As per case facts, the petitioner, a proprietor of "URJA INFRA," was awarded a contract for road construction. During the work, heavy rains and sudden water release from DVC caused ...
IN THE HIGH COURT AT CALCUTTA
(Constitutional Writ Jurisdiction)
APPELLATE SIDE
Present:
The Hon’ble Justice Krishna Rao
W.P.A. No. 17733 of 2025
Amal Biswas
Vs.
The State of West Bengal & Ors.
Mr. Anirban Ray, Sr. Adv.
Mr. Anujit Mukherjee
Mr. Sourav Chatterjee
Mr. Subham Saha
....For the petitioner.
Mr. Partha Chakraborty
Mr. Arghya Chatterjee
….For the State.
Hearing Concluded On : 19.06.2026
Judgment Delivered On : 10.07.2026
Judgment Uploaded On : 10.07.2026
2
Krishna Rao, J.:
1. The petitioner has filed the present writ petition challenging the order
of termination of the contract of the petitioner being Memo No. 1515
dated 28
th July, 2025. The petitioner is the sole proprietor of “URJA
INFRA”. The respondent no.5 published a tender for “Kotalpara
Kshusiganj Road from 0.00 Kmp to 7.90 Kmp - River side embankment
protection and strengthening work – under Hooghly Construction
Division in District of Hooghly during the year 2022-2023”. The
petitioner has participated in the said tender process. The bid of the
petitioner was duly accepted by the respondent no.2 and on 28
th
February, 2024, a Letter of Acceptance was issued to the petitioner.
2. During the commencement of the work, in the month of August 2024,
the heavy rain caused flood resulting into stagnation of water at the
work place. The respondent no.6 by a letter dated 3
rd September, 2024,
called upon the petitioner to rectify damages caused due to heavy rain
and stagnation of water. The petitioner started repair of damaged work
and was communicated to the respondent no. 6 by a letter dated 5
th
September, 2024.
3. By a letter dated 10
th
September, 2024, the respondent no.4 requested
one M. Amarnatha Reddy, Professor at IIT Kharagpur to conduct a
technical audit of the work being undertaken by the petitioner. On 18
th
September, 2024, the locale faced floods not only due to heavy rain but
primarily due to sudden release of water by Damodar Valley
3
Corporation (hereinafter referred to as “DVC”), thereby causing
devastating damages to the road constructed by the petitioner. The
State has taken the decision for release of water by the DVC and no
prior intimation was given to the petitioner. The loss and damage to the
construction undertaken by the petitioner was such that it was not
possible to the petitioner to repair or re-execute the work. The
petitioner by a letter dated 27
th
September, 2024, informed the
respondent no.6 of such situation along with photographs showing the
water stagnation causing damage to the road. The petitioner submitted
bills claiming for excess payment in nature of compensation towards
damages incurred.
4. The Chief Engineer & Director, Road and Building Research Institute,
PW (Roads) Directorate forwarded the test report of the DBM to the
respondent no.6 on 3
rd October, 2024, recording that “Test Result is
within acceptable limit”. On 6
th November, 2024, a meeting was held at
the work site in presence of the respondent no.6 wherein it was assured
the payments against the work done by the petitioner would be
considered and released but no payment was released. The petitioner
has sent a letter dated 19
th
November, 2024, requesting for release of
payment and for extension of time to complete work subject to payment
of bills. The respondents have neither release payment nor extended
the time to complete the work, the petitioner has sent a legal notice to
the respondents on 3
rd
December, 2024.
4
5. Mr. Anirban Ray, Learned Senior Advocate representing the petitioner
submits that on 9
th December, 2024, the respondent no.6 issued a
Memorandum directing the petitioner to rectify the damages to the
constructed road by granting suo moto extension of time till 28
th
February, 2025. The petitioner by a letter dated 18
th December, 2024,
informed the respondents that the damages were caused due to the
natural calamity and thus the petitioner is not liable for the same. By a
communication dated 30
th
December, 2024, the respondent no.6
rejected the claim of the petitioner for compensation. By a letter dated
3
rd
January, 2025, the respondent no.6 informed to the petitioner that
their proposal for constructing paver block was not acceptable and
directed the petitioner to complete repair work as outlined in the
communication dated 16
th December, 2024.
