No Acts & Articles mentioned in this case
2025:MHC:2743Arb.O.P.(Com.Div.) Nos.139
& 253 of 2021
1/23
In the High Court of Judicature at Madras
Reserved on
25.11.2025
Delivered on:
02.12.2025
Coram :
The Honourable Mr.Justice N.ANAND VENKATESH
Arbitration O.P.(Com.Div.) Nos.139 & 253 of 2021
Arb.O.P.(Com.Div) No.139 of 2021 :
Electronics Corporation of
Tamil Nadu Ltd., rep.by
its Managing Director,
692, Anna Salai, Nandanam,
Chennai-35. ...Petitioner
Vs
United Telecom Ltd.,
18A/19, Doddanekundi
Industrial Area,
Mahadevapura Post,
Bangalore-560048. ...Respondent
Arb.O.P. (Com.Div.) No.253 of 2021 :
United Telecom Ltd., rep.by its
Senior Manager (Marketing),
No.18A/19, Doddanekundi
Industrial Area, Mahadevapura Post,
Bangalore-560048. ...Petitioner
Vs
https://www.mhc.tn.gov.in/judis ( Uploaded on: 02/12/2025 03:54:11 pm )
Arb.O.P.(Com.Div.) Nos.139
& 253 of 2021
2/23
M/s.Electronics Corporation of
Tamil Nadu Ltd., rep.by
its Managing Director,
MHU Complex, II Floor,
692, Anna Salai, Nandanam,
Chennai-35. ...Respondent
PETITIONS under Section 34 of the Arbitration and Conciliation
Act, 1996 praying
(i) to set aside the award dated 10.3.2021 with respect to the
interest awarded by the Tribunal in the dispute arising out of contract
dated 23.1.2013 (Arb.O.P. (Com.Div.) No.139 of 2021); and
(ii) to set aside the impugned award dated 10.3.2021 with
respect to the findings of the sole Arbitrator in issues (ii), (iii), (v),
(vi), (viii) and (xiv) of the award (Arb.O.P.(Com.Div.)No.253 of 2021).
For Petitioner in
Arb.O.P.No.139 of 2021
& For Respondent in
Arb.O.P.No.253 of 2021 : Mr.V.Srikanth for
Mr.E.Ganesh
For Respondent in
Arb.O.P.No.139 of 2021
& For Petitioner in
Arb.O.P.No.253 of 2021 : Mr.M.S.Krishnan, SC for
Mr.J.James https://www.mhc.tn.gov.in/judis ( Uploaded on: 02/12/2025 03:54:11 pm )
Arb.O.P.(Com.Div.) Nos.139
& 253 of 2021
3/23
COMMON ORDER
M/s.Electronic Corporation of Tamil Nadu Limited (ELCOT) filed
Arb.O.P.(Com.Div.) No.139 of 2021 under Section 34 of the Arbitration
and Conciliation Act, 1996 (for short, the Act) against the claim
allowed by the learned Arbitrator pertaining to payment of interest
towards delayed payments vide award dated 10.3.2021.
2. M/s.United Telecom Limited (UTL) filed Arb.O.P.(Com.Div.) o.
253 of 2021 against those claims, which were rejected by the learned
Arbitrator by the very same award dated 10.3.2021.
3. Heard both.
4. The facts leading to filing of these petitions are as follows:
(a) The ELCOT floated a tender on 22.5.2012 for the supply and
commissioning of 7,84,000 laptops throughout the State of Tamil Nadu
for Phase II for the year 2012-2013. The UTL submitted their bid for
the supply of 2,00,000 laptop computers. Vide Letter of Acceptance
(LoA) dated 17.12.2012, the ELCOT decided to allot a quantity of https://www.mhc.tn.gov.in/judis ( Uploaded on: 02/12/2025 03:54:11 pm )
Arb.O.P.(Com.Div.) Nos.139
& 253 of 2021
4/23
2,50,000 laptop computers with back-ups to the UTL.
(b) In the said LoA, the ELCOT also provided details regarding
specification of the laptop computers as well as back-ups to be
supplied by the UTL. Through the said LoA, the UTL was also called
upon to submit a security deposit amounting to 3% of the purchase
order value and execute a supply agreement within one week from the
date of issuance of the LoA.
