As per case facts, respondents sought permission for a multi-storey building. An initial sanction for an eight-storey building in April 1985 lapsed as no construction began within two years due ...
CALCUTTA MUNICIPAL CORPORATION & ANR.
v.
SRI ANIL RATAN BANERJEE AND ORS.
OCTOBER 26, 1994
[B.P. JEEV AN REDDY AND SUHAS C. SEN, JJ.]
Calcutta Municipal Corporation Act, 1951-Bengal Municipal Act,
1932-Construction-Multi-storeyed
Building-No commencement within
two years after sanction
of plan-Construction after two years-Held, fresh
permission to be obtained
Bengal Municipal
Act, 1932-Sections 379, 325-Deemed sanction
Held, not applicable when the sanction sought for is prohibited under law.
A
B
c
The Respondents entered into an Agreement with an owner of a
site. The Vendor
at the instance of the Respondent had sought
permission for construction
of eight storeyed building, which was D
sanctioned on 27.4.1985.
The permission became inoperative since no construction took
place
in the site due to disputes between the Respondents and the
Vendor.
The Respondents
withi~ the said period of two years, on 2.2.1987
applied for sanction
of a revised building plan with a changed layout.
They also appl!ed for renewal
of sanctioned plan on 16.4.87.
E
On 24.8.1987 the Respondents applied for permission to construct
twelve floors on the basis
of a new plan.
Since no orders were passed in F
any of these applications, the Respondents started to proceed with the
construction
in view of deemed permission -when it was obstructed,
the Respondents preferred a writ petition
in the High Court against the
petitioners. During the pendency
of the writ petition, the
Single Judge
had allowed the Respondents to make construction upto ground floor
levels
by interim orders subject to an undertaking that they would G
demolish the construction, if it is found to have been made in violation
of the
Plan submitted on 24th August, 1987.
The writ petition was allowed. The Writ Appeal filed by the
petitioners was also dismissed. In the present S.L.P., the petitioners
contended that
(1) the
Plan sanctioned on 27.4.1985 stood lapsed due to H
191
192 SUPREME COURT REPORTS [1994] SUPP. 5 S.C.R.
A no construction activity; (2) there is no provision for renewal of
sanction; (3) the sanction for 12 floors could not have been granted due
to the law
in force and (4) the maximum permissible height of the
building is only 8 meters.
B
c
D
Allowing the appeal, this Court
HELD : 1. The
responden~s are not legally entitled to make any
construction on the basis of the deemed sanctioned plan (submitted on
August
24., 1987) on or after September 24, 1989.
(200-D)
2. The High Court was, in error in permitting the respondents to
proceed with the construction
of the twelve storey building on the basis
of the Plan submitted on 24.8.1987 and in giving other allied directions. (200-E)
3. The construction made pursuant to the orders of the High Court
should allowed to be retained and two more floors may be constructed
by the Respondents
but not so as to exceed the total height of eight
metres -and not
at any rate beyond nine meters.
(201-A)
CIVIL APPELLATE JURISDICTION : Civil Appeal No. 7056 of
1994.
From the Judgment and Order dated 29.3.94
of the Calcutta High Court
E in F.M.A.T. No. 1718of1992.
F
G
IN
Special Leave Petition (C) No. 10331 of 1994.
Tapas Ray, Manoj
Prasad, Deva Prasad Mukherjee, Rajesh and Mrs. B.
Sunita Rao for the Appellar.ts/Petitioner.
K.K. Venugopal and Robin Mukherjee, Rajendra Singhvi and Ashok
K. Singh for the Respondents.
The Judgment
of the Court was delivered by
B.P.
JEEV AN REDDY, J. Leave granted. Heard counsel for the
parties.
The appeal
is preferred by the Calcutta Municipal Corporation against
the judgment
of a Division Bench of the Calcutta High Court dismissing
H F.M.A.T. No. 1718of1992
which was directed against the.iudgment ofa
CALCUTT A MUN. CORPN. v. A. R. BANERJEE [JEEV AN REDDY, J.] 193
learned single Judge allowing the writ petition filed by the respondents. The A ..
