Binodini Infrastructure Pvt. Ltd. Vs. State of Odisha

  Orissa High Court W.P.(C) No.8589 of 2024
Link copied!

Case Background

As per case facts, Binodini Infrastructure Pvt. Ltd. was blacklisted for six years by the Chief Engineer, Bridges (WBP), Odisha, for failing to complete two bridge construction projects within the ...

Bench

Applied Acts & Sections
Hello! How can I help you? 😊
Disclaimer: We do not store your data.
Document Text Version

W.P.(C) No.8589 of 2024 Page 1 of 89

ORISSA HIGH COURT : CUTTACK

W.P.(C) No.8589 of 2024

In the matter of an Application under Articles 226 & 227

of the Constitution of India, 1950.

***

Binodini Infrastructure Pvt. Ltd.

Registered Office

At: Bahadurbagichapada

Bhawanipatna

District: Kalahandi, Odisha

Represented through

Managing Director

(Being authorized by Board of Directors)

Sri Pradipta Kumar Singh

Aged about 48 years

Son of Late Nrusingha Charan Singh

At: Bahadurbagichapada

P.O./P.S.: Bhawanipatna

District: Kalahandi, Odisha. … Petitioner

-VERSUS-

1. State of Odisha

Represented through

Commissioner-cum- Secretary

Work Department, State Secretariat

Bhubaneswar, District: Khurda.

2. F.A.-cum-Special Secretary to Government

Works Department, Government of Odisha

State Secretariat, Bhubaneswar.

W.P.(C) No.8589 of 2024 Page 2 of 89

3. Engineer-in-Chief (Civil), Odisha

Bhubaneswar, District: Khordha.

4. Chief Engineer

Bridge World Bank Project, Odisha

Bhubaneswar, District: Khordha.

5. Chief Engineer, (DPI & Roads)

Works Department, Odisha

Bhubaneswar, District: Khordha.

6. Chief Construction Engineer

Jeypore (R & B ) Circle, Jeypore

7. Superintending Engineer

Malkanagiri (R & B) Division

Malkangiri. … Opposite Parties.

Advocates appeared in this case:

For the Petitioner : M/s. Prabodha Chandra Nayak,

S.K. Sahoo, Advocates

For the Opposite Parties : Mr. Saswat Das,

Additional Government Advocate

P R E S E N T:

HONOURABLE CHIEF JUSTICE

MR. HARISH TANDON

AND

HONOURABLE JUSTICE

MR. MURAHARI SRI RAMAN

Date of Hearing : 06.05.2026 :: Date of Judgment : 20.05.2026

JUDGMENT

W.P.(C) No.8589 of 2024 Page 3 of 89

MURAHARI SRI RAMAN, J.—

The petitioner, craving to question the propriety and

legality of order dated 30.03.2024 passed by the Chief

Engineer, Bridges (WBP), Odisha, blacklisting the

company for six years for having failed to achieve the

desired milestones as per agreement and complete the

works entrusted within period stipulated in terms of

conditions of contract, beseeches exercise of power

conferred on this Court under the provisions of Articles

226 and 227 of the Constitution of India for grant of

following relief(s):

“It is therefore prayed that this Hon‟ble Court may be

graciously pleased to issue rule NISI in the nature of any

appropriate writ/writs and/or any other writ/writs

and/or order/orders and/or direction/directions calling

upon the opposite parties to show cause as to why:

(i) The impugned order No.14974, dated 30.03.2024

under Annexure-1, passed by the opposite party

No.4 in blacklisting and debarring the petitioner to

participate in any tender for six years without

following due procedure shall not be declared illegal,

arbitrary and same shall not be quashed.

(ii) The action and decision of the opposite party No.4

under Annexure-1 in blacklisting the petitioner shall

not be declared illegal, arbitrary, unreasonable and

violative of Article 14 and 19(1)(g) of the Constitution

of India;

W.P.(C) No.8589 of 2024 Page 4 of 89

And may pass such other order(s)/direction(s) as this

Hon‟ble Court deems just and proper;

And for this act of kindness, the petitioner shall as in duty

bound ever pray.”

Facts:

2. The present case emanates from two work orders,

namely:

i. “Construction of H.L. Bridge over river Saberi, at

16/000 km of Mathili-Kaliguda road in Malkangiri

district” with stipulation to commence on

27.12.2017 and complete on 26.06.2019 vide

Agreement No.45P-1/2017-18 (hereinafter be

referred to as “Work No.1”).

ii. Bid identification No.58/2016-17 for the work

“Construction of H.L. Bridge over river Satpadhara,

at km 2/000 of Govindapalli-Kamalapadar-

Gajaguda road in Malkangiri district under State

Plan” with stipulation to commence on 28.11.2017

and complete on 27.02.2019 vide Agreement

No.33P-1/2017-18 (hereinafter be referred to as

“Work No.2”).

2.1. Due to unforeseen circumstances, the petitioner could

not complete the Work No.2 in time and upon

consideration of request, extension of time was allowed

up to 30.06.2020. Yet no substantial work being shown

W.P.(C) No.8589 of 2024 Page 5 of 89

to have been progressed, vide Letter No.3079, dated

25.06.2021 issued by the Executive Engineer,

Malkangiri (R&B) Division while granting period to

complete the work by 31.03.2022, the petitioner was

instructed to show cause failing which action would be

initiated for rescission of the agreement.

2.2. After furnishing replies eliciting the difficulties faced by

the petitioner and it is brought to the notice of the Chief

Engineer (World Bank Projects), Bhubaneswar by Letter

dated 10.05.2023 that though super structure drawing

was approved in Directorate of Design on 30.11.2022,

the same was not communicated to the petitioner. In the

said letter the authority was requested to allow the

petitioner to execute the balance work and release the

escalation cost up to 30.06.2020. Notwithstanding such

reply, the Works Department intimated the Chief

Engineer, World Bank Projects regarding approval of

rescission proposal of contract in terms of Clause 2(b)(i)

1

of Agreement No.33P1 of 2017-18. Consequent upon

such communication, an Office Order dated 23.08.2023

was issued by the Superintending Engineer, Malkangiri

(R&B) Division which reads as follows:

“The contract bearing No.33P1/2017-18 for the work

„Construction of HL Bridge over river Saptadhara at km

1

“To rescind the contract (of which rescission notice in writing to the contractor

under the hand of the Executive Engineer shall be conclusive evidence) 20% of the

value of left-over work will be realized from the contractor as penalty.”

W.P.(C) No.8589 of 2024 Page 6 of 89

2/0 of Govindapalli-Kamalapadar-Gajiaguda road in

Malkangiri District under State Plan‟ has been rescinded

under Clause 2b(i) of the said P1 Agreement executed by

Binodini Infrastructure Pvt. Ltd. „Super‟ Class Contractor

vide Letter No.33086, dated 10.08.2023 of Chief Engineer

(World Bank Projects), Odisha, Bhubaneswar.”

2.3. Assailing such order of rescission of contract with

respect to Work No.2, the petitioner approached this

Court by way of filing an application registered as

W.P.(C) No.31693 of 2023, wherein vide order dated

29.09.2023 notice was issued and the matter was

directed to be listed along with W.P.(C) No.29863 of 2023

which related to Work No.1.

2.4. While the matter was sub judice, two show cause notices

on 18.10.2023 were issued with respect to above both

the works.

2.5. Show Cause Notice vide Letter No.C-II-MLK-05/2016—

44375, dated 18.10.2023 with respect to Work No.1 was

issued indicating as follows:

“Please take notice that you have been entrusted with the

work „Construction of H.L Bridge over river Saberi at

16.000 Km. of Mathili-Kaliaguda road in the district of

Malkangiri under state plan vide Agreement No.45-P1 of

2017-18 of the Executive Engineer, Malkangiri (R&B)

Division, Malkangiri with the date of commencement as

27.12.2017 and stipulated date of completion as

26.06.2019. You have not completed the said work till

W.P.(C) No.8589 of 2024 Page 7 of 89

rescission of contract by the Government in Works

Department vide Letter No.13148, dated 08.08.2023.

***

Further on the final notice of the Superintending Engineer,

Malkangiri (R&B) Division vide Letter No.3139, dated

30.06.2021 where he has stated that on his inspection to

bridge site, no men and machineries were found in

execution of the bridge project and he has again

requested you to gear up the work in a war footing basis

by engaging sufficient men and machineries with

maximum working hour to complete back log quantities of

the work by 31.03.2022 otherwise suitable action as per

relevant clauses of the agreement will be initiated for

rescission of the agreement. But no such initiative was

found to be taken by you. Hence, it is apprehended that

due to your such type of apathetic attitude and deliberate

negligence the above work couldn‟t have been completed

till date and could not be put to use of General Public.

In view of the above factual matrix, you are hereby

directed to submit your explanation within 15 days from

the date of issue of this show cause notice why suitable

action shall not be taken by the undersigned under

Appendix-XXXIV of Odisha Public Works Department

Code, Volume-II and under Clause No.121 of the DTCN,

failing which it is to be deemed that you have nothing to

reply against this show cause and accordingly the action

as deemed proper will be processed against you without

any further intimation.”

2.6. Show Cause Notice vide Letter No.C-II-MLK-05/2016—

44374, dated 18.10.2023 with respect to Work No.2 was

issued indicating as follows:

W.P.(C) No.8589 of 2024 Page 8 of 89

“Please take notice that you have been entrusted with the

work „Construction of HL Bridge over river Saptadhara at

2.00km of Govindapalli-Kamalapadar-Gujiaguda road in

the district of Malkangiri under State plan vide Agreement

No.33P1 of 2017-18 executed by the Executive Engineer,

Malkangiri (R&B) Division, Malkangiri with the date of

commencement as 28.11.2017 and stipulated date of

completion as 27.02.2019. You have not completed the

said work till rescission of contract by the Government in

Works Department vide Letter No.13147, dated

08.08.2023.

***

Though you have been allowed with the extension of time

up to 30.06.2020 vide Government in Works Department

Letter No.6805, dated 03.06.2020, the bridge work could

not be completed within the extended period also. The

Superintending Engineer, Malkangiri (R&B) Division vide

Letter No.3842, dated 26.08.2020 issued another show

cause notice to you regarding slow progress of work.

Neither you have expedited the work nor you have

applied for further extension of time to complete the said

work.

***

The Superintending Engineer, Malkanglri (R&B) Division

issued final notice vide Letter No.357, dated 25.01.2021

to you with a request to execute the back log quantities of

the work by engaging sufficient men and machineries

with maximum working hours as well as to achieve the

target for completion of the above project otherwise

suitable action as per relevant clauses of the agreement

will be initiated for rescission of the agreement. It proves

that due to your lack of interest and deliberate negligence

W.P.(C) No.8589 of 2024 Page 9 of 89

the above work couldn‟t be completed till date and could

not be put to use of General Public.

In view of the above factual matrix, you are hereby

directed to submit your explanation within 15 days from

the date of issue of this show cause notice why suitable

action shall not be taken by the undersigned under

Appendix-XXXIV of Odisha Public Works Department

Code, Volume-II and under Clause No.121 of the DTCN,

failing which it is to be deemed that you have nothing to

reply against this show cause and accordingly the action

as deemed proper will be processed against you without

any further intimation.”

2.7. Imposing penalty of Rs.74,96,518/- with respect to Work

No.2 a demand has been raised vide Letter No.4815,

dated 26.10.2023 by the Superintending Engineer,

Malkangiri (R&B) Division with instruction to deposit

balance penalty to the tune of Rs.10,52,210/- after

adjustment of amounts due on account of earnest

money deposit, initial security deposit, security deposit,

withheld for extension of time and value of work

executed as per final/joint measurement for payment.

2.8. By Letter Nos.BIPL/283/2023-24 (Work No.1) and

BIPL/282/2023-24 (Work No.2), dated 23.10.2023 citing

pendency of writ petitions being W.P.(C) No.29863 of

2023 and W.P.(C) No.31693 of 2023 the petitioner

objected to steps taken for blacklisting/debarring

exercising power under Appendix-XXXIV of the Odisha

Public Works Department Code, Volume-II (“OPWD

W.P.(C) No.8589 of 2024 Page 10 of 89

Code”, for brevity) read with Clause No.121 of the DTCN.

An affidavit dated 29.01.2024 was filed in W.P.(C)

No.31693 of 2023 before this Court with the following

undertaking:

“That the petitioner files this affidavit with undertaking to

complete the balance work, i.e., Construction of HL Bridge

over river Saptadhara at km 2/000 of Govindpalli-

Kamalapadar-Gajiaguda road in Malkangiri district under

State plan within a period of 8 months from the date of

order in terms of agreement and will not claim escalation

for the said period.”

2.9. The writ petition being W.P.(C) No.29863 of 2023

(relating to Work No.1) came to be disposed of on

01.03.2024 with the following observation:

“4. In the additional affidavit filed by the petitioner

dated 02.02.2024, at paragraph-3 the petitioner has

stated as follows:

„3. That, the petitioner files this present Affidavit

with an undertaking to complete the remaining

portion of the work “Construction of H.L. Bridge

over river Saberi at 16/000 of Mathili-Kaliguda

Road in Malkangiri district under State Plan”

within a stipulated period of eight (8) months

from the date of order in terms of agreement

and hence shall not claim escalation for the

said period.

***

6. In view of the above, this writ petition stands

disposed of directing the opposite parties to

W.P.(C) No.8589 of 2024 Page 11 of 89

permit the petitioner to complete the work

within the period of eight months as indicated

in paragraph-3 of the affidavit dated

02.02.2024.”

2.10. Assailing the order dated 01.03.2024, the State of

Odisha moved the Hon’ble Supreme Court of India in

S.L.P.(Civil) No.14142 of 2024 [Civil Appeal No.7085 of

2025], wherein the following order was passed on

14.05.2025:

“Leave granted.

The issue involved in the present appeal is covered by the

decision in State of Odisha & Ors. Vrs. Binodini

Infrastructure Pvt. Ltd.-[Civil Appeal No.5228 of 2025]

2

dated 15.04.2025, wherein the following order was

passed:

„After hearing learned counsel appearing for the parties,

we find that the directions as contained in paragraph 3 of

the impugned order could not possibly have been issued

by the High Court as the same would fall in the domain of

re-writing the terms of contract. The challenge before the

High Court in the Writ Petition was to an order vide which

the contract granted to the respondent was rescinded.

