Writ Petition, Condonation of Delay, Consumer Protection Act, Limitation Act, Bombay High Court, Godrej Projects, Flat Allotment, Forfeiture
 02 Jul, 2026
Listen in 01:07 mins | Read in 27:00 mins
EN
HI

Godrej Projects Development Ltd. Vs. R.K.Ramani, and Jayanti Ramani

  Bombay High Court WP 9689 OF 2025
Link copied!

Case Background

As per case facts, the Petitioner, a developer, terminated a flat allotment and forfeited the paid amount, citing default from the complainants. The complainants challenged this, initially filing a complaint ...

Bench

Applied Acts & Sections

No Acts & Articles mentioned in this case

Hello! How can I help you? 😊
Disclaimer: We do not store your data.
Document Text Version

wp 9689 of 2025.doc

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

CIVIL APPELLATE JURISDICTION

WRIT PETITION NO.9689 OF 2025

Godrej Projects Development Ltd. ... Petitioner

versus

R.K.Ramani, and

Jayanti Ramani … Respondents

Mr. Mayur Khandeparkar with Mr. Sunil A. Vyas, Ms. Rishika Virwadia, Ms.

Sakshi Verma, Ms. Sonam Singh i/by Fox Mandal and Associates LLP, for

Petitioner.

Ms. Ami Mandani, for Respondent No.2.

CORAM: N.J.JAMADAR, J.

RESERVED ON : 24 JUNE 2026

PRONOUNCED ON : 2 JULY 2026

JUDGMENT :

1. Rule. Rule made returnable forthwith, and, with the consent of the

learned Counsel for the parties, heard finally.

2. This petition under Article 227 of the Constitution of India assails an

order dated 26 May 2025 passed by the State Consumer Disputes Redressal

Commission, Maharashtra (the State Commission) in Revision Petition

No.RP/25/2, whereby the revision preferred by the Petitioner – original

opposite party against an order dated 6 August 2024 passed by the District

Consumer Disputes Redressal Commission (the District Commission) in

MA/22/29, thereby condoning the delay in filing the complaint, came to be

dismissed, observing, inter alia, that the period during which the complaint

SSP 1/18

SWAROOP

SHARAD

PHADKE

Digitally

signed by

SWAROOP

SHARAD

PHADKE

Date:

2026.07.02

19:36:54

+0530

wp 9689 of 2025.doc

was pending before the State Commission was required to be excluded and,

in the interest of justice, delay deserved to be condoned by adopting a liberal

approach.

3. Background facts leading to this petition can be stated, in brief, as

under :

3.1 Respondent Nos.1 and 2 – complainants had booked a flat being 103,

C Wing, Godrej Central project, developed by the Petitioner for an aggregate

consideration of Rs.2,19,55,239/-. The complainants had parted with part

consideration of Rs.45,15,844/-. Allotment letter was issued by the Petitioner

to the complainants. The Petitioner claimed that there was default on the part

of the complainants to pay the balance consideration, despite repeated

remainders to make the payment in accordance with the terms of the

agreement between the parties. Thus, the Petitioner professed to terminate

the allotment and proceed to forfeit an amount of Rs.45,15,844/- paid by the

complainants.

3.2 The complainants responded to the said termination letter and

questioned the legality and propriety of the said course. Eventually, the

complainants filed original Complaint No.18/685, along with MA No.18/288

seeking condonation of delay in preferring the complaint, on 13 August 2018,

before the State Commission. By an order dated 16 April 2019, the State

Commission returned the complaint along with the application for condonation

SSP 2/18

wp 9689 of 2025.doc

of delay for filing the same before the proper forum opining that the State

Commission has no pecuniary jurisdiction to entertain the complaint and it

was required to be filed before the District Commission.

3.3 The Petitioner asserts, the complainants committed default in

presenting the complaint before the proper forum within the period of one

month, as directed by the State Commission. Instead, a fresh complaint being

No.CC/22/185, was filed before the District Commission purportedly under

Section 34 of the Consumer Protection Act, 2019 (the CP Act, 2019) along

with an application for condonation of delay of 76 days, though the actual

delay was of 1192 days.

