Arbitration Appeal, Section 34, Arbitral Award, Coercion, Undue Influence, Economic Duress, Patent Illegality, Severability, Hindustan Steelworks, NOIDA
0  22 Sep, 2023
Listen in 01:27 mins | Read in 144:00 mins
EN
HI

Hindustan Steelworks Construction Limited Vs. New Okhla Industrial Development Authority

  Allahabad High Court Arbitration Appeal No.219 of 2022
Link copied!

Case Background

As per case facts, Hindustan Steelworks Construction Limited (HSCL) was contracted by NOIDA for flyover construction. The work was suspended due to cost inflation concerns, leading to a Supplementary MoU ...

Bench

Applied Acts & Sections

No Acts & Articles mentioned in this case

Hello! How can I help you? 😊
Disclaimer: We do not store your data.
Document Text Version

Arbitration Appeal No.219 of 2022

1.

Neutral Citation No. - 2023:AHC:184463-DB

A.F.R

Reserved

Case :- APPEAL UNDER SECTION 37 OF ARBITRATION AND

CONCILIATION ACT 1996 No. - 219 of 2022

Appellant :- Hindustan Steelworks Construction Limited

Respondent :- New Okhla Industrial Development Authority

Counsel for Appellant :- Varad Nath, Agarwal Archi Piyush

Counsel for Respondent :- Kaushalendra Nath Singh

Hon'ble Manoj Kumar Gupta,J.

Hon'ble Vikram D. Chauhan,J.

(Per Manoj Kumar Gupta, J.)

1.The instant appeal has been filed under Section 13 of the

Commercial Courts, Commercial Division and Commercial Appellate

Division of High Courts Act, 2015 read with Section 37 of the

Arbitration and Conciliation Act, 1996 (for the sake of brevity

hereinafter referred to as 'the Act') challenging the order of the

Commercial Court, Gautam Budh Nagar dated 23.5.2022 in Arbitration

Case No. 13 of 2015, setting aside the Arbitral Award dated 15.12.2014,

by the Sole Arbitrator, in a dispute between the parties.

BACKGROUND

2. In the year 2002, the New Okhla Industrial Development

Authority (NOIDA), the respondent herein, entered into negotiation

with U.P. State Bridge Corporation Limited for construction of two

flyovers with clover leaves and allied work at M.P. Road No.3 Express

Highway near Amity School and at T-junction near Film City, Gautam

Arbitration Appeal No.219 of 2022

2.

Budh Nagar. It submitted a proposal of Rs.106.10 crores for execution

of the Project on turnkey basis, including centage charges but which

was not accepted.

3.The appellant herein, i.e. Hindustan Steel Works Construction

Limited (HSCL), is a Government of India Undertaking, registered

under the Companies Act, 1956. It also gave proposal to NOIDA to

execute the Project at the same cost of Rs.106.10 crores. The offer of

HSCL was accepted by NOIDA and the parties entered into a formal

contract- a Memorandum of Understanding (MoU) on 27.03.2003. The

work under the contract was to be completed by the HSCL within 27

months from the date of start, which was to be counted from 30 days

after the receipt of deposit advance from NOIDA or from the date of

possession of land, which ever is earlier. The HSCL was obliged to

submit performance security equivalent to 5% of the contract value in

shape of bank guarantee. NOIDA was under obligation to pay interest

free deposit advance of 15% of project cost secured by the bank

guarantee (excluding centage charges) within thirty days from the date

of award of work. The advance so paid was to be adjusted in the

subsequent demand of funds on the basis of actual work executed by

HSCL. The subsequent demand was to be submitted after utilization of

75% of the deposit advance released as above. Under Clause 7, HSCL

was entitled to price variation in cost of building material as per NHAI

Arbitration Appeal No.219 of 2022

3.

guidelines and formula for computing the same was provided for in the

General Conditions of Contract (GCC) executed between the parties in

addition to the MoU. Clause 11 stipulated that if the work is

temporarily suspended due to any reason which is not attributable to

HSCL, suitable extension of time shall be granted by the NOIDA on the

request of HSCL. In case the work is delayed due to reasons

attributable to HSCL, it was made liable to penalty at the rate of 5% per

month of centage charges to NOIDA. The period for which extension

would be granted is provided in the GCC. The GCC also provided for

compensation to HSCL in case of suspension of work exceeding 30

days in certain circumstances. Clause 14 made the agreement

irrevocable till the expiry of defect liability period unless there has been

breach of any terms and conditions of the MoU. Clause 22 contained an

arbitration clause for resolution of disputes or differences between the

parties, arising out of the contract. It reads thus: -

“In the event of any question, dispute or difference not being

settled in between the parties the matter shall be referred to

Chairman/C.E.O. NOIDA for nominations of an arbitrator, whose

decision shall be final and binding on the both of the parties.”

4.The General Conditions of Contract (GCC) contained specific

provisions relating to – Extension of Time (Clause 2); Interest Free

Mobilization of Advance (Clause 7B); Payment due to increase/

decrease in prices (Price Escalation) after receipt of contract for works

Arbitration Appeal No.219 of 2022

4.

and the manner of calculation thereof (Clause 8); Foreclosure of

Contract Due to Abandonment or Reduction in Scope of Work (Clause

11); Cancellation of Contract in Full or Part (Clause 12); Suspension of

Work and payment of compensation to the contractor in cases where

such suspension is not attributable to any default on part of the

contractor (Clause 13) etc.

5. In terms of the agreement, HSCL started work since 7.04.2003.

6. On 6.09.2003, the State Government directed for holding of

enquiry, suspecting that contract value was highly inflated. On

19.09.2003, the NOIDA addressed a communication to HSCL

informing it that a Review Committee had been constituted by it to

review the cost of the project. HSCL was required to submit all

drawings and other relevant details before the said Committee. It was

also directed to slow down the project till it is cleared by the Review

Committee.

7. It seems that thereafter the Review Committee got the costing

done by M/s SOWil Limited, a project planning and appraisal company

and Indian Institute of Technology (IIT) Delhi. According to the report

of M/s SOWil, the cost was on higher side by around 40 crores. The

report of IIT, assesses the costing to be inflated by 60 crores.

Consequently, on 22.09.2003, the appellant was directed to stop all

work with immediate effect. The work, therefore, came to a standstill

Arbitration Appeal No.219 of 2022

5.

and remained suspended for 928 days.

8.Under Clause 13 (iii) of GCC, if work remains suspended for

more than four months, HSCL had the option to treat it as ‘foreclosure

of contract’ under Clause 11 of GCC and thereby entitling it to

payment for the work already executed, cost of building material lying

at the construction site or its stores and reasonable compensation.

NOIDA would not be entitled to recovery, if any done against

Mobilisation Advance. Any retention money held had to be released.

All Bank Guarantees would stand discharged forthwith.

9. However, HSCL chose not to invoke Clause 11 of GCC and it

continued to negotiate with NOIDA for resumption of work. Series of

meetings were held between the parties. NOIDA insisted on revision

of rates, but which was not agreed to by HSCL.

10.The Chief Executive Officer, NOIDA in a communication dated

12.10.2004 addressed to the Special Secretary, U.P. Government,

Lucknow disclosed that NOIDA had taken legal advice, according to

which it would be exposed to monetary claim of damages, besides cost

escalation, in case the contract is terminated and that would not be in

the public interest and therefore it should make effort for a negotiated

settlement with HSCL. It was also brought to the notice of the

Government that HSCL was, by that time, paid Rs.49.98 crores and

according to report of experts, the value of work executed was Rs.20

Arbitration Appeal No.219 of 2022

6.

crores only. Thus, there was excess payment of around Rs.30 crores.

Therefore, he suggested that NOIDA should be permitted to proceed

with the contract, subject to re-negotiation of price and HSCL agreeing

to the amendments in the original contract.

11.In response, the State Government by letter dated 11.03.2005

permitted NOIDA to go ahead with the contract, subject to re-

negotiation of the terms of MoU to make the contract value

competitive.

12. According to HSCL, at that time, it was under acute financial

distress because of abrupt suspension of work. It was unable to meet its

financial obligations. It therefore agreed to give up its right to claim

damages and price escalation during the period work remained

suspended by its letters dated 29.04.2005 and 10.05.2005.

13.The parties executed a Supplementary MoU dated 22.03.2006.

The letters dated 29.04.2005 and 10.05.2005 of HSCL, wherein it

agreed to forego its claim towards damages and price escalation during

the period contract remained suspended, were made part of the

Supplementary MoU. The Supplementary MoU stipulated that the

appellant would complete the project at the original cost of Rs.106.10

crores and not claim compensation and price escalation on account of

suspension of work.

Arbitration Appeal No.219 of 2022

7.

14. The parties signed the Supplementary MoU on 22.03.2006 and

the contract period was extended. The parties also agreed that subject to

any contrary term in the Supplementary MoU, the provisions contained

in the earlier MoU would continue to govern the rights of parties.

15. On 8.04.2006, HSCL re-commenced the work at the site and

completed the work on 30.04.2008.

16. On 25.02.2008, just before completion of work, HSCL made

claims towards price variation under Clause 8 of GCC. It referred to

Clause (1) of Supplementary MoU in contending that Clause 8 of GCC

would not stand suspended by execution of Supplementary MoU. It

was emphasised that HSCL only waived price escalation during

suspension period. The price escalation provision for the period after

recommencement of work remained binding on the parties and

therefore NOIDA should honour its claim towards price escalation.

Again on 10.04.2008, HSCL send another communication to NOIDA,

emphasising that price escalation Clause 8 of GCC remained suspended

as per terms of Supplementary MoU only during period of suspension

of work. It would stand revived for the period post recommencement of

work. Therefore, its bills towards price escalation for the said period be

honoured forthwith. To the same effect were the letters dated

23.05.2008 and 16.09.2008.

Arbitration Appeal No.219 of 2022

8.

17.It is noteworthy that during all this period, HSCL never made any

claim towards damages on account of suspension of work, either under

Clause 13(ii)(b) of GCC nor under any other provisions of the Contract

being conscious of the fact that vide Clause 3 of Supplementary MoU,

it had agreed to forego all claims in respect thereof.

18.However, vide a letter dated 16.02.2009, almost one year after

completion of work, HSCL made a claim of Rs.37.12 crores towards

damages during suspension period relying on Clause 13(ii)(b) of GCC.

It also claimed Rs.23.9420 crores towards price escalation for the

period – prior to and post recommencement of work and Rs.42.00 lakhs

towards extra work, apart from interest i.e. total sum of Rs.76.8316

crores. HSCL also invoked Clause 22 of the MoU dated 27.03.2003 and

requested NOIDA to refer the dispute to arbitration. It made the same

request vide letter dated 20.03.2009. However, NOIDA vide letter

dated 17.06.2009 rejected all the claims relying on Clause 3 of the

Supplementary MoU and refused to refer the matter to arbitration.

REFERENCE TO ARBITRATOR

19. On 7.9.2009, HSCL approached this Court under Section 11 of

the Act for appointment of arbitrator. In para 9 of the said application,

HSCL for the first time alleged undue influence and coercion on part of

NOIDA in obtaining Supplementary MoU containing clause relating to

waiver of the right of HSCL to claim damages/liquidated damages

Arbitration Appeal No.219 of 2022

9.

under Clause 13(ii)(b) of GCC during the suspension period. It also

raised other claims. This Court allowed the application under Section

11 of the Act and referred the matter to a sole arbitrator.

ARBITRATION PROCEEDINGS

20.HSCL filed its Statement of Claim (SOC) before the Arbitral

Tribunal under nine different heads. There were two major claims. The

first major claim (Claim No.1) of Rs.23.9420 Crores was in respect of

escalation of price while work was in progress i.e. excluding the period

when work remained suspended. It was based on Clause 7 of MoU read

with Clause 8 of GCC. The other major claim was Claim No.2 towards

damages allegedly suffered on account of suspension of work. The said

claim was based on Clause 13(ii)(b) of GCC for a sum of Rs.35.92

Crores. The detail of all the claims is as follows :-

Claim Head of Claim Amount Claimed

Claim 1On account of Price VariationRs. 2394.20 Lakhs

Claim 2On account of Suspension of

Work

Rs. 3592.00 Lakhs

Claim 3On account of delayed

payment IRA 3 and 4

Rs. 388.68 Lakhs

Claim 4Damages on account of extra

Bank Guarantee Charges

Rs. 27.44 Lakhs

Claim 5Damages on account of

expected loss of profit

Rs. 1060.00 Lakhs

Claim 6On account of cost of

Arbitration

Rs. 25 Lakhs

Arbitration Appeal No.219 of 2022

10.

Claim 7On account of InterestRs. 5666.34 Lakhs

Claim 8On account of Pendente lite

Interest

12% on Awarded

Amount

Claim 9Extra items of work Rs. 36.18 Lakhs

Claim 10On account of Final BillRs. 48.85 Lakhs

TOTAL 9677.61 Lakhs

21.The NOIDA denied the claims of HSCL by filing Statement of

Defence (SOD). It specifically pleaded therein that the claims relating

to escalation/price variation (Claim No.1) and compensation owing to

suspension of work (Claim No.2) are not sustainable in view of HSCL

having unequivocally agreed to forego these claims during process of

re-negotiation and also while entering into the Supplementary MoU. It

also pleaded that HSCL had not alleged any coercion or duress at the

time of entering into Supplementary MoU nor till the completion of

work in pursuance of Supplementary MoU. The plea of duress and

coercion was taken for the first time before the arbitrator and thus not

sustainable in law. It contended that in a commercial bargain, plea of

coercion and duress is unsustainable, particularly in the instant case,

where HSCL is a Government of India Undertaking and had at its

disposal best of legal advise and also the option to treat the suspension

of work to be foreclosure of contract and in which event, it would have

Arbitration Appeal No.219 of 2022

11.

been paid value of the work executed and other amounts as envisaged

under Clause 11 of GCC.

22. The parties filed documentary evidence and also various

affidavits in support of their respective cases. By order dated

17.05.2012, the Arbitral Tribunal permitted the parties to lead oral

evidence, but no oral evidence was led by any party. The tribunal

framed as many as twenty (20) issues. It ultimately passed a final award

on 15.12.2014 in favour of HSCL awarding a sum of Rs.97.10 crores,

inclusive of the cost of arbitration, alongwith pendente lite and future

interest.

23.The issues framed by the Arbitral Tribunal are as follows:-

1.Whether the purported question, dispute and or

difference regarding execution of Supplementary MOU is

immoral, one sided, wholly unconscionable, unilateral,

induced by 'Undue Influence', obtained under duress,

without free will and consent, under coercion etc. as

contained in paragraphs 7 and 8 of the Statement of Facts

and Claims is the subject matter of reference to arbitration

before the arbitral Tribunal for adjudication?