The High Court had travelled beyond the prayer made in

the Writ Petition. Instead of going through the validity of

the order impugned, the High Court granted further time

to the respondent to complete the contract, which was not

2

Vide Special Leave to Appeal (C) No(s). 1479 of 2025 [Arising out of order dated

12.01.2024 in WP(C) No.37679 of 2023 passed by the High Court of Orissa at

Cuttack in the case of Binodini Infrastructre Pvt. Ltd., Kalahandi Vrs. State of

Odisha].

W.P.(C) No.8589 of 2024 Page 12 of 89

within the domain of the High Court in exercise of the

power under Article 226 of the Constitution of India.

For the reasons mentioned above, the impugned order

passed by the High Court is set aside. However, the legal

issues raised by the appellant in the Writ Petition having

not been gone into by the High Court, we remit the matter

to the High Court for examination thereof. All the

arguments by both the parties are left open.‟

In view of the above order, the impugned order stands set

aside and the matter stands remitted to the High Court,

for examination of the issues therein.

The appeal stands allowed accordingly.”

2.11. So far as writ petition being W.P.(C) No.31693 of 2023

relating to Work No.2 is concerned, counter affidavit has

been filed by the opposite parties, copy of which was

served on the counsel for the petitioner on 11.03.2024.

2.12. Thus, both the writ petitions are now pending before this

Court.

2.13. It is submitted by the petitioner that the blacklisting

order dated 30.03.2024 for six years is arbitrary and

contrary to the Codal Provisions contained in sub-rule

(c) of Rule A of Appendix-XXXIV of the OPWD Code read

with Works Department Office Memorandum

No.16131/W, dated 26.11.2021. While the writ petition,

being W.P.(C) No.31693 of 2023 relating to Work No.2 is

pending, the opposite parties in the counter affidavit

filed therein took a stand that the petitioner had not

W.P.(C) No.8589 of 2024 Page 13 of 89

assured nor applied for extension of time seeking to

complete the balance work of the bridge. Without taking

cognizance of the fact that the petitioner did furnish

affidavit before this Court showing its inclination to

complete the Work No.2 “within eight months from the

date of order in terms of the agreement”, such stand is

not in consonance with the order dated 02.02.2024

passed by this Court in the said writ petition, which

reads as follows:

“2. An additional affidavit dated 29.01.2024 has been

filed by the petitioner undertaking to complete the

work in question within a period of eight months

from the date of order in terms of the agreement. To

that effect, Mr. P.P. Mohanty, learned Additional

Government Advocate for the State-Opposite Parties

seeks time to obtain instructions.”

2.14. Further submission is made by the petitioner that

though this Court by order dated 01.03.2024 passed in

W.P.(C) No.29863 of 2023 relating to Work No.1 taking

similar affidavit furnished in the said case into

consideration directed the opposite parties to permit the

petitioner to complete the work within the period

mentioned therein.

2.15. Objecting to continuance of blacklisting order, it is

submitted that in view of order dated 02.02.2024 passed

by this Court in the writ petition being W.P.(C) No.31693

of 2023 relating to Work No.2 the impugned order vide

W.P.(C) No.8589 of 2024 Page 14 of 89

Annexure-1 is liable to be quashed being arbitrary and

illegal.

Counter affidavit of the opposite parties:

3. The Superintending Engineer having issued notices on

very many occasions requested the petitioner to

complete the work and thereby given opportunities to

complete the work within the period extended. On

inspection of the site by the authority as no men and

machineries were found, steps were taken.

3.1. Perceiving poor performance of the petitioner, who

showed indifference to complete the works, the authority

rescinded the contracts, and on receiving instruction

from the Chief Construction Engineer, Jeypore (R&B)

Circle in Letter No.5368, dated 13.10.2023, the Chief

Engineer (WBP) issued Show Cause Notice Nos.44374

and 44375, dated 18.10.2023 (Annexure-11 enclosed

with the writ petition) contemplating action as per

Clause 121 of the DTCN in terms of Appendix-XXXIV of

the OPWD Code.

3.2. It is highlighted that challenging the decision to rescind

the contracts with respect to Work Nos.1 and 2, the

petitioner filed writ petitions being W.P.(C) Nos.29863 of

2023 and 31693 of 2023 and requested the authority

concerned not to take step with respect to blacklisting.

Nonetheless, questioning the legality of order dated

W.P.(C) No.8589 of 2024 Page 15 of 89

01.03.2024 passed in W.P.(C) No.29863 of 2023, the

opposite parties approached the Hon’ble Supreme Court

of India in SLP(C) No.14142 of 2024, wherein by order

dated 15.07.2024 stay of operation of said order of this

Court was granted. Nevertheless, in W.P.(C) No.31693 of

2023 counter affidavit has been filed by the opposite

parties.

3.3. With technical details, it is submitted by the opposite

parties that the petitioner could have completed the

work within the extended period as allowed by the

authority and thereby the ground citing non-completion

of works within the period stipulated, as sought to be

extended by the petitioner, has been denied. Referring to

many Show Cause Notices issued to the petitioner

granting liberty to accomplish the works, it is asserted

that the petitioner remained indolent and recalcitrant. It

is pertinent to quote the following reply found place in

the counter affidavit:

“12. That in reply to the averments made in Paragraph

Nos. 07 and 08 of the writ petition, it is humbly

submitted that due to abnormal delay in progress,

the petitioner had been requested from time to time

to expedite the progress of work. As on 09.07.2019,

the petitioner had left the approach road work in

haphazard position in which it was causing

inconvenience to the public. So, the petitioner had

been asked in written to complete the approach road

work. The petitioner could have completed the work

W.P.(C) No.8589 of 2024 Page 16 of 89

by 27.02.2019. The petitioner failed to submit the

testing report of test pile within stipulated period of

completion for which further drawing could not be

obtained from the authority concerned and also, the

petitioner had not deployed sufficient manpower

and machineries as required for the bridge work,

show-cause notices were issued to the Petitioner as

to why penal action as per Clause 2(b)(i) shall not be

initiated against it. In spite of the Show Cause

notices, as to why the contracts in question shall not

be terminated for causing the delay in completing

the work, the petitioner had neither attended at

work site of bridge properly nor responded to the

communication made by the Executive Engineer vide

his Letter dated 09.07.2019 and 15.07.2019 and

failed to complete the bridge work.

***

16. That the averments made in Paragraph No.12 of the

writ petition are disputed and denied. It is humbly

submitted that the original time period was 15

months (01 year 03 months) to complete the total

bridge work. Basing on Letter dated 14.12.2021 of

the petitioner, the petitioner had already lost more

than 04 years since date of commencement of bridge

work i.e. 28.11.2017, but pile integrity test and pile

dynamic test over the river had not attended to

complete it, in which other drawings could not be

obtained from the authority concerned in absence of

above report. After lapses of maximum time period,

the petitioner had able to submit the Dynamic Test

Report in 02 (two) phases i.e on 21.12.2021 for

Abutment and 23.03.2022 for Piers. Basing on

above report, the final drawing and design dated

W.P.(C) No.8589 of 2024 Page 17 of 89

30.11.2022 was provided to the site engineer of the

petitioner for execution of work. Still then the

petitioner had not started that work. From time to

time the petitioner had been reminded to start the

work otherwise suitable action will be initiated for

rescission of the agreement.”

3.4. The opposite parties stuck to the action taken by the

opposite parties and sought for dismissal of the writ

petition.

Hearing:

4. As the blacklisting order poses “civil death” of the

petitioner’s business activities and the same debars it

from participating in tenders, urgency in the matter

being shown, the matter is taken up for hearing.

4.1. The pleadings being completed, heard Sri Prabodha

Chandra Nayak, learned Advocate for the petitioner; Sri

Saswat Das, learned Additional Government Advocate

for the opposite parties. Written note of submissions has

been filed by the counsel for respective parties on

06.05.2026.

4.2. Being directed to list the matter for “orders”, the matter

being listed, the Judgment is pronounced.

Rival contentions and submissions with written note of

submissions:

W.P.(C) No.8589 of 2024 Page 18 of 89

5. With the above background of factual scenario, though

the matters challenging propriety of decision taken for

rescinding the works in question are pending

adjudication, Sri Prabodha Chandra Nayak, learned

Advocate, insisted for hearing of the matter relating to

debarring the petitioner from participating in tenders by

contending that where certain things are required to be

done in certain way, the same must be done in that

manner, but not otherwise as other methods are

necessarily forbidden inasmuch as the authorities have

not adhered to the Codal Provisions in proper

perspective. He relied on following dictum in Avtar Singh

Vrs. State of Punjab, (2023) 18 SCC 717:

“15. It is a settled law that where a power is given to do

a certain thing in a certain way, the thing must be

done in that way or not at all. Other methods are

necessarily forbidden. Reference can be made to

Dharani Sugars & Chemicals Ltd. Vrs. Union of

India, (2019) 5 SCC 480.”

5.1. It is with vehemence argued that the reasons ascribed

for the conclusion arrived at by the Chief Engineer,

Bridges (WBP), Odisha, vide order dated 30.03.2024 to

blacklist the petitioner are vague and incoherent with

the grounds enshrined in Rule A of Appendix-XXXIV to

the OPWD Code.

5.2. It is canvassed before this Court that mere rescission of

contracts does not contemplate step to be taken for

W.P.(C) No.8589 of 2024 Page 19 of 89

debarment/blacklisting the contractor under the said

Code. The authority prior to taking a decision to

blacklist the petitioner ought to have conducted enquiry

and ought to make specific fact-finding that the

ground(s) existed warranting order to be passed for

blacklisting. Without granting reasonable, fair and

meaningful opportunity of hearing to the petitioner the

impugned order vide Annexure-1, being illegal,

whimsical and arbitrary, is liable to be quashed”.

5.3. The learned Advocate for the petitioner referred to and

relied on the following decisions to countenance his

argument that the authority prior to action proposed

should mention specifically and unambiguously the

grounds:

i. Erusian Equipment and Chemicals Ltd. Vrs. State of

West Bengal, (1975) 1 SCC 70, wherein it has been

observed as follows:

“12. Under Article 298 of the Constitution the

executive power of the Union and the State

shall extend to the carrying on of any trade

and to the acquisition, holding and disposal of

property and the making of contracts for any

purpose. The State can carry on executive

function by making a law or without making a

law. The exercise of such powers and functions

in trade by the State is subject to Part III of the

Constitution. Article 14 speaks of equality

W.P.(C) No.8589 of 2024 Page 20 of 89

before the law and equal protection of the

laws. Equality of opportunity should apply to

matters of public contracts. The State has the

right to trade. The State has there the duty to

observe equality. An ordinary individual can

choose not to deal with any person. The

Government cannot choose to exclude persons

by discrimination. The order of blacklisting

has the effect of depriving a person of

equality of opportunity in the matter of

public contract. A person who is on the

approved list is unable to enter into

advantageous relations with the Government

because of the order of blacklisting. A person

who has been dealing with the Government in

the matter of sale and purchase of materials

has a legitimate interest or expectation. When

the State acts to the prejudice of a person

it has to be supported by legality.

***

15. The blacklisting order does not pertain to any

particular contract. The blacklisting order

involves civil consequences. It casts a slur.

It creates a barrier between the persons

blacklisted and the Government in the

matter of transactions. The blacklists are

“instruments of coercion”.

16. In passing an order of blacklisting the

government department acts under what is

described as a standardised Code. This is a

code for internal instruction.

***

W.P.(C) No.8589 of 2024 Page 21 of 89

19. Where the State is dealing with individuals in

transactions of sales and purchase of goods,

the two important factors are that an individual

is entitled to trade with the Government and an

individual is entitled to a fair and equal

treatment with others. A duty to act fairly

can be interpreted as meaning a duty to

observe certain aspects of rules of natural

justice. A body may be under a duty to give

fair consideration to the facts and to consider

the representations but not to disclose to those

persons details of information in its

possession. Sometimes duty to act fairly can

also be sustained without providing

opportunity for an oral hearing. It will depend

upon the nature of the interest to be affected,

the circumstances in which a power is

exercised and the nature of sanctions involved

therein.

***

20. Blacklisting has the effect of preventing a

person from the privilege and advantage

of entering into lawful relationship with

the Government for purposes of gains. The

fact that a disability is created by the order of

blacklisting indicates that the relevant

authority is to have an objective satisfaction.

Fundamentals of fair play require that the

person concerned should be given an

opportunity to represent his case before

he is put on the blacklist.”

W.P.(C) No.8589 of 2024 Page 22 of 89

ii. UMC Technologies Private Limited Vrs. Food

Corporation of India, (2021) 2 SCC 551, wherein the

following is the observation:

“13. At the outset, it must be noted that it is

the first principle of civilised

jurisprudence that a person against whom

any action is sought to be taken or whose

right or interests are being affected

should be given a reasonable opportunity

to defend himself. The basic principle of

natural justice is that before adjudication

starts, the authority concerned should

give to the affected party a notice of the

case against him so that he can defend

himself. Such notice should be adequate

and the grounds necessitating action and

the penalty/action proposed should be

mentioned specifically and

unambiguously. An order travelling

beyond the bounds of notice is

impermissible and without jurisdiction to

that extent. This Court in Nasir Ahmad Vrs.

Custodian General, Evacuee Property, (1980) 3

SCC 1 has held that it is essential for the

notice to specify the particular grounds on the

basis of which an action is proposed to be

taken so as to enable the noticee to answer the

case against him. If these conditions are not

satisfied, the person cannot be said to have

been granted any reasonable opportunity of

being heard.

W.P.(C) No.8589 of 2024 Page 23 of 89

14. Specifically, in the context of blacklisting

of a person or an entity by the State or a

State Corporation, the requirement of a

valid, particularised and unambiguous

show-cause notice is particularly crucial

due to the severe consequences of

blacklisting and the stigmatisation that

accrues to the person/entity being

blacklisted. Here, it may be gainful to

describe the concept of blacklisting and the

graveness of the consequences occasioned by

it. Blacklisting has the effect of denying a

person or an entity the privileged opportunity of

entering into Government contracts. This

privilege arises because it is the State who is

the counterparty in Government contracts and

as such, every eligible person is to be afforded

an equal opportunity to participate in such

contracts, without arbitrariness and

discrimination. Not only does blacklisting

take away this privilege, it also tarnishes

the blacklisted person’s reputation and

brings the person ’s character into

question. Blacklisting also has long-

lasting civil consequences for the future

business prospects of the blacklisted

person.

