As per case facts, Petitioner challenged the technical evaluation and declaration of Respondent No.6 as L-1 for a road construction project, alleging non-disclosure of debarment, criminal cases, and incomplete projects ...
THE HIGH COURT OF SIKKIM : GANGTOK
(Civil Extraordinary Jurisdiction)
---------------------------------------------------------------------------------------------------
SINGLE BENCH : THE HON’BLE MRS. JUSTICE MEENAKSHI MADAN RAI, JUDGE
---------------------------------------------------------------------------------------------------
WP(C) No.75 of 2025
Petitioner : Hill Brow Metallics & Construction Pvt. Ltd.
versus
Respondents : Ministry of Defence and Others
Application under Article 226 of the Constitution of India
-----------------------------------------------------------------------------------------------
Appearance
Mr. Tarique Sidique, Mr. Norzang Lepcha and Ms. Nima Phuti Lepcha,
Advocates for the Petitioner.
Ms. Sangita Pradhan, Deputy Solicitor General of India for the
Respondents No.1 to 5.
Mr. Sudesh Joshi, Advocate for the Respondent No.6.
-----------------------------------------------------------------------------------------------
Date of hearing : 01-12-2025
Order reserved : 01-12-2025
Order pronounced & uploaded : 03-12-2025
ORDER
Meenakshi Madan Rai, J.
1. In the instant Petition, the Petitioner seeks an interim
relief, viz.;
“Stay the impugned letter/Summary of Technical Evaluation
dated 04.10.2025 issued by the respondent no.5 whereby
the technical committee of respondent no.5 has illegally,
unlawfully, arbitrarily and wrongly evaluated bid documents
of respondent no.6 during the technical evaluation and all
consequential actions/proceedings including issuance of
Letter of Acceptance (LoA) to Respondent No.6 who has
been illegally and arbitrarily declared as L-1.”
2. Learned Counsel for the Petitioner submits that the
Respondent No.5 the Chief Engineer, Border Roads Organisation,
invited bids from eligible contractors for the construction and
improvement of Rishi-Rongli-Kupup road in East Sikkim, as
detailed in the Request for Proposal (RFP) [Annexure P-2] to the
Petition. Both the Petitioner and the Respondent No.6 , M/s
Rajinder Infrastructure Private Limited participated in the tender
WP(C) No.75 of 2025
Hill Brow Metallics & Construction Pvt. Ltd. vs. Ministry of Defence and Others 2
process relating to the Tender ID No.2025_BRO_706797_1. The
technical committee of the Respondent No.5, vide the Summary of
Technical Evaluation, dated 04-10-2025, illegally and arbitrarily
declared Respondent No.6, M/s Rajinder Infrastructure Private
Limited, as qualified in the technical bid despite it not meeting the
requirements thereof and permitted it to participate in the next
stage of bidding. The Respondent No.5 then declared that the
financial bids of all technically responsive bidders would be opened
on 11-10-2025, at 1700 hours. Thereafter, without following due
process the financial bids were opened on 22-10-2025 declaring
Respondent No.6 as L-1. It is canvassed by Learned Counsel for
the Petitioner that the technical bid of Respondent No.6 is required
to be set aside as illegal and arbitrary the selection of Respondent
No.6 being in violation of the terms of the technical requirements
of the Request for Proposal (RPF) consideration. That, the
Respondent No.6 in the “Integrity Pact Format” filed along with its
documents had declared that it had no previous transgressions in
the last three years, immediately before signing of the Integrity
Pact, which could justify its exclusion from the tender process
which is contrary to records.
(i) That, Clause 2.1.14 of the RFP specifically lays down
that the bidder shall be deemed to be a non-performing party, if it
attracts any or more of the conditions detailed in the clause, in any
of its ongoing or completed projects. The paragraph below sub -
Clause (xx) of Clause 2.1.14 provides that, the bidder shall give
the list of projects of Expressways, National Highways, works of
Ministry of Road Transport and Highways, or it’s implementing
agencies (NHAI/NHIDCL/State PWDs/BRO) and the status of the
each project and on the bid submission date undertake that they
WP(C) No.75 of 2025
Hill Brow Metallics & Construction Pvt. Ltd. vs. Ministry of Defence and Others 3
do not attract any of the above categories. It is clarified that the
categories indicated in the paragraph (supra) includes the
categories detailed in Clause 2.1.14 (i) to (xx). All bidders were
also to give not only the details of ongoing projects but also details
of updated ongoing process of black listing if any under any
contract with the authority and the Government.