0
matter pertains to the grant of permission for construction of a multi-storey
building
in the
South Suburban area of Calcutta.
Until January 4, 1984, the Calcutta Municipal Corporation Act, 1951
governed the area then comprised in Calcutta municipality. The South
Suburban area, with which we are concerned herein, was not a part of B
Calcutta Municipal Corporation area until that date. It was an independent
municipality, governed by the Bengal Municipal Act, 1932. On January 4,
1984, the South Suburban municipal area alongwith certain other municipal
areas was merged with the Calcutta municipal corporation area and a new
Act viz., The Calcutta Municipal Corporation Act, 1980 was brought into C
force in place of the Calcutta Municipal Corporation Act, 1951. Even so,
the new Act governed and applied only to the original Calcutta municipal
corporation area but not to the newly added areas including the South
Suburban area. Since, regulations governing the construction of buildings
were not framed under the 1980 Act, the regulations made under the 1951 ·
Act continued to govern the original Calcutta municipal area, while the D
Bengal Municipal Act, 1932 including the regulations made thereunder
continued to govern the newly added areas including South Suburban area,
by virtue
of
Section 635 (ii) (g) of the 1980 Act.
On February 20, 1989, the Bengal Municipal Act and the rules made
thereunder ceased to apply to the newly added areas by virtue of an E
amendment to the Calcutta Municipal Corporation Act, 1980. The 1980 Act
was extended to the said newly added areas with effect from the said date.
(This was the effect
of omission of clause (g) of
Section 635 (ii) with effect
from the said date.) On 12th December, 1990, new building rules were
issued under the Calcutta Municipal Corporation Act, 1980.
F
The respondents-writ petitioners entered into an agreement with the
owner
of the site concerned herein,
Sri D.R.K. Kamani, to purchase the
same. They say that, at their instance, Sri Kamani applied to the Calcutta
municipal corporation for permission
to construct a multi-storeyed complex
on the said site, which is situated within the erstwhile
South Suburban G
municipal area. On April 27, 1985, the municipal corporation sanctioned
the plan for the construction of a eight-storeyed building. This sanction, it is
obvious, was given under and governed by the provisions
of Bengal
Municipal Act, 1932 and the regulations made thereunder, which were
in
force in the said area at that time. However, no construction was made
-not
even commenced -within two years of the permission, with the result that H
A
B
c
D
E
F
G
H
194 SUPREME COURT REPORTS (1994] SUPP. 5 S.C.R.
the said permission became ineffective and inoperative on the expiry of the
said period.
On F<:bruary 2, 1987, i.e., within the said two years period, the
respondents applied for sanction
of a revised building plan with eight
stories but
with a changed layout. On April 16, 1987, the respondents
applied for renewal
of the sanctioned plan dated April 27, 1985, without
withdrawing the application for the revised plan submitted on February 15,
1987.
On August 24, 1987 the respondents applied for perm1ss1on to
construct a building comprising
of twelve floors on the basis of a new plan.
No orders were passed by the Corporation authorities on any
of these three
applications within thirty days
of their respective submission.
On this basis,
the respondents say and assert that the permission applied for by them on
August 24, 1987 must be deemed to have been sanctioned on the expiry
of
thirty days by virtue of the
Section 319 of the Bengal Municipal Act, 1932.
{The municipal corporation, however, says that the said plan was rejected
on April 29, 1988; the respondents dispute the receipt of any such order.)
The respondents' case
is that when they proposed to proceed with the
construction
of the building in accordance with the plan submitted on
August 24, 1987, in view
of the deemed permission, the authorities of the
corporation obstructed the same and did not allow the constrnction to
proceed. This obstruction, according to the respondents, disentitles the
municipal corporation from objecting to
or interfering with their
construction
even after the expiry of two years from August 24, 1987.
