No Acts & Articles mentioned in this case
2025:MHC:22661 OP No. 60 of 2018
IN THE HIGH COURT OF JUDICATURE AT MADRAS
RESERVED ON : 19.09.2025
PRONOUNCED ON : 23.09.2025
CORAM
THE HONOURABLE MR.JUSTICE N.ANAND VENKATESH
OP No. 60 of 2018
AND
ARB O.P(COM.DIV.) NO. 77 OF 2021
OP No. 60 of 2018
Chief Engineer
Metropolitan Transport Project
(Railways), Southern Railway, Egmore,
Chennai-600 008.
Petitioner(s)
.Vs.
1. Engineering Products (I)
Limited, 3D, EC Chambers,
No.92, G.N.Chetty Street, T.Nagar,
Chennai-600 017.
2.Mr.S.Balachandran
Chief Electrical Engineer,
Delhi Metro Rail Corporation Limited,
Kochi.
https://www.mhc.tn.gov.in/judis ( Uploaded on: 18/11/2025 08:39:29 pm )
2 OP No. 60 of 2018
3.Mr.A.K.Sinha
Chief Planning and Development
Engineer, Southern Railway
Chennai-600 003.
4.Mr.K.Govindasai Babu
Deputy Financial Adviser and Chief
Accounts Officer,
Headquarters Office, Southern Railway,
Chennai-600 003.
Respondent(s)
PRAYER
Original Petition filed under Section 34 of the Arbitration and
Conciliation Act, 1996, to set aside the arbitral award of respondents 2 to 4
dated 17.11.2014 made in relation to the disputes arising out of Agreement
No.MTP/Civil/ 368/2000 in so far as the award under claims 5,8, and 12 are
concerned and to direct the respondents to pay the cost to the petitioner.
For Petitioner(s):Mr.P.T.Ramkumar
Standing Counsel
For Respondent(s) :
Mr.K.Harishankar
and
Ms.Mithreyi Kasthurirangan https://www.mhc.tn.gov.in/judis ( Uploaded on: 18/11/2025 08:39:29 pm )
3 OP No. 60 of 2018
Arb O.P(COM.DIV.) No. 77 of 2021
M/s. Engineering Projects (i) Ltd
3-D, EC Chmabers, 92 GN Chetty
Street,T.Nagar
Chennai 600 017.
Petitioner
.Vs.
The Chief Engineer
MTP (Railways)
Southern Railways, Egmore,
Chennai 600 008.
Respondent(s)
PRAYER
Petition filed under Section 34 of Arbitration and Conciliation Act, 1996,
that the Award of the Arbitral Tribunal dated 17.11.2014 made by the Arbitrators
in relation to the disputes arising out of the agreement
No.MTP/CIVIL/368/2000 dated 12.09.2000 in so far as disallowing part of the
claim No.1, 2, entire claim No.3, part of claim No.5,6, entire claim No.7, part of
claim No.8. entire claim No.10, part of claim No.12 and entire claim No.13 are
concerned may be set aside.
For Petitioner(s):Mr.K.Harishankar
and
Ms.Mithreyi Kasthurirangan
For Respondent(s) :Mr.P.T.Ramkumar
Standing Counsel for Railways https://www.mhc.tn.gov.in/judis ( Uploaded on: 18/11/2025 08:39:29 pm )
4 OP No. 60 of 2018
COMMON ORDER
These petitions have been filed under Section 34 of the Arbitration and
Conciliation Act, 1996 [for brevity hereinafter referred as 'the Act'] against the
award of the Arbitral Tribunal dated 17.11.2014. Insofar as
Arb.O.P(Com.Div.)No.77 of 2021, disallowing the part of the Claim Nos.1, 2,
5, 6, 8 and 12 and disallowing the entire claim in Claim Nos. 3, 7, 10 and 13 has
been put to challenge. Insofar as OP.No.60 of 2018, the award granting Claim
Nos.5, 8 and 12 has been put to challenge.
2.The respondent invited tenders for execution of MRTS Phase-II
between Thirumalai (LUZ) - Velachery, specifically for Pile Foundation and
RCC works in columns, beams and slabs of the station building at Kotturpuram
adjoining Buckingham Canal.
3.The petitioners bid was accepted by Letter of Acceptance dated
22.5.2000 for a contract value of Rs.5,52,08,490/-. The agreement was
executed on 12.09.2000 with a stipulated completion period of 12 months https://www.mhc.tn.gov.in/judis ( Uploaded on: 18/11/2025 08:39:29 pm )
5 OP No. 60 of 2018
commencing from 22.5.2000 upto 21.5.2001.
4.The completion of work was delayed due to several factors. Extension
of time was granted by the respondents under Clause 17(2) of the General
Conditions of Contract [GCC]. The work was ultimately completed on
10.11.2004 and completion certificate was also issued by the respondents.
5.Disputes arose between the parties and hence an Arbitral Tribunal was
constitued by order dated 29.01.2008. The Tribunal after hearing both sides
passed an award dated 17.11.2014. The same has been put to challenge in these
petitions by both the petitioner and the respondents with respect to certain
claims.
6.Heard the learned counsel for the petitioner and the learned counsel
appearing on behalf of the respondents. https://www.mhc.tn.gov.in/judis ( Uploaded on: 18/11/2025 08:39:29 pm )
6 OP No. 60 of 2018
7.The claim made by the claimant, the substantiation made by the
claimant, the defence taken by the Southern Railways and the findings rendered
by the Arbitral Tribunal are tabulated and extracted hereunder for easy
understanding:
S.No.Description of
Claim
Substantiation
made by the
Claimant
Defence raised
by the
Respondent
Findings
rendered in
the Arbitral
Award
Claim
1
Increase of 30%
on the value of
the work done
during the
extended
The Claimant
submits that
though the
contract
stipulated a
completion
period of 12
months, delays
in drawings and
material supply
on the part of
the Respondent
extended the
work by over 3
years. It is
urged that the
rates quoted
became
unworkable
owing to
inflation and
escalation. The
Claimant
contends that
substantial work
to the value of
₹4,88,50,501/-
was executed
during this
extended
period, for
The
Respondent
has sought
rejection of
the claim,
contending
that the
delays were
occasioned by
the Claimant’s
failure to
mobilize
skilled labour,
machinery and
planning,
including
repeated
failures of the
batching
plant. It is
further
contended
that
extensions
were granted
only upon the
Claimant’s
request and
rider
agreements
were executed
The Tribunal
held that the
original 12-
month
completion
period for the
Rs.
