Associate Builders Vs. Delhi Development Authority

  Supreme Court Of India Civil Appeal /10531/2014
Link copied!

Case Background

The case was originally filed in the Delhi High Court, where a Single Judge upheld the arbitral award. On appeal, the Division Bench reversed the decision, rejecting and reducing claims. ...

Bench

Applied Acts & Sections

No Acts & Articles mentioned in this case

Hello! How can I help you? 😊
Disclaimer: We do not store your data.
Document Text Version

Page 1 REPORTABLE

IN THE SUPREME COURT OF INDIA

CIVIL APPELLATE JURISDICTION

CIVIL APPEAL NO. 10531 OF 2014

(ARISING OUT OF SLP (CIVIL) NO.14767 OF 2012)

Associate Builders …Appellant

Versus

Delhi Development Authority …Respondent

J U D G M E N T

R.F.Nariman,J.

1.Leave granted.

2.The appellant herein was awarded a certain construction work contract

by the DDA vide a letter of award dated 14

th

May, 1992. DDA was building a

colony consisting of 7,000 houses in Trilok Puri in the trans-Yamuna area. 168

Middle Income Group houses and 56 Lower Income Group houses, Grade-A

Pocket- B (balance work) was awarded for the tendered amount of

Rs.87,66,678/-. The contract was to be completed in 9 months. Admittedly, it

was ultimately completed only in 34 months, the contractor completing 166

Middle Income Group houses and 36 Lower Income Group houses. The total

value of work that was done amounted to Rs.62,84,845/-. As many as 15

1

Page 2 claims were made by the contractor and the High Court of Delhi appointed one

Shri K.D. Bali to arbitrate the present dispute.

3.We are concerned here with claims 9, 10, 11 and 15, for these claims

have been allowed by the Arbitrator and the DDA’s objections have been

dismissed by the learned Single Judge of the High Court of Delhi. The

Division Bench in an appeal under Section 37 of the Arbitration Act, 1996 has

stepped in to set aside the judgment of the Single Judge and negative these

claims. We are also concerned with claims 12 and 13 which have been scaled

down by the Division Bench.

4. Claims 9, 10, 11 and 15 read as follows:

“Claim No.9: Claimants claim Rs. 20,950/- on account of hire

charges of centering shuttering due to delay in laying of

conduiting.

a) That the respondents had granted certain work of

electrification but the said agency did not lay the conduit

resulting in delay in removing the shuttering and causing hire

charges. This fact was reported to the respondents vide

claimant's letter dated 30.10.92 followed by reminders and also

found place in hindrance register.

b) That this is the actual expenditure incurred and thus the

claimant is entitled for its refund.

c) That the detailed break-up of this claim has been appended

separately.

Claim No.10: Claimants claim Rs.33,450/- being the hire

charges of shuttering due to stoppage of work in block no. 100

and 101.

a) That the department had virtually stopped the work in block

100 & 101 on 20.7.93 and it continued up to 26.2.94. During

this period no work was allowed to be executed in these two

2

Page 3 blocks resulting in blockade or centering and shuttering in the

said two blocks.

b) That by stoppage of work in these two blocks the claimants

had suffered hire charges of shuttering due to respondent's

lapses and defaults.

c) It is further stated that there was no justification for stoppage

of work and the action was arbitrary and totally unjust.

d) That the detail of this claim has been outlined and appended

separately and the same shall from part of the statement of

facts.

Claim No. 11: Rs.2,00,000/- payable as damages on account of

hire charges of tools & plants and scaffolding.

a) That due to prolongation of the contract on account of the

respondents the claimants had to maintain tools & plants,

scaffolding etc, during the prolongation of the contract resulting

in expenditure for the same.

b) That the said articles remained at site beyond the stipulated

period and the claimants suffered loss due to the said

prolongation.

Claim No. 15: Claimants claim damages Rs.6,25,979/- on

account of establishment due to prolongation of the contract.

a) That the claimants had contemplated maintenance of

establishment during stipulated period of completion but the

work was prolonged due to various delays and defaults on the

part of the respondents.

b) It is further stated that the claimants had to pay the

establishment payment during prolongation and the said

expenditure was unproductive and un contemplated.

c) It is further stated that the claimants had maintained

establishment beyond the stipulated completion due to the

respondent's breach and thus entitled for payment.

d) That the respondents were also aware that the claimant has

maintained regular establishment and thus, incurred expenditure

and the claimants had also made several representations.”

3

Page 4 Claims 12 and 13 read as follows:

“Claim No. 12: Claimants claim Rs.7,12,394/- as damages

@20% for execution of the work.

a) That the work was delayed because of the Respondents for

the reasons as set out in the letter indicating hindrances

encountered during execution of the work resulting delay in

execution of the work for a period of 25 months.

b) It is further stated that the claimants incurred unproductive

after stipulated date of completion.

c) It is further stated that during prolongation there had been

steep rise in cost of material and labour.

d) That the claim of 20% is also lent support from the cost

index as issued by the competent authority and only applicable

on the work which was executed during prolongation.

e) That as per cost index it comes to more than 30% whereas

the claimants had claimed 20 & being highly rational and just.

f) That the claimants had appended the details of this claim

separately based on cost index to show that the claimant had

actually incurred this additional expenditure due to the

respondents. Copy of the hindrances encountered during the

execution of the work at the hands of the respondents has been

enclosed.

g) That the respondents had committed breach and thus liable

for damages.

h) It is further stated that the cost of material issued by the

department has been deducted by assessing the cost.

Claim No. 13: Claimants claim Rs.97,5000/- being the extra at

35% for the work executed in block 100 & 101 effective from

28.2.94 till actual completion.

a) It is further stated that due to delayed execution of the work

of these two blocks the claimants had to incur extra expenditure

as the stoppage of work was utterly arbitrary.

b) That the detailed break-up of this claim is appended with the

statement of facts.”

4

Page 5 5.Though the challenge to claims 2, 3 and 4 were given up before the

Division Bench, they are also relevant and read as follows:

“Claim No.2: Claimants claim Rs.1,62,387/- being the

reimbursement of statutory increase in labour under clause 10-C

a) That the claimants submitted the tender on 6.2.92 and said

offer was accepted on 14.5.92. The date of commencement was to

be reckoned from 24.5.92. The date of stipulated completion was

9 months i.e. 23.2.93 but the work could be completed on 28.3.95.

b) It is further stated that the claimants had submitted the bill for

the value to the extent the work was executed till 4.10.94 for a

sum of Rs. l,12,067/- as per the formula applicable.

c) That the respondents however, did not make a single payment

though, the work was executed after submission of the said bill.

d) That however, a consolidated bill was furnished the

respondents for a sum of Rs. l,62,287/-. Even the said payment

has not been liquidated so far.

e) That the claimants advised the statutory increase as and when

enforced and the claimants also submitted the labour reports

indicating the nature of the labour employed at site.

f) That the respondents had also certified on the bill that the

labour payment has been made as per the labour rate.

g) That it is further stated that since it is a statutory increase, the

same is payable by the respondents. Copy of the both the bills

attached. And thus the claimants be awarded a sum of Rs.

1,62,287/- to the claimants.

Claim No.3: Claimants claim Rs.l,49,862/- being the increase in

cost of stone grit on account closure of the quarry by the order of

the Supreme Court.

a) That it is stated that the claimants had submitted the tender on

the basis of the rate prevailing but due to the Hon'ble Court's

directions for closure of the stone quarry resulting in shortage of

stone chips in the market and consequently rates increased.

b) That the claimants informed the quantum of the increase on

22.6.92 and followed by reminders.

5

Page 6 c) That the respondents had agreed in principle to pay the increase

which was prevailing in the market.

d) That the detailed break-up of this claim has been appended

separately.

e) It is further stated that the claimant was not instrumental for

increase in cost but due to the interference of the Hon'ble

Supreme Court. And the said increase has been taken into account

till the stipulated completion dated 23.2.93.

f) That the claimant is entitled for recovery of the said increase.

Claim No. 4: Claimants claim Rs.12,922/- payable by virtue of

clause 10-C of the agreement and up to the stipulated period

a)That there was steep rise in cost of steel and the claimant

was exposed and the respondents were liable to pay the increase

in steel.

b) That the detailed break-up of this claim has been prepared

and appended.

6. The Arbitrator by a reasoned award dated 23

rd

May, 2005 held that the

entire delay of 25 months in the execution of the project was thanks to the

DDA, none of this delay being attributable to the contractor. The learned

Arbitrator found:

“That all the above four claims are inter linked being related to

the overhead expenses and therefore dealt together.

That the date of commencement of work was 24.5.92 and the

period for completion was 9 months and therefore, the disputed

date of completion was 23.2.93 but the work could be actually

completed on 28.3.95.

That there was delay of 25 months in completion of the work

beyond the stipulated date of completion.

That the Claimants urged that there had been various delays in the

execution of work due to the lapses and defaults of the

Respondents from the very commencement of work. The progress

was held up time and again and the claimants therefore, as back as

6

Page 7 17.2.93 advised the Respondents (C-9 page 167) that the

Claimants are not interested to execute the work beyond the

stipulated date of completion and therefore, their contract be

finalized on the stipulated date of completion as the Claimants

shall be exposed to incur heavy expenditure in overheads for

maintaining establishment watch and ward and tools and plants

and other shuttering material but the Respondents did not refute.

The chief reasons for delay are highlighted below:-

I) Delay in supply of structural and architectural drawings.

