14,080/- along with interest at the
rate of 12% per annum from 29.10.2008 till the date of realization. He
19/42 https://www.mhc.tn.gov.in/judis
OSA (CAD) NOS.150 AND 154 OF 2021
would further argue that the Hon’ble Single Judge dismissed the counter-
claim of the defendant for refund of the advance amount after considering
the fact that the plaintiff incurred huge expenditure on construction. There
is no warrant to interfere with the same. Accordingly, he prayed to dismiss
the appeals.
10. Points for determination
10.1.This Court has carefully considered the rival submissions
and the evidence on record. The following points arise for determination.
1)Whether the delay in construction is attributable to the plaintiff or
the defendant?
2)Whether the termination of Ex-P.2 - Lease Deed by the defendant
vide letter dated 29.10.2008 valid in the eyes of law?
3)Whether the plaintiff is entitled to the base rent?
20/42 https://www.mhc.tn.gov.in/judis
OSA (CAD) NOS.150 AND 154 OF 2021
4)Whether the defendant is entitled to the counter-claim?
5)Is there any warrant to interfere with the Judgement and Decree
dated 19.02.2021 of the Hon’ble Single Judge?
11. Decision and Discussion
11.1.At this juncture, this Court deems fit to state that, the
defendant sent Ex-D.7 - Notice dated 29.10.2008 terminating the Lease
Deed between the parties and therefore, the cause of action arose on
29.10.2008. The plaintiff presented the plaint before this Court on
28.10.2011, which is well within the period of limitation. Further, the
plaintiff filed Ex-P.1 – Acknowledgement of Registration of Firm dated
02.03.2005 issued by the Registrar of Firms, Chennai (Central) which
shows that the plaintiff firm is duly registered under the Indian Partnership
Act, 1932. Notably, the partnership deed also forms part of Ex-P.1. Thus,
the plaintiff firm is a registered firm. Furthermore, in Ex-P.1, partners of
21/42 https://www.mhc.tn.gov.in/judis
OSA (CAD) NOS.150 AND 154 OF 2021
the plaintiff firm have authorized Mr. R. Parthiban, Managing Partner, to
execute lease deeds and other documents on behalf of the firm. This Court
perused the Original Plaint and noticed that the plaint has been duly
verified by the said Mr. R. Parthiban. Therefore, the suit is maintainable.
The appellant has not agitated the decision of the Hon’ble Single Judge
pertaining to Issue Nos.1,2 and 3 of the Civil Suit in this Appeal.
Therefore, this Court upholds the findings of the Hon’ble Single Judge in
respect of Issue Nos.1,2 and 3 therein.
12. Point Nos.1 and 2
12.1.As per Ex-P.2 - Lease Deed dated 29.11.2007, the
plaintiff as lessor had to construct an industrial area with approximately
30,000 sq.ft of factory space and 7,000 sq.ft of office space on 51,200 sq.ft
of land and hand it over to the defendant as lessee within six months from
the date of execution of the lease deed i.e., by 28.05.2008. Relevant clause
thereof (Clause D) reads thus.
22/42 https://www.mhc.tn.gov.in/judis
OSA (CAD) NOS.150 AND 154 OF 2021
“D.The LESSOR understands that the payment of rent
and other outgoings by the LESSEE shall be subject to the
LESSOR putting the LESSEE into exclusive possession of the
factory building, within a period of six (6) months from the date
of execution of this Lease Deed (except as may otherwise be
provided for herein);”
12.2.However, in Ex-P.12 / Ex-D.4 both parties have agreed
in writing that the date of commencement of construction shall be
01.04.2008 and both parties have also signed therein. Relevant portion of
Ex-P.12 / Ex-D.4 is reproduced hereunder :
23/42 https://www.mhc.tn.gov.in/judis
OSA (CAD) NOS.150 AND 154 OF 2021
24/42 https://www.mhc.tn.gov.in/judis
OSA (CAD) NOS.150 AND 154 OF 2021
12.3.In view of Clause 8.4 and 8.5 alluded to infra, Ex-P.2-
Lease Deed can be modified by any changes agreed upon in writing and
signed by both parties. Thus, the date of commencement of construction in
Ex-P.2 – Lease Deed was modified to 01.04.2008 vide Ex-P.12 / Ex-D.4
by both parties. This is not a case of novation as pleaded by the plaintiff as
there is no new contract involving the parties. Notably, the plaintiff's
counsel did not press on the plea of novation in this appeal. For reference,
Clause 8.4 and 8.5 of Ex-P.2 is extracted hereunder :
“8. Miscellaneous:
8.1. . . .