5,52,08,490/
- Crores
contract was
unrealistic
and
unjustified,
given the
difficult site
conditions
(coffer dam
in water,
excavation of
slum).
Relying on
Clause 17(2)
of the GCC,
the Tribunal
found no
delay
attributable
to the
claimant and
upheld the
application of https://www.mhc.tn.gov.in/judis ( Uploaded on: 18/11/2025 08:39:29 pm )
7 OP No. 60 of 2018
which
reimbursement
of escalation at
25% (₹
1,22,12,625/-)
is sought,
placing reliance
on decisions of
the Hon’ble
Supreme Court
permitting
compensation
despite
contractual
prohibitions
when delay is
attributable to
the Respondent.
reaffirming
the original
rates. It is
also the case
of the
Respondent
that the
Claimant
furnished a
“No Claim
Certificate”
before
settlement of
the final bill.
Hence, the
demand for
enhanced
rates is urged
to be an
afterthought
and
untenable.
the Price
Variation
Clause (PVC)
formula as
per Railway
circulars. It
fixed a
reasonable
completion
period of 18
months and
applied PVC
formula to
works
executed
beyond 12
months.
Based on bill-
wise records
from CC Bill
No. 8
onwards, the
Tribunal
calculated
escalation at
Rs.
9,24,035/-
and awarded
this amount
to the
claimant,
ensuring
compensation
while
acknowledgin
g shared
responsibility
of both
parties.
Claim
2
Payment for the
additional
quantity of coffer
dam
arrangements
made.
The Claimant
submits that
though Item 8
of Annexure IVA
referred to
cofferdams in
the Buckingham
The
Respondent
has sought
rejection of
the claim,
contending
that payment
The Tribunal
held that the
Respondent
failed to
prove non-
execution of
coffer dam https://www.mhc.tn.gov.in/judis ( Uploaded on: 18/11/2025 08:39:29 pm )
8 OP No. 60 of 2018
Canal alone,
site conditions
made
cofferdams
necessary for
pile caps and tie
beams across
the site. It is
urged that
execution
extended to
4960 RM as
against 1000
RM stipulated in
the agreement,
and the
Claimant, under
instructions and
supervision of
the Respondent,
carried out such
works. Payment
for the balance
1720 RM,
amounting to
Rs.96,95,000/-,
is therefore
sought.
for cofferdam
works is
governed by
Item 8 of
Annexure IVA
and its
necessity is
determined by
the Engineer-
in-Charge. It
is submitted
that the
Claimant was
duly paid
wherever
cofferdams
were
executed,
even beyond
agreed
quantities,
and that the
Claimant had
signed the
final bill and
variation
statement
without
protest. The
claim is urged
to be an
afterthought
and
unsustainable.
works and
offered no
justification
for
differential
treatment
between
similar pile
rows (Row E
vs. Row F). It
found that
coffer dams
were
technically
necessary for
Rows F, G
and H, given
their cut-off
levels below
MSL.
Rejecting the
claim for full
rates, the
Tribunal
adopted a
reasonable
rate of one-
third
agreement
rate (Rs.
1,875/Rm)
for makeshift
coffer dams,
applying
compensator
y
percentages
—50% (Row
F), 25%
(Row G),
15% (Row H)
—based on
inspection.
The
admissible
perimeter
was fixed at https://www.mhc.tn.gov.in/judis ( Uploaded on: 18/11/2025 08:39:29 pm )
9 OP No. 60 of 2018
858.4389m,
subject to a
4% reduction
for exceeding
the 125%
quantity
limit.
Accordingly,
the Tribunal
awarded Rs.
12,51,604/-
for the
unpaid coffer
dam work.
Claim
3
Compensation for
reduction in scope
work of station
building works.
The Claimant
submits that the
removal of
station building
works, without
any default on
its part,
amounts to
partial
prevention and
breach of
contract. Loss
of profit is
claimed at 10%
of the value of
work worth Rs.
80,00,000/-,
i.e., Rs.
8,00,000/-.
The
Respondent
has sought
rejection of
the claim,
contending
that the
Claimant
executed the
entire scope of
work and, in
fact, exceeded
the agreement
value by
3.73%. It is
submitted that
works worth
Rs.
5,75,89,250.8
0/- Crores
were executed
as against the
agreement
value of Rs.
5,55,20,848.90
/- Crores.
Hence, the
allegation of
reduction of
scope or loss
of profit is
baseless.
The Tribunal
held that the
overall
variation in
execution,
even without
the purported
office
building, was
only 3.73%
above the
agreement
value. It
found that no
agreed work
had been
dropped and
the
Respondent’s
official notes
could not
serve as
proof of any
contractual
obligation to
construct an
office
building.
Accordingly,
the claim was
rejected. https://www.mhc.tn.gov.in/judis ( Uploaded on: 18/11/2025 08:39:29 pm )
10 OP No. 60 of 2018
Claim
4
Payment for
empty boring
The Claimant
submits that
though the
contract
specified no
limit for empty
boring,
abnormal
depths were
encountered,
which could not
have been
anticipated
while quoting
rates. It is
contended that
810m of empty
boring was
carried out
across piles,
incurring Rs.
9,80,726/- and
reimbursement
is sought as the
work was
essential and
unavoidable.
The
Respondent
has sought
rejection of
the claim,
contending
that the
contractor was
required to fix
the working
platform level
to minimize
empty boring,
and that no
extra payment
was
admissible
under the
agreement. It
is further
urged that the
Claimant
failed to set
the platform
optimally,
resulting in
excess empty
boring, and
that the claim
constitutes an
excepted
matter under
the contract.
The Tribunal
noted that
the
Respondent
had not
disputed the
quantum of
empty
boring,
thereby
accepting the
claimant’s
figures. It
held that the
final drawing
was issued
during
execution,
preventing
the claimant
from
foreseeing
and pricing
this work at
the tender
stage.
Rejecting the
allegation of
poor
planning, the
Tribunal
emphasized
that the
claimant, as
an
experienced
contractor
chosen by
the Railways,
could not be
presumed
negligent.
