As per case facts, allottees had booked an apartment with the Promoter, with possession due by June 2017 as per the agreement. When possession was not given, the allottees filed ...
SA-472-2021 (final).doc
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CIVIL APPELLATE JURISDICTION
SECOND APPEAL NO. 472 OF 2021
CCI Projects Private Limited
Office at Rivali Park, CCI Compound, Western
Express Highway, Borivali East,
Mumbai 400 066.
]
]
]
]...Appellant
Versus
1.Mr. Sriram Krishnan
having address at
Krishna, E-404, Vasant Sagar Complex
Thakur Village, Kandivali (East), Mumbai –
400101.
]
]
]
]
]
]
2.Mrs. Vidya Sriram
having address at
Krishna, E-404, Vasant Sagar Complex,
Thakur Village, Kandivali (East), Mumbai –
400101.
]
]
]
]
]
]
3. Mr. Abhijit Kumar Phanikumar
having office at Rivali Park,
CCI Compound, Western Express Highway,
Borivali (East), Mumbai 400 066.
]
]
]
]
]
4.Ms. Nandini Hiten Khatau
having Office at Rivali Park,
CCI Compound, Western Express Highway,
Borivali (East), Mumbai – 400 066.
]
]
]
]
]
5.Ms. Maithili Hiten Khatau
having Office at Rivali Park,
CCI Compound, Western Express Highway,
Borivali (East), Mumbai 400 066.
]
]
]
]
]
6.Mr. Pradip Haridas Udeshi
having Office at Rivali Park,
]
]
]
Sairaj 1 of 40 2026:BHC-AS:9415
SA-472-2021 (final).doc
CCI Compound, Western Express Highway,
Borivali (East), Mumbai 400 066.
]
]
7.Ms. Nayna Bharat Pasta
having office at Rivali Park,
CCI Compound, Western Express Highway,
Borivali (East), Mumbai – 400 066.
]
]
]
]
]…Respondents
——————
Mr. Rubin Vakil, Mr. Abir P. and Mr. Kartik Joshi i/b Wadia Ghandy and Co. for
Appellant.
Mr. Bhavin Gada i/b Mr. Chirag Desai for Respondent Nos. 1 and 2.
——————
Coram : Sharmila U. Deshmukh, J.
Reserved on : 22
nd
April, 2026.
Pronounced on : 18
th
June, 2026.
Judgment :
1.The Second Appeal is filed at the instance of the promoter,
challenging the judgment dated 10
th
March, 2021 passed by
Maharashtra Real Estate Appellate Tribunal, Mumbai [for short,
“Appellate Tribunal”] quashing the order dated 31
st
January, 2019 in
Complaint No. CC006000000056115 passed by MahaRERA and
directing the promoters to pay interest for delayed possession. For
sake of brevity, the parties are referred to as Promoter and allottees.
2.By order dated 5
th
March, 2026, this Court framed the following
substantial questions of law:
“(i) Whether in view of provisions of Section 55 of the
Indian Contract Act, 1872, the acceptance of delayed
performance would disentitle the promisee from
compensation claimed on account of non-performance of
Sairaj 2 of 40
SA-472-2021 (final).doc
contract at the agreed time?
(ii) Whether the provisions of Section 18 of the Real
Estate (Regulation and Development) Act, 2016 will
override the provisions of Section 55 of the Indian
Contract Act, 1872?
(iii) Whether in view of provisions of Section 32 of Indian
Contract Act, 1872, the force majeure events listed in the
contract could have been ignored?”
(iv) Whether the Appeals would be maintainable at
instance of Respondents in view of the concession given
by the Respondents that the issue of interest will be
considered subsequent to the completion of the project?
3.The facts of the case are that allottees filed a complaint under
Section 31 of the Real Estate (Regulation and Development) Act, 2016
[for short, “RERA Act”] with the Maharashtra Real Estate Regulatory
Authority [for short, “1
st
Authority”] stating that the allottees had
booked an apartment in building known as Wintergreen in the project
developed by the Promoters. On 18
th
November, 2014, an agreement
was entered into between the promoters and the allottees and as per
Clause 17 of the agreement, the promoters agreed to give possession
to the allottees on or before 30
th
June, 2017.
4.The grievance was that till the filing of the complaint, the
possession of the flat was not given. The total flat consideration was
Rs. 1,95,06,060/- and the allottees had paid part consideration of Rs.
1,85,32,899/- and apart from that had also paid the sum of Rs.
10,09,220/- towards stamp duty and registration charges on 18
th
Sairaj 3 of 40
SA-472-2021 (final).doc
September, 2014. The service tax, VAT, GST and TDS amounts were also
paid and thus the allottees have paid sum of Rs. 2,05,89,715/- to the
promoter.
5.As per the project registration under RERA, the proposed date of
completion of project was 31
st
December, 2018 and revised proposed
date of completion was 31
st
December, 2019. The allottees sought the
relief of handing over possession of the apartments along with
payment of interest for delayed possession from 1
st
July, 2017 till the
handing over possession.
6.By order dated 31
st
January, 2019, the 1
st
Authority noted the
submission of promoters that the construction work of project could
not be completed for reasons beyond the promoter’s control and that
the construction would be completed before the revised completion
date set out in the registration web page. The submission of learned
counsel for complainants before the 1
st
Authority was that in
Complaint No. CC006000000054636, the 1
st
Authority had directed the
Promoter to handover possession by December, 2019 allowing the
Promoter in the interest of completing the project to complete the
project first with liberty to allottees to demand interest at an
appropriate stage under Section 18 of RERA Act and that similar order
be passed in the present complaint also. The 1
st
Authority directed the
promoter to handover the apartments with occupancy certificate to
Sairaj 4 of 40
SA-472-2021 (final).doc
allottees before 31
st
December, 2019 and that the allottees shall be at
liberty to demand interest at an appropriate stage under Section 18 of
the RERA Act for delay in completing the project and disposed of the
complaint.
7. As against this, the allottees approached the Appellate Tribunal
and by the impugned judgment dated 10
th
March, 2021, the Appellate
Authority quashed and set aside the order of the RERA Authority
directing the following :
“iii) Complaint No. CC006000000056115 is allowed
as under :
a) Promoters shall pay an interest @ State Bank of
India’s highest Marginal Cost of Lending Rate plus
2% to Allottees on the amount paid to Promoters for
delayed period of possession from 1
st
July, 2017 till
handing over possession of flat to Allottees.
b) Promoters shall pay Rs. 25,000/- towards cost to
the Allottees and shall bear own costs.”
8.The Appellate Authority held that there is no authentic evidence
to show that the allottees had accepted the revised date of possession
or had acquiesced or waived their right to interest. It held that the
allottees stayed with the project despite the promoters failing to give
the possession as per the agreed date and gets the statutory right to
claim interest for delayed possession. It held that the promoters
unilaterally extended the date of possession which is not binding on
the allottees. In a concurrent judgment, the non-judicial member
Sairaj 5 of 40
SA-472-2021 (final).doc
agreed with the observations and conclusion recorded by the judicial
member that as the promoters have failed to give possession on the
date i.e. 30
th
June, 2017 agreed in the Agreement for Sale registered
on 18
th
November, 2014 for non-justifiable reasons, the allottees are
entitled to interest for the delayed period of possession.