3.4 The Petitioner resisted the said application.

3.5 By an order dated 6 August 2024, the District Commission

condoned the delay observing that, on account of the presentation of the

complaint initially in a forum which was found to have no pecuniary jurisdiction

and the subsequent presentation of the complaint before the District

Commission, the delay deserved to be condoned.

3.6 Being aggrieved, the Petitioner preferred a revision before the State

Commission.

3.7 By the impugned judgment and order, the State Commission concurred

with the view of the District Commission. It was of the view that the

expression “sufficient cause” was required to be construed liberally and, in the

SSP 3/18

wp 9689 of 2025.doc

facts of the case, the delay deserved to be condoned.

3.8 Being further aggrieved, the opposite party has invoked the writ

jurisdiction.

3.9 During the pendency of the Petition, Respondent No.1 has passed

away.

4. I have heard Mr. Mayur Khandeparkar, learned Counsel for the

Petitioner, and Ms. Mandani, learned Counsel for the Respondent No.2, at

some length. With the assistance of the learned Counsel for the parties, I

have perused the material on record.

5. Mr. Khandeparkar, learned Counsel for the Petitioner, submitted that

there is no power to condone the inordinate delay if the party seeking

condonation of delay fails to ascribe any reason. The computation of the

period of delay of 76 days only, by the complainants was clearly erroneous. In

fact, there was a delay of 1192 days. Emphasis was laid by M r.

Khandeparkar on the fact that the first complaint itself was lodged after the

period of limitation of two years had expired since the termination of the

allotment. Secondly, the complainants were not entitled to have the benefit of

the provision of exclusion of time, as envisaged by Section 14(1)(3) of the

Limitation Act, 1963, as there was complete failure on the part of the

complainant to present the complaint within the period of one month as

directed by the State Commission. The reasons ascribed by the complainants

SSP 4/18

wp 9689 of 2025.doc

for the delay are ex-facie unsustainable to condone huge delay of 1192 days.

6. To buttress the submission that the delay cannot be condoned in the

absence of reasons having been ascribed by the party seeking condonation

of delay, Mr. Khandeparkar placed reliance on the judgment of the Supreme

Court in the case of State of Nagaland V/s. Lipok AO and Ors.

1

.

7. Mr. Khandeparkar would urge, the complaint that was presented before

the District Commission pursuant to the liberty granted by the State

Commission while returning the complaint was not the same complaint which

was returned by the State Commission. No complaint was filed before the

District Commission on 22 July 2022. In such a case, the said complaint

before the District Commission cannot be said to be a continuation of the

complaint which was initially filed before the State Commission. To this end,

Mr. Khandeparkar placed reliance on a judgment of the Supreme Court in the

case of Sri Amar Chand Inani V/s. Union of India

2

.

8. In contrast to this, Ms. Mandani, learned Counsel for Respondent No.2

would submit that the resistance to the condonation of delay on the part of the

Petitioner who has obtained huge amount of Rs.45,15,844/- and reneged

from the contractual obligation, is wholly iniquitous. Complainant No.2 and the

deceased Complainant No.1 were always ready to pay the balanc e

consideration. However, the Petitioner failed to execute registered agreement

1 (2005) 3 SCC 752

2 (1973) 1 SCC 115

SSP 5/18

wp 9689 of 2025.doc

in favour of the complainants, and, therefore, the complainants were insisting

upon the execution of the registered agreement in conformity with the

provisions of the the Maharashtra Ownership Flats (Regulation of the

Promotion of Construction, Sale, Management and Transfer) Act, 1963. Thus,

the unilateral termination of the allotment was completely unjust and illegal.

This backdrop needs to be kept in view while appreciating the challenge to

the order of condoning the delay, submitted Ms. Mandani.

9. Ms. Mandani controverted the submissions on behalf of the Petitioner

that the cause of action arose on the date of issuance of the termination letter.