6. Mr. Ray submits that a meeting was held on 27
th January, 2025, in
presence of the officials of the respondents and the petitioner, wherein
the respondent authorities have admitted to the loss and damage to the
road due to heavy rain and flood. E-file had been initiated for obtaining
necessary concurrence for foreclosure of the existing contract with no
defect liability period in terms of the tender agreement. It is also
recorded that the petitioner has executed the work as per specifications
and outstanding amount would be released at the earliest subject to
certain formal measurements.
7. Mr. Ray submits that the respondent no.6 with the utter disregard to
the decision dated 27
th January, 2025, issued a letter on 2
nd June,
5
2025, by extending the time for completion of work till 6
th September,
2025. Thereafter, by a letter dated 3
rd June, 2025, the petitioner
informed the respondents that the extension granted by the
respondents is defective as the extension was granted only after three
months from the date of expiry of the last extension and without taking
into consideration the Minutes of Meeting dated 27
th January, 2025,
which is binding upon both the parties.
8. On 13
th
June, 2025, the respondent no.6 issued a show cause notice to
the petitioner and the petitioner has submitted reply to the show cause
notice on 18
th
June, 2025. On 2
nd
July, 2025, the respondent no.6
imposed penalty upon the petitioner in terms of Clause 2 of the
agreement. On 8
th July, 2025, the petitioner has submitted reply to the
penalty imposed upon the petitioner and requested the respondents to
withdraw the penalty. The petitioner only to settle the issue informed to
the respondents that the proposed commencement of work for
rectification will be done subject to schedule of rates being reasonably
assessed at the current rate. Without considering the Minutes of the
Meeting and the proposal made by the petitioner, the respondents have
issued show cause notice to the petitioner on 11
th
July, 2025 and the
petitioner has submitted reply to the said show cause notice on 21
st
July, 2025, intimating all the facts.
9. Being aggrieved with the act of the respondent authorities, the
petitioner has preferred a writ petition before this Court being WPA No.
16831 of 2025 and on receipt of the copy of the writ petition, the
6
respondent no.6 has issued memo dated 28
th July, 2025 and
terminated and rescinded the contract and also issued notice to the
petitioner for forfeiture of Earnest Money Deposit and Security Deposit.
10. Mr. Ray submits that on the same day, the petitioner has received a
letter from the respondent no.5, who is a higher authority than the
respondent no.6 informing the petitioner that if the petitioner resumes
and completes the work, the penalty imposed under Clause 2 may be
considered. He submits that the letter issued by the respondent no.6 is
completely contrary to the letter issued by the respondent no.5. The
petitioner also received a memo dated 28
th
July, 2025, issued by the
respondent no.5 to the respondent no.6 permitting the respondent no.6
to take action for termination of the contract.
11. Mr. Ray has relied upon the judgement in the case of Subodh Kumar
Singh Rathore Vs. Chief Executive Officer and Others reported in
(2024) 15 SCC 461 and submits that it is the duty of the courts to
interfere in contractual matters that have fallen prey to an arbitrary
action of the authorities in the guise of technical faults, policy change
or public interest, etc.
12. Mr. Ray has further relied upon the judgment in the case of Unitech
Limited and Others Vs. Telangana State Industrial Infrastructure
Corporation (TSIIC) and Others reported in (2021) 16 SCC 35 and
submits that the jurisdiction under Article 226 is a valuable
7
constitutional safeguard against an arbitrary exercise of State power or
a misuse of authority.
13. Mr. Ray has further relied upon the judgement in the case of Kailash
Nath Associates Vs. Delhi Development Authority and Anr.
reported in (2015) 4 SCC 136 and submits that the principle of law is
that where, by agreement, time is made of the essence of the contract,
it cannot be waived by a unilateral act of a party and unless there is a
consensus ad idem between the parties and a new date is agreed to,
merely because a party to a contract agrees to consider time being
extended for the opposite party to complete the contract, but ultimately
refuses to accord concurrence would not mean that the party has by
conduct waived the date originally agreed as being of the essence of the
contract.
