This appeal challenges the final judgment and order issued by the NCDRC. In that decision, the National Consumer Disputes Redressal Commission (NCDRC) ruled in favor of the complainants (Respondents ...
2025 INSC 143
1
REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO. 3334 OF 2023
GODREJ PROJECTS DEVELOPMENT
LIMITED …APPELLANT(S)
VERSUS
ANIL KARLEKAR & ORS . …RESPONDENT(S)
J U D G M E N T
B.R. GAVAI, J.
1. The present appeal takes exception to the final judgment
and order dated 25
th October, 2022 passed in Consumer
Complaint No. 262 of 2018, whereby the National Consumer
Disputes Redressal Commission (hereinafter, “NCDRC”)
disposed of the Consumer Complaint filed by the Respondents
No. 1 and 2 (hereinafter referred to as, “Complainants” or
“Respondents”) thereby directing the Appellant to deduct only
2
10% of the Basic Sale Price (“BSP” for short) towards
cancellation of the Complainants’ Apartment and refund the
balance amount along with simple interest @ 6% per annum
from the date of each payment till the date of refund. Aggrieved
thereby, the present appeal has been filed under Section 23 of
Consumer Protection Act, 1986.
2. The facts, in brief, giving rise to the present appeal are as
given below.
2.1 On 10
th January, 2014 the Complainants had booked an
Apartment with the Appellant in the project by the name
“Godrej Summit” situated at Sector 104, Gurgaon, Haryana by
an Application Form and submitted Rs. 10,00,000/ - as
application money.
2.2 On 20
th June, 2014 by an allotment letter, the Appellant
allotted an Apartment being Apartment No. C-1501 on the 14
th
floor in Tower ‘C’ to the Complainants in the above-mentioned
project, pursuant to which an Apartment Buyer Agreement
(hereafter referred to as “the Agreement”) was entered into
between the Parties.
3
2.3 On 20
th June, 2017 the Appellant upon completion of
construction applied to and subsequently received the
Occupation Certificate from the Director, Town & Country
Planning Department, Haryana.
2.4 On 28
th June, 2017 the Appellant offered possession to
the Complainants. The Complainants, however, sought
cancellation of the allotment and further sought full refund of
the amount paid.
2.5 On 29
th September, 2017, the Complainants served a
legal notice to the Appellant for refund of the amount paid
totaling Rs. 51,12,310/-.
2.6 Thereafter, on 14
th November, 2017, the Complainants
filed a Consumer Complaint (No. 262 of 2018) before the
NCDRC inter-alia praying that Appellant be directed to refund
the sum totaling Rs. 51,12,310/- paid by the Complainants so
far, with interest @ 18% per annum, calculated from the date
of making each payment till the date of realization of the sum.
2.7 Vide impugned order dated 25
th October, 2022, the
NCDRC disposed of the Consumer Complaint by directing the
Appellant to deduct only 10% of the BSP i.e. Rs. 17,08,140/-
4
only towards cancellation of the Complainants’ Apartment and
refund the balance amount Rs.34,04,170/ - (i.e. Rs.
51,12,310/- minus Rs. 17,08,140/-) along with simple interest
@ 6% per annum from the date of each payment till the date of
refund within three months.
2.8 On 5
th December, 2022, the NCDRC also dismissed the
Review Application filed by the Appellant challenging the
impugned order.
2.9 Aggrieved thereby, on 10
th January 2023 the Appellant
filed the present appeal challenging only the order dated 25
th
October, 2022.
2.10 By an order dated 24
th April, 2023, this Court while
issuing notice had granted stay of the impugned order on the
condition that the Appellant refunds the amount deposited by
the Complainants after deducting 20% (earnest money deposit)
along with interest @ 6% per annum from the date of
cancellation of the contract.
3. We have heard Shri Dhruv Mehta, learned Senior Counsel
appearing on behalf of the Appellant and Shri Ashwarya Sinha,
learned Counsel appearing on behalf of the Respondents.