II) That out of 9 Blocks 2 blocks are abnormally delayed as the

site of the said 21 blocks was made available in piecemeal which

stretched till 26.2.94 whereas the stipulated completion was

23.2.93.

III) Delay in laying the conduit by the electrical agency resulting

in delay in casting of RCC slab and plastering work besides

development work. The said hindrance was removed lastly on

28.3.95.

IV) Abnormal delay in making availability of the alignment

sketch for electrical cables.

V) Inordinate delay in supply of stipulated material such as

cement, steel and pipes.

VI) Delay in decision of finishing· work in kitchen and bath

rooms.

VII) There was inordinate delay in making availability of colour

scheme.

VIII) That the Respondents also abnormally delayed the supply of

door shutters which were to be supplied by the Respondents. The

same were supplied as late as 8.11.94.

IX) Inordinate delay in writing in the electrical conduits resulting

in delay in completion of finishing work.

X) Suspension of work by the Respondents for the period 17.1.94

to 25.2.94 and from 7.8.94 to 22.3.95 because of non-removal of

hindrances.

XI) Delayed payment due to non-sanction of Administrative

Approval and Expenditure Sanction.

That all the delays as set out had been duly recorded 733 to 739

and M.A.S. register pages from 747 to 768 as highlighted by the

7

Page 8 Claimants. The Claimants also relied upon certain documents of

MAS Register supplied by the Respondents.

That the Claimants further stated that the Claimants had also filed

reasons for delay and hold up of the work various defaults of the

Respondents in Annexure pages 740 to 746. The Claimants also

highlighted the correspondence made by the Claimants with

Respondents.

That the Claimants further stated that the said hindrances were

avoidable but the Respondents did not take timely steps.

That the Claimants also referred the contents of the letter dated

10.7.95 (page 885) wherein it was observed that the

Superintending Engineer appreciated the working of the

Claimants and also observed that there was no fault of the

contractor and they have successfully completed the work. The

Claimants further stated that, they had incurred heavy expenditure

on overheads of the lapses and default of the Respondents.

As against this the Respondents stated that there was poor

planning of the claimants and also contended that since the

compensation has been levied under Clause 2 of the agreement

therefore, claim of the claimants deserves to be rejected.

That on record it is conclusively proved that the Respondents

committed breach of contract as they failed to discharge their

obligations in time resulting in prolongations did not deny the

deployment of the tools and plants and machinery at site besides

watch and ward during the prolongation.”

7.It is important to note that before the Division Bench, the learned

counsel for the DDA conceded that this being a pure finding of fact, he would

not be challenging it before the Division Bench.

8.Of the total claim of Rs.37.28 lakhs, the learned Arbitrator awarded an

amount of Rs.23.39 lakhs. Further, the learned Arbitrator has laboriously gone

through all the evidence and answered each claim giving reasons for the same.

8

Page 9 9.By a judgment dated 3

rd

April, 2006, the learned Single Judge of the

High Court of Delhi dismissed the objections of the DDA and upheld the

award. In an appeal filed under Section 37 of the Arbitration Act, vide the

impugned judgment dated 8

th

February, 2012, a Division Bench of the High

Court of Delhi set aside the judgment of the Single Judge on claims 9, 10, 11

and 15, and negatived these claims in toto. Further, claims 12 and 13 were

scaled down doing “rough and ready justice”. Resultantly, the awarded amount

of Rs.7,20,000/- was scaled down to Rs. 5,57,137.50/-.

10.We have heard learned counsel for the parties. Shri M. L. Verma, learned

Senior Advocate appearing on behalf of the appellant, submitted that the

Division Bench has lost sight of the law laid down by this Hon’ble Court when

it comes to challenges made to arbitral awards under Section 34 of the Act. He

has submitted that the Division Bench has acted as if this was a first appeal

from the award and has further submitted that the Division Bench has taken

into account facts which were neither pleaded nor proved before the learned

Arbitrator in order to negative certain claims. He further submitted that it is not

possible for a Bench hearing an objection against an arbitral award to do

“rough and ready justice” – it is bound by the law laid down by this Hon’ble

Court. In particular, he argued that the conceded position is that 25 months

delay was due to the DDA alone. The award read as a whole is just, fair and

reasonable as only certain claims have been granted and every claim granted

has been supported with reasons. The Arbitrator is the sole judge of the quality

9

Page 10 and quantity of evidence before him and he has decided on that evidence. No

errors of law arise from the award and the award has, therefore, been wrongly

set aside.

11.Mr. Amarendra Sharan, learned Senior Advocate appearing on behalf of

the DDA has relied strongly on clause 10C and clause 22 to support the

judgment of the Division bench and has further argued that there has been

duplication so far as certain claims are concerned. He argued that an award in

the teeth of clause 10C and clause 22 would be a jurisdictional error which

would vitiate the award.

12.In as much as serious objections have been taken to the Division Bench

judgment on the ground that it has ignored the parameters laid down in a series

of judgments by this Court as to the limitations which a Judge hearing

objections to an arbitral award under Section 34 is subject to, we deem it

necessary to state the law on the subject.

Section 34 of the Arbitration and Conciliation Act reads as follows-

“Application for setting aside arbitral award.—(1) Recourse

to a Court against an arbitral award may be made only by an

application for setting aside such award in accordance with sub-

section (2) and sub-section (3).

(2) An arbitral award may be set aside by the Court only if—

(a) the party making the application furnishes proof that—

(i) a party was under some incapacity; or

10

Page 11 (ii) The arbitration agreement is not valid under the law to

which the parties have subjected it or, failing any indication

thereon, under the law for the time being in force; or

(iii) the party making the application was not given proper

notice of the appointment of an arbitrator or of the arbitral

proceedings or was otherwise unable to present his case; or

(iv) the arbitral award deals with a dispute not contemplated by

or not falling within the terms of the submission to arbitration,

or it contains decisions on matters beyond the scope of the

submission to arbitration:

Provided that, if the decisions on matters submitted to

arbitration can be separated from those not so submitted, only

that part of the arbitral award which contains decisions on

matters not submitted to arbitration may be set aside; or

(v) the composition of the arbitral tribunal or the arbitral

procedure was not in accordance with the agreement of the

parties, unless such agreement was in conflict with a provision

of this Part from which the parties cannot derogate, or, failing

such agreement, was not in accordance with this Part; or

(b) the Court finds that—

(i) the subject-matter of the dispute is not capable of settlement

by arbitration under the law for the time being in force, or

(ii) the arbitral award is in conflict with the public policy of

India.

Explanation.—Without prejudice to the generality of sub-clause

(ii), it is hereby declared, for the avoidance of any doubt, that

an award is in conflict with the public policy of India if the

making of the award was induced or affected by fraud or

corruption or was in violation of Section 75 or Section 81.

(3) An application for setting aside may not be made after three

months have elapsed from the date on which the party making

that application had received the arbitral award or, if a request

had been made under Section 33, from the date on which that

request had been disposed of by the arbitral tribunal:

Provided that if the Court is satisfied that the applicant was

prevented by sufficient cause from making the application

within the said period of three months it may entertain the

11

Page 12 application within a further period of thirty days, but not

thereafter.

(4) On receipt of an application under sub-section (1), the Court

may, where it is appropriate and it is so requested by a party,

adjourn the proceedings for a period of time determined by it in

order to give the arbitral tribunal an opportunity to resume the

arbitral proceedings or to take such other action as in the

opinion of arbitral tribunal will eliminate the grounds for setting

aside the arbitral award.”

This Section in conjunction with Section 5 makes it clear that an arbitration

award that is governed by part I of the Arbitration and Conciliation Act, 1996

can be set aside only on grounds mentioned under Section 34 (2) and (3), and

not otherwise. Section 5 reads as follows:

“5. Extent of judicial intervention.—Notwithstanding anything

contained in any other law for the time being in force, in matters

governed by this Part, no judicial authority shall intervene except

where so provided in this Part.”

It is important to note that the 1996 Act was enacted to replace the 1940

Arbitration Act in order to provide for an arbitral procedure which is fair,

efficient and capable of meeting the needs of arbitration; also to provide that

the tribunal gives reasons for an arbitral award; to ensure that the tribunal

remains within the limits of its jurisdiction; and to minimize the supervisory

roles of courts in the arbitral process.

It will be seen that none of the grounds contained in sub-clause 2 (a) deal

with the merits of the decision rendered by an arbitral award. It is only when

we come to the award being in conflict with the public policy of India that the

12

Page 13 merits of an arbitral award are to be looked into under certain specified

circumstances.

In Renusagar Power Co. Ltd. v. General Electronic Co., 1994 Supp

(1) SCC 644, the Supreme Court construed Section 7 (1)(b) (ii) of the Foreign

Award (Recognition and Enforcement) Act, 1961.

“7. Conditions for enforcement of foreign awards.—(1) A

foreign award may not be enforced under this Act—

(b) if the Court dealing with the case is satisfied that—

(ii) the enforcement of the award will be contrary to the public

policy.”

In construing the expression “public policy” in the context of a foreign

award, the Court held that an award contrary to

1.The fundamental policy of Indian law

2.The interest of India

3.Justice or morality,

would be set aside on the ground that it would be contrary to the public policy

of India. It went on further to hold that a contravention of the provisions of the

Foreign Exchange Regulation Act would be contrary to the public policy of

India in that the statute is enacted for the national economic interest to ensure

that the nation does not lose foreign exchange which is essential for the

economic survival of the nation (see para 75). Equally, disregarding orders

passed by the superior courts in India could also be a contravention of the

13

Page 14 fundamental policy of Indian law, but the recovery of compound interest on

interest, being contrary to statute only, would not contravene any fundamental

policy of Indian law (see paras 85,95).