(c) The UTL submitted a security in the form of bank guarantee
on 29.12.2012 for a sum of Rs.12,59,21,250/-. Through a letter dated
07.1.2013, the UTL informed the ELCOT that there was a delay due to
various reasons beyond the control of the UTL and therefore,
requested for revision of the delivery schedule for the supply of laptop
computers. But, no response was received from the ELCOT.
(d) In order to fulfil the eligibility criteria specified under Clause
2 of the tender document, the UTL submitted its bid as a part of the
consortium of bidders. The consortium agreement was executed on
23.1.2013 and pursuant to the same, the UTL was appointed as the
prime bidder of the consortium. Thereafter, the parties executed a
supply agreement as required under Clause 3.27 of the tender https://www.mhc.tn.gov.in/judis ( Uploaded on: 02/12/2025 03:54:11 pm )
Arb.O.P.(Com.Div.) Nos.139
& 253 of 2021
5/23
document and the LoA on 23.1.2013.
(e) On 05.2.2013, the ELCOT issued the second LoA to the UTL
and allotted a further quantity of 1,10,000 laptop computers for
supply. The delivery of 2,50,000 laptops was supposed to be
completed by 12.5.2013. Since the time schedule was not adhered to
by the UTL, the ELCOT cancelled 1,20,000 laptops out of 2,50,000
allotted to the UTL and informed the UTL that its order was limited to
the supply of 1,30,000 laptop computers. In the light of partial
termination of the contract by the ELCOT, the UTL submitted a revised
security deposit for the revised quantity amounting to
Rs.6,54,79,100/-.
(f) The UTL completed the supply of laptop computers and the
ELCOT continued to withhold payments for the quantity supplied.
Hence, a dispute arose between the parties. Accordingly, the UTL
issued a letter dated 22.11.2017 invoking the arbitration clause.
Further, O.P.No.395 of 2018 and by order dated 06.8.2018, the
learned Arbitrator was appointed by this Court.
(g) Pursuant to that, the UTL filed the claim petition by making
the following claims: https://www.mhc.tn.gov.in/judis ( Uploaded on: 02/12/2025 03:54:11 pm )
Arb.O.P.(Com.Div.) Nos.139
& 253 of 2021
6/23
“i. to declare that the levy of LD for
deviations in the delivery schedule with respect to
the contract is illegal;
ii. to direct the respondent to make payment
to the claimant of the sums amounting to
Rs.10,91,31,750/- illegally withheld by the
respondent as LD;
iii. to direct the respondent to make
payment to the claimant of the sums amounting to
Rs.90,982/- as being sums illegally withheld by the
respondent;
iv. to direct the respondent to pay a sum of
Rs.19,18,80,000/- being loss of profit due to
unlawful reduction by the respondent of the
ordered quantity of laptops and back packs;
v. to direct the respondent to pay a sum of
Rs.33,67,49,400/- towards the loss of opportunity
to the claimant;
vi. to direct the respondent to compensate
the claimant for the additional bank charges
incurred by the claimant for roll-over of its LCs due
to delay in payments by the respondent,
amounting to Rs.53,19,328/-;
vii. to direct the respondent to make
payment of interest from the date, on which, the
payments were due/cause of action arose till the
date of the filing the statement of claim, being an
amount of Rs.17,28,87,412/- and all interest https://www.mhc.tn.gov.in/judis ( Uploaded on: 02/12/2025 03:54:11 pm )
Arb.O.P.(Com.Div.) Nos.139
& 253 of 2021
7/23
accruing from the date of filing of the statement of
claim till the date of payment of the money
pursuant to an award in favour of the claimant as
per the amounts indicated in Annexure 3; and
viii. to direct the respondent to pay costs of
the proceedings before the Tribunal.”
(h) The ELCOT filed a statement of defence and took a stand
that all sums due and payable to the petitioner had been cleared and
that they were not liable to make any payment. They also alleged that
the entire delay was attributable only to the UTL.
(i) The learned Arbitrator, on considering the pleadings, framed
the following issues:
“(1) Whether the claimant is entitled to
initiate the arbitration proceeding without
participation of its consortium partners?