5
4. Shri Dhruv Mehta submits that the NCDRC has grossly
erred in interfering with the contractual terms as entered into
between the Parties. It is submitted that the Agreement
between the parties specifically provided for a forfeiture clause.
The Agreement provided that the Appellant was entitled to
forfeit the entire earnest money and any other due payable by
the buyer including interest on delayed payment.
5. He further submits that the NCDRC has specifically come
to a conclusion that the Appellant was entitled to cancel the
Apartment and forfeit the amount as per the terms and
conditions of the Application Form and/or the Agreement
between the parties. He submits that having arrived at such a
finding, the NCDRC could not have come to a conclusion that
the condition of forfeiture of 20% of BSP, being the earnest
money liable for forfeiture in case of cancellation, was
unreasonable and interfered with the same by reducing it to
10% of the BSP.
6. He further submits that, from the perusal of the email
addressed by the Respondents to the Appellant, it was clear
that though the Appellant had called upon the Respondents to
6
take possession of the Apartment, they had opted out of the
deal only because there was a recession in the market. He
submits that since the Respondents themselves have cancelled
the deal on account of recession in the market, the Appellant
was fully justified in forfeiting the earnest money deposit.
7. He relies on the judgments of this Court in the cases of
Satish Batra v. Sudhir Rawal
1 and Desh Raj and others v.
Rohtash Singh
2 in support of his submissions.
8. Per contra, Shri Ashwarya Sinha, learned counsel for the
Respondents, relying on the judgments of the NCDRC in the
cases of Komal Aggarwal v. Godrej Projects Development
Ltd.
3, DLF Ltd. v. Bhagwanti Narula
4 and Ramesh
Malhotra and Another v. Emaar Mgf Land Limited and
Another
5, submits that the NCDRC has consistently held that
the condition of forfeiture of 20% of the BSP was not
reasonable and reduced it to 10% of the BSP.
1
(2013) 1 SCC 345
2
(2023) 3 SCC 714
3
Consumer Case No.2139 of 2018 dated 9.11.2022
4
2015 SCC OnLine NCDRC 1613
5
2020 SCC OnLine NCDRC 789
7
9. He further relying on the judgments of this Court in the
cases of Ireo Grace Realtech Private Limited v. Abhishek
Khanna and others
6 and Pioneer Urban Land and
Infrastructure Limited v. Govindan Raghavan
7 submits
that the condition of forfeiture of 20% of the BSP was one-sided
and unconscionable and, therefore, not enforceable in law.
10. He lastly relying on “The Real Estate (Regulation and
Development) Act, 2016” and “The Haryana Real Estate
Regulatory Authority Gurugram (Forfeiture of earnest
money by the builder) Regulations, 2018 ”, submits that in
view of the aforesaid Act and Regulations, the forfeiture of
earnest money deposit cannot be more than 10% of the BSP.
11. In the present case, it is not in dispute that the
Complainants had booked an Apartment with the Appellant for
BSP of Rs.1,70,81,400/- on 10
th January 2014. Accordingly,
an Agreement was entered into between the Appellant and the
Complainants on 20
th June 2014. The Complainants were also
allotted an Apartment on the 14
th Floor in Tower ‘C’ on 20
th
6
(2021) 3 SCC 241
7
(2019) 5 SCC 725
8
June 2014. On 20
th June 2017, the Appellant received the
Occupation Certificate. On 28
th June, 2017, the Appellant
issued an intimation to the Respondents calling upon them to
take possession. However, instead of taking possession, by
email dated 22
nd August 2017/31
st August 2017, the
Respondents refused to take possession and sought
cancellation.
12. The Appellant vide communication dated 1
st September
2017 informed the Respondents that out of the amount
deposited by the Respondents, the Respondents were entitled
to refund of Rs.4,22,845/-. However, the Respondents filed a
complaint seeking refund of an amount of Rs.51,12,310/ -
along with other ancillary reliefs. The NCDRC, as aforesaid,
passed the impugned order.
