As per case facts, news reports exposed the appalling state of National Highways 108B and 208 in Tripura, describing them as "death traps" due to potholes, broken surfaces, and water ...
Page 1 of 47
TRHC010012332026
HIGH COURT OF TRIPURA
AGARTALA
WP(C)(PIL) No.06 of 2026
Court on its own motion
V E R S U S
1. The Union of India, Represented by the Secretary, Ministry of Road
Transport & Highways (MoRTH), Government of India, located at Transport
Bhawan, 1, Parliament Street, New Delhi-110001.
2. National Highways Authority of India (NHAI), Represented by the
Chairman, located at Plot No. G/5 & 6, Sector-10, Dwarka, New Delhi-
110075.
3. The Secretary, PWD (National Highways), Government of Tripura, located
at the P.N. Complex, Gurkhabasti, Agartala, West Tripura.
4. The District Magistrate & Collector, West Tripura District, Agartala.
5. The District Magistrate & Collector, Dhalai District, Ambassa.
6. The District Magistrate & Collector, Khowai District, Khowai.
7. The Chief Engineer, PWD (National Highways), Government of Tripura, is
located at the P.N. Complex, Gurkhabasti, Agartala, West Tripura.
8. The National Highways Infrastructure Development Corporation Limited
(NHIDCL) represented by Deputy General Manager (Project), Karilong,
Teliamura, Ward No. 01, Shisubir, P.O.-Karilong, P.S.-Teliamura, Khowai,
Tripura, Pin-799205.
………Respondent(s).
For Court on its own motion : None.
For Respondent(s) : Mr. S.M. Chakraborti, Advocate General,
Mr. B.N. Majumder, Sr. Advocate,
Mr. Bidyut Majumder, Deputy S.G.I.,
Mr. Rajib Saha, Advocate,
Mrs. Pinki Chakraborty, Advocate.
HON’BLE THE CHIEF JUSTICE MR. M.S. RAMACHANDRA RAO
HON’BLE MR. JUSTICE BISWAJIT PALIT
CAV reserved on : 05.08.2026.
Judgment delivered on : 08.09.2026.
Whether fit for reporting : YES.
Page 2 of 47
TRHC010012332026
JUDGMENT & ORDER
(M.S. Ramachandra Rao, C.J.)
The origin of this PIL:
1) News reports appeared on 04.06.2026 in the local daily “Danik
Sambad”, in the “Tripura Observer” on 06.07.2026 and 18.07.2026, and in the
“Tripura Times” on 18.07.2026 apart from other newspapers, stating that the
condition of certain stretches of the two Highways i.e. NH 108B (connects
Khowai city to Agartala city of length 55 km) and National Highway 208
( Kumarghat – Kailashshar- Khowai- Teliamura- Amarpur- Sabroom of length
158 Km ) were in an appalling state and alleging corruption in the laying of
these Highways by use of substandard materials resulting in collapse of large
portions of the Highways.
2) There were references to both the Highways as “death traps”
containing large potholes, broken surfaces and rainwater accumulation making
daily travel extremely hazardous to the citizens of the State and pointing out
the significant risk to vehicles as well as persons travelling on these roads on
account of these conditions and warning of serious accidents, if the condition
of the road is not improved.
3) The News reports also indicated that the Hon‟ble Chief Minister
of the State of Tripura had written to the Hon‟ble Union Minister of Road,
Transport and Highways drawing the latter‟s attention to the deteriorating
condition of these National Highways in the State and the hardships faced by
the people during the current monsoon season and in particular, the poor
conditions of these two Highways and also NH-08 connecting Churaibari in
North Tripura District to Agartala in the West Tripura District. The news
Page 3 of 47
TRHC010012332026
reports indicated that the Hon‟ble Chief Minister had requested the Hon‟ble
Union Minister to instruct the Managing Director of NHIDCL to regularly
review the progress of construction and repair works with field level officials
in the State of Tripura and take appropriate action for timely completion. The
news report indicates that the Hon‟ble Chief Minister of the State of Tripura
had also discussed in person these issues with the Hon‟ble Union Minister.
4) Since this is an important issue relating to road safety and
connectivity in the State of Tripura, particularly in an area where there are no
railway lines which could be alternatively used for transport of goods and
movement of people, this PIL was registered on 07.07.2026.
The importance of National highways to North Eastern States:
5) National Highways are lifelines to the North Eastern States
because of their geographical location as goods and people move on these
highways so as to reach the nook and corner of these States. It is undeniable
that motorability and safe travel on these highways is the key to the prosperity
of the people of the North Eastern States.
6) The State of Tripura is an important State in the North-Eastern
part of India and is in a corner of the country, immediately next to the country
of Bangladesh. The capital city of Agartala is on the western side of the State
of Tripura adjacent to the country of Bangladesh. The State itself is covered
on almost three sides by the country of Bangladesh.
7) In the State of Tripura, there are 6(six) National Highways
stretching across a total length of 923 Kilometers.
Page 4 of 47
TRHC010012332026
The NHIDCL’s role in road maintenance and providing connectivity:
8) According to the State Government, since 2017, the Ministry of
Road, Transport and Highways, Government of India, in a phased manner at
different times had handed over the administrative role over these Highways
to the National Highways and Infrastructure Development Corporation
Limited (NHIDCL, for short) by excluding the administrative role of the State
PWD (NH).
9) The NHIDCL is a wholly owned Government of India company
incorporated under the provisions of the Companies Act, 2013 and works
under the administrative control of the Ministry of Road, Transport and
Highways, Government of India.
10) Many portions of NH-208 and NH 108B, with which we are
concerned in this PIL, run alongside the International Border of India with
Bangladesh. It is not disputed that there is no train facility in this region
adjoining the International border with the country of Bangladesh. There is a
portion of terrain also having small hills and forests. There are also tribal
habitations in this area.
The events after registering of the PIL:
11) On 7.7.2026, NHIDCL was suo motu impleaded in this PIL as 8
th
respondent and its counsel Mr. Rajib Saha accepted notice.
12) The learned Advocate General also accepted notice for
respondents No.3 to 7 and the Deputy S.G.I. accepted notice for respondent
No.1.
Page 5 of 47
TRHC010012332026
13) On that day, the Secretary, District Legal Services Authority,
Khowai District was also directed to inspect the road stretch of the NH which
is the subject matter of the PIL and file a report by the next date of hearing.
14) The matter was directed to be listed on 28.07.2026.
15) On 27.07.2026 such report was filed by the District Legal
Services Authority, Khowai District, Tripura. This will be adverted to later in
this order.
16) By 3.8.2026, the NHIDCL and the State Government has filed
counter affidavits with exhibits.
17) We have heard all the counsel for the respective parties and
perused the pleadings and documents filed.
The legal position is that the NHIDCL ,as delegate of the Central Government, owes a
duty of care to users of the National Highways:
18) Section 4 and Section 5 of the National Highways Ac,1956 state
as under:
“4. National highways to vest in the Union.—All national highways shall
vest in the Union, and for the purposes of this Act “highways” include—
(i) all lands appurtenant thereto, whether demarcated or not;
(ii) all bridges, culverts, tunnels, causeways, carriageways and other
structures constructed on or across such highways; and
(iii) all fences, trees, posts and boundary, furlong and milestones of such
highways or any land appurtenant to such highways.
5. Responsibility for development and maintenance of national
highways.—It shall be the responsibility of the Central Government to
develop and maintain in proper repair all national highways; but the
Central Government may, by notification in the Official Gazette, direct that
any function in relation to the development or maintenance of any national
highway shall, subject to such conditions, if any, as may be specified in the
notification, also be exercisable by the Government of the State within
which the national highway is situated or by any officer or authority
subordinate to the Central Government or to the State Government.”
Page 6 of 47
TRHC010012332026
19) It is not in dispute that in exercise of powers conferred by Section
5 of the National Highways Act, 1956, vide Notification dt.18.07.2025 issued
by the Ministry of Road, Transport and Highways, Government of India, it
formally directed NHIDCL to independently exercise all statutory functions
relating to the development, execution, and routine maintenance of all
National Highways within the State of Tripura totally excluding the role of the
State Government of Tripura with regard to the same.
20) This delegation of duty by the Central Government to NHIDCL
under the above notification makes NHIDCL owe a duty of care to users of
the National Highways in the State of Tripura as it is made responsible for the
maintenance of highways. This duty of care continues with NHIDCL even if
its activities have been contracted out to Engineering Procurement
Construction (EPC) contractors for laying the highways and maintaining them.
21) It is settled law that a statutory corporation or local authority can
be held liable in tort for injury occasioned on account of omission to oversee,
or for defective supervision of its activities contracted out to another agency.
(See MCD v.Sushila Devi
1
,Vadodra Municipal Corporation v. Purushottam
V.Murjani
2
)
22) In NHAI v. Aam Aadmi Lokmanch
3
, it was held:
“ 66. The terms of the agreement which NHAI entered into with the
concessionaire clearly contemplated the safety of highway users (Clause
18.1.1) and an elaborate highway monitoring mechanism (Clause 19.1). The
agreement also required any unusual occurrences to be reported; an
independent engineer was required to, and did inspect the highway. The
reports of the inspecting engineer reveal that the deficiencies by way of
narrowing of water channels, and the unusual collection of debris, were
1
(1999) 4 SCC 317
2
(2014) 16 SCC 14
3
(2021) 11 SCC 566, at page 623
Page 7 of 47
TRHC010012332026
noted. Even before the incident, NHAI was alive to this; it had separately
written to Rathod, and later to the local administration about it through its
letter dated 15-4-2011. That letter is revealing; it inter alia, states that:
“During pre-monsoon rains all the excavated muck has been carried to NH-
4 along with rain water and block Satara bound traffic lane for quite some
time. The problem will be severe during heavy rains of July and August.
As such safety of highway and tunnel is completely at stake due to
indiscriminate cutting of hills on upper side of tunnel and both the ends.”
67. Having regard to the duty imposed on NHAI by virtue of Sections 4
and 5 of the Highways Act, read with Section 16 of the NHAI Act, there can
be no manner of doubt that NHAI was responsible for the maintenance of
the highway, including the stretch upon which the accident occurred. The
report of the Sub-Divisional Officer clearly shows that inspection reports
were furnished to NHAI shortly before the incident, highlighting the
deficiencies; also, NHAI’s correspondence with Rathod, and the local
administration, reveal that it was aware of the danger and likelihood of risk
to human life, and the foreseeability of the event that actually occurred
later. Further, letters addressed by the local administration and NHAI to
Rathod similarly show that it was incumbent upon him to take remedial
action. The failure of NHAI to ensure remedial action, and likewise the
failure by Rathod to take measures to prevent the accident, prima facie,
disclose their liability.”
