renewable energy, power purchase agreement, tariff
0  23 Apr, 2023
Listen in 02:00 mins | Read in 73:00 mins
EN
HI

Gujarat Urja Vikas Nigam Limited & Ors. Vs. Renew Wind Energy (Rajkot) Private Limited & Ors

  Supreme Court Of India Civil Appeal /3480-3481/2020
Link copied!

Case Background

As per the case facts, the appellant challenged Appellate Tribunal for Electricity (APTEL) orders that rejected their appeals and review petition, affirming a state regulatory commission's decision. The dispute centers ...

Bench

Applied Acts & Sections

No Acts & Articles mentioned in this case

Hello! How can I help you? 😊
Disclaimer: We do not store your data.
Document Text Version

1

REPORTABLE

IN THE SUPREME COURT OF INDIA

CIVIL APPELLATE JURISDICTION

CIVIL APPEAL NO(S). 3480-3481 OF 2020

GUJARAT URJA VIKAS NIGAM

LIMITED & ORS. …APPELLANT(S)

VERSUS

RENEW WIND ENERGY (RAJKOT)

PRIVATE LIMITED & ORS. …RESPONDENT(S)

J U D G M E N T

S. RAVINDRA BHAT, J.

1.The current civil appeals,

1

under Section 125 of the Electricity Act, 2003,

(hereafter, “the Act”) challenge orders of the Appellate Tribunal for Electricity

(hereafter, “APTEL”), dated 06.12.2018 (“first impugned order”)

2

and order

dated 24.07.2020 (“second impugned order”)

3

. The APTEL had, by those

orders, rejected the appeals preferred by the present appellant, and the review

petition, as well. Resultantly, the order of the Gujarat Electricity Regulatory

1 Civil Appeals Nos. 3480 and 3481 of 2020

2 in Appeal No 209/2015

3 in Review Petition No 03/2019

2

Commission (hereafter “the State Commission”), dated 01.07.2015

4

was

affirmed.

2.The first appellant – Gujarat Urja Vikas Nigam Limited (hereafter

“Gujarat Urja”) had approached this court previously challenging the order of

APTEL, which was disposed of by this court

5

granting liberty to it, to seek

review/rectification. Gujarat Urja then preferred a review petition, which was

rejected by APTEL, by the second impugned order. When this appeal was taken

up for hearing, on 14.10.2020, this court had issued notice and stayed the

impugned order of APTEL.

Background

3.Gujarat Urja procures power in bulk on behalf of distribution licensees in

the state of Gujarat; it is an authorized licensee within the meaning of the term

under the Act. The second, third, fourth and fifth appellants are distribution

licensees in the State of Gujarat. The first respondent, Renew Wind Energy

(Rajkot) Pvt Ltd (hereafter “RWE”) is a wind generator which had set up 25.2

MW Wind Turbine Generators at District Rajkot, Gujarat under the Renewable

Energy Certification scheme notified by the Central Electricity Regulatory

Commission (hereafter, “Central Commission”). The second respondent is the

Wind Independent Power Producers Association (hereafter “Association”). The

Respondent No 3, Gujarat Electricity Regulatory Commission (hereinafter “the

4 in petition No 1363/2013

5 Civil Appeal No 1253/2019 by order dated 15.02.2019

3

State Commission”) is the regulatory commission under the Act, for the State of

Gujarat. The fourth respondent, Wish Wind Infrastructure LLP (“Wish Wind”

hereafter) is a wind generator.

4.By Section 86 of the Act

6

, State Commissions discharge several

functions- which include the determination of tariff “for generation, supply,

transmission and wheeling of electricity, wholesale, bulk or retail, as the case

may be, within the State". The tariff determination process should accord with

Sections 62 and 64 of the Act. Section 62, requires “the Appropriate

Commission” (in this case, the State Commission) to determine tariffs in

accordance with the provisions of the Act for – among other purposes, retail

supply of electricity. The State Commissions are also empowered to frame

regulations, under Section 181 of the Act. That power includes the formulation

of the “terms and conditions for determination of tariff Under Section 61".

7

Additionally, the tariff order can be modified or imposed with conditions under

6 The relevant extract of Section 86 is as follows:

"86. Functions of State Commission.-(1) The State Commission shall discharge

the following functions, namely:-

(a) determine the tariff for generation, supply, transmission and wheeling of

electricity, wholesale, bulk or retail, as the case may be, within the State:

……

(b) regulate electricity purchase and procurement process of distribution licensees

including the price at which electricity shall be procured from the generating companies or

licensees or from other sources through agreements for purchase of power for distribution

and supply within the State;

(c) facilitate intra-State transmission and wheeling of electricity;

…..

(e) promote co-generation and generation of electricity from renewable sources of

energy by providing suitable measures for connectivity with the grid and sale of electricity

to any person, and also specify, for purchase of electricity from such sources, a percentage

of the total consumption of electricity in the area of a distribution licensee;

…. [..]”

7 Clause 181(2)(zd) of the Act.

4

Section 64(3). The State Commission is guided by the principles specified in

Section 61 of the Act while formulation of the tariff regulations. This court has

held that state commissions as expert bodies have to strike a balance between

various competing concerns and interests while framing such regulations.

8

The

Gujarat State Commission, for a Multi-Year period (also called the “control

period”), frames Regulations for determination of tariff. The state commission

then determines the Multi-Year Tariff Order based on the data available.

Furthermore, Section 64 (6) prescribes that tariff orders “shall continue to be in

force for such period as may be specified in the Tariff Order unless amended or

revoked”. If any party is aggrieved by any conditions of a given Tariff Order, it

can seek its amendment or revocation. Orders are also appealable under Section

111 to APTEL, and thereafter to this court under Section 125 of the Act. Tariff

Orders under Section 64 of the Act are quasi-judicial in nature and ipso facto

binding on the parties unless amended or modified through law.

5.On 29.01.2010, the Central Electricity Regulatory Commission (Terms

and Conditions for Recognition and issuance of Renewable Energy Certificate

8Kerala State Electricity Board & Anr v. Principal Sir Syed Institute for Technical Studies, 2020 7 SCR 885:

7. [..] “While fixing tariff, the Commission cannot show undue preference to any

consumer of electricity. The Commission, however, is vested with the power to prescribe

differential rates according to the consumers' load factor, power factor, voltage, total

consumption of electricity during any specified period of time at which supply is required. So

far as fixing different rates for these two categories of the educational institutions, these

factors did not come into play. The other permissible differentiating factors are geographical

position of any area, the nature of supply and the purpose for which the supply is

required. As regards this set of differentiating factors, the tariff advantage for government

run and aided educational institutions do not appear to be based on geographical position or

nature of supply. The Commission however has justified the classification of the aforesaid

two sets of tariffs on the basis of purpose for which supply is required by the consumers.”

5

for Renewable Energy Generation) Regulations, 2010 (hereafter “REC

Regulations 2010”) were framed by the Central Commission for the

development of a power market for non-conventional sources of energy by the

issuance of tradable and saleable credit certificates (hereafter “RECs”).

Regulation 5 of the said REC Regulations 2010 provides for the required

eligibility for the renewable generators for participating in the RE Certificates:

"5. Eligibility and Registration for Certificates:

(1) A generating company engaged in generation of electricity from

renewable energy sources shall be eligible to apply for registration

for issuance of and dealing in Certificates if it fulfills the following

conditions:

a. it has obtained accreditation from the State Agency;

b. it does not have any power purchase agreement for the capacity

related to such generation to sell electricity at a preferential tariff

determined by the Appropriate Commission; and

c. it sells the electricity generated either

(i) to the distribution licensee of the area in which the eligible entity is

located, at a price not exceeding the pooled cost of power purchase of

such distribution licensee, or

(ii) to any other licensee or to an open access consumer at a mutually

agreed price, or through power exchange at market determined price.

Explanation. - for the purpose of these regulations 'Pooled Cost of

Purchase' means the weighted average pooled price at which the

distribution licensee has purchased the electricity including cost of

self generation, if any, in the previous year from all the energy

suppliers long-term and short-term, but excluding those based on

renewable energy sources, as the case may be."

6.The objective of the REC Regulations 2010 was to separate the physical

electrical component and the environmental (renewable) component of the

energy for issuance of RECs. This was an alternate mechanism developed for

the sale of renewable energy at a preferential tariff to any licensee or directly to

any consumer. The REC Regulations 2010 aimed at selling the renewable

component through the RE Certificates containing promotional benefits of

6

renewable energy while the physical electrical component was sold as any other

conventional electricity. The REC Regulations 2010 also provided that

generators based on the REC mechanism had the option to sell physical energy

to the distribution licensee at a "price not exceeding the Average Pooled Power

Purchase Cost” (hereinafter as “APPC”) of the distribution licensee

9

. This was

to ensure that generators did not benefit twice over, by selling RECs and also

selling physical energy at higher promotional tariffs or taking concessional

benefits from the concerned distribution licensee.

7.Under the REC Regulations 2010, distribution licensees were not obliged

to purchase the physical component of electricity from renewable energy

generators set up under the REC mechanism since such REC based generators

had alternative options with regard to the physical component of electricity,

namely, (i) sale of electricity power exchanges (ii) wheeling of power for sale to

third parties at mutually agreed rates or (iii) wheeling of power for their own

consumption. In the case of the sale of the physical component of electricity, the

price for the electrical component could not exceed average pooled cost of the

distribution licensees. The regulations also provided that the generators (of

renewable energy) were not eligible for any benefits including banking

facilities, exemption from payment of cross subsidy surcharge etc. amongst

other things. The stated promotional benefits were applicable only in terms of

trading and selling of the RE Certificates.

9 Regulation 5(1)(c) of REC Regulations 2010.

7

8.The REC Regulations 2010 provided for floor price and forbearance price

i.e. minimum price and maximum price respectively at which RECs could be

traded in the power exchange. Those prices i.e. floor price and the forbearance

prices were to be determined by the central commission for the entire country.