2. Whether the arbitral Tribunal has jurisdiction to

decide and declare the validity of Supplementary MOU in

view of allegations of coercion, duress, undue influence

etc.?

3. Whether the Supplementary Memorandum of

Understanding is vitiated by the purported contentions of

coercion, duress, undue influence, economic pressure,

immoral and unreasonable?

4.Whether the Claimant's proposal of Rs. (sic Rest.)

106,09,91,236/- for the Work was accepted by the

Respondent on a lump sum turnkey basis?

5. Whether the GCC are the part of the Claimant's

proposal or the Respondent's letter of acceptance and or the

Arbitration Appeal No.219 of 2022

12.

MOU or the Supplementary MOU?

6. Whether the purported claims of the Claimant are

barred by limitation?

7. Whether the Claimant had made a request for

foreclosure of contract?

8. Whether the Claimant offered and agreed to continue

left over work on grant of extension of time at a fixed cost

of Rs. 106.10 crores?

9. Whether the Claimant agreed not to pursue its claims

pertaining to escalation and compensation due to

suspension of Work?

10. Whether the suspension of Work was due to reasons

beyond the control of New Okhla Industrial Development

Authority?

11.Whether the Claimant has complied the pre-requisite

conditions in respect of the purported disputes before

seeking reference to the arbitration.

12.Whether the costing/ estimation done by IIT, Delhi

for referred in Reports/Letters is acceptable or not?

13. Whether the Claimant is entitled to an amount on

account of price variations? If so, what amount?

14. Whether the Claimant is entitled to an amount on

account of Clause 13(b) of GCC? If so, what amount?

14 (A). Whether the Claimant is entitled to any amount on

account of nonpayment of 4" RA Bill in time? If so what

amount.

15. Whether the Claimant is entitled to damages on

account of extra Bank guarantee charges? If so, what

amount?

16. Whether the Claimant is entitled to damages on

account of loss of profit? If so, what amount?

17. Whether the Claimant did extra items? If so, what are

such items and what amount the Claimant is entitled in

respect thereof.

18. Whether the claim for extra items is maintainable? If

so, what amount the Claimant is entitled.

19.Whether the Claimant is entitled on account of final

bill? If so, what amount?

20. Whether the Claimant is entitled to interest? If so,

what amount and at what rate and for what period.

Arbitration Appeal No.219 of 2022

13.

23 (a).Issues no.1, 2 and 3 were decided together. The tribunal

held that the issue relating to undue influence and coercion was well

within the scope of reference; that it had jurisdiction to decide the

validity of Supplementary MoU on basis of allegations of coercion,

duress and undue influence and that duress and undue influence was

played upon HSCL in obtaining Supplementary MoU, NOIDA being in

a dominating position.

23 (b). Issue no.4 was decided in favour of HSCL and it was held

that the contract price was lumpsum amount of Rs.106,09,236/- plus

price variation as per the contract.

23 (c).Issue no.5 has also been decided in favour of HSCL and it

is held that GCC was integral part of the main contract.

23 (d).The plea of NOIDA relating to the claims being barred by

time was decided vide Issue No.6. The plea was repelled and it was

held that HSCL had invoked the arbitration clause well within three

years and therefore the claims were not barred by time.

23 (e).Issue no.7 was decided in favour of HSCL.

23 (f). Issue no.8 was decided in favour of HSCL and it is held

that the term “fixed cost” is referable to the originally agreed amount

and does not preclude the claim in respect of price variation etc. in

accordance with the MoU, GCC and Supplementary MoU.

Arbitration Appeal No.219 of 2022

14.

23 (g). Issue no.9 has been decided in favour of HSCL and it has

been held that Clause 3 of the Supplementary MoU prohibited claim in

respect of escalation and compensation only from 22.9.2003 till

recommencement of the work. It did not preclude HSCL from making

claim in respect of compensation/escalation subsequent to re-

commencement of the work.

23 (h).Issue no.10 as to whether suspension of work was due to

reasons beyond control of NOIDA, was decided against NOIDA

holding that it was responsible for unnecessarily holding up the work

for a period of 928 days.

23 (i).Issue no.11 has been decided in favour of HSCL holding

that the claimant-appellant had complied with the pre-requisite

conditions before seeking reference to the arbitration.

23 (j).Issue no.12 as to whether costing/estimation done by IIT,

was acceptable or not, has been decided in favour of HSCL.

23 (k).Issue no.13 related to claim in respect of price variation -

post re-commencement of the work. The tribunal, after considering

various clauses of the MoU, GCC and Supplementary MoU made

distinction between claim in respect of price variation and

compensation under Clause 13(ii)(b) of GCC. It held that Price

Variation Clause in the original MoU (Clause 7) and GCC (Clause 8)

remained eclipsed only during work suspension period. Post

Arbitration Appeal No.219 of 2022

15.

recommencement of work, these clauses revived, and the claim of

Rs.23.94 crores towards price variation – post recommencement of

work, was fully admissible and was allowed.

23 (l).Issue no.14 in respect of damages @ Rs.4 lakh per day

during work suspension period has been decided in favour of HSCL

and a sum of Rs.35.92 crores has been awarded as liquidated damages

under Clause 13(ii)(b) of GCC.

23 (m).Issue no.14-A related to award of interest on account of late

payment of 4

th

RA bill. It has been decided in favour of HSCL and a

sum of Rs.1.66 crores has been awarded in its favour.

23 (n).Issue no.15 relating to claim on account of extra bank

guarantee charges was rejected.

23 (o). Issue no.16 relating to claim for damages on account of loss

of profit has been rejected.

23 (p).Issues no.17 and 18 pertaining to claim in respect of extra

work have also been decided against HSCL.

23 (q). Issue no.19 has been decided in favour of HSCL and it has

been awarded Rs.48.85 lakhs towards final bill.

23 (r). Issue no.20 has been decided in favour of HSCL and it is

held that HSCL is entitled to pendente lite and future interest on the

sums awarded.

Arbitration Appeal No.219 of 2022

16.

24. Claim No.1 – towards price escalation has been dealt with under

Issue No.13. It has been decided in favour of HSCL. The other major

Claim No.2 – towards damages @ Rs.4 lakh per day for the period

work remained suspended, also decided in favour of HSCL, is covered

under Issues No.1, 2, 3 and 14.

PROCEEDINGS BEFORE COMMERCIAL COURT (Sec. 34 of

the Act)

25.NOIDA, feeling aggrieved by the award, filed objections under

Section 34 of the Act before the Commercial Court, Gautam Budh

Nagar, which has been allowed by the impugned order dated

23.05.2022.

26. The Commercial Court did not find any perversity in respect of

the finding recorded by the tribunal on issue no.13 i.e. claim in respect

of price variation (Claim No.1). However, it has set aside the award of

Rs.35.02 crores towards damages on account of suspension of work for

period of 928 days (Claim No.2). It held that HSCL by signing the

Supplementary MoU had surrendered its right to compensation during

period of suspension of the contract. It also repelled the plea of

coercion, duress, undue influence and unequal bargaining power set up

by HSCL and the finding of the arbitral tribunal that Supplementary

MoU is void and unenforceable. The award of liquidated damages

under Clause 13(ii)(b) of GCC while deciding issue no. 14 is held to

Arbitration Appeal No.219 of 2022

17.

suffer from a patent illegality warranting exercise of power under

Section 34 of the Act.

27.The Commercial Court placed reliance on a judgement of Delhi

High Court in M/s Classic Motors Limited Vs. Maruti Udyog

Limited

1

, wherein four factors have been laid down to ascertain

whether any duress or coercion has been played upon any party in a

commercial contract. The factors are: (i) Did the party protest before or

soon after the agreement? (ii) Did the party took any step to avoid the

contract? (iii) Did the party has any alternative course of action or

remedy? and (iv) Did the party convey benefit of the independent

advice?

28. The Commercial Court held that the appellant failed to pass the

test laid down in the said judgement. It also placed reliance on the

judgement of the Supreme Court in Central Inland Water Transport

Corporation Ltd. Vs. Brojo Nath Ganguly

2

, judgement of Bombay

High Court in Balaji Pressure Vessels Ltd. Vs. Bharat Petroleum

Corporation Ltd.

3

and judgement of Andhra Pradesh High Court in

Government of Andhra Pradesh Irrigation Department Vs. G.

Kondala Rao

4

and held that the plea of coercion and undue influence

was after thought, “patently erroneous, perverse, in ignorance of vital

11997 (40) DRJ

21986 (3) SCC 156

32014 SCC OnLine, Bombay 1079

4(2004) 1 An WR 526 (WB)

Arbitration Appeal No.219 of 2022

18.

evidence on record, contrary to the terms of the Supplementary MoU

and in clear breach of public policy of India”.

29.The Commercial Court thereafter relying on Dakshin Haryana

Bijli Vitran Nigam Ltd. Vs. M/s Navigant Technologies Pvt. Ltd.

5

held that since in relation to some of the issues, the findings are

perverse, against public policy of India and covered by grounds

contained in sub-section (2) and (2-A) of Section 34 of the Act, the

award cannot be upheld in part as it would amount to modifying the

award. Accordingly, the award has been set aside in its entirety.

30.We have heard Sri Amit Saxena, Senior Advocate assisted by Sri

Varad Nath and Sri Pranay Agarwala, learned counsel for the appellant

and Sri Manish Goyal, Senior Advocate assisted by Sri Kaushalendra

Nath Singh and Ms. Anjali Goklani, learned counsel for the respondent

at great length and perused the material on record with the assistance of

learned counsel for the parties.

SUBMISSIONS OF LEARNED COUNSEL FOR THE

APPELLANT :

31.It is submitted on behalf of the appellant that the impugned order

of the Commercial Court is manifestly illegal and contrary to the well

established principles on which an award of an Arbitral Tribunal could

be set aside. The tribunal decided Issues No. 1, 2, 3 and 14 relating to

award of damages during suspension period in terms of Clause 13(ii)(b)

52021 (7) SCC 657

Arbitration Appeal No.219 of 2022

19.

of the GCC after taking into consideration the case of the parties,

evidence on record and the law laid down by the Supreme Court in

respect of fraud and coercion. The power of the court under Section 34

of the Act is limited one, circumscribed by the parameters laid down

under the said provision. To hold an award to be opposed to public

policy of India, the patent illegality should go to the root of the matter.

In deciding objections under Section 34 of the Act, the court does not

exercise the power of an appellate court and it cannot re-appreciate or

re-assess evidence. Once the tribunal had assessed the evidence before

it in detail, the court does not have jurisdiction to take another view

even if it is possible. The court has to examine whether the view taken

by the Arbitrator is a plausible view on the facts, pleadings and

evidence before it. Once the view taken is found to be a plausible view,

the court will not have power to substitute its findings in place of the

findings recorded by the Arbitral Tribunal. The extent of judicial

scrutiny under Section 34 is very limited.

32.It is urged that the Arbitral Tribunal had in great detail considered

the stipulations contained in the MoU, GCC and Supplementary MoU

as well as the communication exchanged between the parties during the

period contract remained suspended. It had also duly considered the

directions issued by the State Government which prompted NOIDA to

compel the appellant to enter into Supplementary MoU on terms

Arbitration Appeal No.219 of 2022

20.

dictated by it and thereafter arrived at a finding of fact that execution of

the Supplementary MoU by the appellant was a result of undue

influence and coercion. The appellant had no other option left with it

but to accept the conditions imposed upon it for resuming the work or

else the consequences would have been disastrous. It would have

resulted in termination of the contract; blacklisting of the appellant;

difference in cost of balance work got executed from third party being

realised from the appellant; invocation of bank guarantee of Rs.15.30

crores; non payment of unpaid dues of Rs.8.21 crores; loss of

reputation and incurring heavy amount in litigation. It is also urged that

the NOIDA was conscious of his imbalance in negotiating power and it

got legal opinion to compel the appellant to give up its right to claim

damages under the original MoU. The Supplementary MoU dated

5.04.2006 was prepared and drafted by NOIDA and the appellant was

directed to sign the same within 15 days. NOIDA had included in the

Supplementary MoU various terms which absolves it of its liabilities

arising out of its unilateral act of suspending the contract.

33. Even after resumption of work on 8.04.2006, NOIDA continued

to withhold payments due to the appellant for the works executed prior

to suspension of work until the work was completed and delivered by

the appellant Company on 30.04.2008. NOIDA failed to provide

completion certificate and also withheld the bank guarantee.

Arbitration Appeal No.219 of 2022

21.

34.After having successfully delivered the Project, the appellant was

in a position to invoke the arbitration machinery for seeking damages

under the MoU. It did so by way of its letter dated 20.03.2009 and

wherein it specifically made a claim for price variation (Rs.2394.20

lakhs) and damages for suspension of work (Rs.3712.00 lakhs). Again

in para 9 of the arbitration application filed by the appellant under

Section 11 of the ACA before this Court, the plea of coercion was

specifically taken.

35.It was thus contended that the plea of coercion and undue

influence was duly taken by the appellant at the first opportunity. The

Arbitral Tribunal was well within its jurisdiction to examine the said

plea and to record findings in favour of the appellant. The Commercial

Court has wrongly held that the plea of coercion and undue influence or

unequal bargaining power is not applicable in commercial contracts. In

support of the said contention, learned counsel for the appellant has

placed reliance on various judgements which will be discussed while

dealing with the contention.

36.The judgement of the Delhi High Court in Classic Motors was

wrongly treated by the Commercial Court as laying down public policy

of India. The said judgement was rendered by a Single Judge of Delhi

High Court while deciding objections under Section 34. The said

judgement does not consider various decisions of the Supreme Court on

Arbitration Appeal No.219 of 2022

22.

the subject of coercion and undue influence. The Commercial Court has

also wrongly relied on the judgement in Central Inland Water

Transport Corporation Ltd. and Balaji Pressure Vessels Ltd.

37.The issue pertaining to coercion and duress is a pure question of

fact. It was decided by the Arbitral Tribunal after hearing both the

parties and considering all the material evidence on record. The view

taken by the Arbitral Tribunal in this behalf was a plausible view. The

Commercial Court erred in re-appreciating the evidence and giving its

own interpretation to the same.

38.The Supplementary MoU was drafted by NOIDA and the

appellant had no option but to agree to the conditions contained therein,

failing which, the appellant, who had already invested huge sum of

money in the Project, was bound to be sidelined, apart from being

visited with evil consequences provided under the original contract.

Consequently, there was no consensus ad idem between the parties.