13. It will be relevant to refer to clauses 2.6 and 8.4 of the
Agreement entered into between the Parties, which read thus:
“2.6 It has been specifically agreed between
the Parties that, 20% of the Basic Sale Price,
shall be considered and treated as earnest
money under this Agreement (“Earnest
Money”), to ensure the performance,
compliance and fulfillment of the obligations
9
and responsibilities of the Buyer under this
Agreement.
It has been made clear by the Developer and
the Buyer has understood that the Sale
Consideration and Statutory Charges as
mentioned in Schedule VI hereto have been
computed on the basis of Super Built Up Area
of the Apartment. The Buyer agrees that the
calculation of Super Built Up Area in respect
of the Apartment is tentative at this stage and
subject to variations till the Completion of
Construction. In case such variations are
beyond +/- 5%, then the Developer shall take
prior consent of the Buyer.
*** *** ***
8.4 On and from the date of such
termination on account of Buyer’s Event of
Default as mentioned above (“Termination
Date”), the Parties mutually agree that-
(i) The Developer shall, out of the entire
amounts paid by the Buyer to the Developer
till the Termination Date, forfeit the entire
Earnest Money and any other dues payable by
the Buyer including interest on delayed
payments as specified in this Agreement.
(ii) After the said forfeiture, the Developer
shall refund the balance amount to the Buyer
or to his banker/financial institution, as the
case may be, without any interest;
(iii) On and from the Termination Date, the
Buyer shall be left with no right, title, interest,
claim, lien, authority whatsoever either in
10
respect of the Apartment or under this
Agreement and the Developer shall be
released and discharged of all its liabilities
and obligations under this Agreement.
(iv) On and from the Termination Date, the
Developer shall be entitled, without any claim
or interference of the Buyer, to convey, sell,
transfer and/or assign the Apartment in
favour of third party(ies) or otherwise deal
with it as the Developer may deem fit and
appropriate, in such a manner that this
Agreement was never executed and without
any claim of the Buyer to any sale proceeds of
such conveyance, sale, transfer and/or
assignment of the Apartment in favour of
third party(ies).”
14. It can thus be seen that as per the Agreement between
the Parties, the Complainants were required to pay earnest
money deposit of 20% of the BSP, which undisputedly has
been paid. As per clause 8.4, on termination on account of
Buyer’s Event of Default, the Developer was entitled to forfeit
the entire earnest money deposit and other dues including
interest on delayed payments as specified in the Agreement.
15. Undisputedly, only upon the Appellant calling upon the
Respondents to take possession, the Respondents informed
the Appellant vide email dated 22
nd August 2017 as under:
11
“Some of the promised connections from
internal roads to externals have been
abandoned. Overall the place falls to invite
you, entice your And the most painful part is
the fact that the market prices have sharply
fallen and a similar flat to a new buyer is
available at a substantially lower price, not
only in secondary market but even by Godrej
themselves. This is unfair, and one feels
cheated that an old customer of 4 years is a
loser compared to the new one. Under the
circumstances, am pained to state that I want
to cancel my booking of the said flat and
demand that the amount paid till date be
refunded along with applicable interest. We
shall appreciate a prompt action on our
request. Kindly share the cancellation
formalities, and the refund amount.”
16. The stand taken by the Respondents was specifically
borne out by the NCDRC from the written statement filed by
the Appellant.
17. It is thus clear that the Respondents had cancelled the
deal since there was recession in the market. Not only that,
but the NCDRC has specifically observed as under:
“Hence, the action of the OPs in cancelling the
apartment and forfeiting the amount as per
terms and conditions of the application form
and/or the BBA cannot be faulted with.
However, the condition of forfeiture of 20% of
BSP, being the earnest money liable for
forfeiture in case of cancellation appears
unreasonable. It will be in the interest of
12
justice and fair play to both sides, if OPs are
allowed to deduct only 10% of the BSP as
earnest money i.e. Rs.17,08,140/- and refund
the balance amount to the complainants.”