9.In the present case, the State Commission by its order

10

determined the

tariff for procurement of power by distribution licensees from wind energy

generators and also ruled on other commercial issues for wind energy

generators set up under a preferential tariff mechanism. The order provided for

a preferential levelized tariff of 3.56 per kWh for the supply of energy to the

distribution licensee for meeting it’s Renewable Power Purchase Obligation

(RPO). The “control period” of the Order [dated 30.1.2010] was for the period

11.08.2009 to 10.08.2012

11

. The order, inter alia, also provided the following

promotional benefits for wind generators set up for third party sale under a

preferential mechanism:

(a) Exemption from cross subsidy charges for the sale of wind energy to

open access users in the State.

(b) Payment for excess (over and above that set off against monthly

consumption in the 15 minutes time block) would be treated as a sale to

10 Dated 30.01.2010 in Order No 1/2010

11 The relevant provision of the Order reads as follows:

“2.2 Control period The Commission had, vide its Order No.2 of 2006 dated 11th

August,2006, determined the Wind Energy Tariff for a period of three years, i.e. upto 10th

August,2009. The draft for the present order was published on 17.05.2009 and it was

proposed to be effective from 1st July, 2009.However, some of the objectors suggested that

the present order be made effective from the end of previous control period. Since the

previous control period expired on 10th August, 2009, the Commission decides that the

control period for this order will be 3 (three) years w.e.f. 11th August, 2009.”

8

the distribution licensee concerned at a rate of 85% of the preferential

tariff determined by commission for such renewable energy sources.

10.On 17.04.2010, the State Commission notified Gujarat Electricity

Regulatory Commission (Procurement of Energy from Renewable Sources)

Regulations, 2010 (hereafter “State Regulations”). The State Regulations

provided for the percentage of total consumption that distribution licensees were

to purchase from RPOs and further recognized that RPO could be fulfilled by

the purchase of such RECs. Further, obligated entities could fulfil their

renewable purchase obligation through two sources:

(a) Purchase of renewable energy directly (at preferential tariff

determined by State Commission); and

(b) Purchase of RECs at a market price between Floor Price and

Forbearance price determined by Central Commission

11.A Power Purchase Agreement (hereafter “PPA”) in terms of the REC

Regulations 2010, was entered into between the Gujarat Urja and the wind

power developers (hereafter, “WPDs”) including respondent RWE on

29.03.2012. The agreement provided for a ceiling on tariff at ₹ 2.64 per unit for

25 years. In addition to the tariff, WPDs were eligible for the issue of RECs for

each unit of electricity generated and supplied by them to the appellants. The

alternate route available for the WPDs (such as RWE, Wish Wind etc.) at the

time of entering into the PPA was to sell electricity at a promotional tariff of ₹

3.56 per unit - as determined by the State Commission. By choosing the option,

9

the WPDs were ensured tariff at ₹ 2.64 per unit plus tradable RECs whose price

was determined on the basis of the “weighted average pooled price”

12

.

Distribution licensees were enabled to adjust such quantum of power purchased

towards RPO specified under Section 86(1)(e) of the Act. Thus, the interests of

both segments of the industry were taken care of.

12.The State Commission by its order dated 08.08.2012

13

determined the

tariff at which the power could be procured by the distribution licensees and

others from wind power projects commissioned in the control period from

11.08.2012 to 31.03.2016.

13.On 11.07.2013, Central Commission amended the REC Regulations 2010

(hereafter “Second Amendment”) and replaced "at a price not exceeding pooled

cost of the power purchase “with" at the pooled cost of power purchase"

14

along with the relevant statement of reasons for the said amendment. It was

clarified in the amendment that PPAs already executed prior to this amendment

at a tariff lower than APCC would not be affected. The first two respondents

were aggrieved by the order of the Central Commission. They filed a petition

15

12 See Explanation to Regulation 5 of the REC Regulations 2010 which defines average

pooled price as follows:

“the weighted average pooled price at which the distribution licensee has purchased

the electricity including cost of self-generation, if any, in the previous year from all the

energy suppliers long-term and short-term, but excluding those based on renewable energy

sources, as the case may be.”

13 in Order No. 2/2012

14 The relevant amendment to Regulation 5 (c), reads as follows:

“(2) In sub-clause (c) of clause (1) of Regulation 5 of the Principal Regulations, the

words "at price not exceeding the pooled cost of the power purchase of such distribution

licensee" shall be substituted with the words "at the pooled cost of power purchase of such

distribution licensee as determined by the Appropriate Commission".”

15 Petition No. 1363 of 2013

10

before the State Commission arguing that the terms of the PPA had to be

changed in view of the change in the REC regulations. This petition was

allowed by the State Commission directing that the order of the Central

Commission was general and was therefore applicable to all similarly situated

wind power generators. Aggrieved by the order of the State Commission,

Gujarat Urja had preferred an appeal

16

before APTEL. This appeal was rejected

by APTEL by order dated 06.12.2018. The appellants preferred review petition

against APTEL’s order rejecting their appeal against State Commission’s order;

that too was dismissed by APTEL vide order dated 24.07.2020.

Arguments of the Appellant

14.The learned senior counsel for the appellant, Mr. C.A. Sundaram

submitted that governing regulations for the PPAs in question were the CERC

Regulations 2010. Therefore, the State Commission had no jurisdiction to

decide the tariff contrary to the agreement. Further, counsel argued that Central

Commission itself has clarified by the Second Amendment that in respect of

PPAs entered into prior to 11.07.2013, tariffs mutually agreed upon between the

parties would be valid for the entire duration of the PPA (i.e. 25 years) and they

could not be substituted or re-determined by the State Commission. It was

further argued that had the appellants known about the APPC on year-on-year

basis at the time of signing the agreement, they would not have adopted the

REC mechanism but instead would have availed a different method whereby

16 Appeal No. 209/2015

11

prices were fixed and appellants would have been entitled to RPO benefits as

well.

15.Reliance was placed on this court’s judgment in Gujarat Urja Vikas

Nigam Limited v. Solar Semi-Conductors Power Limited Company (India)

Private Limited

17

to argue that if the State Commission re-determines the tariff

amongst the parties, then the aggrieved party cannot be compelled to continue

the said agreement or enter into a new agreement on such increased tariff.

16.The appellants further submitted that State Commission had no

jurisdiction to reopen the PPA as the same was entered into in terms of the REC

Regulations 2010 that was framed by the Central Commission and was within

its exclusive jurisdiction. Moreover, it was argued that the appellants would fail

in their duty towards their consumers if they cannot negotiate for a lower tariff

or if they agree to purchase power at a higher tariff despite the availability of

power at a lower tariff. In such an event, the higher cost of procurement of

power so imposed would be ultimately passed on to the consumers which would

be contrary to a specified public interest, under the Act.

17.The learned senior counsel argued that the definition of the “APPC”

cannot be relied upon in the present case

18

and the PPA in question provided for

a tariff. There was consequently no bar in any law or regulations for the parties

17 (2017) 14 SCR 115

18 APPC as clause 1.1 of the PPA is defined as:

"Average Power Purchase Cost" means the weighted average pooled price at which the

distribution licensee has. Purchased the electricity including cost of self-generation, if any, in the

previous year from all the energy suppliers long-term and short-term; but excluding those based on

renewable energy sources, as the case may be. Further, for this agreement, Average Power Purchase

Cost for the term of the agreement shall be as per Article No. 5.2

12

to agree to such tariff and in fact, REC Regulations 2010 itself recognized that

the PPA can be “at a price not exceeding the pooled purchase cost”. Likewise,

for the sale of such power to customers or the licensees, reference is made to

“mutually agreed price” and therefore reference to “mutually agreed price” can

mean that price can also be a fixed price and need not mean that it has to be

dynamic and varying every year.

18.It was argued that the interpretation placed by APTEL is not founded on

any express provision in the regulations, or anything arising out of necessary

implication. The change in regulations, unless made specifically operable for a

prior period, cannot be construed to be retrospective. Thus, contracts concluded

prior to the entered into prior to the amendment [in 2013] cannot be governed

by amended provisions. Doing so would not only be contrary to the express

terms of the amended regulations but would also be contrary to the terms of the

PPA which do not accommodate or provide for such change in regulations.

19.The appellants further urged that the PPA was consciously entered into

by the respondents on 29.03.2012, which was before the state commission’s

tariff order dated 08.08.2012. The PPAs were signed by the respondents before

11.07.2013, (when the amendment was made to the REC regulations)

voluntarily without any reservation. The terms of the PPA were binding and

enforceable, unaffected by the Second Amendment, which applied

13

prospectively. Learned counsel relied on the clarification by the CERC in the

Statement of Reasons published in this regard.

19

20.It is argued that the National Action Plan on Climate Change and the

Union Ministry of Power resolution dated 28-01-2016 and Tariff Policy

underline the necessity of the co-generation of renewable sources of energy,

progressively, so that it reaches a greater proportion. The policy aims at

increasing investment, and ensuring that viable units generating renewable

energy are set up.

21.It was argued that the PPA was a commercial transaction, freely entered

into between the parties. Neither the appellants nor the first Respondent was

obliged to enter into the PPA nor agree to any specific terms or conditions. In

case the terms were not acceptable, both parties had the freedom to reject the

transaction and seek to sell or buy power through other alternative available

options as provided under the REC Regulations 2010. Further at the time of

signing the PPA, and even thereafter till the filing of the Petition before the

State Commission in the month of December 2013 (i.e. more than one and half

years after the execution of the PPA), the first respondent did not raise any

objections or protest on being allegedly coerced or placed under duress to agree

to the terms and conditions of the PPA. The terms of the PPA were fully in

19 Dated 10.07.2013, which inter alia, stated that

“Some of the stakeholders have suggested to clarify as to whether the PPAs executed at price lower than

APPC would become ineligible under REC Mechanism. It is felt that the tariff for electricity component lower or

higher than APPC may lead to avoidable loss or profit to RE generator. The Commission would like to clarify that the

intention is not to debar the projects that have executed PPA at tariff lower than APPC. This amendment will apply

prospectively and as such will not affect the" already executed PPAs at lower than APPC.”