39.The Supplementary MoU did not override or amend or delete

Clause 13(2)(b) of the GCC, either specifically or by necessary

implications. The Supplementary MoU does not even refer to Clause

13(ii)(b) of the GCC. The Commercial Court has relied upon the

intention and reasoning of executing the Supplementary MoU but

overlooked that no such intention was evident from the language of the

Supplementary MoU.

Arbitration Appeal No.219 of 2022

23.

40.The Arbitrator held that the Supplementary MoU did not amend

the MoU by deleting the Price Variation Clause. The Commercial Court

has upheld claim under Price Variation Claim. The same reasoning as

upheld by the Commercial Court in relation to the Claim awarded for

Price Variation would apply to the claim of Rs. 4 Lakhs per day under

Clause 13 (ii)(b) of the GCC.

41.The Commercial Court accepted the Award given by the

Arbitrator in relation to issue no. 13 i.e. with respect to Award of

Rs. 23.94 Cr on account of price variation. Despite having upheld the

award on that claim, the Commercial Court has wrongly held that since

there is no power to modify the award, "the entire award has to be set

aside", relying on a Supreme Court judgement in the case of Dakshin

Haryana Bijli Vitaran Nigam Ltd. vs M/s Navigant Technologies

(P) Ltd. (supra).

42.The Commercial Court has erred in law in proceeding on this

assumed legal position that where an award comprises several distinct

monetary claims being awarded on independent grounds, and award of

some of the monetary claims are interfered with under Section 34 then

the entirety of the award is set aside even though the award on other

claims was upheld.

Arbitration Appeal No.219 of 2022

24.

43.The judgement Dakshin Haryana Bijli Vitaran Nigam Ltd.'s

case relied upon in the impugned order, is distinguishable on facts. In

the said case, it was not really dealing with the issue of modification of

an Award by the court under Section 34 of the Arbitration Act,

however, it had relied upon the law laid down in the case of

McDermott International Inc vs. Burn Standard Co. Limited

6

to

decide the issue of relevance of a dissenting opinion.

44.In the present case, there were several distinct amounts awarded

by the Tribunal on independent reasonings, including, inter alia, an

amount of Rs. 23.94 Cr towards Price Variation and an amount of

Rs. 35.92 Cr under Clause 13 (ii)(b) of GCC. The Commercial Court

could not have set aside the entire Award because it found that the

Award of Rs. 35.92 Cr under Clause 13 (ii)(b) of GCC was against

public policy. The Court is fully empowered to set aside the award in

regard to particular claim only, while refusing to interfere with the

remaining portion of the Award.

SUBMISSIONS OF LEARNED COUNSEL FOR THE

RESPONDENT:

45.The award of the Arbitral Tribunal primarily flows from the

erroneous finding that the Supplementary MoU between the parties was

signed under coercion and duress. The said finding is not supported by

6 (2006) 11 SCC 181

Arbitration Appeal No.219 of 2022

25.

the evidence on record and hence amounts to a patent illegality as

envisaged under Section 34 of the Act.

46.It has to be ascertained whether the party alleging coercion

exercised a free will or not while entering into the Supplemental

Agreement. For this purpose there are several factors which need to be

looked into. They are (1) Did the party protest before or soon after the

agreement? (2) Did the party take any steps to avoid contract? (3) Did

the party have an alternative course of action or remedy? If so, did the

party pursue or attempt to pursue the same? (4) Did the party convey

benefit of independent advice?

47.If the aforesaid factors are applied on the present facts, the

Arbitral Tribunal failed to consider, that HSCL in their own wisdom

and being fully conscious of their legal rights and remedy, sent letters

dated 29.4.2005 & 10.5.2005 to NOIDA. In these letter(s) HSCL

expressly submitted to complete the contract at the fixed value of

Rs.106.10 crore and voluntarily agreed to claim no compensation or

price escalation at all under the contract. Those letters formed the part

of the Supplementary MoU and no prompt protest was lodged by

HSCL. Since 22.03.2006, when the Supplementary MoU was executed

and work was continued after recommencement, HSCL did not protest

to the execution of the Supplementary MoU, in any form or manner.

Almost after completion of the entire contract and reaping benefits

Arbitration Appeal No.219 of 2022

26.

under it, HSCL used the term coercion, in an attempt to create a false

dispute between the parties by going contrary to the conduct and

express agreement. The plea of coercion and undue influence was not

only sham and an afterthought, but also merely a cause to secure unjust

enrichment at the cost of public exchequer.

48.As regards the second and third factor to prove coercion, the

question remained as to whether HSCL took any step to avoid the

contract or did HSCL have an alternative course of action or remedy?

No steps were taken to either avoid the contract or pursue the rights and

remedies under the MoU or GCC. Despite being aware of its right both

under the Contract and GCC, HSCL conspicuously chose to remain

oblivious in exercising its right, to avoid execution of Supplementary

MoU under coercion or undue influence.

49.Fourth factor pertains to whether HSCL convey benefit of the

independent advice? It is undisputed that HSCL was an organization

which is regulated and controlled by the Government of India. By no

stretch of imagination, it can be assumed that the state entity i.e.

NOIDA can exercise coercion and undue influence on an entity which

is under control of the Government of India. There is no reason to

assume, that HSCL being regulated by Central Government of India,

didn't have able resources or means to have independent legal advice to

determine the rights under the contract and were forced to enter into a

Arbitration Appeal No.219 of 2022

27.

transaction on exercise of coercion and undue influence.

50.The power to set aside only part of the award is conferred on

court by Section 34 only in one contingency which is to be found in

Clause (iv) of sub-section (2) of Section 34 of the Act. In all other

cases, if the court finds that only a part of the award is affected by

illegality which is pointed out to the court, the court cannot itself

modify the award, but if a party to the petition applies to the court in

exercise of its power under sub-section 4 of Section 34, the court can

direct the arbitral tribunal to resume the proceedings and take such

action to eliminate the ground for setting aside the award. The

placement of the proviso under sub-clause (iv) of clause (a) of sub-

section 2 is crucial as it limits the application of the proviso to the said

sub-clause alone. This position cannot be overlooked to extend the

application of the proviso to the entire sub-section (2).

POINTS FOR DETERMINATION:

51.Two points which arise for determination are:

(A) Whether award of damages during the period of suspension

of contract (Claim No.2), by the arbitral tribunal falls within the

clutches of sub-section (2) or (2-A) of Section 34 of the Act, so as

to warrant interference by the Court.

(B) Whether the Court, in proceeding emanating from Section 34

Arbitration Appeal No.219 of 2022

28.

of the Act has power to sever bad part of the award from good

part even in situations not covered under the proviso to Section

34 (2) (a) (iv) of the Act?

ANALYSIS

Point No.1:

52.Section 34 of the Act specifies the grounds on which arbitral

award can be set aside by the court. It is noteworthy that Section 34

was amended by Act No.3 of 2016 w.e.f. 23.10.2015. The application

in the present case was filed post amendment and would therefore be

governed by the amended provisions. The relevant part of Section 34 is

as follows:-

34.Application for setting aside arbitral award. (1)

Recourse to a Court against an arbitral award may be made

only by an application for setting aside such award in

accordance with sub-section (2) and sub-section (3).

(2) An arbitral award may be set aside by the Court only if--

(a) the party making the application furnishes proof that -

(i) a party was under some incapacity; or

(ii) the arbitration agreement is not valid under the law to

which the parties have subjected it or, failing any indication

thereon, under the law for the time being in force; or

(iii) the party making the application was not given proper

notice of the appointment of an arbitrator or of the arbitral

proceedings or was otherwise unable to present his case; or

(iv) the arbitral award deals with a dispute not contemplated

by or not falling within the terms of the submission to

arbitration, or it contains decisions on matters beyond the

scope of the submission to arbitration:

Provided that, if the decisions on matters submitted to

arbitration can be separated from those not so submitted,

only that part of the arbitral award which contains decisions

on matters not submitted to arbitration may be set aside; or

Arbitration Appeal No.219 of 2022

29.

(v) the composition of the arbitral tribunal or the arbitral

procedure was not in accordance with the agreement of the

parties, unless such agreement was in conflict with a

provision of this Part from which the parties cannot

derogate, or, failing such agreement, was not in accordance

with this Part; or

(b) the Court finds that--

(i) the subject-matter of the dispute is not capable of

settlement by arbitration under the law for the time being in

force, or

(ii) the arbitral award is in conflict with the public policy of

India.

Explanation 1.-- For the avoidance of any doubt, it is

clarified that an award is in conflict with the public policy

of India, only if,--

(i) the making of the award was induced or affected by

fraud or corruption or was in violation of section 75 or

section 81; or

(ii) it is in contravention with the fundamental policy of

Indian law; or

(iii) it is in conflict with the most basic notions of morality

or justice.

Explanation 2.--For the avoidance of doubt, the test as to

whether there is a contravention with the fundamental

policy of Indian law shall not entail a review on the merits

of the dispute.

(2-A) An arbitral award arising out of arbitrations other

than international commercial arbitrations, may also be set

aside by the Court, if the Court finds that the award is

vitiated by patent illegality appearing on the face of the

award:

Provided that an award shall not be set aside merely

on the ground of an erroneous application of the law or by

reappreciation of evidence.”

Precedents on scope of Section 34 :

53.In Ssangyong Engineering and Construction Company Ltd.

Vs. National Highways Authority of India (NHAI)

7

, the Supreme

Court considered the scope of Section 34 as amended. The Supreme

7(2019) 15 SCC 131

Arbitration Appeal No.219 of 2022

30.

Court also noted the amendments carried out simultaneously in Section

48, which deals with 'foreign awards', so as to bring the said provision

in line with the amendments made in Section 34.

54.The Supreme Court explained that the phrase “public policy of

India” used in Section 34 and 48 would now mean the “fundamental

policy of Indian Law” as explained in paras 18 and 27 of Associate

Builders. Therein reliance was placed on the meaning assigned to the

aforesaid expression in Renu Sagar. Para 18 and 27 of Associate

Builders reads thus:-

18. In Renusagar Power Co. Ltd. v. General Electric Co.3, the

Supreme Court construed Section 7(1)(b)(ii) of the Foreign

Awards (Recognition and Enforcement) Act, 1961:

7. Conditions for enforcement of foreign awards. (1) A foreign

award may not be enforced under this Act-

(b) if the Court dealing with the case is satisfied that-

(ii) the enforcement of the award will be contrary to the public

policy."

In construing the expression "public policy" in the context of a

foreign award, the Court held that an award contrary to

(i) The fundamental policy of Indian law,

(ii) The interest of India,

(iii) Justice or morality,

would be set aside on the ground that it would be contrary to the

public policy of India. It went on further to hold that a

contravention of the provisions of the Foreign Exchange

Regulation Act would be contrary to the public policy of India in

that the statute is enacted for the national economic interest to

ensure that the nation does not lose foreign exchange which is

essential for the economic survival of the nation (see SCC p. 685,

para 75). Equally, disregarding orders passed by the superior

courts in India could also be a contravention of the fundamental

Arbitration Appeal No.219 of 2022

31.

policy of Indian law, but the recovery of compound interest on

interest, being contrary to statute only, would not contravene any

fundamental policy of Indian law (see SCC pp. 689 & 693, paras

85 & 95).

27. Coming to each of the heads contained in Saw Pipes

judgment, we will first deal with the head "fundamental policy of

Indian law". It has already been seen from Renusagar³ judgment

that violation of the Foreign Exchange Act and disregarding

orders of superior courts in India would be regarded as being

contrary to the fundamental policy of Indian law. To this it could

be added that the binding effect of the judgment of a superior

court being disregarded would be equally violative of the

fundamental policy of Indian law.

55.While holding that the test laid down in Renu Sagar would hold

good even in respect of the amended provision, the wider interpretation

given to the expression in ONGC Limited Vs. Western Geco

International Ltd

8

is held not to lay down the correct position of law.

Thus, under the guise of interfering with an award on the ground that

the Arbitrator has not adopted a judicial approach, the courts'

intervention would be on the merits of the award, which is held to be

the impermissible post-amendment.

56.The Supreme Court also noted that interference with the award on

the ground that it concerns “interest of India” has since been deleted

and, therefore, no longer available for setting aside an award. It is also

clarified that the ground for interference on the basis that it is in

conflict with justice or morality is now to be understood as a conflict

with “most basic notions of morality or justice”. Thus, the public policy

8(2014) 9 SCC 263

Arbitration Appeal No.219 of 2022

32.

of India is held to be confined to (a) the fundamental policy of Indian

Law as understood in paragraphs 18 and 27 of Associate Builders; (b) if

it is against basic notions of justice or morality as understood in paras

36 to 39 of Associate Builders. It is held that with the insertion of sub-

section (2-A) to Section 34, an additional ground has been made

available under Section 34 i.e. “patent illegality appearing on the face

of the award”. The proviso clarifies that the patent illegality should be

such as goes to the root of the matter. It should not merely be confined

to an erroneous application of law. It also does not permit re-

appreciation of evidence. The addition of the said ground does not

mean that what is not subsumed within the fundamental policy of India,

namely, the contravention of Statute not linked to public policy or

public interest, can be brought in by the backdoor when it comes to

setting aside of an award on the ground of patent illegality.

57.Before proceeding further, it would be advantageous to note

paragraphs 36 and 37 of Associate Builders, which have been

approved in Ssangyong Engineering:-

36. The third ground of public policy is, if an award is against

justice or morality. These are two different concepts in law. An

award can be said to be against justice only when it shocks the

conscience of the court. An illustration of this can be given. A

claimant is content with restricting his claim, let us say to Rs 30

lakhs in a statement of claim before the arbitrator and at no point

does he seek to claim anything more. The arbitral award

ultimately awards him Rs 45 lakhs without any acceptable reason

or justification. Obviously, this would shock the conscience of the

Arbitration Appeal No.219 of 2022

33.

court and the arbitral award would be liable to be set aside on the

ground that it is contrary to "justice".

37. The other ground is of "morality". Just as the expression

"public policy" also occurs in Section 23 of the Contract Act,

1872 so does the expression "morality". Two illustrations to the

said section are interesting for they explain to us the scope of the

expression "morality":

"(j) A, who is B's Mukhtar, promises to exercise his influence, as

such, with B in favour of C. and C promises to pay 1000 rupees

to A. The agreement is void, because it is immoral.

(k) A agrees to let her daughter to hire to B for concubinage. The

agreement is void, because it is immoral, though the letting may

not be punishable under the Indian Penal Code (45 of 1860)."