9.Mr. Rubin Vakil, learned counsel appearing for Appellants would
submit that the date mentioned in Section 18 of RERA Act is the
contractual agreement between the parties and Section 55 of the
Indian Contract Act, 1872 [for short, “the Contract Act”] takes note of
the fact that the party is accepting delayed possession. He would point
out that Section 55 deals with performance of reciprocal promises and
where delayed possession is accepted, it in fact, constitutes addendum
to main agreement accepting the alteration of date. He would submit
that under Section 62 of the Contract Act, the parties by conduct can
alter the original contract and in the present case, the allottees by their
conduct had altered the dates specified in the Agreement for sale. He
would further point out that clause 17 of the Agreement for sale
provided that possession shall be handed over on or before 30
th
June,
2017 automatically stand extended when delay is in beyond the control
of the promoter.
10.He would further point out the communication addressed by the
promoter to the allottees updating the allottees about the challenges
Sairaj 6 of 40
SA-472-2021 (final).doc
faced in the subject project and revising the date of possession from
March, 2018 to December, 2018. He submits that the first
communication was addressed on 15
th
April, 2015 and there was no
response or denial to the said communication by allottees which
constitutes an acceptance of revised timelines. He submits that by
communication of 9
th
June, 2017, the Promoter communicated a
revised payment schedule to the allottees which was also accepted and
payments were made accordingly.
11.He submits that provisions of Section 88 of RERA Act provides
that the provisions of RERA Act is in addition to and not in derogation
to other enactment and there is no conflict between the provisions of
RERA Act and Contract Act. He submits that Section 18 of RERA Act is
compensatory in nature and provides for payment of interest without
any proof of loss ocassioned on account of delayed possession. He
submits that it is only the obligation to prove loss which is obviated and
not the provisions of the Contract Act.
12. He would further point out that the initial dates in the schedule
of payments provided for payment on the basis of slabwise
construction and from 30
th
June, 2015 was based on fixed dates and
thereafter, payments were made by the allottees as per the revised
timelines which constitutes an acceptance of delayed possession. He
submits that by their conduct, the allottees have given go-by to the
Sairaj 7 of 40
SA-472-2021 (final).doc
original date. He would further point out that payments were made
even beyond 30
th
June, 2017, which was the date set out in the
agreement for sale for handing over the possession.
13.He would further submit that the order of 1
st
authority is an
order in invitum and the Appellate Authority did not consider the issue
of maintainability of appeal though raised. He submits that the only
remedy available to the Appellate Authority was to remand the matter
and by failing to do so as the order was in invitum, the promoter’s right
to set up the case of acceptance of delayed possession and
consequences thereof as provided under Section 55 of the Contract
Act was taken away. He points out that in the written submissions
before the Appellate Authority, specific plea of maintainability was
raised. He would further point out that the impugned order does not
consider the aspect of concession granted by the allottees by inviting
the order. He submits that the promoter’s remedy of opportunity of
being heard before the 1
st
Authority cannot be substituted by right of
hearing granted at the appellate stage. He would further submit that
the allottees have not canvassed any submission that no concession
was made by them before the Appellate Authority and even in the
present proceedings, there is no such submission canvassed. In
support, he relies upon the following decisions :
Era Realtors Private Limited vs. Prakash Shah and
Sairaj 8 of 40
SA-472-2021 (final).doc
Another
1
Institute of Chartered Accountants of India vs. L. K.
Ratna and Others
2
Sports Authority of India and Another vs. Dr. Kulbir
Singh Rana
3
Rajasthan State Industrial Development and
Investment Corporation and Another vs. Diamond
and Gem Development Corporation Limited and
Another
4
Municipal Corporation of Delhi vs. Gurnam Kaur
5
14.Per contra, Mr. Gada, learned counsel appearing for the Allottees
would submit that the complaint before the 1
st
Authority was filed in
September, 2018 and the order came to be passed in January, 2019 and
till that time, there was no reply filed by the promoter and no stand
taken and therefore, now it is too late to contend that they have lost an
opportunity for placing their stand before the 1
st
Authority. He would
submit that in Affidavit-in-reply filed before the Appellate Authority,
there is no ground of Section 55 of the Contract Act taken and only
case, which was set up was delay beyond their control and waiver and
acquiescence. He submits that for the first time, in the present Second
Appeal, the ground of Section 55 of the Contract Act is taken.
15.He would further submit that whenever the demand was made
1 Second Appeal (St.) No. 27241 of 2023, decided on 14
th
March, 2024.
2 (1986) 4 SCC 537.
3 (2025) 10 SCC 819.
4 (2013) 5 SCC 470.
5 (1989) 1 SCC 101.
Sairaj 9 of 40
SA-472-2021 (final).doc
by the promoter, the payments were made by the allottees and there is
no submission that there is any delay in payment. He would further
submit that the communications which were addressed to the allottees
were in the year 2015 and 2017 and 85% of the amount was demanded
and already paid. He would further point out the additional Affidavit
filed before the Appellate Authority by the promoters contending that
project is at the stage of nearing completion which Affidavit was filed
in November, 2020 and therefore, even at the Appellate stage, the
project was not complete.
16.He would further submit that the provisions of Section 55 of the
Contract Act cannot be read for the purpose of determining date of
possession as envisaged by Section 18 of RERA Act. He submits that by
reason of the complaint being filed, there is already an objection raised
and even the applicable test of Section 55 of the Contract Act stands
satisfied as the complaint makes a specific reference for payment of
interest. He submits that the provisions of Section 55 of the Contract
Act provides that at the time of acceptance of performance, the notice
is required to be given and in the present case, the possession was
given in the year 2021 and the complaint would constitute notice to
claim compensation.
17.He submits that the provisions of RERA Act does not extend the
date mentioned in the Agreement for sale which is sacrosanct. He
Sairaj 10 of 40
SA-472-2021 (final).doc
would further submit that in the communication of 15
th
April, 2015, the
promoter does not seek for consent and neither mentions that
payment timelines would be revised. He submits that as and when
demand was made, the payments were made. He would further submit
that by the time, communication of 2017 was issued, the allottees had
already paid 90% of consideration. He would submit that the Appellate
Authority has appropriately dealt with the case of waiver which was set
up by the promoter.