It was submitted that the cause of action arose on the last of the

communication emanating from the opposite party, which indicates a clear

refusal of the performance of the contractual obligations. Ms. Mandani also

urged that there was no deliberate delay on the part of the complainants to

present the complaint before the District Commission after the complaint was

returned by the State Commission. The original record and proceeding and

the court fees were not returned to the complainants within a reasonable

period. The complainants had to resort to the provisions contained in Right to

Information Act, to obtain the papers and proceedings and secure refund of

the court fees. Thus, there was a delay; which, in the circumstances of the

case, according to Ms. Mandani, deserves to be condoned. L est the

complainants would be rendered remediless.

SSP 6/18

wp 9689 of 2025.doc

10. To bolster up the aforesaid submissions, Ms. Mandani placed reliance

on the judgments of the Supreme Court in the cases of Purni Devi and Anr.

V/s. Babu Ram and Anr.

3

; Ram Ujarey V/s. Union of India

4

and the decision

of this Court in Vilas Tukaram Chavan V/s. Suresh Bhanudas Kulkarni and

Ors.

5

and that of Chhattisgarh High Court in the case of Chairman,

Chhattisgarh State Electricity Board and Anr. V/s. Ghasiram and Ors.

6

11. To begin with few uncontroverted facts. Firstly, the fact that the

complainants had booked Flat No. 103, C Wing, Godrej Central project

developed by the Petitioner is not in dispute. Secondly, the Petitioner had

indisputably issued allotment letter on 10 August 2015. Thirdly, it is

incontrovertible that the complainants had paid a sum of Rs.45,15,844/- to the

Petitioner. Fourthly, by a letter dated 28 January 2016, the Petitioner

professed to terminate the allotment purportedly for the reason that the

complainants did not pay the balance amount in terms of the contract

between the parties, despite ample opportunity. Fifthly, there was exchange

of correspondence, and, eventually, the first complaint bearing No.18/685 was

filed on 13 August 2018 before the State Commission. Indisputably, the State

Commission returned the complaint along with the application for condonation

of delay for presentation to the proper forum on 16 April 2019. The

3 2024 SCC Online SC 482

4 (1999) 1 SCC 685

5 SA No.329 of 2021 dt. 19April 2023

6 FA No.68 of 2009 dt. 15 Oct. 2011

SSP 7/18

wp 9689 of 2025.doc

complainants were directed to submit the complaint before the appropriate

forum, within a period of one month. Lastly, the complaint was eventually filed

on 22 July 2022.

12. In the backdrop of the aforesaid facts, it is rather indisputable that the

complainants had originally lodged the complaint before the State

Commission and that remained on the file on the State Commission till it was

returned for want of pecuniary jurisdiction, on 16 April 2019. Whether the

complainants are entitled to the benefit of the provisions contained in Section

14 of the Limitation Act, 1963, thus, deserves consideration.

13. Section 14 provides for exclusion of time of proceeding bonafide in

Court without jurisdiction. In the case of Consolidated Engg. Enterprises

V/s. Principal Secy. Irrigation Department

7

, the Supreme Court postulated

the conditions which are required to be satisfied before a party could avail the

benefit of the exclusion of time as envisaged by Section 14. Para 21 of the

judgment in the said case reads as under :

“21. Section 14 of the Limitation Act deals with exclusion of

time of proceeding bona fide in a court without jurisdiction.

On analysis of the said section, it becomes evident that the

following conditions must be satisfied before section 14 can

be pressed into service :

(1) Both the prior and subsequent proceedings are civil

proceedings prosecuted by the same party;

(2) The prior proceeding had been prosecuted with due

7 (2008) 7 SCC 169

SSP 8/18

wp 9689 of 2025.doc

diligence and in good faith;

(3) The failure of the prior proceeding was due to defect

of jurisdiction or other cause of like nature;

(4) The earlier proceeding and the latter proceeding must

relate to the same matter in issue; and

(5) Both the proceedings are in a court”

14. In the said case, the Supreme Court further enunciated that the

provisions of Section 14 must be interpreted and applied in a manner that

furthers the cause of justice, rather than aborts the proceedings at hand and

the time taken in diligently pursuing a remedy, in a wrong court, should be

excluded.