When it came to construing the expression “the public policy of India”

contained in Section 34 (2) (b) (ii) of the Arbitration Act, 1996, this Court in

ONGC v. Saw Pipes, 2003 (5) SCC 705, held-

“31. Therefore, in our view, the phrase “public policy of India”

used in Section 34 in context is required to be given a wider

meaning. It can be stated that the concept of public policy

connotes some matter which concerns public good and the public

interest. What is for public good or in public interest or what

would be injurious or harmful to the public good or public

interest has varied from time to time. However, the award which

is, on the face of it, patently in violation of statutory provisions

cannot be said to be in public interest. Such

award/judgment/decision is likely to adversely affect the

administration of justice. Hence, in our view in addition to

narrower meaning given to the term “public policy”

in Renusagar case [1994 Supp (1) SCC 644] it is required to be

held that the award could be set aside if it is patently illegal. The

result would be — award could be set aside if it is contrary to:

(a) Fundamental policy of Indian law; or

(b) The interest of India; or

(c) Justice or morality, or

(d) in addition, if it is patently illegal.

Illegality must go to the root of the matter and if the illegality is

of trivial nature it cannot be held that award is against the public

policy. Award could also be set aside if it is so unfair and

unreasonable that it shocks the conscience of the court. Such

award is opposed to public policy and is required to be adjudged

void.

74. In the result, it is held that:

14

Page 15 (A) (1) The court can set aside the arbitral award under Section

34(2) of the Act if the party making the application furnishes

proof that:

(i) a party was under some incapacity, or

(ii) the arbitration agreement is not valid under the law to which

the parties have subjected it or, failing any indication thereon,

under the law for the time being in force; or

(iii) the party making the application was not given proper notice

of the appointment of an arbitrator or of the arbitral proceedings

or was otherwise unable to present his case; or

(iv) the arbitral award deals with a dispute not contemplated by

or not falling within the terms of the submission to arbitration, or

it contains decisions on matters beyond the scope of the

submission to arbitration.

(2) The court may set aside the award:

(i)(a) if the composition of the Arbitral Tribunal was not in

accordance with the agreement of the parties,

(b) failing such agreement, the composition of the Arbitral

Tribunal was not in accordance with Part I of the Act.

(ii) if the arbitral procedure was not in accordance with:

(a) the agreement of the parties, or

(b) failing such agreement, the arbitral procedure was not in

accordance with Part I of the Act.

However, exception for setting aside the award on the ground of

composition of Arbitral Tribunal or illegality of arbitral

procedure is that the agreement should not be in conflict with the

provisions of Part I of the Act from which parties cannot

derogate.

(c) If the award passed by the Arbitral Tribunal is in

contravention of the provisions of the Act or any other substantive

law governing the parties or is against the terms of the contract.

(3) The award could be set aside if it is against the public policy

of India, that is to say, if it is contrary to:

(a) fundamental policy of Indian law; or

(b) the interest of India; or

15

Page 16 (c) justice or morality; or

(d) if it is patently illegal.

(4) It could be challenged:

(a) as provided under Section 13(5); and

(b) Section 16(6) of the Act.

(B)(1) The impugned award requires to be set aside mainly on the

grounds:

(i) there is specific stipulation in the agreement that the time and

date of delivery of the goods was of the essence of the contract;

(ii) in case of failure to deliver the goods within the period fixed

for such delivery in the schedule, ONGC was entitled to recover

from the contractor liquidated damages as agreed;

(iii) it was also explicitly understood that the agreed liquidated

damages were genuine pre-estimate of damages;

(iv) on the request of the respondent to extend the time-limit for

supply of goods, ONGC informed specifically that time was

extended but stipulated liquidated damages as agreed would be

recovered;

(v) liquidated damages for delay in supply of goods were to be

recovered by paying authorities from the bills for payment of cost

of material supplied by the contractor;

(vi) there is nothing on record to suggest that stipulation for

recovering liquidated damages was by way of penalty or that the

said sum was in any way unreasonable.

(vii) In certain contracts, it is impossible to assess the damages

or prove the same. Such situation is taken care of by Sections 73

and 74 of the Contract Act and in the present case by specific

terms of the contract.”

The judgment in ONGC v. Saw Pipes has been consistently followed

till date.

16

Page 17 In Hindustan Zinc Ltd. v. Friends Coal Carbonisation, (2006) 4 SCC

445, this Court held:

“14. The High Court did not have the benefit of the principles

laid down in Saw Pipes [(2003) 5 SCC 705] , and had

proceeded on the assumption that award cannot be interfered

with even if it was contrary to the terms of the contract. It went

to the extent of holding that contract terms cannot even be

looked into for examining the correctness of the award. This

Court in Saw Pipes [(2003) 5 SCC 705] has made it clear that

it is open to the court to consider whether the award is against

the specific terms of contract and if so, interfere with it on the

ground that it is patently illegal and opposed to the public

policy of India.”

In McDermott International Inc. v. Burn Standard Co. Ltd.,

(2006) 11 SCC 181, this Court held:

“58. In Renusagar Power Co. Ltd. v. General Electric

Co. [1994 Supp (1) SCC 644] this Court laid down that the

arbitral award can be set aside if it is contrary to (a)

fundamental policy of Indian law; (b) the interests of India; or

(c) justice or morality. A narrower meaning to the expression

“public policy” was given therein by confining judicial review

of the arbitral award only on the aforementioned three grounds.

An apparent shift can, however, be noticed from the decision of

this Court in ONGC Ltd.v. Saw Pipes Ltd. [(2003) 5 SCC 705]

(for short “ONGC”). This Court therein referred to an earlier

decision of this Court in Central Inland Water Transport

Corpn. Ltd. v. Brojo Nath Ganguly [(1986) 3 SCC 156 : 1986

SCC (L&S) 429 : (1986) 1 ATC 103] wherein the applicability

of the expression “public policy” on the touchstone of Section

23 of the Indian Contract Act and Article 14 of the Constitution

of India came to be considered. This Court therein was dealing

with unequal bargaining power of the workmen and the

employer and came to the conclusion that any term of the

agreement which is patently arbitrary and/or otherwise arrived

at because of the unequal bargaining power would not only be

ultra vires Article 14 of the Constitution of India but also hit by

Section 23 of the Indian Contract Act. In ONGC [(2003) 5 SCC

17

Page 18 705] this Court, apart from the three grounds stated

in Renusagar [1994 Supp (1) SCC 644] , added another ground

thereto for exercise of the court's jurisdiction in setting aside

the award if it is patently arbitrary.

59. Such patent illegality, however, must go to the root of the

matter. The public policy violation, indisputably, should be so

unfair and unreasonable as to shock the conscience of the

court. Where the arbitrator, however, has gone contrary to or

beyond the expressed law of the contract or granted relief in the

matter not in dispute would come within the purview of Section

34 of the Act. However, we would consider the applicability of

the aforementioned principles while noticing the merits of the

matter.

60. What would constitute public policy is a matter dependent

upon the nature of transaction and nature of statute. For the

said purpose, the pleadings of the parties and the materials

brought on record would be relevant to enable the court to

judge what is in public good or public interest, and what would

otherwise be injurious to the public good at the relevant point,

as contradistinguished from the policy of a particular

Government. (See State of Rajasthan v. Basant Nahata [(2005)

12 SCC 77].)”

In Centrotrade Minerals & Metals Inc. v. Hindustan Copper Ltd.,

(2006) 11 SCC 245, Sinha, J., held:

“103. Such patent illegality, however, must go to the root of the

matter. The public policy, indisputably, should be unfair and

unreasonable so as to shock the conscience of the court. Where

the arbitrator, however, has gone contrary to or beyond the

expressed law of the contract or granted relief in the matter not

in dispute would come within the purview of Section 34 of the

Act.”

104. What would be a public policy would be a matter which

would again depend upon the nature of transaction and the

nature of statute. For the said purpose, the pleadings of the

parties and the materials brought on record would be relevant

so as to enable the court to judge the concept of what was a

public good or public interest or what would otherwise be

injurious to the public good at the relevant point as

18

Page 19 contradistinguished by the policy of a particular government.

(See State of Rajasthan v. Basant Nahata [(2005) 12 SCC

77].)”

In DDA v. R.S. Sharma and Co., (2008) 13 SCC 80, the Court

summarized the law thus:

“21. From the above decisions, the following principles emerge:

(a) An award, which is

(i) contrary to substantive provisions of law; or

(ii) the provisions of the Arbitration and Conciliation Act,

1996; or

(iii) against the terms of the respective contract; or

(iv) patently illegal; or

(v) prejudicial to the rights of the parties;

is open to interference by the court under Section 34(2) of the

Act.

(b) The award could be set aside if it is contrary to:

(a) fundamental policy of Indian law; or

(b) the interest of India; or

(c) justice or morality.

(c) The award could also be set aside if it is so unfair and

unreasonable that it shocks the conscience of the court.

(d) It is open to the court to consider whether the award is

against the specific terms of contract and if so, interfere with it

on the ground that it is patently illegal and opposed to the

public policy of India.