14

compliance with the provisions of the REC Regulations 2010 as the restriction

in those regulations was for the price not to exceed the Pooled Power Purchase

Cost. The price agreed to between the appellant and Respondent No. 1 was

2.64/- per unit or Pooled Power Purchase Cost of the subsequent year,

whichever was lower.

22.The appellants argue that till 11.07.2013 none of the WPDs/ respondents

raised any issue on the tariff of 2.64/kWh for the entire duration of the PPA.

It

was only on 10.12.2013, the first two respondents filed Petition No.1363/ 2013

before the State Commission claiming that the tariff should be the APPC cost

year-on-year basis instead of a fixed

2.64/kWh. This was contrary to the

decision by CERC on the application of Second Amendment only prospectively

-which is, for PPAs entered on or after 11.07.2013. The state commission by its

order (dated 01.07.2015) allowed the respondent’s petition and further directed

that the order is generic in nature and applicable to all similarly placed WPDs-

which was affirmed by the first impugned order. The appellants argue that the

governing Regulations for PPAs adopting the REC Mechanism are 2010 REC

Regulations and the state commission cannot decide on tariff contrary to the

same. When the Central Commission clarified that for PPAs entered into prior

to 11.07.2013, the tariff mutually agreed is valid for the entire duration of the

PPA (25 years), the state commission and APTEL fell into error in substituting

a new tariff at the instance of the WPDs/Respondents. It is pointed out that Rule

15

8

20

of the Electricity Rules, 2005, notified by the Central Government, is

binding, and specifically provides that tariff determined by the Central

Commission (CERC) shall not be subject to re-determination by the

GERC/State Commission.

23.Learned senior counsel argued that if at the time of signing the PPAs

WPDs-Respondents had sought for tariff at APPC on year-on-year basis, the

appellants would not have entered into PPAs under the REC mechanism route

and would have only adopted the alternate route where the price was fixed and

in addition, the appellants would have been entitled to RPO benefits. This is

also clear as the appellants did not sign any PPAs after the Second Amendment

for procuring power under the REC mechanism. The appellants urge that the

Impugned Order is contrary to the decision of this court in Gujarat Urja Vikas

Nigam Limited v Solar Semi-Conductors Power Company (Pvt) Ltd (Supra)

holding that if the state commission re-determines the tariff, it cannot force the

appellants to continue the PPAs or enter into a contract based on such increased

tariff. Furthermore, it is argued that the principle that WPDs having validly

executed the PPAs cannot seek a modification to the tariff terms and conditions

contained in the PPAs under a prevalent dispensation for an increase in the tariff

or for any other terms and conditions: counsel referred to Transmission

20 Rule 8 reads as follows:

"8. Tariffs of generating companies under section 79. –The tariff determined by the Central

Commission for generating companies under clause (a) or (b) of subsection (1) of section 79 of the Act shall not

be subject to redetermination by the State Commission in exercise of functions under clauses (a) or (b) of sub

section (1) of section 86 of the Act and subject to the above the State Commission may determine whether a

Distribution Licensee in the State should enter into Power Purchase Agreement or procurement process with

such generating companies based ,on the tariff determined by the Central Commission."

16

Corporation of Andhra Pradesh Ltd v Sai Renewable Power Private Limited

(hereafter “Transmission Corporation of Andhra Pradesh Ltd")

21

; Gujarat Urja

Vikas Nigam Limited v EMCO Limited (hereafter “Emco Ltd”)

22

; and Gujarat

Urja Vikas Nigam Limited v ACME Solar Technologies (Gujarat) Pvt Ltd &

Others

23

in support of the above contention.

24.Mr. Sundaram argued – for the appellants that the plea of coercion or

duress or unequal bargaining etc, raised by the WPDs was patently erroneous

for the following reasons: (a) the petition before the state commission was filed

only by the first two Respondents; therefore, it cannot be a ground for alleging

coercion against all WPDs; (b) the allegations by the said two Respondents

were vague and unsubstantiated, and an afterthought as no such plea was raised

till December 2013, i.e., till after the amended CERC Regulations; and (c) as

held by this Court such plea of coercion had to be specifically pleaded and

proved. In this regard, reliance was placed on Transmission Corporation of

Andhra Pradesh Ltd (Supra).

25.It is further argued that there is no Regulation of the state or central

commissions prohibiting a term being incorporated in PPA which permits an

option to either party to switch from REC mechanism to Preferential Tariff

Mechanism. The impugned order had not considered judgments referred to by

the appellants on clauses granting power to one party to cancel the contract. In

21 (2010) 8 SCR 636

22 (2016) 1 SCR 857

23 (2017) 16 SCC 498

17

this regard, reliance is placed on Central Bank of India v Hartford Fire

Insurance Co. Ltd

24

; and Her Highness Maharani Shantidevi P Gaikwad v

Savjibai Haribai Patel & Ors

25

.

Respondents’ Submissions

26.Mr. Shyam Divan and Mr. Dhruv Mehta, learned senior counsels

appearing for the first two respondents urged that State Commission had

jurisdiction in the present case. Reliance was placed on the definitional clause

of the PPA (Article 1.1) to submit that commission meant ‘State Commission’.

It was urged that in terms of the extant regulatory framework, (which provided

for regulatory oversight by the appropriate commission), PPAs executed by

generating companies and distribution licensees necessarily required approval

by the appropriate commission. Firstly, Section 86(1)(b) of the Act specifically

vests the State Commission with the power to regulate the electricity purchase

and procurement process of distribution licensees including the price at which

electricity shall be procured from the generating companies. This provision

empowers the state commission to modify, alter or vary the terms of PPAs, to

ensure their compliance in accordance with the regulatory framework.

Secondly, under the Multi Year Tariff Regulations, 2011 (hereafter “GERC

(Multi Year Tariff) Regulations”) notified by the State Commission, , PPAs are

to be mandatorily approved in order for them to be considered effective and

24 AIR 1965 SC 1288

25 2001 (5) SCC 101

18

enforceable. Learned counsel relied on provisions of the Maharashtra Electricity

Regulatory Commission (Multi Year Tariff) Regulations, 2019, (Regulation

21); Delhi Electricity Regulatory Commission Comprehensive (Conduct of

Business) Regulations 2001 (Regulation 45) and Andhra Pradesh Electricity

Regulatory Commission (Distribution Licensee) Regulations, 2013 (Regulation

36) to support the contention that prior filing and approval of PPAs is necessary

and was not undertaken in this case, which undermines its legal efficacy.

27.It was submitted that pooled purchased cost of power to be taken into

consideration under the REC mechanism has to be the APPC of the previous

financial year- which has to be modified / increased on a regular basis. When

pooled purchase cost increases, the floor price of REC will decrease as the floor

price and forbearance price of RECs are subject to fluctuation, at the end of

each control period. Thus, wind power projects under the REC mechanism will

be viable, only when the realization from the power component increases to

compensate for the reduction in prices of RECs. It was submitted that if the

APPC computed is lower than what has been taken by the CERC for the

determination of the REC price band, there could be a viability gap problem for

RE generators under the REC mechanism, especially in cases where the price

discovered in the power exchange is closer to the floor price.

28.It was further submitted that the Second Amendment to REC regulations

specifically replaced the words “at a price not exceeding” to “at the pooled

cost”, which meant that the cost of electricity purchased could neither be lower

19

nor higher than the power purchase cost. Counsel further placed reliance on

Statement of Reasons dated 10.07.2013 issued by the Central Commission

regarding the Second Amendment to contend that REC contracts cannot be

fixed price contracts as they would affect the viability of REC projects as the

price band (floor price / forbearance price) are subject to periodic revision.

Relevant extracts of the said statement of reasons are reproduced below:

“4.3 Analysis and decision

Some of the stakeholders have suggested to clarify as to whether the

PPAs executed at price lower than APPC would become ineligible

under REC Mechanism. It is felt that the tariff for electricity

component lower or higher than APPC may lead to avoidable loss or

profit to RE generator. The Commission would like to clarify that the

intention is not to debar the projects that have executed PPA at tariff

lower than APPC. This amendment will apply prospectively and as

such will not affect the already executed PPAs at lower than APPC.

Regarding suggestion received that PPA of electricity component

should be a fixed price long term contract (without escalation) since

Commission has assumed fixed price while determining REC price

bands in its methodology, it is clarified that the price band is subject

to periodic revision; hence fixed APPC or long-term contract without

escalation might affect viability of RE Projects. In any case proposed

amendment provides that APPC would be determined by the

Appropriate Commission”

29.Counsel appearing for the association submitted that in terms of the

regulatory framework, PPAs executed by generating companies and distribution

licensees have to be approved by the appropriate commission; and that the PPA

in question was never approved by State Commission nor did the appellants

approach the State Commission for such approval. It was further submitted that

floor price and forbearance price are to be determined guided by various

principles, inter alia, variations in APPC across the states, (which is revised on

20

an annual basis). Hence, the APPC cannot be a static concept else variation in

floor price or forbearance price would lead to under recovery to generators.

30.It was further contended that APPC along with REC pricing, together, are

the tariff determined and approved for the supply of power. That is to say that

APPC and REC pricing are two halves of the same whole which constitutes the

overall tariff which a generating company registered under the REC mechanism

is entitled to receive. APPC along with REC pricing is what was intended to be

incorporated as part of the tariff clause in the PPA. If either of the components

is pegged or capped artificially, and without the approval of the State

Commission, it would lead to a skewed application of the REC mechanism to

the detriment of generating company, leading to under-recovery and unviability

of the RE generator.

31.It was argued that Regulation 9(2) of REC Regulations 2010 provides for

the determination of the floor price (minimum price) and the forbearance price

(maximum price) within which the RECs can be traded in power exchanges.