15. In the present case as well, the appellant has

submitted that serious prejudice has been

caused to it due to the Corporation's order of

blacklisting as several other government

corporations have now terminated their

contracts with the appellant and/or prevented

the appellant from participating in future

W.P.(C) No.8589 of 2024 Page 24 of 89

tenders even though the impugned blacklisting

order was, in fact, limited to the Corporation's

Madhya Pradesh regional office. This domino

effect, which can effectively lead to the

civil death of a person, shows that the

consequences of blacklisting travel far

beyond the dealings of the blacklisted

person with one particular Government

Corporation and in view thereof, this

Court has consistently prescribed strict

adherence to principles of natural justice

whenever an entity is sought to be

blacklisted.

***

21. Thus, from the above discussion, a clear legal

position emerges that for a Show-Cause

Notice to constitute the valid basis of a

blacklisting order, such notice must spell

out clearly, or its contents be such that it

can be clearly inferred therefrom, that

there is intention on the part of the issuer

of the notice to blacklist the noticee. Such

a clear notice is essential for ensuring that the

person against whom the penalty of

blacklisting is intended to be imposed, has an

adequate, informed and meaningful

opportunity to show cause against his possible

blacklisting.”

5.4. Advancing further his argument, Sri Prabodha Chandra

Nayak, learned counsel would submit that the Codal

Provisions for blacklisting contractors in sub-rule (c) of

Rule A of Appendix-XXXIV appended to the OPWD Code

W.P.(C) No.8589 of 2024 Page 25 of 89

envisages two aspects, namely (i) Constant non-

achievement of milestones on insufficient and imaginary

grounds; and (ii) non-adherence to quality specifications

despite being pointed out conjoined. Both the aspects

together would form part of one ground. In the present

case, only first two being pointed out by the authority

concerned, the decision taken by the Chief Engineer,

World Bank Projects, Odisha pursuant to Show Cause

Notices dated 18.10.2023 (Annexure-11) is inconsistent

with the Codal Provision; as such, the same suffers vice

of arbitrariness, caprice and fancies of the authority;

and the decision thereon is tainted with mechanical

application of mind. To buttress his argument that these

circumstances as envisaged in sub-rule (c) of Rule A of

Appendix-XXXIV do constitute single whole, he referred

to Sk. Ahmed Vrs. State of Telangana, (2021) 9 SCC 59,

wherein it was held that,

“19. This Court held that when the provisos (i) and (ii) are

separated by conjunctive word “and”, they have to

be read conjointly. The requirement of both the

proviso has to be satisfied to avail the benefit. Para

8 [in Hyderabad Asbestos Cement Products Vrs.

Union of India, (2000) 1 SCC 426] is as follows:

„8. The language of the rule is plain and simple. It

does not admit of any doubt in interpretation.

Provisos (i) and (ii) are separated by the use of

the conjunction “and”. They have to be read

conjointly. The requirement of both the provisos

W.P.(C) No.8589 of 2024 Page 26 of 89

has to be satisfied to avail the benefit. Clauses

(a) and (b) of proviso (ii) are separated by the

use of an “or” and there the availability of one

of the two alternatives would suffice. Inasmuch

as cement and asbestos fibre used by the

appellants in the manufacture of their finished

excisable goods are liable to duty under

different tariff items, the benefit of pro forma

credit extended by Rule 56-A cannot be availed

of by the appellants and has been rightly

denied by the authorities of the Department.‟

***”

5.5. Sri Prabodha Chandra Nayak, learned Advocate

arduously submitted that mere allegation of breach of

contractual obligations without anything more, per se,

does not invite such punitive action. He referred to

following observation of the Hon’ble Supreme Court of

India made in Techno Prints Vrs. Chhattisgarh Textbook

Corporation, (2025) 3 SCR 208:

“34. Plainly, if a contractor is to be visited with the

punitive measure of blacklisting on account of an

allegation that he has committed a breach of a

contract, the nature of his conduct must be so

deviant or aberrant so as to warrant such a punitive

measure. A mere allegation of breach of

contractual obligations without anything more,

per se, does not invite any such punitive

action.

35. Usually, while participating in a tender, the bidder is

required to furnish a statement undertaking that it

has not been blacklisted by any institution so far

W.P.(C) No.8589 of 2024 Page 27 of 89

and, if that is not the case, provide information of

such blacklisting. This serves as a record of the

bidder‟s previous experience which gives the

purchaser a fair picture of the bidder and the

conduct expected from it. Therefore, while the

debarment itself may not be permanent and

may only remain effective for a limited, pre-

determined period, its negative effect continues

to plague the business of the debarred entity

for a long period of time. As a result, it is

viewed as a punishment so grave, that it must

follow in the wake of an action that is equally

grave.

36. In the overall view of the matter more particularly in

the peculiar facts of the case, we have reached the

conclusion that asking the appellant herein to file his

reply to the show cause notice and then await the

final order which may perhaps go against him,

leaving him with no option but to challenge the same

before the jurisdictional High Court will be nothing

but an empty formality. Even otherwise, issuing

of show cause notice if not always then at

least most of the times is just an empty

formality because at the very point of time the

show cause notice is issued the Authority has

made up its mind to ultimately pass the final

order blacklisting the Contractor. In other

words, the show cause notice in most of the

cases is issued with a pre-determined mind. It

has got to be issued because this Court has said

that without giving an opportunity of hearing there

cannot be any order of blacklisting. To meet with

this just a formality is completed by the Authority of

issuing a show cause notice.

W.P.(C) No.8589 of 2024 Page 28 of 89

5.6. It is submitted that since the petitioner pursuing his

remedy bona fide and the propriety and legality of

rescission of contracts being sub judice before this Court

for adjudication in W.P.(C) Nos.29863 of 2023 and

31693 of 2023, the authority should not have shown

haste in taking recourse of banning the petitioner for six

years from participating in any of the tenders

undertaken by the Government of Odisha and

transacting business with the Government of Odisha,

directly or indirectly.

5.7. Stemming on the observations made in Blue Dreamz

Advertising (P) Ltd. Vrs. Kolkata Municipal Corporation,

(2024) 15 SCC 264, the Codal Provisions specifying

modalities for blacklisting/debarment requires strict

interpretation, and non-fulfilment of any of the

conditions thereof would render the decision of the

authority vitiated. It is, thus, asserted that the ban order

dated 30.03.2024 can be regarded as “civil death”

3, for

such a decision tends to “blacklisting” the petitioner

preventing it to eke out livelihood.

5.8. Hence, it is urged fervently for showing indulgence in the

matter.

6. Sri Saswat Das, learned Additional Government

Advocate dispelling controversial contentions raised by

3

See, Shri Artatran Bhuyan Vrs. State of Odisha, 2025 (II) ILR-CUT 104 2 as

followed in Rinabala Sethi Vrs. State of Odisha, 2025 SCC OnLine Ori 4785.

W.P.(C) No.8589 of 2024 Page 29 of 89

the petitioner submitted that the petitioner prior to

passing order banning it from participating in the

bidding process for the work undertaken by the

Government of Odisha and entering into transactions of

business with the Government of Odisha, issued Show

Cause Notices and the reply of the petitioner was found

not to have been specific or cogent. Referring to written

note dated 21.07.2025 submitted by the opposite

parties, he emphasised that in view of State of Odisha

Vrs. Panda Infraproject Limited, (2022) 4 SCC 393, having

adhered to principles of natural justice prior to taking

decision to debar/ban, no flaw in the order dated

30.03.2024 of the Chief Engineer, Bridges (WBP) can be

imputed so as to warrant this Court to interfere with. He

would submit that banning the contractor like the

petitioner who defied to complete the works entrusted

within the period stipulated is an effective measure to

discipline the defiant.

6.1. Explaining further he strenuously contended that the

petitioner even though was granted sufficient

opportunity and extension of period to complete the

works in question, he remained dormant and filed

affidavit before this Court for a direction to the opposite

parties to extend the period so expired knowing fully well

that such a recourse is not open for it to approach by

W.P.(C) No.8589 of 2024 Page 30 of 89

invoking provisions of Articles 226 and 227 of the

Constitution of India.

6.2. In counter reply to the interpretation of use of the word

“and” in sub-rule (c) of Rule A of the Appendix-XXXIV,

Sri Saswat Das, learned Additional Government

Advocate made suave submission that the aspects

contained therein are to be read disjunctively, but not

conjunctively. It is one thing to hold the petitioner

having committed offence of “Constant non-achievement

of milestones on insufficient and imaginary grounds”

and nevertheless, it is another to say “non-adherence to

quality specifications despite being pointed out”. It is

vociferously submitted that two independent aspects

cannot be construed to be one ground. Since the Show

Cause Notices indicated one aspect i.e., “Constant non-

achievement of milestones on insufficient and imaginary

grounds” out of the two aspects in the ground vide sub-

rule (c) of Rule A of Appendix-XXXIV read with Clause

121 of the DTCN, and the reply thereto by the petitioner

being not found favour with, ban order debarring the

petitioner from participating in tenders vide order dated

30.03.2024 has been passed. Valiant attempt was made

by the learned Additional Government Advocate to

construe the word “and” joining two situations /

circumstances enjoined in sub-rule (c) of Rule A of

Appendix-XXXIV to the OPWD Code to be disjunctive.

W.P.(C) No.8589 of 2024 Page 31 of 89

6.3. Referring to Venkataraman Krishnamurthy Vrs. Lodha

Crown Buildmart Pvt. Ltd., (2024) 4 SCC 230 , it is

submitted that the explicit terms contained in Clause

2(b)(i)

4 read with Clause 121 of the DTCN should be

treated to be final word with regard to the intention of

the parties. On the specious plea of regulatory or

adjudicatory forum the petitioner should be discouraged

to insist for judicial review after participation in the

tender and being awarded with the works to accomplish

within the periods stipulated in the guise of seeking

equity or fairness. Such a course to draw sympathy of

this Court is anathema to judicial approach and to insist

for rewriting the contractual framework or superimpose

obligations alien to the agreement.

6.4. He, thus, prayed not to meddle with the order of

debarment vide Annexure-1 and dismiss the writ

petition.

Analysis and discussion:

7. Before this Court the rescission of contracts with respect

to two different works awarded has been under

challenge in W.P.(C) Nos.29863 and 31693 of 2023. In

both the cases the petitioner filed affidavit undertaking

that given extension of further period, it would be in a

4

“To rescind the contract (of which rescission notice in writing to the contractor

under the hand of the Executive Engineer shall be conclusive evidence) 20% of the

value of left-over work will be realized from the Contractor as penalty.”

W.P.(C) No.8589 of 2024 Page 32 of 89

position to complete the works. While in respect of one of

the works, being Work No.1, this Court having directed

the opposite parties to allow the petitioner to complete

the work in W.P.(C) No. 29863 of 2023 vide order dated

01.03.2024, the Hon’ble Supreme Court in the case of

State of Odisha Vrs. Binodini Infrastructure Pvt. Ltd., Civil

Appeal No.7085 of 2025 [Arising out of S.L.P.(C) No.14142

of 2024] vide order dated 14.05.2025 set aside the

matter by holding that this Court could not have issued

such direction inasmuch as such consideration would

fall in the domain of rewriting the terms of contract. In

the other matter being W.P.(C) No.31693 of 2023 the

opposite parties have filed counter refuting the

averments and contentions of the petitioner. Both the

matters are now sub judice before this Court. Rescission

of contracts being questioned in the said writ petitions,

in the present the concern is for ban order clamped

against the petitioner from participating in tenders and

transacting business with the Government.

8. Be that as it may, the order banning/debarring the

petitioner has come to be passed by the Chief Engineer,

Bridges (WBP), Odisha on 30.03.2024 which is subject

matter of challenge in this writ petition.

9. Perusal of Show Cause Notice dated 18.10.2023 with

respect to Work No.1, it transpired that several requests

were made by the authority concerned by issue of

W.P.(C) No.8589 of 2024 Page 33 of 89

notices to the petitioner to complete the works, which

turned out to be futile and went unheeded. Upon

inspection being conducted by the Superintending

Engineer, Malkangiri (R&B) to the spot, it was found

that there were no men or machineries at the site. Such

negligence on the part of the petitioner invited issue of

such notice with the caveat that failure to act with

promptitude would invite action in terms of Clause 121

of the DTCN read with provisions of Appendix-XXXIV of

OPWD Code, Volume-II.

9.1. Perusal of Show Cause Notice dated 18.10.2023 with

respect to Work No.2 (Annexure-11) it is manifest that

notwithstanding several notices issued to the petitioner,

it remained indifferent and failed to complete the work

within the period stipulated, as extended. Even a notice

in Letter No.357 dated 25.01.2021 was issued with

request to complete the balance work with warning that

failure to resume work would entail step under Clause

121 of DTCN read with relevant provisions of Appendix-

XXXIV of OPWD Code, Volume-II.

9.2. Separate replies dated 23.10.2023 were submitted to the

Chief Engineer, World Bank Projects with copies to other

authorities making them aware that the tenability of

decision to rescind the contracts has been pending

before this Court.

W.P.(C) No.8589 of 2024 Page 34 of 89

9.3. Perusal of record further revealed the fact that the

petitioner has been imposed with penalty vide Letter

dated 26.10.2023 issued by the Superintending

Engineer (R&B) Division, Malkangiri (Annexure-12).

9.4. When the material with respect to pendency of cases

relating to the works in question was made known to the

authority concerned, without issuing further notice

contemplating to take drastic step against the petitioner

and/or hearing it the order of ban/debarment has been

passed, which is recognized akin to “blacklisting”,

thereby affecting the fundamental right to carry

business under Article 19(1)(g) of the Constitution of

India. As it emanates ex facie from the reply dated

23.10.2023, the petitioner merely made aware the

authorities regarding pendency of cases before this

Court as against rescission of contracts; but the reply

does not indicate that the petitioner has disclosed the

reasons for non-completion of the works within the

periods stipulated.