18.He would submit that being part of the same project and as
order was already passed by the 1
st
Authority in identical matter, the 1
st
Authority was requested to pass same order which would not
constitute concession. He submits that the allottees were entitled to
the remedy of appeal and there can be no estoppel against law. He
would further submit that there was no argument canvassed on the
aspect of concession and by way of amendment to Appeal memo, the
said issue is raised and being question of fact or mixed question of fact
or law cannot be raised in the Second Appeal. He submits that
concession is what is given up and cannot be withdrawn. He submits
that the right to claim interest was not given up by the allottees. He
would further submit that even the defence of Section 55 of the
Contract Act have been raised for the first time in the Second Appeal,
which is not pure question of law.
Sairaj 11 of 40
SA-472-2021 (final).doc
19.He would submit that in any event, Section 55 of the Contract
Act cannot override the provisions of RERA Act in view of Section 89 of
RERA Act. He submits that allottees have filed the appeal in 2019 and
even at the appellate stage, as the possession was not given, there is
no question of Section 55 of the Contract Act being triggered.
20.He would further submit that the promoter did not argue the
aspect of concession before the Appellate Court and in fact, had
argued delay and would point out the findings of the Appellate
Authority dealing with the submissions canvassed. He submits that by
way of amendment, in the year 2023, the issue of Section 55 of the
Contract Act and the order being an order in invitum has been raised.
He would further submit that the arguments canvassed that no
opportunity of taking the defense of Section 55 of the Contract Act by
reason of the concession given by the allottees is not a ground taken
in the present Second Appeal. He submits that the decision in the case
of Newtech Promoters and Developers Private Limited vs. State of
Uttar Pradesh
6
covers the issue raised in the present case that Section
18 of RERA Act gives an unqualified right to the allottees to stay with
the project and demand interest. He would submit that the concession
which is being argued would be a benefit which is altogether given up
and not a benefit which is deferred and therefore, it cannot be said
6 (2021) 18 SCC 1.
Sairaj 12 of 40
SA-472-2021 (final).doc
that the Appeal is not maintainable. In support, he relies upon the
following decisions :
Newtech Promoters and Developers Private Limited
vs. State of Uttar Pradesh and Others
(supra)
Imperia Structures Limited vs. Anil Patni and
Another
7
Director of Elementary Education, Odisha vs.
Pramod Kumar Sahoo
8
Pathan Murtazakhan Dadamkhan and Others vs.
Pathan Pirkhan Amdumiyan (dead) by LRs.
9
Krishnapasuba Rao Kundapur (dead) after him his
L.R. and Another vs. Dattatraya Krishnaji Karani
10
Babu Ram alias Durga Prasad vs. Indra Pal Singh
(dead) by LRs.
11
K. Chelliah Servai vs. P. Muthusami Servai
12
Hardayal Gir vs. Sohna Ram
13
Boodireddy Chandraiah and Others vs. Arigela
Laxmi and Another
14
Municipal Committee, Amritsar vs. Hazara Singh
15
Director of Settlements, A.P. and Others vs. Mr.
Apparao and Another
16
M/s. Pragatej Builders and Developers Pvt. Ltd. vs.
7 (2020) 10 SCC 783.
8 (2019) 10 SCC 674.
9 1993 Supp (2) SCC 518.
10 1965 SCC OnLine SC 251.
11 (1998) 6 SCC 358.
12 1995 Supp. (1) SCC 202.
13 1970(3) SCC 635.
14 (2007) 8 SCC 155.
15 (1975) 1 SCC 794.
16 (2002) 4 SCC 638.
Sairaj 13 of 40
SA-472-2021 (final).doc
Mr. Abhishek Anuj Sukhadia and Another
17
21.In rejoinder, Mr. Vakil would submit that the written submissions
filed before the Appellate Authority raised the issue of maintainability.
He would further submit that in the Second Appeal, what is required to
be set out is the substantial question of law and not the grounds on
which the order is assailed as in the case of First Appeal. He submits
that once the question of law is framed, the Court can decide the same.
He would submit that by reason of concession given by the allottees,
the promoter’s statutory right to raise appropriate defence before the
1
st
authority is taken away which would also constitute violation of
principles of natural justice. He submits that once the promoters have
acted on the concession, the allottees are estopped from claiming
interest. He submits that by reason of concession granted, there was
no question of raising the issue of Section 55 of the Contract Act. He
submits that the provisions of Section 55 of the Contract Act will have
to be considered for the purpose of deciding the date of performance
which can be determined by the regulatory authority under RERA Act.
He would further submit that act of acceptance of the delayed
performance is implied from acceptance of revised payment schedule.
He would submit that decision in the case of Newtech Promoters and
Developers Private Limited vs. State of Uttar Pradesh and Others
17 Second Appeal No. 688 of 2023 and Second Appeal No. 689 of 2023, decided on 23
rd
January,
2024.
Sairaj 14 of 40
SA-472-2021 (final).doc
(supra), the issue as to the applicability of Section 55 of the Contract
Act was not dealt with and is therefore, distinguishable.
REASONS AND CONCLUSION :
22.In identical facts arising in Second Appeal No. 479 of 2021,
identical questions of law were raised except the fourth substantial
question of law as regards the maintainability of appeal in view of
concession granted by the allottees. Both the Second Appeals were
listed together from time to time, however, were argued separately.
The submissions canvassed on the questions of law are broadly similar
and as the questions stand answered in Second Appeal No. 479 of
2021, the findings are reproduced hereinbelow with necessary
variations. This Court in Second Appeal No. 479 of 2021 have answered
the first three substantial question of law, which would also answer the
first three substantial questions of law raised in this Appeal as under.
23.The first substantial question of law framed by this Court seeks
an answer as to whether there was acceptance of delayed performance
and secondly, whether such acceptance of delayed performance
disentitles the allottees from claiming compensation under Section 18
of RERA Act in the absence of notice by the allottees of their intention
to do so as contemplated by Section 55 of the Contract Act.
24.The RERA Act was enacted for regulating and promoting real
estate sector and to infuse transparency in the sale of real estate
Sairaj 15 of 40
SA-472-2021 (final).doc
projects and to protect the interest of consumer in the real estate
sector providing mechanism under the Act itself for adjudicating the
grievances. The scheme of RERA Act statutorily regulates the
development project creating rights and obligations aimed at ensuring
that the flat purchaser’s interest is protected by imposing obligations
on the promoters to complete the development project in a time
bound schedule and conferring various rights on the allottees upon
failure of the promoter to perform its obligations.
25. Section 18 of RERA Act, reads as under :
“18. Return of amount and compensation.—(1) If the
promoter fails to complete or is unable to give possession
of an apartment, plot or building,—
(a) in accordance with the terms of the agreement for
sale or, as the case may be, duly completed by the date
specified therein; or
(b) due to discontinuance of his business as a developer
on account of suspension or revocation of the
registration under this Act or for any other reason, he
shall be liable on demand to the allottees, in case the
allottee wishes to withdraw from the project, without
prejudice to any other remedy available, to return the
amount received by him in respect of that apartment,
plot, building, as the case may be, with interest at such
rate as may be prescribed in this behalf including
compensation in the manner as provided under this Act:
Provided that where an allottee does not intend to
withdraw from the project, he shall be paid, by the
promoter, interest for every month of delay, till the
handing over of the possession, at such rate as may be
prescribed.
