As per case facts, the petitioner, an enlisted contractor, challenged a show cause notice concerning his removal from the approved list and the subsequent refusal of renewal. He had applied ...
IN THE HIGH COURT AT CALCUTTA
(Constitutional Writ Jurisdiction)
APPELLATE SIDE
Present:
The Hon’ble Justice Krishna Rao
W.P.A. No. 29839 of 2025
Debopriyo Deb Roy
Vs.
Union of India & Ors.
Mr. Aritra Basu
Mr. Ritoban Sarkar
Mr. Tanmoy Sett
Mr. Pran Gopal Das
....For the petitioner.
Mr. Subrata Roy
Mr. Pralay Bhattacharjee
….For the Union of India.
Hearing Concluded On : 25.06.2026
For Clarification On : 13.07.2026
Judgment Delivered On : 23.07.2026
Judgment Uploaded On : 23.07.2026
2
Krishna Rao, J.:
1. The petitioner has filed the present writ petition challenging the show
cause notice dated 28
th October, 2021, wherein the petitioner is
directed to show cause as to why the firm of the petitioner shall not be
removed from the approved list of contractors and communication
dated 15
th December, 2025.
2. The petitioner was an enlisted contractor with the respondent
authorities for the period from 1
st
January, 2016 to 31
st
December,
2020, under Class “B” with index No. B-11. The petitioner by a
representation dated 29
th
September, 2020, made a request for renewal
of his enlistment from the circle period of 2021 to 2025.
3. The respondent authorities have issued show cause notice to the
petitioner on 28
th October, 2021, calling upon the petitioner to show
cause as to why the name of the petitioner shall not be removed from
the approved list of contractors as the petitioner is not fulfilling the
criteria for renewal for the next cycle period of 2021-2025. The
petitioner has submitted a detailed reply to the respondents on 29
th
November, 2021. Inspite of receipt of reply from the petitioner, the
respondents have not taken any steps and on 25
th
July, 2022, the
petitioner has preferred an appeal before the Appellate Authority. No
order is passed in the appeal filed by the petitioner.
4. On 20
th November, 2025, the petitioner again made a request to the
respondent authorities for renewal of his enlistment from January,
3
2026. On 15
th December, 2025, the respondent authorities sent a
detailed reply to the petitioner and refused to renew the enlistment of
the petitioner for the cycle period from January, 2026. In the said
communication, it was informed to the petitioner that recovery of an
amount of Rs. 52,120/- is due from the petitioner as per letter dated
11
th May, 2023 and as per record, an amount of Rs. 38,53,541/- is
outstanding against the petitioner. The petitioner has submitted reply
to the said refusal on 19
th
December, 2025.
5. Mr. Aritra Basu, Learned Advocate, representing the petitioner submits
that with regard to CA No. CE(AF) SZ/KUM/15 of 2015-16 for provision
of parking area and pavement along with lightning facilities at AFS
Kumbhigram, the authorities have illegally cancelled the said tender by
the Shillong Zone on 23
rd September, 2022, with effect from 30
th
September, 2022 and claimed Rs. 44,46,442/-. The petitioner has
issued a notice to the authorities for appointment of Arbitrator on 20
th
December, 2024, making certain claims and also proposed three names
to be appointed as an arbitrator but no arbitrator was appointed.
6. Mr. Basu submits that with regard to recovery of Rs. 52,128/-, the
concern work order was issued in the year 2004 and was duly
completed in 2004 but after a lapse of 20 years, the respondent
authorities have raised claim of the said amount.
7. Mr. Basu submits that as regard to the claim of Rs. 38,53,541/-, the
same was adjudicated by the Learned Arbitrator and as per the Award
4
dated 25
th November, 2024, the said claim has been settled and no
adverse consequence survived against the petitioner. He submits that
during the period 2015 to 2020, the petitioner has completed the works
and an amount of Rs. 1,81,23,173/ - is remain due and payable by the
respondents to the petitioner.