Accordingly,
applying a
reduced rate
to the https://www.mhc.tn.gov.in/judis ( Uploaded on: 18/11/2025 08:39:29 pm )
11 OP No. 60 of 2018
undisputed
extra empty
boring
quantities,
the Tribunal
awarded
Rs.9,17,952/-.
Claim
5
Compensation
towards loss of
profits and
overheads.
The Claimant
submits that the
Respondent
failed to hand
over the site
and drawings as
required under
Section 52 of
the Contract
Act, thereby
committing
breach. Though
the contract
period was 12
months, the
work extended
to 42 months
solely due to
the
Respondent’s
delays. It is
further urged
that schedule
quantities were
misleading,
payments were
delayed, and
the Claimant
suffered heavy
cost escalation.
By applying
Hudson’s
formula, loss of
overheads and
profit is
quantified at Rs.
277,60,000/-.
The
Respondent
has sought
rejection of
the claim,
contending
that the PVC
formula was
inapplicable,
that
extensions
were granted
only at the
Claimant’s
request
through rider
agreements
reaffirming
original rates,
and that
therefore no
escalation or
compensation
was payable.
The claim is
alleged to be
an
afterthought.
The Tribunal
rejected most
of the
claimant’s
contentions
as
unsubstantiat
ed and
abstract
statements,
except the
proven delay
in payment of
CC Bills 26
and 27. It
held that the
claimant was
entitled to
compensation
for the lost
opportunity
of funds
during the
delayed
period.
Accordingly,
the Tribunal
awarded Rs.
21,246/-
towards
interest at
12% p.a. on
the amounts
of the two
bills. https://www.mhc.tn.gov.in/judis ( Uploaded on: 18/11/2025 08:39:29 pm )
12 OP No. 60 of 2018
Claim
6
Payment for the
extra works done
not covered by
the agreement
The Claimant
submits that
under the
instructions and
supervision of
the Respondent,
it executed
additional works
such as
demolition of
abandoned
structures,
cable
protection,
earth cutting,
and formation
of earthen
bunds. It is
urged that the
total value of
such works
comes to Rs.
36,42,025/-, for
which
reimbursement
is claimed.
The
Respondent
has sought
rejection of
the claim,
contending
that
demolition
works were
already settled
under the final
bill and no-
claim
certificate,
that cable
protection was
a contractual
obligation
without any
protest. The
earthwork for
pile caps and
diversions was
incidental to
the contract.
It is
contended
that the
claims are
contrary to
the contract
and
unsupported
by any
records.
The Tribunal
held that the
claimant had
not produced
any proof of
the
Respondent
directing
execution of
the alleged
works and
had never
raised these
claims prior
to arbitration
proceedings.
As the claims
were
unsubstantiat
ed, they were
rejected.
Claim
7
Compensation for
idle labour
The Claimant
submits that it
mobilized
labour,
machinery, and
staff
immediately
after the letter
of acceptance,
The
Respondent
has sought
rejection of
the claim,
contending
that despite
67% of the
site and
The Tribunal
acknowledge
d idling
caused by
shared delay
but found
that the
claimant had
provided no https://www.mhc.tn.gov.in/judis ( Uploaded on: 18/11/2025 08:39:29 pm )
13 OP No. 60 of 2018
but due to the
Respondent’s
failure to issue
drawings, the
workforce
remained idle.
It is contended
that this led to
infructuous
expenditure on
idle labour
quantified at Rs.
18,49,250/-,
which is sought
as
compensation.
drawings
being
available, the
Claimant
failed to make
preliminary
arrangements
such as
winches,
chisels,
bailers, power
supply, and
liner bending
setups. It is
urged that the
delay was due
to poor
planning by
the Claimant,
and the
department
cannot be held
liable.
documentary
proof of
expenditure.
Since
compensation
for delays
was already
considered
under Claims
1 and 5, the
Tribunal
rejected the
claim.
Claim
8
Compensation for
idle Machinery
and Plants - Loss
of productivity
The Claimant
submits that
various
equipment
remained idle
due to the
Respondent’s
defaults and
claimed
compensation
as follows:
1.Rigs and
other machinery
(including
generator, plate
bending, etc.) –
Rs.21,41,750/-.
2.62 KVA
Generator – Rs.
1,35,000/-.
The
Respondent
has sought
rejection of
the claim,
contending
that only two
tripods were
initially
brought, that
essential
machinery
such as liner
bending
machines,
winches, and
batching
plants were
delayed by the
Claimant, and
that no
alternate
arrangements
The Tribunal
partly upheld
the
claimant’s
idling claims
based on
admitted
facts and
reasonable
market rates:
1. Piling Rigs:
Accepted
Respondent’s
own letter
showing
2119 hours
idling;
compensation
awarded at
market rental
rate.
2. Generator:
Rejected for https://www.mhc.tn.gov.in/judis ( Uploaded on: 18/11/2025 08:39:29 pm )
14 OP No. 60 of 2018
3.Plate Bending
Machine – idle
from
01.06.2000 to
16.10.2000, at
Rs. 20,000/-
per month.
4.Batching Plant
– idle from
05.11.2000 to
15.04.2001,
claim of Rs.
5,50,000/-.
5.Welding
Transformer –
idle from
01.06.2000 to
16.10.2000 (Rs.
67,500/-) and
from
16.10.2000 to
01.03.2001 (Rs.
33,750/-).
were made. It
is submitted
that idle
periods were
attributable
solely to the
Claimant’s
poor planning
and failure to
mobilize
resources.
lack of proof.
3. Plate
Bending
Machine
(10hp):
Found 34
days idling,
awarded at
market rate
(lower than
claimant’s
rate).
4. Batching
Plant: Held
Respondent
failed to hand
over land,
causing 5.5
months
delay;
compensation
awarded at
market rate.
5. Concrete
Mixer:
Rejected as
not required
for the
project.
6. Welding
Transformers
: Awarded
partial
compensation
for 3 units at
a
conservative
rate.
Accordingly,
the Tribunal
awarded a
total of Rs.
4,09,659/-. https://www.mhc.tn.gov.in/judis ( Uploaded on: 18/11/2025 08:39:29 pm )
15 OP No. 60 of 2018
Claim
9
Refund of the cost
of empty Gunny
Bags recovered
The Claimant
submits that the
Respondent
recovered Rs.