(2) The promoter shall compensate the allottees in case
of any loss caused to him due to defective title of the
Sairaj 16 of 40
SA-472-2021 (final).doc
land, on which the project is being developed or has been
developed, in the manner as provided under this Act, and
the claim for compensation under this subsection shall
not be barred by limitation provided under any law for
the time being in force.
(3) If the promoter fails to discharge any other obligations
imposed on him under this Act or the rules or regulations
made thereunder or in accordance with the terms and
conditions of the agreement for sale, he shall be liable to
pay such compensation to the allottees, in the manner as
provided under this Act.”
26.Section 18 of RERA Act codifies the summary nature of the
proceedings by discharging the onus of proof of loss upon failure by
the Promoter to hand over possession as per terms of the agreement
or date specified therein. It gives an option to the allottee to exit from
the project with refund of the amounts paid alongwith interest
including compensation or to stay in the project and get interest for
every month of delay till handing over possession. Section 18 thus
confers a statutory right of the allottees to interest for the delayed
possession, if they choose to remain with the project.
27.Section 55 of the Contract Act deals with the consequences of
failure to perform the contract at fixed time in cases where time is of
essence and where time is not of essence. Section 55 reads as under:
“55. Effect of failure to perform at fixed time, in
contract in which time is essential.— When a party to a
contract promises to do a certain thing at or before a
specified time, or certain things at or before specified
times, and fails to do any such thing at or before the
specified time, the contract, or so much of it as has not
been performed, becomes voidable at the option of the
Sairaj 17 of 40
SA-472-2021 (final).doc
promisee, if the intention of the parties was that time
should be of the essence of the contract.
Effect of such failure when time is not essential.—If it
was not the intention of the parties that time should be
of the essence of the contract, the contract does not
become voidable by the failure to do such thing at or
before the specified time; but the promisee is entitled to
compensation from the promisor for any loss occasioned
to him by such failure.
Effect of acceptance of performance at time other
than that agreed upon.—If, in case of a contract
voidable on account of the promisor’s failure to perform
his promise at the time agreed, the promisee accepts
performance of such promise at any time other than that
agreed, the promisee cannot claim compensation for any
loss occasioned by the non-performance of the promise
at the time agreed, unless, at the time of such
acceptance, he gives notice to the promisor of his
intention to do so.”
28.In cases where time is of essence, Section 55 of the Contract Act
provides that the contract, if not performed, becomes voidable at the
option of the promisee, who forgoes the right to compensation for any
loss occasioned by the non-performance in absence of notice at the
time of acceptance of delayed performance. Where time is not of
essence, the contract is not voidable by failure to perform at specified
time, however the promisee is entitled to compensation.
29.In the present case, the flat purchaser’s agreement has been
executed under Maharashtra Ownership Flats Act, 1963 [for short,
“MOFA”]. Section 4 of MOFA prescribes the particulars of flat
purchaser agreement to include inter alia the date on which the
possession shall be handed over to the flat purchaser. The statutory
Sairaj 18 of 40
SA-472-2021 (final).doc
provisions of RERA Act providing for registration of the project
requires the promoter to give the time period within which the project
shall be completed and provides for consequences of failure to hand
over possession as per the date duly specified. Clause 17 of the flat
purchaser’s agreement sets outs that the possession of the premises
shall be given by 30
th
June, 2017. The consequence of failure to hand
over possession is provided in Clause 18 giving the purchaser the
option to terminate the agreement. The clauses in the agreement
makes it clear that the intention of the parties was to make time
essence of contract. As the flat purchaser’s contract is of the nature
demanding compliance with the fixed date for performance and
provides consequence for non-compliance, time is essence of the
contract.
30.The consequence of failure to hand over possession by the date
specified in the agreement in respect of real estate project is provided
under Section 18 of RERA Act. Plain reading of Section 18 does not
indicate that the rights conferred on the allottee upon failure of the
promoter to hand over possession by the date duly specified is
qualified by any contingency. Neither any provision of RERA Act has
been demonstrated which would have the effect of qualifying the
rights under Section 18.
31.Section 18 of RERA Act gives option to the allottees upon failure
Sairaj 19 of 40
SA-472-2021 (final).doc
of the promoter to hand over possession by the date specified in the
agreement or as per the terms of the agreement either to withdraw
from the project with refund of amounts paid along with interest
including compensation or to stay with the project and get interest for
every month of delay. In the context of real estate project, where the
performance of promise of the promoter is to hand over possession by
a specified date, the right given by Section 18 of RERA Act to continue
with the project is nothing but permitting acceptance of delayed
performance without foregoing the right to claim interest for every
month of delay.
32.Section 55 of the Contract Act permits the same option to the
promisee when it gives the right to the promisee to accept the
performance of the promise at a date other than that agreed but
qualifies the right to claim compensation only upon giving notice while
accepting delayed performance.
33.If the right under Section 18 of RERA Act is an unqualified
absolute right, the acceptance of revised timelines and delayed
performance cannot lay fetters on the right to claim interest. The
Hon’ble Apex Court in Imperia Structures Limited vs. Anil Patni
18
while
interpreting Section 18 of RERA Act has held in paragraph 25 as under:
“25. In terms of Section 18 of the RERA Act, if a promoter
fails to complete or is unable to give possession of an
18 (2020) 10 SCC 783.
Sairaj 20 of 40
SA-472-2021 (final).doc
apartment duly completed by the date specified in the
agreement, the promoter would be liable, on demand, to
return the amount received by him in respect of that
apartment if the allottee wishes to withdraw from the
Project. Such right of an allottee is specifically made
“without prejudice to any other remedy available to him”.
The right so given to the allottee is unqualified and if
availed, the money deposited by the allottee has to be
refunded with interest at such rate as may be prescribed.
The proviso to Section 18(1) contemplates a situation
where the allottee does not intend to withdraw from the
Project. In that case he is entitled to and must be paid
interest for every month of delay till handing over of the
possession. It is up to the allottee to proceed either
under Section 18(1) or under proviso to Section 18(1)
…….”.
34. The above interpretation of Section 18 of RERA Act was noted in
the case of Newtech Promoters and Developers Private Limited vs.
State of U.P. (supra). The Hon’ble Apex Court was considering interalia
the issues as to the retroactive operation of RERA Act and the
jurisdiction of the Regulatory Authority to direct refund under the
provisions of RERA Act including Section 18 and other ancillary issues.