23) The ratio of the above decisions clearly makes NHIDCL, whose
activities are similar to the NHAI, and it‟s EPC contractors owe a duty of care
to the users of both Highways.
The stand of the Union of India ( respondent no.1):
24) No pleading has been filed by the Union of India though the
Dy.Solicitor general took notice on it‟s behalf on 7.7.2026.
The stand of the National Highways Authority of India(NHAI) ( respondent no.2):
25) A brief counter affidavit has been filed by the NHAI stating that
it does not possess, manage, execute or maintain any project within the
territorial jurisdiction of the State of Tripura.
Page 8 of 47
TRHC010012332026
The stand of the State of Tripura ( respondent no.3):
26) In its brief counter affidavit, the State Government states that
NH-208 and NH-108B are under the management of NHIDCL exclusively
and it has nothing to do with the management thereof.
27) It stated that NH-108B stretching from Khowai to Agartala was
developed by issuing phased work orders commencing on 15.07.2020 and the
construction work was subsequently completed on 24.04.2023 and 30.05.2024
in two packages.
28) It is also stated that construction of NH-208 stretching from
Kailashahar-Khowai was done through the NHIDCL by work orders issued
commencing on 17.05.2020 and continuing up to 31.03.2026.
29) According to the State Government, both these highways are
under the 5(five) year Defect Liability Period rendering the executing central
agency/concessionaire legally liable for any structural maintenance.
30) It is contended that despite the formal completion of the physical
road construction, extensive rainfall and extreme precipitation recorded during
the 2025 monsoon season resulted in visible longitudinal cracking, structural
fractures, and severe pavement settlement across multiple stretches.
31) It is stated that the State PWD brought these defects in both NH-
208 and NH-108B to the notice of NHIDCL for immediate restoration and to
restore seamless traffic ability, and that the State Government had also
expressed strong displeasure regarding the quality of execution and instructed
NHIDCL officials to rectify all underlying engineering defects immediately. It
is, however, stated that the pace of rectification was highly unsatisfactory and
resulted in prolonged commuter distress.
Page 9 of 47
TRHC010012332026
32) Reference is made to the letter dt.10.05.2025 written by the
Hon‟ble Chief Minister to the Hon‟ble Union Minister of the Road, Transport
and Highways highlighting the critical field observations including
widespread alligator cracking and pavement upheaval extending down to the
sub-grade layer at multiple locations, demanding an immediate investigation
into the design defects and subsurface development.
33) It is stated that on 22.07.2025, the Union Ministry of Road,
Transport and Highways had written a letter to the State Government about
the inspection of the Central Road Research Institute (for short „CRRI‟) and a
team of experts from the said Institute visited the affected sites from
23.07.2025 to 27.07.2025.
34) It is stated that recently on 01.07.2026 the Hon‟ble Chief
Minister of Tripura met the Hon‟ble Union Minister for Road, Transport and
Highways personally and also informed him about the dilapidated condition of
both these highways and there was an assurance given by the Hon‟ble Union
Minister that NHIDCL will execute permanent, long-term corrective measures
without further delay.
35) We have noted the stand of the State of Tripura.
36) While we appreciate the candour of the State of Tripura in
blaming the Union of India and the NHIDCL in it‟s counter affidavit for the
poor condition and safety on both Highway No. 108B and Highway No. 208,
we wish it would have done more since residents of the State are put at risk
and inconvenienced by the current state of the said Highways. Merely meeting
the Union minister or writing letters to the said Minister would hardly result in
Page 10 of 47
TRHC010012332026
any improvement unless something more was done by it against the officials
of the NHIDCL and the EPC contractors engaged by it.
37) If the deterioration in the condition of both Highways had been
noticed during the monsoon period of 2025 which ended on 30.9.2025, and
the NHIDCL and it‟s EPC contractors were hardly doing anything thereafter
for repairing the National highways, the State Government could have asked
the Central Government to re-transfer the administrative control of these
highways to it‟s own administrative control i.e to it‟s PWD (R&B) department
for carrying out maintenance works and got them repaired before April,2026
when the next monsoon season started again. Between 1.10.2025 to 30.4.2026,
there was ample time to do repairs of these Highways. Yet it did nothing.
38) To a query by the Court whether now at least the state of Tripura
is willing to do it, the Advocate General indicated that the unwillingness of the
State Government for this course of action.
39) It could have also explored the possibility of initiating, for the
benefit of it‟s citizens, legal action against both NHIDCL or it‟s contractors
i.e., criminal cases for cheating, and for negligence in maintenance of the
highways as huge sums of more than Rs. 5 crore per km was admittedly spent
for the laying of these Highways.
40) It is baffling that it chose not to do anything other than what is
stated in the counter affidavit.
The report .dt.27.7.2026 of DLSA, Khowai:
41) We shall now advert to the report of the Secretary, District Legal
Services Authority, Khowai District, Tripura, who had made the inspection
pursuant to the direction given by this Court on 07.07.2026.
Page 11 of 47
TRHC010012332026
42) Though the report is a very detailed report covering several small
stretches of these Highways (some details are in Annexure-A to this
judgment), we shall refer to only certain portions of this report, which
indicate the terrible condition of various stretches of the National Highways
208, and 108B, as on the date of inspection, i.e. on 17.07.2026, 18.07.2026
and 20.07.2026.
43) The report covers
(i) 30.32 km covering Mahadebtila to Manikbhandar in
Kamalpur via Jambura, Cherma, Bachhaibari, Behalabari and
Srirampur [NH 208];
(ii) 14 km stretch from Mahadevtila to Mohanbari, Khowai
Via Dhalabil, Padmabil, Baijalbari & Belfang (NH 108 B,
Package 3); and
(iii) 12 km stretch from Mohanbari, Khowai to Mohanpur Via
Subalsing & Hezamara (NH – 108 B, Package – 2).
44) In this report , the ground situation at different chainages on these
portions of the Highways is mentioned typically having all or many of the
following attributes :
“No proper drainage system; pave distress ; numerous Potholes;
Pave shoulder blocked by Silt, vegetation ,debris; edge not
visible; road damage; Shovel/rutting; road depression; water
logging everywhere; RCC drain hole blocked with mud,
vegetation ; Earthen drain damage & blocked, Median damage;
Crash barrier/protection/ Retaining wall is recommended as per
MoRTH/ IRC ; Poor maintenance work done resulting damage
…”
Page 12 of 47
TRHC010012332026
45) The detailed observations of various stretches are annexed to this
order as Annexure. This factual report belies the plea of attempted actions
pleaded by the NHIDCL to repair and maintain the said Highways in a safe
and motorable condition.
The stand of the NHIDCL:
Re: Mohanpur-Hezamara-Subalsingh of NH 108B:
46) In it‟s counter affidavit it is stated by NHIDCL that the
construction and development of NH 108B was undertaken in three separate
Engineering Procurement Construction (EPC) contract packages extending
from Lembuchhera to Khowai, each package being executed independently
under separate contractual arrangements and project management mechanism.
47) According to the NHIDCL, the newspaper reports primarily focus
on the Mohanpur-Hezamara-Subalsingh of NH 108B.
48) In this regard, the NHIDCL contends that execution of the said
work on this bit of said NH commenced on 01.03.2024, and as per the terms
of the contract, the scheduled date for completion of the project was
31.08.2025. It is stated that the work is being carried out in a phased and
systematic manner under the supervision of the competent authorities in
accordance with the applicable contractual specifications and engineering
standards.
49) It is, however, pointed out that the progress of the said project
was adversely affected due to failure of the EPC Contractor to mobilize
adequate manpower, machinery and construction materials at the project site.
It is stated that the NHIDCL‟s Engineer as well as the Project Monitoring Unit
of NHIDCL, on several occasions, issued letters, notices and directions
Page 13 of 47
TRHC010012332026
pointing out the slow progress of the work, inadequate deployment of
resources and the Contractor‟s failure to achieve the contractual milestones. It
is contended that despite repeated communications and continuous monitoring
by the NHIDCL, the EPC Contractor failed to attain the requisite physical
progress in accordance with the timelines prescribed under the contract
agreement, thereby resulting in delay in the execution of the project.
50) It is stated that though the original stipulated date of completion
of this section of the NH 108B was 31.08.2025, first extension of time was
granted on 13.02.2026 with the revised completion date for 04.09.2026,
subject to the imposition of liquidated damages as per the terms of the contract
agreement.
51) It is stated that notwithstanding the grant of extension of time and
continuous monitoring and supervision by the NHIDCL, the progress of the
project could not be accelerated due to the EPC Contractor‟s failure to
adequately mobilize the requisite manpower, machinery and construction
materials at the project site.
52) It is also stated that to ensure the safety and convenience of the
road users and to safeguard the project highway, NHIDCL proactively
initiated contractual measures by awarding the first “Risk and Cost Work” in
September, 2025 for maintenance of the existing road through a third party
agency after following the prescribed tendering procedure and contractual
requirements for Rs.48,25,350.80/-.
53) It is stated that only a part of the proposed Risk and Cost Work
was executed through the third party agency as of now, though almost one
year has elapsed since the said work was entrusted to the third party agency.
Page 14 of 47
TRHC010012332026
54) Thereafter, NHIDCL appears to have initiated a second proposal
in March, 2026 for execution of the emergent works at the Risk and Cost of
the EPC Contractor and tenders had also been invited for undertaking the
requisite maintenance works, but it is stated that the tender process was
extended due to certain reasons, such as the monsoon conditions etc., and it is
stated that the EPC Contractor had achieved only 51.14% physical progress of
the project and has failed to attain the revised Project Milestone-III within the
stipulated date, i.e. 19.01.2026, thereby committing a material default under
the contract agreement.
55) It is admitted that currently the principal difficulty affecting the
project arises from the formation of extensive mud stretches caused by
medium to heavy rainfall. It is admitted that there are major and frequent
disruptions to vehicular movement at different locations, but it is stated that
the NHIDCL is intervening and taking necessary measures to undertake
immediate restoration works.
56) It is also stated that a Suspension Notice was issued to the EPC
Contractor on 23.07.2026.
57) NHIDCL states that it had commenced critical maintenance and
restoration work on a war-footing basis at the risk and cost of the EPC
Contractor on temporary basis. It is stated that adequate machinery, equipment
and manpower have been deployed at all critical locations of the project
stretch to undertake immediate maintenance and restoration works. It is
contended that the NHIDCL was acting with due diligence, promptness and in
strict conformity with the provisions of the EPC Contract Agreement at every
stage of the project.