14. Mr. Partha Chakraborty, Learned Advocate representing the
respondents submits that due to non-continuance with the
construction work of the road by the petitioner includes the
maintenance thereof, the road has been severely damaged and general
public of the said area submitted a mass representation to the
respondent authorities with the request for urgent repair of the
damaged road. On receipt of mass representation, the respondent
authorities requested the petitioner for taking necessary steps for
urgent repair of the said road. He submits that the authorities have
also issued reminders to the petitioner for repair of the road but the
petitioner failed to do so.
8
15. Mr. Chakraborty submits that by a letter dated 5
th September, 2024,
the petitioner informed the respondents that the petitioner has already
started taking steps for repair of the damaged road with the
consultation with the Assistant Engineer and as per the direction of the
respondent authorities. He submits that inspite of communication, the
petitioner failed to repair the damaged road. Thus, the respondents
have no other alternative but to issue show cause notices to the
petitioner for completion of the work. He submits that even after receipt
of show cause notice, the petitioner failed to take any steps for
repairing of the road and proper work for concerned river side
embankment protection and strengthening of the road.
16. Mr. Chakraborty submits that being dissatisfied with the act of the
petitioner for not commencing the work inspite of several reminders
followed by the show cause notices, the respondents have issued show
cause notices under Clause-II of the tender condition and non-
compliance of the show cause notice by the petitioner, the respondents
have issued notice under Clause-III of the tender conditions.
17. Mr. Chakraborty submits that as the petitioner failed to repair the road
inspite of several opportunities, accordingly tender of the petitioner was
terminated. The respondents taking into consideration of the
betterment of livelihood of the people at large of the said area, the road
needed to be restored in an useable condition and for that purpose the
respondents have already floated fresh tender.
9
18. On 28
th February, 2024, Letter of Acceptance–cum–Work Order was
issued to the petitioner for construction of Kotalpara Kshusiganj Road
from 0.00 Kmp to 7.90 Kmp – River side Embankment Protection and
strengthening work - under the Hooghly Construction Division in
District of Hooghly during the year 2022-2023. The time for completion
of the said work was 9 months. The petitioner has commenced the work
as per work order. During execution of work, due to heavy rain and
stagnation of water in the month of August, 2024 and September,
2024, the work undertaken by the petitioner caused grave damages. As
the contract work period of the petitioner was in existence, the
respondents have directed the petitioner to rectify the damages and the
petitioner commenced repair of the damaged work.
19. In the meantime on 18
th September, 2024, the locale faced floods not
only due to rain but primarily due to sudden release of Water by the
Damodar Valley Corporation due to which the road constructed by the
petitioner also got damaged.
20. The respondents have obtained technical audit report from Mr. M.
Amarnatha Reddy, Professor of IIT, Kharagpur and on 3
rd
October,
2024, a report on the conducting test of Bitumen Content of DBM,
Gradation of DBM, in connection with the work for construction of
Kotalpara Khusiganj Road from 0.00 Kmp to 7.90 Kmp – Riverside
Embankment Protection and Strengthening work, under the Hooghly
Construction Division in the District of Hooghly during the year 2023-
2024 is submitted wherein the “Test result is within acceptable limit as
10
per TABLE 500-13 OF MORTH” . From the report, it is clear that the road
constructed by the petitioner with respect to the contract awarded to
him is in accordance with the specifications and there are no fault of
the petitioner for use of any degrades materials.