18. This Court in the case of Satish Batra v. Sudhir Rawal
(supra), after considering the earlier judgments of this Court,
has observed thus:
“15. The law is, therefore, clear that to justify the
forfeiture of advance money being part of
“earnest money” the terms of the contract should
be clear and explicit. Earnest money is paid or
given at the time when the contract is entered
into and, as a pledge for its due performance by
the depositor to be forfeited in case of non-
performance by the depositor. There can be
converse situation also that if the seller fails to
perform the contract the purchaser can also get
double the amount, if it is so stipulated. It is also
the law that part-payment of purchase price
cannot be forfeited unless it is a guarantee for
the due performance of the contract. In other
words, if the payment is made only towards part-
payment of consideration and not intended as
earnest money then the forfeiture clause will not
apply.
16. When we examine the clauses in the instant
case, it is amply clear that the clause extracted
hereinabove was included in the contract at the
moment at which the contract was entered into.
It represents the guarantee that the contract
would be fulfilled. In other words, “earnest” is
given to bind the contract, which is a part of the
13
purchase price when the transaction is carried
out and it will be forfeited when the transaction
falls through by reason of the default or failure
of the purchaser. There is no other clause that
militates against the clauses extracted in the
agreement dated 29-11-2011.
17. We are, therefore, of the view that the seller
was justified in forfeiting the amount of Rs
7,00,000 as per the relevant clause, since the
earnest money was primarily a security for the
due performance of the agreement and,
consequently, the seller is entitled to forfeit the
entire deposit. The High Court has, therefore,
committed an error in reversing the judgment of
the trial court.”
19. This Court has held that to justify the forfeiture of
advance money being part of “earnest money” the terms of the
contract should be clear and explicit. It has been observed that
the earnest money is paid or given at the time when the
contract is entered into and, as a pledge for its due
performance by the depositor to be forfeited in case of non-
performance by the depositor. However, this Court clarified
that if the payment is made only towards part-payment of
consideration and not intended as earnest money then the
forfeiture clause will not apply.
14
20. Recently, this Court in the case of Desh Raj and others
(supra), after considering the earlier judgments, has reiterated
the aforesaid legal position.
21. We, therefore, find that Shri Dhruv Mehta, learned Senior
Counsel is justified in placing reliance on the aforesaid
judgments of this Court.
22. However, the issue does not rest at that. It will be
relevant to consider the reciprocal obligations of the Appellant
i.e., the Developer in case the Developer does not comply with
the timelines in the Agreement. Clauses 4.2 and 4.3 of the
Agreement are as follows:
“4.2. The Apartment shall be ready for
occupation within 42 months from the date
of issuance of Allotment Letter. (“Tentative
Completion Date"), however the Developer
is entitled for a grace period of 6 months
over and above this 42 month's period.
Upon the Apartment being ready for
possession and occupation the Developer
shall issue the Possession Notice to the
Buyer of the Apartment.
Notwithstanding the above, the Developer
shall be entitled to an extension of time
from the Tentative Completion Date for
issue of the Possession Notice, if the
Completion of Construction of the said
Apartment or the part/portion of the
15
Project where the said Apartment is
situated is delayed on account of any of the
following reasons –
(i) Non-availability of steel, cement,
other building materials, water or
electric supply or labour, or
(ii) Any change in the Applicable Law or
existence of any injunction, stay
order, prohibitory order or directions
passed by any Court, Tribunal, Body
or Competent Authority; or
(iii) Delay in securing any permission,
Approvals, NOC, sanction building
plan, building completion and/or
occupation certificate, water,
electricity, drainage or sewerage
connection from the Competent
Authority for reasons beyond the
control of the Developer, or
(iv) Force Majeure Event or any other
reason (not limited to the reasons
mentioned above) beyond the control
of or unforeseen by the Developer,
which may prevent, restrict, interrupt
or interfere with or delay the
construction of Project on the Subject
Lands or which may prevent the
Developer in performing its
obligations under this Agreement;
16
In case there are is any delay on account of
the aforesaid reasons, the Developer shall
keep the Buyer fully informed about the
same along with a revised tentative date of
possession.