The Hon’ble Apex Court considered the statutory scheme of RERA Act
and observed in paragraph 24 as under:
“24. The unqualified right of the allottee to seek refund
referred under Section 18(1)(a) and Section 19(4) of the
Act is not dependent on any contingencies or stipulations
thereof. It appears that the legislature has consciously
provided this right of refund on demand as an
unconditional absolute right to the allottee, if the
promoter fails to give possession of the apartment, plot
or building within the time stipulated under the terms of
the agreement regardless of unforeseen events or stay
orders of the court/tribunal, which is in either way not
attributable to the allottee/homebuyer, the promoter is
under an obligation to refund the amount on demand
Sairaj 21 of 40
SA-472-2021 (final).doc
with interest at the rate prescribed by the State
Government including compensation in the manner
provided under the Act with the proviso that if the
allottee does not wish to withdraw from the project, he
shall be entitled for interest for the period of delay till
handing over possession at the rate prescribed.”
(emphasis supplied).
35.The Hon’ble Apex Court has interpreted the statutory provisions
of Section 18 and Section 19(4) of RERA Act noting the legislative
intent. It has held that Section 18 of RERA Act confers an unqualified,
unconditional absolute right upon the allottee to claim under Section
18 of RERA Act. Though it is sought to be contended, that the decision
in Newtech Promoters and Developers Pvt. Ltd. vs. State of UP
(supra) was not founded on considerations which arise in the present
case, the Hon’ble Apex Court has interpreted the statutory scheme of
the RERA Act to hold that the right of allottee under Section 18(1)(a) of
the Act is unqualified right not affected by any contingencies or
stipulations or an unforeseen event or even stay orders of the Court or
Tribunals. On appreciation of the legislative intent, it places the right
of allottee to seek refund on demand beyond the impact of any
enactment by interpreting the right to be an unqualified absolute
right. The interpretation of Section 18 of RERA Act by the Hon’ble
Apex Court would bind this Court.
36.As the Hon’ble Apex Court has held the provisions of Section 18
to be beyond the pale of any qualification or condition, Section 55 of
Sairaj 22 of 40
SA-472-2021 (final).doc
Contract making the right to demand interest conditional upon giving
notice to the promisor of his intention, would have the effect of
qualifying the absolute right of the allottee under Section 18 of RERA
Act, which runs contrary to the statutory provisions and the
interpretation by the Hon’ble Apex Court.
37.Under the provisions of Section 18 of RERA Act, primacy is given
to the due date specified in the agreement by linking the failure to
hand over possession to the terms of agreement or as per the date
specified, whereas Section 55 of Contract Act contemplates a situation
of extension of time de-hors the date specified in the agreement. The
unqualified absolute right of the allottee stands statutorily recognized
in Section 18 of RERA Act and the continuation with the project, which
if expressed in the language of Section 55 of the Contract Act
constitutes acceptance of delayed performance, does not impact the
unfettered statutory right conferred by Section 18 of RERA Act to
claim interest.
38.The Appellate Authority has come to a finding of fact that there
is no authentic evidence to show that the allottees accepted revised
date of possession or that the allottees have in fact acquiesced. The
revised timelines were unilateral and the contention of Mr. Vakil of
acceptance of delayed performance is premised on the basis that by
accepting the revised dates of payment in accordance with revised
Sairaj 23 of 40
SA-472-2021 (final).doc
schedule, the allottees have accepted the delayed performance by
their conduct. The payment schedule agreed between the parties
enumerates that the initial payments from Serial No 1 to 9 were
construction linked payments and would show that at Serial No 9, the
casting work of terrace slab would commence. From Serial No 10 to 15,
the payments are linked to specified dates. For Serial No 10 to 15 to
apply, the commencement of casting work of terrace slab was required
to be completed. If the construction itself was delayed, the payments
at Serial No 1 to 9 would be delayed and consequently the subsequent
payments.
39.The acceptance of delayed possession is premised on the
communications of 15
th
April, 2015, 14
th
March, 2017 and 19
th
August,
2017. The contents of the communications dated 15
th
April, 2015 and
14
th
March, 2017 indicate that the same is mere information to the
allottees about the reasons for the delay and an assurance of handing
over final possession by March, 2018. In the communication of 19
th
August, 2017, the allottees are informed about the RERA date of
handing over possession of December, 2019 and that they would
endeavour to complete the project in or around December, 2018 and
that such early completion would lead to earlier demands for payment.
40.The communications, at the highest conveys information about
the delay and gives assurance to complete the project. The revised
Sairaj 24 of 40
SA-472-2021 (final).doc
timelines are couched in a manner so as to be in nature of information
requiring no further acts by the allottees.
41. Even accepting that there was acceptance of revised date of
possession, considering Section 18 of RERA Act, the allottees were
well within their rights to accept the delayed performance without
foregoing their right to interest for delayed possession.
42.As the terms of the agreement provided for the possession to be
handed over by 30
th
June, 2017, the Appellate Tribunal has rightly
directed payment of interest from 1
st
July, 2017 till handing over of
possession.
43.The contention of Mr. Vakil is that the date mentioned in Section
18 is contractual agreement and Section 55 of the Contract Act
constitutes an addendum to the main agreement. The provisions of
Section 18 of RERA Act would militate against such contention as
primacy is given to the date specified in the agreement, which under
Section 4 of MOFA is required to be in writing. The purported
alteration based on conduct of parties cannot be accepted as an
addendum to the main agreement. Accepting such contention would
require an inquiry for determining the agreed date of possession for
purpose of Section 18 of RERA Act. It needs to be noted that the claim
for interest is to be filed with the Regulatory Authority as opposed to
the Adjudicatory Authority, which is tasked with the function of
Sairaj 25 of 40
SA-472-2021 (final).doc
adjudicating compensation. Section 38 of RERA Act confers the power
on the Regulatory Authority to impose penalty or interest for
contravention of obligations by the promoters, the allottees etc or the
rules or regulations made thereunder.
44.Rule 6 of Maharashtra Real Estate (Regulation and Development)
(Recovery of Interest, Penalty, Compensation, Fine payable, Forms of
Complaints and Appeal, etc.) Rules, 2017 provides for manner of filing
complaints with the Authority and the manner of holding of inquiry by
the Authority and Rule 6(2)(c) provides that on the date so fixed, the
Authority to explain the Respondent or his authorized representative
about the alleged contravention and if the Respondent pleads guilty,
the Authority shall record the plea and pass such orders including the
imposition of penalty and if he does not plead guilty and contests then
the Authority must demand explanation from him. Rule 6(2)(h)
provides that where upon consideration of evidence produced before
it, the Authority is satisfied that the Respondent is in contravention of
provisions of Act or rules and regulations made therein, it shall pass
such orders including imposition of penalty as it may think fit and if
not, dismiss the complaint. The provisions indicate the summary nature
of inquiry contemplated to be conducted while deciding Section 18
complaint.