21. On 19
th November, 2024, the petitioner made a request to the
respondent authorities for release of payment and for extension of time
as the time for completion of work was going to be expired on 29
th
November, 2024. On 9
th
December, 2024, the respondent no.6 directed
the petitioner to rectify the damages and granted extension till 28
th
February, 2024. On 27
th
January, 2025, a meeting was held in
presence of the respondent authorities and the same was recorded in
the Minutes of Meting which reads as follows:
“Minutes of Meeting held on 27/01/2025 at 12:00 PM
in the office of the Engineer-in Chief & Ex-officio
Secretary, Public Works Department 8
th Floor,
Nabanna, Howrah on present condition of
Kotalpara Khusigang Road from 0.00 Kmp to 7.90
Kmp – River Side Embankment and strengthening work
The meeting has been presided over by the
Engineer-in-Chief, PWD. The list of officers and
members present is separately enclosed.
Name of Work - Kotalpara Khusiganj Road from
0.00 Kmp to 7.90 Kmp – River Side Embankment
Protection and Strengthening work
Tender No :- 33/Hooghly Construction
Division/SEWC-II/PWD of 2023-24
Administrative Approval No:- GO2324011172PD
dated 06-12-2023 (CP – 1 to 3)
Administrative Approval Amount:-
Rs248039931.00
11
Estimated Amount put to Tender:-
Rs233070148.00
Tendered Amount:- Rs256260628.00
Contractual Rate:- 9/95% Above
Work Order No.: 371 dated 28.02.2024 of the
Superintending Engineer, Western Circle No-II. PWD
(CP 4 to 5)
Date of Commencement:- 29/02/2024
Schedule of completion:- 29/11/2024
Name of Agency:- URJA INFRA, Khidirpur, Post
Office Chhabaghati, District Murshidabad, Pin
742201, West Bengal
Brief History of the work:-
The Assistant Engineer, Hooghly Construction,
Sub-Division – II, PWD, who was present from the
beginning of the project work, has informed that the
entrusted agency completed the following works
before the monsoon:-
Upto to 75 mm Dense Bituminous Macadam
– I (DBM-I) layer from Chainage 0.000 km to
5.360 km, 5.500 Km to 6.620 Km and Ch.
7.290 Km to 7.900 km
Up to Wet Mix Macadam (WMM) from
Chainage 5.360 km to 5.500 km and 6.620
km to 7.290 km
Assistant Engineer has also stated that the
different layers of the road crust were executed as
per the work specifications.
High rainfall and discharge in the Damodar
River led to flood-like situations in the first week of
August 2024. Water levels rose to 500-800 mm
below the road crust in many stretches, causing
depressions. The executed DBM layer from 3.570
Km to 4.270 Km was totally damaged thereafter.
The Chief Engineer, West Zone, PWD has sent a
proposal for Technical Audit to the Professor
12
Amarnath Reddy, IIT Kharagpore on 10/09/2024,
Again devastating flood was occurred in between
September 17-22, 2024. Floodwaters from the
Damodar River, situated on the left side of the
road, suddenly overflowed and inundated the road
in certain stretches. As a result, seepage through
embankments caused settlements and depressions
at hard crust levels and pavement surfaces.
Embankment settlements occurred at various
locations due to piping action. Professor Amarnath
Reddy, IIT Kharagpur, visited the site on 18
October 2024, Professor Amarnath Reddy, IIT
Kharagpur, has submitted a scope of work on
05/12/2024 for evaluation of on-going road
construction which is under consideration of the
department,
The quality of the executed work is currently
under review by the Road and Building Research
Institute.
Present Condition :-
The road has been severely damaged due to
flooding and the subsequent passage of a large
number of heavily loaded commercial vehicles over
the damaged road. Approximately 1.5 Km of the
road remain in good condition, while the remaining
portion is in a dilapidated state. Public agitation is
escalating daily.
View of Agency :-
The agency, URJA INFRA, has been directed to
rectify the work; however, they have stated that it
would be very difficult for them to undertake such
repair work.