15. In the case at hand, it is necessary to note, there is no qualm over the

point that the conditions enumerated above were fulfilled. The controversy

essentially revolves around the time consumed by the complainants in filing

the complaint before the District Commission after the complaint was returned

by the State Commission. In the application for condonation of delay before

the District Commission, it was averred that the cause of action arose on 26

July 2017, the day petitioner vide reply dated 26 July 2017 to the legal notice

issued by the complainants justified the termination of the allotment and the

forfeiture of the amount.

16. Mr. Khandeparkar would urge that, in the original complaint No.18/685,

it was contended that the original complaint was filed along with an

SSP 9/18

wp 9689 of 2025.doc

application for condonation of delay on the premise that the cause of action

arose on 28 January 2016, the day the termination letter was issued. Thus,

the assertion in the fresh complaint filed before the District Commission that

the cause of action arose on 26 July 2017 was demonstrably incorrect. In

any event, Mr. Khandeparkar would urge, the cause of action would not arise

from the date of reply to the legal notice as the allotment was terminated by a

letter dated 28 January 2016.

17. In the application for condonation of delay filed before the District

Commission it was averred that, after the State Commission returned the

complaint by an order dated 16 April 2019, despite follow-up, the file was not

traceable. Eventually, an application was required to be made under RTI Act,

and, thereafter, the complaint filed before the State Commission was

returned. Covid-19 intervened. The complainants being the senior citizens

were cautious with their movements. The deceased complainant No.1 was

infected with Covid-19 on 27 June 2022. Eventually, after recovery, the

complainants lodged the complaint.

18. In the backdrop of the aforesaid assertions and having regard to the

period of delay in filing the complaint after the return of the complaint by the

State Commission, the question as to when the cause of action first arose,

pales in significance. The delay in lodging the complaint before the State

Commission was relatively of lesser duration i.e. 7 and half months. Thus, the

SSP 10/18

wp 9689 of 2025.doc

controversy boils down to the question whether the reasons ascribed in the

application for condonation of delay in filing the complaint before the District

Commission constituted sufficient cause.

19. Before exploring an answer on facts, it would be advantageous to note

the difference in the approach expected of the superior Court in the case

where the Court of first instance has exercised discretion to condone the

delay, and, in the case where the Court of first instance has declined to

condone the delay. There is subtle yet significant difference in the way the

superior Court ought to approach the two distinct situations. In a case where

the Court of first instance has condoned the delay, the revisional or superior

court ought to be loath to interfere in the exercise of positive discretion, unless

the Court finds that the discretion has been exercised though no reasons

were ascribed for condonation of delay or the order is otherwise perverse. In

the latter case, where the Court of first instance has refused to condone the

delay, the entire matter is open before the superior Court, and, it would be

permissible to examine the justifiability of the reasons ascribed for the

condonation of delay afresh to determine whether the delay deserves to be

condoned.

20. It is also trite that the expression “sufficient cause” often receives liberal

consideration so as to advance the cause of substantive justice. The over-

arching principle that informs such liberal consideration is that, the procedure,

SSP 11/18

wp 9689 of 2025.doc

being a handmaid of justice, should not be allowed to score a march over the

substantive justice. If there is no lack of bonafide or intentional or deliberate

delay, the application for condonation of delay deserves a liberal

consideration.

21.A useful reference in this context can be made to the judgment of the

Supreme Court in the case of N. Balakrishnan V/s. M. Krishnamurthy 

8

wherein the law was enunciated as under:

“9. It is axiomatic that condonation of delay is a matter of

discretion of the court Section 5 of the Limitation Act does not

say that such discretion can be exercised only if the delay is

within a certain limit. Length of delay is no matter, acceptability

of the explanation is the only criterion. Sometimes delay of the

shortest range may be uncondonable due to want of acceptable

explanation whereas in certain other cases delay of very long

range can be condoned as the explanation thereof is

satisfactory. Once the court accepts the explanation as sufficient

it is the result of positive exercise of discretion and normally the

superior court should not disturb such finding, much less in

reversional jurisdiction, unless the exercise of discretion was on

whole untenable grounds or arbitrary or perverse. But it is a

different matter when the first cut refuses to condone the delay.

