commercial dispute, contract law
0  27 Nov, 2018
Listen in 2:00 mins | Read in 13:00 mins
EN
HI

Cci Projects (P) Ltd. Vs. Vrajendra Jogjivandas Thakkar

  Supreme Court Of India Civil Appeal /6784-6785/2018
Link copied!

Case Background

Bench

Applied Acts & Sections

No Acts & Articles mentioned in this case

Hello! How can I help you? 😊
Disclaimer: We do not store your data.
Document Text Version

1

Reportable

IN THE SUPREME COURT OF INDIA

CIVIL APPELLATE JURISDICTION

CIVIL APPEAL Nos. 6784-6785 OF 2018

CCI Projects (P) Ltd. ……Appellant

VERSUS

Vrajendra Jogjivandas Thakkar ..…. Respondent

WITH

CIVIL APPEAL Nos. 6786-6787 OF 2018

(CCI Projects (P) Ltd. vs. Vrajendra Jogjivandas Thakkar)

JUDGMENT

Uday Umesh Lalit, J.

1. These appeals under Section 23 of the Consumer Protection Act, 1986

are directed against the common order dated 23.01.2018 passed by the

National Consumer Disputes Redressal Commission, New Delhi

(“Commission” for short) in Consumer Case Nos.975 and 976 of 2016.

2. In Consumer Case No.976 of 2016, Vrajendra J. Thakkar, HUF had

booked a residential flat with the appellant in a project named “White Spring

2

Building”, which the appellant was to construct at Village Magathane

Dattapada Road, Borivali (East), Mumbai, for a consideration of

Rs.90,38,850/- and flat No.6A in the building was allotted to said Vrajendra J.

Thakkar, HUF. The parties entered into an agreement dated 30.10.2012 and

in terms of Clause 17 of said Agreement, the possession was to be delivered

by August, 2014. However, in terms of the Agreement, the date of delivery of

possession would stand automatically extended in the event of any of the

contingencies specified in the said clause which was to the following effect:

“Possession of the said Premises in the said Building

shall be given by The Promotor to the Purchaser on or

before August, 2014 on a “best effort” basis. Provided

that in the even of occurrence of any of the following

events, the aforesaid date of possession shall

automatically stand extended by a period by which the

possession is delayed on account of such event(s) –

(a) Non-availability of steel, cement, other building of

construction materials, water or electricity supply;

(b) War, civil commotion, strike, lockout, riots, acts of

terrorism, epidemics, earthquake, flood, other act of

God, any prohibitory order of any court, tribunal or

authority against the development of the said

Properties:

(c) Any notice, order, rule, notification, circular of the

Government and/or other public or competent

authority, court, tribunal or Quasi-judicial body or

authority;

(d) Delay in getting NOC, permissions licenses,

approvals, consents, connections, plans, occupancy,

3

certificate, completion certificate and permissions from

MCGM and other authorities/bodies.

(e) Change in any law, rules, regulations, bye-laws of any

Government, authorities, public/local bodies affecting

the development of the said Properties.

(f) Any notice/direction notification, order from the

forest department, Ministry of environmental

department, pollution control department, MCGM, any

Government Department or public body/local

Authority, in respect to the said Properties;

(g) Delay or default in payment of the balance purchase

price and/or other amounts payable hereunder by the

Purchaser to the Promoter (without prejudice to the

right of the Promoter to terminate this Agreement in

terms of clause 12 above.”

3. Said Vrajendra Thakkar, HUF thereafter transferred the allotment in

favour of mother of the present respondent namely Kumudben Jagjivandas

Thakkar. Said Kumudben Thakkar thereafter gifted the very same Apartment

to the present respondent.