(2) Whether there is a delay on the part of
the claimant in performing the contract and
whether the respondent has suffered any loss due
to any deviation in delivery schedule?
(3) Whether the levy of liquidated damages
by the respondent upon the claimant is
unreasonable, illegal or against the provisions of
the contract?
(4) Whether the claimant is entitled to claim
or raise disputes other than the claims made in the
notice dated 22.11.2017 invoking arbitration? https://www.mhc.tn.gov.in/judis ( Uploaded on: 02/12/2025 03:54:11 pm )
Arb.O.P.(Com.Div.) Nos.139
& 253 of 2021
8/23
(5) Whether the recovery of liquidated
damage is valid?
(6) Whether the respondent is liable to pay
the claimant the sum of Rs.10,91,31,750/- stated
to have been recovered as liquidated damages?
(7) Whether the respondent is liable to make
payment of Rs.90,982/- to the claimant as claimed
in the claim statement?
(8) Whether the respondent is liable to pay a
sum of Rs.19,18,80,000/- to the claimant as loss of
profit as claimed in the claim statement?
(9) Whether the claimant is entitled to a sum
of Rs.33,67,49,400/- from the respondent as
claimed in the claim statement?
(10) Whether the claimant is entitled to a
sum of Rs.53,19,328/- from the respondent as
claimed in the claim statement?
(11) Whether the claimant is entitled to the
interest of Rs.17,28,87,412/- from the respondent
as claimed in the claim statement?
(12) Whether the respondent is liable to pay
interest if any, pendente lite and further interest?
(13) To what other reliefs the parties are
entitled to?
The following a dditional i ssue was framed as
issue No.14 on 20.12.2019:
(14) Whether the respondent is entitled to
appropriate the amount due to the claimant made https://www.mhc.tn.gov.in/judis ( Uploaded on: 02/12/2025 03:54:11 pm )
Arb.O.P.(Com.Div.) Nos.139
& 253 of 2021
9/23
under invoices raised by them for supply of laptops
without filing any claim or counter claim?”
(j) On the side of the UTL, C.W.1 was examined and Ex.C.1 to
Ex.C.44 were marked. On the side of the ELCOT, R.W.1 was examined
and Ex.R.1 to Ex.R.30 were marked.
(k) The learned Arbitrator, on considering the facts and
circumstances of the case and the evidence that was let in by both
sides, passed an award in the following terms:
“1. The respondent shall be liable to make
payment of Rs.90,982/- to the claimant, towards
the amount withheld;
2. The claimant is entitled to the interest
amount of Rs.17,28,87,412/- from the respondent
for the delayed payments towards the bills, with
interest on the said amount at 9% per annum from
September 2018 till realization;
3. The deduction of Rs.10,91,31,750/- by
the respondent by way of recovery from the bill
amounts of the claimant as liquidated damages is
legal and as per the terms of contract between the
parties and the respondent is not liable to pay the
said amount to the claimant;
4. The respondent is not liable to pay
Rs.19,18,80,000/- to the claimant as loss of profit;
5. The claimant is not entitled for
Rs.33,67,49,400/- from the respondent towards https://www.mhc.tn.gov.in/judis ( Uploaded on: 02/12/2025 03:54:11 pm )
Arb.O.P.(Com.Div.) Nos.139
& 253 of 2021
10/23
loss of opportunity;
6. The claimant is not entitled for
Rs.53,19,328/- from the respondent towards
rollover of Lcs;
7. The claims of the claimant are disposed in
the above terms;
8. The parties shall bear their own costs.”
(l) Both parties have questioned the award under Section 34 of
the Act by filing the above petitions.
5. This Court has carefully considered the submissions of the
learned counsel on either side and perused the materials available on
record and more particularly the impugned award.
6. The learned Senior Counsel appearing on behalf of the UTL
submitted that the learned Arbitrator went wrong in denying the claim
made by the UTL except granting the claim towards payments that
were withheld and the interest amount for the delayed payments.