4.3. Subject to the provisions of Clause 4.2
herein above, in the event the Developer
fails or neglects to issue the Possession
Notice on or before the Tentative
Completion Date and/or on such date as
may be extended by mutual consent of the
Parties, then the Developer shall be liable
to pay to the Buyer a compensation for the
entire period of such delay computed at the
rate of Rs. 5/- (Rupees Five only) per
month per square feet of the Super Built
Up Area of the Apartment.
In the alternative, the Developer, at the
request of the Buyer, may refund the total
amounts already received in respect of the
said Apartment together with simple
interest at the rate of 15% per annum to
the Buyer. It has been agreed between the
Parties that upon such repayment, the
Agreement shall stand terminated and the
Buyer shall not be entitled to claim any loss
and/or damages whatsoever. The said
refund by the Developer to the Buyer, sent
through cheque/demand draft by
registered post acknowledgement due or by
courier at the address of the Buyer
mentioned herein, shall be full and final
satisfaction and settlement of all claims of
the Buyer under this Agreement,
irrespective of whether the Buyer
accepts/encashes the said
cheque/demand draft or not. Thereafter
17
the Buyer shall cease to have any interest
or claim on the said Apartment and the
proportionate undivided interest in the
Common Areas and Facilities and Limited
Common Areas and Facilities whatsoever
or howsoever. The Developer thereafter
shall be entitled to sell the said Apartment
along with undivided interest in the
Common Areas and Facilities and Limited
Common Areas and Facilities to any
prospective buyer/third party of its
choice.”
23. If we consider the obligations of the Developer in the event
it does not comply with the timelines, a very meagre
compensation is provided to the Apartment purchaser. Not
only that clause 4.2 of the Agreement, which provides that the
Apartment shall be ready for occupation within 42 months
from the date of issuance of Allotment Letter, also provides that
the Developer would be entitled for a grace period of 6 months
over and above this 42 months’ period. The said clause 4.2
further provides for various eventualities in case of which the
Developer would be entitled to further extension of period for
handing over the possession.
24. In any case, clause 4.3 of the Agreement provides that,
subject to the provisions of clause 4.2 of the Agreement, if the
18
Developer fails or neglects to issue the Possession Notice on or
before the Tentative Completion Date and/or on such date as
may be extended by mutual consent of the Parties, the
Developer shall be liable to pay to the Buyer a meagre
compensation for such a delay at the rate of Rs.5/- per month
per square feet of the Super Built Up Area of the Apartment.
25. It can thus be seen that the Agreement is one-sided and
totally tilted in favour of the Developer.
26. In the case of Central Inland Water Transport
Corporation Limited and Another v. Brojo Nath Ganguly
and Another
8, this Court, by taking recourse to Article 14 of
the Constitution of India, has held that the courts will not
enforce an unfair and unreasonable contract or an unfair and
unreasonable clause in a contract, entered into between
Parties who are not equal in bargaining power. It will be
relevant to refer to the following observations of this Court in
the said case:
“89. ……We have a Constitution for our
country. Our judges are bound by their oath
to “uphold the Constitution and the laws”. The
Constitution was enacted to secure to all the
8
(1986) 3 SCC 156
19
citizens of this country social and economic
justice. Article 14 of the Constitution
guarantees to all persons equality before the
law and the equal protection of the laws. The
principle deducible from the above
discussions on this part of the case is in
consonance with right and reason, intended
to secure social and economic justice and
conforms to the mandate of the great equality
clause in Article 14. This principle is that the
courts will not enforce and will, when called
upon to do so, strike down an unfair and
unreasonable contract, or an unfair and
unreasonable clause in a contract, entered
into between parties who are not equal in
bargaining power. It is difficult to give an
exhaustive list of all bargains of this type. No
court can visualize the different situations
which can arise in the affairs of men. One can
only attempt to give some illustrations. For
instance, the above principle will apply where
the inequality of bargaining power is the
result of the great disparity in the economic
strength of the contracting parties. It will
apply where the inequality is the result of
circumstances, whether of the creation of the
parties or not. It will apply to situations in
which the weaker party is in a position in
which he can obtain goods or services or
means of livelihood only upon the terms
imposed by the stronger party or go without
them. It will also apply where a man has no
choice, or rather no meaningful choice, but to
give his assent to a contract or to sign on the
dotted line in a prescribed or standard form or
to accept a set of rules as part of the contract,
however unfair, unreasonable and
unconscionable a clause in that contract or
form or rules may be. This principle, however,
20
will not apply where the bargaining power of
the contracting parties is equal or almost
equal. This principle may not apply where
both parties are businessmen and the
contract is a commercial transaction.”