In such cases, the superior cut would be free to consider the

cause shown for the delay afresh and it is open to such superior

court to come to its own finding even untrammeled by the

conclusion of the lower court.

8 (1998) 7 SCC 123

SSP 12/18

wp 9689 of 2025.doc

10.The reason for such a different stance is thus:

The primary function of a court is to adjudicate the

dispute between the parties and to advance substantial justice.

Time limit fixed for approaching the court in different situations in

not because on the expiry of such time a bad cause would

transform into a good cause.

11.Rules of limitation are not meant to destroy the right of

parties. They are meant to see that parties do not resort to

dilatory tactics, but seek their remedy promptly. the object of

providing a legal remedy is to repair the damage caused by

reason of legal injury. Law of limitation fixes a life-span for such

legal remedy for the redress of the legal injury so suffered. Time

is precious and the wasted time would never revisit. During

efflux of time newer causes would sprout up necessitating newer

persons to seek legal remedy by approaching the courts. So a

life span must be fixed for each remedy. Unending period for

launching the remedy may lead to unending uncertainty and

consequential anarchy. Law of limitation is thus founded on

public policy. It is enshrined in the maxim Interest reipublicae up

sit finis litium (it is for the general welfare that a period be putt to

litigation). Rules of limitation are not meant to destroy the right of

the parties. They are meant to see that parties do not resort to

dilatory tactics but seek their remedy promptly. The idea is that

every legal remedy must be kept alive for a legislatively fixed

period of time.

12.A court knows that refusal to condone delay would result

foreclosing a suitor from putting forth his cause. There is no

presumption that delay in approaching the court is always

deliberate. This Court has held that the words "sufficient cause"

SSP 13/18

wp 9689 of 2025.doc

under Section 5 of the Limitation Act should receive a liberal

construction so as to advance substantial justice vide

Shakuntala Devi Jain V/s. Kuntal Kumari (AIR 1969 SC 575)

and State of W.B. V/s. Administrator, Howrah Municipality

((1972) 1 SC 366).

13.It must be remembered that in every case of delay there can

be some lapse on the part of the litigant concerned. That alone

is not enough to turn down his plea and to shut the door against

him. If the explanation does not smack of mala fides or it is not

put forth as part of a dilatory strategy the court must show

utmost consideration to the suitor. But when there is reasonable

ground to think that the delay was occasioned by the party

deliberately to gain time then the court should lean against

acceptance of the explanation. While condoning delay the Could

should not forget the opposite party altogether. It must be borne

in mind that he is a looser and he too would have incurred quiet

a large litigation expenses. It would be a salutary guideline that

when courts condone the delay due to laches on the part of the

applicant the court shall compensate the opposite party for his

loss.”

(emphasis supplied)

22. In the case of State of Nagaland V/s. Lipok AO and Ors. (supra), on

which reliance was placed by Mr. Khandeparkar, the Supreme Court after

adverting to the previous pronouncements, including the aforesaid decision

in the case of N. Balakrishnan (supra), enunciated that :

“12…...The the expression “sufficient cause” is adequately

elastic to enable the court to apply the law in a meaningful

manner which subserves the ends of justice - that being the

SSP 14/18

wp 9689 of 2025.doc

life-purpose for the existence of the institution of courts. It is

common knowledge that this Court has been making a

justifiably liberal approach in matters instituted in this Court.

But the message does not appear to have percolated down

to all the other courts in the hierarchy. This Court reiterated

that the expression "every day's delay must be explained"

does not mean that a pedantic approach should be made.