8.2. . . .
8.4 No amendment or modification of this agreement is
to be valid or binding on any party unless it is made in writing,
refers expressly to this agreement and is signed by or on behalf
of all parties
8.5. Any notice or other communication given or made
in accordance with this agreement must be -
a. in writing, may, in addition to any other effective
mode of service, be sent by registered or recorded delivery post,
b. and must be addressed to the and served on the Parties at
25/42 https://www.mhc.tn.gov.in/judis
OSA (CAD) NOS.150 AND 154 OF 2021
their addresses shown on the first page of this agreement or any
other address that each may notify the other from time to time in
writing as being its address for service for the purposes of this
agreement.”
13.This Court deems fit to extract Clause 5 of Ex-P.2-Lease
Deed for ready reference :
“Clause 5
“5.TENURE & TERMINATION OF LEASE DEED:
5.1.The Term of the Lease Deed shall be six (6) years
commencing on the Rent Commencement Date (the “Lock in
Period). The LESSEE shall have the option to renew the Lease
Deed for one (1) additional three (3) years period upon the
terms and conditions set forth herein and upon mutual
agreement of the rental payments for such additional three (3)
years period (the “Renewal Period”).
5.2.The LESSOR agrees to complete construction of the
Premises and satisfy the conditions of item 4.2(a) and (b) hereof
within six (6) months from the date of execution of this Lease
Deed (the Outside Completion Date”). Notwithstanding
anything to the contrary contained herein, if the LESSOR does
not deliver the Industrial Building in accordance with the
specifications set forth herein (as may be modified upon mutual
26/42 https://www.mhc.tn.gov.in/judis
OSA (CAD) NOS.150 AND 154 OF 2021
agreement between the LESSOR and the LESSEE) and the
LESSOR has not obtained the unconditional and unqualified
plan sanction approval permitting the occupation and use of the
Premises for undertaking the industrial activity by the LESSEE,
with twelve (12) months from the date of execution of the Lease
Deed, the LESSEE shall have the option to terminate the Lease
Deed and the Token Advance and any Security Deposits
(together with any interest accrued thereon) shall be
immediately returned to the LESSEE together with all interest
accrued thereon. Additionally, the LESSOR shall reimburse the
LESSEE for all amounts paid by the LESSEE with respect to (i)
Stamp Duty paid by LESSEE in connection with this Lease
Deed. (ii) all fees incurred by LESSEE in connection with
LESSEE'S environmental due diligence conducted at the Lease
Deed Premises and (iii) all fees incurred by LESSEE in
connection with LESSEE'S title search conducted for the Lease
Deed Premises.
5.3.LESSEE's Right to terminate: The LESSEE's has the
right to terminate this Lease Deed, without being imposed with
any penalty, for any of the following grounds:
a.The Rent Commencement Date not becoming effective;
b.The LESSOR not delivering the Premises to the
LESSEE free, clear, unencumbered with for its use and
27/42 https://www.mhc.tn.gov.in/judis
OSA (CAD) NOS.150 AND 154 OF 2021
occupation by the LESSEE within twelve (12) months of the date
the Lease Deed is executed by the Parties;
c.The LESSOR not delivering the Premise to the
LESSEE arising out of non-receipt of approval of the plan
sanction papers or rejection of the plan sanction papers within
twelve (12) months o the date the Lease Deed is executed by the
Parties;
5.4. In the event of termination of the Lease Deed by the
LESSEE for any or all of the reasons as set forth herein, the
LESSOR shall immediately upon receipt of the written notice
from the LESSEE notifying the termination of the Lease Deed,
return to the LESSEE all monies paid by the LESSEE whether
as by way of Token Advance, Security Deposits or by whatever
name called without any deductions whatsoever (unless
otherwise specifically set forth herein) “
No need to offer explanation for the above extract as it’s self-explanatory.