58. In paragraphs 38 and 39 (Associate Builders), it has been

explained that the concept of morality as envisaged under Section 23 of

the Contract Act is confined to sexual immorality and not to any other

case. As regards construction of the terms of a contract, it has been held

that it is primarily for an arbitrator to decide unless the arbitrator

construes the contract in a manner that no fair minded or respectable

person would construe it. In other words, interference with an

interpretation given by the arbitrator to the terms of the contract is not

warranted if it is a possible view.

59.In para 41 of the Law Report, it has been held that a finding

based on no evidence at all or an award which ignores vital evidence in

arriving at its decision would be perverse and liable to be set aside on

the ground of patent illegality. Likewise, an evidence taken behind the

back of the party and a decision based on it would also fall in the same

Arbitration Appeal No.219 of 2022

34.

category, as such a decision would not be a decision based on evidence

led by the parties.

60. More recently in Delhi Airport Metro Express Pvt Ltd Vs.

Delhi Metro Rail Corporation Ltd

9

, the Supreme Court again

considered the scope of interference by the Court with an award under

Section 34 in context of the interpretation given by the Arbitral

Tribunal to the terms of the contract. In the said judgement again, the

test of “possible view” laid down in previous judgements has been

reiterated as laying down the correct position of law. The expression

“patent illegality” in Section 34 (2-A) has been explained thus:-

29. Patent illegality should be illegality which goes to the root of

the matter. In other words, every error of law committed by the

Arbitral Tribunal would not fall within the expression “patent

illegality”. Likewise, erroneous application of law cannot be

categorised as patent illegality. In addition, contravention of law

not linked to public policy or public interest is beyond the scope

of the expression“patent illegality”. What is prohibited is for

courts to re-appreciate evidence to conclude that the award

suffers from patent illegality appearing on the face of the award,

as courts do not sit in appeal against the arbitral award. The

permissible grounds for interference with a domestic award under

Section 34(2-A) on the ground of patent illegality is when the

arbitrator takes a view which is not even a possible one, or

interprets a clause in the contract in such a manner which no fair-

minded or reasonable person would, or if the arbitrator commits

an error of jurisdiction by wandering outside the contract and

dealing with matters not allotted to them. An arbitral award

stating no reasons for its findings would make itself susceptible to

challenge on this account. The conclusions of the arbitrator which

are based on no evidence or have been arrived at by ignoring vital

evidence are perverse and can be set aside on the ground of patent

illegality. Also, consideration of documents which are not

9(2022) 1 SCC 131

Arbitration Appeal No.219 of 2022

35.

supplied to the other party is a facet of perversity falling within

the expression “patent illegality”.

61.In para 31 of the Law Report, the Supreme Court placing reliance

on the interpretation given in Ssangyong Engineering reiterated the

legal position that “contravention of a Statute not linked to a public

policy or public interest” cannot be a ground to set at naught an arbitral

award as being discordant with the fundamental policy of Indian Law

and neither it can be brought within the confine to “patent

illegality.... .”

62.In Municipal Corporation of Delhi Vs. Jagan Nath Ashok

Kumar and another

10

, the Supreme Court held that the Arbitrator is

“the sole judge of the quality as well as quantity of evidence and it will

not be for this Court to take upon itself the task of being a judge of the

evidence before the arbitrator. It may be possible that on the same

evidence the Court might have arrived at a different conclusion than the

one arrived at by the arbitrator but that by it self is no ground in our

view for setting aside the award of an arbitrator.”

63.In State of Jharkhand and others Vs. HSS Integrated SDN

and another

11

, the Supreme Court placing reliance on NHAI Vs.

Progressive -NVR (JV)

12

reaffirmed the “possible view” theory -

“In Progressive-MVR (supra), after considering the catena of

10(1987) 4 SCC 497

11(2019) 9 SCC 798

12(2018) 14 SCC 688

Arbitration Appeal No.219 of 2022

36.

decisions of this Court on the scope and ambit of the proceedings

under Section 34 of the Arbitration Act, this Court has observed

and held that even when the view taken by the arbitrator is a

plausible view, and/or when two views are possible, a particular

view taken by the Arbitral Tribunal which is also reasonable

should not be interfered with in a proceeding under Section 34 of

the Arbitration Act.”

64.In Maharashtra State Electricity Distribution Co. Ltd. Vs.

Datar Switchgear Ltd

13

, it is held that the Arbitral Tribunal is the

master of evidence and the findings of fact recorded by an Arbitral

Tribunal on basis of the evidence on record are beyond scope of

scrutiny under Section 34 of the Act. It is observed as follows:-

“The proposition of law that the Arbitral Tribunal is the master of

evidence and the findings of fact which are arrived at by the

arbitrators on the basis of evidence on record are not to be

scrutinised as if the Court was sitting in appeal now stands settled

by a catena of judgments pronounced by this Court without any

exception thereto.”

Application to the facts of the case :

65.Keeping in mind the above principles, we now proceed to

examine whether the Commercial Court acted within the bounds of its

jurisdiction in setting aside the award in respect of Claim No.2 towards

liquidated damages on account of suspension of work. The said claim

of Rs.35.92 crores was made under Clause 13 of GCC.

66.Clause 13 of GCC confers power upon the Engineer-in-Chief to

suspend progress of the works or any part thereof for such time and in

such manner as he may consider necessary. When suspension of work

13(2018) 3 SCC 133

Arbitration Appeal No.219 of 2022

37.

is for reasons enumerated in sub-para 13(i)(b) or (c), it would entitle the

contractor to damages at the rate of Rs. 4 lakhs per day for the period

exceeding 30 days. If suspension is prolonged for more than four

months, it gives further option to treat such suspension as foreclosure

of contract due to abandonment or reduction in scope of work. As the

entire controversy hinges on the interpretation and scope of the said

Clause, therefore, it is reproduced below for convenience of reference:-

CLAUSE 13

Suspension of Work

(i)The Contractor shall, on receipt of the order in writing of

the Engineer-in-Charge whose decision shall be final and binding

on the Contractor) suspend the progress of the works or any part

thereof for such time and in such manner as the Engineer-In-

Charge may consider necessary so as not to cause any damage or

injury to the work already done or endanger the safety thereof for

any of the following reasons: -

(a) on account of any default on the part of the Contractor or;

(b)for proper execution of the works or part thereof for reasons

other than the default of the Contractor; or

(c)for safety of the works or part thereof.

The Contractor shall, during such suspension, properly protect

and secure the works to the extent necessary and carryout the

instructions given by the Engineer-In-Charge.

(ii)lf the suspension is ordered for reasons (b) and (c) in sub-

para (i) above.

(a)the Contractor shall be entitled to an extension of time

equal to the period of every such suspension PLUS 25% for

completion of the item or group of items of work for which a

separate period of completion is specified in the contract and of

which the suspended work forms a part, and;

(b)if the total cumulative period of all such suspensions in

respect of an item or group of items if work for which a separate

period of completion is specified in the contract exceeds thirty

days, the Contractor shall in addition to (a) above, be entitled to

@ Rs. 4,00,000/- (Rupees Four Lakh) per day for the period

exceeding 30 days.

Arbitration Appeal No.219 of 2022

38.

(iii) If the works or part thereof is suspended on the orders of

the Engineer-In- Charge for more than four months at a time,

except when suspension is ordered for reason (a) in sub-para (i)

above, the Contractor may treat such suspension under clause 11.

i.e. foreclosure of Contract due to abandonment or reduction in

scope of work.”

67.The Arbitral Tribunal, while deciding issue no.10, has held that

suspension of work was for reasons attributable to the respondent

(NOIDA). The reason for suspension of work, thus, does not fall under

sub-para (a) of Clause 13 (i) of GCC. In such an event, three situations

are contemplated with different consequences -

(i)the contractor would be entitled to extension of time equal

to the period of every such suspension, as also, 25% for

completion of the item or group of items of work for which a

separate period of completion is specified in the contract and of

which suspended work forms a part;

(ii)if the period of suspension exceeds 30 days, the contractor

would in addition to above, be entitled to Rs. 4 lakh per day for

the period exceeding 30 days; and

(iii)if the period of suspension exceeds four months at a time,

as in the instant case, the contractor had the option to treat such

suspension as ‘fore closure of contract’ under Clause 11 of GCC.

68. Clause 11 of GCC contemplates payment of compensation to the

contractor in the event there is foreclosure of work. It also provides for

Arbitration Appeal No.219 of 2022

39.

the manner of calculation of compensation. It reads thus : -

CLAUSE 11:

Foreclosure Of Contract Due To Abandonment Or Reduction In

Scope Of Work.

If at any time after acceptance of the offer, NOIDA shall decide

to abandon or reduce the scope of the works for any reason

whatsoever and hence not require the whole or any part of the

works to be carried-out, the Engineer-In-Charge shall give notice

in writing to that effect to the Contractor and the Contractor shall

act accordingly in the matter. The Contractor shall have no claim

to any payment of compensation or otherwise whatsoever, on

account of any profit or advantage which he might have derived

from the execution of the works in full but which he did not

derive in consequence of the foreclosure of the whole or part of

the works.

The Contractor shall be paid at contract rates full amount for

works executed at site and in addition, a reasonable amount as

certified by the Engineer-In-Charge for the items hereunder

mentioned which could not be utilized on the works to the full

extent in view of the foreclosure.

i)Any expenditure incurred on preliminary site work,

e.g. temporary access roads, temporary labour huts, staff

quarters and site office. Storage accommodation and water

storage tanks.

ii) NOIDA shall have the option to take over

Contractor's materials or any part thereof either brought to

site or of which the Contractor is legally bound to accept

delivery from suppliers (for incorporation in or incidental to

the work) provided however, NOIDA shall be bound to take

over the materials or such portions thereof as the Contractor

does not desire to retain. For materials taken over or to be

taken over by NOIDA cost of such materials shall be paid.

The cost, shall, however, take into account purchase price,

cost of transportation and damage which may have been

caused to materials whilst in the custody of the Contractor.

Arbitration Appeal No.219 of 2022

40.

iii)Reasonable compensation for transfer of T&P from

site to Contractor's permanent stores or to his other works,

whichever is less on actuals. If T&P are not transported! to

either of the said places, no cost of transportation shall be

payable.

iv) Reasonable compensation for repatriation of

Contractor's site staff and imported labour to the extent

necessary.

The Contractor, shall, if required by the Engineer-In-Charge

furnish to him books of account wage books, time sheets

and other relevant documents and evidence as may be

necessary to enable him to certify the reasonable amount

payable under this condition.

v)Recovery if any due, against Mobilisation Advance

will not be effected. Any retention money held shall be

released. All Bank Guarantees submitted to NOIDA shall be

discharged forthwith.

The reasonable amount of items on (i), (iii) and (iv) above shall

not be in excess of 4% (Four Percent) of the cost of the work

remaining incomplete on the date of closure, i.e. total stipulated

cost of the work as per accepted tender less the cost of work

actually executed under the contract and less the cost of

Contractor's materials at site taken over by the NOIDA as per

item (ii) above.

69.It is an admitted position that even after expiry of four months of

suspension, HSCL did not exercise its right of foreclosure. The parties

kept negotiating with each other to break the deadlock. A number of

meetings were held between them. Ultimately, HSCL by letter dated

29.4.2005 prayed for (i) revocation of the order suspending the work;

(ii) extension of time in terms of Clause 13 and Clause 22 of GCC; and

(iii) agreed not to make any claim towards escalation in prices or any

Arbitration Appeal No.219 of 2022

41.

kind of compensation during suspension period. The letter dated

29.4.2005 is reproduced below: -

HINDUSTAN STEELWORKS CONSTRUCTION LTD .

(A Govt. of India Undertaking) 118 Vandhana 11 Tolstoy Marg,

New Delhi-110001

Ref. HSCL/DGM/ND/NOIDA – Flyover/2005-2240

Dt. 29.04.2005

The Chief Executive Officer,

New Okhla Industrial Development Authority.

Main Administrative Building.

Sector-VI, NOIDA,

Distt. Gautam Budh Nagar – 201301.

Sub: - NOIDA Board Special Meeting held on 26 April 2005 for

the Construction of Flyovers in NOIDA vide Letter No.

NOIDA/CPE/2005/191, Dated 15 April 2005.

Dear Sir,

Pursuant to the discussion held at the Special Meeting of

NOIDA BOARD on 26 April 2005, it has been decided to

commence the unfinished work of "Noida Flyovers" which was

Suspended by the NOIDA Authority on 22 September 2003. It is

submitted that we started the work of the "NOIDA FLYOVERS"

and carried out the same till the work was suspended, with utmost

sincerity, diligence and commitment and at no point of time, there

was any breach or default on our part.

However, in the interest of Social Justice and Public

Interest, it has been decided by us to complete the work at a Cost

of Rs. 106.10 Crores. Further, we also agree not to pursue any

escalation and compensation claim for abrupt Suspension of work

with effect from 22 September 2003, as desired in the meeting.

Since considerable time has elapsed from the date of

suspension of work, we request, in the interest of justice, for

extension of time, in terms of Clause 13 and Clause 2.2 of

General Conditions of Contract. Further, you may please

appreciate the financial crunch we have undergone due to sudden

and long suspension of work, therefore it is requested to kindly

release the large pending amount immediately to meet the market

liabilities and also to enable us to remobilise.

Arbitration Appeal No.219 of 2022

42.

At the end, we would like to submit that the balance work

in regard to the present assignment shall be completed in

accordance with the existing Design/ Drawings which were

already submitted, on the basis of which work has been executed

so far.

In view of the foregoing, NOIDA Authority may kindly

revoke the Suspension Order at the earliest to enable us to

commence The work after Remobilisation of our resources which

may take around a month from the date of revocation of the

Suspension Order/release of pending payments.

Thanking you.

Yours faithfully,

For Hindustan Steelworks Construction Ltd.

(V.K. Singh)

Dy. General Manager.

70.HSCL reiterated its above stand that it would complete the

remaining work at agreed cost of Rs. 106.10 crores and not claim any

compensation for the suspension period by another letter dated

10.5.2005, which is as follows:-

HINDUSTAN STEELWORKS CONSTRUCTION LTD.

(A Govt of India Undertaking) 118, Vandhana. 11 Tolstoy Marg,

New Delhi-110001

Ref.HSCL/DGM/ND/NOIDA-Flyover/2005-2252.

Dt:10.05.2005

To

The Chief Executive Officer, New Okhla Industrial Development

Authority.

Main Administrative Building.

Sector-VI, NOIDA, District. Gautam Budh Nagar-201 301.

Sub: Construction of Two No. Flyovers in NOIDA

Ref: Our Letter No-HSCL/DGM/ND/NOIDA - Flyovers/2005-

2240, dated 29.04.2005 and clarifications on 09.05.2005 to

NOIDA Boards Query.