(ii) It was urged by Learned Counsel that the Respondent
No.6 had not disclosed relevant information pertaining to its
debarment by a public undertaking being Greater Mohali Area
Development Authority (GMADA) and Punja b Urban Development
Authority (PUDA) from carrying out contract works or the fact that
a criminal case was registered against Gurinder Pal Singh , who
holds 99.95% shares of the Respondent No.6 Company . The
information pertaining to Charge-sheet filed against Respondent
No.6 Company and Gurinder Pal Singh under Section 420 of the
Indian Penal Code and Prevention of Money Laundering Act, 2002,
was also concealed. Relying on Annexure P-8, P-9 and P-12,
Learned Counsel submitted that Respondent No.5 failed to take
into consideration that Respondent No.6 was entrusted with the
construction of high altitude road to Indo-China Border from Dorjila
Base, which was to commence from 07 -12-2021 and to be
completed by 25-05-2024. This project is still incomplete but
information pertaining to such incompletion was not furnished by
Respondent No.6 to Respondent No.5, who has overlooked this
shortcoming. In another contract pertaining to construction of high
altitude road to Indo-China Border from Kerang, the project was to
commence from 18 -12-2021 and was to be completed on 26-05-
2024. The Petitioner has failed to complete it on the scheduled
date as also construction of ITBP high altitude road to Indo-China
WP(C) No.75 of 2025
Hill Brow Metallics & Construction Pvt. Ltd. vs. Ministry of Defence and Others 4
Border from Leema which was to commence from 10 -11-2022 and
the date of completion is 03-01-2026. In the last contract the
progress of the work is not in terms of the area to be covered and
flies in the face of details required by Annexure P-7.
(iii) That, it is in such circumstances that the interim relief
(supra) is being sought, as Respondent No.5 failed to take steps
despite the Petitioner have issued an e-mail to them firstly on 12-
11-2025 and thereafter on detecting defects and rectifying the
errors, sent a repeat e-mail on 15-11-2025 at 11.29 a.m .,
regardless of which further steps were taken by Respondent No.5
in favour of Respondent No.6.
3. Learned Deputy Solicitor General of India (DSGI) for
the Respondent No.1 to 5 submitted that , there has been no
illegality or arbitrariness in the act of the Respondent No.5 who has
already issued the LoA on 17-11-2025 to the Respondent No.6.
The Learned DSGI denied knowledge of the e -mail dated 15-11-
2025.
4. Learned Counsel for the Respondent No.6 for his part
contended that after following due process and all necessary
considerations by the Respondent No.5 in terms of the R FP,
Respondent No.6 was found to be the lowest bidder and declared
as “L-1”. Consequent thereto , the LoA was issued to the
Respondent No.6 upon which steps are yet to be taken by
Respondent No.6. It was clari fied that although the Petitioner
placed reliance on Annexure P-16, i.e., the proceedings in Punjab
and Haryana High Court in M/s. Rajinder Infrastructure Pvt. Ltd. vs.
State of Punjab and Others
1
the Counsel for the Petitioner failed to
apprise this Court that the Counsel representing the Respondent
1
CWP No.7158 of 2023 (O&M) dated 03-12-2024
WP(C) No.75 of 2025
Hill Brow Metallics & Construction Pvt. Ltd. vs. Ministry of Defence and Others 5
No.6 in the said matter had conceded that both orders debarring
the Respondent No.6 by the GMADA and PUDU respectively were
not defensible and he was therefore under instructions to submit
that the said Orders be deemed to have been withdrawn.
(i) Walking this Court through the provisions of Section
41(ha) of the Specific Relief Act, 1963, it was urged that the
provision clearly lays down conditions when an injunction cannot
be granted by the Court. Strength was also drawn from the
decision of the Supreme Court in N. G. Projects Limited vs. Vinod
Kumar Jain and Others
2
, wherein the Supreme Court has cautioned
that, construction of roads is an infrastructure project, therefore
the intent of the legislature shoul d be kept in view and
infrastructure projects should not be stayed. In the said matter, it
was observed that the High Court would have been well advised to
hold its hand to “stay the construction” of the infrastructure
project. Besides, the decision as to whether the bidder satisfies
the tender condition is primarily upon the authority inviting the
bids. Reliance was also placed on Jagdish Mandal vs. State of Orissa
and Others
3
, wherein the Supreme Court observed that it is the
authority considering the tender who has to take into consideration
various points while determining the validity of the tender. This
was done by Respondent No.5 and pursuant thereto has carried
out the necessary scrutiny and the LoA was issued to the
Respondent No.6. Hence, the interim relief or the prayers sought
by the Petitioner in the Writ Petition are not tenable.
5. I have given due consideration to the rival submissions
advanced by Learned Counsel for the parties, perused the Petition
and all documents relied on by the Petitioner.