4,43,946/-
towards the
cost of empty
cement bags
despite there
being no clause
in the contract
authorising such
recovery. It is
urged that since
empty cement
bags are not
the
Respondent’s
property under
Clause 33(3) of
the GCC, the
recovery is
without
contractual
basis and
refund is
sought.
The
Respondent
has sought
rejection of
the claim,
contending
that under
Clause 33(3)
of the GCC
empty cement
bags are
departmental
property and
that the
Claimant
failed to
return them.
Hence,
recovery of
Rs. 2,95,964/-
at Rs. 2 per
bag was
rightly made.
The Tribunal
noted that
the
Respondent
did not
dispute the
claimant’s
contention
that cement
was issued in
HDPE bags
and offered
no evidence
of supply in
gunny bags.
It held that
the recovery
made on this
basis was
unjustified.
Accordingly,
the Tribunal
awarded Rs.
2,95,964/- to
the claimant.
Claim
10
Refund of the
rebate of 19%
offered
The Claimant
submits that it
relied on the
Respondent’s
planning and
cooperation to
complete the
work on time,
but due to
misrepresentati
on, suppression
of facts and
failure of
project
management,
the rebate
granted has no
justification.
Refund of the
The
Respondent
has sought
rejection of
the claim,
contending
that the
quoted rate
was based on
the Claimant’s
own
assessment,
and that
delays arose
from the
Claimant’s
failure to
mobilize rigs,
batching plant
The Tribunal
held that a
negative
percentage
quoted in the
tender
constituted a
firm value
accepted by
the Railways
and could not
be treated as
a rebate.
Since the
claimant had
not attached
any
conditions to
the rate https://www.mhc.tn.gov.in/judis ( Uploaded on: 18/11/2025 08:39:29 pm )
16 OP No. 60 of 2018
rebate of 19%
amounting to
Rs.
1,33,32,164/-
upto Bill No CC-
32 dated
01.02.2006 is
sought for from
the Respondent.
and
manpower,
except for
minor delay in
handing over
encroached
portions for
which
extension was
granted.
offered, the
claim was
found not
maintainable
and was
rejected.
Claim
11
Refund of
recovery towards
cost of excess
consumption of
cement
The Claimant
submits that the
Respondent
recovered Rs.
5,80,422/- for
alleged excess
cement
consumption,
despite the
Claimant
demonstrating
that usage was
within the
supplied
quantities.
Refund of the
recovered sum
is sought.
The
Respondent
has sought
rejection of
the claim,
contending
that excess
cement
consumption
of 2477 bags
arose due to
wastage, pipe
choking, and
finishing
works. It is
further
contended
that recovery,
including
penalty, was
rightly made,
and that the
Claimant had
signed the
material
reconciliation
statements
and furnished
no-claim
certificates.
The Tribunal
found that
wastage for
operational
procedures
like priming
and testing is
an
"indispensabl
e" and
"inevitable"
part of the
work. The
Respondent's
own
admission of
cement use
for "touch up
works" and
"choking of
pipeline"
supported
this.
At the same
time, the
Tribunal
found the
Claimant
partly at fault
for not
keeping
separate
records of
cement used
for priming, https://www.mhc.tn.gov.in/judis ( Uploaded on: 18/11/2025 08:39:29 pm )
17 OP No. 60 of 2018
which led to
confusion.
Considering
this shared
responsibility,
the Tribunal
ordered 50%
reimburseme
nt of the
recovered
amount,
awarding Rs.
2,72,829/-.
Claim
12
Loss of businessThe Claimant
submits that
delay of more
than 30 months
in execution due
to the
Respondent’s
breach caused
late return of
deposits and
guarantees,
resulting in a
loss of potential
profits of Rs.
60,00,000 /-
from alternate
projects.
The
Respondent
has sought
rejection of
the claim,
contending
that delays
were caused
solely by the
Claimant’s
failure to
mobilize
materials,
skilled
manpower and
poor day to
day
management.
The majority
held that the
Respondent’s
withholding
of funds
caused the
claimant a
financial loss
from erosion
of money
value due to
inflation.
Applying an
Annual
Monetary
Appreciation
Rate (AMAR)
of 11.08%
(derived from
the average
SBI lending
rate) to the
withheld
sums, the
majority
calculated
compensation
at Rs.
4,40,370/-.
One
arbitrator https://www.mhc.tn.gov.in/judis ( Uploaded on: 18/11/2025 08:39:29 pm )
18 OP No. 60 of 2018
dissented,
awarding NIL
on the
grounds that
the claim was
speculative,
the contract
barred
interest on
guarantees
and no proof
of potential
profit
existed.
Accordingly,
by majority,
the Tribunal
awarded Rs.
4,40,370/-
for the
money that
was wrongly
withheld.
Claim
13
Interest charges
on the amount of
final bill and
security deposit
The Respondent
unduly delayed
payment of the
final bill and
retention of the
security deposit
and performance
guarantee,
depriving the
Claimant of rightful
funds. The
Respondent is
liable to pay
interest of
Rs.8,13,935/-
(Rs.1,46,227 on
the final bill and
Rs.6,67,708 on
security/guarantee)
at 18% p.a. from
due dates to actual
payment from
10.12.2004 to
03.02.2006.
The
Respondent
has sought
rejection of
the claim,
contending
that delay in
final payment
was solely due
to the
Claimant’s
defaults in
providing a
site engineer,
finalising
measurements
, and scrutiny
of documents.
It is urged
that no
interest is
payable.
The claim for
interest on
delayed
release of
security
deposit
amounts to
double
compensation
and is barred
under Clause
16(3) of the
GCC, which
expressly
prohibits
payment of
interest on
amounts due
to the
contractor.
Since this
clause https://www.mhc.tn.gov.in/judis ( Uploaded on: 18/11/2025 08:39:29 pm )
19 OP No. 60 of 2018
governs the
contract, the
tribunal holds
that the
claimant’s
demand for
interest on
delayed
payment of
the final bill
is untenable
and therefore
rejected.