With these principles and statutory provisions, particularly,

Section 34(2) of the Act, let us consider whether the arbitrator

as well as the Division Bench of the High Court were justified

in granting the award in respect of Claims 1 to 3 and

Additional Claims 1 to 3 of the claimant or the appellant DDA

has made out a case for setting aside the award in respect of

19

Page 20 those claims with reference to the terms of the agreement duly

executed by both parties.”

J.G. Engineers (P) Ltd. v. Union of India, (2011) 5 SCC 758, held:

“27. Interpreting the said provisions, this Court in ONGC

Ltd. v. Saw Pipes Ltd.[(2003) 5 SCC 705] held that a court can

set aside an award under Section 34(2)(b)(ii) of the Act, as

being in conflict with the public policy of India, if it is (a)

contrary to the fundamental policy of Indian law; or (b)

contrary to the interests of India; or (c) contrary to justice or

morality; or (d) patently illegal. This Court explained that to

hold an award to be opposed to public policy, the patent

illegality should go to the very root of the matter and not a

trivial illegality. It is also observed that an award could be set

aside if it is so unfair and unreasonable that it shocks the

conscience of the court, as then it would be opposed to public

policy.”

Union of India v. Col. L.S.N. Murthy, (2012) 1 SCC 718, held:

“22. In ONGC Ltd. v. Saw Pipes Ltd. [(2003) 5 SCC 705] this

Court after examining the grounds on which an award of the

arbitrator can be set aside under Section 34 of the Act has said:

(SCC p. 727, para 31)

“31. … However, the award which is, on the face of it, patently

in violation of statutory provisions cannot be said to be in

public interest. Such award/judgment/decision is likely to

adversely affect the administration of justice. Hence, in our

view in addition to narrower meaning given to the term ‘public

policy’ in Renusagar case [Renusagar Power Co.

Ltd. v. General Electric Co., 1994 Supp (1) SCC 644] it is

required to be held that the award could be set aside if it is

patently illegal”.

Fundamental Policy of Indian Law

Coming to each of the heads contained in the Saw Pipes judgment, we

will first deal with the head “fundamental policy of Indian Law”. It has already

20

Page 21 been seen from the Renusagar judgment that violation of the Foreign Exchange

Act and disregarding orders of superior courts in India would be regarded as

being contrary to the fundamental policy of Indian law. To this it could be

added that the binding effect of the judgment of a superior court being

disregarded would be equally violative of the fundamental policy of Indian

law.

In a recent judgment, ONGC Ltd. v. Western Geco International Ltd.,

2014 (9) SCC 263, this Court added three other distinct and fundamental

juristic principles which must be understood as a part and parcel of the

fundamental policy of Indian law. The Court held-

“35. What then would constitute the “fundamental policy of

Indian law” is the question. The decision in ONGC [ONGC

Ltd. v. Saw Pipes Ltd., (2003) 5 SCC 705] does not elaborate that

aspect. Even so, the expression must, in our opinion, include all

such fundamental principles as providing a basis for

administration of justice and enforcement of law in this country.

Without meaning to exhaustively enumerate the purport of the

expression “fundamental policy of Indian law”, we may refer to

three distinct and fundamental juristic principles that must

necessarily be understood as a part and parcel of the fundamental

policy of Indian law. The first and foremost is the principle that in

every determination whether by a court or other authority that

affects the rights of a citizen or leads to any civil consequences,

the court or authority concerned is bound to adopt what is in

legal parlance called a “judicial approach” in the matter. The

duty to adopt a judicial approach arises from the very nature of

the power exercised by the court or the authority does not have to

be separately or additionally enjoined upon the fora concerned.

What must be remembered is that the importance of a judicial

approach in judicial and quasi-judicial determination lies in the

fact that so long as the court, tribunal or the authority exercising

powers that affect the rights or obligations of the parties before

them shows fidelity to judicial approach, they cannot act in an

21

Page 22 arbitrary, capricious or whimsical manner. Judicial approach

ensures that the authority acts bona fide and deals with the

subject in a fair, reasonable and objective manner and that its

decision is not actuated by any extraneous consideration. Judicial

approach in that sense acts as a check against flaws and faults

that can render the decision of a court, tribunal or authority

vulnerable to challenge.

38. Equally important and indeed fundamental to the policy of

Indian law is the principle that a court and so also a quasi-

judicial authority must, while determining the rights and

obligations of parties before it, do so in accordance with the

principles of natural justice. Besides the celebrated audi alteram

partem rule one of the facets of the principles of natural justice is

that the court/authority deciding the matter must apply its mind to

the attendant facts and circumstances while taking a view one

way or the other. Non-application of mind is a defect that is fatal

to any adjudication. Application of mind is best demonstrated by

disclosure of the mind and disclosure of mind is best done by

recording reasons in support of the decision which the court or

authority is taking. The requirement that an adjudicatory

authority must apply its mind is, in that view, so deeply embedded

in our jurisprudence that it can be described as a fundamental

policy of Indian law.

39. No less important is the principle now recognised as a

salutary juristic fundamental in administrative law that a decision

which is perverse or so irrational that no reasonable person

would have arrived at the same will not be sustained in a court of

law. Perversity or irrationality of decisions is tested on the

touchstone of Wednesbury principle [Associated Provincial

Picture Houses Ltd. v. Wednesbury Corpn., (1948) 1 KB 223:

(1947) 2 All ER 680 (CA)] of reasonableness. Decisions that fall

short of the standards of reasonableness are open to challenge in

a court of law often in writ jurisdiction of the superior courts but

no less in statutory processes wherever the same are available.

40. It is neither necessary nor proper for us to attempt an

exhaustive enumeration of what would constitute the fundamental

policy of Indian law nor is it possible to place the expression in

the straitjacket of a definition. What is important in the context of

the case at hand is that if on facts proved before them the

arbitrators fail to draw an inference which ought to have been

drawn or if they have drawn an inference which is on the face of

it, untenable resulting in miscarriage of justice, the adjudication

even when made by an Arbitral Tribunal that enjoys considerable

22

Page 23 latitude and play at the joints in making awards will be open to

challenge and may be cast away or modified depending upon

whether the offending part is or is not severable from the rest.”

It is clear that the juristic principle of a “judicial approach” demands that

a decision be fair, reasonable and objective. On the obverse side, anything

arbitrary and whimsical would obviously not be a determination which would

either be fair, reasonable or objective.

The Audi Alteram Partem principle which undoubtedly is a fundamental

juristic principle in Indian law is also contained in Sections 18 and 34 (2) (a)

(iii) of the Arbitration and Conciliation Act. These Sections read as follows:

“18. Equal treatment of parties.— The parties shall be treated

with equality and each party shall be given a full opportunity to

present his case.

34. Application for setting aside arbitral award.—

(2) An arbitral award may be set aside by the Court only if

(a) the party making the application furnishes proof that—

(iii) the party making the application was not given proper

notice of the appointment of an arbitrator or of the arbitral

proceedings or was otherwise unable to present his case; ”

The third juristic principle is that a decision which is perverse or so

irrational that no reasonable person would have arrived at the same is

important and requires some degree of explanation. It is settled law that where-

1.a finding is based on no evidence, or

23

Page 24 2.an arbitral tribunal takes into account something irrelevant to the

decision which it arrives at; or

3.ignores vital evidence in arriving at its decision,

such decision would necessarily be perverse. A good working test of perversity

is contained in two judgments. In H.B. Gandhi, Excise and Taxation Officer-

cum-Assessing Authority v. Gopi Nath & Sons, 1992 Supp (2) SCC 312 at p.

317, it was held:

“7. …................It is, no doubt, true that if a finding of fact is

arrived at by ignoring or excluding relevant material or by taking

into consideration irrelevant material or if the finding so

outrageously defies logic as to suffer from the vice of irrationality

incurring the blame of being perverse, then, the finding is

rendered infirm in law.”

In Kuldeep Singh v. Commr. of Police, (1999) 2 SCC 10 at

para 10, it was held:

“10. A broad distinction has, therefore, to be maintained between

the decisions which are perverse and those which are not. If a

decision is arrived at on no evidence or evidence which is

thoroughly unreliable and no reasonable person would act upon

it, the order would be perverse. But if there is some evidence on

record which is acceptable and which could be relied upon,

howsoever compendious it may be, the conclusions would not be

treated as perverse and the findings would not be interfered

with.”

It must clearly be understood that when a court is applying the “public

policy” test to an arbitration award, it does not act as a court of appeal and

consequently errors of fact cannot be corrected. A possible view by the

24

Page 25 arbitrator on facts has necessarily to pass muster as the arbitrator is the ultimate

master of the quantity and quality of evidence to be relied upon when he

delivers his arbitral award. Thus an award based on little evidence or on

evidence which does not measure up in quality to a trained legal mind would

not be held to be invalid on this score

1

. Once it is found that the arbitrators

approach is not arbitrary or capricious, then he is the last word on facts. In P.R.

Shah, Shares & Stock Brokers (P) Ltd. v. B.H.H. Securities (P) Ltd.,

(2012) 1 SCC 594, this Court held:

“21. A court does not sit in appeal over the award of an Arbitral

Tribunal by reassessing or reappreciating the evidence. An award

can be challenged only under the grounds mentioned in Section

34(2) of the Act. The Arbitral Tribunal has examined the facts and

held that both the second respondent and the appellant are liable.