4. In Consumer Case No.976 of 2016, Smt. Hemali Vrajendra Thakkar

had booked a residential flat with the appellant in the same project and Flat

No.6B was allotted to her for the same consideration of Rs.90,38,850/-. She

also entered into similar agreement dated 30.10.2012 having identical clauses

including the aforesaid Clause No.17 to deliver the possession by August,

2014. Later, the aforesaid allotment was transferred by Hemali Vrajendra

4

Thakkar in favour of her mother-in-law namely Kumudben Thakkar who in

turn gifted the same to the respondent herein. The gift deed dated 19.08.2015

contained one of the recitals as under:

“And Whereas, although the Donee has other siblings

too but right from beginning the Donor and her late

husband had been staying with the Donee and his

family at the aforementioned address and it is only the

Donee who had been taking care of each and every

thing of the Donor and her husband from the smallest

to the biggest of their requirements. … … …”

5. On or about 02.06.2016, the aforesaid Consumer Case Nos.975 and

976 of 2016 were filed contending inter alia that though sum of

Rs.85,86,911/- had been deposited in respect of each of the flats, no

possession was delivered by the appellant. In the circumstances following

reliefs were prayed for:

“a. OP be directed to handover the legal possession of

flat to complainant within one month AND

b. OP be directed to pay to Complainant 18% interest

per annum on Rs.85,86,911/- from September 2014 on

the consideration amount already paid to OP till OP

handover the possession of the flat to Complainant. Or

c. if granting prayer a) & b) is legally not possible then

in alternative OP be directed to hand over any other

newly constructed flat to complainant consisting same

area, at the same rate in same locality in tower with

same facility. OR

5

d. OP be directed to refund the Complainant

Rs.2,00,00,000/- (Rupees Two Crore) the current

market value of the said flat. AND

e. AND OP be directed to pay the complainant 18%

interest per annum on Rs.85,86,911/- from September,

2014 on the consideration amount already paid to OP

till OP refund complainant Rs.2,00,00,000/- the current

market value of the said flat. AND

f. OP be directed to pay complainant Rs.5,00,000/- as

compensation for causing mental stress, harassment

and agony. AND

g. OP be directed to pay to Complainant Rs.1,00,000/-

as litigation cost.

h. Any other relief as Hon’ble Commission deem fit

and proper.”

6. The appellant resisted the complaints and submitted that the

construction activity had begun after obtaining requisite permissions.

However, New Development Control Rules stood notified in 2012 which

obliged the builder/developer to prefer fresh application after seeking

mandatory permission from the Fire Department. An application in that behalf

was made on 21.12.2012 after complying with the mandatory provisions but

the amended No Objection Certificate came to be granted only on 07.05.2013.

Additionally, between August, 2013 till September, 2015 i.e. for more than 24

months there was restriction on sand mining activity as a result of which, one

of the basic raw material for construction had become scarce in the market. It

6

was further stated that the complainants themselves were in default and as

such demand for payment of Rs.1,04,207/- in respect of each of the flats

towards interest on outstanding amounts was raised and appropriate debit

notes were issued by the appellant.

7. During the pendency of the matters before the Commission, the

possession of the aforesaid flats 6A and 6B was offered by the appellant vide

letter dated 16.11.2016. On 10.07.2017 the Commission directed the

complainants to pay admitted sums to the appellant and to deposit the

disputed sums with the Commission, whereafter the possession of the flats

was taken on 04.08.2017. The matters before the Commission thus stood

confined to the issue whether the complainants in both the cases were entitled

to any compensation in respect of delayed payment or whether the appellant

was entitled to have the period extended in terms of aforesaid clause No.17.

8. The Commission rejected the submission in respect of amended NOC

granted on 07.05.2013. It further rejected the submission regarding non-

availability of sand by observing that no document had been placed on record

to substantiate such claim. The Commission observed that except the sum of

Rs.104,207/- which the appellant sought to recover towards interest for

delayed payment, rest of the sums were not disputed by the complainants and

7

stood paid to the appellant. After considering the rival claims the

Commission disposed of the complaints with following directions:

“1. The balance, if any, out of the amount deposited

by the complainant with this Commission before

taking possession of the flat and proportionate

interest which may have accrued on that amount

deducting (i) the interest amount of Rs.10427/- (in

both the complaints) and (ii) an amount equivalent

to compensation payable to the complainant in terms

of direction (3) below, shall be released to the

opposite party.

2. The amount of Rs.104207/- shall (in both the

cases) be released to the complainant along with

proportionate interest which may have accrued on

that amount.

3. The opposite party shall pay compensation in the

form of simple interest @ 8% per annum on the

amount which had been paid by that date, to the

complainant, w.e.f. 01.09.2014 till the date on which

the possession was actually delivered to him. The

compensation to the extent available shall be

adjusted out of the amount payable to the

complainant in terms of direction (1) above.