The floor price and the forbearance are to be determined by CERC for the entire

country guided by various principles, inter alia, variations in APPC across the

States, which is revised on an annual basis. Therefore, if APPC is made static

then variation in Floor Price/ Forbearance price would lead to under recovery to

generators.

32.The APPC to be taken into consideration under the REC mechanism must

be dynamic and must be revised on a regular basis. When APPC is increased,

21

the floor price of REC comes down and vice versa and the same is subject to

change every year. The APPC along with REC pricing, together, are the tariff

determined and approved for the supply of power. In other words, the APPC

and REC pricing are two halves of the same whole, which constitute the overall

tariff which a generating company registered under the REC mechanism is

entitled to receive. APPC along with REC pricing is what was intended to be

incorporated as part of the tariff clause in the PPA. If either component is

pegged or capped artificially, and that too without approval from GERC, the

same would lead to a skewed application of the REC mechanism to the

detriment of the generating company, leading to under-recovery and unviability

of the RE Generator.

33.It was submitted that the tariff in the PPA was in violation of the principal

regulation, which does not contemplate a fixed long-term price/ tariff. It is,

therefore, illegal and had to be aligned with the regulation. The APTEL

correctly aligned the tariff to the regulation. The regulation has not been

challenged and it has the force of statute and it mandates that PPAs should be

aligned to the regulations. Reliance is placed on PTC India Ltd. v. CERC

(hereafter “PTC India”)

26

.

34.Counsel for the third respondent argued that there could not be a tariff

between a generating company and a distribution licensee in a PPA which was

not in line with the CERC Regulations and tariff orders issued by the State

26 (2010) 3 S.C.R. 609

22

Commission. It was further contended that the court cannot enforce a contract

where unequal bargaining power exists amongst the parties. It was further

submitted that State Commission has rightly observed that the fixed tariff of

2.64/unit for a period of 25 years by the parties violates not only the provisions

of the Act but also the National Electricity Policy and tariff policy as notified

under Section 3 of the Act which promotes renewable energy sources through

preferential pricing.

35.Counsel for Wish Wind submitted that it cannot be bound by the onerous

terms of the PPA as it was never approved by the State Commission and thus

not in consonance with the statutory procedure prescribed under the Act.

Learned counsel also submitted that present proceedings are not a case where a

contract has been interdicted by the State Commission but rather where a

contract has been aligned with the relevant regulatory regime in the exercise of

the regulatory power vested by the Act. In response to Gujarat Urja’s argument

that State Commission has no jurisdiction to reopen the PPA, it was submitted

that Section 86(1)(b) of the Act places an obligation upon distribution licensees

to get PPAs (executed by them) approved by the State Commission and in the

present case, state commission never had the opportunity to verify/regulate such

PPAs in accordance with the law.

36.It was also submitted that Section 86(1)(b) of the Act empowers the state

commission to modify, alter or vary the terms of the agreement of PPAs, to

ensure their compliance in accordance with the regulatory framework

23

established under the Act. It was further submitted that taking into consideration

the definition of APPC, it is evident that floor price and forbearance price are

dynamic in nature and APPC being associated with the floor price and the

forbearance price is also required to be determined on a year-to-year basis so

that the guaranteed return to the generators is not affected.

Analysis and Findings

37.The crisis arising out of, and the enormous environmental cost involved

in the continued use of fossil fuels has led governments, world over, to promote

alternative and renewable sources of energy. The rapid growth of renewable

energy over the decade and a half has witnessed that solar and wind power are

now the cheapest sources of energy in many countries in the world. Once green

energy was an expensive alternative, however, it is now helping to reduce

energy bills.

38.The rapidly changing economics of such sources has led, the Union

government to realize that solar and other renewables can potentially transform

the energy landscape, increase access and help India meet its climate change

objectives. Grid transmission capacity has been a barrier; however, distributed

and off-grid solar solutions provide a viable solution for increasing energy

access. Being dependent primarily on cheap coal-based power generation,

traditional thinking on energy has been that increase in renewable energy’s

share of electricity generation would further impair local distribution

24

companies’ poor financial situation. Over the years, India has established a

comprehensive policy and regulatory frameworks to encourage renewable

energy development. India began its development of wind power in the 1990s

and has significantly increased its capacity over the last few years. Compared to

established countries with wind energy capacities like the USA or Denmark,

India is a latecomer. Yet, its support for wind power, through its policies has

resulted in India becoming the producer with the fourth largest installed wind

power capacity, in the world; wind power accounts for 10% of India’s total

installed power capacity. As of February 2023, the installed capacity of wind

power in India was 42,015 megawatts (MW).

27

39.Section 86 of the Act enumerates the functions of state commissions;

Section 86 (1)(e) reads as follows:

“Section 86(1): The State Commission shall discharge the following

functions, namely:

****************** *****************

(e) promote cogeneration and generation of electricity from

renewable sources of energy by providing suitable measures for

connectivity with the grid and sale of electricity to any person, and

also specify, for purchase of electricity from such sources, a

percentage of the total consumption of electricity in the area of a

distribution licensee;”

40.State Commissions have placed significant emphasis on the last part of

this important clause while developing regulations for Distribution Licensees

27 Physical Progress (Achievements) Ministry of New and Renewable Energy, Govt. of

India. https://mnre.gov.in/the-ministry/physical-progress, visited on 06.04.2023 at 20:30

hours.

25

under their jurisdiction. The National Tariff Policy, issued by the Central

Government in terms of Section 3 of the Act states as follows:

“Clause 6.4: Non-conventional sources of energy generation

including co-generation:

(1) Pursuant to provisions of section 86(1)(e) of the Act, the

Appropriate Commission shall fix a minimum percentage for purchase

of energy from such sources taking into account availability of such

resources in the region and its impact on retail tariffs. Such

percentage for purchase of energy should be made applicable for the

tariffs to be determined by the SERCs latest by April 1, 2006.”

By virtue of Regulation 4 (1) of the REC Regulations 2010, there are two

categories of RECs: solar and non-solar. Regulation 4 (2) mandates that “non-

solar certificate shall be sold to the obligated entities to enable them to meet

their obligation for purchase from renewable energy sources other than solar.”

Regulation 5 (1) of the REC regulations (extracted earlier) spells out the

eligibility conditions for renewable energy generating companies to apply and

seek registration for certificates; these are that the company should have: (a)

obtained accreditation from the State Agency; (b) it does not have any power

purchase agreement for the capacity related to such generation to sell electricity

at a preferential tariff determined by the Appropriate Commission; and (c) it

sells the electricity generated either-(i) to the distribution licensee of the area in

which the eligible entity is located, at a price not exceeding the pooled cost of

power purchase of such distribution licensee, or (ii) to any other licensee or to

an open access consumer at a mutually agreed price, or through power exchange

at market determined price. What is meant by “pooled cost or purchase” is

26

elaborated in the Explanation (to Regulation 5) to mean “the weighted average

pooled price at which the distribution licensee has purchased the electricity

including cost of self-generation, if any, in the previous ·year from all the

energy suppliers long-term and short-term, but excluding those based on

renewable energy sources. as the case may be.”

41.The objectives of the REC Regulations 2010 were described in the

judgment of this court, reported as Hindustan Zinc Ltd. v. Rajasthan Electricity

Regulatory Commission,

28

 

“44. [..] Regulations have been enacted in order to effectuate the

object of promotion of generation of electricity

from renewable sources of energy as against the polluting sources

of energy which principle is enshrined in the Act, the National

Electricity Policy of 2005 and the Tariff Policy of 2006. The

provisions requiring purchase of minimum percentage of

energy from renewable sources of energy have been framed with an

object of fulfilling the constitutional mandate with a view to protect

environment and prevent pollution in the area by utilising renewable

energy sources as much as possible in larger public interest.[..]”

42.The approach of this court, therefore, has to consider the objective of the

policy of promoting non-renewable sources of energy, the purpose of

introducing RECs, and the progressive obligations placed upon licensees, to

ensure that they purchase energy from such “green” or “clean” sources, in a

viable manner. In the present case, the obligation to procure renewable energy,

is located in the Gujarat Electricity Regulatory Commission

(Procurement of Energy from Renewable Sources) Regulations, 2010 (hereafter

28 (2015) 7 S.C.R. 1104

27

the “Renewable Sources Regulations”). Regulation 4 (1) of the said Renewable

sources Regulations reads as follows:

“4. Quantum of Renewable Purchase Obligation (RPO)

4.1 Each distribution licensee shall purchase electricity (in kWh) from

renewable energy sources, at a defined minimum percentage of the

total consumption of its consumers including T&D losses during a

year. Similarly, Captive and Open Access user(s) / consumer(s) shall

purchase electricity (in kWh) from renewable energy sources, at a

defined minimum percentage of his/her total consumption during a

year.

The defined minimum percentages are given below in the Table 1.

If the above-mentioned minimum quantum of power purchase from

solar and other renewable energy sources is not available in a

particular year, then in such cases, additional wind or other energy,

over and above that shown in column 3 and 5, shall be utilized for

fulfillment of the RPO in accordance with column 2.

Provided further that such obligation to purchase renewable energy

shall be inclusive of the purchases, if any, from renewable energy

sources already being made by the obligated entity concerned:

Provided also that the power purchases under the power purchase

agreements for the purchase of renewable energy sources already

entered into by the distribution licensees shall continue to be made till

their present validity, even if the total purchases under such

agreements exceed the percentage as specified hereinabove.”

28

43.In terms of Regulation 9 (1) of the Renewable Sources

Regulations, if an obligated entity

29

(such as the present

appellant) does not fulfil the renewable purchase obligation as

provided in the regulations during any year and also does not

purchase the certificates, the State Commission may direct the

obligated entity to deposit into a separate fund, to be created

and maintained by such obligated entity, such amount as the

State Commission may determine. Thus, obligated entities,

(distribution licences included) had to take steps to

progressively increase the purchase of power from renewable

energy sources. To incentivize this, flexibility was granted; the

power generators could either have the tariff fixed, according

to the State Commission’s Tariff determination order, or adopt

another mechanism, i.e., the one contemplated in the REC

Regulations.