The case as put forward by the first respondent has been

accepted. Even the minority view was that the second respondent

was liable as claimed by the first respondent, but the appellant

was not liable only on the ground that the arbitrators appointed

by the Stock Exchange under Bye-law 248, in a claim against a

non-member, had no jurisdiction to decide a claim against

another member. The finding of the majority is that the appellant

did the transaction in the name of the second respondent and is

therefore, liable along with the second respondent. Therefore, in

the absence of any ground under Section 34(2) of the Act, it is not

possible to re-examine the facts to find out whether a different

decision can be arrived at.”

It is with this very important caveat that the two fundamental principles

which form part of the fundamental policy of Indian law (that the arbitrator

1

Very often an arbitrator is a lay person not necessarily trained in law. Lord Mansfield, a famous

English Judge, once advised a high military officer in Jamaica who needed to act as a Judge as follows:

“General, you have a sound head, and a good heart; take courage and you will do very

well, in your occupation, in a court of equity. My advice is, to make your decrees as your head and

your heart dictate, to hear both sides patiently, to decide with firmness in the best manner you can;

but be careful not to assign your reasons, since your determination may be substantially right,

although your reasons may be very bad, or essentially wrong”.

It is very important to bear this in mind when awards of lay arbitrators are challenged.

25

Page 26 must have a judicial approach and that he must not act perversely) are to be

understood.

Interest of India

The next ground on which an award may be set aside is that it is contrary

to the interest of India. Obviously, this concerns itself with India as a member

of the world community in its relations with foreign powers. As at present

advised, we need not dilate on this aspect as this ground may need to evolve on

a case by case basis.

Justice

The third ground of public policy is, if an award is against justice or

morality. These are two different concepts in law. An award can be said to be

against justice only when it shocks the conscience of the court. An illustration

of this can be given. A claimant is content with restricting his claim, let us say

to Rs. 30 lakhs in a statement of claim before the arbitrator and at no point

does he seek to claim anything more. The arbitral award ultimately awards him

45 lakhs without any acceptable reason or justification. Obviously, this would

shock the conscience of the court and the arbitral award would be liable to be

set aside on the ground that it is contrary to “justice”.

Morality

The other ground is of “morality”. Just as the expression “public policy”

also occurs in Section 23 of the Indian Contract Act, so does the expression

26

Page 27 “morality”. Two illustrations to the said section are interesting for they explain

to us the scope of the expression “morality”.

“(j) A, who is B's Mukhtar, promises to exercise his influence, as

such, with B in favour of C, and C promises to pay 1,000 rupees

to A. The agreement is void, because it is immoral.

(k) A agrees to let her daughter to hire to B for concubinage. The

agreement is void, because it is immoral, though the letting may

not be punishable under the Indian Penal Code (XLV of 1860).”

In Gherulal Parekh v. Mahadeo Dass Maiya, 1959 Supp (2) SCR 406,

this Court explained the concept of “morality” thus-

“Re. Point 3 - Immorality: The argument under this head is rather

broadly stated by the learned Counsel for the appellant. The

learned counsel attempts to draw an analogy from the Hindu Law

relating to the doctrine of pious obligation of sons to discharge

their father's debts and contends that what the Hindu Law

considers to be immoral in that context may appropriately be

applied to a case under s. 23 of the Contract Act. Neither any

authority is cited nor any legal basis is suggested for importing

the doctrine of Hindu Law into the domain of contracts.

Section 23 of the Contract Act is inspired by the common law of

England and it would be more useful to refer to the English Law

than to the Hindu Law texts dealing with a different matter. Anson

in his Law of Contracts states at p. 222 thus:

"The only aspect of immorality with which Courts of Law

have dealt is sexual immorality........... ."

Halsbury in his Laws of England, 3rd Edn., Vol. 8, makes a

similar statement, at p. 138 :

"A contract which is made upon an immoral consideration

or for an immoral purpose is unenforceable, and there is no

distinction in this respect between immoral and illegal contracts.

The immorality here alluded to is sexual immorality."

In the Law of Contract by Cheshire and Fifoot, 3rd Edn., it

is stated at p. 279:

27

Page 28 "Although Lord Mansfield laid it down that a contract

contra bonos mores is illegal, the law in this connection gives no

extended meaning to morality, but concerns itself only with what

is sexually reprehensible."

In the book on the Indian Contract Act by Pollock and

Mulla it is stated at p. 157:

"The epithet "immoral" points, in legal usage, to conduct or

purposes which the State, though disapproving them, is unable, or

not advised, to visit with direct punishment."

The learned authors confined its operation to acts which

are considered to be immoral according to the standards of

immorality approved by Courts. The case law both in England

and India confines the operation of the doctrine to sexual

immorality. To cite only some instances: settlements in

consideration of concubinage, contracts of sale or hire of things

to be used in a brothel or by a prostitute for purposes incidental

to her profession, agreements to pay money for future illicit

cohabitation, promises in regard to marriage for consideration,

or contracts facilitating divorce are all held to be void on the

ground that the object is immoral.

The word "immoral" is a very comprehensive word.

Ordinarily it takes in every aspect of personal conduct deviating

from the standard norms of life. It may also be said that what is

repugnant to good conscience is immoral. Its varying content

depends upon time, place and the stage of civilization of a

particular society. In short, no universal standard can be laid

down and any law based on such fluid concept defeats its own

purpose. The provisions of S. 23 of the Contract Act indicate the

legislative intention to give it a restricted meaning. Its

juxtaposition with an equally illusive concept, public policy,

indicates that it is used in a restricted sense; otherwise there

would be overlapping of the two concepts. In its wide sense what

is immoral may be against public policy, for public policy covers

political, social and economic ground of objection. Decided cases

and authoritative text-book writers, therefore, confined it, with

every justification, only to sexual immorality. The other limitation

imposed on the word by the statute, namely, "the court regards it

as immoral", brings out the idea that it is also a branch of the

common law like the doctrine of public policy, and, therefore,

should be confined to the principles recognized and settled by

Courts. Precedents confine the said concept only to sexual

immorality and no case has been brought to our notice where it

28

Page 29 has been applied to any head other than sexual immorality. In the

circumstances, we cannot evolve a new head so as to bring in

wagers within its fold.”

This Court has confined morality to sexual morality so far as section 23

of the Contract Act is concerned, which in the context of an arbitral award

would mean the enforcement of an award say for specific performance of a

contract involving prostitution. “Morality” would, if it is to go beyond sexual

morality necessarily cover such agreements as are not illegal but would not be

enforced given the prevailing mores of the day. However, interference on this

ground would also be only if something shocks the court’s conscience.

Patent Illegality

We now come to the fourth head of public policy namely, patent

illegality. It must be remembered that under the explanation to section 34 (2)

(b), an award is said to be in conflict with the public policy of India if the

making of the award was induced or affected by fraud or corruption. This

ground is perhaps the earliest ground on which courts in England set aside

awards under English law. Added to this ground (in 1802) is the ground that an

arbitral award would be set aside if there were an error of law by the arbitrator.

This is explained by Lord Justice Denning in R v. Northumberland

Compensation Appeal Tribunal. Ex Parte Shaw., 1952 1 All ER 122 at page

130:

“Leaving now the statutory tribunals, I turn to the awards of the

arbitrators. The Court of King's Bench never interfered by

certiorari with the award of an arbitrator, because it was a

29

Page 30 private tribunal and not subject to the prerogative writs. If the

award was not made a rule of court, the only course available to

an aggrieved party was to resist an action on the award or to file

a bill in equity. If the award was made a rule of court, a motion

could be made to the court to set it aside for misconduct of the

arbitrator on the ground that it was procured by corruption or

other undue means: see the statute 9 and 10 Will. III, c. 15. At one

time an award could not be upset on the ground of error of law by

the arbitrator because that could not be said to be misconduct or

undue means, but ultimately it was held in Kent v. Elstob, (1802)

3 East 18, that an award could be set aside for error of law on the

face of it. This was regretted by Williams, J., in Hodgkinson v.

Fernie, (1857) 3 C.B.N.S. 189, but is now well established.”

This, in turn, led to the famous principle laid down in Champsey Bhara

Company v. The Jivraj Balloo Spinning and Weaving Company Ltd., AIR

1923 PC 66, where the Privy Council referred to Hodgkinson and then laid

down:

“The law on the subject has never been more clearly stated than

by Williams, J. in the case of Hodgkinson v. Fernie (1857) 3

C.B.N.S. 189.

“The law has for many years been settled, and remains so at this

day, that, where a cause or matters in difference are referred to an

arbitrator a lawyer or a layman, he is constituted the sole and

final judge of all questions both of law and of fact …… The only

exceptions to that rule are cases where the award is the result of

corruption or fraud, and one other, which though it is to be

regretted, is now, I think firmly established viz., where the

question of law necessarily arises on the face of the award or

upon some paper accompanying and forming part of the award.

Though the propriety of this latter may very well be doubted, I

think it may be considered as established.”

“Now the regret expressed by Williams, J. in Hodgkinson v.

Fernie has been repeated by more than one learned Judge, and it

is certainly not to be desired that the exception should be in any

way extended. An error in law on the face of the award means, in

their Lordships’ view, that you can find in the award or a

30

Page 31 document actually incorporated thereto, as for instance, a note

appended by the arbitrator stating the reasons for his judgment,

some legal proposition which is the basis of the award and which

you can then say is erroneous. It does not mean that if in a

narrative a reference is made to a contention of one party that

opens the door to seeing first what that contention is, and then

going to the contract on which the parties’ rights depend to see if

that contention is sound. Here it is impossible to say, from what is

shown on the face of the award, what mistake the arbitrators

made. The only way that the learned judges have arrived at

finding what the mistake was is by saying: “Inasmuch as the

Arbitrators awarded so and so, and inasmuch as the letter shows

that then buyer rejected the cotton, the arbitrators can only have

arrived at that result by totally misinterpreting Cl.52.” But they

were entitled to give their own interpretation to Cl. 52 or any

other article, and the award will stand unless, on the face of it

they have tied themselves down to some special legal proposition

which then, when examined, appears to be unsound. Upon this

point, therefore, their Lordships think that the judgment of Pratt, J

was right and the conclusion of the learned Judges of the Court of

Appeal erroneous.”