27. This Court in the case of Pioneer Urban Land and
Infrastructure Limited (supra) was considering similar
clauses in an Agreement between a Developer and an
Apartment Purchaser. This Court observed thus:
“6.4. A perusal of the apartment buyer's
agreement dated 8-5-2012 reveals stark
incongruities between the remedies available
to both the parties. For instance, Clause 6.4(ii)
of the agreement entitles the appellant builder
to charge interest @18% p.a. on account of
any delay in payment of instalments from the
respondent flat purchaser. Clause 6.4(iii) of
the agreement entitles the appellant builder to
cancel the allotment and terminate the
agreement, if any instalment remains in
arrears for more than 30 days. On the other
hand, as per Clause 11.5 of the agreement, if
the appellant builder fails to del iver
possession of the apartment within the
stipulated period, the respondent flat
purchaser has to wait for a period of 12
months after the end of the grace period,
before serving a termination notice of 90 days
on the appellant builder, and even thereafter,
the appellant builder gets 90 days to refund
only the actual instalment paid by the
respondent flat purchaser, after adjusting the
21
taxes paid, interest and penalty on delayed
payments. In case of any delay thereafter, the
appellant builder is liable to pay interest @9%
p.a. only.
6.5. Another instance is Clause 23.4 of the
agreement which entitles the appellant
builder to serve a termination notice upon the
respondent flat purchaser for breach of any
contractual obligation. If the respondent flat
purchaser fails to rectify the default within 30
days of the termination notice, then the
agreement automatically stands cancelled,
and the appellant builder has the right to
forfeit the entire amount of earnest money
towards liquidated damages. On the other
hand, as per Clause 11.5(v) of the agreement,
if the respondent flat purchaser fails to
exercise his right of termination within the
time limit provided in Clause 11.5, then he
shall not be entitled to terminate the
agreement thereafter, and shall be bound by
the provisions of the agreement.
6.6. Section 2(1)(r) of the Consumer
Protection Act, 1986 defines “unfair trade
practices” in the following words:
“2.(1)(r) “unfair trade practice” means a
trade practice which, for the purpose of
promoting the sale, use or supply of any goods
or for the provision of any service, adopts any
unfair method or unfair or deceptive
practice.…”,
22
and includes any of the practices enumerated
therein. The provision is illustrative, and not
exhaustive.
xxx xxx xxx
6.8. A term of a contract will not be final and
binding if it is shown that the flat purchasers
had no option but to sign on the dotted line,
on a contract framed by the builder. The
contractual terms of the agreement dated 8-
5-2012 are ex facie one-sided, unfair and
unreasonable. The incorporation of such one-
sided clauses in an agreement constitutes an
unfair trade practice as per Section 2(1)(r) of
the Consumer Protection Act, 1986 since it
adopts unfair methods or practices for the
purpose of selling the flats by the builder.
7. In view of the above discussion, we have no
hesitation in holding that the terms of the
apartment buyer's agreement dated 8-5-2012
were wholly one-sided and unfair to the
respondent flat purchaser. The appellant
builder could not seek to bind the respondent
with such one-sided contractual terms.”