7. On the contrary, the learned counsel appearing for the ELCOT
submitted that the learned Arbitrator assigned sufficient reasons for
denying all the other claims made by the UTL and the same do not https://www.mhc.tn.gov.in/judis ( Uploaded on: 02/12/2025 03:54:11 pm )
Arb.O.P.(Com.Div.) Nos.139
& 253 of 2021
11/23
suffer from perversity or patent illegality.
8. The UTL had made a claim for the release of the sums
withheld as liquidated damages and had also claimed for the loss
towards unlawful reduction in the quantity that was originally ordered.
The UTL further claimed for the loss of opportunity and the loss
suffered due to roll over of the LCs. The learned Arbitrator, while
dealing with all the claims, had properly appreciated the relevant
clause in the agreement between the parties and also the evidence
that was let in by both sides and rejected those claims. This Court
finds that the reasoning assigned by the learned Arbitrator while
rejecting the other claims is a possible view taken by the learned
Arbitrator based on the relevant clauses in the agreement/tender
document and the documents that were marked by both sides. This
Court cannot sit on appeal against those findings since the findings did
not suffer from any perversity or patent illegality.
9. On a careful consideration of the submissions made on either
side, the only issue that has to be gone into by this Court pertains to https://www.mhc.tn.gov.in/judis ( Uploaded on: 02/12/2025 03:54:11 pm )
Arb.O.P.(Com.Div.) Nos.139
& 253 of 2021
12/23
the interest portion that was awarded by the learned Arbitrator to the
tune of Rs.17,28,87,412/- towards delayed payment. In fact, the
learned counsel on either side mainly focused their arguments on this
issue.
10. The tender document provided for commissioning of the
laptop computers, which was defined as switching on the laptop
computers and testing its functions in the presence of the head of the
institutions. Clause 3.25 provided that the issuance of the LoA signified
beginning of the contract with the successful bidder. Clause 3.32 also
provided for the liquidated damages for non fulfilment of the delivery
schedule at the rate of 1% per week on the value of the undelivered
quantity subject to a maximum of 5% on the undelivered quantity. It
also provided that the liquidated damages would be automatically
deducted from the bills submitted by the supplier.
11. As per the payment terms, Clause 5.3 provided that 97% of
the payment would be released after successful completion of supply
and acceptance by the respective institutions. As per Clause 5.4, the https://www.mhc.tn.gov.in/judis ( Uploaded on: 02/12/2025 03:54:11 pm )
Arb.O.P.(Com.Div.) Nos.139
& 253 of 2021
13/23
balance 3% would be released after successful completion of the
warranty period of one year from the date of supply and acceptance by
the respective institutions. The tender itself provided for the model
form of the contract and the supply schedule was fixed as hereunder:
# Cumulative quantity to be
delivered
Supply schedule in
calendar days from
the date of LOA
1 15% of ordered quantity Within 60 days
2 45% of ordered quantity Within 90 days
3 80% of ordered quantity Within 135 days
4 100% of ordered quantity Within 150 days
12. It is not in dispute that since the UTL was not able to fulfil
the requirement, the ELCOT cancelled 1,20,000 laptops out of
2,50,000 allotted to the UTL and ultimately what was supplied by the
UTL was 1,30,000 laptops.
13. The learned Arbitrator had taken into consideration the fact
that there was, in fact, delay on the part of the UTL in making the
supply and hence, confirmed the levy of liquidated damages by the
ELCOT. For the limited purpose of looking into the findings of the
learned Arbitrator by allowing the claim towards interest on delayed
payment, it will suffice to take note of issue Nos.2, 3 and 11. https://www.mhc.tn.gov.in/judis ( Uploaded on: 02/12/2025 03:54:11 pm )
Arb.O.P.(Com.Div.) Nos.139
& 253 of 2021
14/23
14. For issue No.2, which pertained to the delay in the
performance of the contract, the learned Arbitrator came to the
conclusion that the UTL could not justify the delay in the supply of
laptops only on the ground that there was delay in payment. Hence,
the learned Arbitrator rendered a finding that there was delay on the
part of the UTL.
15. Issue No.3 pertained to levy of liquidated damages. In the
light of the finding that there was delay on the part of the UTL in
supplying the laptop, the learned Arbitrator took into consideration the
relevant clause, which provided for the liquidated damages and
rendered a finding that the ELCOT was justified in deducting the
liquidated damages.