9.5. It cannot be gainsaid that in order to impose stringent

condition, like ban/debarment/blacklisting which would

have effect of impinging upon constitutional right of the

contractor, the authority exercising such power must be

more circumspect and such recourse preventing the

contractor from carrying on business would have

unreasonable restriction on the right flowing from Article

W.P.(C) No.8589 of 2024 Page 35 of 89

19(1)(g). Article 14 of the Constitution of India

safeguards such persons being contemned without

affording opportunity of hearing. Such is the facet is

audi alteram partem.

9.6. This Court in Sumitra Sethy Vrs. The Indian Railways,

W.P.(C) No.6182 of 2025, vide Judgment dated

06.05.2026 observed thus:

“7. It is no gainsaying that the blacklisting or

debarment has an effect of eliminating a person

from participating in any contract with the

Government nor will have any such privilege and

advantage of entering into the contract with the

Government agencies. It is, in effect, deprived a

person from having any commercial

relationship with the Government or its

agencies and has an impact on the right to

trade or profession as provided under Article

19(1)(g) of the Constitution of India. Such

fundamental right is always subject to the

established procedure of law and in the event

it is found that the person has committed a

gross error or violated the terms and

conditions of the contract, there is no fetter in

debarring such person to participate in any

tender, nor will be entitled to establish a

contractual relationship with the public

authority. In such sense, it is time and again

regarded as a “civil death” and therefore, it is

a paramount duty of the authorities to adhere

the principles of natural justice before it

W.P.(C) No.8589 of 2024 Page 36 of 89

proceeds to inflict an order of debarment

and/or blacklisting on the person.

8. The aforesaid concept/notion is further fortified in

the judgment rendered by the Apex Court in case of

Raghunath Thakur Vrs. State of Bihar; (1989) 1 SCC

229 in the following:

„4. Indisputably, no notice had been given to the

appellant of the proposal of blacklisting the

appellant. It was contended on behalf of the

State Government that there was no

requirement in the rule of giving any prior

notice before blacklisting any person. Insofar

as the contention that there is no requirement

specifically of giving any notice is concerned,

the respondent is right. But it is an implied

principle of the rule of law that any order

having civil consequence should be passed

only after following the principles of natural

justice. It has to be realised that blacklisting

any person in respect of business ventures has

civil consequence for the future business of the

person concerned in any event. Even if the

rules do not express so, it is an elementary

principle of natural justice that parties affected

by any order should have right of being heard

and making representations against the order.

In that view of the matter, the last portion of

the order insofar as it directs blacklisting of the

appellant in respect of future contracts, cannot

be sustained in law. In the premises, that

portion of the order directing that the appellant

be placed in the blacklist in respect of future

contracts under the Collector is set aside. So

W.P.(C) No.8589 of 2024 Page 37 of 89

far as the cancellation of the bid of the

appellant is concerned, that is not affected.

This order will, however, not prevent the State

Government or the appropriate authorities from

taking any future steps for blacklisting the

appellant if the Government is so entitled to do

in accordance with law i.e. after giving the

appellant due notice and an opportunity of

making representation. After hearing the

appellant, the State Government will be at

liberty to pass any order in accordance with

law indicating the reasons therefor. We,

however, make it quite clear that we are not

expressing any opinion on the correctness or

otherwise of the allegations made against the

appellant. The appeal is thus disposed of.‟

***

10. It is manifest from the ratio of law enunciated in the

above report that the order of blacklisting and/or

debarment not only prevents and/or excludes a

person from participating in any contractual

relationship with the Government or its agencies but

is also deprived of his livelihood as a stigma would

be attached to him which cannot be inflicted without

giving ample opportunity to defend. Even if the terms

and conditions embodied in the tender document

does not contain an express provision relating to

issuance of a show cause preceding the order of

blacklisting, yet the rule of natural justice being

paramount cannot be abridged and/or whittled

down which is one of the ethos of the constitutional

rights guaranteed in the Constitution of India. The

maxim audi alteram partem is ingrained and

W.P.(C) No.8589 of 2024 Page 38 of 89

inhered into the legal system and even a

person cannot be penalised and/or condemned

without giving an opportunity of hearing. As

indicated hereinabove the debarment/blacklisting

has the blend of a civil death, such order cannot be

passed without affording an opportunity to defend

and for such reason the issuance of show cause

becomes inevitable.

11. In a recent judgment rendered by the Hon‟ble

Supreme Court in M/s. A.K.G. Construction and

Developers Pvt. Ltd. Vrs. State of Jharkhand and

others; (2026) 4 SCR 331, the Apex Court was

considering a case where a show cause notice was

issued to the contractor with regard to the

termination of a contract for the reasons reflected in

the said show cause notice but the authorities while

terminating the contract proceeded to pass an order

of blacklisting and/or debarment. The Apex Court

did not interfere with the order of termination

of a contract but set aside the order of the

debarment as both the circumstances relating

to a termination of a contract and imposition

of a blacklisting and/or debarment are

distinct, different and separate. It is held that

the show cause notice which was restricted to a

termination of contract cannot be stretched to mean

that it is also for the debarment in the following:

„3. Upon careful consideration of the impugned

State action, which terminates the contract and

blacklists the appellant without meaningful

distinction, we hold that the termination order

is substantiated and justified. However, the

blacklisting order suffers from patent

W.P.(C) No.8589 of 2024 Page 39 of 89

infirmities: it evinces no application of

mind, disregards the mandatory precept

of audi alteram partem, and fails to

precede with a show-cause notice

requiring the contractor to demonstrate

why such drastic action should not be

taken. Blacklisting, being stigmatic and

exclusionary in nature, cannot be imposed

mechanistically but must comport with

principles of natural justice and

reasonableness.

***

22. Returning to the facts of the present case, at

the outset, it is apparent that the show cause

notice dated 04.06.2024 does not purport to be

a show cause notice for blacklisting at all. It

perhaps expects the contractor to assume that

it is for termination as well as for blacklisting.

Even if we accept the submissions of Mr.

Kumar Anurag Singh that, as there is no

provision for prior notice before termination,

this show cause notice must be taken to be for

blacklisting, we are of the opinion that it still

falls short of the requirement of a proper show

cause notice for blacklisting. This is for the

reason that as the decision to blacklist is

independent of the decision to terminate, the

Department must demonstrate application of

mind before it takes the next step of

blacklisting the contractor, over an order of

termination. Upon taking such a decision, it

must also issue a show cause notice calling

upon the contractor to explain why a

W.P.(C) No.8589 of 2024 Page 40 of 89

consequential order of blacklisting should also

not be passed. The letter must be indicative of

the proposed decision to blacklist and the

requirement of the contractor to respond to it.

The show cause notice dated 04.06.2024 falls

short of these requirements. Similarly, the final

order of blacklisting, dated 23.08.2024, also

does not list the reasons as to why an order of

blacklisting has become necessary.‟ ***”

9.7. There is no cavil that the order of banning/blacklisting/

debarment would be akin to “civil death”, this Court in

Kwick Soft Solutions Pvt. Ltd., Tamilnadu Vrs. State of

Odisha, W.P.(C) No.24026 of 2024 vide order dated

21.08.2025

5 observed as follows:

“3. It is no doubt true that the debarment or blacklisting

of any individual or an entity to participate in a

tender process is akin to a “civil death” as a person

is deprived of entering into any commercial

relationship with the public or the Government. Any

order of debarment or blacklisting is always

regarded as a stigma attached to the commercial

dealing with the Government and in effect debars

from a person to have the award of the Government

contracts. The debarment or blacklisting has an

effect of bringing a person from the privilege

and advantage of entering into a lawful

relationship with the Government or its

instrumentalities and above all impacts the

livelihood. In effect such debarment has a far-

reaching consequence in public contracts and,

5

Referred to in Rinabala Sethi Vrs. State of Odisha, W.P.(C) No.21309 of 2024,

vide Judgment dated 22.12.2025.

W.P.(C) No.8589 of 2024 Page 41 of 89

therefore, the authority must view the misconduct

more scrupulously before taking a decision of

debarment/blacklisting. The misdeed must be of

such magnitude which in ordinary sense is not

expected from a reasonable man. It may at times

should be judged on the parameter of unfair means

or illegal gain. The minimal or accidental omission or

mistake, which was subsequently rectified, if it does

not, cause any prejudice or hinders in its invocation

as the Bank remain committed to the person, in

whose favour the Bank Guarantee is issued to

honour the same, the authority must view the

mistake in such perspective. Mere non-incorporation

of UIN of the Odisha Police and incorporation of the

PAN number of one of the Directors of the petitioner-

Company mistakenly neither invalidates the said

Bank Guarantee nor put any invasion into its

invocation by the Odisha Police in the event the

same is warranted from the conduct of the

petitioner. Apart from the same, the said ministerial

mistake was rectified by the Bank issuing the Bank

Guarantee, which does not in our view invites the

civil death as held by the Apex Court in the case of

Gorkha Security Services Vrs. Government (NCT of

Delhi) and others, (2014) 9 SCC 105 in the following:

„16. It is a common case of the parties that the

blacklisting has to be preceded by a show-

cause notice. Law in this regard is firmly

grounded and does not even demand much

amplification. The necessity of compliance with

the principles of natural justice by giving the

opportunity to the person against whom action

of blacklisting is sought to be taken has a valid

and solid rationale behind it. With

W.P.(C) No.8589 of 2024 Page 42 of 89

blacklisting, many civil and/or evil

consequences follow. It is described as

“civil death” of a person who is foisted

with the order of blacklisting. Such an

order is stigmatic in nature and debars

such a person from participating in

government tenders which means

precluding him from the award of

government contracts.‟ ***”

9.8. At this juncture careful reading of Show Cause Notices

dated 18.10.2023 would depict that except for slow pace

of work being flagged, nothing is emanated with specific

terms with regard to the grounds on which the action for

banning was contemplated.

9.9. It may be necessary to have regard to Clause 121 of the

DTCN, which is reproduced hereunder [ vide Counter

affidavit, paragraph 6]:

“121.A contractor may be blacklisted as per amendment

made to Appendix XXXIV to OPWD Code, Volume-II

on rules for blacklisting of contractors vide Letter No.

3365 dated 01.03.2007 of Works Department,

Odisha.

(a) Misbehavior/threatening of departmental

supervisory officers during work/tendeiing

process,

(b) Involvement in any sort of tender fixing,

(c) Constant non-achievement of milestones

insufficient and imaginary grounds and non-

W.P.(C) No.8589 of 2024 Page 43 of 89

adherence to quality specifications despite

being pointed out.

(d) Persistent and intentional violation of important

conditions of contract.

(e) Security consideration of the State, i.e., any

action that jeopardizes the security of the

State.

(f) Submission of false/fabricated/forged

documents for consideration of a tender.”

9.10. Relevant portion of Appendix XXXIV is quoted

hereunder:

“Appendix-XXXIV

Codal provisions for blacklisting

Contractors

A. The Chief Engineer of a department may blacklist a

contractor with the approval of concerned

Administrative Department on the following grounds:

(a) Misbehaviour/threatening of departmental and

supervisory officers during execution of

work/tendering process.

(b) Involvement in any sort of tender fixing.

(c) Constant non-achievement of milestones

on insufficient and imaginary grounds

and non-adherence to quality

specifications despite being pointed out.

(d) Persistent and intentional violation of important

conditions of contract.

W.P.(C) No.8589 of 2024 Page 44 of 89

(e) Security consideration of the State i.e., any

action that jeopardizes the security of the

State.

(f) Submission of false/fabricated/forged

documents for consideration of a tender.

(g) Non submission of Additional Performance

Security (APS) within stipulated period

inpursuance to Works Department Office

memorandum No 14299/W, dated 03.10.2017.

The Divisional Officer shall report to the Chief

Engineer if in his opinion any of the above wrong

has/have been committed by any contractor. On

receipt of such a report from the Divisional Officer

the Chief Engineer shall make due enquiry and if

considered necessary, issue show cause notice to

the concerned contractor who in turn shall furnish

his reply, if any, within a fortnight from the date of

receipt of the show cause notice. Therefore, if the

Chief Engineer is satisfied that there is sufficient

ground, he shall blacklist the concerned contractor

with the approval of the Administrative Department.

After issue of the order of blacklisting of the said

contractor, the Chief Engineer shall intimate to all

Chief Engineers of other Administrative

Departments, the Registering Authority as provided

under Rule 4 of PWD Contractor‟s Registration

Rules, 1967 and Department of Information &

Technology for publication in web site of State

Government.

B. The registration certificate of blacklisted contractor

shall remain automatically suspended while

allowing him to complete all his ongoing work(s)

W.P.(C) No.8589 of 2024 Page 45 of 89

unless otherwise rescinded by the competent

authority on grounds of breach of conditions of

agreement.

C. The name(s) of partners and allied concerns of the

blacklisted contractors shall also be communicated

to all concerned. Care shall be taken to see that the

contractor blacklisted and his partners do not

transact any business with Government under a

different name or title.

D. Once the blacklisting order is issued it shall not be

revoked ordinarily unless:

(i) On review in later date, the Chief Engineer is of

the opinion that there is sufficient justification

to revoke the order of blacklisting, or

(ii) In respect of the same offense, the accused has

been honourably acquitted by court of law.

The concerned Chief Engineer will obtain order from

the concerned Administrative Department before

revoking the order of blacklisting. The order of

revocation shall also be communicated to all

concerned.

6[The blacklisting period per offence shall be limited

to 03 (three) years subject to an overall maximum

6

This clause has been introduced by virtue of Office Memorandum File

No.07180200982020/16131/W, dated 26.11.2021:

“Sub.: Codal provisions for blacklisting of contractor

Government after careful consideration have been pleased to make the

following provision under Rule-D of Appendix-XXXIV of OPWD Code,

Volume-II:

„The blacklisting period per offence shall be limited to 03 (three) years

subject to an overall maximum cumulative period of 10 (ten) years for

multiple offences‟.

This shall form a part of the Appendix-XXXIV of OPWD Code, Volume- II.”

W.P.(C) No.8589 of 2024 Page 46 of 89

cumulative period of 10 (ten) years for multiple

offences.]

E. The Chief Engineer and Administrative Department

shall maintain a list of blacklisted contractor.