8.The learned counsel for the claimant submitted that the findings that
were rendered by the Arbitral Tribunal insofar as Claim Nos.1, 2, 3, 5, 6 and 7
are concerned, it is unintelligible and it suffers from perversity and the same is
liable to be interfered by this Court. The learned counsel in order to substantiate
his submission, relied upon the following judgments:
a) Associate Builders .Vs. Delhi Development
Authority reported in (2015) 3 SCC 49
b) Ssangyong Engineering & Construction Company
Limited Vs. National Highways Authority of India (NHAI)
reported in (2019) 15 SCC 131
c) Dyna Technologies (P) Ltd. v. Crompton Greaves
Ltd., reported in (2019) 20 SCC 1
d) Gayatri Balasamy v. ISG Novasoft Technologies
Ltd., reported in (2025) 7 SCC 1 https://www.mhc.tn.gov.in/judis ( Uploaded on: 18/11/2025 08:39:29 pm )
20 OP No. 60 of 2018
9.Per contra, the learned Standing Counsel appearing on behalf of the
Southern Railways justified the findings rendered by the Arbitral Tribunal
insofar as all the claims are concerned except Claim Nos.5, 8 and 12 are
concerned. The learned Standing Counsel further submitted that out of the total
claim amount of Rs.45,33,700/-, already the Southern Railways has paid a sum
of Rs.36,00,000/- to the claimant.
10.This Court has carefully considered the submissions made on either
side and the materials available on record.
11.Insofar as the Judicial approach that is expected while dealing with a
petition under Section 34, it will be relevant to take note of the judgment of the
Apex Court in Associate Builders case referred supra and the relevant portion
is extracted hereunder:
28. In a recent judgment, ONGC Ltd. v. Western Geco
International Ltd. [(2014) 9 SCC 263 : (2014) 5 SCC (Civ) 12] ,
this Court added three other distinct and fundamental juristic https://www.mhc.tn.gov.in/judis ( Uploaded on: 18/11/2025 08:39:29 pm )
21 OP No. 60 of 2018
principles which must be understood as a part and parcel of the
fundamental policy of Indian law. The Court held : (SCC pp. 278-
80, paras 35 & 38-40)
“35. What then would constitute the ‘fundamental policy of
Indian law’ is the question. The decision in ONGC [(2003) 5 SCC
705 : AIR 2003 SC 2629] does not elaborate that aspect. Even
so, the expression must, in our opinion, include all such
fundamental principles as providing a basis for administration of
justice and enforcement of law in this country. Without meaning
to exhaustively enumerate the purport of the expression
‘fundamental policy of Indian law’, we may refer to three distinct
and fundamental juristic principles that must necessarily be
understood as a part and parcel of the fundamental policy of
Indian law. The first and foremost is the principle that in every
determination whether by a court or other authority that affects
the rights of a citizen or leads to any civil consequences, the
court or authority concerned is bound to adopt what is in legal
parlance called a ‘judicial approach’ in the matter. The duty to
adopt a judicial approach arises from the very nature of the
power exercised by the court or the authority does not have to be
separately or additionally enjoined upon the fora concerned.
What must be remembered is that the importance of a judicial
approach in judicial and quasi-judicial determination lies in the
fact that so long as the court, tribunal or the authority exercising
powers that affect the rights or obligations of the parties before
them shows fidelity to judicial approach, they cannot act in an
arbitrary, capricious or whimsical manner. Judicial approach
ensures that the authority acts bona fide and deals with the
subject in a fair, reasonable and objective manner and that its
decision is not actuated by any extraneous consideration. Judicial
approach in that sense acts as a check against flaws and faults https://www.mhc.tn.gov.in/judis ( Uploaded on: 18/11/2025 08:39:29 pm )
22 OP No. 60 of 2018
that can render the decision of a court, tribunal or authority
vulnerable to challenge.
***
38. Equally important and indeed fundamental to the policy
of Indian law is the principle that a court and so also a quasi-
judicial authority must, while determining the rights and
obligations of parties before it, do so in accordance with the
principles of natural justice. Besides the celebrated audi alteram
partem rule one of the facets of the principles of natural justice is
that the court/authority deciding the matter must apply its mind to
the attendant facts and circumstances while taking a view one
way or the other. Non-application of mind is a defect that is fatal
to any adjudication. Application of mind is best demonstrated by
disclosure of the mind and disclosure of mind is best done by
recording reasons in support of the decision which the court or
authority is taking. The requirement that an adjudicatory authority
must apply its mind is, in that view, so deeply embedded in our
jurisprudence that it can be described as a fundamental policy of
Indian law.
39. No less important is the principle now recognised as a
salutary juristic fundamental in administrative law that a decision
which is perverse or so irrational that no reasonable person
would have arrived at the same will not be sustained in a court of
law. Perversity or irrationality of decisions is tested on the
touchstone of Wednesbury [Associated Provincial Picture Houses
Ltd. v. Wednesbury Corpn., (1948) 1 KB 223 : (1947) 2 All ER
680 (CA)] principle of reasonableness. Decisions that fall short of
the standards of reasonableness are open to challenge in a court
of law often in writ jurisdiction of the superior courts but no less in
statutory processes wherever the same are available.
40. It is neither necessary nor proper for us to attempt an
exhaustive enumeration of what would constitute the fundamental
policy of Indian law nor is it possible to place the expression in https://www.mhc.tn.gov.in/judis ( Uploaded on: 18/11/2025 08:39:29 pm )
23 OP No. 60 of 2018
the straitjacket of a definition. What is important in the context of
the case at hand is that if on facts proved before them the
arbitrators fail to draw an inference which ought to have been
drawn or if they have drawn an inference which is on the face of
it, untenable resulting in miscarriage of justice, the adjudication
even when made by an Arbitral Tribunal that enjoys considerable
latitude and play at the joints in making awards will be open to
challenge and may be cast away or modified depending upon
whether the offending part is or is not severable from the rest.”