8. Mr. Basu submits that during the pendency of the present writ petition,
by a letter dated 13
th
January, 2026, the respondent no.3 informed the
petitioner that the name of the petitioner is removed from the approved
list of the contractors by a letter dated 4
th
June, 2022. He submits that
the respondents have ignored the facts that with respect to CA No.
CCE/NAR/DIN-01 of 2015-16, an Award has been passed by the
Learned Sole Arbitrator in favour of the petitioner and the respondents
have not challenged the said Award.
9. Mr. Basu submits that the letter dated 4
th June, 2022, was never
served upon the petitioner. He submits that the respondents cannot
remove the name of the petitioner from the approved list of contractors
of the respondents for indefinite period. In support of his case, he has
relied upon the judgment in the case of Vetindia Pharmaceuticals
Limited vs. State of Uttar Pradesh and Another reported in (2021)
1 SCC 804 and submits that an order of black listing beyond 3 years
or maximum of 5 years was disproportionate.
10. Mr. Basu has further relied upon the judgment in the case of Kulja
Industries Limited Vs. Chief General Manager, Western Telecom
5
Project Bharat Sanchar Nigam Limited and Others reported in
(2014) 14 SCC 731 and submits that the debarment is never
permanent and the period of debarment would invariably depend upon
nature of the offence committed by the erring contractor.
11. Mr. Basu has relied upon the judgment in the case of M/s. Erusian
Equipment and Chemicals Ltd. Vs. State of West Bengal and
Another reported in (1975) 1 SCC 70 and submits that fundamentals
of fair play require that the person concern should be given an
opportunity to represent his case before he is put on the blacklist.
12. Mr. Basu has further relied upon the judgment in the case of Lt.
Governor, Delhi and Others Vs. HC Narinder Singh reported in
(2004) 13 SCC 342 and submits that second penalty based on the
same cause of action would amount to double jeopardy.
13. Mr. Subrata Roy, Learned Advocate, representing the respondent
authorities submits that by a letter dated 28
th October, 2021, a show
case notice was issued to the petitioner, as the firm falls under Para
7(a) of Engineer-in-Chief’s Branch letter dated 24
th
April, 2020, calling
upon the petitioner as to why his name shall not be removed from the
approved list of contractors as the petitioner not full filling the criteria
for renewal of his enlistment for the next cyclic period of 2021 to 2025.
14. Mr. Roy submits that the petitioner has not submitted any show cause
reply and accordingly the renewal of the firm has not been considered.
He submits that the term “removal” has been used in the letter dated
6
4
th June, 2022, but the said letter is to be read in conjunction with
Engineer-in-Chief’s Branch letter dated 24
th April, 2020, which clearly
specifies that if the firm falls under para 7, renewal of the firm shall not
be carried out for the next cycle period i.e. 2021-2025.
15. Mr. Roy submits that no specific time period is applicable to Head
Quarter, CEEC letter dated 4
th
June, 2022 and the petitioner can apply
for renewal/ fresh enlistment provided the petitioner satisfied all the
criteria of renewal / fresh enlistment.
16. Mr. Roy submits that the petitioner is relying upon the Award passed
by the Learned Sole Arbitrator but the Learned Sole Arbitrator has
opined that there is no illegality or irregularity in cancelling the
contract by the respondents. He submits that the cancellation of the
contract has not been declared invalid or illegal by the Learned
Arbitrator.