The doctrine must be applied in a rational common sense

pragmatic manner. When substantial justice and technical

considerations are pitted against each other, cause of

substantial justice deserves to be preferred for the other

side cannot claim to have vested right in injustice being

done because of a non-deliberate delay. There is no

presumption that delay is occasioned deliberately, or on

account of culpable negligence, or on account of mala fides.

A litigant does not stand to benefit by resorting to delay. In

fact he runs a serious risk. Judiciary is not respected on

account of its power to legalise injustice on technical

grounds but because it is capable of removing injustice and

is expected to do so.”

23. It is equally true that the delay cannot be condoned if the party seeking

condonation of delay fails to offer a reasonable and rational explanation.

Delay cannot be condoned as a matter of generosity. Length of delay does

bear upon the exercise of discretion, though it would be harsh to expect a

litigant to account for each day’s delay. A useful reference can be made to

the judgment of the Supreme Court in the case of Basawaraj and Anr. V/s.

SSP 15/18

wp 9689 of 2025.doc

Special Land Acquisition Officer

9

wherein the Supreme Court enunciated

the law as under :

“15. The law on the issue can be summarised to the effect

that where a case has been presented in the court beyond

limitation, the applicant has to explain the court as to what

was the “sufficient cause” which means an adequate and

enough reason which prevented him to approach the court

within limitation. In case a party is found to be negligent, or for

want of bonafide on his part in the facts and circumstances of

the case, or found to have not acted diligently or remained

inactive, there cannot be a justified ground to condone the

delay. No court could be justified in condoning such an

inordinate delay by imposing any condition whatsoever. The

application is to be decided only within the parameters laid

down by this court in regard to the condonation of delay. In

case there was no sufficient cause to prevent a litigant to

approach the court on time condoning the delay without any

justification, putting any condition whatsoever, amounts to

passing an order in violation of the statutory provisions and it

tantamounts to showing utter disregard to the legislature”.

24. On the touchstone of the aforesaid principles, reverting to the facts of

the case at hand, this Court finds that the claim of the complainants that they

could not obtain the original complaint and the court fee refund, which they

insisted for, after the State Commission directed return of the complaint,

finds support in the contemporaneous documents. It appears that the

9 (2013) 14 scc 81

SSP 16/18

wp 9689 of 2025.doc

documents were furnished to the complainants under the RTI on 5 April

2022. Those documents reveal that, in view of the application of the

complainants for return of the court fee paid on the complaint, which was

ordered to be returned, the orders of the then President of the State

Commission were obtained and it was informed on 27 January 2022 that the

Court fee cannot be refunded. These documents, prima facie, indicate that

the complainants were pursuing claim for refund of court fee. It thus implies

that, by that time, the original complaint preferred before the State

Commission was not returned.

25. Secondly, the exigency of the situation that arose on account of Covid-

19 Pandemic, is a matter of record. Pursuant to the orders passed by the

Supreme Court in Suo Motu Writ Petition (Civil) No.3 of 2020, limitation was

suspended from 15 March 2020 to 28 February 2022. Thirdly, it appears that

the complainant No.1 was unwell since 27 June 2022, as he was allegedly

infected with Covid-19 contagion. Medical certificate was annexed to the

application to support the said claim.

26. In view of the aforesaid nature of the documents and the material

pressed into service on behalf of the complainants, I find it rather difficult to

accede to the submission on behalf of the Petitioner that, no reasons were

ascribed for the delay. The broad situation that emerges is also required to

be kept in view. Complainant No.2, who has lost her husband – complainant

SSP 17/18

wp 9689 of 2025.doc

No.1, is pursuing the proceedings taking umbrage at the forfeiture of the sum

of Rs.45,15,844/- deposited by them in the year 2015 towards part

consideration. Evidently, no agreement for sale was registered in conformity

with the obligation of the Promoter under MOFA, 1963. Complainant No.2 is

left to wage a battle against the Petitioner, an established prayer in the real

estate sector. The Complaint No. 2 is primarily seeking the refund of the part

consideration i.e. Rs.45,15,844/-, which is a significant amount. Thus, on

balance, this Court is of the considered view that, prima facie, justice of the

case lies in favour of the Complainant.