Decision :-
An E file has been initiated for obtaining
necessary concurrence for fore closer of the existing
contract with no Defect Liability Period (DLP) under
Clause 3B of the tender agreement 2911(ii) vide
File No. PWD-25/8/2025-DIR(PWD)-Dept. of PWD
(Computer No. 1110493). According to the report
from the working wing, the work completed so far
has been executed in accordance with the work
specifications, and measurements have been
recorded in the Measurement Book (MB). Payment
has also been made, except for the full rate of
13
Dense Bituminous Macadam (DBM) and payment
for a certain quantity of earthwork carried out,
which are pending due to post- level measurement
and subsequent calculations.
However, the Road and Building Research
Institute will cross-check the work and submit a
report at the earliest.
The concerned Executive Engineer has been
directed to make necessary preparation for the
immediate repair of the road by inviting a fresh
Notice Inviting e-Tender (NIeT) under the Non-Plan
Head, subsequent to the decision to close the
present tender.”
22. As per the said Minutes of Meeting, the respondents have already
moved proposal for foreclosure of the existing contract with no defect
liabilities and for inviting a fresh Notice Inviting e-Tender. The
respondent authorities after the period of five moths from the decision
taken in the meeting issued a notice to the petitioner on 2
nd June,
2025, by suo moto extension of time up to 6
th September, 2025, for
immediate rectification of work executed by the petitioner.
23. Now the question whether after taking a decision for foreclosure of the
work awarded to the petitioner and initiation of fresh tender, the
respondents can suo moto extend the time for rectification of the work
executed by the petitioner.
24. Before the meeting held on 27
th
January, 2025, the Chief Engineer (HQ)
by a letter dated 24
th
January, 2025, requested the Chief Engineer and
Director, Road and Building Research Institute to carry out thorough
inspection of the work and requested to submit report. On 3
rd
April,
14
2025, the Research Officer and the Chief Engineer, Road and Building
Research Institute submitted report wherein it is concluded that
“Distress noticed during inspection may be co-related with prolonged
water stagnation (if any), Slope stability and seepage analysis, which
are beyond the present scope of work of R & BRI”.
25. In the letter dated 2
nd
June, 2025, the respondents have not stated
about the decision taken by the authorities in the meeting held on 27
th
January, 2025. The respondent authorities have filed report as well as
affidavit-in-opposition to the writ petition but the authorities have not
explained with regard to the Minutes of Meeting dated 27
th
January,
2025. In the meeting, the authorities have admitted that the road has
been severely damaged due to flooding and the subsequent passage of a
large number of heavily loaded vehicles over the damaged road. The
experts have also submitted test report wherein it is stated that the test
result is within the acceptable limit as per table 500-13 of MORTH.
26. The respondents have relied upon the mass representation submitted
by the resident of the said area with respect to damage road but the
said mass representation is of the month of August, 2024. In the
meeting dated 27
th
January, 2025, the public agitation is also taken
into consideration.
27. In the case of Kailash Nath Associates (supra) the Hon’ble Supreme
Court held that:
15
“19. The Division Bench followed the
judgment of Tilley v. Thomas. It further went on to
follow Anandram Mangturam v. Bholaram
Tanumal and held :
“32. The decision holds that the principle of
law is that where, by agreement, time is made of
the essence of the contract, it cannot be waived
by a unilateral act of a party and unless there is
consensus ad idem between the parties and a
new date is agreed to, merely because a party to
a contract agrees to consider time being
extended for the opposite party to complete the
contract, but ultimately refuses to accord
concurrence would not mean that the party has
by conduct waived the date originally agreed as
being of the essence of the contract.”
28. It is not the case of the respondent authorities that the Minutes of the
Meeting is not concluded one or the said decision is taken without any
authority or the decision dated 27
th January, 2025, is withdrawn. The
meeting was attended by the following officials:
16
29. If all the competent officials were present and have taken a decision
consciously, thus the authorities after the period of more than five
months without any justification cannot suo moto extend the time for
rectification of the work.
30. The other aspect in the matter is that on 28
th July, 2025, the
respondent no.6 has issued the impugned order of termination of
contract and forfeited the Earnest Money Deposit and Security Deposit,
subsequently the respondent no.5 who is the higher authority informed
the petitioner if the petitioner took up rectification and complete the
work in all aspect, then the penalty which has been imposed may be
considered. Again on the same day, the respondent no. 5 informed the
respondent no. 6 that the respondent no. 6 may take necessary action
in terms of the Clause 3 of 2911 of the agreement. The said
communication reveals that before taking decision by the respondent
no. 5, the respondent no. 6 has issued the impugned order.