This judgment has been consistently followed in India to test awards

under Section 30 of the Arbitration Act, 1940.

In the 1996 Act, this principle is substituted by the ‘patent illegality’

principle which, in turn, contains three sub heads -

(a) a contravention of the substantive law of India would result in the death

knell of an arbitral award. This must be understood in the sense that such

illegality must go to the root of the matter and cannot be of a trivial nature.

This again is a really a contravention of Section 28(1)(a) of the Act, which

reads as under:

31

Page 32 “28. Rules applicable to substance of dispute.—(1) Where the

place of arbitration is situated in India,—

(a) in an arbitration other than an international commercial

arbitration, the arbitral tribunal shall decide the dispute

submitted to arbitration in accordance with the substantive law

for the time being in force in India;”

(b) a contravention of the Arbitration Act itself would be regarded as a patent

illegality- for example if an arbitrator gives no reasons for an award in

contravention of section 31(3) of the Act, such award will be liable to be set

aside.

(c) Equally, the third sub-head of patent illegality is really a contravention of

Section 28 (3) of the Arbitration Act, which reads as under:

“28. Rules applicable to substance of dispute.— (3) In all cases,

the arbitral tribunal shall decide in accordance with the terms of

the contract and shall take into account the usages of the trade

applicable to the transaction.”

This last contravention must be understood with a caveat. An arbitral

tribunal must decide in accordance with the terms of the contract, but if an

arbitrator construes a term of the contract in a reasonable manner, it will not

mean that the award can be set aside on this ground. Construction of the terms

of a contract is primarily for an arbitrator to decide unless the arbitrator

construes the contract in such a way that it could be said to be something that

no fair minded or reasonable person could do.

In McDermott International Inc. v. Burn Standard Co. Ltd., (2006)

11 SCC 181, this Court held as under:

32

Page 33 “112. It is trite that the terms of the contract can be express or

implied. The conduct of the parties would also be a relevant

factor in the matter of construction of a contract. The

construction of the contract agreement is within the jurisdiction of

the arbitrators having regard to the wide nature, scope and ambit

of the arbitration agreement and they cannot be said to have

misdirected themselves in passing the award by taking into

consideration the conduct of the parties. It is also trite that

correspondences exchanged by the parties are required to be

taken into consideration for the purpose of construction of a

contract. Interpretation of a contract is a matter for the arbitrator

to determine, even if it gives rise to determination of a question of

law. (See Pure Helium India (P) Ltd. v. ONGC [(2003) 8 SCC

593] and D.D. Sharma v. Union of India [(2004) 5 SCC 325]).

113. Once, thus, it is held that the arbitrator had the jurisdiction,

no further question shall be raised and the court will not exercise

its jurisdiction unless it is found that there exists any bar on the

face of the award.”

In MSK Projects (I) (JV) Ltd. v. State of Rajasthan, (2011) 10 SCC

573, the Court held:

“17. If the arbitrator commits an error in the construction of the

contract, that is an error within his jurisdiction. But if he wanders

outside the contract and deals with matters not allotted to him, he

commits a jurisdictional error. Extrinsic evidence is admissible in

such cases because the dispute is not something which arises

under or in relation to the contract or dependent on the

construction of the contract or to be determined within the award.

The ambiguity of the award can, in such cases, be resolved by

admitting extrinsic evidence. The rationale of this rule is that the

nature of the dispute is something which has to be determined

outside and independent of what appears in the award. Such a

jurisdictional error needs to be proved by evidence extrinsic to the

award. (See Gobardhan Das v. Lachhmi Ram [AIR 1954 SC 689],

Thawardas Pherumal v. Union of India [AIR 1955 SC 468],

Union of India v. Kishorilal Gupta & Bros. [AIR 1959 SC 1362],

Alopi Parshad & Sons Ltd. v. Union of India [AIR 1960 SC 588],

Jivarajbhai Ujamshi Sheth v. Chintamanrao Balaji [AIR 1965 SC

214] and Renusagar Power Co. Ltd. v. General Electric

Co. [(1984) 4 SCC 679 : AIR 1985 SC 1156] ).”

33

Page 34 In Rashtriya Ispat Nigam Ltd. v. Dewan Chand Ram Saran, (2012) 5

SCC 306, the Court held:

“43. In any case, assuming that Clause 9.3 was capable of two

interpretations, the view taken by the arbitrator was clearly a

possible if not a plausible one. It is not possible to say that the

arbitrator had travelled outside his jurisdiction, or that the view

taken by him was against the terms of contract. That being the

position, the High Court had no reason to interfere with the

award and substitute its view in place of the interpretation

accepted by the arbitrator.

44. The legal position in this behalf has been summarised in para

18 of the judgment of this Court in SAIL v. Gupta Brother Steel

Tubes Ltd. [(2009) 10 SCC 63: (2009) 4 SCC (Civ) 16] and which

has been referred to above. Similar view has been taken later

in Sumitomo Heavy Industries Ltd. v. ONGC Ltd. [(2010) 11 SCC

296: (2010) 4 SCC (Civ) 459] to which one of us (Gokhale, J.)

was a party. The observations in para 43 thereof are instructive in

this behalf.

45. This para 43 reads as follows: (Sumitomo case [(2010) 11

SCC 296 : (2010) 4 SCC (Civ) 459] , SCC p. 313)

“43. … The umpire has considered the fact situation and

placed a construction on the clauses of the agreement

which according to him was the correct one. One may at

the highest say that one would have preferred another

construction of Clause 17.3 but that cannot make the

award in any way perverse. Nor can one substitute one's

own view in such a situation, in place of the one taken

by the umpire, which would amount to sitting in appeal.

As held by this Court in Kwality Mfg. Corpn. v. Central

Warehousing Corpn. [(2009) 5 SCC 142 : (2009) 2 SCC

(Civ) 406] the Court while considering challenge to

arbitral award does not sit in appeal over the findings

and decision of the arbitrator, which is what the High

Court has practically done in this matter. The umpire is

legitimately entitled to take the view which he holds to

be the correct one after considering the material before

him and after interpreting the provisions of the

34

Page 35 agreement. If he does so, the decision of the umpire has

to be accepted as final and binding.”

13.Applying the tests laid down by this Court, we have to examine whether

the Division Bench has exceeded its jurisdiction in setting aside the arbitral

award impugned before it.

14.A large part of the judgment is an extract from the arbitral award. It is

important to note that the Division Bench held:

“9. A perusal of the award would reveal, from the portions

extracted herein above, that with reference to evidence led before

him the learned Arbitrator has held delay attributable to DDA, a

finding of fact which is based on evidence and rightly conceded to

by Sh. Bhupesh Narula, Advocate who appears for DDA as being

beyond judicial review power of this Court pertaining to a

reasoned award. But, while awarding Rs.8,27,960/- the reasoning

adopted by the learned Arbitrator is questioned as being the result

of ignoring the well-recognized legal principles on the subject,

Learned counsel argued that the reasoning is the ipse dixit of the

learned Arbitrator.”

15.The Division Bench while considering claims 9, 10, 11 and 15 found

fault with the application of Hudson’s formula which was set out by the

learned Arbitrator in order to arrive at the claim made under these heads. The

Division Bench said that it was not possible for an Arbitrator to mechanically

apply a certain formula however well understood in the trade. This itself is

going outside the jurisdiction to set aside an award under Section 34 in as

much as in McDermott’s case (supra), it was held:

35

Page 36 “104. It is not in dispute that MII had examined one Mr D.J.

Parson to prove the said claim. The said witness calculated the

increased overheads and loss of profit on the basis of the formula

laid down in a manual published by the Mechanical Contractors

Association of America entitled “Change Orders, Overtime,

Productivity” commonly known as the Emden Formula. The said

formula is said to be widely accepted in construction contracts for

computing increased overheads and loss of profit. Mr D.J. Parson

is said to have brought out the additional project management

cost at US$ 1,109,500. We may at this juncture notice the different

formulas applicable in this behalf.

(a) Hudson Formula: In Hudson's Building and Engineering

Contracts, Hudson Formula is stated in the following terms:

“Contract head

office overhead

and profit

percentage

× Contract

sum

Contract

period

× Period

of

delay”

In the Hudson Formula, the head office overhead percentage is

taken from the contract. Although the Hudson Formula has

received judicial support in many cases, it has been criticised

principally because it adopts the head office overhead percentage

from the contract as the factor for calculating the costs, and this

may bear little or no relation to the actual head office costs of the

contractor.