-or
from September 24, 1987 (the dee.med permission is available and effective
from September 24, 1987, i.e., on the expiry of thirty days from the date of
application); as the case may be. The appellant-corporation, however, says,
firstly, that the respondents ~re not entitled to any deemed permission of the
plan applied for on August 24, 1987 inasmuch as the law then governing
did not pennit construction
of a twelve-storey building on the plot of the
respondents, having regard to the width
of the road abutting the said
plot/site.
Secondly, they say that even if it is assumed that any such deemed
pennission can be invoked by the respondents, the same came to an end on
the expiry
of two years, i.e., on
September 24, 1989 and inasmuch as the
respondents have not constructed the building within the said period
of two
years, the deemed pennission,
if any, can no longer enure to them
thereafter. They deny that they ever interfered with the construction
of the
building by the Respondents. According to them, no construction
whatsoever was undertaken on the said plot on account
of the differences
and disputes between the respondents and their vendor,
Sri Kamani.
..
CALCUITA MUN. CORPN. v. A. R. BANERJEE [JEEVAN REDDY, J.) 195
. .
Be that as it may, the respondents approached the Calcutta High Court A
by way of Writ Petition No. I 1814 of 1989 on September 28, 1989. The
prayers
in the writ petition are the following :
(a) to direct the respondent-corporation to issue a formal letter
certifying the building plan submitted on August 24, I 987 in terms
of
Section 319 of the Bengal Municipal Act, 1932; B
(b) to direct the municipality to issue a formal letter sanctioning the
revised building plan submitted on February
15, 1987 under
Section 319 of
the I 932 Act;
(c) to restrain the municipality from interfering with their construction C
in accordance with the plan submitted by them;
(d) to restrain the municipality from giving effect to any order (not
communicated to the writ petitioners)
in respect of the matters in issue;
(e) for a declaration that the plans submitted on August 24, 1987 and
D
February 15, 1987 are sanctioned by operation oflaw.
The learned
Single Judge allowed the writ petition on the following
· reasoning:
I. That there was no bar or impediment to renew the sanctioned plan
E
(for eight-storeyed building) granted on April 27, 1985, inasmuch as the
said sanction was given on a consideration
of all the relevant factors and
also because there has been no change
in the circumstances warranting
refusal
of renewal.
2. The building plan submitted on August 24, 1987 (for a twelve- F
storeyed building) fulfils the requisites of law and inasmuch as it was not
rejected within a period
of thirty days, it must be deemed to have been
sanctioned on the expiry
of thirty days. The writ petitioners have a riglrt to
start the construction
in
terms of such deetll"ed sanctioned plan.
The respondents were, accordingly, directed to permit the writ
G
petitioners to proceed with the construction in terms of the revised building
plan filed on August 24, 1987 on condition that the petitioners will not
commit breach
of any relevant Rules or bye-laws prevailing on the date of
filing of the said plan. The corporation was further directed to issue a
formal permission within sixty days. It was also directed that the said plan
H
A
B
c
D
E
F
G
H
196 SUPREME COURT REPORTS [1994] SUPP. 5 S.C.R.
must be deemed to have been sanctioned from the date of the said judgment
and its validity period shall be two years from that date.
On Appeal, the Division Bench referred to the frequent legislative
changes (referred to at the inception
of this judgment) and opined that since
it is difficult for the ordinary people to keep track
of the legislative changes,
"the Court has to take a practical and pragmatic view of the matter." It held
that "the plan submitted on August 24, 1987 should be treated as deemed to
have been sanctioned
as within the period of thirty days no objection was
taken. Subsequent objection beyond that statutory period
of thirty days
cannot change the legal fiction inasmuch as
in every case of deemed
sanction, construction has to be made strictly in accordance with the rules
and regulations or in other words no construction could be made on the
basis
of a deemed sanction of plan in contravention of the building rules
and regulations prevailing at the time when such plan
w~ deemed to have
been sanctioned." The Division Bench thus affirmed the finding of the
learned single Judge that the writ petitioners have a right to make
construction in accordance with the plan submitted on August 24, 1987 and
that it must be deemed to have been sanctioned on the expiry
of thirty days
therefrom.