31. As regard to the maintainability of the writ petition in the case of
Unitech Limited (supra), the Hon’ble Supreme Court held that:
“39. A two-Judge Bench of this Court in ABL
International Ltd. v. Export Credit Guarantee
Corpn. of India Ltd., analysed a long line of
precedent of this Court to conclude that writs
under Article 226 are maintainable for asserting
contractual rights against the State, or its
instrumentalities, as defined under Article 12 of the
Indian Constitution.
39.1. Speaking through N. Santosh Hegde, J.
the Court held :
17
“27. … the following legal principles
emerge as to the maintainability of a writ
petition:
(a) In an appropriate case, a writ
petition as against a State or an
instrumentality of a State arising out of a
contractual obligation is maintainable.
(b) Merely because some disputed
questions of fact arise for consideration,
same cannot be a ground to refuse to
entertain a writ petition in all cases as a
matter of rule.
(c) A writ petition involving a
consequential relief of monetary claim is
also maintainable.”
This exposition has been followed by this
Court, and has been adopted by the three-Judge
Bench decisions of this Court in State of
U.P. v. Sudhir Kumar and Popatrao Vyankatrao
Patil v. State of Maharashtra.
39.2. The decision in ABL International,
cautions that the plenary power under Article 226
must be used with circumspection when other
remedies have been provided by the contract. But
as a statement of principle, the jurisdiction under
Article 226 is not excluded in contractual matters.
39.3. Article 23.1 of the development
agreement in the present case mandates the
parties to resolve their disputes through an
arbitration. However, the presence of an arbitration
clause within a contract between a State
instrumentality and a private party has not acted
as an absolute bar to availing remedies under
Article 226.
39.4. If the State instrumentality violates its
constitutional mandate under Article 14 to act fairly
and reasonably, relief under the plenary powers of
Article 226 of the Constitution would lie. This
principle was recognised in ABL International.
“28. However, while entertaining an
objection as to the maintainability of a writ
petition under Article 226 of the Constitution of
18
India, the court should bear in mind the fact
that the power to issue prerogative writs
under Article 226 of the Constitution is plenary
in nature and is not limited by any other
provisions of the Constitution. The High Court
having regard to the facts of the case, has a
discretion to entertain or not to entertain a writ
petition. The Court has imposed upon itself
certain restrictions in the exercise of this
power. And this plenary right of the High
Court to issue a prerogative writ will not
normally be exercised by the Court to the
exclusion of other available remedies unless
such action of the State or its instrumentality
is arbitrary and unreasonable so as to violate
the constitutional mandate of Article 14 or for
other valid and legitimate reasons, for which
the Court thinks it necessary to exercise the
said jurisdiction.”
39.5. Therefore, while exercising its
jurisdiction under Article 226, the Court is entitled
to enquire into whether the action of the State or its
instrumentalities is arbitrary or unfair and in
consequence, in violation of Article 14. The
jurisdiction under Article 226 is a valuable
constitutional safeguard against an arbitrary
exercise of State power or a misuse of authority.
39.6. In determining as to whether the
jurisdiction should be exercised in a contractual
dispute, the Court must, undoubtedly eschew,
disputed questions of fact which would depend
upon an evidentiary determination requiring a trial.
But equally, it is well settled that the jurisdiction
under Article 226 cannot be ousted only on the
basis that the dispute pertains to the contractual
arena. This is for the simple reason that the State
and its instrumentalities are not exempt from the
duty to act fairly merely because in their business
dealings they have entered into the realm of
contract. Similarly, the presence of an arbitration
clause does (sic not) oust the jurisdiction under
Article 226 in all cases though, it still needs to be
decided from case to case as to whether recourse to
a public law remedy can justifiably be invoked.