12.It is also relevant to take note of the judgment of the Apex Court in
Ssangyong Engineering & Construction Company case referred supra and
the relevant portion is extracted hereunder:
76. However, when it comes to the public policy of India,
argument based upon "most basic notions of justice", it is clear
that this ground can be attracted only in very exceptional
circumstances when the conscience of the Court is shocked by
infraction of fundamental notions or principles of justice. It can be
seen that the formula that was applied by the agreement
continued to be applied till February 2013 - in short, it is not
correct to say that the formula under the agreement could not be
applied in view of the Ministry's change in the base indices from
1993-1994 to 2004-2005. Further, in order to apply a linking
factor, a Circular, unilaterally issued by one party, cannot possibly https://www.mhc.tn.gov.in/judis ( Uploaded on: 18/11/2025 08:39:29 pm )
24 OP No. 60 of 2018
bind the other party to the agreement without that other party's
consent. Indeed, the Circular itself expressly stipulates that it
cannot apply unless the contractors furnish an
undertaking/affidavit that the price adjustment under the Circular
is acceptable to them. We have seen how the appellant gave
such undertaking only conditionally and without prejudice to its
argument that the Circular does not and cannot apply. This being
the case, it is clear that the majority award has created a new
contract for the parties by applying the said unilateral Circular and
by substituting a workable formula under the agreement by
another formula dehors the agreement. This being the case, a
fundamental principle of justice has been breached, namely, that
a unilateral addition or alteration of a contract can never be
foisted upon an unwilling party, nor can a party to the agreement
be liable to perform a bargain not entered into with the other
party. Clearly, such a course of conduct would be contrary to
fundamental principles of justice as followed in this country, and
shocks the conscience of this Court. However, we repeat that this
ground is available only in very exceptional circumstances, such
as the fact situation in the present case. Under no circumstance
can any court interfere with an arbitral award on the ground that
justice has not been done in the opinion of the Court. That would
be an entry into the merits of the dispute which, as we have seen,
is contrary to the ethos of Section 34 of the 1996 Act, as has
been noted earlier in this judgment. https://www.mhc.tn.gov.in/judis ( Uploaded on: 18/11/2025 08:39:29 pm )
25 OP No. 60 of 2018
13.Insofar as the scope of Section 31 and the triple test applied in Dyna
Technologies case referred supra, the relevant portions are extracted hereunder:
34.The mandate under Section 31(3) of the Arbitration Act is to
have reasoning which is intelligible and adequate and, which can in
appropriate cases be even implied by the courts from a fair reading of
the award and documents referred to thereunder, if the need be. The
aforesaid provision does not require an elaborate judgment to be
passed by the arbitrators having regard to the speedy resolution of
dispute.
35. When we consider the requirement of a reasoned order,
three characteristics of a reasoned order can be fathomed. They are:
proper, intelligible and adequate. If the reasonings in the order are
improper, they reveal a flaw in the decision-making process. If the
challenge to an award is based on impropriety or perversity in the
reasoning, then it can be challenged strictly on the grounds provided
under Section 34 of the Arbitration Act. If the challenge to an award is
based on the ground that the same is unintelligible, the same would be
equivalent of providing no reasons at all. Coming to the last aspect
concerning the challenge on adequacy of reasons, the Court while
exercising jurisdiction under Section 34 has to adjudicate the validity of
such an award based on the degree of particularity of reasoning
required having regard to the nature of issues falling for consideration.
The degree of particularity cannot be stated in a precise manner as the
same would depend on the complexity of the issue. Even if the Court
comes to a conclusion that there were gaps in the reasoning for the
conclusions reached by the Tribunal, the Court needs to have regard to
the documents submitted by the parties and the contentions raised
before the Tribunal so that awards with inadequate reasons are not set
aside in casual and cavalier manner. On the other hand, ordinarily
unintelligible awards are to be set aside, subject to party autonomy to
do away with the reasoned award. Therefore, the courts are required to https://www.mhc.tn.gov.in/judis ( Uploaded on: 18/11/2025 08:39:29 pm )
26 OP No. 60 of 2018
be careful while distinguishing between inadequacy of reasons in an
award and unintelligible awards.
14.Keeping the above principles in mind, this Court will test the
reasoning given by the Arbitral Tribunal and the decision arrived at for each
claim.
15.Insofar as the first claim is concerned, it is basically a claim made for
escalation in cost due to the delay in the completion of the work.
16.The Arbitral Tribunal came to a categorical conclusion that the nature
of work was such that it was highly unlikely that the work could have been
completed in 12 months. However, a time frame of 12 months was fixed under
the contract. The time was not the essence of the contract since the Southern
Railways was granting several time extensions under Clause 17(2) of GCC.
The Tribunal found that it is the Southern Railways which was responsible for
the delay. Having rendered such a finding, the Tribunal went on to apply, Price https://www.mhc.tn.gov.in/judis ( Uploaded on: 18/11/2025 08:39:29 pm )
27 OP No. 60 of 2018
Variation Clause [PVC] formula for calculating the compensation for escalation
in cost.
17.In the considered view of this Court, the contract is of the year 2000
and the work was completed in the year 2004 and at that point of time, this PVC
formula was not even in force. This came into existence only in the year 2011.
Hence, as a fundamental principle, the Tribunal ought not to have applied the
PVC formula for a contract which came into existence much before the coming
into force of this formula. The error in applying this formula further gets even
more bad since both the parties were not put on notice and were not heard on
the application of the PVC formula. Therefore, it clearly amounts to violation
of principles of natural justice. If the claimant had been informed that the PVC
formula is going to be applied, atleast the claimant would have the opportunity
to oppose the same and the Tribunal should have considered the said objection.
Since this basic procedure was not followed, the Tribunal fell in error by
applying PVC formula for calculating the escalation in cost. https://www.mhc.tn.gov.in/judis ( Uploaded on: 18/11/2025 08:39:29 pm )
28 OP No. 60 of 2018
18.Yet another error that was committed by the Tribunal is that the
Tribunal unilaterally without any basis fixed a period of 18 months as a
reasonable completion period. After doing so, the Tribunal took into
consideration only the period from 18.6.2001 for computation of escalation
cost.
19.There is yet another error committed by the Tribunal by apportioning a
delay of five months on the claimant. There was absolutely no scientific basis
for attributing this delay on the claimant and it was done merely on conjectures
and surmises. In the light of the above discussion, the compensation that was
computed under the heading escalation of cost suffers from patent illegality and
the reasoning is also unintelligible. Thus, there was no justification in limiting
the compensation amount to Rs.9,24,035/- under this head and the claimant will
be entitled for 30% increase in the rates by restricting the same to the quantum
of work done during the extended period and the amount claimed by the
claimant has to be necessarily awarded. https://www.mhc.tn.gov.in/judis ( Uploaded on: 18/11/2025 08:39:29 pm )
29 OP No. 60 of 2018
20. The next claim pertains to the payment for the additional quantity of
coffer dam arrangements made by the claimant. Under this claim, the claimant
had provided necessary coffer dams in certain locations when the piles and tie
beams came within the close proximity to the canal necessitating creation of
working space by means of temporary coffer dams to arrest the flow of running
water as well as heavy seepage.