16. Issue No.11 was the important issue, which directly arises
for consideration in these petitions.
17. The learned Arbitrator rendered a finding that the UTL had
claimed interest under three heads namely https://www.mhc.tn.gov.in/judis ( Uploaded on: 02/12/2025 03:54:11 pm )
Arb.O.P.(Com.Div.) Nos.139
& 253 of 2021
15/23
(i) Interest on delayed payment of 97%
of the invoice amount to the tune of
Rs.16,56,92,342/-;
(ii) Interest on delayed payment of 3%
retention amount to the tune of
Rs.59,26,686/-; and
(iii) Interest on delayed payment on the
earnest money deposit (EMD) amount of
Rs.12,68,384/-.
18. The learned Arbitrator had taken into consideration Clause
17(c), which provided for payment of 97% to be released by the
ELCOT after successful completion of the supply and acceptance by the
respective institutions. The UTL provided the particulars of delay by
means of annexure, which formed part of the Enterprise Resource
Planning (ERP) that is maintained by the ELCOT. Therefore, the
annexure was not actually prepared by the UTL. But, they had merely
shown the particulars that were available with the ELCOT in the ERP. https://www.mhc.tn.gov.in/judis ( Uploaded on: 02/12/2025 03:54:11 pm )
Arb.O.P.(Com.Div.) Nos.139
& 253 of 2021
16/23
19. The learned Arbitrator rendered a finding that the amount
towards interest was payable if the payment was made beyond 3 days
after the supply. But, nowhere in the contract or in the tender
conditions, there was any reference to the three days’ time.
20. The learned counsel appearing for the ELCOT submitted that
such a finding rendered by the learned Arbitrator runs contrary to the
contract between the parties and is in violation of Section 28(3) of the
Act. To substantiate this submission, he relied upon the following two
judgments of the Hon’ble Apex Court:
“(i) ONGC Vs. Saw Pipes Ltd.
[reported in 2003 (5) SCC 705] ; and
(ii) OPG Power Generation (P) Ltd.
Vs. Enexio Power Cooling Solutions
(India) (P) Ltd. [reported in 2025 (2)
SCC 417].” https://www.mhc.tn.gov.in/judis ( Uploaded on: 02/12/2025 03:54:11 pm )
Arb.O.P.(Com.Div.) Nos.139
& 253 of 2021
17/23
21. The Hon’ble Apex Court, in the above judgments, held that
the decision taken by the Arbitral Tribunal must be in accordance with
the terms of the contract and that the decision must be taken within
the bounds of its jurisdiction conferred under the Act or the contract. It
was further held that where the Arbitral Tribunal passed an award
against the terms of the contract, the award would be patently illegal.
22. Ordinarily, the terms of the contract should be understood
in the way the parties wanted and intended them to be. However, the
Arbitral Tribunal can read an unexpressed term in the agreement
where there is a basis to come to the conclusion that such a term was
always and obviously intended by the parties thereto. In the absence
of the same, the terms of the contract will have to be understood in
the way, in which, the parties have expressed their intention in the
agreement and if any interpretation is given beyond such intention of
the parties, it cannot even be held to be a possible view. Under such
circumstances, the award will suffer from perversity. https://www.mhc.tn.gov.in/judis ( Uploaded on: 02/12/2025 03:54:11 pm )
Arb.O.P.(Com.Div.) Nos.139
& 253 of 2021
18/23
23. In the case in hand, the learned Arbitrator rendered a finding
that 97% amount to be released towards the respective invoice had to
be released within a period of 3 days. This finding has no basis.
24. The learned Arbitrator rendered a finding that Clause 17(c)
provided that 97% payment would be released by the ELCOT after
successful completion of the supply and acceptance by the respective
institutions.
25. On carefully going through the annexure, this Court is the
considered view that the learned Arbitrator was able to find that there
was substantial delay in releasing the payments. The delay, which
originally started with 16 days, at one stage even reached 336 days.