Updated list of blacklisted contractors shall be

communicated to all concerned by the Chief

Engineers on a quarterly basis.

F. Checklist as per Annexure-I, shall be furnished by

the concerned Chief Engineer for blacklisting the

contractor.

G. Checklist as per Annexure-II, shall be furnished by

the concerned Chief Engineer for revoking

blacklisting order.

Explanation:

(i) Action taken under this rule shall be in

addition to any action taken under Rule 11 of

PWD Contractor‟s Registration Rules,1967

(Appendix-VIII of OPWD Code, Vol.-II). On

revocation of order of blacklisting, registration

certificate of the contractor shall valid

automatically, if not otherwise become invalid

which shall be recorded in the registration

certificate by the revoking authority.

(ii) The ground mentioned above for blacklisting of

contractor shall be deemed to be deleted from

the grounds for cancellation/suspension of

registration certificate under Rule 11(a) of PWD

Contractor‟s Registration Rules, 1967

(AppendixVIII of OPWD Code, Vol.-II).”

W.P.(C) No.8589 of 2024 Page 47 of 89

9.11. Ground on which the authority concerned proceeded to

ban the petitioner is sub-rule (c) of Rule A of the

Appendix-XXXIV. Having glance at the provisions as

referred to above read with order dated 30.03.2024

(Annexure-1), it emerges that “Even after several notices

and persuations, the contractor constantly failed to

achieve the desired milestones as per agreement and did

not complete the above works within the time stipulated

violating the conditions of contract and Codal

Provisions.”

9.12. It is apparent that the ground for jumping to conclusion

to debar the petitioner from participating in Government

tenders falls within the ambit of sub-rule (c) of Rule A of

Appendix-XXXIV. Rule A consists of seven grounds

stemming on which the competent authority can invoke

power to blacklist/debar a contractor. Minute reading of

the order impugned would suggest that the ground on

which the Chief Engineer, Bridges (WBP) proceeded was

sub-rule (c) thereof. As debarment is stated to be for “six

years”, it does not emanate from said order the reason

for invocation of introduced clause by virtue of Office

Memorandum dated 26.11.2021.

9.13. Sub-rule (c) of Rule A comprehends two aspects, namely:

i. Constant non-achievement of milestones on

insufficient and imaginary grounds; “and”

W.P.(C) No.8589 of 2024 Page 48 of 89

ii. non-adherence to quality specifications despite

being pointed out.

9.14. Both the situations are placed under one entry as a

composite ground. However, unless the deficiencies are

put to notice of the petitioner in specific terms with

respect to both the situations, it may not possibly

appropriate for the authority to jump to conclusion that

the contract invites stringent restriction.

9.15. At this stage Show Cause Notices vide Annexure-11 are

required to be taken into consideration. Meaningful

reading of the tenor and texture of such notices would

only indicate that notices were issued to the petitioner

requesting it to complete the balance work. However, it

does not emerge therefrom that the contemplated action

for blacklisting was intimated in specific terms and

ground(s) specified in sub-rule (c) of Rule A. It is only the

Show Cause Notices dated 18.10.2023 which depict that

failure to resume both the works would attract steps as

per Clause 121 of the DTCN read with Rule A of the

Appendix-XXXIV of the OPWD Code.

9.16. It is interesting to note that Show Cause Notices dated

18.10.2023 does not indicate whether there was any

“insufficient and imaginary ground” that led to “constant

non-achievement of milestones”. In the Show Cause

Notice dated 18.10.2023 with respect to Work No.2 it is

W.P.(C) No.8589 of 2024 Page 49 of 89

stated that “The Superintending Engineer, Malkangiri,

Malkangiri (R&B) Division again issued another show

cause notice vide Letter No.5823, dated 11.11.2020

where he has stated that even though you have

committed during contract management meeting held on

06.07.2020 in his office to start the bridge work by 2

nd

week of September, 2020, till November, 2020 you did

not taken any initiative.” It is further revealed therefrom

that “the Superintending Engineer, Malkangiri (R&B)

Division issued final notice vide Letter No.357, dated

25.01.2021 to you with a request to execute the backlog

quantities of the work by engaging sufficient me and

machineries with maximum working hours as well as

achieve the target for completion of the above project”.

Similar facts are also found place in Show Cause Notice

dated 18.10.2023 with respect to Work No.1.

9.17. Above recitals emanating from the Show Cause Notices

would indicate that the extensions granted for

completion of works were during the period of pandemic.

There is no iota of indication found in said Show Cause

Notices with respect to “non-adherence to quality

specifications”. Had the authority wanted real reason for

the delay and non-accomplishment of the works

entrusted to the petitioner, it should have issued notice

to submit explanation for the delay and affording

opportunity of hearing. Failure to give such an

W.P.(C) No.8589 of 2024 Page 50 of 89

opportunity would render the order legally fragile not on

the ground of lack of jurisdiction on the part of the

authority concerned but on the ground of violation of

principles of natural justice. There can be no dispute

that while the authority is free to exercise his

jurisdiction on consideration of all relevant facts, a full

opportunity to controvert the same and to explain the

circumstances surrounding such facts, as may be

considered relevant by the contractor, must be afforded

to him prior to the finalization of the decision. See,

Commissioner of Income Tax Vrs. Amitabh Bachchan,

(2016) 3 SCR 516.

9.18. In Oryx Fisheries Pvt. Ltd. Vrs. Union of India, (2010) 13

Addl. SCR 234 it has been stated thus:

“22. Relying on the underlined portions in the show

cause notice, learned counsel for the appellant urged

that even at the stage of the show cause notice the

third respondent has completely made up his mind

and reached definite conclusion about the alleged

guilt of the appellant. This has rendered the

subsequent proceedings an empty ritual and an idle

formality.

23. This Court finds that there is a lot of substance in

the aforesaid contention.

24. It is well settled that a quasi-judicial authority, while

acting in exercise of its statutory power must act

fairly and must act with an open mind while

initiating a show cause proceeding. A show cause

W.P.(C) No.8589 of 2024 Page 51 of 89

proceeding is meant to give the person·proceeded

against a reasonable opportunity of making his

objection against the proposed charges indicated in

the notice.

25. Expressions like „a reasonable opportunity of

making objection‟ or „a reasonable opportunity of

defence‟ have come up for consideration before this

Court in the context of several statutes.

26. A Constitution Bench of this Court in Khem Chand

Vrs. Union of India and others, reported in AIR 1958

SC 300, of course in the context of service

jurisprudence, reiterated certain principles which are

applicable in the present case also.

27. Chief Justice S.R. Das speaking for the unanimous

Constitution Bench in Khem Chand (supra) held that

the concept of „reasonable opportunity‟ includes

various safeguards and one of them, in the words of

the learned Chief Justice, is:

„(a) An opportunity to deny his guilt and

establish his innocence, which he can only

do if he is told what the charges leveled

against him are and the allegations on

which such charges are based;‟

28. It is no doubt true that at the stage of show cause,

the person proceeded against must be told the

charges against him so that he can take his defence

and prove his innocence. It is obvious that at that

stage the authority issuing the chargesheet, cannot,

instead of telling him the charges, confront him with

definite conclusions of his alleged guilt. If that is

done, as has been done in this instant case, the

W.P.(C) No.8589 of 2024 Page 52 of 89

entire proceeding initiated by the show cause notice

gets vitiated by unfairness and bias and the

subsequent proceeding become an idle ceremony.

29. Justice is rooted in confidence and justice is the goal

of a quasi-judicial proceeding also. If the functioning

of a quasi-judicial authority has to inspire

confidence in the minds of those subjected to its

jurisdiction, such authority must act with utmost

fairness. Its fairness is obviously to be manifested

by the language in which charges are couched and

conveyed to the person proceeded against. In the

instant case from the underlined portion of the show

cause notice it is clear that the third respondent has

demonstrated a totally close mind at the stage of

show cause notice itself. Such a close mind is

inconsistent with the scheme of Rule 43 which is set

out below. The aforesaid rule has been framed in

exercise of the power conferred under Section 33 of

The Marine Products Export Development Authority

Act, 1972 and as such that Rule is statutory in

nature.

***

31. It is of course true that the show cause notice cannot

be read hyper-technically and it is well settled that it

is to be read reasonably. But one thing is clear that

while reading a show-cause notice the person who

is subject to it must get an impression that he will

get an effective opportunity to rebut the allegations

contained in the show cause notice and prove his

innocence. If on a reasonable reading of a show-

cause notice a person of ordinary prudence gets the

feeling that his reply to the show cause notice will

be an empty ceremony and he will merely knock his

W.P.(C) No.8589 of 2024 Page 53 of 89

head against the impenetrable wall of prejudged

opinion, such a show cause notice does not

commence a fair procedure especially when it is

issued in a quasi-judicial proceeding under a

statutory regulation which promises to give the

person proceeded against a reasonable opportunity

of defence.

32. Therefore, while issuing a show-cause notice, the

authorities must take care to manifestly keep an

open mind as they are to act fairly in adjudging the

guilt or otherwise of the person proceeded against

and specially when he has the power to take a

punitive step against the person after giving him a

show cause notice.

33. The principle that justice must not only be

done but it must eminently appear to be done

as well is equally applicable to quasi judicial

proceeding if such a proceeding has to inspire

confidence in the mind of those who are subject

to it.

34. A somewhat similar observation was made by this

Court in the case of Kumaon Mandal Vikas Nigam

Limited Vrs. Girja Shankar Pant & others, (2001) 1

SCC 182. In that case, this court was dealing with a

show cause notice cum charge sheet issued to an

employee. While dealing with the same, this Court in

paragraph 25 (page 198 of the report) by referring to

the language in the show cause notice observed as

follows:

„25. Upon consideration of the language in the

show-cause notice-cum-charge-sheet, it has

been very strongly contended that it is clear

W.P.(C) No.8589 of 2024 Page 54 of 89

that the Officer concerned has a mindset even

at the stage of framing of charges and we also

do find some justification in such a submission

since the chain is otherwise complete.‟

35. After paragraph 25, this Court discussed in detail

the emerging law of bias in different jurisdictions

and ultimately held in paragraph 35 (page 201 of

the report), the true test of bias is:

„35. The test, therefore, is as to whether a mere

apprehension of bias or there being a real

danger of bias and it is on this score that the

surrounding circumstances must and ought to

be collated and necessary conclusion drawn

therefrom— in the event however the

conclusion is otherwise inescapable that there

is existing a real danger of bias, the

administrative action cannot be sustained.‟

36. Going by the aforesaid test any man of ordinary

prudence would come to a conclusion that in the

instant case the alleged guilt of the appellant has

been prejudged at the stage of show cause notice

itself.”

9.19. In Commissioner of Central Excise, Bhubaneswar Vrs.

Champdany Industries Limited, (2009) 14 (Addl.) SCR

211 it is unequivocally laid down as follows:

“50. Apart from that, the point on Rule 3 which has been

argued by the learned counsel for the Revenue was

not part of its case in the show-cause notice. It is

well settled that unless the foundation of the case is

made out in the show-cause notice, Revenue cannot

W.P.(C) No.8589 of 2024 Page 55 of 89

in Court argue a case not made out in its show-

cause notice. [See: Commissioner of Customs,

Mumbai Vrs. Toyo Engineering India Limited, (2006)

7 SCC 592, para 16].

51. Similar view was expressed by this Court in the

case of Commissioner of Central Excise, Nagpur Vrs.

Ballarpur Industries Ltd., (2007) 8 SCC 9. In

paragraph 27 of the said report, learned Judges

made it clear that if there is no invocation of the

concerned rules in the show-cause notice, it would

not be open to the, Commissioner to invoke the said

Rule.”

9.20. The Supreme Court in case of Commissioner of Customs,

Mumbai Vrs. Toyo Engineering India Limited, (2006)

Supp.5 SCR 657 noted that the Department cannot be

allowed travel beyond the show cause notice and,

therefore, it would be against the principles of natural

justice that a person who has not been confronted with

any ground is saddled with liability thereof. Since the

issue did not form the basis of the show cause notice

and was not even confronted to the order passed beyond

show cause notice is to be quashed. In the instant case,

the Show Cause Notices do not with specificity spelt out

with regard to twin conditions envisioned in sub-rule (c)

of Rule A of Appendix-XXXIV appended to the OPWD

Code. The Show Cause Notices dated 18.10.2023 and

the impugned order dated 30.03.2024 are silent about

the circumstances/aspects which led to construe that

W.P.(C) No.8589 of 2024 Page 56 of 89

the explanation of the petitioner was “insufficient and

imaginary grounds”. Neither the Show Cause Notices nor

did the order demonstrate that there was “non -

adherence to quality specifications despite being pointed

out”.

9.21. Numerous grounds are found mentioned in Rule A. Each

ground is placed separately as item (a) through (g). Had

both the aspects in Ground contained in sub-rule (c) of

Rule A “Constant non-achievement of milestones on

insufficient an imaginary grounds ” “and” “non-

adherence to quality specifications despite being pointed

out” were to be treated as separate grounds, then there

was no difficulty in formulating each of them in separate

items. Before analyzing the nuance of grounds found

enumerated under Rule A, OPWD Code, a doctrinaire

principle ingrained in noscitur-a-sociis may be referred to

as reflected in State Vrs. Hospital Mazdoor Sabha, (1960)

2 SCR 866 may be regarded as relevant for the present

purpose. The Hon’ble Supreme Court of India held,

“This rule, according to Maxwell, means that, when two or

more words which are susceptible of analogous meaning

are coupled together they are understood to be used in

their cognate sense. They take as it were their colour from

each other, that is, the more general is restricted to a

sense analogous to a less general.

The same rule is thus interpreted in “Words and Phrases”

(Vo. XIV, p. 207):

W.P.(C) No.8589 of 2024 Page 57 of 89

„Associated words take their meaning from one another

under the doctrine of noscitur-a-sociis, the philosophy of

which is that the meaning of a doubtful word may be

ascertained by reference to the meaning of words

associated with it; such doctrine is broader than the

maxim Ejusdem Generis.‟

In fact the latter maxim „is only an illustration or specific

application of the broader maxim noscuntur-a-sociis‟.”