44.The relevant conditions and stipulations set out in the PPA in this case,

are extracted below:

“RATES AND CHARGES

5.1 Monthly energy charges: the GUVNL shall pay for the delivered

energy as certified by the SEA of Gujarat SLDC, for the term of this

agreement from the commercial operation date of signing of power

purchase agreement whichever is later, to the power producer every

month. The tariff payable by GUVNL for energy purchased shall be as

per clause 5.2 herein.

29 An “obligated entity” is defined in Regulation 2 (k) as “the entity mandated under

clause (e) of subsection (1) of section 86 of the (Electricity) Act to fulfil the renewable

purchase obligation and identified under clause 3 of these Regulations.

29

5.2. GUVNL shall pay a fixed rate of Rs. 2.64 per KWh (average

power purchase cost for previous FY i.e. 2010-11) during the term of

this agreement for delivered energy certified by Gujarat SLDC in the

monthly State energy Account (SEA):

a) In case in any subsequent FY the APPC goes below the APPC goes

below the APPC of FY 2010-11, the applicable tariff for ensuring. FY

shall be such lower APPC of the previous year.

b) Power producer and power procurer both have option to switch

over from REC mechanism to preferential tariff after 10 years from

commissioning of the 23.10 MW WTGS. In case either party exercises

the option, the tariff shall be Rs. 3.56 per KWh (as determined by

GERC through order no. 1 of 2010 dated 30.1.2010) for balance term

of the agreement. Further, power producer shall submit documentary

evidence to GUVNL for de-registration of wind project from REC

mechanism in case either party ·exercise. Option to switch over from

REC to preferential tariff.

5.3 For each KVRAH drawn from the grid, the Company shall pay at

the rate of as determined by the Commission to GETCO from time to

time for each KARH drawn.

5.4 Till the intra-State ABT is implemented, the certificate issued by

GEDA for generation share of wind turbine shall be acceptable for

monthly energy bill. The other provisions of intrastate ABT and Open

access regulations appearing in this agreement shall also be

applicable only after the intra-State ABT is implemented.

************************ ****************

ARTICLE 9

TERM, TERMINATION AND DEFAULT

9.1 Term of the agreement: This agreement shall become effective

upon the executive and delivery thereof by the parties hereto and

unless terminated pursuant to other provisions of the agreement, shall

continue to be in force for such time until the completion of a period

of 25 (twenty five) years from the commercial operation date.”

………………………..

Did the PPA in the present case, require prior approval of the state

commission

30

45.RWE and the other respondents urge that the PPA was unenforceable

because it was not approved by the State Commission. This court is of the

considered view that the argument is unmerited and insubstantial.

46.The State Commission’s regulations (Renewable Sources Regulations)

relating to procurement of energy from Renewable Sources, provides, inter alia,

pertinently, as follows:

“3. Applicability of Renewable Purchase Obligation: These

Regulations shall apply to: (1) Distribution licensee (2) Any other

person consuming electricity

(i) generated from conventional Captive Generating Plant having

capacity of 5 MW and above for his own use and / or

(ii) procured from conventional generation through open access and

third party sale.”

47.From a reading of the above provision, it is evident that there was never

any provision, which mandated prior approval by the state commission, of PPAs

entered into, by parties, in exercise of their free choice, in relation to renewable

energy sources. As a matter of fact, in the case of renewable power, the state

commission had approved a model PPA. Further, the tariff terms and conditions

to the extent decided are by the Central Commission and not by the State

Commission. These are incorporated in the model PPA. Neither the

commission, nor the contesting respondents, during the hearings in the present

appeals, were able to point out any provision in the PPA in the present case,

which conflicted with any provision of the model PPA, or any express

regulation. Furthermore, it was not established how in the absence of any

31

reference to the Multi Year Tariff Regulations, they were applicable to PPAs

relating to renewable energy sources.

48.This court is also of the considered view, that in the absence of specific

norms prescribing prior approval of PPAs like in the case of provisions of

Regulation 21 of the Maharashtra Electricity Regulatory Commission (Multi

Year Tariff) Regulations, 2019; Regulation 45 of the Delhi Electricity

Regulatory Commission Comprehensive (Conduct of Business) Regulations

2001 and Regulation 36 of the Andhra Pradesh Electricity Regulatory

Commission (Distribution Licensee) Regulations, 2013, the respondent’s

arguments on this aspect cannot be accepted. In these circumstances, the

findings of APTEL, not based on any stipulated obligations under provisions of

the state regulations, requiring approval of the state commission, for its

operation, cannot be sustained.

Whether change in the REC Regulations obliged revision of the PPA in this

case

49.In Emco Ltd (supra), the parties had entered into a PPA on 09.12.2010 for

the sale and purchase of solar power. The PPA was modified on 07.05.2011 in

view of certain difficulties in the location of the unit. When the PPA was

entered into, the tariff order was applicable. The PPA was thus entered into

during the control period of the first tariff order. The second tariff order came

into force on 27.01.2012. It granted certain concessions to purchase and availing

of the benefit of accelerated depreciation under the income tax and did not grant

32

such benefits to purchasers and tariff payable to power purchasers which did not

avail of the benefit of accelerated depreciation. The respondent Emco had not

availed accelerated depreciation. Despite that, it approached the Gujarat State

Commission, seeking a determination of the tariff afresh, contending that the

position had changed. This court noticed that the power purchaser had

contended that notwithstanding that it entered into a PPA during the control

period, it was not obliged to sell power to the distributor for a price specified in

the PPA and was legally entitled to seek fixation of separate tariff. The Court

rejected the contention after noticing the arguments. The relevant extracts of the

judgment (In Emco Ltd.) are as below:

“11. The case of the first respondent is that notwithstanding the fact

that it entered into a PPA during the "control period" specified in the

First Tariff Order, it is not obliged to sell power to the appellant for

the price specified in Article5.2 of the PPA and is legally entitled to

seek (from the second respondent) fixation of a separate tariff. It is the

further case of the first respondent that under the PPA, the appellant

is under an obligation to procure the power from the first respondent

for a period of 25 years if the first respondent commences the

generation of power within the "control period" and is also obliged to

pay for the power procured by it at the rates specified in Article 5.2 of

the PPA. But the obligation of the first respondent to sell power

generated by it to the appellant at the rates specified in Article 5.2 of

the PPA comes into existence only on the happening of the two

contingencies i.e. the first respondent (i) commencing the generation

of power within the "control period" stipulated under the First Tariff

Order; and (ii) choosing to avail the "benefit of accelerated

depreciation" under the Income Tax Act. According to the first

respondent, the stipulation under the First Tariff Order that the tariff

fixed there under is not applicable to those Projects which "do not get

such benefit, the Commission would on a petition in that respect

determine a separate tariff taking into account all the relevant facts

from not" would only imply that tariff fixed under the First Tariff

Order is not applicable to those Projects/power producers which do

not avail the "benefit of accelerated depreciation" under the Income

Tax Act.

xxxxxx xxxxxx xxxxxx

33

13. We have already noticed that the first respondent did not

commence generation of power within the "control period" stipulated

under the First Tariff Order and also did not avail the "benefit of the

accelerated depreciation" under the Income Tax Act. It is admitted on

all hands that the "benefit of accelerated depreciation" mentioned in

the First Tariff Order and the PPA is the stipulation contained in

Section 32(1)(i) of the Income Tax Act read with Rule 5(1-A) of the

Income Tax Rules. They provide for the method and manner in which

depreciation of the assets of an assessee is to be calculated.

xxxxxx xxxxxx xxxxxx

26. Apart from that, the conclusion of the Tribunal in the instant case

is wrong. First of all the PPA does not give any option to the

respondent to opt out of the terms of the PPA. It only visualises a

possibility of the producer not commissioning its Project within the

"control period" stipulated under the First Tariff Order and provides

that in such an eventuality what should be the tariff applicable to the

sale of power by the first respondent. Secondly, the PPA does not

"entitle" the first respondent to the "tariff as determined by the"

second respondent by the Second Tariff Order. On the other hand, the

PPA clearly stipulates that in such an eventuality:

"Above tariff shall apply for solar projects commissioned on or

before 31-12-2011. In case, commissioning of solar power project is

delayed beyond 31-12-2011, GUVNL shall pay the tariff as

determined

by the Hon'ble GERC for solar projects effective on the date of

commissioning of solar power project or abovementioned tariff,

whichever is lower."

(emphasis supplied)”

50.In Transmission Corporation of Andhra Pradesh Ltd (Supra), the state

commission had, by an order dated 20.06.2001 directed generators of non-

conventional energy to supply power exclusively to the A.P. Transmission

Corporation. Energy developers were not permitted to sell power to third

parties. The Commission also approved the rate prevailing earlier for supply @

2.25/- per unit with a 5% escalation per annum from 1994-1995 being the

base year. The parties entered into PPA after the passing of the Regulatory

Commission’s order. The PPA embodied or reflected the tariff @ 2.25/- per

34

unit with escalation @ 5% per annum having 1994 as the base year to be revised

annually upto 2003-04. After that, the purchase price was to be decided by the

state commission. The stipulation also provided that further review of the

purchase price on the completion of 10 years from the commissioning of the

project would be made.

51.The A.P. Transmission Corporation’s functions devolved upon discoms

by operation of law. In this background, the state commission exercised suo

motu powers to revise non-conventional energy purchase tariffs. The APTEL

rejected the appeal of the A.P. Transmission Corporation. This court held that

once agreements were signed and were enforceable in law, such enforceable

obligations could not be frustrated. The court also negatived the arguments on

behalf of the power generator that they had been subjected to coercion or

duress. The observations of this court in this regard are pertinent in this regard

and are extracted below:

“39. [..] In the present case the order dated 20-6-2001 was fully

accepted by

the parties without any reservation. After the lapse of more than

reasonable time of their own accord they voluntarily signed the PPA

which contained a specific stipulation prohibiting sale of generated

power by them to third parties. The agreement also had a renewal

clause empowering TRANSCO/ APTRANSCO/Board to revise the

tariff. Thus, the documents executed by these parties and their conduct

of acting upon such agreements over a long period, in our view, bind

them to the rights and obligations stated in the contract. The parties

can hardly deny the facts as they existed at the relevant time, just

because it may not be convenient now to adhere to those terms.