The· correctness of the said view is questioned by the Calcutta
municipal corporation
in this Appeal.
Shri Tapas Ray, learned counsel for the municipal corporation, urged
the following contentions:
1. That the plan sanctioned on April 27, 1985 for a eight-storeyed
building lapsed on 26th
of April, 1987 since no construction was made and
completed within two years. Indeed, no construction was commenced by
that date. It
is true that on April 16, 1987 the respondents applied
;or
renewal of the said plan but there was no provision in the Bengal Municipal
Act for granting such renewal. Even assuming that such renewal could be
granted and must be deemed to have been granted, such deemed renewal
too expired on April
16, 1989 or, at any rate, on April 26, 1989.
Admittedly, no construction was made, much less completed, by the said
date.
In other words, the sanction of the said plan, both actual and deemed,
lapsed by 26th
of April, 1987 and 26th April 1989 respectively.
'No
construction can be permitted on the basis of such plan after the said dates.
2. So far as the deemed sanction of the twelve-storeyed building
applied for on August 24, 1987 is concerned, it cannot be deemed to have
been sanctioned on the expiry
of thirty days by virtue of Section 319 of the
Bengal
' Municipal Act for the reason that no such permission could have
CALCUTTA MUN. CORPN. v. A. R. BANERJEE [JEEVAN REDDY, J.] 197
been actually grahted under the law then in force in the said area, having A
regard to the width of the road abutting the respondents' plot and other
relevant circumstances. The Division Bench has itself recognised that the
deemed permissiob cannot be inconsistent with the relevant rules and
regulations. No deemed pe:mission can be conceived of which is
inconsistent with die relevant rules and regulations.
3. The position today
is that the building rules framed in the year, 1990
(with effect from
!December I, 1990) are more stringent than the pre
existing rules and regulations. According to these rules the maximum
height
of a building in the respondents' plot cannot exceed eight metres.
B
4. Both the learned single Judge and the Division Bench erred in not C
examining the question whether the plan for twelve-storeyed building
applied for by the respondents
on August 24, 1987 could at all have been
granted
in accordance with the law then in force in the said area. This
should have been done before granting the declaration that the said plan
must be deemed to have been granted and that the respondents are entitled
to make construction
in accordance therewith. D
5. The learned Judges of the High Court were not justified in holding
that the municipal authorities were negligent
in responding to the
respondents' applications for permission.
It is equally not correct to suggest
that the respondents are entitled to
an extended period for constructing a
building on account
of the alleged obstruction by the municipal authorities. E
Since no construction was ever made, there was no obstruction by the
authorities, and even
if there was such obstruction, it was perfectly valid
and justified since the respondents had no authority
in law to proceed with
the construction.
Sri K.K. Venugopal, learned counsel appearing for the respondents- F
writ petitioners, supported the reasoning and conclusion of the High Court
and submitted that the writ issued by the High Court
is nothing more than a
formalisation
of the legal position obtaining by virtue of
Section 319 of the
1932 Act. Learned counsel also brought to our notice, by way
of written
submissions, certain subsequent developments which according to the
G
learned counsel establish the mala tides on the part of the Corporation.
Now
it is true that on April 27, 1985 permission was granted for
construction
of a eight-storey building on the premises in question. But it is
admitted, at the same time, that no construction could be made within the
period
of two years therefrom because of the disputes between the H
A
B
c
D
E
F
G
H
198
SUPREME COURT REPORTS [1994] SUPP. 5 S.C.R.
respondents and Sri Karnani. (The learned single Judge has referred -to
these disputes in his Judgment and observed that because of these disputes,~
no construction could be undertaken by the writ petitioners. The learned
Judge has also recorded that the writ petitioners had to file a Suit for
specific performance which came to
an end only when conveyance deeds
were executed through Court
in favour of the writ petitioners. To the same
effect
is the statement of the Respondents-writ petitioners in Para 4 (g)
of
their counter filed in this appeal). These disputes were settled only some
time later. (A mutation certificate was granted on July 4, 1989 by Calcutta
municipal corporation
in favour of the respondents.) By virtue of Section
325
of the 1932 Act, no construction can be carried on after the expiry of
two years from the date of grant of permission. The petitioners say that they
had applied for renewal
of the said sanctioned plan on April 16, 1987.