9.22. In Parle Agro Private Limited Vrs. CCT, (2017) 7 SCC 540

it has been said that it must be borne in mind that

noscitur-a-sociis is merely a rule of construction and it

cannot prevail in cases where it is clear that the wider

words have been deliberately used in order to make the

scope of the defined word correspondingly wider. It is

only where the intention of the Legislature in associating

wider words with words of narrower significance is

doubtful, or otherwise not clear that the present rule of

construction can be usefully applied.

9.23. Rule A begins with expression— “The Chief Engineer of a

department may blacklist a contractor with the approval

of concerned Administrative Department on the following

grounds”. Said expression is followed by seven categories

of grounds enumerated in sub-rules (a) through (g). The

setting of said Rule inculcates in mind only one thing

that the Chief Engineer is empowered to take decision to

blacklist a contractor subject to approval of the

Administrative Department on the grounds mentioned in

W.P.(C) No.8589 of 2024 Page 58 of 89

sub-rules (a) to (g) on any one ground or combination of

grounds; nonetheless, each sub-rule is a ground to be

construed independently. Twin condition is specified in

sub-rule (c) of Rule A. The languages employed in Clause

121 of the DTCN and sub-rule (c) of Rule A of Appendix-

XXXIV appended to the OPWD Code, Volume-II are

identically worded. Rule A read as a whole indicates that

the blacklisting of the contractor can be done on the

grounds enumerated therein. Seven independent

grounds are reflected in said Rule A. As has already

been observed above each ground is separately

enumerated from sub-rule (a) to sub-rule (g). Sub-rule

(c) is one of the grounds contained in Rule A. Therefore,

the suggestion of the learned Additional Government

Advocate to read the word “and” between two

expressions, i.e., “Constant non-achievement of

milestones on insufficient an imaginary grounds” “and”

“non-adherence to quality specifications despite being

pointed out” disjunctively cannot be acceded to for the

simple reason that while enumerating different grounds

the OPWD Code specified separately each ground; then

there was no difficulty in placing two disjunctive

situations/aspects, as pleaded by the opposite parties

through the learned Additional Government Advocate, in

different segment. The intent of the Government to treat

both the conditions as one ground for the purpose of

W.P.(C) No.8589 of 2024 Page 59 of 89

taking step to blacklist a contractor is loud and clear

and no ambiguity can be imputed.

9.24. It is well-established principle of statutory interpretation

that the word “or” is normally disjunctive and the word

“and” is normally conjunctive. Both of them can be read

as vice-versa, but that interpretation is adopted only

where the intention of the legislature is manifest. See,

Central Council for Research in Ayurvedic Sciences Vrs.

Bikartan Das, (2023) 11 SCR 731.

9.25. In Bhavnagar University Vrs. Palitana Sugar Mill (P) Ltd.,

(2003) 2 SCC 111 it has been enunciated as follows:

“It is the basic principle of construction of statute that the

same should be read as a whole, then chapter by chapter,

section by section and words by words. Recourse to

construction or interpretation of statute is necessary when

there is ambiguity, obscurity, or inconsistency therein and

not otherwise. An effort must be made to give effect to all

parts of the statute and unless absolutely necessary, no

part thereof shall be rendered surplusage or redundant.”

9.26. In Renaissance Hotel Holdings Inc. Vrs. B. Vijaya Sai,

(2022) 5 SCC 1, it has been emphasized as follows:

“66. It is thus trite law that while interpreting the

provisions of a statute, it is necessary that the

textual interpretation should be matched with the

contextual one. The Act must be looked at as a

whole and it must be discovered what each section,

each clause, each phrase and each word is meant

W.P.(C) No.8589 of 2024 Page 60 of 89

and designed to say as to fit into the scheme of the

entire Act. No part of a statute and no word of a

statute can be construed in isolation. Statutes

have to be construed so that every word has a

place and everything is in its place. ***

67. Another principle that the High Court has failed to

notice is that a part of a section cannot be read in

isolation. This Court, speaking through A.P. Sen, J.,

in Balasinor Nagrik Coop. Bank Ltd. Vrs. Babubhai

Shankerlal Pandya, (1987) 1 SCC 606, observed

thus:

„4. *** It is an elementary rule that

construction of a section is to be made of

all parts together. It is not permissible to

omit any part of it. For, the principle that

the statute must be read as a whole is

equally applicable to different parts of the

same section.‟

This principle was reiterated by this Court in

Kalawatibai Vrs. Soiryabai, (1991) 3 SCC 410:

„6. *** It is well settled that a section has to

be read in its entirety as one composite

unit without bifurcating it or ignoring any

part of it.‟ ***”

9.27. On the basis of said principle, when Rule A of the

Appendix-XXXIV of the OPWD Code, Volume-II is

studied, it manifests that from sub-rules (a) to (g) of Rule

A contains independent ground mentioned in each sub-

rule. Each ground contained in each sub-rule is distinct

from one and the other. Sub-rules (a) to (g) comprehend

W.P.(C) No.8589 of 2024 Page 61 of 89

different identifiable circumstance/event/ground in each

sub-rule. In that sense, sub-rule (c) of Rule A is to be

read as one composite whole.

9.28. The Show Cause Notice and the order impugned do not

contain reason as to why the reply of the petitioner did

contain “insufficient and imaginary ground”. Cursory

glance at replies at Annexure-13 would show that the

petitioner has simply intimated the authority concerned

regarding challenge being made before this Court

against the rescission of contract; but such replies do

not reflect that the petitioner has proffered cause of

delay in completion of the works. If the authority

concerned decided to discard such replies and wished to

proceed with the matter on merit in the context of

blacklisting the petitioner, he should have shown

deference by issuing further intimation with more details

eliciting the circumstances that the petitioner was

required to explain as to its “constant non-achievement

of milestone on insufficient and imaginary ground and

non-adherence to quality specifications despite being

pointed out”. If the replies dated 23.10.2023 does not

reveal that the petitioner has offered specific explanation

indicating both the aspects on the ground vide sub-rule

(c) of Rule A of the Appendix-XXXIV, OPWD Code,

Volume-II, the authority should have shown alacrity by

issuing further notice by mentioning specific instance/

W.P.(C) No.8589 of 2024 Page 62 of 89

ground to which the petitioner was required to place his

defence/explanation.

9.29. In A.K.G. Construction and Developers Pvt. Ltd. Vrs. State

of Jharkhand, (2026) 4 SCR 331 it has been highlighted

as follows:

“23. The contractual relationship between the parties is

governed by two legal regimes. While GCC governs

termination, the 2012 Rules govern blacklisting.

Proceedings for termination should not be conflated

with proceedings for blacklisting. In the latter action,

what is at stake is the future of the contractor. A

blacklisting order assumes that the contractor is an

incorrigible entity, at least for some time to come, in

this case such an assumption was intended to

operate for five years. For giving effect to such a

premise, there has to be sufficient evidence, clear

application of mind and stronger adherence to

principles of natural justice

7. The blacklisting order

dated 23.08.2004 falls short of this requirement and

is liable to be set aside.”

9.30. Hence, the order dated 30.03.2024 passed by the Chief

Engineer, Bridges (WBP), Odisha cannot withstand

judicial scrutiny.

10. Reading of order dated 30.03.2024 of the Chief

Engineer, Bridges (WBP), Odisha debarring the

petitioner for six years manifests that he has invoked

7

Kulja Industries Ltd. Vrs. Chief General Manager, Western Telecom Project BSNL,

(2014) 14 SCC 731; Blue Dreamz Advertising (P) Ltd. Vrs. Kolkata Municipal

Corporation, (2024) 15 SCC 264, Techno Prints Vrs. Chhattisgarh Textbook

Corporation, (2025) 3 SCR 208.

W.P.(C) No.8589 of 2024 Page 63 of 89

Rule D of Appendix-XXXIV as amended by virtue of

Office Memorandum, dated 26.11.2021. As per such

amended provision, the blacklisting period per offence

shall be limited to three years subject to an overall

maximum cumulative period of ten years for multiple

offences. Neither Show Cause Notices nor does the order

impugned reveal that there was any proposition to

initiate proceeding to impose punishment for cumulative

period with respect to multiple “offences” attracting

Codal Provisions for banning/blacklisting contractor.

10.1. The term “offence” as found place in Rule D of Appendix-

XXXIV has not been defined in the OPWD Code. The

Hon’ble Supreme Court of India in the case of Standard

Chartered Bank Vrs. Directorate of Enforcement, (2006) 4

SCC 278 laid down the interpretation of “offence” in

absence of definition in the following manner:

“29. Both, Section 50 providing for imposition of penalty

and Section 56 providing for prosecution, speak of

contravention of the provisions of the Act.

Contravention is the basic element. The

contravention makes a person liable both for penalty

and for prosecution. Even though the heading to

Section 56 refers to offences and prosecutions, what

is made punishable by the section is the

contravention of the provisions of the Act and the

prosecution is without prejudice to any award of

penalty. The award of penalty is also based on the

same contravention. Section 63 confers the power of

W.P.(C) No.8589 of 2024 Page 64 of 89

confiscation of currency, security or any other money

or property in respect of which a contravention of the

provisions of the Act has taken place conferred

equally on the adjudicating authority and the court,

whether it be during an adjudication of the penalty

or during a prosecution. Whereas Section 64(1)

relating to preparation or attempt at contravention is

confined to Section 56, the provision for prosecution,

sub-section (2) of Section 64 makes the attempt to

contravene or abetment of contravention, itself a

contravention, for the purposes of the Act including

an adjudication of penalty under the Act. Section 68

relating to offences by companies, by sub-section (1)

introduces a deeming provision that the person who

was in charge of and was responsible to the

company for the conduct of the business of the

company, shall also be deemed to be guilty along

with the company of the contravention of the

provisions of the Act and liable to be proceeded

against and punished accordingly. The proviso, no

doubt, indicates that a person liable to punishment

could prove that the contravention took place without

his knowledge or that he exercised all due diligence

to prevent such contravention. Sub-section (2) again

speaks only of a contravention of the provisions of

the Act and the persons referred to in that sub-

section are also to be deemed to be guilty of the

contravention and liable to be proceeded against

and punished accordingly.

The word “offence” is not defined in the Act.

According to Concise Oxford English Dictionary, it

means, “an act or instance of offending”. Offend

means, “commit an illegal act” and illegal means,

“contrary to or forbidden by law”. According to New

W.P.(C) No.8589 of 2024 Page 65 of 89

Shorter Oxford English Dictionary, an offence is “a

breach of law, rules, duty, propriety, etiquette, an

illegal act, a transgression, sin, wrong,

misdemeanour, misdeed, fault”. Thus, an offence

only means the commission of an act contrary to or

forbidden by law. It is not confined to the

commission of a crime alone. It is an act committed

against law or omitted where the law requires it and

punishable by it. In its legal signification, an offence

is the transgression of a law; a breach of the laws

established for the protection of the public as

distinguished from an infringement of mere private

rights; a punishable violation of law, a crime, the

doing that which a penal law forbids to be done or

omitting to do what it commands (see P. Ramanatha

Aiyar‟s Advanced Law Lexicon, 3rd Edn., 2005, p.

3302).

This Court in Depot Manager, Andhra Pradesh State

Road Transport Corporation Vrs. Mohd. Yousuf

Miya, (1997) 2 SCC 699 stated that the word

“offence” generally implies infringement of a public

duty, as distinguished from mere private rights

punishable under criminal law.

In Brown Vrs. Allweather Mechanical Co., (1954) 2

QB 443 = (1953) 1 All ER 474 = (1953) 2 WLR 402

(DC) it was described as: (All ER p. 476 A-B)

A failure to do something prescribed by a statute

may be described as an offence, though no criminal

sanction is imposed but merely a pecuniary sanction

recoverable as a civil debt.

The expression “offence” as defined in Section 3(38)

of the General Clauses Act means an act or omission

W.P.(C) No.8589 of 2024 Page 66 of 89

made punishable by any law for the time being in

force.

“Punishable” as noticed by this Court in Sube Singh

Vrs. State of Haryana, (1989) 1 SCC 235 is

ordinarily defined as deserving of, or capable or

liable to punishment. According to Concise Oxford

English Dictionary, “punish” means, “inflict a

penalty on as retribution for an offence, inflict a

penalty on someone for (an offence)”.

In New Shorter Oxford English Dictionary (Vol. 2, 3rd

Edn., reprint 1993), the meaning of “punishment” is

given as, “infliction of a penalty in retribution for an

offence; penalty imposed to ensure application and

enforcement of a law”.

Going by Black ‟s Law Dictionary (8th Edn.) it is:

“A sanction— such as a fine, penalty, confinement,

or loss of property, right, or privilege— assessed

against a person who has violated the law.”

According to Jowitts Dictionary of English Law, Vol.

2, (2nd Edn. by John Burke), punishment is the

penalty for transgressing the law.

It is significant to notice that Section 68, both in sub-

section (1) and in sub-section (2) uses the

expression, shall be liable to be proceeded against

and punished accordingly. There does not appear to

be any reason to confine the operation of Section 68

only to a prosecution and to exclude its operation

from a penalty proceeding under Section 50 of the

Act, since the essential ingredient of both is the

contravention of the provisions of the Act. A

company is liable to be proceeded against under

W.P.(C) No.8589 of 2024 Page 67 of 89

both the provisions. Section 68 is only a provision

indicating who all in addition can be proceeded

against when the contravention is by a company or

who all should or could be roped in, in a

contravention by a company. Section 68 only

clarifies the nature and mode of proceeding when

the contravention of any of the provisions of the Act

is by a company, whether it be by way of

adjudication to impose a penalty or by way of

prosecution leading to imprisonment and a fine.”

10.2. In Black‟s Law Dictionary by Henry Campbel l Black,

Revised Fourth Edition [St. Paul, Minn., West Publishing

Co., 1968] the meaning of the terms “cumulative”,

“cumulative punishment” and “cumulative sentences”

have been described as follows:

“Cumulative.— Additional; heaping up; increasing;

forming an aggregate. The word signifies that two things

are to be added together, instead of one being a repetition

or in substitution of the other. People Vrs. Superior Court,

10 Wend., N.Y., 285; Regina Vrs. Eastern Archipelago,

Co., 18 Eng. Law & Eq. 183.