Therefore, interest can be awarded where there was delay in releasing
the amount within a reasonable time. Even though the contract does
not anywhere provide the time limit for the release of the payment, it
cannot be a reason to deny the claim for interest when the amount
was not released within a reasonable time. https://www.mhc.tn.gov.in/judis ( Uploaded on: 02/12/2025 03:54:11 pm )
Arb.O.P.(Com.Div.) Nos.139
& 253 of 2021
19/23
26. If the ELCOT was in a position to levy liquidated damages
wherever there was a delay in the supply of materials from the bills
that were raised by the UTL, the same concept of delay must also
befall whenever there was a delay in releasing the payment. As per
the relevant clause, the payment had to be released immediately after
the successful completion of the supply and acceptance by the
respective institutions and those particulars were available in the
annexure. Therefore, there had been consistent delay in releasing 97%
payment of the invoice amount. Even if the learned Arbitrator was not
justified in fixing three days’ time, which was nowhere found in the
contract, the intention between the parties to get the amount released
within a reasonable time can always be read into the contract as an
unexpressed term in the contract. Hence, the learned Arbitrator was
justified in awarding interest on the delayed payment of 97% of the
invoice amount.
27. In so far as the interest awarded on the delayed payment of
3% retention amount was concerned, the learned Arbitrator took into
consideration Clause 17(d) of the contract. On the facts of the present https://www.mhc.tn.gov.in/judis ( Uploaded on: 02/12/2025 03:54:11 pm )
Arb.O.P.(Com.Div.) Nos.139
& 253 of 2021
20/23
case, the learned Arbitrator found that there was no issue of any
breach of warranty. Those particulars were available in Annexure II of
the statement of claim.
28. The last issue pertained to interest on delayed payment of
the EMD amount.
29. The learned Arbitrator took into consideration the return of
the EMD amount of Rs.20 lakhs paid by the UTL only on 19.7.2016
under Ex.C.28 and for that delay, the learned Arbitrator granted
payment of interest. Hence, the learned Arbitrator rendered a finding
that the UTL would be entitled to interest of Rs.17,28,87,412/- from
the date of entering into the award till the date of payment at the rate
of 9% per annum. This finding does not suffer from any perversity or
patent illegality warranting the interference of this Court.
30. The particulars that were provided by the UTL, while claiming
interest, were based on the ERP that was maintained by the ELCOT. If
really the ELCOT wanted to contest the claim, they could have resisted https://www.mhc.tn.gov.in/judis ( Uploaded on: 02/12/2025 03:54:11 pm )
Arb.O.P.(Com.Div.) Nos.139
& 253 of 2021
21/23
the claim. However, it is seen that the ELCOT had casually denied this
claim in their statement of defence. Apart from that, they have not let
in any evidence to disprove the facts contained in the annexure. Even
during the cross examination of C.W.1, no questions have been put to
the witness regarding the interest claim.
31. Apart from that, even in the proof affidavit filed by the
ELCOT, there was absolutely no mention about the interest
component. When R.W.1 was cross examined, several questions were
put vide question Nos.52 to 55 on the side of the UTL regarding the
release of payment. Thus, the ELCOT had not effectively questioned or
disproved the claim made by the UTL for interest on the particulars
that were available in the ERP maintained by the ELCOT. In fact, such
a finding has been rendered on appreciation of evidence and it is a
factual finding rendered by the learned Arbitrator.
32. In the light of the above discussions, this Court does not find
any ground to interfere with the award dated 10.3.2021 passed by the
learned Arbitrator. https://www.mhc.tn.gov.in/judis ( Uploaded on: 02/12/2025 03:54:11 pm )
Arb.O.P.(Com.Div.) Nos.139
& 253 of 2021
22/23
33. Accordingly, both the above original petitions stand
dismissed. No costs.
02.12.2025
Index : Yes
Neutral Citation : Yes
RS https://www.mhc.tn.gov.in/judis ( Uploaded on: 02/12/2025 03:54:11 pm )
Arb.O.P.(Com.Div.) Nos.139
& 253 of 2021
23/23
N.ANAND VENKATESH,J
RS
Arb.O.P.(Com.Div.) Nos.139 &
253 of 2021
02.12.2025 https://www.mhc.tn.gov.in/judis ( Uploaded on: 02/12/2025 03:54:11 pm )
Legal Notes
Add a Note....