21.While deciding this issue, the Arbitral Tribunal has taken into
consideration an enquiry that was made from some persons who were residents
living adjacent to the site. If the Tribunal makes any such enquiry and relies
upon the statements made by those persons, obviously the claimant must be put
on notice and such statements cannot be recorded behind the back of the
claimant. This will clearly tantamount to violation of principles of natural
justice. When the claimant had made a claim for 1720 meters by providing all
the particulars, the Tribunal has restricted to 858.4389 meters and such
reduction has been made on mere conjectures and even the rates have been
reduced on ad hoc basis. This procedure followed by the Tribunal is in violation https://www.mhc.tn.gov.in/judis ( Uploaded on: 18/11/2025 08:39:29 pm )
30 OP No. 60 of 2018
of Section 28(2) of the Act, which provides as follows:
28(2)
Th
e
arbitr a l t r i b u n a l sh a l l d e c i d e ex aequo e t b o n o or as am i a b le c o m p o s i t e u r
only if the parties have expressly authorised it to do so.
22.Even in technical arbitrations, the arbitrators cannot render findings on
mere conjectures and on ad hoc basis. There must be some scientific basis for
rendering findings. If that is done, the Court cannot sit over such findings of a
specialist. In this case, the findings that have been rendered for Claim No.2 and
the final compensation arrived at clearly suffers from non compliance of Section
28(2) of the Act, violation of principles of natural justice, patent illegality and it
is also unintelligible. Therefore, the compensation that was claimed by the
claimant under this head has to be granted.
23.Insofar as the third claim is concerned, the claimant claimed
compensation for removal of station building works. This claim was made with
the support of the letter dated 22.02.2001 [Ex.P.14] entrusting station building https://www.mhc.tn.gov.in/judis ( Uploaded on: 18/11/2025 08:39:29 pm )
31 OP No. 60 of 2018
works to the claimant. Despite this exhibit, the Tribunal without any reason
concluded that there is no reduction in scope merely because the over all
executed value exceeded 3.73 %. The Tribunal has gone to the extent of
holding that since there was no agreement for carrying out this work, there is no
justification for making the claim. This finding disregards the evidence
available and also it violates principles of natural justice. Moreover, the
findings of the Tribunal insofar as Claim No.3 is concerned suffers from patent
illegality due to ignorance of vital evidence. Accordingly, the claimant has
sought for 10% of the excluded work value of Rs.80,00,000/- amounting to
Rs.8,00,000/-. The quantum of compensation claimed by the claimant is
reasonable and it has some basis and it ought to have been granted by the
Tribunal.
24.The next issue pertains to Claim No.5 which has been put to challenge
both by the claimant as well as the Southern Railways. Claim No.5 pertains to
loss of profits and overheads. This claim was made due to prolongation and
variation in work. While discussing this claim, the entire finding has been https://www.mhc.tn.gov.in/judis ( Uploaded on: 18/11/2025 08:39:29 pm )
32 OP No. 60 of 2018
rendered in favour of the claimant and the Tribunal also holds that the claimant
deserves to be compensated for the lost opportunity by way of reasonable
compensation. The compensation that has been arrived at for Claim No.5 is
reasonable and the view taken by the Tribunal is probable and plausible view.
Hence, no interference is warranted.
25.Insofar as Claim No.6 is concerned, it pertains to payments for other
works done not covered by the agreement. The Tribunal has rejected this claim
on the ground that till the final bill was submitted, the claimant did not even
make any claim under this head.
26.Clause 43(1) of GCC provides that the contractor shall prepare and
furnish the engineers once in every month an account giving full and detailed
particulars of all claims for any additional expenses to which the contractor may
consider himself entitled to and all the extra and additional works ordered by
the engineer. Since this condition was not complied with, this claim has been https://www.mhc.tn.gov.in/judis ( Uploaded on: 18/11/2025 08:39:29 pm )
33 OP No. 60 of 2018
rejected. The view taken by the Tribunal is a possible and plausible view and
just because another view is possible for this Court, that is not a ground to
interfere under Section 34 of the Act.
27.Insofar as the Claim No.7 is concerned, it deals with compensation for
idle labour. The Tribunal has rendered a finding that since compensation has
been granted for Claim Nos.1 and 5, no separate compensation can be granted
for idle labour. Under this claim, the Tribunal ignored documentary evidence
on variation and prolongation which resulted in the machinery and labour being
kept idle due to respondent's failure to issue drawings. This Court must only
examine as to whether ignoring such evidence had any impact on the final
conclusion arrived at by the Tribunal. Claim No.1 pertained to escalation cost
and Claim No.5 pertained to loss of profits and overheads. The Tribunal felt
that since compensation is given under these heads, no separate compensation is
required under this head. This view taken by the Tribunal is a plausible view
which does not require the interference of this Court. https://www.mhc.tn.gov.in/judis ( Uploaded on: 18/11/2025 08:39:29 pm )
34 OP No. 60 of 2018
28.Insofar as the findings rendered by the Tribunal for Claim Nos.8 - 13,
this Court finds that the reasoning given by the Tribunal does not suffer from
any perversity and the compensation that was fixed under Claim Nos.8, 9, 11
and 12 are reasonable. Therefore, the same does not warrant the interference of
this Court.
29.The upshot of the above discussion is that except Claim Nos.1, 2 and 3
where this Court has interfered with the award passed by the Arbitral Tribunal,
the findings rendered with respect to the other claims are hereby sustained.
30.The next issue is as to whether the invalid portion of the award is
severable from the valid portion of the award and the award can be modified.
Useful reference can be made to the judgment of the Apex Court in Gayatri
Balasamy v. ISG Novasoft Technologies Ltd reported in (2025) 7 SCC 1.