27. For the foregoing reasons, this Court in exercise of the supervisory

jurisdiction does not find any justifiable reason to interfere with the exercise

of the positive discretion to condone the delay by the District Commission,

which order has been affirmed by the State Commission. The Writ Petition,

therefore, deserves to be dismissed.

28. Hence, the following order :

ORDER

(i) The Writ Petition stands dismissed with cosrts.

(ii) Rule discharged.

( N.J.JAMADAR, J. )

SSP 18/18

Reference cases

Description

Navigating Consumer Disputes: The Bombay High Court's Stance on Delay Condonation

The recent ruling by the Bombay High Court in Godrej Projects Development Ltd. v. R.K. Ramani & Jayanti Ramani serves as a pivotal reference point in [Main Keyword 1], specifically regarding the principles governing [Main Keyword 2]. This significant judgment, thoroughly detailed on CaseOn, upholds the condonation of delay by lower consumer forums, reinforcing a liberal interpretation of 'sufficient cause' in the pursuit of substantive justice.

Issue: Condonation of Delay in Consumer Complaint

The central question before the Bombay High Court was whether the State Consumer Disputes Redressal Commission and the District Consumer Disputes Redressal Commission correctly exercised their discretion in condoning a significant delay in filing a consumer complaint. The delay arose from an initial filing in a forum lacking pecuniary jurisdiction, subsequent return of the complaint, and various intervening factors such as the COVID-19 pandemic and the complainant's health issues. The petitioner, Godrej Projects Development Ltd., argued that the delay was inordinate and lacked sufficient justification, making the condonation unwarranted.

Rule: Legal Principles for Condonation of Delay

The High Court relied on established legal precedents and statutory provisions concerning the condonation of delay:

Section 14 of the Limitation Act, 1963

This section allows for the exclusion of time spent prosecuting proceedings bona fide in a court that ultimately lacks jurisdiction. The Supreme Court in Consolidated Engg. Enterprises V/s. Principal Secy. Irrigation Department outlined key conditions for applying Section 14:

  • Both prior and subsequent proceedings must be civil and prosecuted by the same party.
  • The prior proceeding must have been pursued with due diligence and in good faith.
  • The failure of the prior proceeding must be due to a defect of jurisdiction or a similar cause.
  • Both proceedings must relate to the same matter in issue.
  • Both proceedings must be in a 'court' (which includes consumer forums for this purpose).

The court emphasized that Section 14 should be interpreted to further the cause of justice, excluding time diligently spent pursuing a remedy in a wrong forum.

Interpretation of 'Sufficient Cause' and Discretionary Powers

The expression 'sufficient cause' under Section 5 of the Limitation Act often receives a liberal construction to advance substantive justice. The Supreme Court in N. Balakrishnan V/s. M. Krishnamurthy distinguished between situations where a lower court *condones* delay and where it *refuses* to do so:

  • When a lower court condones delay, superior courts are generally reluctant to interfere unless the discretion was exercised on untenable grounds, arbitrarily, or perversely.
  • When a lower court refuses to condone delay, superior courts are free to re-examine the reasons and make their own findings.

However, this liberal approach does not imply condoning delay as a matter of generosity. As highlighted in Basawaraj and Anr. V/s. Special Land Acquisition Officer, a party seeking condonation must provide a reasonable and rational explanation. Negligence or lack of bona fides should preclude condonation.

Impact of COVID-19 Pandemic

The court also acknowledged the Supreme Court's orders in Suo Motu Writ Petition (Civil) No.3 of 2020, which suspended the period of limitation from March 15, 2020, to February 28, 2022, due to the COVID-19 pandemic.