45.The Hon’ble Apex Court in Newtech Promoters and Developers
Sairaj 26 of 40
SA-472-2021 (final).doc
(P) Ltd. (supra), considered whether the jurisdiction to direct
return/refund of amount to the allottee under Sections 12, 14, 18 and
19 of RERA Act vests with the Regulatory Authority or Adjudicating
Authority. It noted the delineation of jurisdiction conferred upon the
Adjudicating Authority and Regulatory Authority under RERA Act. It
held in paragraph 76 as under:
“76. The further submission made by the learned
counsel for the appellants is that the return of the
amount adversely impacts the promoter and such a
question can be looked into by the adjudicating officer in
the better prospective. The submission has no
foundation for the reason that the legislative intention
and mandate is clear that Section 18(1) is an indefeasible
right of the allottee to get a return of the amount on
demand if he promoter is unable to hand over
possession in terms of the agreement for sale or failed
to complete the project by the date specified and the
justification which the promoter wants to tender as his
defence as to why the withdrawal of the amount under
the scheme of the Act may not be justified appears to
be insignificant and the Regulatory Authority with
summary nature of scrutiny of undisputed facts may
determine the refund of the amount which the allottee
has deposited, while seeking withdrawal from the
project, with interest, that too has been prescribed
under the Act, as in the instant case, the State of Uttar
Pradesh has prescribed MCLR +1% leaving no discretion
to the Authority and can also claim compensation as per
the procedure prescribed under Section 71(3) read with
Section 72 of the Act.”
46.The decision makes it clear that the legislative intent was to
invest the Regulatory Authority with the jurisdiction to decide the
complaints under Section 18 by conducting summary nature of scrutiny
of undisputed facts, which may not fit in the scheme of determination
Sairaj 27 of 40
SA-472-2021 (final).doc
of agreed date of possession in context of Section 55 of Contract Act,
which would require an adjudicating process.
47.Perusal of the statutory provisions of RERA Act would indicate
that the date referable to Section 18(1) of the Act as the date specified
in the agreement is sacrosanct and where the project is ongoing and
covered by the RERA Act, the only manner in which the extension can
be sought is under Section 6 of RERA Act by extension of registration.
Section 18 of RERA Act confers an unqualified absolute right upon the
allottee to accept delayed performance without foregoing their right
to claim compensation for every month of delay, which right is not
affected by non issuance of notice of intention to claim compensation.
The first substantial question of law is answered accordingly. In light
of the discussion above, the Appellate Authority has rightly granted
interest for every month of delayed performance.
48.In so far as the second question of law as to the overriding effect
of Section 18 of RERA Act qua Section 55 of Contract Act, the
contention of Mr. Vakil is that there is no conflict between the two
provisions as the question is what is the agreed date for handing over
possession as the revision of timelines was pre-RERA. In Newtech
Promoters and Developers Pvt Ltd (supra), the Hon’ble Apex Court
considered whether RERA Act is retrospective or retroactive in its
operation and legal consequences and held in paragraph 40 as under:
Sairaj 28 of 40
SA-472-2021 (final).doc
“40. The clear and unambiguous language of the statute
is retroactive in operation and by applying purposive
interpretation rule of statutory construction, only one
result is possible i.e. the legislature consciously enacted a
retroactive statute to ensure sale of plot, apartment or
building, real estate project is one in an efficient and
transparent manner so that the interest of consumers in
the real estate sector is protected by all means and
Sections 13, 18(1) and 19(4) are all beneficial provisions
for safeguarding the pecuniary interest of the
consumers/allottees. In the given circumstances, if the
Act is held prospective then the adjudicatory mechanism
under Section 31 would not be available to any of the
allottees for an ongoing project. Thus it negates the
contention of the promoters regarding the contractual
terms having an overriding effect over the retrospective
applicability of the Act, even on facts of this case.”
49.The Hon’ble Apex Court has held that RERA Act being retroactive
will apply after getting the ongoing projects and future projects
registered under Section 3 to prospectively follow the mandate of
RERA Act and specifically negated the contention of the contractual
terms having an overriding effect over the retrospective applicability
of the Act.
50.The retroactive nature of RERA Act would result in creating new
obligations under Section 18 applicable to the flat purchaser’s
agreement. Section 18 confers a right on the allottees to claim interest
for every month of delay, where the possession is not handed over by
the due date, by continuing with the project. To express Section 18 of
RERA Act in the language of Section 55 of Contract Act, is that even
though the flat purchaser’s agreement is voidable at the option of the
Sairaj 29 of 40
SA-472-2021 (final).doc
allottee as the possession was not handed over by due date, by
continuing with the project, the allottee accepts the performance at a
time other than that agreed. The distinction between Section 18 of
RERA Act and Section 55 of Contract Act, comes upon such acceptance
and where Section 18 confers right upon the allottee to continue with
the project and be entitled to claim interest for every month of
delayed possession, Section 55 permits compensation to be claimed
only when he gives notice to the promoter of his intention to do so.
Whereas Section 18 of RERA Act gives an unqualified absolute
statutory right to claim interest unimpeded by any condition, Section
55 of Contract Act lays fetters on that right making it subject to giving
notice of intention to claim compensation. The inconsistency between
the two provisions appears on the aspect of right to claim
compensation.
51. RERA Act being a special enactment will prevail over Contract
Act, a general law. Section 89 of RERA Act gives it an overriding effect
over anything inconsistent with the other laws and the retroactive
application of RERA Act would impose an obligation on the promoter
to pay interest for the delayed possession computed from the date of
handing over possession as specified in the agreement even in the
absence of any notice to the promoter by the allottee of its intention
to do so.
Sairaj 30 of 40
SA-472-2021 (final).doc
52.Coming to the third question of law as to whether the force
majeure events listed in the contract could be ignored, Covid 19
pandemic falls within the ambit of force majeure clause. The date of
handing over possession under the agreement for sale was June, 2017
and as per RERA registration, the possession was to be handed over by
2019. The force majeure event of Covid-19 was subsequent to the due
date of performance by the Appellant and does not impact the
performance of the contract.
53. Mr. Vakil has emphasised on the RERA Order dated 18
th
May,
2020 seeking to exclude period of six months which was clarified to be
treated as moratorium period for purpose of calculating interest under
Section 18 of RERA Act. In M/s Pragatej Builders and Developers Pvt
Ltd vs Abhishek Anju Sukhadia (supra), the Co-ordinate Bench of this
Court considered the circulars issued by MahaRERA for moratorium
during Covid-19 pandemic. It held that where the possession was to be
handed over before the Covid 19 pandemic, the subsequent Covid 19
pandemic lockdown cannot come to the aid of the promoter for
claiming any relief for payment of interest and it cannot seek to take
advantage of Covid 19 pandemic to escape the liability to pay interest.
As the issue is settled by the decision of the Co-ordinate Bench, the
same does not constitute substantial question of law.
54.The fourth substantial question of law is the maintainability of
Sairaj 31 of 40
SA-472-2021 (final).doc
Appeal as according to Mr. Vakil, the order of 1
st
Authority was passed
in view of the concession given by the allottees and thereafter the
allottees could not have appealed against the said order. He would
submit that the Appeal ought to have been remanded to the 1
st
Authority as the decision takes away the right of the promoter to raise
their defense to the complaint under Section 18 of RERA Act.