Conditions of a contract cannot be altered/avoided on presumptions

or assumptions or the parties having a second thought that a term of

contract may not be beneficial to them at a subsequent stage. They

would have to abide by the existing facts, correctness of which, they

35

can hardly deny. Such conduct, would be hit by allegans contraria

non est audiendus.”

-----------------------------

42. Now, we will proceed to examine the merits or otherwise of the

findings recorded by the Tribunal that the PPAs executed by the

parties were result of some duress and thus, it will not vest the

authorities with the power to review the tariff and other granted

incentives. PPAs were executed prior and subsequent to the issuance

of the order dated 20-6 2001. Different persons executed the contracts

at different times in full awareness of the terms and conditions of such

PPAS. To frustrate a contract on the ground of duress or coercion,

there have to be definite pleadings which have to be substantiated

normally by leading cogent and proper evidence. However, in the case

where summary procedure is adopted like the present one, at least

some documentary evidence or affidavit ought to have been filed

raising this plea of duress specifically.

43. [..] From the record before us, nothing was brought to our notice

to state the plea of duress and to prove the alleged facts which

constituted duress, so as to vitiate and/or even partially reduce the

effect of the PPAs. On the one hand, the Tribunal appears to have

doubted the binding nature of the contracts stating that they contained

unilateral conditions introduced by virtue of order and approval of the

Regulatory Commission, while on the other hand, in para 53 of the

order, it proceeded on the presumption that PPAS are final and

binding and still drew the conclusion that the Regulatory Commission

could not revise the tariff. Even in the order, no facts have been

pointed out which, in the opinion of the Tribunal, constituted duress

within

the meaning of the Contract Act so as to render the contract

voidable.”

52.In Gujarat Urja v. Solar Power Company India Pvt. Ltd.

30

(hereafter

“Solar Power Company India Pvt. Ltd”), the issue involved was whether the

State Commission could extend the control period. One of the arguments made

was that having regard to the terms of the PPA, the exercise of such power to

extend the control period was not available under the statute. The Court (per

Kurian Joseph, J) referred to Gujarat Urja Vikas Nigam Ltd. v. Tarini

Infrastructure Ltd.

31

wherein it was held that:

30 (2017) 14 S.C.R. 115

31 (2016) 5 S.C.R. 990

36

“10. While Section 61 of the Act lays down the principles for

determination of tariff, Section 62 of the Act deals with different kinds

of tariffs/charges to be fixed. Section 64 enumerates the manner in

which determination of tariff is required to be made by the

Commission. On the other hand, Section 86 which deals with the

functions of the Commission reiterates determination of tariff to be

one of the primary functions of the Commission which determination

includes, as noticed above, a regulatory power with regard to

purchase and procurement of electricity from generating companies

by entering into PPA(s). The power of tariff determination/fixation

undoubtedly is statutory and that has been the view of this Court

expressed in paras 36 and 64 of A.P. TRANSCO v. Sai Renewable

Power (P) Ltd. This, of course, is subject to determination of price of

power in open access (Section 42) or in the case of open bidding

(Section 63). In the present case, admittedly, the tariff incorporated in

PPA between the generating company and the distribution licensee is

the tariff fixed by the State Regulatory Commission in exercise of its

statutory powers. In such a situation it is not possible to hold that the

tariff agreed by and between the parties, though finds mention in a

contractual context, is the result of an act of volition of the parties

which can, in no case, be altered except by mutual consent. Rather, it

is a determination made in the exercise of statutory powers which got

incorporated in a mutual agreement between the two parties involved.

********** ***********

This Court in Solar Power Company India Pvt. Ltd(Supra)further

observed that:

35. This Court should be specially careful in dealing with matters of

exercise of inherent powers when the interest of consumers is at stake.

The interest of consumers, as an objective, can be clearly ascertained

from the Act. The Preamble of the Act mentions "protecting interest of

consumers" andSection61 (d) requires that the interests of the

consumers are to be safeguarded when the appropriate Commission

specifies the terms and conditions for determination of tariff. Under

Section 64 read with Section 62, determination of tariff is to be made

only after considering all suggestions and objections received from

the public. Hence, the generic tariff once determined under the statute

with notice to the public can be amended only by following the same

procedure. Therefore, the approach of this Court ought to be cautious

and guarded when the decision has its bearing on the consumers.

36. Regulation 85 provides for extension of time. It may be seen that

the same is available only in two specified situations - (i) for extension

of time prescribed by the Regulations, and (ii) extension of time

prescribed by the Commission in its order for doing any act. The

control period is not something prescribed by the Commission under

37

the Conduct of Business Regulations. The control period is also not an

order by the Commission for doing any act. Commissioning of a

project is the act to be performed in terms of the obligation under the

PPA and that is between the producer and the purchaser viz.

Respondent 1 and appellant. Hence, the Commission cannot extend

the time stipulated under the PPA for doing any act contemplated

under the agreement in exercise of its powers under Regulation 85.

Therefore, there cannot be an extension of the control period under

the inherent powers of the Commission.

37. The Commission being a creature of statute cannot assume to

itself

any powers which are not otherwise conferred on it. In other words,

under the guise of exercising its inherent power, as we have already

noticed above, the Commission cannot take recourse to exercise of a

power, procedure for which is otherwise specifically provided under

the Act.”

53.The concurring view expressed by Banumathi J, crucially held that:

“Sanctity of power purchase agreement

22. It is contended that Section 86(1)(b) of the Act empowers the State

Commission to regulate the price of sale and purchase of electricity

between the generating companies and distribution licensees and the

terms and conditions of the PPA cannot be set to be inviolable. Merely

because in PPA, tariff rate as per Tariff Order, 2010 is incorporated

that does not empower the Commission to vary the terms of the

contract to the disadvantage of the consumers whose interest the

Commission is bound to safeguard. Sanctity of PPA entered into

between the parties by mutual consent cannot be allowed to be

breached by a decision of the State Commission to extend the earlier

control period beyond its expiry date, to the advantage of the

generating company, Respondent 1 and disadvantage of the appellant.

Terms of PPA are binding on both the parties equally.

66. In Gujarat Urja Vikas Nigam Ltd. v. EMCO Ltd., facts were

similar and the question of law raised was whether by passing the

terms and conditions of PPA, the respondent can assail the sanctity of

PPA. This Court held that power producer cannot go against the

terms of the PPA and that as per the terms of the PPA, in case, the

first respondent is not able to commence the generation of electricity

within the "control period" the first respondent will be entitled only

for lower of the tariffs.”

38

54.Similarly, in Bangalore Electricity Supply Co. Ltd. vs. Konark Power

Projects Ltd. & Ors

32

this court held as follows: 

“13. The contention that Under Regulations 5.2, 5.3, 5.4 of the 2004

Regulations as well as Sections 61 and 62 of the Electricity Act, power

is vested with the Commission to vary the tariff is concerned, such

power specifically provided for in the said Regulations will only

operate prior to fixing of the tariff once the concerned Power

Purchase Agreements are ultimately concluded and the terms are

agreed between the parties under the Power Purchase Agreements,

thereafter, in our considered opinion, Regulation 5.1 of the 2004

Regulations alone would apply in the case of the parties before us.

Consequently, there was no scope for the Commission to vary the

tariff agreed between the parties under the approved Power Purchase

Agreement.”

55.Section 61 of the Act enacts the basis for tariff determination. On the

other hand, Section 62 is concerned with the fixation of various other charges

and tariffs. Section 64 lists the manner and procedure for tariff determination by

the Commission. Section 86 lists the functions of the Commission and reiterates

the determination of tariffs to be a prominent task of the commission. Tariff

determination no doubt, comprehends the exercise of regulatory function,

including purchase, sourcing, procurement of electricity from generators, by

distribution and other licensees, and their sales. This part involves generating

companies entering into PPA(s) with procuring entities or licensees. Tariff

fixation is a statutory function. Yet, by virtue of Section 42, it is subject to open

access determination of the price of power, and subject to Section 63 wherever

it involves open bidding. In the facts of this case, the PPA incorporated a tariff

between the respondents and Gujarat Urja constituted the tariff fixed by the

32  (2016) 13 SCC 515

39

State Regulatory Commission in the exercise of its statutory powers. The issue

and sale of RECs, constituted an important part of that bargain, between the two

parties, based on the assessment of their commercial interest.

56.The important feature of the REC Mechanism is that in it, WPDs (i.e.

respondents) had to sell power to distribution licensees at a mutually agreed

price, not exceeding the Average Power Purchase Cost ('APPC') of the

DISCOMs, (such as Gujarat Urja). The WPDs were entitled to the additional

benefit of Renewable Energy Certificates issued to it which could be traded in

Power Exchange for a price. The consideration payable to WPDs consisted of

firstly, a mutually agreed power Component and secondly a green component

through RECs traded in the Exchange. The alternative to the WPDs was to sell

to licensees at a preferential tariff, determined by the state commission. In the

latter event, WPDs were not entitled to the additional benefit of the green

component, which was the tradable RECs the sale of which would have led to

increased revenues. The respondent WPDs chose the REC mechanism, while

entering into PPAs in these cases, with Gujarat Urja. The PPAs entered by

WPDs provided for the fixed tariff of ₹2.64/kWh for the entire term (25 years),

as mutually agreed (Article 5.2 of PPA). WPDs were entitled to and were

trading RECs in the power exchange, deriving extra monetary benefits: which,

at the relevant period was ₹ 1.50/kWh (floor price at the time of signing of

PPA). The Preferential Tariff determined by the state commission, for WPDs

not opting for the REC Mechanism was ₹ 3.56/kWh. The WPDs were not

40

entitled to any additional REC benefits, had they adopted the preferential tariff

route.