28. The view taken by this Court in the case of Pioneer Urban
Land and Infrastructure Limited (supra) was followed in the
case of Wing Commander Arifur Rahman Khan and Aleya
Sultana and others v. DLF Southern Homes Private
Limited (Now Known as Begur OMR Homes Private Limited)
23
and others
9.
29. Further, a three-judge Bench of this Court in the case of
Ireo Grace Realtech Private Limited (supra) approved the
legal position as laid down in the case of Pioneer Urban Land
and Infrastructure Limited (supra).
30. It is further to be noted that when the cases of Pioneer
Urban Land and Infrastructure Limited (supra), Wing
Commander Arifur Rahman Khan and Aleya Sultana and
others (supra) and Ireo Grace Realtech Private Limited
(supra) were decided, they were decided based on the
provisions of the Consumer Protection Act, 1986. Relying on
the provisions of Section 2(1)(r) of the Consumer Protection
Act, 1986, which defines the term “unfair trade practice”, this
Court held that the contractual terms which are ex facie one-
sided, unfair and unreasonable would constitute unfair trade
practice as per the aforesaid definition of “unfair trade
practice”.
31. Now, Parliament in 2019 has enacted the Consumer
Protection Act, 2019, which has specifically provided a
9
(2020) 16 SCC 512
24
definition for “unfair contract”. It will be apposite to refer to the
relevant part of clause (46) of Section 2 of the Consumer
Protection Act, 2019, which reads thus:
2. Definitions.- In this Act, unless the
context otherwise requires,-
xxx xxx xxx
(46) “unfair contract” means a contract
between a manufacturer or trader or
service provider on one hand, and a
consumer on the other, having such terms
which cause significant change in the
rights of such consumer, including the
following, namely:-
(i) requiring manifestly excessive
security deposits to be given by a
consumer for the performance of
contractual obligations; or
(ii) imposing any penalty on the
consumer, for the breach of contract
thereof which is wholly
disproportionate to the loss occurred
due to such breach to the other party
to the contract; or
xxx xxx xxx
(vi) imposing on the consumer any
unreasonable charge, obligation or
condition which puts such consumer
to disadvantage;”
25
32. No doubt that the aforesaid definition would be applicable
after the Consumer Protection Act, 2019 came into effect,
however, even prior to that while considering the term “unfair
trade practice”, this Court has found that such one-sided
Agreements, as in the present case, would be covered by the
definition of term “unfair trade practice”.
33. Insofar as the judgment in the case of Satish Batra
(supra) is concerned, the clause providing for “forfeiture of
earnest money deposit” cannot be said to be one-sided. It will
be relevant to refer to the term which fell for consideration
before this Court in the aforesaid case, which reads thus:
“(e) If the prospective purchaser fails to
fulfil the above condition, the transaction
shall stand cancelled and earnest money
will be forfeited. In case I fail to complete
the transaction as stipulated above, the
purchaser will get double the amount of
the earnest money. In both conditions,
the dealer will get 4% commission from
the faulting party.”
34. It can thus be seen that in the aforesaid case though the
term in the Agreement provided for forfeiture of the earnest
money in the event the prospective purchaser fails to fulfill the
26
conditions, it also provided for payment of double the amount
of earnest money by the vendor to the purchaser in case the
vendor fails to complete the transaction. As such, the said
term cannot be said to be one-sided.
35. Similarly, in the case of Desh Raj and others (supra),
this Court was considering an Agreement to Sell with respect
to the landed property. A perusal of the judgment would reveal
that it was a case of an Agreement between two equal Parties
and there are no terms in the Agreement which could be said
to be one-sided and tilted totally in favour of one of the Parties.
36. We are, therefore, of the view that the present case would
not be governed by the law laid down by this Court in the cases
of Satish Batra (supra) and Desh Raj and others (supra), but
would be governed by the law as laid down in the cases of
Pioneer Urban Land and Infrastructure Limited (supra),
Wing Commander Arifur Rahman Khan and Aleya
Sultana and others (supra) and Ireo Grace Realtech
Private Limited (supra).