Assuming that an application for renewal was indeed made and even
if by
virtue
of the fiction contained in Section 319 the said renewal permission is
deemed to have been granted, even then this renewed deemed permission
expired on April
16, 1989 -and, admittedly, even by this date no
construction has been made on the premises.
On 24th August, 1987 the
respondents had applied for permission to construct a twelve-storey
building and even
if we assume that such a permission must be deemed to
liave been granted by virtue of the
Section 319, this deemed permission too
came to an end on August 24, 1989 or say, on September 24, 1989. It has
been found by the learned single Judge that "Admittedly, no construction
has been raised within the premises either in terms
of the first building plan
sanctioned
in 1985 or in terms of the revised plan filed subsequently. There
is neither any specified permission of renewal nor there is any thing on
record to show that the writ petitioners have been permitted to go with the
construction either in terms
of the first building plan or in terms of the
revised building
plan." The Division Bench has not recorded any finding to
the ~ontrary. Indeed, the Division Bench has also recorded that "In the
instant case, because
of pendency of litigation and disputes the owner did
not think
it is to be fit to make any investment until and unless the matter is
set at
rest." Thus, it is clear that even by September 24, 1989, no
construction was made
by the respondents on the said premises.
The respondents, no doubt, assert that they had commenced
construction before 24th August, 1989 and that
it could not be proceeded
with an account
of the obstruction by the municipal authorities. Sri
Venugopal brought to our notice a notice issued by the municipal
corporation dated 21st November,
1990 and a commencement report dated
October
14, 1991. But these are all proceedings subsequent to September
CALCUTTA MUN. CORPN. v. A. R. BANERJEE [JEEVAN REDDY, J.] 199
24, 1989 and also subsequent to the filing of the writ petition and cannot, A
therefore, help the respondents' assertion. The respondents rely upon an
observation
in the judgment of the Division Bench to the following effect:
"That apart, construction has actually taken place on the
basis
of a plan that could have been sanctioned as the law
prevailing at that time
in that event nothing could have been B
done."
But the above sentence -assuming that it is a correct rendering - is
followed immediately by the following observation :
"In the ins.tant case, because of pendency of litigation and C
disputes, the owner did not think it to be fit to make any
investment until and unless the matter
is set at
rest."
In the circumstances, it must be held that no construction was made by
the respondents on the said site upto 24th September 1989.
Apart from the above, there
is yet another problem in the way of the
respondents. Section 319 expressly states that even
in case of a deemed
permission, the applicant cannot execute the work
'.'so· as to contravene any
D
of the provisions of this Act or of Schedule VI or any Rule or Bye-law
applying thereto." Neither the learned single Judge nor the Division Bench
have gone into and/or recorded any finding that having regard to the
E
position of law obtaining on 24th August, 1987 and the width of the road
on which the said premises abuts, a pennission for twelve-storey building
could have been granted. Neither the learned single Judge nor the Division
Bench have gone into this aspect. They have assumed that such a
permission could have been granted. The said assumption
is challenged by
the corporation before
us. F
Assuming that permission for a twelve-floors building could have been
granted under the law obtaining
in August 1987, the question still remains -
not having made any construction on the basis
of the said plan before
September 24, 1989, can any construction be made thereafter? The answer
can only
be in the negative.