87. Accordingly, the questions of law referred to
by Gayatri Balasamy [Gayatri Balasamy v. ISG Novasoft https://www.mhc.tn.gov.in/judis ( Uploaded on: 18/11/2025 08:39:29 pm )
35 OP No. 60 of 2018
Technologies Ltd., 2024 SCC OnLine SC 1681] are
answered by stating that the Court has a limited power
under Sections 34 and 37 of the 1996 Act to modify the
arbitral award. This limited power may be exercised under
the following circumstances:
87.1. When the award is severable, by severing the
“invalid” portion from the “valid” portion of the award, as held
in Part II of our Analysis;
87.2. By correcting any clerical, computational or
typographical errors which appear erroneous on the face of
the record, as held in Parts IV and V of our Analysis;
87.3. Post-award interest may be modified in some
circumstances as held in Part IX of our Analysis; and/or
87.4. Article 142 of the Constitution applies, albeit, the
power must be exercised with great care and caution and
within the limits of the constitutional power as outlined in
Part XII of our Analysis.
"5. Extent of judicial intervention.-Notwithstanding
anything contained in any other law for the time being in
force, in matters governed by this Part, no judicial authority
shall intervene except where so provided in this Part. https://www.mhc.tn.gov.in/judis ( Uploaded on: 18/11/2025 08:39:29 pm )
36 OP No. 60 of 2018
31. Form and contents of arbitral award.-(1) An arbitral
award shall be made in writing and shall be signed by the
members of the Arbitral Tribunal.
(2) For the purposes of sub-section (1), in arbitral
proceedings with more than one arbitrator, the signatures of
the majority of all the members of the Arbitral Tribunal shall
be sufficient so long as the reason for any omitted signature
is stated.
(3) The arbitral award shall state the reasons upon
which it is based, unless-
(a) the parties have agreed that no reasons are to be given;
or
(b) the award is an arbitral award on agreed terms under
Section 30.
(4) The arbitral award shall state its date and the
place of arbitration as determined in accordance with
Section 20 and the award shall be deemed to have been
made at that place.
(5) After the arbitral award is made, a signed copy
shall be delivered to each party.
(6) The Arbitral Tribunal may, at any time during the
arbitral proceedings, make an interim arbitral award on any
matter with respect to which it may make a final arbitral https://www.mhc.tn.gov.in/judis ( Uploaded on: 18/11/2025 08:39:29 pm )
37 OP No. 60 of 2018
award.
(7)(a) Unless otherwise agreed by the parties, where
and insofar as an arbitral award is for the payment of money,
the Arbitral Tribunal may include in the sum for which the
award is made interest, at such rate as it deems reasonable,
on the whole or any part of the money, for the whole or any
part of the period between the date on which the cause of
action arose and the date on which the award is made.
(b) A sum directed to be paid by an arbitral award
shall, unless the award otherwise directs, carry interest at
the rate of two per cent higher than the current rate of
interest prevalent on the date of award, from the date of
award to the date of payment.
Explanation.-The expression "current rate of interest" shall
have the same meaning as assigned to it under clause (b) of
Section 2 of the Interest Act, 1978 (14 of 1978).
(8) The costs of an arbitration shall be fixed by the
Arbitral Tribunal in accordance with Section 31-A.
31.The interference into Claim Nos.1, 2 and 3 are certainly a severable
part and the award passed by the Arbitral Tribunal can be modified insofar as
Claim Nos.1, 2 and 3 are concerned. https://www.mhc.tn.gov.in/judis ( Uploaded on: 18/11/2025 08:39:29 pm )
38 OP No. 60 of 2018
32.In the light of the above findings, insofar Claim No.1 is concerned,
the entire compensation sought for by the claimant with respect to increase of
30% of value of work done during the extended period for the quantum of work
done during the extended period is granted. Accordingly, compensation of
Rs.1,22,12,625/- has to be paid by the Southern Railways to the claimant under
this head.
33.Insofar as Claim No.2 is concerned, for payment of additional quantity
of coffer dam arrangements made, the claimant is entitled to be paid a total
compensation of Rs.96,95,000/- as claimed by the claimant.
34.Insofar as Claim No.3 is concerned, for payment towards removal of
station building works, the claimant is entitled to be paid a total compensation
of Rs.8,00,000/- as claimed by the claimant. https://www.mhc.tn.gov.in/judis ( Uploaded on: 18/11/2025 08:39:29 pm )
39 OP No. 60 of 2018
35.In the result, OP.No.60 of 2018, filed by the Southern Railways is
dismissed. Arb.OP(Com.Div.).No.77 of 2021, filed by the claimant is partly
allowed and the decision arrived at by the Tribunal insofar as Claim Nos.1, 2
and 3 are concerned stands modified and there shall be a direction to the
Southern Railways to pay a compensation of Rs.1,22,12,625/- for
Claim No.1, a compensation of Rs.96,95,000/- for Claim No.2 and a
compensation of Rs.8,00,000/- for Claim No.3 and it shall be paid along with
interest at the rate of 18% p.a., from the date of filing of the petition i.e., from
10.8.2021 till the date of actual payment. These amounts shall be paid by the
Southern Railways to the Claimant within a period of eight (8) weeks from the
date of receipt of the order with interest. No costs.
23-09-2025
Index:Yes
Speaking
Neutral Citation:Yes
KP https://www.mhc.tn.gov.in/judis ( Uploaded on: 18/11/2025 08:39:29 pm )
40 OP No. 60 of 2018
To
1.Engineering Products (I)
Limited, 3D, EC Chambers, No.92,
G.N.Chetty Street, T.Nagar,
Chennai-600 017.
2.Mr.S.Balachandran
Chief Electrical Engineer, Delhi Metro
Rail Corporation Limited, Kochi.
3.Mr.A.K.Sinha
Chief Palnning and Development
Engineer, Chennai-600 003.
4.Mr.K.Govindasai Babu
Deputy Financial Adviser and Chief
Accounts Officer, Headquarters Office,
Southern Railway, Chennai-600 003.
5.The Chief Engineer, Mtp (railways)
Southern Railways, Egmore,
Chennai 600 008 https://www.mhc.tn.gov.in/judis ( Uploaded on: 18/11/2025 08:39:29 pm )
41 OP No. 60 of 2018
N.ANAND VENKATESH J.
kp
OP No. 60 of 2018
AND
ARB O.P(COM.DIV.) NO. 77 OF 2021
...
23-09-2025 https://www.mhc.tn.gov.in/judis ( Uploaded on: 18/11/2025 08:39:29 pm )
Legal Notes
Add a Note....