17. Heard the Learned Counsel for the respective parties, perused the
materials on record and the judgments relied by the petitioner. The
petitioner was the enlisted contractor of the respondent authorities. On
29
th
September, 2020, the petitioner has applied for renewal of his
enlistment from the year 2021 to 2025. On 28
th
October, 2021, the
respondents have issued show cause notice to the petitioner on the
allegation that the work order issued to the petitioner by the ADG (NEI)
Guwahati in the month of June, 2021, was cancelled, therefore,
renewal of the enlistment falls under para 7 of the Engineer-in-Chief’s
7
Branch letter dated 24
th April, 2020 and directed to show cause as to
why the name of the petitioner is not removed from the approved list of
contractors as the petitioner was not fulfilling the criteria for renewal of
his enlistment for the next circle i.e. 2021-2025. The petitioner has
submitted his reply to the show cause notice which is appearing at
page 30 being Annexure “P/5” of the writ petition but the respondents
are denying with respect to any reply submitted by the petitioner. The
petitioner has relied upon the Award passed by the Learned Sole
Arbitrator dated 25
th
November, 2024, wherein the Learned Arbitrator
has partly awarded the claim of the petitioner to the tune of Rs.
22,84,010/- with interest at the rate of 2% higher than the prevailing
rate of interest.
18. Enlistment of the petitioner was not renewed for the period from 2021
to 2025, the petitioner has made another request to the respondent
authorities on 20
th November, 2025, for renewal of the enlistment of the
petitioner for the period from 2026 onwards but by a communication
dated 15
th December, 2025, the respondent authorities informed the
petitioner that the work order being CA No. CE(AF)SZ/KUM/15 of
2015-16 was cancelled on 23
rd
September, 2022, in which an amount
of Rs.44,46,442/- is due against the petitioner. In the said
communication, it was further informed to the petitioner that claim of
Rs. 52,120/- and Rs. 38,53,541/- are also outstanding dues against
the petitioner.
8
19. The show cause notice dated 28
th October, 2021, issued on the
allegation that ADG (NEI) Guwahati, has issued WLR for the Qtr.
Ending June 2021 by a letter dated 15
th September, 2021, wherein it
was informed that the contract awarded to the petitioner was cancelled.
After issuance of the said show cause notice, the respondents have not
taken any action. From the communication dated 13
th January, 2026,
the petitioner came to know that the respondents have removed the
name of the petitioner from the approved list of contractors by a letter
dated 4
th
June, 2022. It is the specific case of the petitioner that the
said communication was not served to the petitioner and the
respondents have also not produced any record to show that the letter
dated 4
th
June, 2022, was served upon the petitioner.
20. The respondents have relied upon Para 7 (a) of the Engineer-in-Chief’s
Letter dated 24
th April, 2020, on the basis of which renewal of the
enlistment of the petitioner was not considered which reads as follows:
“Criteria for Renewal
7. All contractors who apply for renewal will
be re-enlisted in the same Class/categories of
enlistment. Renewal of enlistment of all contractors
who submit required documents and fulfill the
criteria of renewal shall be carried out except those
falling under the following categories. Renewal of
enlistment of such contractors shall be carried out
only after obtaining approval of this HQ:-
(a) Contractors whose contracts have been
cancelled and unrealized recoveries exist thereto
and cases, where cancellation of contract has
been declared invalid/ illegal in arbitration/court
of law.
9
(b) Contractors in whose completed works
during last five years, serious defects were
noticed which are substantially attributed to
the performance of Contractors, established
through Court of Inquiry or Tech Boards of
Officers and disciplinary action is pending/
initiated.
(c) Contractors who could not secure any
work in the last five years ending last date of
receipt of application for renewal (refer Para 6
(a)) either in MES/DG MAP or any Govt
Dept/Public Sector undertaking/AWHO/
ANWHO/DGsNP/CGEWHO or in case they
could not secure any works, they have not
participated in tendering in MES or have
participated in tendering but have not been in
first three lowest quotations.
(d) Contractors who are habitual litigants.
(e) Contractors not found fir for renewal
for reasons other than (a) to (d) above, ie
unethical conduct.
(f) Contractors who are already removed
on account of any default on their part, or
debarred, but period of debarment is not yet
over. Contractors against whom the
debarment would be over after the stipulated
date(s), the stipulated date(s) would be
deemed to be extended accordingly.