Dear Sir,

Further to our above referred letter and clarifications to NOIDA Board

on 09.05.2005, we inform that suitable extension of time may kindly

Arbitration Appeal No.219 of 2022

43.

be granted as per clause 11 of the M.O.U. for this work.

We further inform that in public interest, we will complete the work

within our agreed scope at a fixed cost of Rs.106.10 crores and will

not pursue escalation and compensation claim for past abrupt

suspension of work.

In addition, we submit that considering the prevailing trend of price

increase for construction material, NOIDA Authority may kindly

revoke the suspension orders at the earliest and kindly release the

large pending amount immediately to meet the market liabilities to

enable us to commence the work after remobilization of our resources

which may take about a month from the revocation of the Suspension

Order / Release of payments, considering all the Practical aspects.

Your immediate and kind response in the above matter is solicited.

Thanking You,

Yours Faithfully.

for Hindustan Steelworks Construction Ltd.

(V.K. SINGH)

Dy. General Manager

71.On the above assurance of HSCL, NOIDA, after seeking

approval of the Government, revoked the suspension by letter dated

8.3.2006, subject to the parties executing a supplementary MoU

containing specific clause that HSCL would not claim any escalation or

compensation on account of suspension of work.

72.Thus, after several rounds of meetings and deliberations, the

parties entered into a supplementary MoU on 22.3.2006, which is as

follows: -

1. Except in so far this Supplementary Memorandum of

Understanding otherwise provides the earlier Memorandum

of Understanding between the parties hereto for the

construction of the aforesaid Flyover shall continue to

remain in full force.

Arbitration Appeal No.219 of 2022

44.

2. In accordance with Clause 11 of the earlier Memorandum

of Understanding NOIDA has granted extension of time at

the request of HSCL. HSCL shall resume further

construction of the Flyover within 30 days allowed for

remobilisation, from the date of issue of recommencement

letter No. Noida/CPE/Flyover/2006/177 dt. 08.03.2006.

3. In accordance with the letter No.-HSCL/DGM/ND/

NOIDA-Flyover/2005-2240dt. 29.04.2005 and letter No.-

HSCL/DGM/ND/NOIDA-Flyover/2005-2252

dt.10.05.2005 and subsequent meetings between the officer

of NOIDA and HSCL, HSCL unequivocally agrees to

complete the work on the original fixed cost of Rs. 106. 10

crores and not demand any escalation or any compensation,

whatsoever on account of suspension of work during the

period from 22.09.2003 till its recommencement. The letter

dt. 29.04.2005 and 10.05.05 shall be deemed to be part of

this Supplementary Memorandum of Understanding.

4 NOIDA has granted extension. Accordingly, the

remaining works of the project shall be completed within

stipulated period as per MOU, considering suspension

period i.e. from 22.09.2003 to recommencement, so that

HSCL still gets a total period of 27 months to complete the

project as stipulated in the earlier Memorandum of

Understanding.

5. Subject to the aforesaid clauses, all other terms and

conditions as set out in the earlier MOU shall continue to

govern the terms and conditions of the contract between the

parties hereto for construction of Flyover with cloverleaves

M.P. Road 3 and Express Highway and allied work near

Amity School and Construction of Flyover and allied works

at T-Junction near Film City in District Gautam Budh

Nagar.

73.The effect of Clause 1 of Supplementary MoU was that matters

specifically provided therein would have an overriding effect, leaving

remaining matters to be governed by the original contract. Under

Clause 3, it was stipulated that as agreed by HSCL in its letters dated

29.4.2005 and 10.5.2005, it ‘will not demand any escalation or any

Arbitration Appeal No.219 of 2022

45.

compensation, whatsoever on account of suspension of work during the

period from 22.9.2003 till its recommencement’. These letters were

made part of Supplementary MoU. Accordingly, in terms of Clause 1 of

Supplementary MoU, Clause 13(ii)(b) of GCC, making provision for

liquidated damages for period of suspension of contract, stood

superseded. HSCL was precluded from making any claim towards

damages for the suspension period.

74.Despite the same, arbitral tribunal allowed Claim No. 2 of Rs.

35.92 crores towards liquidated damages under Clause 13(ii)(b) of

GCC, after declaring Supplementary MoU to be void and

unenforceable on ground of coercion, undue influence and duress,

having been exercised by NOIDA upon HSCL in obtaining the same.

The relevant findings from the award are extracted below:-

182. The Ld. Counsel for the Respondent has again

reiterated his submissions and case law and set out in a

chronological order the factors leading to the signing of the

Supplementary MOU. He argued that the Supplementary

MOU is a well thought out document which was also acted

upon by the parties and as such the same cannot be

challenged now as being vitiated by undue influence etc.

The same case law was again referred.

183. On the other hand, the Claimant has reiterated the

submissions made with regard to issue No.2 and pointed

out that the bills worth Rs.8.21 crores were held up, bank

guarantees worth Rs.20 crores were with the Respondent

and that there was a threat of cancellation of the contract

and awarding the balance work at his risk and cost.

Claimant has also stated that various senior lawyers

re-consulted by the Respondent felt that the Claimant

should be "compelled" to sign the Supplementary MOU, he

Arbitration Appeal No.219 of 2022

46.

also argued that the idling of the resources were costing the

Claimant very heavily and cancellation of the contract and

consequent awarding the same at the Claimant's risk and

costs would lead to the heavy litigation.

184. It is also evident that the Claimant has also set-up a

case that what was obtained under duress and coercion is

the clause that prohibited escalation and compensation and

not the entire agreement. The letters obtained by the

Respondent from various senior lawyers (Volume C - 1)

show that their intention was to compel the Claimant to

sign the MOU.

185. The points of both the parties were summarized in the

written briefs filed with regard to issues No.2 & 3.

186. In view of the above including the long period of

suspension, the opinions of the lawyers, the held up

amounts etc., I find force in the contention of the Claimant

that the Supplementary agreement has not been signed out

of freewill.

187. Thus on issues 1 to 3 I hold that the issue of coercion

is a matter to be decided by the tribunal, that the tribunal

has the jurisdiction to decide the validity of the same and

that the Supplementary MOU was not in fact signed by the

Claimant out of free will.

(emphasis supplied)

75.The commercial court held the aforesaid finding to be patently

illegal and violative of public policy of India.

Plea of unequal bargaining power in a commercial contract :

76. One of the findings of the Commercial Court is that plea of

unequal bargaining power, which has been accepted by the arbitral

tribunal in holding Supplementary MoU to be void and unenforceable,

does not apply to a commercial transaction. In coming to the said

conclusion, Commercial Court placed reliance on the judgement of the

Arbitration Appeal No.219 of 2022

47.

Supreme Court in Central Inland Water Transport Corporation

(supra) and of Bombay High Court in Balaji Pressure Vessels Ltd.

(supra).

77.In Central Inland (supra), the Supreme Court was examining the

terms of contract of employment between employer and employee. In

that context, it examined the issue as to whether a particular term of the

contract which was unconscionable could still be enforced. A large

number of decisions of the Courts of United States, United Kingdom

and France were noticed and thereafter it was concluded that all legal

systems permit judicial review of a contractual transaction in certain

circumstances. The Courts will not enforce an 'unfair and unreasonable

contract', or an 'unfair and unreasonable clause in a contract', entered

into between the parties who are not equal in bargaining power. By way

of illustration, it is noted that one such case would be where there is

great disparity in the economic strength of the contracting parties. The

second would be “where a man has no choice, or rather no meaningful

choice, but to give his assent to a contract or to sign on the dotted line

in a prescribed or standard form or to accept a set of rules as part of

the contract, however unfair, unreasonable and unconscionable a

clause in that contract or form or rules may be”. An exception to the

above will be a case “where the bargaining power of the contracting

parties is equal or almost equal. This principle may not apply where

Arbitration Appeal No.219 of 2022

48.

both the parties are businessmen and the contract is a commercial

transaction”. However, it is also observed that “in today's complex

world of giant corporations with their vast infra-structural

organizations and with the State through its instrumentalities and

agencies entering into almost every branch of industry and commerce,

there can be myriad situations which result in unfair and unreasonable

bargains between parties possessing wholly disproportionate and

unequal bargaining power. These cases can neither be enumerated nor

fully illustrated. The court must judge each case on its own facts and

circumstances”.

78.In Balaji Pressure Vessels Ltd. (supra) the petitioner, which

raised the plea of coercion, was manufacturer of cylinders which were

used by the oil industries for liquid petroleum gas. The petitioner

supplied oil cylinders in pursuance of purchase orders issued in its

favour by the Oil Companies. The initial purchase order dated

1.05.1999 stipulated a provisional price of Rs. 678.77. The terms and

conditions of the purchase order, inter alia, envisaged a formula for

price escalation/de-escalation, according to which, final price would be

fixed by the respondents and communicated to the petitioner. The

provisional price fixed on 1.04.1999 was amended by letter dated

30.07.1999. The controversy between the parties arose when the

respondents issued a Circular letter dated 31.10.2000 stating that as per

Arbitration Appeal No.219 of 2022

49.

report of Industry Task Force, they had decided to revise the

provisional price to Rs.645 w.e.f. 1.07.1999 and the differential amount

would be realised by adjustment in future bills. The plea of coercion

raised by the petitioner was repelled by holding that there was nothing

on record to show that any illegitimate pressure was exerted on the

petitioner so as to pressurize it to enter into contract against its will. It

was held that as a matter of fact on 28.06.1999 when the petitioner was

informed that the final price would be fixed after review by Industry

Task Force, there was no question of the petitioner accepting depressed

price under any economic compulsion. It willingly accepted the

conditions contained in the letter dated 28.06.1999. The Court noticed

that in fact the petitioner accepted the provisional price expecting that

the final price would be higher than the provisional price.

Consequently, the plea that the petitioner had no choice left in the

matter or any coercion was exercised on it, has been repelled.

78(a). In concluding part of the judgment, it has been observed that

the plea of unequal bargaining power was hardly open to the petitioner.

Even in the said case, after noticing the legal position expounded in

Atlas Express Ltd. vs. Kafco (Importers & Distributors) Ltd.,

14

, it

was held that a plea of economic duress, if taken, has to be examined

on the basis of principles laid down by the Privy Council in Pao On

14 QBD (1989) 1 All ER 641

Arbitration Appeal No.219 of 2022

50.

and others vs. Lau Yiu Long and others

15

. The relevant extract from

the said judgment is as follows: -

12. In Altas Express Ltd. (supra), we find a good deal of

discussion on economic duress as a factor which vitiates a

consent. A litany of judgments has been noted, where English

judges have acknowledged the existence of this concept, and

applied it to a variety of situations. The passages from the

Judgment of Lord Scarman in Pao On v. Lau Yiu quoted therein

succinctly bring out the meaning of economic duress. Duress,

whatever form it takes, is a coercion of the will so as to vitiate

consent, notes the learned judge, but explains that in a contractual

situation commercial pressure on a party alone is not enough.

There must be some factor "which could in law be regarded as a

coercion of his will so as to vitiate his consent". In such cases, it

may be material to enquire whether the person alleged to have

been coerced did or did not protest; whether, at the time he was

allegedly coerced into making the contract, he did or did not have

an alternative course open to him such as an adequate legal

remedy; whether he was independently advised; and whether

after entering the contract he took steps to avoid it. Simple

commercial pressure is not good enough. The pressure so as to

constitute duress must be such that the victim must have entered

the contract against his will, must have had no alternative course

open to him, and must have been confronted with coercive acts

by the party exerting the pressure. In other words, the pressure

exercised by the other party must be such as the law would not

regard legitimate. After a review of various authorities on the

point, the necessary ingredients of a plea of economic duress as a

ground for avoiding a contract are stated by the Delhi High Court

as follows:

“(a) Pressure which is illegitimate;

(b) Its effect on the victim i.e. that the pressure must be a

significant cause inducing the Claimant to enter into the contract;

(c) Lack of reasonable alternative i.e. that the practical effect of

the pressure was that there is compulsion on, or a lack of practical

choice for, the victim."

79.In a recent judgment in Gas Authority of India Ltd Vs. Indian

15 22 (1979) 3 All ER 65 (PC)

Arbitration Appeal No.219 of 2022

51.

Petrochemicals Corporation Ltd and others

16

, the Supreme Court in

case of a commercial contract between M/s Gas Authority of India Ltd.

(for short 'GAIL'), a Government of India undertaking and Indian

Petrochemicals Corporation Ltd. (for short 'IPCL'), formerly a public

sector undertaking, upheld the plea of unequal bargaining power while

striking down certain conditions of a contract between them.

79(a).The plea of IPCL that it had no choice but to enter into

contract accepting the conditions stipulated by GAIL, in view of its

unequal bargaining powers was accepted, observing thus :-

22.On a basic principle, it cannot be doubted that once

GAIL has laid down the pipeline, it is entitled to structure

in its cost in the contract. However, the issue is not simply

that. We are faced with a scenario where two public sector

enterprises entered into a contract in pursuance of the

allocation made by the MOPNG. There was also a time

constraint for IPCL. After incurring a heavy expenditure in

the construction of the Gandhar Plant, IPCL had very little

choice but to enter into the contract. What is of most

significance is that IPCL was bound to follow the allocation

terms provided by the principal authority, i.e., MoPNG.

Thus, as pleaded by IPCL, they were faced with a

"Hobson's choice", where they had to either give up the

contract or accept the clauses levying transportation

charges. On a conspectus of the above factors, it can be said

that GAIL exercised an unequal bargaining power at the

time of signing the contract.

(emphasis supplied)

80.In a more recent judgment in Kalpraj Dharamshri & Others vs.

Kotak Investment Advisors Ltd. & Others,

17

the Supreme Court

applied the principles laid down in Central Inland (supra) in striking

16(2023) 3 SCC 629

17 2021 (10) SCC 401

Arbitration Appeal No.219 of 2022

52.

down unconscionable clause in a commercial transaction. The relevant

extract is as follows: -

115. We are, therefore, of the view, in light of the law laid down

in Central Inland Water Transport Corpn. Ltd., KIAL cannot

be held to be bound by such unconscionable clause in the letter,

which is in a prescribed format.

(emphasis supplied)

81.None of the above judgments envisage a complete bar in

examining the plea of economic duress in a contract between two

business entities. However, as observed in Central Inland (supra),

each case must be judged on its own facts and circumstances.