Cumulative punishment.—

An increased punishment inflicted for a second or third

conviction of the same offense, under the statutes relating

to habitual criminals. State Vrs. Hambly, 126 N.C. 1066,

35 S.E. 614.

Cumulative sentences.— Separate sentences (each

additional to the others) imposed upon a defendant who

has been convicted upon an indictment containing several

counts, each of such counts charging a distinct offense, or

W.P.(C) No.8589 of 2024 Page 68 of 89

who is under conviction at the same time for several

distinct offenses; one of such sentences being made to

begin at the expiration of another. Carter Vrs. Mc-

Claughry, 22 S.Ct. 181, 183 U.S. 365, 46 L.Ed. 236.”

10.3. Thus being conspectus of the terms “offence”,

“cumulative”, “cumulative offence”, and “cumulative

sentences”, there can be no confusion rests in mind that

there must first be a recording of finding that the

various offences are charged and proved/established by

clear evidence vis-à-vis explanation by the defender and

such offences warrants imposition of punishments/

penalties to be treated cumulatively. Ground contained

in sub-rule (c) of Rule A of Appendix-XXXIV of the OPWD

Code, Volume-II is clear indication that the twin

conditions enumerated therein are required to be

fulfilled before taking action for banning/blacklisting/

debarring for more than one offence contemplated in the

introduced provision by virtue of Office Memorandum

dated 26.11.2021.

10.4. It may be pertinent to have regard to the interpretation

of penal provisions as reiterated in Fuleshwar Gope Vrs.

Union of India, (2024) 10 SCR 315:

“31. It is well understood that penal statutes are statutes

to be interpreted strictly. This canon of construction

has been reiterated time and again. It is apposite

here to refer to certain authorities in this context.

W.P.(C) No.8589 of 2024 Page 69 of 89

31.1 Maxwell in The Interpretation of Statutes (11th Edn.)

has observed:

„The effect of the rule of strict construction might

almost be summed up in the remark that, where an

equivocal word or ambiguous sentence leaves a

reasonable doubt of its meaning which the cannons

of interpretation failed to solve, the benefit of the

doubt should be given to the subject and against the

legislature which has failed to explain itself. But it

yields to the paramount rule that every statute is to

be expounded according to its expressed or manifest

intention and that all cases within the mischief

aimed at our, if the language permits, to be held to

fall within its remedial influence‟

Observations in the twelfth edition, in this context,

are also educative:

„The strict construction of penal statutes seems

to manifest itself in four ways : In the

requirement of express language for the creation of

an offence; in interpreting strictly words setting out

the elements of an offence; in requiring the

fulfillment to the letter of statutory conditions

precedent to the infliction of punishment; and in

insisting on the strict observance of technical

provisions concerning criminal procedure and

jurisdiction.‟ ***”

10.5. Show Cause Notices dated 18.10.2023 (Annexure-11)

and consequent order dated 30.03.2024 (Annexure-1) do

not transpire that the authority has returned any finding

as to “offence” being committed by the petitioner and

there was scope in the circumstances to impose

W.P.(C) No.8589 of 2024 Page 70 of 89

penalties/punishments like debarment/blacklisting to

have cumulative effect. In absence of such finding being

recorded on the material available on record, this Court

is of the opinion that the circumstances did not exist

warranting the petitioner to ban “from participating or

bidding for any work to be undertaken by the

Government of Odisha” and “from transacting business

with the Government of Odisha directly, in the name of

proprietary bidder or indirectly under different name or

title” for a period of “six years”.

10.6. In absence of proper, clear, unequivocal and specific

charge being stated in the Show Cause Notices

(Annexure-11) as indicated in the foregoing paragraphs,

with reference to the Office Memorandum dated

26.11.2021 the Chief Engineer proceeded on an

erroneous approach as if the blacklisting could be

clamped consecutively for six years (limited to three

years per offence) at the drop of the hat. As is already

observed that the petitioner had had no opportunity to

justify the reasons for not being able to complete the

works within the period stipulated, the instruction to

complete the works by the authority concerned appears

to be during the pandemic, i.e., 2020-21 or 2021-22. The

reply dated 23.10.2023 cannot be construed to be

explanation on the merit; rather it is only intimation

regarding pendency of cases before this Court against

W.P.(C) No.8589 of 2024 Page 71 of 89

rescission of contract(s) by way of filing writ petitions. Be

that be. In view of A.K.G. Construction and Developers

Pvt. Ltd. Vrs. State of Jharkhand, (2026) 4 SCR 331 since

it is not forthcoming that the petitioner is incorrigible

entity upon analysis of sufficient evidence, clear

application of mind and stronger adherence to principles

of natural justice, it is entitled to the benefit of audi

alteram partem and right to reason with respect to

banning/blacklisting/debarment having impact on its

future transactions which in the considered view of this

Court falls within the connotation of “civil death” and

“civil consequences”.

10.7. In this respect the decision of the Hon’ble Supreme

Court of India rendered in ASP Traders Vrs. State of

Uttar Pradesh, (2025) 7 SCR 1462 may be pertinent to

derive guidelines for the administrative authorities to

proceed with the Show Cause Notice. The following

summation of principles as propounded in the said

reported case may be taken as guidelines in the present

matter:

“18. The principles of natural justice mandate that when

a taxpayer submits a response to a show cause

notice, the adjudicating authority is required to

consider such response and render a reasoned,

speaking order. This is not a mere procedural

formality, but a substantive safeguard ensuring

fairness in quasi-judicial proceedings. The right to

W.P.(C) No.8589 of 2024 Page 72 of 89

appeal under Section 107 of the CGST Act, 2017, is

predicated upon the existence of a formal

adjudication. An appeal can lie only against an

„order‟, and in the absence of a reasoned order

passed under Section 129(3) of the Act, the taxpayer

is effectively deprived of the statutory remedy of

appeal. Such a deprivation undermines the

foundational principles of fairness, due process, and

access to justice, rendering the right of appeal

illusory or nugatory. It is now settled law that failure

to issue a speaking order in response to a show

cause notice creates a legal vacuum. Any

consequential action including imposition of tax or

penalty, would then be unsupported by authority of

law, thereby potentially violating Article 265 of the

Constitution of India, which prohibits the levy or

collection of tax except by authority of law.

18.1. In this context, useful guidance may be drawn from

the decision in M/s. Kranti Associates (P) Ltd & Anr.

Vrs. Masood Ahmed Khan & Ors., (2010) 9 SCC 496,

wherein, this Court emphasized that fairness,

transparency, and accountability are inseparable

from the duty to provide reasons. The Court held

that failure to furnish reasons violates the principles

of natural justice and renders the right of appeal or

judicial review illusory. In paragraph 51 of the

judgment, the Court distilled the following key

principles:

„a. In India the judicial trend has always been to

record reasons, even in administrative

decisions, if such decisions affect anyone

prejudicially.

W.P.(C) No.8589 of 2024 Page 73 of 89

b. A quasi-judicial authority must record reasons

in support of its conclusions.

c. Insistence on recording of reasons is meant to

serve the wider principle of justice that justice

must not only be done it must also appear to be

done as well.

d. Recording of reasons also operates as a valid

restraint on any possible arbitrary exercise of

judicial and quasi-judicial or even

administrative power.

e. Reasons reassure that discretion has been

exercised by the decision maker on relevant

grounds and by disregarding extraneous

considerations.

f. Reasons have virtually become as

indispensable a component of a decision

making process as observing principles of

natural justice by judicial, quasi-judicial and

even by administrative bodies.

g. Reasons facilitate the process of judicial review

by superior Courts.

h. The ongoing judicial trend in all countries

committed to rule of law and constitutional

governance is in favour of reasoned decisions

based on relevant facts. This is virtually the life

blood of judicial decision making justifying the

principle that reason is the soul of justice.

i. Judicial or even quasi-judicial opinions these

days can be as different as the judges and

authorities who deliver them. All these

W.P.(C) No.8589 of 2024 Page 74 of 89

decisions serve one common purpose which is

to demonstrate by reason that the relevant

factors have been objectively considered. This

is important for sustaining the litigants‟ faith in

the justice delivery system.

j. Insistence on reason is a requirement for both

judicial accountability and transparency.

k. If a Judge or a quasi-judicial authority is not

candid enough about his/her decision making

process then it is impossible to know whether

the person deciding is faithful to the doctrine of

precedent or to principles of incrementalism.

l. Reasons in support of decisions must be

cogent, clear and succinct. A pretence of

reasons or „rubber-stamp reasons‟ is not to be

equated with a valid decision making process.

m. It cannot be doubted that transparency is the

sine qua non of restraint on abuse of judicial

powers. Transparency in decision making not

only makes the judges and decision makers

less prone to errors but also makes them

subject to broader scrutiny. (See David Shapiro

in Defence of Judicial Candor (1987) 100

Harward Law Review 731-737).

n. Since the requirement to record reasons

emanates from the broad doctrine of fairness in

decision making, the said requirement is now

virtually a component of human rights and was

considered part of Strasbourg Jurisprudence.

See (1994) 19 EHRR 553, at 562 para 29 and

Anya vs. University of Oxford, 2001 EWCA Civ

W.P.(C) No.8589 of 2024 Page 75 of 89

405, wherein the Court referred to Article 6 of

European Convention of Human Rights which

requires, “adequate and intelligent reasons

must be given for judicial decisions”.

o. In all common law jurisdictions judgments play

a vital role in setting up precedents for the

future. Therefore, for development of law,

requirement of giving reasons for the decision

is of the essence and is virtually a part of “Due

Process”.”

19. Therefore, even assuming that the payment was

made by the appellant, voluntarily or otherwise, the

proper officer could not be absolved of the statutory

obligation to pass a reasoned order in Form GST

MOV-09 and upload the corresponding summary in

Form GST DRC-07. Compliance with these

procedural requirements is essential not only for

ensuring transparency and accountability in tax

administration, but also for safeguarding the

taxpayer‟s appellate rights under the CGST Act,

2017. Such adherence is in consonance with the

constitutional mandate under Article 265 of the

Constitution of India.”

Conclusion:

11. As discussed supra neither the order dated 30.03.2024

(Annexure-1) nor the Show Cause Notices dated

18.10.2023 (Annexure-11) indicate the grounds for

blacklisting in terms of Rule A of Appendix-XXXIV of

OPWD Code in clear and unequivocal terms. The Show

Cause Notices are silent about existence of twin

W.P.(C) No.8589 of 2024 Page 76 of 89

conditions as a ground envisaged in sub-rule (a) of Rule

A for blacklisting nor is there any finding of fact

returned in the impugned order to show such ground

(twin conditions) established. Therefore, this matter

deserves intervention.

11.1. The ban/debarment/blacklisting is construed as “civil

death” having substantial impact on the fundamental

right to carry on business as envisioned under Article

19(1)(g) of the Constitution of India, and as such penal

action leads to civil or evil consequence, the provisions

vesting power on the authority to impose penalties are

required to be conceived strictly.

11.2. It is true that penal provisions must be strictly

construed; but having regard to the nature of the offence

involved, such strict construction may be refused to be

adopted. Looking to the gravity of offence, narrow and

pedantic, literal and lexical construction of penal

provisions can be eschewed. Reference may be had to

Murlidhar Meghraj Loya Vrs. State of Maharashtra, (1976)

3 SCC 684 and Kisan Trimbak Kothula Vrs. State of

Maharashtra, (1977) 1 SCC 300. Having regard to the

intent of the OPWD Code, harmonious construction may

be adhered to while invoking the provisions of Appendix-

XXXIV so as to strike a balance between the right of the

contractee-Government and the right of the contractor.

W.P.(C) No.8589 of 2024 Page 77 of 89

11.3. This apart, one must bear in mind that Codal Provisions

in Appendix-XXXVI is part of the OPWD Code, which are

executive instructions and mere procedures facilitating

smooth functioning of works entrusted to the

contractors. It is well settled that procedural laws must

be liberally construed to serve as handmaid of justice

and not as its mistress. [See, Sardar Amarjit Singh Kalra

Vrs. Pramod Gupta, (2003) 3 SCC 272, N. Balaji Vrs.

Virendra Singh, (2004) 8 SCC 312 and Kailash Vrs.

Nanhku, (2005) 4 SCC 480].

11.4. In G.J. Fernandez Vrs. State of Mysore, (1967) 3 SCR 636

= AIR 1967 SC 1753 it has been observed thus:

“12. Taking first the contention with respect to the Code

not being followed in the matter of tenders, the

question that arises is whether this Code consists of

statutory rules or not. The High Court has observed

that the so-called rules in the Code are not framed

either under any statutory enactment or under any

provision of the Constitution. They are merely in the

nature of administrative instructions for the

guidance of the department and have been issued

under the executive power of the State. Even after

having said so, the High Court has considered

whether the instructions in the Code were followed

in the present case or not. Before however we

consider the question whether instructions in the

Code have been followed or not, we have to decide

whether these instructions have any statutory force.

If they have no statutory force, they confer no right

on any body and a tenderer cannot claim any rights

W.P.(C) No.8589 of 2024 Page 78 of 89

on the basis of these administrative instructions. If

these are mere administrative instructions it may be

open to Government to take disciplinary action

against its servants who do not follow these

instructions but non-observance of such

administrative instructions does not in our opinion

confer any right on any member of the public like a

tenderer to ask for a writ against Government by a

petition under Article 226. The matter may be

different if the instructions contained in the Code are

statutory rules. Learned counsel for the appellant is

unable to point out any statute under which these

instructions in the Code were framed. He also

admits that they are administrative instructions by

Government to its servants relating to the Public

Works Department. But his contention is that they

are rules issued under Article 162 of the

Constitution. Now Article 162 provides that

“executive power of a State shall extend to the

matters with respect to which the legislature of the

State has power to make laws”. This Article in our

opinion merely indicates the scope of the executive

power of the State; it does not confer any power on

the State Government to issue rules thereunder. As

a matter of fact wherever the Constitution envisages

issue of rules it has so provided in specific terms.