Page 15 of 47
TRHC010012332026
58) There is a reference to the engagement of the services of the
CSIR-Central Road Research Institute (CRRI) for conducting its investigation
on 22.07.2025 and inspection by a team of experts from the said Institute of
the affected sites from 23.07.2025 to 27.07.2025.
59) According to NHIDCL, though the inspection was done more
than a year back, the report of the inspection was submitted by the CSIR-
CRRI institute to the respondent No.8 only on 23.6.2026.
60) There is also reference in the counter affidavit to the request of
the NHIDCL for technical assistance from the National Institute of
Technology, Agartala for another independent technical assessment of the
project, and it is stated that the NIT, Agartala had given its technical report on
28.04.2026.
61) It is stated that maximum major damages to the road have already
been attended to by providing Granular Sub-Base material and other suitable
materials and that at present, traffic is moving and required restoration and
safety measures would continue to be undertaken during the suspension period
to ensure safe movement of traffic.
Re: Subalsingh-Khowai (near Mahadevtilla) Section on NH-108B, Agartala-Khowai
Package-III:
62) It is stated that the development and upgradation work relating to
this stretch was successfully completed on 30.05.2024 and thereafter, the
project entered the Defect Liability Period of five years.
63) It is stated that the defects noticed on the project Highway were
continuously communicated by the NHIDCL Engineers and the Project
Monitoring Unit to the EPC Contractor, but the Contractor had persistently
failed to undertake the required remedial measures in an effective and timely
Page 16 of 47
TRHC010012332026
manner. It is stated that they had also issued a Cure Period Notice on
23.08.2025 and upon expiry of the stipulated cure period, and in the absence
of satisfactory compliance by the contractor, they had also issued an intention
to terminate notice on 03.11.2025 in accordance with the contract.
64) It is stated that even prior to the issuance of this notice, NHIDCL
had issued a Risk and Cost Work value at Rs.2,19,85,380/- on 13.10.2025 to a
third party agency.
65) But the work could not be commenced due to contractual
complications arising from the failure of the third party agency to comply with
the stipulated contractual requirements, thereby preventing execution of the
proposed maintenance works through the said agency.
66) It is stated that after continuous directions of the NHIDCL, the
EPC Contractor commenced maintenance and restoration works, resulting in
substantial improvement in the condition of the project road up to March,
2026. Therefore, it is stated that NHIDCL did not proceed further with the
proposed termination of the contract and instead continued to monitor the
Contractor‟s performance with a view to ensuring compliance with its
contractual obligations.
67) However, it is stated that after the onset of the monsoon season in
April, 2026, this stretch of the project road once again exhibited signs of
distress and deterioration at various locations, and again communications were
issued to the EPC Contractor to undertake immediate maintenance and
rectification works in accordance with its contractual obligations.
Page 17 of 47
TRHC010012332026
68) It is stated that notwithstanding the same, the EPC Contractor
failed to undertake the required maintenance and rectification works to the
extent and standard envisaged under the contract agreement.
69) So, NHIDCL issued a fresh Cure Period Notice on
04.07.2026/10.07.2026. It is stated that currently rectification works covering
approximately 3.985 Kms were being undertaken.
70) Reference is again made to the CSIR-CRRI report dt.23.06.2026
and it is stated that it contains findings and recommendations regarding the
causes of the pavement failure and the remedial measures to be adopted. It is
also stated that certain technical aspects and supplementary inputs from the
said Institute are still awaited and will be placed on record later.
71) It is contended that the NHIDCL had informed the EPC
Contractor on 29.07.2026 that all major damages existing on the project road
as on 28.07.2026 would be rectified by using suitable materials so as to restore
and maintain the highway in a motorable and traffic-worthy condition on or
before 15.09.2026 and that this would continue up to 30.10.2026.
Re: Khowai (Mahadevtilla)-Srirampur-Manikbhandar-Bamanchara of NH-208:
72) NHIDCL then dealt with the above stretch of NH-208.
73) It is stated that this was undertaken in 10(ten) separate EPC
contract packages and that the newspaper articles primarily focused on the
completed work on the stretch of Khowai (Mahadevtilla)-Srirampur-
Manikbhandar-Bamanchara of NH-208 and that this stretch is a continuation
of NH-108B referred to earlier.
74) It is stated that the development and upgradation work relating to
this stretch of NH-208 (Kailashahar-Khowai Package-V) was completed on
Page 18 of 47
TRHC010012332026
17.04.2023; that there was unprecedented and exceptionally heavy rainfall in
August, 2024, and then major defects, including alligator cracking, rutting and
complete pavement distress occurred on various stretches of the project road.
75) It is stated that damages were noticed over an aggregate length of
approximately 11 kms between Khowai (near Mahadevtilla) and Paschim
Bachaibari, out of the total extent length of 25.600 kms., with approximately
3.300 kms comprising severely affected stretches requiring extensive
restoration.
76) It is stated that these were communicated to the contractor, but he
did not undertake the required restoration work within the stipulated time and
did not discharge its maintenance obligations under the contract. It is stated
that a Cure Period Notice was issued on 13.09.2025, and that between
December, 2025 to March, 2026 substantial improvement was achieved in the
road condition.
77) It is, however, stated that again in the rainy season in April, 2026,
several stretches of the project road once again exhibited signs of distress and
deterioration. It is alleged that the EPC Contractor did not take timely
measures or adequate measures to redress the recurring defects and that the
maintenance works carried out by the contractor fell short of the standards and
obligations prescribed under the EPC contract agreement.
78) It is stated that Cure Period Notice was issued on 04.07.2026/
10.07.2026.
79) Reference is again made to the CSIR-CRRI technical reports
dt.02.09.2025, 09.03.2026.
Page 19 of 47
TRHC010012332026
80) It is contended that though the NHIDCL was doing its duty to
ensure timely rectification and maintenance of the project road, the
deterioration was attributable to the EPC Contractor‟s persistent failure to
discharge its contractual obligations in the required manner, coupled with
technical factors identified during investigation.
81) It is assured that on or before 15.08.2026 all major damages
existing on the project road would be rectified by using suitable materials so
as to restore and maintain the highway in a motorable and traffic-worthy
condition and it would continue to take such measures up to 15.10.2026.
Re: Srirampur-Manikbhandar-Bamanchara Section of NH-208 (Kailashahar-Khowai
Package-IV):
82) Then the NHIDCL deals with the Srirampur-Manikbhandar-
Bamanchara Section of NH-208 (Kailashahar-Khowai Package-IV), which
attained physical completion on 21.11.2024.
83) But the story is no different, and is practically a replica of what
occurred with regard to the other stretches of the NH-108B and NH-208
mentioned above.
84) It is stated ultimately by the NHIDCL that it would place on
record periodic weekly progress reports indicating the prevailing condition of
the project road, i.e. NH-208 and NH-108B, mentioning the maintenance and
rectification works carried out, deployment of manpower and machinery and
the progress achieved in restoring and maintaining the highway in a motorable
and traffic-worthy condition.
Consideration of the pleas of NHIDCL:
85) At the outset we may point out that the counsel for the NHIDCL,
to a query from the Court, stated that though the EPC contractors engaged by
Page 20 of 47
TRHC010012332026
the NHIDCL for laying the above National Highways, were receiving more
than Rs.5 crore per Km.
86) From the plea taken by NHIDCL, Mohanpur-Hezamara-
Subalsingh of NH 108B contract commenced on 01.03.2024, and as per the
terms of the contract, the scheduled date for completion of the project was
31.08.2025. Risk and Cost work notice was given in September,2025 , Cure
period notice was given on 10.1.2026 (4 1/2 months after the stipulated date
of completion) and extension of work were admittedly granted on 13.2.2026
and the time extended to 4.9.2026.
87) Thereafter, NHIDCL appears to have initiated a second proposal
in March, 2026 for execution of the emergent works at the Risk and Cost of
the EPC Contractor and tenders had also been invited for undertaking the
requisite maintenance works, but it is stated that the tender process was
extended due to certain reasons, such as the monsoon conditions etc., and it is
stated that the EPC Contractor had achieved only 51.14% physical progress of
the project and has failed to attain the revised Project Milestone-III within the
stipulated date, i.e. 19.01.2026, thereby committing a material default under
the contract agreement.
88) If the work which was to be completed by 31.8.2025, is not
completed even one year later, and only 51% of work is done, it raises grave
doubts as to whether proper care was taken by NHIDCL in the selection of the
EPC contractor/s for execution of this work considering the high cost of Rs. 5
Crore per Km.
89) There is also a distinct possibility of officials of NHIDCL
colluding with the EPC contractor/s as it appears that the NHIDCL shown a
Page 21 of 47
TRHC010012332026
lot of leniency towards the EPC contractor/s for whatever reason by giving
him repeated extensions.
90) Moreover admittedly the CSIR-Central Road Research Institute
(CRRI) had done the inspection of the damaged stretches of road from
23.7.2025 to 27.7.2025. It is incomprehensible to us that the said Institute
delayed giving it‟s report till 23.6.2026, (by almost a year). No explanation is
offered by the Union of India (respondent no.1) for this inordinate delay in
giving of the report by it‟s Institute.
91) According to counsel for NHIDCL, it was waiting for this report
for guidance as to how repair work is to be done.
92) We are baffled as to why the NHIDCL was waiting for the
duration of time of almost one year for the said report, when it has competent
Engineering staff on it‟s rolls, who could have speeded up the repair work
using their expertise before the next monsoon season again commenced in
April, 2026.
93) Coming to the Subalsingh – Khowai ( Near Mahadevtila)
stretch of NH 108B, according to NHIDCL, this stretch was completed on
30.5.2024 and a completion certificate was issued on 25.11.2024 to the EPC
contractors. But immediately when the next monsoon season of 2025 started,
major defects were noticed i.e., alligator cracking, rutting and complete
pavement distress on various stretches of the highway were observed.
94) This suggests that work done during the actual execution of the
project by the EPC Contractor was probably of poor quality possibly because
of poor supervision of work by NHIDCL.
Page 22 of 47
TRHC010012332026
95) Again in monsoon season of April, 2026 the project road again
exhibited distress and deterioration at various locations. Again Cure Period
notice was given on 10.7.2026.
96) These events indicate that all is not above board with the EPC
contractors‟ selection by NHIDCL and possibly they did not have the requisite
expertise and experience for the work of laying of the National Highway
though they were receiving more than Rs.5 crore per Km.