82.We now proceed to discuss the judgments cited on behalf of

HSCL in support of its plea that economic duress had vitiated the

supplementary memorandum of understanding executed between the

parties on 22.03.2006. The first case cited is by the Supreme Court in

National Insurance Company Limited vs. Boghara Polycab Private

Limited

18

, where the High Court while disposing of the application

under Section 11 of the Act, left the issue relating to accord and

satisfaction of the claim to be decided by the arbitral tribunal. It has

been observed that the view taken by the High Court that it was prima

facie satisfied that the discharge voucher was not issued voluntarily and

the claimant was under some compulsion or coercion and that the

matter deserved detailed consideration by the arbitral tribunal, did not

18 (2009) 1 SCC 267

Arbitration Appeal No.219 of 2022

53.

require interference by the Apex Court. The said judgment is not of

much help to HSCL, except to the extent that in commercial

transactions, a plea relating to economic duress is not completely

barred and can be set up by a party and in which event, it would require

adjudication by the court or by the tribunal, as the case may be.

83.On the same line is the judgment of Supreme Court in K.

Ramachandra Rao vs. Union of India & Others,

19

wherein the

Supreme Court left open the issue relating to accord and satisfaction

based on no-dues certificate alleged to have been obtained under undue

influence, to be decided by the court below while disposing of

application under Section 20 of the Arbitration Act, 1940.

84.The next judgment is by the Delhi High Court in Supermint

Exports Private Limited vs. New India Assurance Company

Limited and Others

20

. In the said case, again a discharge voucher was

alleged by the claimant to have been obtained by the other side by

exercising undue influence and coercion. It has been held that such a

defence is permissible in law. Further in the facts of that case, it was

held that the finding returned by the arbitral tribunal that the discharge

voucher was obtained by coercion, did not suffer from any such

infirmity that may warrant interference by the court under Section 34 of

the Act.

19 1994 Supp (2) SCC 545 (2)

20 2021 SCC OnLine Del 5237

Arbitration Appeal No.219 of 2022

54.

85.Another judgment of the Delhi High Court in New India

Assurance Company Limited vs. Khanna Paper Mills Limited

21

was relied upon in contending that the finding of an arbitral tribunal on

the issue of duress and coercion in a particular case is a finding of fact

and cannot be interfered by the court. In this regard, reliance has been

placed on paragraph no. 81 of the judgment which is extracted below: -

81. In the present case, the learned Arbitral Tribunal has found,

on facts, that Khanna was under financial duress when it signed

the joint discharge voucher on 27th May 2013. These findings,

predicated on material on record, cannot be revisited under

Section 34 of the 1996 Act, as they cannot be said to suffer from

perversity, as understood in law. While this aspect of financial

duress is by itself sufficient to sustain the finding of the learned

Arbitral Tribunal that Khanna's claims did not stand extinguished

by accord and satisfaction, the additional fact that Khanna had

been made to sign a blank discharge voucher is of no little

significance. Getting an insured to sign a blank discharge voucher

is a practice which has been specifically deprecated by the

Supreme Court in Boghara Polyfabz. It partakes, even by itself,

of the nature of coercion. It cannot be expected that an insured

would, willy nilly, and of its own volition, sign a blank discharge

voucher, even before being told the amount which is being

released to it.

85(a). As would reveal from a bare perusal of the passage quoted

above, the court did not interfere with the finding of the arbitral tribunal

after reaching to a satisfaction that the said finding did not suffer from

perversity as understood in law. We are reluctant to read the aforesaid

observation as laying down that in no case, a finding relating to

coercion and duress returned by an arbitral tribunal, can be interfered

21 (2022) SCC OnLine Del 4269

Arbitration Appeal No.219 of 2022

55.

with under Section 34 of the Act. It would depend upon fact of each

case and if the finding suffers from a patent illegality or is covered by

any of the grounds stipulated under Section 34 of the Act, then it would

definitely be within the scope of interference by the Court.

86.In Associated Constructions vs. Pawanhans Helicopters Pvt.

Ltd.

22

, the contractor issued no-dues certificate, specifically mentioning

that insistence on part of the other side for issuance of such a certificate

as a condition precedent for clearing off the dues would amount to

economic duress. It is again based on facts of that case and would help

HSCL only to the extent that the plea of economic duress, if otherwise

proved, can be a valid defence to counter the plea of accord and

satisfaction. The relevant paragraphs are extracted below: -

26. The letter dated 9-12-1991 from Pawanhans to the contractor

shows that payment could be considered provided the contractor

submitted a “no-claim certificate”. It appears that such certificate

was indeed issued but with no result on which the contractor in

his letter dated 26-12-1991 in reply to the letter dated 9-12-1991,

once again submitted that the payments be released insofar as

they had been certified by the architects/consultants and if there

was a dispute regarding the other payments, they should be

referred to an arbitrator and in desperation further adds :

"However, if you want to hold us to economic duress

by not paying what you wish to pay, without 'no-claim

certificate’, we shall treat it as 'duress and issue you such a

certificate much against our willingness as we cannot afford

to liquidate our dues by such a certificate.

Please do not hold us to a ransom and arrange to pay.

In case you would still like to insist, let us know, so that we

could issue you such a certificate under duress as we have

serious financial problems"

22 2008 (16) SCC 128

Arbitration Appeal No.219 of 2022

56.

27. It appears that despite the pleading tone of the aforesaid letter,

no payment was made on which the contractor wrote yet another

letter dated 17-2-1992 in which it was submitted as under :

"In spite of our claim statements, you have insisted on

‘no-claim certificate’, we hereby give you this certificate

that we have ‘no-claims’ and hence you pay us what you

might have worked out as our ‘final dues’.

In case, you have a particular draft in which a 'no-

claim’ certificate needs to be issued to receive our dues of

our bill, please let us have the draft, or else this letter may

be treated as the certificate of no claim from our side.”

30. We have reproduced the correspondence in extenso to show

that the contractor was compelled to issue a "no-dues certificate"

and in this view of the matter, it could not be said that the

contractor was bound by what he had written. It is also clear that

there is voluminous correspondence over a span of almost 2 years

between the submission of the first final bill on 3-6-1991 and the

second final bill dated 2-2-1993 and as such the claim towards

escalation or the plea of the submission of a "no-dues certificate"

under duress being an afterthought is not acceptable.

87. The position which thus emerges is that there is no absolute bar in

raising plea of duress/coercion and unequal bargaining power in a

commercial contract between two business entities, albeit a heavy

burden lies on the party who raises it, to prove the same. Therefore, we

are of the opinion that finding of the arbitral tribunal that it was

competent to examine the plea of duress, coercion and unequal

bargaining power does not suffer from any such illegality as would

require interference under Section 34 of the Act.

Economic Duress :

88.The Commercial Court has also held, as noted above, that HSCL

had failed to prove the four factors specified in Classic Motors Ltd.

Arbitration Appeal No.219 of 2022

57.

(supra) and has therefore failed to prove duress and coercion.

89. It is noteworthy that the four factors stipulated in M/s Classic

Motors (supra) to adjudge whether any duress or coercion was played

on a party in a commercial contract, primarily relates to ascertainment

of the fact as to whether the party had raised any protest before or after

the agreement or took any step to avoid the contract or recourse to any

alternative course of action. The fourth factor is also inter-twined with

the above three factors and which relates to party aggrieved having

benefit of the independent advice.

90.It was vehemently contended by learned senior counsel appearing

for HSCL that the judgment in M/s Classic Motors was rendered by

the Delhi High Court while deciding objections under Section 34 of the

Act. Therefore, it cannot be placed at such high pedestal as to treat the

principles laid down therein as the public policy of India and set aside

the award by applying the aforesaid principles.

91.The argument though attractive at first blush, does not have any

substance. In fact, the judgment in M/s Classic Motors does not

formulate any new test or principles of law. It only reiterates the legal

position laid down in number of previous judgments. These judgments

elaborately take into account the statutory provisions, the view of the

Privy Council and the famous treatise on Contract by Chitty.

92.It is evident from para 31 of the Law Report in M/s Classic

Arbitration Appeal No.219 of 2022

58.

Motors that it places reliance on the judgment in Unikol Bottlers

Limited vs. Dhillon Kool Drinks

23

, wherein the aforesaid principles

have been noted after discussing the provisions of the Contract Act.

Para 31 from the Law Report in M/s Classic Motors is extracted

below: -

(31) The plea of the plaintiff that clause 21 is invalid because of

unequal bargaining power and duress and coercion also needs to

be examined at this stage. My attention is drawn to a decision of

this Court in Unikol Bottlers Ltd. Vs. Dhillon Kool Drinks,

reported in 1994 (28) DRJ 483. Paragraph 32 of the said

judgment being relevant for my purpose is extracted below:-

"For a valid contract it is essential that the parties have

given their free consent for it. Section 10 of the Contract

Act statutorily recognises the requirement of free consent

for a valid contract. Section 13 of the Contract Act defines

consent as follows:- `two or more persons are said to

consent when they agree upon the same thing in the same

sense'. Section 14 of the said Act defines `free consent' as

`consent is said to be free when it is not caused by :- (1)

Coercion, as defined in Section 15; (2) undue influence, as

defined in Section 16; or (3) fraud, as defined in Section 17

or (4) misrepresentation, as defined in Section 18; or (5)

mistake, subject to the provisions of Sections 20,21, and 22.

Consent is said to be so caused when it would not have

been given but for the existence of such coercion, undue

influence, fraud, misrepresentation or mistake, 'Section 15

& 16 define coercion and undue influence. What follows

from these statutory provisions is that an agreement to be

valid should be the result of free consent apart from other

requirements. While dealing with the question of

duress/coercion and unequal bargaining power one is really

concerned with the question of free will i.e. did the parties

enter into the agreement with a free will? It is the plaintiff

who has raised the question of its will being dominated by

the defendants and, therefore, not being a free agent.

Therefore, the plaintiff is on test. It has to be ascertained

whether the plaintiff exercised a free will or not while

231994 (28) DRJ 483

Arbitration Appeal No.219 of 2022

59.

entering into the Supplemental Agreement. For this purpose

there are several factors which need to be looked into. They

are - (1) Did the plaintiff protest before or soon after the

agreement? (2) Did the plaintiff take any steps to avoid the

contract? (3) Did the plaintiff have an alternative course of

action or remedy? If so, did the plaintiff pursue or attempt

to pursue the same? (4) Did the plaintiff convey benefit of

independent advice?"

93.The judgment in M/s Classic Motors also takes note of

paragraph 37 of the judgment in Unikol Bottlers Limited (supra)

which is pertinent to the controversy involved and is therefore extracted

below: -

(33) From the facts available before me, it is crystal clear that the

defendant did not exercise any duress on the plaintiff or that the

agreement was arrived at with the plaintiff without its free

consent. At paragraph 37 of the judgment in Unikol Bottlers Ltd.

(Supra.) it has been held thus:-

"The contracts are meant to be performed and not to be

avoided. Justice requires that men who have negotiated at

arm's length, be held to their bargains unless it can be

shown that their consent was vitiated by fraud, mistake or

duress. The real test is to first establish that the means

pursued were illegitimate in the sense of amounting to or

threatening a crime, tort or a breach of contract (though

possible not plausible breach of contract will suffice).

Secondly, one must establish that the illegitimate means

were a reason, though not necessarily the pre-dominate

reason for the victim's submission. Applying these tests to

the facts of the present case. I am unable to persuade myself

to hold that the consent of the plaintiff to enter into the

Supplemental Agreement was not free or was vitiated on

any of the grounds urged before me and discussed

hereinbefore."

94.In another judgment in Sara International Limited vs. Rizhao

Steel Holding Company Limited

24

, the same principles have been

242013 SCC OnLine 2236

Arbitration Appeal No.219 of 2022

60.

applied to determine the plea of economic duress. The jurisprudential

aspects based on the Commentary by Chitty on Contract and certain

judgments of the Privy Council and Court of Appeal were elaborately

considered. Chitty at 7-008 has observed that in a commercial

transaction, it is not uncommon that pressure and threats do take place,

but the two important factors which are to be considered are whether,

(i) the pressure or threat is legitimate; and (ii) its effect on the victim.

The relevant observations are extracted below: -

“a. 7-008 "Legitimacy of the pressure or threat. Once it is

accepted that the basis of duress does not depend upon the

absence of consent, but on the combination of pressure and

absence of practical choice, it follows that two questions become

all-important. The first is whether the pressure or the threat is

legitimate; the second, its effect on the victim. Clearly, not all

pressure is illegitimate, nor even are all threats illegitimate. In

ordinary commercial activity, pressure and even threats are

both commonplace and often perfectly proper...".

(emphasis supplied)

Chitty, further elaborating, observed that : -

e. 7-031 "Reasonable alternative. It is certainly relevant whether

or not the victim had a reasonable alternative. The victim s lack

of choice was emphasised by Lord Scarman in the Pao On and

Universe Sentinel cases and has clearly been an important factor

in those cases in which relief has been given..."

f. 7-034 "Protest.In the Pao On case it was said that it was

relevant whether or not the victim protested. This again seems to

be a question of evidence as whether or not the threat had a

coercive effect. It has been accepted for many years that when a

payment is made in order to avoid the wrongful seizure of goods,

protest "affords some evidence...that the payment was not

voluntarily made", but that the fact that the payment was made

without protest does not necessarily mean that the payment was

voluntary".

Arbitration Appeal No.219 of 2022

61.

g. 7-035 "Independent advice. Likewise in the Pao On case it was

said that it is relevant whether or not the victim had independent

advice. The relevance of this is perhaps less obvious: access to

legal advice, for example, will not increase the range of options

available to the victim, and lack of advice therefore cannot be an

absolute requirement. However, whether or not the victim

appreciated that he had an alternative remedy and what the

practical implications of following it would be are relevant to the

question of causation".

95.Privy Council in Pao On (supra) observed that "Duress,

whatever form it takes, is a coercion of the will so as to vitiate

consent.........in a contractual situation commercial pressure is not

enough. There must be present some fact 'which could in law be

regarded as a coercion of his will so as to vitiate his consent'. ...........In

determining whether there was a coercion of will such that there was

no true consent, it is material to inquire whether the person alleged to

have been coerced did or did not protest; whether, at the time he was

allegedly coerced into making the contract, he did or did not have an

alternative course open to him such as an adequate legal remedy;

whether he was independently advised; and whether after entering the

contract he took steps to avoid it. All these matters are relevant in

determining whether he acted voluntarily or not."

96.The Bombay High Court in Balaji Pressure Vessels (supra)

applied the same test laid down by Privy Council in Pao On (supra) in

adjudging whether economic duress had vitiated the contract between

Arbitration Appeal No.219 of 2022

62.

the parties or not. It has been concluded that simple commercial

pressure is not good enough to vitiate the consent. The pressure

exercised by the other party must be such as the law would not regard

legitimate.