We may for example, refer to Article 309, the proviso

to which lays down in specific terms that the

President or the Governor of a State may make rules

regulating the recruitment and the conditions of

service of persons appointed to services and posts

under the Union or the State. We are therefore of

opinion that Article 162 does not confer any power

on the State Government to frame rules and it only

indicates the scope of the executive power of the

W.P.(C) No.8589 of 2024 Page 79 of 89

State. Of course, under such executive power, the

State can give administrative instructions to its

servants how to act in certain circumstances; but

that will not make such instructions statutory rules

which are justiciable in certain circumstances. In

order that such executive instructions have the force

of statutory rules it must be shown that they have

been issued either under the authority conferred on

the State Government by some statute or under

some provision of the Constitution providing therefor.

It is not in dispute that there is no statute which

confers any authority on the State Government to

issue rules in matters with which the Code is

concerned; nor has any provision of the Constitution

been pointed out to us under which these

instructions can be issued as statutory rules except

Article 162. But as we have already indicated,

Article 162 does not confer any authority on the

State Government to issue statutory rules. It only

provides for the extent and scope of the executive

power of the State Government, and that coincides

with the legislative power of the State Legislature.

Thus under Article 162, the State Government can

take executive action in all matters in which the

legislature of the State can pass laws. But Article

162 itself does not confer any rule making power on

the State Government in that behalf. We are

therefore of opinion that instructions contained in the

Code are mere administrative instructions and are

not statutory rules. Therefore even if there has been

any breach of such executive instructions that does

not confer any right on the appellant to apply to the

court for quashing orders in breach of such

instructions. It is unnecessary for us to decide

whether there has been in fact a breach of any

W.P.(C) No.8589 of 2024 Page 80 of 89

instruction contained in the Code with respect to

tenders and we do not therefore so decide. But

assuming that there has been any breach that is a

matter between the State Government and its

servant, and the State Government may take

disciplinary action against the servant concerned

who disobeyed these instructions. But such

disobedience did not confer any right on a person

like the appellant, to come to court for any relief

based on the breach of these instructions. It is for

this reason that we are not referring to the Code,

though the High Court did consider whether there

was any breach of these administrative instructions

and came to the conclusion that there was no

breach. In the view we take it is unnecessary for us

to consider this, for we are of opinion that no claim

for any relief before a court of law can be founded

by a member of the public, like the appellant, on the

breach of mere administrative instructions.”

11.5. In P. Tulsi Das Vrs. Government of Andhra Pradesh,

(2002) Supp.3 SCR 306 it has been laid down as follows:

“On a careful consideration of the principles laid down in

the above decisions in the light of the fact situation in

these appeals we are of the view that they squarely apply

on all fours to the cases on hand in favour of the

appellants. The submissions on behalf of the respondent-

State that the rights derived and claimed by the

appellants must be under any statutory enactment or

Rules made under Article 309 of the Constitution of India

and that in other respects there could not be any

acquisition of rights validly, so as to disentitle the State to

enact the law of the nature under challenge to set right

serious anomalies which crept in and deserved to

W.P.(C) No.8589 of 2024 Page 81 of 89

undone, does not merit our acceptance. It is by now well

settled that in the absence of Rules under Article 309 of

the Constitution in respect of a particular area, aspect or

subject, it was permissible for the State to make

provisions in exercise of its executive powers under Article

162 which is co-extensive with its Legislative powers

laying conditions of service and rights accrued to or

acquired by a citizen would be as much rights acquired

under law and protected to that extent. The orders passed

by the Government, from time to time beginning from

February 1967 till 1985 and at any rate upto the passing

of the Act, to meet the administrative exigencies and cater

to the needs of public interest really and effectively

provided sufficient legal basis for the acquisition of rights

during the period when they were in full force and effect.

The orders of the High Court as well as the Tribunal also

recognised and upheld such rights and those orders

attained finality without being further challenged by the

Government, in the manner known to law. Such rights,

benefits and perquisites acquired by the Teachers

concerned cannot be said to be rights acquired otherwise

than in accordance with law or brushed aside and

trampled at the sweet will and pleasure of the

Government, with impunity. Consequently we are unable

to agree that the Legislature could have validly denied

those rights acquired by the appellants retrospectively,

not only depriving them of such rights but also enact a

provision to repay and restore the amounts paid to them

to State. The provisions of the Act, though can be valid in

its operation „in futuro‟ cannot be held valid in so far as it

purports to restore status quo ante for the past period

taking away the benefits already available, accrued and

acquired by them. For all the reasons stated above the

reasons assigned by the majority opinion of the Tribunal

could not be approved in our hands. The provisions of

W.P.(C) No.8589 of 2024 Page 82 of 89

Section 2 and 3(a) insofar as they purport to take away

the rights from 10.02.1967 and obligates those who had

them to repay or restore it back to the State is hereby

struck down as arbitrary, unreasonable and

expropriatory and as such is violative of Articles 14 and

16 of the Constitution of India. No exception could be

taken, in our view, to the prospective exercise of powers

thereunder without infringing the rights already acquired

by the appellants and the category of the persons

similarly situated whether approached courts or not

seeking relief individually. The provisions contained in

Section 2 have to be read down so as to make it only

prospective, to save the same from the unconstitutionality

arising out of its retrospective application.”

11.6. In the case of R. Sai Bharathi Vrs. J. Jayalalitha, (2003)

Supp.6 SCR 85, the Hon’ble Supreme Court held:

“Even if the Government order is traced to have been

issued under executive power of the State under

Article 162, such a Code will not be enforceable

when the language used is not in mandatory terms

and they are intended to be mere guidelines or

instructions to the concerned persons in authority.

Therefore, as long as such a Code of Conduct is not

enforceable in any court of law and does not even provide

what action could possibly be taken in case of breach by

the Chief Minister, the prohibition contained therein is

only having ethical or moral effect and any breach thereof

cannot be treated to be unlawful or even illegal within the

meaning of Section 43 IPC. To constitute a ground for civil

action under Section 43, there must be a right in a party

which can be enforced. It may be a breach of contract or a

claim for damages or some such similar right accruing

under any law. There is no law which debars the Chief

W.P.(C) No.8589 of 2024 Page 83 of 89

Minister from participating in a sale conducted by any

Department of the Government or any of the Corporations

or any public sector undertaking affording a cause for civil

action especially when no fraud or illegal gain .is

involved. Therefore, we are constrained to hold that the

offence under the aforesaid provision has not been

established. In fact, there is nothing in the charge to

indicate nor did the prosecution take a specific stand at

any stage of the trial that the purchase of T ANSI foundry

property by A-I from the Government would furnish a

ground for a particular civil action. The nature of civil

action that could be initiated cannot be left to the guess

work and the accused cannot be expected to meet such

case at this stage.”

11.7. Thus, with the above conspectus of legal position with

respect to executive instructions compiled in the form of

a Code (here OPWD Code), they are construed to be

guidelines to the authorities of the Departments of the

Government and the language of any of such

instructions is in the nature of mandatory character, the

authority is obligated to strictly adhere to the same.

While the provisions dealing with procedural aspect

conferring power to invoke authority and arrive at the

conclusion are procedural in nature which can be

construed liberally, the provision enabling the authority

to impose penalty like banning/blacklisting/debarring is

to be interpreted strictly as the same would involve civil

or evil consequence having restrictive impact on the

business of the contractor offending Article 14 read with

W.P.(C) No.8589 of 2024 Page 84 of 89

Article 19(1)(g) of the Constitution of India. Any decision

to blacklist/debar a contractor from participating in

tenders need to be taken strictly within the parameters

of law and has to comport with the principle of

proportionality.

11.8. Such view has explicitly been stated in Blue Dreamz

Advertising (P) Ltd. Vrs. Kolkata Municipal Corporation,

(2024) 15 SCC 264 with the following observations:

“24. What is significant is that while setting out the

guidelines prescribed in USA, the Court noticed that

comprehensive guidelines for debarment were

issued there for protecting public interest from those

contractors and recipients who are non-responsible,

lack business integrity or engage in dishonest or

illegal conduct or are otherwise unable to perform

satisfactorily. The illustrative cases set out also

demonstrate that debarment as a remedy is to be

invoked in cases where there is harm or potential

harm for public interest particularly in cases where

the person‟s conduct has demonstrated that

debarment as a penalty alone will protect public

interest and deter the person from repeating his

actions which have a tendency to put public interest

in jeopardy. In fact, it is common knowledge that in

notice inviting tenders, any person blacklisted is

rendered ineligible. Hence, blacklisting will not only

debar the person concerned from dealing with the

employer concerned, but because of the

disqualification, their dealings with other entities

also is proscribed. Even in the terms and conditions

of tender in the present case, one of the conditions of

W.P.(C) No.8589 of 2024 Page 85 of 89

eligibility is that the agency should not be

blacklisted from anywhere.

25. In other words, where the case is of an ordinary

breach of contract and the explanation offered by

the person concerned raises a bona fide dispute,

blacklisting/debarment as a penalty ought not to be

resorted to. Debarring a person albeit for a certain

number of years tantamounts to civil death

inasmuch as the said person is commercially

ostracised resulting in serious consequences for the

person and those who are employed by him.

26. Too readily invoking the debarment for ordinary

cases of breach of contract where there is a bona

fide dispute, is not permissible. Each case, no doubt,

would turn on the facts and circumstances thereto.

27. Examining the facts of this case from that

perspective, we find that the appellant, after the

award of the tender, has admittedly paid an amount

of Rs.3,71,96,265, though, according to the

Corporation, the outstanding amount as on the date

of the debarment was Rs.14,63,24,727. However,

as would be clear from the facts discussed

hereinabove, right from the inception there have

been issues between the appellant and the

Corporation with regard to the fulfilment of the

reciprocal obligations in the bid document. There has

been exchange of correspondence between the

parties with each side blaming the other for not

performing the reciprocal obligations. While the

appellant had a case with regard to the non-

issuance of work orders; non-receipt of formal format

of bank guarantee; refusal of no-objection certificate

for obtaining connection from Calcutta Electric

W.P.(C) No.8589 of 2024 Page 86 of 89

Supply Corporation Ltd.; existence of only 200 out of

250 allotted street hoardings and so on

demonstrating breach of obligations by the

Corporation, the Corporation had a case that bank

guarantee was not the mode of payment and as

such there was no reason to insist on bank

guarantee; that in the joint inspection the appellant's

men failed to cover all the areas and thereafter

when the appellant was asked to submit a list of

allotted location, the appellant failed to furnish the

same and further there was huge default on the part

of the appellant.

28. Even in the order dated 02.03.2016 by which the

appellant was debarred for a period of five years,

the reason given is that the tender notice had clearly

stated that the street hoardings in the annexures

would be allotted on “as is where is” basis; that the

company having understood the scope and effect of

the terms and conditions of the notice accepted the

award; that “no-objection certificate” is not required

in respect of the existing hoardings; that there was

no document to show that the company had applied

to Calcutta Electric Supply Corporation Ltd. for

connection and that it appeared to the Corporation

that the company did not have the financial capacity

to pay and as such the company was creating

problems on one pretext or the other since obtaining

the allotment of sites. The order also stated that the

appellant had set up a bad example to others having

interest to enjoy the advertisement rights.

29. All these reasons fall far short of rendering the

conduct of the appellant in the present case, so

abhorrent as to justify the invocation of the drastic

W.P.(C) No.8589 of 2024 Page 87 of 89

remedy of blacklisting/debarment. The appellant

very clearly has been subjected to a

disproportionate penalty. The Corporation has lifted

a sledgehammer to crack a nut. We disapprove of

the said course of action on the facts of this case.

***

34. The Division Bench has, in our opinion, not

appreciated the case in its proper perspective.

Merely saying that the blacklisting order carried

reasons is not good enough. Do the reasons justify

the invocation of the penalty of blacklisting and is

the penalty proportionate, was the real question.

35. The Division Bench has observed that blacklisting is

a business decision by which the party affected by

the breach decides not to enter into any contractual

relationship with the party committing the breach. It

also observed that between two private parties the

right to take any such decision is absolute and

untrammelled by any constraints whatsoever. The

observations are too sweeping in their ambit and

wholly overlook the fact that the respondent

Corporation is a statutory body vested with the duty

to discharge public functions. It is not a private

party. Any decision to blacklist should be strictly

within the parameters of law and has to comport

with the principle of proportionality.

36. The Division Bench having noticed the fact that any

decision to blacklist will be open to scrutiny on the

anvil of the doctrine of proportionality has failed to

apply the principle to the facts of the case in the

correct perspective. The Division Bench has also

failed to correctly appreciate the ratio of the decision

W.P.(C) No.8589 of 2024 Page 88 of 89

in B.S.N. Joshi & Sons Ltd. Vrs. Nair Coal Services

Ltd., (2006) 11 SCC 548.

37. There has been no enquiry by the Division Bench as

to whether the conduct of the appellant was part of

the normal vicissitudes in business and common

place hazards in commerce or whether the appellant

had crossed the rubicon warranting a banishment

order, albeit for a temporary period in larger public

interest.”

11.9. In the wake of the above the order dated 30.03.2024

passed by the Chief Engineer, Bridges (WBP), Odisha

(Annexure-1) cannot be held to be tenable in the eye of

law and hence, the same is hereby quashed and set

aside. The matter is thus reverted to the stage of Show

Cause Notices dated 18.10.2023. However, liberty is

reserved to the petitioner to file reply to Show Cause

Notices and the authority may take this opportunity to

intimate the petitioner about existence of twin

conditions in clear, unambiguous and specific terms, if

such material is available on record, so that proper

defence/explanation can be prepared and reasons

explaining the ground suggested by the opposite parties

for banning/blacklisting/debarring can be cited.

11.10. In such event the authority concerned would be

required to consider such explanation and afford the

petitioner opportunity of hearing. After adhering to

formalities required for adhering to the principles of

W.P.(C) No.8589 of 2024 Page 89 of 89

natural justice, appropriate action may be taken by the

authority assigning reason for such decision.

11.11. Needless to observe that the decision taken thereon

shall be communicated to the petitioner forthwith. It is

clarified that until the ground(s) are examined in the

light of discussions made above and appropriate finding

is recorded thereon, the order of banning/blacklisting/

debarment ceases to operate.

12. In the result, finding merit in the writ petition the same

is allowed to the above extent and pending Interlocutory

Application(s), if any, shall stand disposed of, but in the

circumstances, there shall be no order as to costs.

I agree

(HARISH TANDON) (MURAHARI SRI RAMAN )

CHIEF JUSTICE JUDGE

High Court of Orissa, Cuttack