55. In the written submissions before the Appellate Authority, the
Promoters had pleaded, under the heading of “Appeal Misuse of Legal
Process”, that the allottees prayed for a similar order as passed in the
connected complaint and that the appeal is mala fide. There is no
specific plea raised to the maintainability of the appeal on the ground
of concession granted by the allottees and there is no pleading or
argument canvassed seeking remand of the matter to the 1
st
Authority,
which is sought to be pleaded for the first time in Second Appeal
proceedings. There is no foundation in the pleadings on maintainability
of Appeal in view of the purported concession granted by the allottees.
As there was no such pleading or argument of concession, the allottees
did not have the chance to meet the case of concession before the
Appellate Authority.
56.The allottees in the present case are identically placed in the
same project as the allottees in CC006000000054636, who had filed
identical complaint before the 1
st
Authority. Similar submissions were
Sairaj 32 of 40
SA-472-2021 (final).doc
raised in the other complaint and as the 1
st
Authority had already
passed the order in the other complaint, the allottees requested for
similar order to be passed. The submission recorded in paragraph 3 of
the 1
st
Authority’s order reads as under:
“3. The learned counsel for the Complainants submitted
that MahaRERA in Complaint no. CC006000000054636,
has directed the Respondent to handover possession by
December, 2019 allowing the Respondent, in the interest
of completing the project, to complete the project first
with liberty to Complainants to demand interest at an
appropriate stage, as per the provisions of Section 18 of
the Real Estate (Regulation and Development) Act, 2016
and that similar order be passed in the present complaint
also. Further, he submitted that the Respondent be
directed to initiate process of society formation.”
57.The above submissions canvassed by learned counsel for
allottees was a plea of parity being fully aware of the earlier order and
that same consequences would follow. The request for identical order
does not explicitly abandon the right to interest and the intent was to
follow the same course as the allottees in other complaint. The
contention of Mr. Vakil is in fact an argument on estoppel and waiver of
right to file appeal, which principle is traceable to Section 96(3) of
Code of Civil Procedure, 1908 precluding the filing of appeal against a
consent decree. For estoppel to operate it must be shown that there
was express waiver, compromise or relinquishment of some benefit
which is now sought in the appeal. The submissions does not indicate
any express waiver by the allottees. The request for similar order is not
Sairaj 33 of 40
SA-472-2021 (final).doc
a concession as there is no waiver or abandonment of right. Even
accepting that the submission of the Advocate for the allottees
constitutes a concession, the allottees had a right under Section 18 of
RERA Act to demand interest for every month of delayed possession
and deferment of the statutory right to demand interest, if accepted as
concession, amounts to concession given by the Advocate on question
of law, which would not preclude the allottees from filing the appeal as
there can be no estoppel against law.
58.Dealing with the citations relied upon by Mr. Vakil, the decision in
the case of Era Realtors Private Limited vs. Prakash Shah and
Another
19
was pressed into service in support of the contention that
the Appeal was not maintainable in view of the concession of the
allottees. In the case of Era Realtors Private Limited (supra), the
complaint was filed under Section 18 of RERA Act for a direction to
Developer to execute a registered Agreement for sale, to pay interest
for delayed possession and to pass GST credit on to the Respondents
therein. The RERA Authority directed handing over possession and
payment of interest on the amounts collected after May, 2017 with the
finding recorded that the amount post May, 2017 had already been
collected after executing registered agreement for sale in accordance
with Section 13 of RERA Act. The Appellate Authority was moved to
19 S.A. (St.) No. 27241 of 2023, decided on 14
th
March, 2024.
Sairaj 34 of 40
SA-472-2021 (final).doc
the extent of denial of payment of interest before May, 2017, which
was entertained by the Appellate Tribunal. The contention before this
Court was that the Respondents specifically agreed before the
Regulatory Authority that the interest can be only paid after the
implementation of the RERA Act and therefore, the regulatory
authority directed the payment of interest post May, 2017. It is in such
facts where the Respondents therein gave up their claim for interest
prior to May, 2017 that this Court held that the Appeal was not
maintainable. Before the Appellate Authority, the Respondents therein
claimed that no such concession was given by them before the
Regulatory Authority and as the Respondent’s neither filed an
application before the Regulatory Authority complaining about
erroneous recording of concession nor any specific ground was raised
in Appeal, this Court held that the Appellate Authority could not have
entertained the Appeal. In the facts of that case, there was an express
waiver of the benefit by the Respondents which was thereafter,
questioned before the Appellate Authority on the ground that no such
concession was given. The present factual scenario is completely
distinguishable as there is no express waiver of any benefit.
59.The decision in the case of Institute of Chartered Accountants
of India vs. L. K. Ratna (supra) holds that if natural justice is violated at
first stage, the right of appeal is not so much a true right of appeal as a
Sairaj 35 of 40
SA-472-2021 (final).doc
corrected initial hearing. Essentially, it holds that the defense of
natural justice before the Trial Court cannot be cured by giving a
hearing at the Appellate stage. There is no quarrel with the said
proposition. In the present case, the order of 1
st
authority notes the
submission of learned counsel for Promoter in the order of 31
st
January, 2019. It is not the case of Promoters that there was no
hearing which was given to them. The complaint was filed in
September, 2019 and there was an ample opportunity available to the
promoter to file their reply. In the hearing of 31
st
January, 2019, it is
not even the submission of promoter that the time be given for the
purpose of filing reply. It was open for the promoters to advance
arguments now sought to be raised before this Court for payment of
interest before the 1
st
Authority. The only submission canvassed is that
the construction work or project could not be completed for reasons
beyond the Promoter’s control. The order of 31
st
January, 2019 was not
passed without without giving an opportunity of hearing to the
promoter, merely on the basis of submissions of learned counsel
appearing for Allottees. The violation of principles of natural justice is
an afterthought raised in the present case.
60.The decision of Sports Authority of India vs. Dr. Kulbir Singh
Rana (supra) is on the aspect of maintainability of the Appeal, once the
concession has been given. As this Court has already held that the
Sairaj 36 of 40
SA-472-2021 (final).doc
order of the 1
st
Appellate Authority was only on parity and not a
concession given, the decision does not assist the case of the
promoter. Similarly, the decision in the case of Rajasthan Industrial
Development and Investment Corporation vs. Diamond and Gem
Development Corporation Limited (supra) reiterates the principles of
estoppel which does not assist the case of the promoter.
61.In light of the above discussion, the substantial questions of law
are answered as under:
(a) Under the provisions of Section 18 of RERA Act,
the handing over possession as per terms of
agreement or as per the date specified is sacrosanct
remaining unqualified by any contingencies outside
the terms of the agreement and is not affected by
the acceptance of delayed performance. The allottee
would be well within their statutory right to claim
interest for every month of delayed possession for
the period specified in the flat purchaser’s
agreement till the date of handing over possession.