97.The Supreme Court in GAIL Ltd. (supra) has virtually applied

the same principles to judge the plea of duress, coercion and unequal

bargaining power. It held that IPCL was put in a situation where it was

left with no meaningful choice. In such a case, not raising protest or not

taking steps to avoid the contract looses its significance.

98.It emerges from the above discussion that the factors specified in

M/s Classic Motors have their foundation in the basic jurisprudence

and have been recognized in large number of other judgments. These

principles have repeatedly been held to be guiding factors to adjudge

the sustainability of a plea of economic duress.

Whether any option or remedy was available to HSCL:

99.Now the all important question is whether HSCL was having any

meaningful choice after the work was suspended by NOIDA? Whether

there was any pressure or threat which was illegitimate so as to vitiate

consent to the new bargain i.e., Supplementary MoU?

100.The material on record reveals that the work was stopped as IIT

(Delhi) reported the contract value to be higher by 60 crores. Another

project appraisal and planning company estimated the value of contract

Arbitration Appeal No.219 of 2022

63.

to be inflated by about 40 crores. Undoubtedly, HSCL did not agree to

the proposal of NOIDA for revision of rates. At the same time, HSCL

also did not invoke the option of treating the contract to be a

'foreclosure', nor terminated the same and sue NOIDA for damages, as

in its economic wisdom, it felt that it would be more detrimental to it.

On the other hand, the stand of NOIDA was that the mobilization

advance and other amounts already paid to HSCL towards running

bills, i.e. a sum of Rs. 49.98 crores, if taken into account, there was

excess payment of about Rs. 20 – 30 crores, as compared to the work

executed by that time. The consistent legal opinion it received was that

determination of contract at the stage would be counter-productive and

also against public interest. Therefore, it should ensure that a negotiated

settlement takes place with HSCL. So, both the parties were vitally

interested in breaking the deadlock so that the work is resumed. To

achieve the said objective, they engaged themselves in several rounds

of negotiations and ultimately, the ice was broken with NOIDA,

accepting the stand of HSCL that there would be no reduction in

contract value and it would be granted reasonable time extension to

complete the project. In return, HSCL agreed to forego its claim for

damages for the suspension period. It was out and out a commercial

bargain by the parties, keeping their respective economic interests in

mind.

Arbitration Appeal No.219 of 2022

64.

101.Even if we assume for argument's sake that there was pressure on

HSCL to waive its right to claim damages for the suspension of work,

on basis of legal advice received by NOIDA, we find nothing

illegitimate in the same. In the words of Chitty - “Clearly, not all

pressure is illegitimate, nor even are all threats illegitimate. In

ordinary commercial activity, pressure and even threats are both

commonplace and often perfectly proper”.

102.HSCL understood the nuances of giving up its right to price

escalation and damages during the period work remained suspended. It

knew that it would not mean waiver of its right to claim price escalation

prior to suspension of work or post resumption of work but only

damages for the suspension period. This is evident from various

communications which took place between the parties, post resumption

of work:-

(a) On 25.02.2008 HSCL made a claim towards price variation

as per Clause 8 of the GCC. It emphasised therein that

Supplementary MoU ‘prohibits only escalation or any

compensation for suspension of work during the period from

22.09.2003 till its recommencement’. Therefore, its claim in

relation to price variation be accepted.

(b) It seems that NOIDA vide letter dated 5.02.2008 informed

HSCL that ‘no escalation payment will be made to you as per

term of revised MoU’.

(c) In response, HSCL vide letter dated 10.04.2008 emphasised

Arbitration Appeal No.219 of 2022

65.

that Clause 3 of Supplementary MoU only prohibited ‘escalation

or any compensation whatsoever on account of suspension of

work during the period from 22.09.2003 till its commencement’.

It was further emphasised that the claim for price escalation was

submitted excluding the suspension period. ‘The price variation

claims have been submitted covering the period from 7.04.2003

to 22.09.2003 i.e. till suspension and after recommencement till

date excluding the suspension period. Therefore our price

variation bills are fully justified and are tenable in all respect in

accordance with Clause 7 of original MoU, Clause 8 of General

Conditions of Contract which have neither been superseded nor

amended and Clause 3 of Supplementary MoU’.

103. Notably, the work was completed on 30.04.2008. HSCL, neither

during course of execution of work, nor after its completion, made any

claim towards damages during suspension period being fully conscious

of the implications of Clause 3 of Supplementary MoU whereunder it

had explicitly agreed not to demand ‘any compensation whatsoever on

account of suspension of work during the period from 22.09.2003 till

its recommencement’. The only claim it was making was towards price

escalation.

104.However, while giving notice dated 16.02.2009, HSCL invoked

the arbitration clause under the contract and submitted a list of disputes

and claims to be referred for arbitration. It, inter alia, included a claim

of Rs.37.12 crores towards damages for suspension of work under

Clause 13 of GCC. It was followed by another letter dated 20.03.2009

Arbitration Appeal No.219 of 2022

66.

to the same effect.

105.Even while making the above claim for liquidated damages

during suspension period under Clause 13(ii)(b) of GCC, it never

alleged any undue influence, duress or coercion having ever been

exercised over it in making it sign the Supplementary MoU.

106.HSCL, when it approached the High Court under Section 11 of

the Act for appointment of arbitrator, alleged for the first time that

Supplementary MoU was a result of undue influence, coercion and

duress upon it. The above chain of events lends full support to the view

taken by the court below that the claim in respect of damages for

suspension of work was 'afterthought and sham'.

107.Recently the Supreme Court in NTPC Ltd. Vs. SPML Infra

Ltd.

25

, was examining a plea of economic duress set up by SPML Infra

Ltd. in a case arising out of Section 11(6) of the Act. In the said case,

after issuance of a completion certificate by NTPC and release of final

payment, SPML issued no-demand certificate. Till that time, there was

no pending claim of any kind of SPML against NTPC. However, while

releasing final payment, NTPC withheld the bank guarantees on

account of certain pending disputes with regard to other projects

between the parties. SPML being aggrieved thereby, preferred a writ

petition in the jurisdictional high court for quashing of the order by

25 2023 SCC OnLine SC 389

Arbitration Appeal No.219 of 2022

67.

which the bank guarantees were retained by NTPC. An interim order

was passed in the said petition restraining NTPC from invoking the

bank guarantees. During pendency of the writ petition, the parties

entered into multiple discussions and thereafter arrived at settlement

agreement in writing dated 27.5.2020, whereunder NTPC agreed to

release the original bank guarantees while SPML agreed not to raise

any claim of any nature against NTPC pertaining to the contract. On

30.6.2020, NTPC released the bank guarantees in compliance of the

settlement agreement. SPML thereafter withdrew the writ petition. One

month later, on 10.10.2020, SPML filed petition under Section 11(6)

alleging coercion and economic duress in execution of the settlement

agreement. The application was resisted by NTPC on the ground that

there were no subsisting disputes between the parties in view of the

settlement agreement dated 27.5.2020 and the application for

arbitration was an afterthought and abuse of the process of law. The

Supreme Court firstly examined the scope of the power of the court to

decide the issue of non-arbitrability of a dispute. It relied on its

previous decision in Vidya Drolia & Others v. Durga Trading

Corporation,

26

, in holding that the scope of judicial review in such

matters is very limited, confined only to weeding out of manifestly ex

facie non-existent disputes. The important aspect considered in the

26 (2021) 2 SCC 1

Arbitration Appeal No.219 of 2022

68.

judgment, which is relevant for the case in hand, is the issue of

economic duress. Whether the allegations of coercion and economic

duress in the execution of settlement agreement between the parties

was at all made out? The Supreme Court noticed that the execution of

the settlement agreement led to the release of the bank guarantees.

After reaping the benefits of the settlement agreement, the writ petition

was withdrawn. SPML never alleged any economic duress while the

settlement agreement was being complied with by the parties. It was

only after one month of withdrawal of the writ petition in compliance

of the settlement agreement that SPML for the first time, raised the plea

of economic duress. In such backdrop, it was held that the plea lacked

bonafides and was ex facie frivolous and untenable. The relevant

observations in this behalf are as follows: -

47. The plea of coercion and economic duress must be seen in the

context of the execution of the Settlement Agreement not being

disputed, and its implementation leading to the release of the

Bank Guarantees on 30.06.2020 also not being disputed. Almost

three weeks after the release of the Bank Guarantees, a letter of

repudiation was issued by SPML on 22.07.2020. This letter was

issued about two months after the Settlement Agreement was

executed and in fact during the subsistence of the Writ Petition.

After reaping the benefits of the Settlement Agreement, the Writ

Petition was withdrawn on 21.09.2020. It is thereafter that the

present application under Section 11(6) of the Act was filed. The

sequence of events leads us to conclude that the letter of

repudiation was issued only to wriggle out of the terms of the

Settlement Agreement.

48. The foregoing clarifies beyond doubt that the claims sought to

be submitted to arbitration were raised as an afterthought.

Further, SPML's allegations of coercion and economic duress in

Arbitration Appeal No.219 of 2022

69.

the execution of the Settlement Agreement lack bona fide. They

are liable to be knocked down as ex facie frivolous and untenable.

108.In the instant case also, it has been rightly observed by the court

below that HSCL entered into Supplementary MoU after due

deliberation. It reaped the benefit of Supplementary MoU on basis

whereof the order of suspension of work was withdrawn and HSCL

succeeded in completing the project. It did not raise any protest while

executing the work in terms of the conditions stipulated in the

Supplementary MoU. As noted above, HSCL itself admitted in series of

communications that the effect of the Supplementary MoU is only

giving up of its right to claim compensation on account of suspension

of work. Its claim relating to price escalation for the period when work

was not on hold, would remain unaffected. Fully knowing the

implications of the fresh bargain between the parties, it completed the

project. At that time, the only dispute between the parties was with

regard to its claim relating to price escalation which in fact has also

been allowed by the tribunal and the court below. However, at no point

of time, it ever raised any plea of economic duress in acceding to the

demand of NOIDA to give up claims in respect of damages on account

of the suspension of work. Almost after an year, it raised the claim for

damages under Clause 13 of GCC and which has therefore been rightly

held to be afterthought and sham.

Arbitration Appeal No.219 of 2022

70.

109.In the above backdrop, the seminal question is whether there was

any meaningful choice available to HSCL or not. It is worthwhile to

reiterate that it had the option of foreclosure under Clause 11 of GCC.

Now, the said choice was a meaningful choice or not has to be

examined. It is contended by counsel for HSCL that at the relevant

time, HSCL was not in position to exercise the above options as it

would have ruined it financially on account of -

(a) pending unpaid dues of Rs. 8.21 crores;

(b) possibility of denial of extension of time;

(c) lack of option to terminate the contract;

(d) possibility of termination leading to disqualification /

blacklisting and costs of balance works being claimed by the

NOIDA;

(e) invocation of bank guarantees, and

(f) costs of litigation and loss of reputation.

110.The argument is specious and is to be rejected outright. In case of

exercise of option of foreclosure under Clause 11 of GCC,

compensation and damages payable to the contractor duly takes into

account unpaid dues, price of unused materials lying at the site and in

godowns and reasonable compensation for repatriation of contractors'

site staff and imported labour to the extent necessary. HSCL also had

the advantage of there being in place a prohibition in respect of

recovery of dues against mobilization advance. Additionally, NOIDA

Arbitration Appeal No.219 of 2022

71.

would have been under obligation to release retention money. All bank

guarantees would have got discharged automatically. Thus, there was

no possibility of any financial loss or loss in terms of reputation, nor

any possibility of blacklisting, as is tried to be projected. We have no

hesitation in accepting the contention of counsel for the respondent that

the plea taken in this behalf is non-evidentiary, speculative and without

any basis.

111.We also completely agree with the finding of the Commercial

Court that had HSCL not agreed to the new deal, NOIDA would not

have permitted HSCL to go ahead with the contract. In that event, the

only option left with HSCL was to sue for damages. Then, as observed

by court below, question would have arisen “why Respondent No. 1

(HSCL herein) waited for a period beyond 120 days and by applying

principles of mitigation of damages, Respondent No. 1 (HSCL) would

not have been able to get compensation @ Rs. 4 lakhs per day for 928

days. Thus, the intention, the circumstances at the time of signing of

Supplementary MoU clearly speaks of the ad idem of the parties at that

time and the findings of the Learned Arbitrator are contrary to the

specifically and expressly agreed, contractual terms between the

parties”.

Arbitration Appeal No.219 of 2022

72.

Unjust enrichment:

112.The contention of counsel for NOIDA that raising such a sham

claim as above was part of modus operendi of HSCL to unjustly enrich

itself at the cost of public exchequer, also has considerable force. It is

an admitted fact on record that HSCL had entered into a joint venture

agreement with M/s Navyug Engineering Company Ltd. (NECL) dated

25.3.2003. Any amount received under the contract was to be shared

between HSCL and NECL in proportion of 4.25% to 95.75%. Thus,

HSCL was getting hardly Rs. 5 crores under the contract as centage

charges and the entire remaining amount was to go to a private entity

(NECL). It is not a case where money would transfer hand from one

instrumentality of the State to another. It would essentially result in

unjust enrichment of NECL at the cost of public exchequer, which

would definitely be against public policy of India.

Conclusion :

113.We have no hesitation in upholding the finding of the court below

that by allowing Claim No.2, the arbitral tribunal had tried to rewrite

the terms of contract between the parties. The court below has also

rightly held that the finding of the arbitral tribunal that economic duress

had any role in the bargain, was based on conjectures and surmises,

without any material on record to sustain such findings, resulting in a

patent illegality, warranting interference under Section 34 of the Act.

Arbitration Appeal No.219 of 2022

73.

Consequently, award made in respect of Claim No. 2 has rightly been

held by the court below to be unsustainable in law.

Point No. 2

Whether arbitral award can be set aside in part?

114.This leads us to the second crucial question. What would be the

effect of turning down Claim No. 2 on the remaining part of the award?

Whether there was any impediment in setting aside part of the award

and upholding the remaining part which was found to be valid?

115.Section 32 of the Act deals with termination of arbitral

proceedings. It reads as follows :-

Termination of proceedings.-- (1) The arbitral proceedings shall

be terminated by the final arbitral award or by an order of the

arbitral tribunal under sub-section (2).

(2) The arbitral tribunal shall issue an order for the termination

of the arbitral proceedings where--

(a) the claimant withdraws his claim, unless the respondent

objects to the order and the arbitral tribunal recognises a

legitimate interest on his part in obtaining a final

settlement of the dispute;

(b) the parties agree on the termination of the proceedings;

or

(c) the arbitral tribunal finds that the continuation of the

proceedings has for any other reason become unnecessary

or impossible.