(b) Emden Formula: In Emden's Building Contracts and Practice,

the Emden Formula is stated in the following terms:

“Head office

overhead and

profit

× Contract

sum

× Period

of

delay”

100 Contract

period

Using the Emden Formula, the head office overhead percentage is

arrived at by dividing the total overhead cost and profit of the

contractor's organisation as a whole by the total turnover. This

formula has the advantage of using the contractor's actual head

office overhead and profit percentage rather than those contained

in the contract. This formula has been widely applied and has

received judicial support in a number of cases including Norwest

36

Page 37 Holst Construction Ltd. v. Coop. Wholesale Society Ltd. [Decided

on 17-2-1998, [1998] EWHC Technology 339], Beechwood

Development Co. (Scotland) Ltd. v. Mitchell [ Decided on 21-2-

2001, (2001) CILL 1727] and Harvey Shopfitters Ltd. v. Adi Ltd. [

Decided on 6-3-2003, (2004) 2 All ER 982 : [2003] EWCA Civ

1757].

(c) Eichleay Formula: The Eichleay Formula was evolved in

America and derives its name from a case heard by the Armed

Services Board of Contract Appeals, Eichleay Corporation. It is

applied in the following manner:

Step 1

Contract

billings

× Total

overhead

for

contract

period

= Overhead

allocable

to the

contract

Total

billings for

contract

period

Step 2

Allocable overhead = Daily overhead rate

Total days of contract

Step 3

Daily

contract

overhead

rate

× Number

of days

of delay

= Amount of

unabsorbed

overhead”

This formula is used where it is not possible to prove loss of

opportunity and the claim is based on actual cost. It can be seen

from the formula that the total head office overhead during the

contract period is first determined by comparing the value of

work carried out in the contract period for the project with the

value of work carried out by the contractor as a whole for the

contract period. A share of head office overheads for the

contractor is allocated in the same ratio and expressed as a lump

sum to the particular contract. The amount of head office

overhead allocated to the particular contract is then expressed as

37

Page 38 a weekly amount by dividing it by the contract period. The period

of delay is then multiplied by the weekly amount to give the total

sum claimed. The Eichleay Formula is regarded by the Federal

Circuit Courts of America as the exclusive means for

compensating a contractor for overhead expenses.

105. Before us several American decisions have been referred to

by Mr. Dipankar Gupta in aid of his submission that the Emden

Formula has since been widely accepted by the American courts

being Nicon Inc. v. United States [ Decided on 10-6-2003 (USCA

Fed Cir), 331 F. 3d 878 (Fed. Cir. 2003)], Gladwynne

Construction Co. v. Mayor and City Council of

Baltimore [Decided on 25-9-2002, 807 A. 2d 1141 (2002) : 147

Md. App. 149] and Charles G. William Construction

Inc. v. White [271 F 3d 1055 (Fed. Cir. 2001)].

106. We do not intend to delve deep into the matter as it is an

accepted position that different formulae can be applied in

different circumstances and the question as to whether damages

should be computed by taking recourse to one or the other

formula, having regard to the facts and circumstances of a

particular case, would eminently fall within the domain of the

arbitrator.”

16.Obviously, the Division Bench has exceeded its jurisdiction in

interfering with a possible view of the Arbitrator on facts.

17.The Division Bench then went on to hold:

“17. There is admittedly no evidence that the contractor i.e. the

respondent had a central establishment. It appears to be a case

where the contractor is petty contractor and the only expenses

incurred are at the site. The claim is towards hire charges paid

for centering and shuttering, hiring tools, plants and scaffoldings

i.e. the claim is not for the contractor’s own equipment lying idle.

There is just no evidence that the contractor paid charges as

claimed by him. Not a single bill raised by the alleged person who

let on hire the equipment to the contractor has been filed nor any

evidence adduced for the payment made. Except for listing a 10

HP Water Pump, 4 number 1 HP water pump, 3 mixers, 250

scaffolding bamboos, 150 ballis and 2 vibrators in Annexure-J to

the Statement of Claim, no document proving hiring the same and

38

Page 39 brought at the site has been led. We highlight that the claim is on

account of hire Charges paid and there is no evidence of said

payment. It does happen that where a work is stopped, the person

who taken an equipment on hire returns the same and re-hires the

same when work recommences. Thus, Claim No. 9, 10 and 11

cannot be allowed because there is no evidence to support the

claims. Damages on account of establishment expenses incurred

during period contract got prolonged have certainly to be

recompensed, but we find no evidence in the form of books of

accounts, vouchers etc. to show payments to the staff or expenses

incurred in maintaining an establishment at site in the form of a

site office. The wages register, photocopy whereof was filed before

the Arbitrator, pertains to wages paid to the unskilled, semi-

skilled and skilled labour deployed to execute the works. The

pleadings pertaining to the claim would show that as per the

contractor he had deployed one Executive Officer, one Graduate

Engineer, one Junior Engineer, one Accountant, one Storekeeper

and Supervisor and one Mechanic at the site and had also

deployed watch and ward. Details of the persons employed have

been listed in Annexure-N to the Statement of Claim and the

documents filed to establish the same would evidence that the

contractor has filed photocopies of the salary register, which are

available from pages No.1255 to 1322, but unfortunately for the

contractor, the cat is out of the bag when we look at the

documents. They pertain to payments made for a site at Mayur

Vihar. We highlight that the contract in question pertains to flats

and houses at Trilokpuri and not Mayur Vihar. It is apparent that

the contractor has tried to pull the wool on the eyes of the

primary adjudicator of the claim. It is not the case of the

contractor that these persons were simultaneously supervising the

work at two sites. Assuming this was the case, the matter would

then have been adjudicated with reference to same number of

persons supervising two sites and the time spent at each site by

them.

18. Thus, the award pertaining to Claim Nos. 9, 10, 11 and 15 is

liable to be sent aside and it is so set aside. We need not therefore

take corrective action on the apparent error i.e. the learned

Arbitrator has worked out the claim on the original contract value

of Rs. 87,66,678/-, of course by reducing it by 15%, but ignoring

that final work executed was only in sum of Rs.62,84,845/-.”

39

Page 40 18.Mr. Verma argued correctly that there is nothing on record to show that

the contractor is a petty contractor and that the only expenses incurred are at

the site. He has shown us that the contract itself required execution of the

work by a Class-I contractor and has further shown us that Class-I contractors

require to have certain stipulated numbers of works worth large amounts before

they can apply for the tender and that their financial soundness has to be

attested too by banker’s certificate showing that their worth is over 10 crores of

rupees. Further, he has pointed out from the statement of claims before the

Arbitrator that there was evidence for claims 9, 10 and 11 laid before the

Arbitrator which the Arbitrator has in fact accepted. Also establishment

expenses were set out in great detail before the Arbitrator and it is only on this

evidence that the Arbitrator ultimately has awarded these claims. Mr. Verma is

also right in saying that the Division Bench was completely wrong in stating

that the establishment expenses pertained to payments for a site at Mayur Vihar

as opposed to Trilok Puri which were where the aforesaid houses were to be

constructed. He pointed out that in the completion certificate dated 30

th

May,

1997 given by the DDA to the appellant, it is clear that the houses that were, in

fact, to be constructed were in Mayur Vihar, Phase-II, which is part of the

Trilok Puri trans-Yamuna area.

It is most unfortunate that the Division Bench did not advert to this

crucial document at all. This document shows not only that the Division

Bench was wholly incorrect in its conclusion that the contractor has tried to

40

Page 41 pull the wool over the eyes over the DDA but it should also have realized that

the DDA itself has stated that the work has been carried out generally to its

satisfaction barring some extremely minor defects which are capable of

rectification. It is clear, therefore, that the Division Bench obviously exceeded

its jurisdiction in interfering with a pure finding of fact forgetting that the

Arbitrator is the sole Judge of the quantity and quality of evidence before him

and unnecessarily bringing in facts which were neither pleaded nor proved and

ignoring the vital completion certificate granted by the DDA itself. The

Division Bench also went wrong in stating that as the work completed was

only to the extent of Rs. 62,84,845/-, Hudson’s formula should have been

applied taking this figure into account and not the entire contract value of

Rs.87,66,678/- into account.

19.Here again, the Division Bench has committed a grave error. Hudson’s

formula as is quoted in McDermott’s case is as follows:

“(a) Hudson Formula: In Hudson's Building and Engineering

Contracts, Hudson Formula is stated in the following terms:

“Contract head

office overhead

and profit

percentage

× Contract

sum

Contract

period

× Period

of

delay”

In the Hudson Formula, the head office overhead percentage is

taken from the contract. Although the Hudson Formula has

received judicial support in many cases, it has been criticised

principally because it adopts the head office overhead percentage

from the contract as the factor for calculating the costs, and this

may bear little or no relation to the actual head office costs of the

contractor.”

41

Page 42 20.It is clear that to apply this formula one has to take into account the

contract value that is awarded and not the work completed. On this score

again, the Division Bench is to be faulted.

21.In dealing with claims 12 and 13, the Division Bench stated:

“19. Pertaining to Claim No.12 and 13, the learned Arbitrator

has recompensed the contractor 20% price hike in the cost of

material and labour noting, that there was a steep hike in the

period in question when the contract got prolonged by 25 months.

We highlight that though the Arbitrator has found the delay to be

25 months, recompense has been restricted to only 20 months.

20. As noted herein above, partial recompense under Clause 10C,

has been granted to the contractor, but the same i.e. the Clause in

question requiring applicability during contract stipulated period,

it is apparent that the contractor would be entitled to full

recompense for price hike during the extended 25 months period

and not the 20 months to which the learned Arbitrator has

restricted the recompense to.

21.But, for the benefit granted under Clause 10C wherein Rs.

1,62,387/-, Rs.46,184/- and Rs.12,922/- have been awarded

under Claim Nos. 2, 3 and 4, said amounts have to be adjusted,

but not in full, for the reason these include the amounts payable

during the contract stipulated period.