4. The opposite party shall also pay Rs.25,000/- as

the cost of litigation in each complainant to the

complainant.

5. The payment by the OP in terms of the order shall

be made within three months from today.”

8

9. In these appeals challenging the correctness of the decision of the

Commission, we heard Mr. Sanjiv Sen, learned Senior Advocate and Dr.

Vinod Kumar Tewari, learned Advocate for the parties.

10.It was submitted by Mr. Sanjiv Sen, learned Senior Advocate:

(a) The complaints were not maintainable in as much as the original

allottees had transferred their interest. Reliance was placed on the

decision of this Court in Haryana Urban Development Authority

v. Raje Ram

1

.

(b) The time lost between 21.12.2012 till 07.05.2013 on account of

mandatory requirement for re-submission of plans, the appellant

was entitled to have that period extended.

(c) The National Green Tribunal had banned sand mining activities

across the country on 05.08.2013 which came to be relaxed only

when new policy was formulated by Union of India in September,

2015. It was submitted that the availability of sand during this

period had come down to 20% of what it was before.

It was therefore submitted that the appellant was not at fault. In any

case the possession was offered on 16.11.2016 and thus it was only a short

1

(2008) 17 SCC 407

9

period of more than 2 years between August, 2014 and 16.11.2016 which was

the period in question. In his submission, the period stood completely

explained and as such the Commission was not justified in imposing liability

on the appellant.

11.The learned Advocate for the respondent on the other hand submitted

that the transfers effected by the parties were within the family. He submitted

that the appellant was not entitled to any extension of period. He further

submitted that the order passed by the National Green Tribunal had banned

illegal sand mining activity and not sand mining activity itself. The sand was

thus available in market.

12.We have gone through the record and considered the rival

submissions. The decision of this Court in the case of Haryana Development

Authority (supra) turned on individual facts of the case where the very

entitlement of the subsequent allottees to claim damages or compensation for

delayed delivery of possession was found to be unsustainable. Said decision

of this Court related to cases where the original allottees had transferred the

allotment in favour of total strangers with the permission of the authority and

as found by this Court, the subsequent allottees were aware that there was

10

delay in delivering the allotted plots on account of time taken in forming the

layout or on account of encroachment and yet had purchased the interest of

the original allottees. In the present case the transfers were effected within the

family where the members had been living together. The decision of this

Court in Haryana Urban Development Authority (supra) cannot be stretched

to say that in every case where there is a transfer, the complaint by the

subsequent transferee would not be maintainable at all.

13.At the same time, the appellant is justified in saying that as a result of

mandatory requirements to resubmit the plans and get the fresh NOC in

respect of fire safety permission, the period between 21.12.2012 to

07.05.2013 stood completely explained. Thus, out of the period between

August, 2014 till 16.11.2016, the appellant would be entitled to have a period

of 6 months of extension. That still leaves us with a period of a year and 8

months. The Commission has awarded 8% interest on the deposited sum.

The deposited sum in either case being Rs.85.86 lakhs, going by the direction

issued by the Commission, the interest element in respect of the period of one

year and 8 months would be in the region of Rs.11.4 lakhs. We now consider

the second part of the submission. It is true that there was no complete ban on

sand mining. But as a result of reduced availability of sand in the market, the

11

demand and supply ratio must have been upset. The appellant would therefore

be entitled to some benefit on that count.

14.Considering the entirety of the matter, in our view, instead of direction

No.3 issued by the Commission, a lumpsum payment of Rs.5 lakhs in

substitution of said direction, would meet the ends of justice. We, therefore,

modify the directions issued by the Commission. Retaining directions 1, 2 &

4, the direction No.3 is substituted and in its place the appellant would be

required to pay a lumpsum compensation of Rs.5 lakhs to the respondent in

respect of each case. We direct that all the sums covered by the directions

shall be made over within 2 months from today failing which the respondent

complainant shall be entitled to 8% interest on the amounts in question.

15.With these directions civil appeals stand disposed of. No costs.

......………..……..……J.

(Uday Umesh Lalit)

..……..…..……………J.

(R. Subhash Reddy)

New Delhi,

November 27, 2018

Reference cases

Description

Legal Notes

Add a Note....