14.Perusal of Ex-P.12 / Ex-D.4 further reveals that both
parties were uncertain about various aspects and specifications of the
construction. The plaintiff has pleaded that this being a large-scale built-to-
28/42 https://www.mhc.tn.gov.in/judis
OSA (CAD) NOS.150 AND 154 OF 2021
suit arrangement, the construction progressed under the regular supervision
of the defendant and their representatives, who frequently kept changing
their requirements; that the defendant company was dependent on a French
Multinational Company and the construction had to be done according to
the needs of the foreign company; that, therefore, drawings and
specifications kept changing; that this led to delay in construction; and that
the defendant is trying to wriggle out of the contract due to a drop in the
defendant’s export potential. This is further supported by letters to the
defendant on various dates. Further, P.W.1 has deposed about the frequent
changes demanded by the defendant. On the other hand, though the
defendant in its written statement denied that the commencement date of
construction was agreed to be 01.04.2008, they admitted the same at the
time of trial. As stated supra, both parties have signed in Ex-P.12 / Ex-D.4.
The written statement of the defendant, excluding the counter-claim, is
nothing more than an evasive denial of the plaint averments. The
defendant side has not examined any of their people directly connected
29/42 https://www.mhc.tn.gov.in/judis
OSA (CAD) NOS.150 AND 154 OF 2021
with the Ex-P.2 - Lease Deed. As a matter of fact, D.W.1 has himself
admitted that he is deposing only based on records and that he joined the
defendant company only in November, 2012. Further, he has deposed that
he did not receive any oral instruction from the persons directly connected
with Ex-P.2 - Lease Deed. The defendant has not produced anything to
show that it was ready and willing to perform its part of the contract. In
essence, the plaintiff has pleaded and proved that the shift in the date of
commencement from 29.11.2007 to 01.04.2008 is due to the delay on the
side of the defendant.
15.Then, the defendant sent a letter dated 02.08.2008 (Ex-P.4 /
Ex-D.5) to the plaintiff wherein they stated that they had provided the
plaintiff with all the necessary drawings duly signed for the purpose of
construction of the office and factory buildings to be undertaken by the
plaintiff. Further stated that the construction has already commenced from
01.04.2008 and that the plaintiff has to complete the construction by
30/42 https://www.mhc.tn.gov.in/judis
OSA (CAD) NOS.150 AND 154 OF 2021
30.09.2008. The plaintiff has replied to the same vide letter dated
07.08.2008 (Ex-P.3) wherein he has stated that the defendant instructed the
plaintiff to stop the construction work until further notice in a meeting held
on 02.07.2008; that toilet locations are yet to be confirmed; that 13 days
delay due to rain had to be adjusted as per the terms; and that the period
for which the work was stopped on defendant’s instruction should be
adjusted with the deadline for construction. Notably, in view of Clause 4.3,
for each day of delay caused by any natural disturbance, the Outside
Completion Date shall be extended by one day. Consequently, to resolve
the issues, a meeting was held on 26.08.2008. In Ex-P.5 – minutes of the
said meeting, interalia it is stated that the deadline was extended till
30.12.2008 and the plaintiff was to provide the facility for fit-outs by
15.11.2008. Notably, the defendant had signed in Ex-P.5 – minutes of the
said meeting, but, the plaintiff had refused to sign therein. The plaintiff,
though denied the other contents of Ex-P.5, has admitted in his evidence
that in the said meeting, both parties agreed to the extension of the
31/42 https://www.mhc.tn.gov.in/judis
OSA (CAD) NOS.150 AND 154 OF 2021
deadline till 30.12.2008 keeping in mind the delay caused on the side of
the defendant and also the delay on account of rainfall. The defendant does
not dispute the contents of Ex-P.5 and the same is prepared by their
company and duly signed by their Managing Director - Mr.Chetan Desai.
Ex-P.5 states that the extension of deadline till 30.12.2008 is owing to the
two months of stalled construction and on account of rainfall. This would
show that both parties have orally agreed to the extension of time for
performance of contract, but, one of the party i.e., the plaintiff has not
signed the minutes of the meeting for certain apprehensions.
15.1.The learned counsel for the plaintiff cited the Judgement
of the Hon’ble Supreme Court in Keshavlal Lallubhai Patel and Ors. Vs.
Lalbhai Trikumlal Mills Ltd., reported in AIR 1958 SUPREME COURT
512 to support his argument that oral agreements on extension of time for
performance of contract are valid. However, the same is not applicable to
the case on hand as Clause 8.4 of Ex-P.2 provides that such modifications
32/42 https://www.mhc.tn.gov.in/judis
OSA (CAD) NOS.150 AND 154 OF 2021
can be effected only in writing duly signed by both parties. The underlying
principle therein would not be applicable when there is an express
agreement to the contrary. Since the oral agreement on extension of time
for performance is not reduced into writing and duly signed by both
parties, it does not modify or alter Ex-P.2 in view of Clause 8.4 and 8.5
alluded to supra.