97) The NHIDCL goes on to state that the EPC contractor had issued
a communication dt.29.7.2026 stating that all major damages existing on the
project road as on 28.7.2026 shall be rectified by using suitable materials so as
to restore and maintain the highway in motorable and traffic worthy condition.
It remains to be seen how far this directive works and whether the so called
repairs will survive till the next monsoon season in April,2027.
98) Coming to the Khowai (near Mahadevtila) – Srirampur
section of NH 208 ( Kailashshahar to Khowai Package –V) ( pg.61), the
development and upgradation work relating to this stretch of NH-208 was
completed on 17.04.2023. According to NHIDCL, there was unprecedented
and exceptionally heavy rainfall in August, 2024, and then major defects,
including alligator cracking, rutting and complete pavement distress occurred
on various stretches of the project road. There appears to have been
correspondence exchanged between the NHIDCL and the EPC contractor
during this period, but nothing is mentioned as to anything being done for
improving the road condition between September, 2024 till Septmeber,2025.
This silence is inexplicable.
Page 23 of 47
TRHC010012332026
99) It is stated that a Cure Period Notice was issued on 13.09.2025,
and that between December, 2025 to March, 2026 substantial improvement
was achieved in the road condition.
100) It is, however, stated that again in the rainy season in April, 2026,
several stretches of the project road once again exhibited signs of distress and
deterioration.
101) Thus every monsoon season since 2023 including the current year
monsoon, there have been recurring problems of a serious nature with this
highway stretch.
102) Next as regards the Srirampur-Manikbhandar-Bamanchara
Section of NH-208 (Kailashahar-Khowai Package-IV), it is stated that it
attained physical completion on 21.11.2024. But the story is no different, and
is practically a replica of what occurred with regard to the other stretches of
the NH-108B and NH-208 mentioned above.
103) We may point out that according to it‟s official web site, as the
executing arm of the Government of India‟s vision to realize the “Act East
Policy,” NHIDCL is supposed to play a pivotal role as the nodal agency in the
North Eastern region. It is supposed to be actively engaged in providing
seamless regional integration, enhancing border area connectivity and paving
the way for the development of border roads, economic corridors and feeder
routes for inland waterways under the ambitious Bharatmala Pariyojana
(BMP).
104) The enhanced connectivity envisaged through these efforts is
supposed to strengthen cross-border trade and commerce, fortify national
security and lays the foundation for a more economically integrated South and
Page 24 of 47
TRHC010012332026
Southeast Asia. More importantly, it is supposed to bring inclusive
development to remote and underdeveloped regions, knitting them into the
national fabric with renewed vigour and opportunity.
105) The stand of the State Government and the report of the DLSA,
Khowai show that the NHIDCL is far from achieving any of these objectives
as can be seen of the pitiable state of the stretches of NH 108B and 208
discussed above.
106) This Court has a duty to make all the respondents accountable as
they have not properly discharged their responsibilities in discharge of their
functions in maintaining in a safe and motorable condition these National
Highways though considerable amount of the tax payers money was spent for
laying them from time to time.
107) In Vijay Rajmohan v. CBI
4
, the Supreme Court indicated the
importance of accountability of officers or authority in charge of institutions
as a very important aspect in administrative law. It stated that „accountability‟
governs the relationship between the “duty bearers” and the “right holders”. It
declared :
“34. Accountability in itself is an essential principle of
administrative law. Judicial review of administrative action will
be effective and meaningful by ensuring accountability of the
officer or authority in charge.
35. The principle of accountability is considered as a
cornerstone of the human rights framework. It is a crucial
feature that must govern the relationship between “duty bearers”
in authority and “right holders” affected by their actions.
Accountability of institutions is also one of the development goals
4
(2023) 1 SCC 329, at page 346
Page 25 of 47
TRHC010012332026
adopted by the United Nations in 201519 and is also recognised
as one of the six principles of the Citizens Charter Movement20.
36. Accountability has three essential constituent dimensions :
(i) responsibility, (ii) answerability, and (iii) enforceability.
Responsibility requires the identification of duties and
performance obligations of individuals in authority and with
authorities. Answerability requires reasoned decision-making so
that those affected by their decisions, including the public, are
aware of the same. Enforceability requires appropriate
corrective and remedial action against lack of responsibility and
accountability to be taken. Accountability has a corrective
function, making it possible to address individual or collective
grievances. It enables action against officials or institutions for
dereliction of duty. It also has a preventive function that helps to
identify the procedure or policy which has become non-
functional and to improve upon it.” (emphasis supplied)
108) This principle was reiterated in Yash Developers v. Harihar
Krup Coop.Society.
5
The Court emphasized:
“59. The Executive branch has a constitutional duty to ensure
that the purpose and object of a statute is accomplished while
implementing it. It has the additional duty to closely monitor the
working of a statute and must have a continuous and a real time
assessment of the impact that the statute is having. As stated
above, reviewing and assessing the implementation of a statute is
an integral part of Rule of Law. The purpose of such review is to
ensure that a law is working out in practice as it was intended. If
not, to understand the reason and address it quickly. It is in this
perspective that this Court has, in a number of cases, directed the
Executive to carry a performance/assessment audit of a statute or
has suggested amendments to the provisions of a particular
enactment so as to remove perceived infirmities in its working.
5
(2024) 9 SCC 606
Page 26 of 47
TRHC010012332026
60. Constitutional courts are fully justified in giving such
directions as they are in a unique position of perceiving the
working of a statute while exercising judicial review, during
which they could identify the fault-lines in the implementation of
a statute. This extraordinary capacity to assess the working of a
statute is available to the judicial institution because of its
unique position where : (i) disputes, based on the statutory
provisions unfold before it, (ii) claims of rights or allegations of
dereliction of duties are raised with varied, and sometimes,
contradictory interpretations of the same text of the statute, (iii)
submissions of lawyers opens up a debate and as officers of the
Court experienced lawyers would lay bare the fault-lines in the
statutory scheme, (iv) many a times court silently witnesses the
play of statutory power relegating the deserving to the backseat,
and the undeserving taking away all the benefits.
61. Laws that are made by Parliament or the Legislative
Assemblies create rights, entitlements, duties or liabilities.
Application of such empowerments or disabilities gives rise to
competing claims or conflicting interests. For resolution of these
disputes, constitutional courts provide public law remedies13
where claims and contestations are decided by the High Courts
on a case-by-case basis. Judicial review is generally episodic,
and is intended to resolve the lis on a case-to-case basis. Though
cases are decided on their own merit and the lis disposed of,
what is left behind is the institutional memory of the Court about
the working of the statute and its interpretation preserved as
precedents. Over a period of time, a critical mass of adjudicatory
determinations on the working of the statute is built. This critical
mass, coupled with the experiences gained by the Judges and the
Court on the working of the statute, is of immense value for
auditing the working of the legislation. It enables the court to
assess whether the purpose and object of the Act is being
achieved or not.”
Page 27 of 47
TRHC010012332026
109) It is high time the Union of India starts a systemic audit of the
working of the NHAI and NHIDCL as newspaper reports are full nowadays of
National Highways built at a huge cost disintegrating sometimes even before
their inauguration or shortly thereafter and even before the first monsoon
season or immediately thereafter.
110) Coming to the instant PIL, we feel sorry for the citizens of the
State whose lives and livelihoods are put at risk by the NHIDCL and it‟s EPC
Contractors and the inability of the State Government in improving things
much.
111) As the Highway stretches dealt with above are in a poor
motorable condition putting lives of travelers thereon to risk and the NHIDCL
has failed to discharge the duty of care expected of it, and a large amount of
tax payer‟s money has been utilized to pay the EPC Contractors by the
NHIDCL, we direct that:
(a) The NHIDCL shall file bi-weekly progress reports starting from
the next date of hearing stating about the progress of the repair and
maintenance work by the respective EPC agencies for (i) Mohanpur-
Hezamara-Subalsingh of NH 108B (ii) Subalsingh – Khowai (Near
Mahadevtila) stretch of NH 108B (iii) Khowai (near Mahadevtila) –
Srirampur section of NH 208 (Kailashshahar to Khowai Package–V)
and (iv) Srirampur-Manikbhandar-Bamanchara Section of NH-208
(Kailashahar-Khowai Package-IV);
(b) The State Government shall explore the possibility of taking
civil/criminal proceedings against the NHIDCL and it‟s EPC contractors
Page 28 of 47
TRHC010012332026
for putting it‟s residents to huge risk without providing safe and
motorable passage on these Highways;
(c) On completion of the repairs , there shall be an audit of the
condition of these stretches of roads by the Engineering staff of Border
Roads Organisation and the said organization shall submit the audit
report to this Court in a sealed cover by 30 January 2027;
(d) The NHIDCL and it‟s contractors shall cooperate with the said
audit in all respects;
(e) In view of the facts and circumstances as evidenced by the
material record in this case, the Union of India (respondent no.1) shall
cause an inquiry to ascertain :
(i) whether there was any corruption in the selection of
contractors for laying of these Highways by NHIDCL?
(ii) whether there is collusion between the NHIDCL officials
and the EPC contractors because of which the EPC contractors
had used substandard materials causing the road condition to
deteriorate every year?
It shall file a report in this Court on these aspects in 3 months i.e.,
by 1.12.2026.
If it finds evidence of impropriety/corruption as mentioned
above, it shall initiate appropriate civil/criminal action against the respective
NHIDCL‟s officers and EPC Contractors found responsible.
List on 22.9.2026.
Page 29 of 47
TRHC010012332026
Copy of this order be also supplied to the Director General of
Border Roads Organization under the Ministry of Defence, Union of India,
Seema Sadak Bhavan, Ring Road, Delhi Cantonment, New Delhi -110010.
(BISWAJIT PALIT, J) (M.S. RAMACHANDRA RAO, CJ)
ANNEXURE
The observation of various stretches of the NH 2018 and NH
108B by the District Legal Services Authority, Khowai are:
Chainage-wise Details in respect of NH 208:
Mahadebtila to Manikbhandar in Kamalpur via Jambura, Cherma,
Bachhaibari, Behalabari and Srirampur [NH 208].