39.7. The jurisdiction under Article 226 was
rightly invoked by the Single Judge and the
19
Division Bench of the Andhra Pradesh High Court
in this case, when the foundational representation
of the contract has failed. Tsiic, a State
instrumentality, has not just reneged on its
contractual obligation, but hoarded the refund of
the principal and interest on the consideration that
was paid by Unitech over a decade ago. It does not
dispute the entitlement of Unitech to the refund of
its principal.”
32. In the case of Subodh Kumar Singh Rathore (supra), the Hon’ble
Supreme Court held that:
“128. The sanctity of public tenders lies in
their role in upholding the principles of equal
opportunity and fairness. Once a contract has come
into existence through a valid tendering process, its
termination must adhere strictly to the terms of the
contract, with the executive powers to be exercised
only in exceptional cases by the public authorities
and that too in loathe. The courts are duty bound to
zealously protect the sanctity of any tender that
has been duly conducted and concluded by
ensuring that the larger public interest of upholding
bindingness of contracts are not sidelined by a
capricious or arbitrary exercise of power by the
State. It is the duty of the courts to interfere in
contractual matters that have fallen prey to an
arbitrary action of the authorities in the guise of
technical faults, policy change or public interest,
etc.
129. The sanctity of contracts is a
fundamental principle that underpins the stability
and predictability of legal and commercial
relationships. When public authorities enter into
contracts, they create legitimate expectations that
the State will honour its obligations. Arbitrary or
unreasonable terminations undermine these
expectations and erode the trust of private players
from the public procurement processes and tenders.
Once a contract is entered, there is a legitimate
expectation, that the obligations arising from the
contract will be honoured and that the rights
arising from it will not be arbitrarily divested except
for a breach or non-compliance of the terms agreed
thereunder. In this regard we may make a
20
reference to the decision of this Court
in Sivanandan C.T. v. High Court of Kerala wherein
it was held that a promise made by a public
authority will give rise to a legitimate expectation
that it will adhere to its assurances. The relevant
portion reads as under:
“18. The basis of the doctrine of legitimate
expectation in public law is founded on the
principles of fairness and non-arbitrariness in
Government dealings with individuals. It
recognises that a public authority's promise or past
conduct will give rise to a legitimate expectation.
The doctrine is premised on the notion that public
authorities, while performing their public duties,
ought to honour their promises or past practices.
The legitimacy of an expectation can be inferred if it
is rooted in law, custom, or established procedure.
* * *
45. The underlying basis for the application of
the doctrine of legitimate expectation has expanded
and evolved to include the principles of good
administration. Since citizens repose their trust in
the State, the actions and policies of the State give
rise to legitimate expectations that the State will
adhere to its assurance or past practice by acting
in a consistent, transparent, and predictable
manner. The principles of good administration
require that the decisions of public authorities must
withstand the test of consistency, transparency,
and predictability to avoid being regarded as
arbitrary and therefore violative of Article 14.”
33. In the case is hand, the petitioner has challenged the order of
termination. It is the specific case of the petitioner that once the
respondent authorities have taken a decision in the meeting for
foreclosure of the work after considering the whole aspect of the matter
and taking into consideration of report that the petitioner is at no fault
of the damages occurred to the work executed by the petitioner and
after the period of five months without recalling or withdrawing the
21
decision of the meeting dated 27
th January, 2025, the respondent
authorities in an arbitrary manner suo moto extended the time and
directed the petitioner to rectify the damages. The petitioner has filed
the writ petition on the ground of arbitrary act of the respondent
authorities.
34. Considering the above, the impugned Memo No. 1515 dated 28
th
July,
2025, is set aside and quashed.
35. WPA No. 17733 of 2025 is allowed.
Parties shall be entitled to act on the basis of a server copy of the
Judgment placed on the official website of the Court.
Urgent Xerox certified photocopies of this judgment, if applied for,
be given to the parties upon compliance of the requisite formalities.
(Krishna Rao, J.)
Legal Notes
Add a Note....