37. It will further be relevant to refer to the following
observations by a Bench consisting of three learned Judges of
27
this Court in the case of Maula Bux v. Union of India
10:
5. Forfeiture of earnest money under a
contract for sale of property — Movable or
immovable — If the amount is reasonable,
does not fall within Section 74. That has
been decided in several cases: Chiranjit
Singh v. Har Swarup; Roshan Lal v. Delhi
Cloth and General Mills Company Ltd.
Delhi [1910 SCC OnLine All 98 : ILR (1911)
33 All 166] ; Mohd Habibullah v. Mohd
Shafi [1919 SCC OnLine All 87 : ILR 41 All
324] ; Bishan Chand v. Radhakishan Das.
[1897 SCC OnLine All 52 : ILR (1897) 19
All 490] These cases are easily explained,
for forfeiture of reasonable amount paid as
earnest money does not amount to
imposing a penalty. But if forfeiture is of
the nature of penalty. Section 74 applies.
Where under the terms of the contract the
party in breach has undertaken to pay a
sum of money or to forfeit a sum of money
which he has already paid to the party
complaining of a breach of contract, the
undertaking is of the nature of a penalty.”
38. It can be seen that this Court has held that if the
forfeiture of earnest money under a contract is reasonable,
then it does not fall within Section 74 of the Indian Contract
Act, 1872, inasmuch as, such a forfeiture does not amount to
imposing a penalty. It has further been held that, however, if
10
(1969) 2 SCC 554
28
the forfeiture is of the nature of penalty, then Section 74 would
be applicable. This Court has further held that under the
terms of the contract, if the party in breach undertook to pay
a sum of money or to forfeit a sum of money which he ha d
already paid to the party complaining of a breach of contract,
the undertaking is of the nature of a penalty.
39. Relying on the aforesaid observations of this Court, the
NCDRC, in a series of cases right from the year 2015, has held
that 10% of the BSP is a reasonable amount which is liable to
be forfeited as earnest money. The NCDRC has initially taken
this view in the case of DLF Ltd. v. Bhagwanti Narula
(supra). The said view has been followed subsequently in
various judgments of the NCDRC. We see no reason to upset
the view consistently taken by the NCDRC based on the
judgment of this Court in the case of Maula Bux (supra).
40. Though we are not inclined to interfere with the direction
of the NCDRC for refund of the amount in excess of 10% of the
BSP, we however find that the NCDRC was not justified in
awarding interest on the amount to be refunded.
41. As has been pointed out herein above, after the
29
Agreement was entered into between the Parties in the year
2014, only after the possession was offered by the Appellant to
the Respondents, they sought cancellation of the allotment.
The reason given by them is that on account of sharp decline
in the prices, a person would be able to buy a flat at a
substantially lower price even in Primary market.
42. It is quite probable that the Respondents would have
utilised the money which was payable by them to the Appellant
for purchasing another property at a lower rate.
43. In the facts and circumstances, therefore, we find that the
NCDRC was not justified in awarding interest on the amount
to be refunded by the Appellant.
44. In pursuance of our order dated 24
th April 2023, the
Appellant has refunded an amount of Rs.22,01,215/- to the
Respondents. After deducting an amount of Rs.17,08,140/-
(i.e. 10% of the BSP) from Rs.51,12,310/- (amount paid by the
Respondents to the Appellant) , the amount comes to
Rs.34,04,170/-. The Appellant is, therefore, required to pay
balance amount of Rs.12,02,955/ - [Rs.34,04,170/- minus
Rs.22,01,215/-] to the Respondents. We, therefore, direct the
30
Appellant to pay the said amount of Rs.12,02,955/- to the
respondents within a period of six weeks from today.
45. The appeal is partly allowed in the above terms.
46. Pending application(s), if any, shall stand disposed of.
..............................J
(B.R. GAVAI)
..............................J
(S.V.N. BHATTI)
NEW DELHI;
FEBRUARY 03, 2025
Legal Notes
Add a Note....