Day – 1 (17/07/2026)
Chainage Observation
Risk
level
Km 101 + 300
Road width 10.1m, midpoint 5.3, Pave shoulder:-
RHS- 1.5 & LHS 1.4, Silt, vegetation covered the
shoulder, cracks on pavement, no proper drainage
system, edge not visible
High
Km 101 + 275
Pave shoulder blocked by Silt, vegetation, cracks
on pavement, no proper drainage system, edge not
visible, Left side pave block by truck parked for
days not known
High
Km 101 + 150
Pave distress, pothole of approx Length 5.2m &
Breadth 3.2m, pave surface crack, median damage
and block by silt, vegetation, no longitudinal mark,
edge mark, pave shoulder block by silt, vegetation.
High
Km 101 + 135
Pave shoulder block by stock of bamboo, Heap of
hay, Median block by silt, vegetation, pave
distress, water logging in potholes, no proper
drainage, edge not visible, no safety rules .
High
Km 101 + 100
Pave shoulder blocked by Silt, vegetation, cracks
on pavement, no proper drainage system, edge not
visible, road distress.
High
Km 101+ 080
Median damage, mostly covered with vegetation,
shoulder edge not visible all blocked with heap of
hay not removed for many days.
High
Page 30 of 47
TRHC010012332026
Km 101+050
Road damage, drain hole in the pave median is
blocked by silt, vegetation, debris due to which
water logging & causing damage to road. Both
side pave is block with heap of hay, sand, silt,
vegetation, no edge is visible.
High
Km 101+020
Road damage, water logging everywhere, no
proper drainage system, pave edge not visible, all
blocked with vegetation. Camber percentage not
maintained as a result water logging. Mile stone,
KM stone not visible, all block with vegetation,
multiple potholes.
High
Km 100+960
Edge not visible, no longitudinal mark, Camber
percentage not maintained as a result water logged
in the potholes at different places.
High
Km 100+950
Cast in place culvert under construction, no safety
measures, area surrounded by paddy land, no
protection, pave block by mud & vegetation.
High
Km 100+920
to 70m
Road damage upto approx 70 m, poor repairing
done, pave Shoveling /rutting, Hectometer stone of
200 m absent, Km stone is not visible due to
vegetation, silt.
High
Km 100+850
No proper drainage system, water logged in the
median, pave distress
High
Km 100+830
No proper drainage system, water logged in the
median, pave distress , numerous Potholes.
High
Km 100+750
No edge, no camber percentage visible, road fully
damage, no drainage system. Width 18.4 including
shoulder & lay over, no mark for truck lay over,
crash barrier is required as the area is surrounded
by agricultural land.
High
Km 100+730
No proper drainage system, pave distress,
numerous Potholes, Pave shoulder blocked by
Silt, vegetation, edge not visible.
High
Km 100 + 620
No proper drainage system, pave distress,
numerous Potholes, Pave shoulder blocked by
Silt, vegetation, edge not visible.
High
Km 100+400
No proper drainage system, pave distress,
numerous Potholes, Pave shoulder blocked by
Silt, vegetation, edge not visible.
High
Km 100+250
to Km
100+150
No proper drainage system, pave distress ,
numerous Potholes, Pave shoulder blocked by
Silt, vegetation, heap of hay, edge not visible.
High
Km 99+980
No proper drainage system, pave distress ,
numerous Potholes, Pave shoulder blocked by
Silt, vegetation, edge not visible , Km stone not
visible, road damage approx length 5.2 m and
breadth 8 m.
High
Km 99+940 to No proper drainage system, pave distress , High
Page 31 of 47
TRHC010012332026
Km 99+900 numerous Potholes, Pave shoulder blocked by
Silt, vegetation, edge not visible , Km stone not
visible, road damage approx length 40 m damage.
After every meter road damage of approx 700
sq.m.
Km 99+890
No proper drainage system, pave distress ,
numerous Potholes, Pave shoulder blocked by
Silt, vegetation, edge not visible.
High
Km 99+700 to
Km 99+630
No proper drainage system, pave distress ,
numerous Potholes, Pave shoulder blocked by
Silt, vegetation, edge not visible , Shovel/rutting ,
road depression.
High
Km 99+630
Culvert one side road (left side) is totally damage
& carriage way is through one side (under
maintenance culvert), cast culvert
High
Km 99+490 to
Km 99+450
No proper drainage system, pave distress ,
numerous Potholes, Pave shoulder blocked by
Silt, vegetation, edge not visible , Shovel/rutting ,
road damage approx width 10 m and length 30m.
High
Km 99+420
No proper drainage system, pave distress ,
numerous Potholes, Pave shoulder blocked by
Silt, vegetation, edge not visible , Shovel/rutting ,
road damage length 10 m & Width 5 m
High
Km 99+300 to
Km 99+250
Junction road damage (Width 10 m & Length 50
m, deep 1 to 2 ft. depth), No proper drainage
system, pave distress , numerous Potholes, Pave
shoulder blocked by Silt, vegetation, edge not
visible .
High
Km 99+230
Potholes size Length 3m, Breath 5m, No proper
drainage system, pave distress , numerous
Potholes size Length 3m, Breath 5m, Pave
shoulder blocked by Silt, vegetation, edge not
visible , Shovel/rutting , road damage
High
Km 99+050 to
Km 99+020
Bridge 40 m Length & 3.5 m slab, edge of the
bridge not visible, filled with mud & vegetation.
Potholes, drain hole in the bridge block with mud
& vegetation, both side of drain hole in the bridge
after every 2 m is blocked with mud & vegetation
resulting road weak & damage.
High
Km 99+00
No proper drainage system, pave distress ,
numerous Potholes, Pave shoulder blocked by
Silt, vegetation, edge not visible , Shovel/rutting,
water logged in potholes.
High
Km 98+970
No proper drainage system, pave distress ,
numerous Potholes, Pave shoulder blocked by
Silt, vegetation, edge not visible .
High
Km 98+960
No proper drainage system, pave distress ,
numerous Potholes, Pave shoulder blocked by
Silt, vegetation, edge not visible .
High
Page 32 of 47
TRHC010012332026
Km 98+950 to
Km 98+900
No proper drainage system, pave distress ,
numerous Potholes, Pave shoulder blocked by
Silt, vegetation, edge not visible , road damage of
approx W-7.5 m & L- 50m
High
Km 98+900 to
Km 98+850
No proper drainage system, pave distress ,
numerous Potholes, Pave shoulder blocked by
Silt, vegetation, edge not visible.
High
Km 98+770
No proper drainage system, pave distress ,
numerous Potholes, Pave shoulder blocked by
Silt, vegetation, edge not visible , road damage of
approx W-10m, L-10 m & depth 2 ft.
High
Km 98+770 to
Km 98+720
No proper drainage system, pave distress ,
numerous Potholes of depth min 10mm, Pave
shoulder blocked by Silt, vegetation, edge not
visible.
High
Km 98+620 to
Km 98+430
No proper drainage system, pave distress ,
numerous Potholes, Pave shoulder blocked by
Silt, vegetation, edge not visible & road damage
(Width – 10 m & L - 190 m)
High
Km 98+420 to
Km 98+250
Side Drain damage (W- 10.2 m & L- 170 m), no
edge, earthen shoulder damage, numerous small
potholes (100 to 150 mm), shovel/rutting/road
damage (depth 1 ft to 1.5 ft), road side drain
protection wall damage & broken ,all gravels
broken down, drain blocked, Drain damage L-
25.3 m
High
Km 98+150
No proper drainage system, pave distress ,
numerous Potholes, Pave shoulder blocked by
Silt, vegetation, edge not visible,Holes in the
culvert block by silt, vegetation, debris, crash
barrier required.
High
Km 98+150 to
Km 97+920
No proper drainage system, pave distress ,
numerous Potholes, Pave shoulder blocked by
Silt, vegetation, edge not visible , Road damage
(W-10 m & L 230 m), potholes approx depth 1 ft
to 1.5 ft.
High
Km 97+920
No proper drainage system, pave distress ,
numerous Potholes, Pave shoulder blocked by
Silt, vegetation, edge not visible , Road damage
approx (W-5m, L – 25 m & depth -1.5 ft to 2 ft.)
High
Km 97+750
No proper drainage system, pave distress ,
numerous Potholes, Pave shoulder blocked by
Silt, vegetation, edge not visible , road damage
approx (W-5m & L- 10 m)
High
Km 97+720
No proper drainage system, pave distress ,
numerous Potholes, Pave shoulder blocked by
Silt, vegetation, edge not visible, road damage
approx (W-5m & L-5.5 m)
High
Page 33 of 47
TRHC010012332026
Km 97+680 to
Km 97+640
No proper drainage system, pave distress ,
numerous Potholes, Pave shoulder blocked by
Silt, vegetation, edge not visible, damage W- 16
m including footpath L-40 m, edge covered with
mud & vegetation, drain block by mud &
vegetation.
High
Km 97+620
No proper drainage system, pave distress ,
numerous Potholes, Pave shoulder blocked by
Silt, vegetation, edge not visible, road damage
approx (W-5m & L-7m)
High
Km 97+550
No proper drainage system, pave distress ,
numerous Potholes, Pave shoulder blocked by
Silt, vegetation, edge not visible, road damage
approx (W-5m & L-3m)
High
Km 97+500
RCC culvert crash barrier is recommended both
side as the height of both side from ground is
approx 4 to 5 m.
High
Km 97+520 to
Km 97+350
No proper drainage system, pave distress ,
numerous Potholes, Pave shoulder blocked by
Silt, vegetation, edge not visible, road damage
approx (W-10m & L-170 m) Depth 1-2 ft.
potholes depth approx 6 inch to 1 ft.
High
Km 97+200 to
Km 97+130
earthen drain block with sand, vegetation,pave
cracks, No proper drainage system, pave distress ,
numerous Potholes approx L 70m, Pave shoulder
blocked by Silt, vegetation, edge not visible.
High
Km 97+120 to
Km 96+980
No proper drainage system, pave distress ,
numerous Potholes, Pave shoulder blocked by
Silt, vegetation, edge not visible , road damage
(W-6/7 m), pave cracks, earthen drain blocked.
High
Km 96+960 to
Km 96 + 420
No proper drainage system, pave distress ,
numerous Potholes, Pave shoulder blocked by
Silt, vegetation, edge not visible, road damage
approx (W-10m & L-540 m, Shoveling/ rutting,
Earthen drain block (LHS side), requirement of
embankment protection on hill cut slope in both
side, RCC drain damage approx 61 m.
High
Km 96+415 to
Km 96+350
Potholes, drain of both side damage & blocked,
edge not visible, no longitudinal mark, km &
hectometer stone absent & not visible due to
block by vegetation, silt, debris, no safety
measures, pave crack, pave distress & damage
approx (W-10m & L-65m) .