15.2.However, the oral agreement coupled with Ex-P.3 and
Ex-P.5 would show that the 2 months stall in construction is attributable
primarily to the defendant. In Ex-P.3, the plaintiff claims that the
defendant instructed the plaintiff to stop the construction work until further
notice in a meeting held on 02.07.2008. The defendant has not disputed the
same.
16.According to the defendant, vide Ex-D.6, they sent an
e-mail to the architect of the plaintiff pointing out the corrections in the
existing drawings and requesting to rectify the same, despite which, the
33/42 https://www.mhc.tn.gov.in/judis
OSA (CAD) NOS.150 AND 154 OF 2021
plaintiff did not fulfil their part of the contract. The learned senior counsel
for the appellant / defendant has submitted that the e-mail is a document as
per Section 3 of the Evidence Act, 1872; that D.W.1 who is the Finance
Controller of the defendant firm, in his chief examination by way of
affidavit has complied with the substantial requirement of Section 65B of
the Evidence Act; and that, therefore, Ex-D.6 would be admissible in law.
16.1.In support of the above argument, he relied on Super
Cassettes Industries Ltd. Vs. Shreya Broadcasting Pvt. Ltd., reported in
2019 SCC Online Del 7314. Essential facts of the case are: The plaintiff
therein is a copy right holder for various literary, music and other works. In
random monitoring, the plaintiff therein came to know that the defendant
therein has been broadcasting plaintiff therein’s copyright work without
their permission / licence. P.W.2 recorded the programmes wherein
copyrighted work of the plaintiff therein were broadcasted. In the pursuant
Suit, P.W.2 marked the CDs / DVDs containing those recordings. The
34/42 https://www.mhc.tn.gov.in/judis
OSA (CAD) NOS.150 AND 154 OF 2021
defendant therein raised objection that 65B Certificate has not been
produced and hence, the same is inadmissible in view of Anwar P.V. Vs.
P.K. Basheer, reported in (2014) 10 SCC 473. The Hon’ble Delhi High
Court rejected the objection of the defendant therein by observing that the
affidavit of P.W.2 satisfies the requirement laid down under Section 65B of
the Indian Evidence Act and also the law laid in Anvar P.V’s case (supra).
16.2.Notably, the Hon’ble Supreme Court in Arjun Panditrao
Khotkar v. Kailash Kushanrao Gorantyal., reported in (2020) 7 SCC 1
has held that certificate under sub-section (4) of section 65B is mandatory
and a condition precedent to admit any electronic record as secondary
evidence. There is no prescribed form for a certificate under Section 65B.
In this case, Ex-D.6 was produced by D.W.1 on the date of filing his chief
affidavit. D.W.1 qua Financial Controller of the defendant company qua a
responsible official with authorization to use the relevant devices/network,
has duly complied with all the substantial requirements of a certificate
35/42 https://www.mhc.tn.gov.in/judis
OSA (CAD) NOS.150 AND 154 OF 2021
under Section 65B in his chief affidavit. Therefore, keeping in mind the
aforementioned case laws, this Court is of the view that Ex-D.6 is
admissible as per law. No doubt that mere admission of a document does
not amount to proof. In this case, D.W.1 was not working with the
defendant at the time of sending of the alleged e-mail. Further, neither the
sender nor the recipients of the email were examined. Further, there is no
sufficient proof that the said e-mail was actually sent to and received by
the recipients. Therefore, this Court is of the considered view that, Ex-D.6
is not proved by the defendant. Even assuming that Ex-D.6 is proved,
Clause 8.5 alluded to supra requires any communication to be in writing
and sent via post in addition to any other mode of communication.
Consequently, the defendant fails in its pursuit to establish that the plaintiff
has not performed his part of contract by not producing the drawings and
plan duly approved and that the delay is caused by the plaintiff.