2
(2022) 6 SCC 127
3
(2007) 14 SCC 517
WP(C) No.75 of 2025
Hill Brow Metallics & Construction Pvt. Ltd. vs. Ministry of Defence and Others 6
6. It is pertinent to mention at this juncture that upon
perusal of the Petition, on the last date, an enquiry was made by
this Court with regard to the locus standi of the authorised person
of the Petitioner. Learned Counsel for the Respondent No.6
submitted that in State Bank of Travancore vs. Kingston Computers
India Private Limited
4
, the Supreme Court has observed that there
has to be evidence of a resolution passed by the Board of Directors
of the company, authorising such persons to file the representation
against the Respondents. No such documents have been furnished
by the Petitioner. Per contra the Counsel for the Petitioner invited
the attention of this Court to the affidavit filed by the authorised
person “Sonam Choda Tamang ” as also Special Power of Attorney,
wherein the said person has been authorised by the Directors of
the Petitioner Company to take all steps as detailed therein on
behalf of the Petitioner Company. The attention of this Court was
also invited to the certified true copy of the resolution passed at
the meeting of Board of Director s of Hill Brow Metallics &
Construction Pvt. Ltd. held on 03-11-2025, at 11.30 p.m. at Jora
NH-06, Road near Jora the Mall, Opposite Agriculture College Jora,
Raipur (CG) - 492012, wherein the Board resolved that Sonam
Choda Tamang was the constituted attorney of the company.
That, the Special Power of Attorney specified that, the Power of
Attorney given to Sonam Choda Tamang was issued in pursuance
to delegation of power vide resolution, dated 03-11-2025, passed
by the Board of Directors.
7. Having considered and perused the above document s, I
am of the considered view that the locus standi of the authorised
person requires no further discussion.
4
(2011) 11 SCC 524
WP(C) No.75 of 2025
Hill Brow Metallics & Construction Pvt. Ltd. vs. Ministry of Defence and Others 7
8. While considering the competing submissions advanced
by Learned Counsel for the parties, at this stage I find that the
Petitioner has made out a prima facie case to grant an interim
relief for the reason that the RFP lays down certain requisites for a
bidder to qualify and even if the Order of the Punjab and Haryana
High Court (supra) is taken into consideration, which reflects that,
the orders of debarment of the Respondent No.6 vide Orders dated
11-08-2021 and 06-07-2022 were deemed to be withdrawn as not
defensible, it appears that in the instant bid, no disclosure was
made by the Respondent No.6 with regard to details pertaining to
its ongoing contracts and the work progress as required in
Annexures of the RFP. It is also noticed that the Petitioner had
issued an e-mail to all Respondents dated 15-11-2025, at 11.29
a.m. Surprisingly on 17-11-2025, the LoA in a rather unholy hurry
was issued to the Respondent No.6. From the timelines which are
reflected hereinbelow it is evident that prior to the e-mail sent by
the Petitioner to Respondent No.5, the Respondent No.5 was taking
its time with regard to the bid and the LoA, viz., on 05-05-2025
the RFP was issued by the Respondent No.5. On 20 -06-2025 the
technical bids were opened. On 04 -10-2025 the results of
technical bids were declared. On 11-10-2025 the bids were to be
opened. On the said date the bids were not opened and the date
was extended to 22-10-2025. Even after the opening of the bids
on 22-10-2025, no steps were taken by Respondent No.5 but on
17-11-2025 immediately after the e-mails were sent to the
Respondents on 15-11-2025, the LoA was issued.
9. The submission of Learned DSGI that Respondent No.5
was not aware of the e-mails cannot be countenanced. Appositely
the LoA is not a contract, in this circumstance, reliance placed by
WP(C) No.75 of 2025
Hill Brow Metallics & Construction Pvt. Ltd. vs. Ministry of Defence and Others 8
Learned Counsel for the Respondent No.6 on N. G. Projects Limited
(supra) stating that the High Court should “stay its hand” in
matters of infrastructure development is not relevant as the
contract work has not even commenced nor has a da te been set for
such commencement. Only the LoA has been issued. It is now
settled law that issuance of L oA does not tantamount to a
concluded contract. The dates for commencement and completion
of the contract have not been specified as that stage is yet to be
reached.
10. Hence, in the fa cts and circumstances detailed
hereinabove and in consideration of the balance of convenience
and inconvenience of the parties, the impugned letter/Summary of
Technical Evaluation, dated 04-10-2025, is stayed along with steps
in the context of the LoA dated 17-11-2025, until further orders of
this Court.
11. It is clarified that the observations made hereinabove
are only for the purposes of interim stay and shall in no manner be
construed as findings on the merits of the Writ Petition.
( Meenakshi Madan Rai )
Judge
03-12-2025
Approved for reporting : Yes
ds/sdl
Legal Notes
Add a Note....