High
Km 96 + 330
to Km 96+150
No proper drainage system, numerous potholes,
pave cracks, edge not visible, pave shoulder block
by silt , vegetation, debris, pave distress approx
W- 10 m & L- 180 m.
High
Page 34 of 47
TRHC010012332026
Km 96+150 to
Km 96 + 100
Median fully damage, pave crack, Km stone not
visible, hectometer stone not visible, No proper
drainage system, edge not visible, pave shoulder
block by silt , vegetation, debris.
High
Km 96+100 Major junction island badly damage. High
Km 96+00 to
Km 95+850
Pave cracks, road damage approx (W-10 m & L-
150m), edge not visible block by vegetation, no
drainage system, camber not maintained.
High
Km 95+800 to
Km 95+440
Earthen drain damage & blocked, Median damage,
Pave cracks, numerous potholes , road damage
approx L- 360 m.
High
Km 95+360 to
Km 95 + 270
No proper drainage system, numerous potholes,
pave cracks, edge not visible, pave shoulder block
by silt , vegetation, debris, road damage approx
(L- 90 m & W-10 m)
High
Km 95+240 to
Km 95+130
No proper drainage system, numerous potholes,
pave cracks, edge not visible, pave shoulder block
by silt , vegetation, debris, road damage approx
(L- 110 m & W-10 m)
High
Km 95+100 to
Km 94+800
Pave cracks, RCC drain hole blocked with mud
vegetation, edge not visible as block with mud
High
Km 94+790 Road damage approx (W-10 m & L-35 m) High
Km 94+750 to
Km 94 + 500
Numerous potholes, RCC drain hole blocked with
mud, vegetation, Road damage approx (W-10 m &
L-250 m), pave cracks.
High
Km 94+500 to
Km 94+300
Numerous potholes, RCC drain hole blocked with
mud, vegetation, Road damage approx (W-10 m &
L-200 m), pave cracks.
High
Km 94+270 Road damageapprox (W-10 m & L-30m),. High
Km 94+200 Test pit done
Km 94+160
Road damage approx (W-10 m & L-20 m), road
edge broken, drain blocked, pave cracks, barriers
recommended by the side of culvert, crash barrier
recommended on the RHS of the road as height
from ground level is more than 3 m,
High
Km 94+050 to
Km 93+850
Pave cracks, road damage approx (L-200 m x W-
10 m)
High
Km 93+830 to
Km 93 + 050
Drain damage (LHS), earthen drain damage,
numerous potholes, road damage approx (W-10 m
& L 220 m) Right side embankment protection
recommended (RHS), drain block by silt,
vegetation, debris, mud, Crash barrier
recommended in the culvert , drain hole block.
High
Day 2 (18/07/2026)
Km 101+ 050 Test pit done
Km 93+050 to
Km 92+760
Poor maintenance & repairing work done resulting
to damage, RCC drain hole block both side with
High
Page 35 of 47
TRHC010012332026
mud/vegetation, Road damage/distress .
Km 92+750
Road damage approx (W-10 m & L- 11 m), No
proper drainage system, numerous potholes, pave
cracks, edge not visible, pave shoulder block by
silt , vegetation, debris.
High
Km 92+680
Poor maintenance & repairing work done resulting
topave damage approx (W-7 m & L- 4 m), No
proper drainage system, numerous potholes, pave
cracks, edge not visible, pave shoulder block by
silt , vegetation, debris.
High
Km 92+630 to
Km 92+580
No proper drainage system, numerous potholes,
pave cracks, edge not visible, pave shoulder block
by silt , vegetation, debris .
High
Km 92+400
Road damage approx (W- 6m & L-20 m), No
proper drainage system, numerous potholes, pave
cracks, edge not visible, pave shoulder block by
silt , vegetation, debris.
High
Km 92+300
Road damage approx (W-8m & L-15m), No
proper drainage system, numerous potholes, pave
cracks, edge not visible, pave shoulder block by
silt , vegetation, debris.
High
Km 92+250 to
Km 91+950
Road damage , No proper drainage system,
numerous potholes, pave cracks, edge not visible,
pave shoulder block by silt , vegetation, debris.
High
Km 91+930
Culvert repair, earthen drain damage, settlement
damage (W-6 m & L-10 m).
High
Km 91+850 to
Km 91+750
Culvert protection recommended, Crash barrier
recommended, No proper drainage system,
numerous potholes, pave cracks, edge not visible,
pave shoulder block by silt , vegetation, debris,
Road damage.
High
Km 91+600
Road damage approx (W-10 m & L-8 to 10 m &
depth 1 to 1.5 ft.), No proper drainage system,
numerous potholes, pave cracks, edge not visible,
pave shoulder block by silt , vegetation, debris.
High
Km 91+530 to
Km 91+500
Road damage approx (depth approx 1 ft.), No
proper drainage system, numerous potholes, pave
cracks, edge not visible, pave shoulder block by
silt , vegetation, debris.
High
Km 91+370 to
Km 91+230
Road damage approx (W-10 m & depth 230 mm),
No proper drainage system, numerous potholes,
pave cracks, edge not visible, pave shoulder block
by silt , vegetation, debris.
High
Km 91+140 to
Km 90+930
No proper drainage system, numerous potholes,
pave cracks, edge not visible, pave shoulder block
by silt , vegetation, debris, Road damage ( W-
10m).
High
Page 36 of 47
TRHC010012332026
Km 90+800 to
Km 90+450
Road damage (W-10 m) continues……. High
Km 90+470
Road damage (W-10 m, L-11m & depth 300 mm),
No proper drainage system, numerous potholes,
pave cracks, edge not visible, pave shoulder block
by silt , vegetation, debris.
High
Km 90+450 to
Km 90+350
Road damage (W-10 m) continue……. High
Km 90+270 to
Km 90+00
Road damage (W-10 m) continue…….
High
Km 90+030
Drain damage (L-70 m), road damage 70 cm, No
proper drainage system, numerous potholes, pave
cracks, edge not visible, pave shoulder block by
silt , vegetation, debris.
High
Km 89+550
Land slide (LHS), Edge broken, Drain block,
Road damage ,Edge broken & damage (L- 200m),
Drain – blocked (200 m ),
hill cut slope height approx 20 to 25 m resulting
landslide and road damage, protection
recommended.
High
Km 89+550 to
Km 89+450
No proper drainage system, numerous potholes,
pave cracks, edge not visible, pave shoulder block
by silt , vegetation, debris, road damage.
High
Km 89+230 to
Km 89+020
No proper drainage system, numerous potholes,
pave cracks, edge not visible, pave shoulder block
by silt , vegetation, debris, pave damage.
High
Km 88+800 to
Km 88+700
Crash Barrier recommended (LHS), poor
maintenance & repairing, No proper drainage
system, numerous potholes, pave cracks, edge not
visible, pave shoulder block by silt , vegetation,
debris, pave damage.
High
Km 88+470
Road damage approx (L-3 m / B-3 m), No proper
drainage system, numerous potholes, pave cracks,
edge not visible, pave shoulder block by silt ,
vegetation, debris.
High
Km 88+400 to
Km 88+200
No proper drainage system, numerous potholes,
pave cracks, edge not visible, pave shoulder block
by silt , vegetation, debris.
High
Km 88+150
Road damage approx (W-5 m & L- 5 m), No
proper drainage system, numerous potholes, pave
cracks, edge not visible, pave shoulder block by
silt , vegetation, debris.
High
Km 87+970
Road damage, No proper drainage system,
numerous potholes, pave cracks, edge not visible,
pave shoulder block by silt , vegetation, debris.
High
Km 87+950
Road damage approx (W-10 m & L-8m), No
proper drainage system, numerous potholes, pave
High
Page 37 of 47
TRHC010012332026
cracks, edge not visible, pave shoulder block by
silt , vegetation, debris.
Km 87+850
Crash Barrier recommended RHS approx (L-150
m) , road damage approx (L-3 m & B-3m), No
proper drainage system, numerous potholes, pave
cracks, edge not visible, pave shoulder block by
silt , vegetation, debris.
High
Km 87+720 to
Km 87+680
Bridge inspection path block with
mud/silt/vegetation,
Potholes block with mud/silt/vegetation,
Poor maintenance,
Drain block.
High
Km 87+630 to
Km 87+580
Road damage,
Median damage, No proper drainage system,
numerous potholes, pave cracks, edge not visible,
pave shoulder block by silt , vegetation, debris.
High
Km 86+700 to
Km 86+550
Crash barrier recommended approx (L-100 m),
road damage, No proper drainage system,
numerous potholes, pave cracks, edge not visible,
pave shoulder block by silt , vegetation, debris.
High
Km 86+540
Road damage approx ( W-10 m, L-20 m & depth
300 mm to 450 mm), No proper drainage system,
numerous potholes, pave cracks, edge not visible,
pave shoulder block by silt , vegetation, debris.
High
Km 86+350
Road edge broken & damage, Drain blocked,
Drain damage (L- 80 m LHS& L-80 m RHS),No
proper drainage system, numerous potholes, pave
cracks, edge not visible, pave shoulder block by
silt , vegetation, debris.
High
Km 86+330
Drain broken & damage approx (L-15m),
Inspection path of bridge block by silt, mud,
vegetation, Poor maintenance, No proper drainage
system, numerous potholes, pave cracks, edge not
visible, pave shoulder block by silt , vegetation,
debris.
High
Km 86+250 to
Km 85+900
Crash Barrier required both side, Both side
surrounded by paddy filed, Bridge, No proper
drainage system, numerous potholes, pave cracks,
edge not visible, pave shoulder block by silt ,
vegetation, debris.
High
Km 85+880
Both side land slide, Both side protection
recommended as per MoRTH, IRC, Both side
drain blocked, Edge broken & damage, Pave
cracks, distress, damage, pave shoulder block by
silt/vegetation/debris.
High
Km 85+800 to Road damage, Drain blocked both side, Land slide High
Page 38 of 47
TRHC010012332026
Km 85+650 both side, Both side protection recommended as
per MoRTH, IRC, No proper drainage system,
numerous potholes, pave cracks, edge not visible,
pave shoulder block by silt , vegetation, debris.
Km 85+580 to
Km 85+400
Road damage approx (W-10m & L-30 m), Pave
Cracks, Drain block, Drain damage approx (L-40
m), Edge broken, Culvert protection required,
crash barrier is recommended due to water
bodysituated beside the road in the RHS.
High
Km 85+300 to
Km 85+050
Road damage , Pave Cracks, Drain block, Drain
damage , Edge broken, crash barrier/protection is
recommended as per MoRTH, IRC.