57.The respondents successfully complained before the State Commission,

and APTEL, that the PPA, which they had entered into with Gujarat Urja,

whereby the tariff was fixed at 2.64/kWh (with the price of RECs sold by

them) was, in the long run, less beneficial than

3.56/kWh. During the hearing,

it was sought to be urged that the cost of RECs in the exchange, had been

decreasing, whereas the preferential tariffs had risen. On this aspect, Regulation

9 of the REC Regulations 2010 prescribes the price determination mechanism

for RECs in the power exchange. Proviso to Regulation 9 (1) of the REC

Regulations 2010 empowers the central commission, in consultation with the

Central Agency and the Forum of Regulators, to provide the floor price and

forbearance price separately for solar and non-solar certificates. This provision

is important because it enables regulatory intervention in the public interest: if

the price went below a certain limit, the floor price was to be prescribed, to take

care of the interests of generators- like the respondents; if the price went too

high, a forbearance price could be fixed, to take care of the interests of the

consumers and distributors. By Regulation 9 (2) of the REC Regulations 2010,

the Central Commission, was to be guided, in determining the floor and

forbearance price, by diverse factors, such as (a) variation in cost of generation

of different renewable energy technologies falling under solar and non-solar

41

category, across states in the country; (b) variation in the Pooled Cost of

Purchase across States in the country; (c) Expected electricity generation for

non-renewable energy sources [including (i) expected renewable energy

capacity under preferential tariff (ii) expected renewable energy under

mechanism of certificates] (d) Renewable purchase obligation targets set by

various State Commissions. By virtue of Explanation to Regulation 5 (1) of the

REC Regulations, “the weighted average pooled price at which the distribution

licensee has purchased the electricity including cost of self-generation, if any,

in the previous year from all the energy suppliers long-term and short-term, but

excluding those based on renewable energy sources, as the case may be.” An

important factor which cannot be lost sight of is that all the respondent’s WPDs

were registered, under the REC Regulations, based on the state commission’s

tariff order, of 2010. It is undisputed, that to register under the REC Regulations

2010, an entity (such as WPDs) had to be (a) accredited, with a State Agency

[(defined by Regulation 2 (n) of the REC Regulations as an agency “designated

by the State Commission to act as the agency for accreditation and

recommending the renewable energy projects for registration”) and an entity

“not having any power purchase agreement for the capacity related to such

generation to sell electricity at a preferential tariff determined by the

Appropriate Commission].

58.Furthermore, the state commission, in its tariff order, dated 30.01.2010

(which was operative for three years, with the control period beginning from

42

10.08.2009) while determining the preferential tariff, had observed that it would

apply for 25 years:

“The Commission, therefore, determines the tariff for generation of

electricity from wind energy projects at Rs.3.56 (constant) for its

entire project life of 25 years i.e. from the first year to the twenty fifth

year. This tariff shall be applicable for purchase of wind energy by

Distribution Licensees/ other entities for complying with the

renewable power purchase obligations specified in the regulation by

commission from time to time. This tariff is applicable to wind energy

projects which commission brand new wind energy plants and

equipments on 11th August, 2009 onwards.”

59.In the present case, the PPA was entered into by the parties on

29.03.2102, within the control period stipulated in the tariff order of 2010. The

change in the REC Regulations 2010, whereby the Explanation to Regulation 5

was amended resulted in a change. The pre-existing clause that the power would

be "at a price not exceeding pooled cost of the power purchase" was altered to

"at the pooled cost of power purchase". This change, was through the Second

Amendment (to the REC Regulations), carried out on 10.07.2013. It is a matter

of record, that for the period between 29.03.2102 and 10.07.2013 - and indeed,

after the Second Amendment, no difficulty was experienced in the pricing

mechanism agreed by the parties, under the PPA. It was on 10.12.2013 that the

respondent WPD approached the state commission for re-determination of

tariff. Clearly, this was an opportunistic attempt to derive advantage from the

change, brought about by the Second Amendment, and seek to have it applied to

an existing contract, which cannot be countenanced. In view of these reasons, it

43

is held that the reasoning of APTEL, and the State Commission cannot be

upheld.

Applicability of the Second Amendment to pre-existing contracts- the general

law

60.Power Purchase Agreements are essentially not statutory contracts;

however, certain terms contained in those contracts, are regulated by law, i.e.

applicable regulations, under the Act. The PPA between a generating company

or, as in this case, a wind generator, and a distribution licensee, such as Gujarat

Urja, is the outcome of a carefully considered decision, whereby the parties,

after due deliberations and negotiations, agree on terms, which are based on

existing law and regulations. Aside from contending that the PPA had to be

approved, (which this court has rejected in a previous part of this judgment) but

was not, the respondents also urge, independently, that the Second Amendment

had necessitated re-visiting of the terms of the PPA, relating to the payment of

average pooled power purchase cost, given that the amendment mandated that

the power would be at the pooled power purchase cost, as opposed to the

previous provision, which stated that the cost would not exceed the pooled

power purchase cost.

61.Regulation 1 (2) of the Second Amendment clearly provides that the

amendments were to come into force from the date of their publication in the

Official Gazette, which is 10

th

July, 2013. Furthermore, the Statement of

44

Reasons, accompanying the Second Amendment, clarified that existing PPAs

were not affected:

“Some of the stakeholders have suggested to clarify as to whether the

PPAs executed at price lower than APPC would become ineligible

under REC Mechanism. It is felt that the tariff for electricity

component lower or higher than APPC may lead to avoidable loss or

profit to RE generator. The Commission would like to clarify that the

intention is not to debar the projects that have executed PPA at tariff

lower than APPC. This amendment will apply prospectively and as

such will not affect the already executed PPAs at lower than APPC.”

62.The Constitution Bench of this Court, in PTC India (supra) had indicated

that state commissions possess the power to vary existing contracts, especially

PPAs:

“40. [..] To regulate is an exercise which is different from making of

the regulations. However, making of a regulation under Section 178 is

not a precondition to the Central Commission taking any

steps/measures under Section 79(1). As stated, if there is a regulation,

then the measure under Section 79(1) has to be in conformity with

such regulation under Section 178. This principle flows from various

judgments of this Court, which we have discussed hereinafter. For

example, under Section 79(1)(g), the Central Commission is required

to levy fees for the purpose of the 2003 Act. An order imposing

regulatory fees could be passed even in the absence of a regulation

under Section 178. If the levy is unreasonable, it could be the subject-

matter of challenge before the appellate authority under Section 111

as the levy is imposed by an order/decision-making process. Making

of a regulation under Section 178 is not a precondition to passing of

an order levying a regulatory fee under Section 79(1)(g). However, if

there is a regulation under Section 178 in that regard then the order

levying fees under Section 79(1)(g) has to be in consonance with such

regulation.

*********

40. [..] One must keep in mind the dichotomy between the power to

make a regulation under Section 178 on the one hand and the various

enumerated areas in Section 79(1) in which the Central Commission

is mandated to take such measures as it deems fit to fulfil the objects

of the 2003 Act. Applying this test to the present controversy, it

becomes clear that one such area enumerated in Section 79(1) refers

to fixation of trading margin. Making of a regulation in that regard is

not a precondition to the Central Commission exercising its powers to

fix a trading margin under Section 79(1)(j), however, if the Central

45

Commission in an appropriate case, as is the case herein, makes a

regulation fixing a cap on the trading margin under Section 178 then

whatever measures the Central Commission takes under Section 79(1)

(j) have to be in conformity with Section 178. One must understand

the reason why a regulation has been made in the matter of capping

the trading margin under Section 178 of the Act. Instead of fixing a

trading margin (including capping) on a case-to-case basis, the

Central Commission thought it fit to make a regulation which has a

general application to the entire trading activity which has been

recognised, for the first time, under the 2003 Act. Further, it is

important to bear in mind that making of a regulation under Section

178 became necessary because a regulation made under Section 178

has the effect of interfering and overriding the existing contractual

relationship between the regulated entities. A regulation under

Section 178 is in the nature of a subordinate legislation. Such

subordinate legislation can even override the existing contracts

including power purchase agreements which have got to be aligned

with the regulations under Section 178 and which could not have been

done across the board by an order of the Central Commission under

Section 79(1)(j).

*********

43. [..] While deciding the nature of an order (decision) vis-à-vis a

regulation under the Act, one needs to apply the test of general

application. On the making of the impugned 2006 Regulations, even

the existing power purchase agreements (PPA) had to be modified and

aligned with the said Regulations. In other words, the impugned

Regulations make an inroad into even the existing contracts. This

itself indicates the width of the power conferred on CERC under

Section 178 of the 2003 Act. All contracts coming into existence after

making of the impugned 2006 Regulations have also to factor in the

capping of the trading margin. This itself indicates that the impugned

Regulations are in the nature of subordinate legislation. Such

regulatory intervention into the existing contracts across the board

could have been done only by making regulations under Section 178

and not bypassing an order under Section 79(1)(j) of the 2003 Act.

Therefore, in our view, if we keep the above discussion in mind, it

becomes clear that the word “order” in Section 111 of the 2003 Act

cannot include the impugned 2006 Regulations made under Section

178 of the 2003 Act.”

63.Whilst there cannot be any doubt that regulations framed under the Act

can be made applicable to existing contracts, what is discernible from PTC

India (supra) is that in that case, the applicability of the Trading Margin

Regulations which for the first time, compelled persons engaged in trading of

46

electricity, in terms of Section 2 (17) of the Act, to register, obtain licenses, and

operate within the margin limits indicated in the regulations. These provisions

introduced a new regime, regulating an area, or activity which had hitherto been

unregulated. The entire edifice of prescribing general standards for application

to all those operating within its sweep, is to ensure that they are universal and

constitute a code. The observations in PTC India (supra), therefore, are to be

seen in this context. Being regulations of general application, dealing with a

range of commercial activity, there could have been no question of existing

contracts, operating in isolation, through separate silos, outside of their

framework. In the present case, however, the PPAs were entered into in the

exercise of equal bargaining power, after due negotiation by the parties, and

within the framework of existing regulations: both central and state. Therefore,

unless any later amendment expressly overrides existing contracts, the terms of

such agreements bind the parties.