(g) Any case of unusual nature shall be
referred to this HQ well within time for
advice/ clearance.
[Notes: Regarding (a) to (e) above, action shall to
be taken to obtain the explanation of the
contractor(s) by serving notice to him bringing out
the issue as applicable and allowing four weeks’
time to furnish replies. The issue shall be
decided taking into account the replies of the
contractor(s) and after referring the complete
case to this HQ. In respect of (d) above, a
contractor will be considered a habitual litigant if
he moves the Court more than once ignoring
arbitration clause and the Court does not upload
his view.]”
10
21. The petitioner has relied upon the Award passed by the Learned
Arbitrator dated 25
th November, 2024. In the said Award, a specific
issue is decided “Whether the termination of the contract vide order
dated 31
st July, 2020, is legally valid and justified or not?” While
deciding the said issue, the Learned Arbitrator held that “In view of the
above discussions, the Tribunal is of the opinion that there is no illegality
or irregularity in cancelling the contract by the respondent and as such
the said issue answered in negative and in favour of the respondent.”
22. The Learned Arbitrator has decided the issue in negative but has
passed an Award directing the respondents for payment of the amount
of Rs. 22,84,010/- along with interest. The respondents raised counter
claim against the petitioner in the arbitration proceedings. The Learned
Arbitrator decided four counter claims of the respondents in the said
award by rejecting all counter claims of the respondents, which reads
as follows:
“COUNTER CLAIM NO.1 :
19. In para 53 of the Statement of Defence the
respondent has asserted that as per Special
Conditions of Contract, as indicated in Appx. 'E' (R-
24), the qualification for deployment of Engineer
has been prescribed wherein the qualification for
Resident Engineer is BE/ B.Tech (Civil) with 15
years experience; Project Engineer is BE/B.Tech
(Civil) with 10 years experience or Diploma in Civil
Engineering with 15 years experience and for Site
Supervisor - Civil Engineering or Electrical
Engineering. The respondent has raised a counter
claim amounting to Rs.2,16,68,000/- as per Clause
67(a) of IAFE-2249 on the ground that no
experience certificate has been produced by the
claimant in respect of the aforesaid employees.
There is no adequate pleading from the
11
respondent's side in this respect. Further, the
scrutiny for experience certificate is to be done at
initial stage by the respondent, but that has not
been done nor the respondent asked for such
certificate. Even if there is any violation, the
respondent has waived it allowing the concerned
workers to continue. The respondent has failed to
substantiate this claim for recovery in terms of
Clause 67(F) of IAFW-2249. Hence, this counter
claim stands rejected.
COUNTER CLAIM NO.2 :
20. In para 54 the respondent has pleaded
that the department's claim for the expenditure
incurred in execution of the balance work left by
the claimant, which was done under risk and cost
of the contractor due to non-completion of the work,
with effect from September 2020 to June 2022 i.e.
for 22 months. But in support of this counter claim
the respondent has not produced any document of
payment to the respective officer/employees as
well as amount spent in other respect as mentioned
in the said paragraph. The claimant has denied the
claim. There is no adequate pleading and evidence
in this respect from the respondent. The respondent
has failed to prove their claim with reliable and
sufficient materials
In view of the above fact situation this counter
claim stands rejected.
COUNTER CLAIM NO.3 :
21. In para 55 of the Statement of Defence,
the respondent has made a counter claim of
Rs.7,00,000/- for non-providing of Site Lab as per
Clause 33 of the Contract and Rs.5,75,000/-, for
not providing furnished site office as per Clause
34(E) of the Contract Agreement (as amended).
In this counter claim the respondent has not
furnished the adequate and relevant materials to
come to a finding as prayed for. Further, the
respondent has also not indicated the provisions in
the contract agreement for recovery of such amount
for failure of the claimant. There is no adequate
pleading in support of the claim. The respondent
12
allowed the claimant to continue with the work in
spite absence of such requirement.