High
Km 84+750 to
Km 84+450
No proper drainage system, numerous potholes,
pave cracks, edge not visible, pave shoulder block
by silt , vegetation, debris, protection is
recommended as per MoRTH, IRC.
High
Km 83+450 to
Km 83+150
No proper drainage system, numerous potholes,
pave cracks, edge not visible, pave shoulder block
by silt , vegetation, debris, Culvert block by
vegetation, protection is recommended as per
MoRTH, IRC.
High
Km 82+500 to
Km 81+300
No proper drainage system & damage, numerous
potholes, pave cracks, edge not visible, pave
shoulder block by silt, vegetation, debris, Poor
maintenance, protection is recommended as per
MoRTH, IRC.
High
Km 81+300
Pave distress & damage , No proper drainage
system & damage, numerous potholes, pave
cracks, edge not visible, pave shoulder block by
silt, vegetation, debris, Crash barrier damage, Pave
Depression, Crash barrier is recommended both
side (Valley) as per MoRTH, IRC.
High
Km 81+250 to
Km 80+900
Cracks, Poor maintenance, Edge not visible, Crash
barrier/protection is recommended both side as per
MoRTH, IRC, numerous potholes, pave
depression.
High
Km 80+600 to
Km 80+200
No proper drainage system & block with silt,
vegetation, numerous potholes, pave cracks, edge
not visible, pave shoulder block by silt, vegetation,
debris , pave damage, Crash barrier/protection is
recommended.
High
Day 3 (20/07/2026)
Km 80+200 to
Km 78+350
Pave Cracks, Pave Edge block, Road damage,
Crash barrier/protection/retaining wall is
recommended (Valley) as per MoRTH/ IRC, Poor
maintenance work done resulting damage.
High
Page 39 of 47
TRHC010012332026
Km 79+250
Pave Cracks, Pave Edge block, Road damage,
Crash barrier/protection/ Retaining wall is
recommended (Valley) as per MoRTH/ IRC, Poor
maintenance work done resulting damage.
High
Km 78+650
Crash barrier/protection is recommended (Valley)
as per MoRTH/ IRC.
High
Km 78+325 Test pit done
Km 78+325 to
Km 77+100
Pave Cracks,Pave Edge block, Road damage,
Crash barrier/protection/retaining wall is
recommended (Valley) as per MoRTH/ IRC, Poor
maintenance work done resulting damage
High
Km 77+100
Road damage & broken, Embankment broken,
Base moving out.
High
Km 77+090 to
Km 75+700
Pave Cracks, Pave Edge block, Road damage,
Crash barrier/protection/ Retaining wall is
recommended as per MoRTH/ IRC.
High
Km 75+700 to
Km 74+900
Edge block, Bridge inspection path block, No
marks, pave cracks, road damage , no stone.
High
Km 74+900
No proper drainage system, numerous potholes,
pave cracks, edge not visible, pave shoulder block
by silt,vegetation, debris, pave
distress/depression/damage.
High
Km 74+890
No proper drainage system, numerous potholes,
pave cracks, edge not visible, pave shoulder block
by silt, vegetation, debris, pave
distress/depression/damage.
High
Km 74+890 to
Km 74+620
No proper drainage system, numerous potholes,
pave cracks, edge not visible, pave shoulder block
by silt, vegetation, debris, pave
distress/depression/damage, marks not visible.
High
Km 74+550
No proper drainage system, numerous potholes,
pave cracks, edge not visible, pave shoulder block
by silt, vegetation, debris, pave
distress/depression/damage approx (W-12.4m, L-
24 m, depth 9/18.4 inch).
High
Km 74+500 to
Km 74+470
Road damage approx (W-12 m & depth 1 ft. 1
inch, L-30m), RCC drain not visible, No proper
drainage system, numerous potholes, pave cracks,
edge not visible, pave shoulder block by silt,
vegetation, debris.
High
Km 74+280 to
Km 74+150
No proper drainage system, numerous potholes,
pave cracks, edge not visible, pave shoulder block
by silt, vegetation, debris, Crash barrier/protection/
Retaining wall is recommended as per MoRTH/
IRC.
High
Km 74+050 to
Km 73+600
No proper drainage system, numerous potholes,
pave cracks, edge not visible, pave shoulder block
by silt, vegetation, debris, RCC drain hole block,
High
Page 40 of 47
TRHC010012332026
Chainage-wise Details in respect of NH 108B:
Mahadevtila to Mohanbari, Khowai Via Dhalabil, Padmabil, Baijalbari &
Belfang (NH 108 B, Package 3)
Day -1 (18/07/2026)
Chainage Observation
Risk
Level
Km 45+300 No proper drainage system, numerous potholes, High
Pave damage/distress/depression,
Marks not visible.
Km 73+550 to
Km 73+300
No proper drainage system, numerous potholes,
pave cracks, edge not visible, pave shoulder block
by silt, vegetation, debris, Pave
damage/distress/depression,
Marks not visible.
High
Km 73+250 to
Km 73+00
No proper drainage system, numerous potholes,
pave cracks, edge not visible, pave shoulder block
by silt, vegetation, debris, Crash barrier/protection/
Retaining wall is recommended as per MoRTH/
IRC, pave damage/distress/depression.
High
Km 72+950 to
Km 72+600
No proper drainage system, numerous potholes,
pave cracks, edge not visible, pave shoulder block
by silt, vegetation, debris, Crash barrier/protection/
Retaining wall is recommended as per MoRTH/
IRC, pave damage/distress/depression, poor
maintenance resulting damage.
High
Km 72+600
No proper drainage system, numerous potholes,
pave cracks, edge not visible, pave shoulder block
by silt, vegetation, debris, Crash barrier/protection/
Retaining wall is recommended as per MoRTH/
IRC, pave damage/distress/depression approx (W-
11.4m, L- 50m).
High
Km 72+550 to
Km 71+120
No proper drainage system, numerous potholes,
pave cracks, edge not visible, pave shoulder block
by silt, vegetation, debris, road damage, multiple
cracks, RCC drain hole block with silt, vegetation,
debris, bridge inspection path block with debris
etc.
High
Km 71+120
Median damage approx L- 1.4 m, junction median
block by fruit seller, mud, vegetation, no proper
drainage system, numerous potholes, pave cracks,
edge not visible, pave shoulder block by silt,
vegetation, debris.
High
Km 71+068
(end point)
No proper drainage system, numerous potholes,
pave cracks, edge not visible, pave shoulder block
by silt, vegetation, debris, median damage.
High
Page 41 of 47
TRHC010012332026
Mahadevtila to Mohanbari, Khowai Via Dhalabil, Padmabil, Baijalbari &
Belfang (NH 108 B, Package 3)
pave cracks, edge not visible, pave shoulder block
by silt, vegetation, debris,
crackslongitudinal/tranverse, Road damage/distress.
Km 45+100
No proper drainage system, numerous potholes,
pave cracks, edge not visible, pave shoulder block
by silt, vegetation, debris, no marking/marking
faded, water logged in the potholes, no hectometre
stone, no safety measures, poor repair &
maintenance work done.
High
Km 44+990
No proper drainage system, numerous potholes,
pave cracks, edge not visible, pave shoulder block
by silt, vegetation, debris, edge disrupted, earthen
shoulder damage,
Road damage approx (L-5.7, B- 6m) cracks
High
Km 44+910
No proper drainage system, numerous potholes,
pave cracks, edge not visible, pave shoulder block
by silt, vegetation, debris, road damage approx (L-2
m & W-6 m) cracks
High
Km 44+800
No proper drainage system, numerous potholes,
pave cracks, edge not visible, pave shoulder block
by silt, vegetation, debris, road damage approx (L-
25m & W-12m)
High
Km 44+750
No proper drainage system, numerous potholes,
pave cracks, edge not visible, pave shoulder block
by silt, vegetation, debris, road damage approx (L-
20m & W-6m),Poor maintenance.
High
Km 44+720
No proper drainage system, numerous potholes,
pave cracks, edge not visible, pave shoulder block
by silt, vegetation, debris, road damage.
High
Km 44+550
Bridge inspection path of both side encroach by silt
vegetation & mud, crash barrier/protection required
to extended in both side of the bridge as the Height
is 4.5 m depth from ground level.
High
Km 44+500 to
Km 44+400
No proper drainage system, numerous potholes,
pave cracks, edge not visible, pave shoulder block
by silt, vegetation, debris, road damage.
High
Km 44+400
Cast in place culvert, Crash barrier required for
approx 35 to 40 m as height is approx 3 to 3.5 m
from ground level both side of the culvert. No
proper drainage system, pave cracks, edge not
visible, pave shoulder block by silt, vegetation,
debris.
High
Page 42 of 47
TRHC010012332026
Mahadevtila to Mohanbari, Khowai Via Dhalabil, Padmabil, Baijalbari &
Belfang (NH 108 B, Package 3)
Km 44+230
No proper drainage system, pave cracks, edge not
visible, pave shoulder block by silt, vegetation,
debris, road damage approx (L-6m & B- 5m), Edge
block with heap of hay.
High
Km 44+120
No proper drainage system, numerous potholes,
pave cracks, edge not visible, pave shoulder block
by silt, vegetation, debris,long grasses,
Heap of hay both side
High
Km 44+030
Edge encroach both side with long bushes, Stone not
visible, Shoulder edge broken, numerous potholes
approx depth 100 mm, pave cracks, road damage
approx (L- 30m, W-12m).
High
Km 43+990
Road damage approx (W-5m & L 6m), No proper
drainage system, numerous potholes, pave cracks,
edge not visible, pave shoulder block by silt,
vegetation, debris.
High
Km 43+900
Road damage approx (W-6m & L-5m), No proper
drainage system, numerous potholes, pave cracks,
edge not visible, pave shoulder block by silt,
vegetation, debris.
High
Km 43+900
No proper drainage system, numerous potholes,
pave cracks, edge not visible, pave shoulder block
by silt, vegetation, debris, road damage/distress.
High
Km 43+880
No proper drainage system, numerous potholes,
pave cracks, edge not visible, pave shoulder block
by silt, vegetation, debris, road damage/distress.
High
Km 43+840 to
Km 43+750
No proper drainage system, numerous potholes,
pave cracks, edge not visible, pave shoulder block
by silt, vegetation, debris, road damage/distress.
High
Km 43+700 to
Km 43+530
Khowai bridge, both edge encroach with mud and
vegetation, hole block.