Analysis: Applying the Rules to the Facts

The Bombay High Court meticulously applied these rules to the specific circumstances of the case:

The complainants had booked a flat and paid a significant amount (Rs. 45,15,844/-). The petitioner unilaterally terminated the allotment in January 2016 and forfeited the amount. The first complaint was filed before the State Commission in August 2018, approximately 7.5 months after the termination letter. The State Commission returned the complaint in April 2019, citing lack of pecuniary jurisdiction, and directed re-filing within one month before the appropriate forum. However, the complaint was eventually re-filed before the District Commission in July 2022.

The court found that the conditions for applying Section 14 of the Limitation Act were fulfilled, as the initial proceedings were pursued bona fide but in a forum without jurisdiction. The core of the controversy then shifted to the delay *after* the State Commission returned the complaint.

The complainants provided several reasons for this subsequent delay:

  1. **Difficulty in obtaining documents and court fee refund:** The complainants asserted they faced challenges in retrieving their original complaint and securing a refund of court fees after the State Commission's order. This claim found support in contemporaneous documents, including the need to make an RTI application, indicating a genuine effort to follow up.
  2. **COVID-19 Pandemic:** The period of suspended limitation due to the pandemic (March 2020 to February 2022) directly impacted the timeline, providing a legitimate reason for a portion of the delay.
  3. **Complainant's Illness:** Complainant No.1 was infected with COVID-19 in June 2022, further contributing to the delay in re-filing.

The High Court noted that the District Commission and State Commission, having exercised their positive discretion to condone the delay, had done so with justifiable reasons. The court emphasized that procedure should serve as a handmaid of justice, and where there is no deliberate or mala fide delay, a liberal consideration is warranted, especially in consumer cases where substantial amounts are involved and one party may be significantly disadvantaged. The ongoing struggle of Complainant No.2, now a widow, against an established real estate developer for a significant refund underscored the need for a just outcome.

For legal professionals tracking such nuanced rulings, CaseOn.in's 2-minute audio briefs provide an invaluable resource. These concise summaries quickly convey the essence of complex judgments, helping lawyers and students understand the critical aspects of [Main Keyword 2] without sifting through extensive legal text.

Conclusion: High Court Upholds Condonation of Delay

Based on its comprehensive analysis, the Bombay High Court found no justifiable reason to interfere with the positive exercise of discretion by the District Commission and the State Commission in condoning the delay. The court concluded that the broad circumstances, including the genuine efforts of the complainants, the impact of the pandemic, and health issues, constituted 'sufficient cause'. Consequently, the Writ Petition filed by Godrej Projects Development Ltd. was dismissed, and the Rule discharged, affirming the lower forums' decisions to allow the consumer complaint to proceed.

Summary of the Judgment

The Bombay High Court dismissed a writ petition filed by Godrej Projects Development Ltd. challenging the condonation of delay by the State and District Consumer Commissions. The court upheld the lower forums' decisions, finding that the reasons provided by the complainants—including difficulties in obtaining documents post-transfer of jurisdiction, the COVID-19 pandemic, and one complainant's illness—constituted 'sufficient cause'. The judgment reiterates the principle of liberally interpreting 'sufficient cause' to ensure substantive justice, particularly when discretion has been positively exercised by lower courts.

Why This Judgment is an Important Read for Lawyers and Students

This judgment offers critical insights for legal professionals and students specializing in consumer law and civil procedure. It meticulously illustrates the application of Section 14 of the Limitation Act, 1963, in the context of consumer disputes, detailing the conditions under which time spent in a wrong forum can be excluded. Furthermore, it reinforces the judiciary's liberal approach to condoning delay, especially when substantive justice is at stake, and clarifies the appellate court's role when reviewing a lower court's positive exercise of discretion. The inclusion of real-world factors like administrative delays and global pandemics (COVID-19) in assessing 'sufficient cause' makes this a highly practical and relevant precedent for understanding the dynamic nature of limitation laws.

Disclaimer

All information provided in this article is for informational purposes only and does not constitute legal advice. While efforts have been made to ensure accuracy, readers should consult with a qualified legal professional for advice pertaining to their specific circumstances.

Legal Notes

Add a Note....