Indeed; even if any construction was G
commenced before that date, it qnnot be continued thereafter according to
Section
325 of the Bengal Municipal Act. It must be remembered that the
writ petition itself was filed on 28th September, 1989, i.e., after the expiry
of the two years period from August 24, 1987 or from September 24, 1987,
as the case may be. The new Building Rules issued under the Calcutta
Municipal Act,
1980 came into force on and from 12th December, 1990. H
200 SUPREME COURT REPORTS [1994] SUPP. 5 S.C.R.
A Inasmuch as the respondents had not made the construction wi'.:bin the two
years' period
of any of the three applications afo1esaid and also because
there was not even an application for renewal
of the alleged deemed
sanction on the basis
of the plan submitted on August 24, 1987, no
construction could have
been carried on by the respondents after September
24, 1989, unless they obtained a fresh pennission according to law.
B
c
D
E
F
G
H
It is brought to our notice by the learned counsel for the Respondents
that by an order dated November 29, 1990, a learned single Judge
of the
High Court had allowed the respondents
"to make construction upto the
ground floor level
in suppression of the notice dated 21st November, 1990
as :ssued by the District Building Survaeyor under Section
40 l of the
Calcutta Municipal Corporation Act, 1980" subject to an undertaking that
they would demolish the construction,
if it is found to have been made in
violation
of the plan submitted on 24th August, 1987. All this shows again
that the only construction that has been made
is of the ground floor and that
too under the
interin:i orders of the High Court in the present proceedings.
In the above circumstances, it must be held that the respondents are not
legally entitled to make any construction on the basis
of the deemed
sanctioned plan (submitted on August 24, 1987) on or after September 24,
1989 -
or for that matter, after the filing of the writ petition. The High Court
was, therefore,
in error in pennitting the respondents (writ petitioners) to
proceed with the construction
of the twelve-storey building on the basis of
the plan submitted
0n August 24, 1987 and in giving other allied directions.
)
In view of the fact that the respondents' vendor was granted pennission
for a eight-storey puilding on 27.4.1985 and because of other relevant facts
and circurrystancls of this case, we called upon the learned counsel for the
corporation to tellr
us whether it is possible for the corporation to grant
pennission today for construction
of a building on the said premises as per
the plan sanctioned on April 27, 1985 or as per the plan applied for on
August 24, 1987.
'the learned counsel has, however, stated after obtaining
instru~tions from the corporation that no pennission beyond the height of
eight meters can 6e granted in the said premises having regard all the
relevl:lnt facts and circumstances. It is also stated by the learned counsel that
the site
.in question is abutting on a road with a width of less than 3.5 meters
and
in view of
t~at fact also, construction of a building of a height
exceeding eight meters cannot
be pennitted.
The question then arises as to what should
be done with the
construction
of ground floor which has already taken place on the basis of
the interim orders of the
I-Jigh Court in accordance with the plan submitted
CALCUTTA MUN. CORPN. v. A. R BANERJEE [JEEVAN ru:;DDY, J.] 201
on 24th August, 1987. Having regard to all the facts and circumstances of A
the case, we direct that the said construction should be allowed to be
retained and two more floors may
be constructed by the respondents
thereon but not so as to exceed the total height
of eight meters -and
not at
any rate beyond nine meters. Having regard to the construction
of ground
floor already made pursuant to the orders
of t.he High Court, we do not
think
it appropriate to direct the respondents to apply for fresh permission B
in accordance with the
1990 Building Rules. This direction does not,
however, preclude the respondents from applying for permission in
accordance with the Rules in force, if they are so advised, and proceed to
make construction
in accordance with the permission that may be granted
thereon.
Sri Venugopal disputed the corporation's contention that the road
abutting the said premises
is only of a width not exceeding 3.5 meters. It is
c
not possible for us to pronounce upon this disputed question of fact. It is
enough to observe that it shall be open to the respondents to approach the
concerned authorities
of the corporation and if such authorities are satisfied
that the width
of the road is more than 3.5 meters, they may permit the D
respondents to raise such construction or such further construction, as the
case may be,
as may be permissible under the Rules now in force.
The appeal
is, accordingly, allowed with the above directions. There
shall be no order as to costs.
V.M. Appeal allowed.
E
Legal Notes
Add a Note....