64.That amendments to laws, or regulations, unless expressly retrospective,

are always prospective, is a settled proposition. In Purbanchal Cables &

Conductors (P) Ltd. v. Assam State Electricity Board & Ors.

33

, the position was

articulated in this manner:

“39. [..] This Court, time and again, has observed that any

substantive law shall operate prospectively unless retrospective

operation is clearly made out in the language of the statute. Only a

procedural or declaratory law operates retrospectively as there is no

vested right in procedure.

33 (2012) 6 S.C.R. 905

47

40. In the absence of any express legislative intendment of the

retrospective application of the Act, and by virtue of the fact that the

Act creates a new liability of a high rate of interest against the buyer,

the Act cannot be construed to have retrospective effect. Since the Act

envisages that the supplier has an accrued right to claim a higher rate

of interest in terms of the Act, the same can only be said to accrue for

sale agreements after the date of commencement of the Act i.e. 23-9-

1992 and not any time prior.”

65.In Commissioner of Income Tax v Vatika Township (P) Ltd.

34

, this court

observed, in this context, that:

“31. Of the various rules guiding how a legislation has to be

interpreted, one established rule is that unless a contrary intention

appears, a legislation is presumed not to be intended to have a

retrospective operation. The idea behind the rule is that a current law

should govern current activities. Law passed today cannot apply to

the events of the past. If we do something today, we do it keeping in

view the law of today and in force and not tomorrow's backward

adjustment of it. Our belief in the nature of the law is founded on the

bedrock that every human being is entitled to arrange his affairs by

relying on the existing law and should not find that his plans have

been retrospectively upset. This principle of law is known as lex

prospicit non respicit : law looks forward not backward. As was

observed in Phillips v. Eyre [Phillips v. Eyre, (1870) LR 6 QB 1], a

retrospective legislation is contrary to the general principle that

legislation by which the conduct of mankind is to be regulated when

introduced for the first time to deal with future acts ought not to

change the character of past transactions carried on upon the faith of

the then existing law.

32. The obvious basis of the principle against retrospectivity is the

principle of “fairness”, which must be the basis of every legal rule as

was observed in [L'Office Cherifien des Phosphates v. Yamashita-

Shinnihon Steamship Co. Ltd., (1994) 1 All ER 20 (HL)] Thus,

legislations which modified accrued rights or which impose

obligations or impose new duties or attach a new disability have to be

treated as prospective unless the legislative intent is clearly to give the

enactment a retrospective effect; unless the legislation is for purpose

of supplying an obvious omission in a former legislation or to explain

a former legislation. We need not note the cornucopia of case law

available on the subject because aforesaid legal position clearly

emerges from the various decisions and this legal position was

conceded by the counsel for the parties. In any case, we shall refer to

few judgments containing this dicta, a little later.”

34 (2014) 12 S.C.R. 1037

48

This proposition was again explained and applied in Union of India v.

Indusind Bank Ltd

35

.

66.In view of the above discussion, it is held that agreements, such as the

PPAs in the present case, entered into, voluntarily by the parties, before the

Second Amendment, were not affected, by its terms. The findings to the

contrary in the impugned order, are set aside.

Were the respondents coerced into entering into PPAs

67.The State Commission had concluded that the PPAs were also

unenforceable, to the extent of being in non-conformity with the pre-amended

Rule 5, of the REC Regulations, as the contracts were entered into by parties

with unequal bargaining power. This aspect was noted by APTEL, which held

as follows:

“9.19 [..] The State Commission after careful consideration of the

submissions made by both the parties and after due analysis of the

available material on record has recorded its findings in the

impugned order that the conditions envisaged in the PPA relating to

the tariff and other associated conditions appeared to be one sided in

favour of the Appellant and accordingly concluded the case of

coercion or duress and unequal bargaining power between the parties

being responsible for executing an Agreement full of unjustness and

perversity. In view of these facts, we hold that the State Commission

has analysed this issue rightly in accordance with law and passed the

order assigning cogent reasoning. Thus, we do not find any material

case or ground for our interference in the matter.

10. SUMMARY OF OUR FINDINGS:

Having regard to the careful consideration and critical analysis of the

facts and submissions of the learned counsel for the Appellants as

well as the Respondents, we hold that the findings of the State

Commission are just and right in accordance with law.”

35 (2016) 11 S.C.R. 700

49

68.In Transmission Corporation of Andhra Pradesh Ltd (supra), this court

observed, in the context of a contention of coercion, as follows:

“42. [..] To frustrate a contract on the ground of duress or coercion,

there have to be definite pleadings which have to be substantiated

normally by leading cogent and proper evidence. However, in the case

where summary procedure is adopted like the present one, at least

some documentary evidence or affidavit ought to have been filed

raising this plea of duress specifically.[..]”

69.In Shanti Budhiya Vesta Patel & Ors. v. Nirmala Jayprakash Tiwari&

Ors.

36

, this court held that to establish fraud or coercion, there should be“(a) an

express allegation of coercion or fraud, and (b) all the material facts in support

of such allegations must be laid out in full and with a high degree of precision.

In other words, if coercion or fraud is alleged, it must be set out with full

particulars.” The court had cited and applied the principle enunciated in

Bishundeo Narain v. Seogeni Rai

37

where it was held that:

“ […] Now if there is one rule which is better established than any

other, it is that in cases of fraud, undue influence and coercion, the

parties pleading it must set forth full particulars and the case can only

be decided on the particulars as laid. There can be no departure from

them in evidence. General allegations are insufficient even to amount

to an averment of fraud of which any court ought to take notice,

however strong the language in which they are couched may be, and

the same applies to undue influence and coercion. [See Order 6 Rule

4 of the Civil Procedure Code.]”

70.In New Indian Assurance Co. Ltd v Genus Power Infrastructure Ltd

38

this

court dealt with the standard of pleadings and evidence, needed in cases, where

coercion or duress is alleged:

36 (2010) 4 S.C.R. 958

37 (1951) 1 SCR 548

38 2014 (12) SCR 360

50

"8. It is therefore clear that a bald plea of fraud, coercion, duress or

undue influence is not enough and the party who sets up a plea, must

prime facie establish the same by placing material before the Chief

Justice/his designate.”

71.In the present case, this salutary rule was thrown to the wind, by the State

Commission. In this court’s opinion, APTEL, in the most cavalier fashion,

virtually rubber stamped the State Commission’s findings on coercion, in regard

to the entering into the PPA by the parties. There was no shred of evidence, nor

any particularity of pleadings, beyond a bare allegation of coercion, alleged

against Gujarat Urja. It is incomprehensible how such an allegation could have

been entertained and incorporated as a finding, given that the respondents are

established companies, who enter into negotiations and have the support of

experts, including legal advisers, when contracts are finalized. The findings

regarding coercion are, therefore, wholly untenable. This court is also of the

opinion that the casual approach of APTEL, in not reasoning how such findings

could be rendered, cannot be countenanced. As a judicial tribunal, dealing with

contracts and bargains, which are entered into by parties with equal bargaining

power, APTEL is not expected to casually render findings of coercion, or fraud,

without proper pleadings or proof, or without probing into evidence. The

findings of coercion are therefore, set aside.

Conclusions

72.In view of the foregoing discussion, it is held that the concurrent findings

and orders of the State Commission and APTEL cannot be sustained. They are

51

accordingly set aside. The appeals are allowed, with costs payable to the

appellants.

.................................................J.

[SANJAY KISHAN KAUL]

................................................J.

[S. RAVINDRA BHAT]

...............................................J.

[M. M. SUNDRESH]

New Delhi,

April 13, 2023

52

ITEM NO.1501 COURT NO.13 SECTION XVII

S U P R E M E C O U R T O F I N D I A

RECORD OF PROCEEDINGS

Civil Appeal No(s). 3480-3481/2020

GUJARAT URJA VIKAS NIGAM LIMITED & ORS. Appellant(s)

VERSUS

RENEW WIND ENERGY (RAJKOT) PRIVATE LIMITED & ORS.Respondent(s)

([ HEARD BY HON'BLE SANJAY KISHAN KAUL, HON'BLE S. RAVINDRA

BHAT AND HON'BLE M.M. SUNDRESH ,JJ. ]

IA No. 77529/2020 - GRANT OF INTERIM RELIEF)

Date : 13-04-2023 These matters were called on for hearing

today.

For Appellant(s) Ms. Hemantika Wahi, AOR

Ms. Jesal Wahi, Adv.

Ms. Srishti Khindaria, Adv.

For Respondent(s) Ms. Nishtha Kumar, AOR

Mr. Vishal Gupta, AOR

Mr. Nikilesh Ramachandran, AOR

Mr. Nitin Saluja, AOR

UPON hearing the counsel the Court made the following

O R D E R

Hon’ble Mr. Justice S. Ravindra Bhat pronounced the

reportable judgment of the Bench comprising Hon’ble Mr.

Justice Sanjay Kishan Kaul, His Lordship and Hon’ble Mr.

Justice M.M. Sundresh.

It is held that the concurrent findings and orders of the

State Commission and APTEL cannot be sustained. They are

accordingly set aside. The appeals are allowed, with costs

payable to the appellants in terms of the reportable judgment.

Pending application(s), if any, are disposed of.

53

(HARSHITA UPPAL) (MATHEW ABRAHAM)

SENIOR PERSONAL ASSISTANT COURT MASTER (NSH)

(Original signed Reportable Judgment is placed on the

file)

Reference cases

Description

Legal Notes

Add a Note....