22. The total of the three sums comes to Rs, 2, 21,493/-. We have

another problem. Neither counsel could help us identify the

components thereof i.e. the component relatable to the 9 months

during which the work had to be completed and the 25 months

during which the contract got prolonged. Thus, we apply the Rule

of ‘Rough and Ready Justice’. We divide the sum by 34 to work

out the proportionate increase per month. Rs. 2,21,493/- divided

by 34 = Rs.6,514.50 and multiplying the same by 25, the figure

comes to Rs.1,62,862.50.

23. Adopting, for the reasons given by the Arbitrator, that 20%

hike in the balance work done after the contract stipulated period

i.e. benefit to be granted under this head for work done in sum of

Rs.37,02,066/- and accepting the sum of Rs.7,20,000/- being the

42

Page 43 resultant figure, subtracting Rs.1,62,862.50, the figure arrived at

is Rs.5,57,137.50.”

22.Here again, the Division Bench has interfered wrongly with the arbitral

award on several counts. It had no business to enter into a pure question of

fact to set aside the Arbitrator for having applied a formula of 20 months

instead of 25 months. Though this would inure in favour of the appellant, it is

clear that the appellant did not file any cross objection on this score. Also, it is

extremely curious that the Division Bench found that an adjustment would

have to be made with claims awarded under claims 2, 3 and 4 which are

entirely separate and independent claims and have nothing to do with claims 12

and 13. The formula then applied by the Division Bench was that it would

itself do “rough and ready justice”. We are at a complete loss to understand

how this can be done by any court under the jurisdiction exercised under

Section 34 of the Arbitration Act. As has been held above, the expression

“justice” when it comes to setting aside an award under the public policy

ground can only mean that an award shocks the conscience of the court. It

cannot possibly include what the court thinks is unjust on the facts of a case for

which it then seeks to substitute its view for the Arbitrator’s view and does

what it considers to be “justice”. With great respect to the Division Bench, the

whole approach to setting aside arbitral awards is incorrect. The Division

Bench has lost sight of the fact that it is not a first appellate court and cannot

interfere with errors of fact.

43

Page 44 23.We come now to the arguments of Mr. Sharan in support of the Division

Bench judgment. The learned counsel strongly relied on clause 10C and clause

22. These two clauses are set out as below:

Clause 10C of the agreement reads as follows:

“If during the progress of the works, the price of any material

incorporated in the works, (not being a material supplied from the

Engineer-in-Charge's stores in accordance with Clause 10 hereof

and/or wages of labour increases as direct result of the coming

into force of any fresh law, or statutory rule or order (but not due

to any changes in sales tax) and such increase exceed ten per cent

of the price and/or wages prevailing at the time of receipt of the

tender for the work, and contractor thereupon necessarily and

properly pays in respect of the material (incorporated in the

work) such increased price and/or in respect of labour engaged

on the execution of the work such increased wages, then the

amount of the contract shall accordingly be varied provided

always that any increase so payable is not, in the opinion of the

Superintending Engineer (whose decision shall be final and

binding) attributable to delay in execution of the contract within

the control of the contractor. Provided, however, no

reimbursements shall be made if the increase is not more than

10% of the said prices/wages and if so the reimbursements shall

be made only on the excess over 10% and provided further that

any such increase shall not be payable if such increase has

become operative after the contract or extended date of

completion of the work in question.

If during the progress of the works, the price of any material

incorporated in the works (not being a material supplied from the

Engineer-in-Charge's stores in accordance with Clause 10 hereof)

and/or wages of labour is decreased as a direct result of the

coming into force of any fresh law or statutory rule or order (but

not due to any changes in sales tax) and such decrease exceeds

ten per cent of the prices and/or wages prevailing at the time of

receipt of the tender for the work, Delhi Development Authority

shall in respect of materials incorporated in the work (not being

materials supplied from the Engineer-in-Charge's stores in

accordance with Clause 10 hereof) and/or labour engaged on the

execution of the work after the date of coming into force of such

law, statutory rule or order be entitled to deduct from the dues of

44

Page 45 the contractor such amount as shall be equivalent of difference

between the prices of materials and/ or wages as they prevailed at

the time of receipt of tender for the work minus ten per cent

thereof and the prices of materials and/ or wages of labour on the

coming into force of such law, statutory rule or order.

The contractor shall for the purpose of this condition keep such

books of account and other documents as are necessary to show

the amount of any increase claimed or reduction available and

shall allow inspection of the same by a duly authorised

representative of Delhi Development Authority and further shall,

at the request of the Engineer-in-Charge furnish, verified in such

a manner as the Engineer-in-Charge may require. Any document,

so kept and such other information as the Engineer-in-Charge

may require.

The contractor shall, within a reasonable time of his becoming

aware of any alteration in the prices of any such materials and/ or

wages of labour give notice thereof to the Engineer-in- Charge

stating that the same is given in pursuance to the condition

together with all information relating thereto which he may be in

a position to supply.”

Clause 22 reads as follows:

“All sums payable by way of compensations under any of these

conditions shall be, considered as reasonable compensation to be

applied to this use of Delhi Development Authority without

reference to the actual loss or damage sustained, and whether or

not any damage shall have been sustained.

Specifications and Conditions:

1. The contractor must get acquainted with the proposed site for

the works and study specifications and conditions carefully before

tendering. The work shall be executed as per programme

approved by the Engineer-in-Charge. If part of site is not

available for any reasons or there is some unavoidable delay in

supply of materials stipulated by the Departments, the programme

of construction shall be modified accordingly and the contractor

shall have no claim for any extras or compensation on this

account.”

45

Page 46 24.Clause 10C concerns itself with the price of material incorporated in the

works or wage or labour increases. It has been seen that claims 9, 10 and 11

have nothing to do with either of the aforesaid subjects. In seeking to apply

this clause to claim 15, the simple answer is that this clause will not apply

when a claim for damages is made. Further, the Arbitrator considered this

clause in detail and only awarded amounts under this clause in excess of 10

percent as required by the clause when it came to awarding amounts under

claims 2, 3 and 4, which fell within the ambit of clause 10C. The DDA in the

appeal before the Division Bench correctly gave up any challenge to these

claims as has been recorded in paragraph 4 of the order under appeal.

25.The Arbitrator has dealt with this clause in detail and has construed and

applied the same correctly while dealing with claims 2, 3 and 4 and has

obviously not applied the said clause to claims 9, 10, 11 and 15 as no occasion

for applying the same arose. The award cannot be faulted on this ground.

26.Also, so far as clause 22 is concerned, the DDA did not raise any

argument based on this clause before the learned Arbitrator. However, it must

in fairness be stated that it was argued before the learned Single Judge. In para

15 of his judgment, the learned Judge sets the clause out and then follows a

judgment of the High Court of Delhi in Kochhar Construction Works v.

DDA & Anr., (1998) 2 Arb. LR 209. Apart from the fact that a learned Single

Judge of the same court is bound by a previous judgment of a Single Judge, the

conclusion of the learned Single Judge that if the appellant is at fault and the

46

Page 47 contract is prolonged for an inordinate period of time, it cannot be said that the

respondents cannot be compensated for the same is correct. Besides, this point

was not urged before the Division Bench and must be taken to be given up.

Mr. Sharan cited Harsha Constructions v. Union of India & Ors., (2014) 9

SCC 246 to say that in respect of excepted matters, no arbitration is possible,

and that this being a jurisdictional point, he should be allowed to raise it before

us. Unfortunately for Mr. Sharan, the clause does not operate automatically. It

only operates if an objection is taken stating that part of the site is not available

for any reason. Nowhere has the DDA stated which part of the site is not

available for any reason. Further, the learned Single Judge’s reason for

rejecting an argument based on this clause also commends itself to us as the

object of this clause is that no claim for extras should be granted only if there is

an unavoidable delay. We have seen that the delay was entirely avoidable and

caused solely by the DDA itself.

27.One more point needs to be noted. An argument was made before the

learned Single Judge that there has been a duplication of claims awarded. The

learned Judge dealt with this argument as follows:

“18. Learned counsel for the petitioner in respect of ground P,

once again makes a reference to the issue that there is

overlapping of the claim. I am unable to accept the submission

made by the learned counsel. The consequence of delay may have

more than one ramifications including the cost of material the

supervision required at the site, the inability of the contractor to

utilise the manpower at some other place, the inability of the

contractor to make, profits from some other contract by utilisation

of the same resources. All these aspects are liable to be

47

Page 48 considered. The Arbitrator has considered the claims separately

and has dealt with, claims 9, 10, 11 & 15 together. Claims 12 &

13 have been thereafter dealt with on the same principles since it

was found that it was not the respondent, who was responsible for

the delay for a period of 25 months beyond the stipulated

condition of 9 months.

19. There is thus no question of overlapping in different heads and

the grievance of the petitioner is rejected.”

28.The Single Judge is clearly right. We have gone through all the 15

claims supplied to us and we find that none of these claims are in fact

overlapping. They are all contained under separate heads. This argument,

therefore, must also fail.

29. The appeal is, therefore, allowed and the judgment of the Division Bench

is set aside. The judgment of the Single Judge is upheld and consequently, the

Arbitral award dated 23

rd

May, 2005 is as a whole upheld. There will be no

order as to costs.

..................................................J.

(Ranjan Gogoi)

………………………………..J.

(R.F. Nariman)

New Delhi,

November 25, 2014