(b) Whereas Section 18 of RERA Act gives an
unqualified absolute statutory right to claim interest
unimpeded by any condition, Section 55 of Contract
Sairaj 37 of 40
SA-472-2021 (final).doc
Act lays fetters on that right making it subject to
giving notice of intention to claim compensation. The
inconsistency between the two provisions is on the
aspect of claim of compensation. RERA Act being a
special enactment will prevail over Contract Act, a
general law. Section 89 of RERA Act gives it an
overriding effect over anything inconsistent with the
other laws and the retroactive application of RERA
Act would impose an obligation on the promoter to
pay interest for the delayed possession computed
from the date of handing over possession as
specified in the agreement even in the absence of
any notice to the promoter by the allottee of its
intention to do so.
(c) The aspect of seeking benefit of moratorium is
covered by decision of this Court in M/s. Pragatej
Builders and Developers Pvt. Ltd. vs. Abhishek Anju
Sukhadia (supra) and being settled does not give rise
to substantial question of law.
Sairaj 38 of 40
SA-472-2021 (final).doc
(d) The submission of the allottees before the 1
st
authority was plea of parity and the request for
identical order does not explicitly abandon the right
to interest and for estoppel to operate, there must be
express waiver, compromise or relinquishment of the
benefit. The allottees have a right under Section 18 of
RERA Act to demand interest for every month of
delayed possession and deferment of the statutory
rights, if accepted, as concession, amounts to
concession given by the Advocate on question of law
which would not preclude the allottees from filing
the Appeal.
62.In light of the substantial questions of law answered as above,
the Second Appeal stands dismissed.
63.In view of above, nothing survives for consideration in pending
Applications, if any, and the same stand disposed of.
[Sharmila U. Deshmukh, J.]
64.At this stage, learned counsel appearing for the Appellant seeks
relief of stay of execution proceedings for period of four weeks from
today. Though the said request is opposed by learned counsel
Sairaj 39 of 40
SA-472-2021 (final).doc
appearing for the Respondent, considering that the statement was
operating during the pendency of Second Appeal, the execution
proceedings to be deferred by period of four weeks from 24
th
June,
2026.
[Sharmila U. Deshmukh, J.]
Sairaj 40 of 40
The Bombay High Court recently delivered a landmark judgment in CCI Projects Private Limited vs. Mr. Sriram Krishnan & Ors., a crucial ruling on RERA Act Section 18 and Delayed Possession Compensation. This significant decision, now thoroughly analyzed on CaseOn, provides much-needed clarity on promoter obligations and allottee rights under the Real Estate (Regulation and Development) Act, 2016.
', 'The case originated from a complaint filed by allottees against CCI Projects Private Limited, the promoter of the 'Wintergreen' project. An agreement for sale, dated November 18, 2014, stipulated possession by June 30, 2017. However, possession was not granted even by the time the complaint was filed. The allottees had paid a significant portion of the flat consideration, along with stamp duty and registration charges.
", 'The promoter initially proposed a completion date of December 31, 2018, later revised to December 31, 2019, under RERA registration. The allottees sought possession and interest for delayed delivery from July 1, 2017.
', "The Maharashtra Real Estate Regulatory Authority (MahaRERA) initially directed the promoter to hand over possession by December 2019, allowing allottees to claim interest later. Dissatisfied, the allottees appealed to the Maharashtra Real Estate Appellate Tribunal, which quashed MahaRERA's order and directed the promoter to pay interest at SBI's highest Marginal Cost of Lending Rate plus 2% from July 1, 2017, along with costs. The promoter then challenged this decision in the High Court.
", 'The Bombay High Court framed four substantial questions of law to address the promoter's appeal:
", 'The High Court meticulously analyzed each question, drawing upon statutory provisions and established precedents.
', 'The Court combined Issues 1 and 2, concluding that **RERA Act Section 18** confers an unqualified and absolute statutory right on allottees to claim interest for delayed possession. Unlike Section 55 of the Indian Contract Act, which requires notice for compensation if delayed performance is accepted, RERA Act Section 18 allows allottees to remain with the project and still claim interest for every month of delay, without any precondition of notice. This means that merely accepting a revised payment schedule or delayed possession does not waive the allottees' right to interest.
", 'The Court emphasized that RERA Act is a special enactment designed to protect consumer interests in real estate. Section 89 of the RERA Act gives it an overriding effect over inconsistent provisions in other laws. Citing Supreme Court judgments in Imperia Structures Limited vs. Anil Patni and Newtech Promoters and Developers Private Limited vs. State of U.P., the High Court reaffirmed that the RERA Act has retroactive application and establishes an unconditional right to interest for allottees when possession is delayed beyond the agreed-upon date.
', 'The Court clarified that the date specified in the agreement for sale is sacrosanct under Section 18 of the RERA Act, and any purported alteration through the conduct of parties would undermine the summary nature of RERA proceedings.
', 'For legal professionals seeking swift insights into complex rulings like this, CaseOn.in offers concise 2-minute audio briefs that highlight key takeaways and implications, making it easier to stay updated on critical developments in real estate law.
', 'Addressing Issue 3, regarding force majeure events, the Court noted that the agreed possession date was June 2017, and the revised RERA date was 2019. The COVID-19 pandemic, cited as a force majeure event, occurred much later. The Court relied on its co-ordinate bench decision in M/s Pragatej Builders and Developers Pvt Ltd vs. Abhishek Anju Sukhadia, which held that force majeure events occurring after the due date for possession cannot be used by promoters to escape liability for interest on prior delays. Therefore, this issue did not constitute a substantial question of law.
', 'On Issue 4, concerning the maintainability of the appeal due to an alleged concession, the Court found no merit in the promoter's argument. The allottees' request for a 'similar order' as in a connected complaint was interpreted as a 'plea of parity,' not an explicit abandonment of their right to interest. The Court clarified that for estoppel or waiver to apply, there must be an express waiver, compromise, or relinquishment of a benefit. Since the right to claim interest under Section 18 of RERA is a statutory right, a concession on a question of law by an advocate does not preclude an appeal, as there can be no estoppel against law.
", "Furthermore, the Court dismissed the promoter's claim of natural justice violation, noting they had ample opportunity to present their case before MahaRERA.
", 'The Second Appeal was dismissed by the Bombay High Court. The Court affirmed that allottees possess an unqualified, absolute statutory right under Section 18 of the RERA Act to claim interest for delayed possession from the original agreed date. This right is not contingent on providing notice of intent to claim compensation and overrides any conflicting provisions in the Indian Contract Act, 1872. Force majeure events occurring after the original possession deadline do not exempt promoters from liability for earlier delays. Moreover, a request for a 'similar order' based on a comparable case does not constitute an express waiver of statutory rights, ensuring the maintainability of an appeal.
", 'This judgment is critical for several reasons:
', 'All information provided in this analysis is for informational purposes only and does not constitute legal advice. Readers should consult with a qualified legal professional for advice on specific legal issues.
']
Legal Notes
Add a Note....