36/42 https://www.mhc.tn.gov.in/judis
OSA (CAD) NOS.150 AND 154 OF 2021
17.In essence, the plaintiff has proved that the initial delay of
6 months in commencement of construction and the subsequent delay of 2
months is primarily attributable to the defendant. The defendant has failed
to prove that there was delay on part of the plaintiff. In such
circumstances, the defendant terminating Ex-P.2-Lease Deed vide letter
dated 29.10.2008 exercising Clause No.5.2 and Clause No.8 (supra)
claiming that the plaintiff failed to hand over the industrial area is not
justifiable as the delay is primarily attributable to them. Therefore, the
same is invalid. Point Nos.1 and 2 are answered accordingly in favour
of the plaintiff and against the defendant.
Point Nos. 3, 4 and 5
18.The plaintiff never handed over possession of the property
to the defendant as per the terms and requirements of Ex-P.2 – Lease Deed.
D.W.1 in his cross-examination has deposed that the construction was
almost over as on 30.09.2008. The Plaintiff has pleaded that it received
37/42 https://www.mhc.tn.gov.in/judis
OSA (CAD) NOS.150 AND 154 OF 2021
Rs.1,03,75,008/- from the defendant under Ex-P.2 as an advance. To the
contrary, the defendant has mentioned in its counter-claim that
Rs.1,17,02,840/- was given to the plaintiff as advance. Notably, the
plaintiff has not disputed the same. Further, plaintiff has pleaded that they
incurred Rs.3.75 Crores on Construction. However, they have not
substantiated the same. In such circumstances, this Court is of the view
that, the plaintiff carried out the construction out of the advance money
paid by the defendant only. In view of the decision in Point Nos.1 and 2,
the defendant is not entitled to refund of the advance money of
Rs.1,17,02,840/-. The plaintiff is entitled to retain the same as
compensation towards the construction cost incurred by it.
19.Further, the plaintiff has not adduced any evidence to show
that the building was idle and could not be rented out after the
construction. Now that the plaintiff is enriched with the superstructure
constructed on their land out of the advance money given by the defendant,
38/42 https://www.mhc.tn.gov.in/judis
OSA (CAD) NOS.150 AND 154 OF 2021
granting it base rent would amount to enriching it at the cost of the
defendant in an unjust manner, which is not permissible under law.
Therefore, this Court decides that the plaintiff is entitled to retain the
advance money of Rs.1,17,02,840/- as compensation, however, is not
entitled to base rent. Point No.3 is answered accordingly in favour of the
defendant and against the plaintiff. Point No.4 is answered
accordingly in favour of the plaintiff and against the defendant. The
Hon’ble Single Judge is not justified in awarding base rent. Therefore, the
Judgement and Decree dated 19.02.2021 is liable to be interfered to the
aforementioned extent. Point No.5 is answered accordinngly.
20.Resultantly,
(i)OSA (CAD) No.154 of 2021 is partly allowed without costs
in the following manner :
39/42 https://www.mhc.tn.gov.in/judis
OSA (CAD) NOS.150 AND 154 OF 2021
(a)The Judgement and Decree dated 19.02.2021 of the Hon’ble
Single Judge to the extent that the plaintiff is entitled to a
declaration that the termination of the Lease by the defendant vide
letter dated 29.10.2008 is illegal, is confirmed.
(b)The Judgement and Decree dated 19.02.2021of the Hon’ble
Single Judge to the extent of awarding the plaintiff with base rent
for a sum of Rs.1,40,14,080/- together with interest at the rate of
12% per annum from 29.10.2008 till the date of realization, is set
aside.
(c)The defendant is not entitled to claim the advance money of
Rs.1,17,02,840/- from the plaintiff.
(d)The plaintiff's entitlement to the cost of the Civil Suit is
retained.
40/42 https://www.mhc.tn.gov.in/judis
OSA (CAD) NOS.150 AND 154 OF 2021
(ii)OSA (CAD) No.150 of 2021 is dismissed. No costs.
Consequently, connected Miscellaneous Petitions are closed.
[R.SUBRAMANIAN, J.] [R.SAKTHIVEL, J.]
14 / 03 / 2024
Index : Yes
Internet : Yes
Neutral Citation: Yes
Speaking Order
TK
41/42 https://www.mhc.tn.gov.in/judis
OSA (CAD) NOS.150 AND 154 OF 2021
R.SUBRAMANIAN, J.
AND
R.SAKTHIVEL, J.
TK
PRE-DELIVERY JUDGMENT MADE IN
OSA (CAD) NOS.150 AND 154 OF 2021
14 / 03 / 2024
42/42 https://www.mhc.tn.gov.in/judis
Legal Notes
Add a Note....