In view of the above discussions, this counter
claim stands rejected.
COUNTER CLAIM NO.4 :
22. At para-56 of the Statement of Defence the
respondent has prayed for an amount of
Rs.25,00,000/- on the ground that due to non-
completion of the work in time for the fault of the
claimant related tender for furniture was not
completed by the respondent as the procedure was
in vogue and the cost of furniture tendered has
been escalated and as such the respondent has
prayed for recovery of the same from the claimant.
Further, an amount of Rs.7,50,00,000/- has been
claimed by the respondent for defamation of the
respondent organization due to non-completion of
the project in time. Apart from making this bald
statement in the Statement of Defence, no other
materials have been produced by the respondent.
The claim for Rs.25,00,000/- on account of
escalation of furniture cost is remote one. Further,
the respondent has not made any whisper as to
how and in what manner they have been defamed
due to non-execution of the work in time. The
respondent has not been able to substantiate this
counter claim and accordingly this claim stands
rejected.”
23. In the month of November, 2025, the petitioner has further requested
for renewal of its enlistment and in reply to the same, the respondents
have informed the petitioner about several pending dues against the
petitioner by a communication dated 15
th
December, 2025. The
petitioner has submitted detailed reply to the respondents on 19
th
December, 2025. In the said reply, the petitioner has taken the stand
that with regard to the provision of parking area and pavement in
connection with CA No. CE(AF)/SZ/KUM/15 of 2015-16, the petitioner
13
has already issued notice under Section 21 of the Arbitration and
Conciliation Act, 1996 but no Arbitrator is appointed. With regard to
the recovery of Rs. 52,128/-, the alleged claim is in connection with the
work order of 2004 and the petitioner has completed the work in the
year 2004 and lapse of about 20 years, the respondents have raised the
alleged claim. As regard to the claim of Rs. 38,53,541/-, the said claim
was the subject-matter of arbitration proceeding and an Award was
passed on 25
th
November, 2024 and no Award was passed with respect
to the said amount in favour of the respondents, thus the respondents
cannot claim any further amount from the petitioner.
24. In the show cause notice, the respondents have relied upon one
cancellation order and subsequently, the respondents have raised
further claims. The petitioner has submitted reply to the said claims
but in the impugned order dated 13
th June, 2026, the authorities have
only relied upon para 7(a) of the Engineer-in-Chief’s Branch Letter
dated 24
th April, 2020, but have not considered the details submitted
by the petitioner.
25. As per Clause 1.14(d) of the Enlistment of Contractors, Standing
Security Deposit, upgrading, removal and down grading of the
contractors provides that “the contractors whose contracts have been
cancelled and unrealized recoveries exist thereto, cases, where
cancellation of contract has been declared invalid/illegal in
arbitration/court of law, shall be decided after obtaining approval of E-in-
C Branch.”
14
26. The respondents have issued show cause notice only on the basis of
cancellation of work order but in the impugned order of removal dated
4
th June, 2022, the respondents have taken further ground that the
petitioner has not submitted complete requisite documents for renewal.
The petitioner could not get an opportunity of hearing with regard to
the non-submission of complete documents for renewal. Thus, the
impugned order dated 4
th
June, 2022, is set aside and quashed.
27. Considering the above, the Engineer-in-Chief, the respondent no. 2 is
directed to consider the reply submitted by the petitioner dated 19
th
December, 2025 and if necessary, an opportunity of personal hearing
be given to the petitioner and pass reasoned and speaking order within
a period of four weeks from the date of receipt of this order and to
communicate the same to the petitioner within a week thereafter.
28. WPA No. 29839 of 2025 is disposed of.
Parties shall be entitled to act on the basis of a server copy of the
Judgment placed on the official website of the Court.
Urgent Xerox certified photocopies of this judgment, if applied for,
be given to the parties upon compliance of the requisite formalities.
(Krishna Rao, J.)
15
Legal Notes
Add a Note....