High
Km 43+330
Both edge encroach& block with heap of firewood,
vegetation, drying cowdung on the bridge pave.
High
Km 43+300 to
Km 43+100
No proper drainage system, numerous potholes,
pave cracks, edge not visible, pave shoulder block
by silt, vegetation, debris, crash Barrier
(LHS)recommended as the approx height from
ground level is 3 to 3.5 m.
High
Km 43+050 to
Km 42+600
No proper drainage system, numerous potholes,
pave cracks, edge not visible, pave shoulder block
by silt, vegetation, debris, road damage/
Distress/Depression, poor maintenance & repair.
High
Km 42+600 Crash barriers recommended both side. High
Km 42+480
No proper drainage system, numerous potholes,
pave cracks, edge not visible, pave shoulder block
High
Page 43 of 47
TRHC010012332026
Mahadevtila to Mohanbari, Khowai Via Dhalabil, Padmabil, Baijalbari &
Belfang (NH 108 B, Package 3)
by silt, vegetation, debris, road
damage/distress/depression/Shoveling/rutting.
Km 42+100
No proper drainage system, pave cracks, edge not
visible, pave shoulder block by silt, vegetation,
debris, Crash barriers recommended.
High
Km 41+900
Crash barriers recommended. No proper drainage
system, pave cracks, edge not visible, pave shoulder
block by silt, vegetation, debris.
High
Km 41+060
Crash barriers recommended. No proper drainage
system, pave cracks, edge not visible, pave shoulder
block by silt, vegetation, debris.
High
Km 39+950
No proper drainage system, numerous potholes,
pave cracks, edge not visible, pave shoulder block
by silt, vegetation, debris, road damage,
Edge broken.
High
Km 39+780
Crash barrier recommended. No proper drainage
system, pave cracks, edge not visible, pave shoulder
block by silt, vegetation, debris.
High
Km 39+550
Both embankment hill cut slope protection
recommended. No proper drainage system, pave
cracks, edge not visible, pave shoulder block by silt,
vegetation, debris.
High
Km 39+050
Crash barriers recommended. No proper drainage
system, pave cracks, edge not visible, pave shoulder
block by silt, vegetation, debris.
High
Km 38+600
Crash barrier recommended. No proper drainage
system, pave cracks, edge not visible, pave shoulder
block by silt, vegetation, debris.
High
Km 38+530
Crash barrier recommended. No proper drainage
system, pave cracks, edge not visible, pave shoulder
block by silt, vegetation, debris.
High
Km 38+370
Crash barrier recommended. No proper drainage
system, pave cracks, edge not visible, pave shoulder
block by silt, vegetation, debris.
High
Km 38+230
Crash barrier recommended. No proper drainage
system, numerous potholes, pave cracks, edge not
visible, pave shoulder block by silt, vegetation,
debris, road damage approx (L- 8m, W-12m).
High
Km 38+100
Crash barrier recommended. No proper drainage
system, pave cracks, edge not visible, pave shoulder
block by silt, vegetation, debris, no marking.
High
Km 38+050 to
Km 38+00
No proper drainage system, numerous potholes,
pave cracks, edge not visible, pave shoulder block
by silt, vegetation, debris, road damage approx (L-
90m & W- 6 to 7 m)
High
Page 44 of 47
TRHC010012332026
Mahadevtila to Mohanbari, Khowai Via Dhalabil, Padmabil, Baijalbari &
Belfang (NH 108 B, Package 3)
Km 37+830
Crash barrier recommended. No proper drainage
system, pave cracks, edge not visible, pave shoulder
block by silt, vegetation, debris, no safety measures.
High
Km 37+530
No proper drainage system, numerous potholes,
pave cracks, edge not visible, pave shoulder block
by silt, vegetation, debris, road damage approx (L-
10m & W- 5 to 6m).
High
Km 37+300
Crash barrier recommended. No proper drainage
system, pave cracks, edge not visible, pave shoulder
block by silt, vegetation, debris, no safety measures
High
Km 37+150
Drain fully blocked, no proper drainage system,
pave cracks, edge not visible, pave shoulder block
by silt, vegetation, debris, no safety measures.
High
Km 36+600
RCC drain hole block with debris/gravels/ dry
leaves , no proper drainage system, pave cracks,
edge not visible, pave shoulder block by silt,
vegetation, debris, no safety measures.
High
Km 36+400
Bridge inspection path block with silt/mud/
vegetation, edge not visible block by silt, vegetation,
debris, no safety measures.
High
Km 36+400 to
Km 36+300
No proper drainage system, numerous potholes,
pave cracks, edge not visible, pave shoulder block
by silt, vegetation, debris, road damage approx (W-
12 m cracks)/Depression.
High
Km 36+300 Crash barrier recommended High
Km 36+300 to
Km 34+830
Maintenance & repair work poor (all damage), pave
surface rough, no proper drainage system, edge not
visible and block by vegetation.
High
Km 34+100
Pave shoulder block by pole of bamboo, firewood &
raw material (sand), no proper drainage system,
pave cracks, edge not visible.
High
Km 31+300 End of package 3
2. Chainage-wise Details in respect of NH 108B:
Mohanbari, Khowai to Mohanpur Via Subalsing & Hezamara
(NH – 108 B, Package – 2)
Day – 2 (18/07/2026)
Chainage Observation
Risk
Level
Km 31+300 Package 2 starts
Page 45 of 47
TRHC010012332026
Mohanbari, Khowai to Mohanpur Via Subalsing & Hezamara
(NH – 108 B, Package – 2)
Km 31+300
Retaining wall in hill cut slope recommended, Edge
broken, no shoulder, newly constructed drain
damage, muddy road, deep tyre rutted pave, no
safety measures.
High
Km 31+250
Road damage (full road), shoulder not visible, no
proper drainage system, retaining wall/crash barrier
recommended, muddy road, deep tyre rutted pave,
no safety measures.
High
Km 31+200
Newly constructed drain damage, no proper
drainage system, incomplete protection wall in hill
cut slope, muddy road, no safety measures.
High
Km 31+050
No proper drainage system, incomplete protection
wall in hill cut slope, muddy road deep rutted pave,
no safety measures.
High
Km 31+00
Crash barrier/Retaining wall/Protection required, no
drainage system, no safety measures.
High
Km 30+950 to
Km 30+900
Both side no embankment protection, no drainage
system, muddy road, no safety measures.
High
Km 30+830
Drain damage, no proper drainage, deep rutted pave,
muddy pave, no safety measures.
High
Km 30+800
No proper drainage, deep rutted muddy pave, no
safety measures.
High
Km 30+580
No proper drainage, deep rutted muddy pave, no
safety measures.
High
Km 30+400
No drainage system, crash barrier/ protection
recommended, no safety measures.
High
Km 30+300
Edge damage, Culvert side
Edge damage, Culvert protection wall required, no
proper drainage, no safety measures.
High
Km 29+830
Culvert protection wall required, Crash
barrier/protection recommended, no proper
drainage, no safety measures.
High
Km 29+650
Protection/Retaining wall in cut hill slope, crash
barrier recommended, no proper drainage, no safety
measures .
High
Km 29+400
No culvert protection, no proper drainage, deep
rutted muddy pave, no safety measures.
High
Km 29+300
Crash barrier recommended, no proper drainage
system, no safety measures.
High
Km 29+170
Crash barrier recommended, no proper drainage
system, no safety measures.
High
Km 28+350
No proper drainage system, no safety measures,
deep rutted muddy road of depth approx. 2-2.5ft.
High
Km 27+950 to No proper drainage system, no safety measures, High
Page 46 of 47
TRHC010012332026
Mohanbari, Khowai to Mohanpur Via Subalsing & Hezamara
(NH – 108 B, Package – 2)
Km 26+00 numerous deep rutted muddy road of depth approx.
2-2.5ft., culvert protection recommended in
chainage Km 27+160.
Day - 3 (20/07/2026)
Km 19+300
(Mohanpur) to
Km 19+400
RCC drain hole block, WMM base, Rectification on
the damage portion, no safety measures.
High
Km 19+400 to
Km 19+900
DBM started one side (Poor), earthen drain not yet
constructed, no safety measures.
High
Km 19+900 to
Km 20+150
DBM both side, Earthen drain not yet constructed,
no safety measures.
High
Km 20+150 to
Km 20+300
Block road (we went through existing old road,
culvert complete but water cannot pass through due
to block by mud, no proper drainage system.
High
Km 20+380 culvert covered with silt/vegetation High
Km 20+380 to
Km 20+650
No proper drainage, work under process (road
block)
High
Km 20+650 Bridge under construction not even 10% done High
Km 20+720 to
Km 21+050
DBM both side, no proper drainage High
Km 21+050 to
Km 21+100
Culvert block by vegetation, deep rutted muddy
road, no proper drainage.
High
Km 21+100 to
Km 22+200
DBM damage, RCC drain hole all blocked by
silt/vegetation.
High
Km 22+200 to
Km 22+280
CTSB done & damage, Earthen drain not yet
constructed.
High
Km 22+280 to
Km 22+530
DBM complete & damage,
Both side drain not yet constructed
High
Km 22+530 to
Km 22+780
Crash barrier required both side, deep rutted muddy
pave of various depth
High
Km 22+780 to
Km 22+940
DBM both side, Crash barrier recommended, no
safety measures.
High
Km 22+940 to
Km 23+080
DBM one side RHS, no drainage system, WMM
damage one side LHS
High
Km 23+080 to
Km 23+900
WMM damage, numerous potholes, crash barrier
required , Muddy road of multiple damage approx
Depth 300 mm.
High
Km 23+980 to
Km 24+550
WMM fully damage, Crash barrier/Protection
required
High
Km 24+450 to
Km 24+800
No drainage, deep rutted muddy road with multiple
depth of 1 feet and more.
High
Km 25+00 to
Km 25+450
DBM damage High
Page 47 of 47
TRHC010012332026
Mohanbari, Khowai to Mohanpur Via Subalsing & Hezamara
(NH – 108 B, Package – 2)
Km 25+450 WMM damage High
Km 25+500 DBM damage, RCC drain hole block. High
Km 25+700 to
Km 25+900
DBM one side RHS under construction High
Km 25+900 to
Km 26+00
Due to newly bridge under construction, the
adjacent existing old road is used and it has no
proper drainage system, numerous potholes, pave
damage, no temporary arrangement, no safety
measures, edge not visible, shoulder block by
silt/debris/vegetation.
High
(BISWAJIT PALIT, J) (M.S. RAMACHANDRA RAO, CJ)
Pulak
Legal Notes