(3)Subject to Section 33 and sub-section (4) of Section 34, the

mandate of the arbitral tribunal shall terminate with the

termination of the arbitral proceedings.

Arbitration Appeal No.219 of 2022

74.

116.Thus arbitration proceedings stand terminated with the passing of

the final arbitral award or by an an order of the arbitral tribunal under

sub-section (2). Sub-section (2) envisages an order by the arbitral

tribunal to terminate the proceedings in the circumstances enumerated

therein. Sub-section (3) deals with two exceptions where the mandate

of the arbitral tribunal survives for limited purposes even after passing

of the final award. The first exception is for carrying out correction and

interpretation of award or make an additional award. The second

exception is provided under Section 34 (4) of the Act.

117.In earlier part of the judgment, we have discussed Section 34(2)

and (2-A) which specifies the grounds on which an arbitral award can

be set aside by the court. Sub-section (4) enable the arbitral tribunal to

eliminate the grounds which may result in an arbitral award, being set

aside. It is open to a party to request the court to adjourn the

proceedings for a period of time determined by it in order to give the

arbitral tribunal an opportunity to resume the arbitral proceedings or to

take such other action as in the opinion of the arbitral tribunal will

eliminate the grounds for setting aside the arbitral award. The said

power can be exercised by the court only on an application made by a

party and not suo motu. As the purpose is to afford opportunity to the

arbitral tribunal to eliminate the grounds on which there is possibility of

award being set aside, it automatically follows that the stage for

Arbitration Appeal No.219 of 2022

75.

exercising such a power is bestowed before the award is set aside and

not afterwards.

118.The power is not to be confused with an order of remand, as

understood in legal parlance, where a higher court after setting

aside/quashing the order under challenge, remands the matter back to

the court/tribunal to decide the proceedings afresh or in the light of the

observations made in the remand order. In clear distinction to an order

of remand sensu stricto, the power conferred by sub-section (4) of

Section 34 is with the purpose of permitting parties to take measures

which can eliminate the grounds for setting aside the arbitral award by

the court. In Kinnari Mullick and another vs. Ghanshyam Das

Damini

27

, the Supreme Court has lucidly explained the scope of

Section 34(4) as follows:-

15. On a bare reading of this provision, it is amply clear

that the Court can defer the hearing of the application filed

under Section 34 for setting aside the award on a written

request made by a party to the arbitration proceedings to

facilitate the Arbitral Tribunal by resuming the arbitral

proceedings or to take such other action as in the opinion of

Arbitral Tribunal will eliminate the grounds for setting

aside the arbitral award. The quintessence for exercising

power under this provision is that the arbitral award has not

been set aside. Further, the challenge to the said award has

been set up under Section 34 about the deficiencies in the

arbitral award which may be curable by allowing the

Arbitral Tribunal to take such measures which can

eliminate the grounds for setting aside the arbitral award.

No power has been invested by the Parliament in the Court

to remand the matter to the Arbitral Tribunal except to

27(2018) 11 SCC 328

Arbitration Appeal No.219 of 2022

76.

adjourn the proceedings for the limited purpose mentioned

in sub-section 4 of Section 34. This legal position has been

expounded in the case of McDermott International Inc.

(supra). In paragraph 8 of the said decision, the Court

observed thus:

“8…..parliament has not conferred any power of

remand to the Court to remit the matter to the arbitral

tribunal except to adjourn the proceedings as

provided under sub-section (4) of Section 34 of the

Act. The object of sub-section (4) of Section 34 of the

Act is to give an opportunity to the arbitral tribunal to

resume the arbitral proceedings or to enable it to take

such other action which will eliminate the grounds for

setting aside the arbitral award.”

16. In any case, the limited discretion available to the Court

under Section 34 can be exercised only upon a written

application made in that behalf by a party to the arbitration

proceedings. It is crystal clear that the Court cannot

exercise this limited power of deferring the proceedings

before it suo moto. Moreover, before formally setting aside

the award, if the party to the arbitration proceedings fails to

request the Court to defer the proceedings pending before

it, then it is not open to the party to move an application

under Section 34 (4) of the Act. For, consequent to disposal

of the main proceedings under Section 34 of the Act by the

Court, it would become functus officio. In other words, the

limited remedy available under Section 34 (4) is required to

be invoked by the party to the arbitral proceedings before

the award is set aside by the Court.

119.Chapter VIII comprises of two sections only. Section 35 attaches

finality to an arbitral award and Section 36 provides that after expiry of

time for making an application to set aside arbitral award under Section

34 or subject to provisions of sub-section (2) of Section 34, the arbitral

award would be enforced in accordance with the provisions of the Code

of Civil Procedure, 1908, in the same manner as if it were a decree of

court.

Arbitration Appeal No.219 of 2022

77.

120.Under the scheme of the Act, after passing of a final arbitral

award, only following possibilities are contemplated:-

(a) correction of computation errors, clerical or typographical

errors or errors of a similar nature [Section 33(1)(a)];

(b) give an interpretation of a specific point or part of the

award [Section 33(1)(b)];

(c) make an additional award as to claims presented in the

arbitral proceedings but omitted from the arbitral award, on

request of a party [Section 33(4)];

(d) give arbitral tribunal an opportunity to resume the arbitral

proceedings or to take such other action, as in the opinion of the

arbitral tribunal, will eliminate the grounds for setting aside the

arbitral award [Section 34(4)];

(e) setting aside of an award by a Court [Section 34(2)(2-A)] or

in an appeal [Section 37];

(f) commencement of fresh arbitration proceedings in cases

where an arbitral award is set aside, subject to limitation [Section

43(4)].

121.It is noteworthy that under the new Arbitration Act, the court has

not been conferred with any explicit power to modify arbitral award or

to remit it to the arbitrator unlike Sections 15 and 16 of the Arbitration

Arbitration Appeal No.219 of 2022

78.

Act, 1940 (hereinafter referred to as 'the old Act'). This has been

purposely done to minimize judicial interference by the courts in

arbitral awards. The courts have been given only supervisory role to

ensure fairness and strike at arbitrariness, violation of public policy of

India, patent illegalities appearing on the face of record, jurisdictional

error and the like (Section 34 (2) and (3)).

122.In McDermott International Inc. (supra), the Supreme Court

after comparing the provisions of the old Act with the new one held as

follows:-

52. The 1996 Act makes provision for the supervisory role

of courts, for the review of the arbitral award only to ensure

fairness. Intervention of the court is envisaged in few

circumstances only, like, in case of fraud or bias by the

arbitrators, violation of natural justice, etc. The court cannot

correct errors of the arbitrators. It can only quash the award

leaving the parties free to begin the arbitration again if it is

desired. So, scheme of the provision aims at keeping the

supervisory role of the court at minimum level and this can

be justified as parties to the agreement make a conscious

decision to exclude the court's jurisdiction by opting for

arbitration as they prefer the expediency and finality offered

by it.

123.The departure from the scheme of the old Act has been further

elaborated in Project Director, National Highways No.45 E and 220

National Highways Authority of India Vs. M. Hakeem and

another

28

as under:-

19. The statutory scheme under Section 34 of the

28(2021) 9 SCC 1

Arbitration Appeal No.219 of 2022

79.

Arbitration Act, 1996 is in keeping with the UNCITRAL

Model Law and the legislative policy of minimal judicial

interference in arbitral awards.

20. By way of contrast, under Sections 15 and 16 of the

Arbitration Act, 1940, the court is given the power to

modify or correct an award in the circumstances mentioned

in Section 15, apart from a power to remit the award under

Section 16 as follows: -

“15. Power of Court to modify award.- The Court

may by order modify or correct an award-

(a) where it appears that a part of, the award is upon a

matter not referred to arbitration and such part can be

separated from the other part and does not affect the

decision on the matter referred; or

(b) where the award is imperfect in form, or contains

any obvious error which can be amended without

affecting such decision; or

(c) where the award contains a clerical mistake or an

error arising from an accidental slip or omission.

16. Power to remit award.- (1) The Court may from

time to time remit the award or any matter referred to

arbitration to the arbitrators or umpire for

reconsideration upon such terms as it thinks fit-

(a) where the award has left undetermined any of the

matters referred to arbitration, or where it determines

any matter not referred to arbitration and such matter

cannot be separated without affecting the

determination of the matters referred; or

(b) where the award is so indefinite as to be incapable

of execution; or

(c) where an objection to the legality of the award is

apparent upon the face of it., (2) Where an award is

remitted under sub- section (1) the Court shall fix the

time within which the arbitrator or umpire shall

submit his decision to the Court:

Provided that any time so fixed may be extended by

subsequent order of the Court.

(3) An award remitted under sub- section (1) shall

become void on the failure of the arbitrator or umpire

to reconsider it and submit his decision within the

time fixed.”

21. As a result therefore, a judgment in terms of the award

is given under Section 17 of the 1940 Act which reads as

Arbitration Appeal No.219 of 2022

80.

follows: -

“17. Judgment in terms of award.- Where the Court

sees no cause to remit the award or any of the matters

referred to arbitration for reconsideration or to set

aside the award, the Court shall, after the time for

making an application to set aside the award has

expired, or such application having been made, after

refusing it, proceed to pronounce judgment according

to the award, and upon the judgment so pronounced a

decree shall follow and no appeal shall lie from such

decree except on the ground that it is in excess of, or

not otherwise in accordance with, the award.”

22. Thus, under the scheme of the old Act, an award may be

remitted, modified or otherwise set aside given the grounds

contained in Section 30 of the 1940 Act, which are broader

than the grounds contained in Section 34 of the 1996 Act.

124.The dictum in McDermott International Inc. (supra) quoted

above, was relied upon in holding that the court under Section 34 of the

new Act does not have power to modify an award. It has been held that

there would also be no power vested in the court to remit the matter to

the arbitrator except within the limited scope of sub-section (4) of

Section 34. It would be useful to take note of the relevant observations

made in this behalf:-

30.….......... Further, if the power to remit the matter to

the arbitrator is read into Section 34, it would render

inexplicable the deliberate omission by Parliament of a

provision analogous to Section 16 of the Arbitration Act,

1940 in the present Act. Section 16 of the 1940 Act

specifically armed courts with the power to remit the matter

to arbitration. Noticeably, the scope of remission under the

present Act is confined to that prescribed in sub-section (4)

of Section 34. .....

31. Thus, there can be no doubt that given the law laid

down by this Court, Section 34 of the Arbitration Act, 1996

Arbitration Appeal No.219 of 2022

81.

cannot be held to include within it a power to modify an

award. ..........

125.Again, in National Highways Authority of India Vs P.

Nagaraju @ Cheluvaiah and another

29

, it has been reiterated that the

court in proceedings emanating from Section 34 does not have power to

modify the award; the only option would be to set aside the award-

26. Under the scheme of the Act 1996 it would not be

permissible to modify the award passed by the learned

Arbitrator to enhance or reduce the compensation based on

the material available on record in proceeding emanating

from Section 34 of Act, 1996. The option would be to set

aside the award and remand the matter. ...

126.We now come to Dakshin Haryana Bijli Vitran Nigam Ltd.

(supra) on which reliance has been placed by the court below in

holding that the law mandates that an arbitral award cannot be upheld

in part while setting aside the remaining part. In the said case, the main

issue before the Supreme Court was regarding the date from which

period of limitation for filing a petition under Section 34 of the Act

would commence. Would it be the date on which the draft award was

circulated to the parties or the date on which the signed copy of the

award was provided? The Supreme Court answered the said question

holding that the limitation for filing objections under Section 34 would

be reckoned from the date on which signed copy of the award was

made available to the parties. While arriving at the said conclusion, the

292022 SCC OnLine SC 864

Arbitration Appeal No.219 of 2022

82.

Supreme Court also observed that where the court set-asides the award,

the dispute between the parties has to be decided afresh, as there is no

power to modify an arbitral award. The relevant extract is quoted

below:-

“In law, where the Court sets aside the award passed by the

majority members of the tribunal, the underlying disputes

would require to be decided afresh in an appropriate

proceeding. Under Section 34 of the Arbitration Act, the

Court may either dismiss the objections filed, and uphold

the award, or set aside the award if the grounds contained in

sub-sections (2) and (2A) are made out. There is no power

to modify an arbitral award.”

127.None of the above judgments cited by Sri Manish Goyal, learned

Senior Counsel appearing for the respondent – NOIDA deals with

sevarability of award, but with power of the court to modify an arbitral

award. As discussed, that power is definitely not conferred on the

arbitral tribunal, unlike under the old Act.

128.Before we proceed further, we would like to take notice of few

more provisions of the Act which are relevant for deciding the

controversy.

129.As already noted, Section 34 defines the limited terrain in which

the court can exercise its supervisory role in setting aside an arbitral

award. It is crucial to understand the meaning of word 'award' under the

Act. As per Section 2(c), an award is an umbrella term that

encompasses a final award as well as an interim award. An interim

Arbitration Appeal No.219 of 2022

83.

award is also a final award on matters covered thereby, but made at an

interim stage. This has been explained in McDermott International

Inc. (supra) as follows:-

68.The 1996 Act does not use the expression "partial

award". It uses interim award or final award. An award has

been defined under Section 2 (c) to include an interim

award. Sub-section (6) of Section 31 contemplates an

interim award. An interim award in terms of the said

provision is not one in respect of which a final award can

be made, but it may be a final award on the matters covered

thereby, but made at an interim stage.

130.Then there can be an additional award as to claims presented in

the arbitral proceedings but omitted from the arbitral award [Section 33

(4)]. Sub-section (7) of Section 33 extends the provisions of Section 31

to an additional award. Thus, an additional award has to strictly

conform to all the requirements of an 'arbitral award'. There is no

manner of doubt, keeping in view the scheme of the new Act, that an

award whether interim, final or additional, is subject to challenge

before a court of law only by an application and in the manner

contemplated under Section 34. Thus, in a given case, there could be

multiple awards. By way of illustration, we may gainfully refer to

McDermott International Inc. (supra) where there was an additional

award, a partial (interim) award and a final award. It is open to a party

to take recourse to independent proceedings under Section 34 in

challenging each award. Thus, there can be as many number of

Arbitration Appeal No.219 of 2022

84.

challenges under Section 34 as are the awards in a particular case. It is

also possible in a given case that one or more of these awards may go

in favour of a particular party and the remaining against it. Resultantly,

the party may prefer objections under Section 34 only against the award

which goes against it and may not challenge the other award(s) which

is/are in its favour. There is no provision under the Act which mandates

a party to advance a challenge to all the awards. Can the Court in such

a situation reject the objection under Section 34 holding it to be not

maintainable as all awards have not been challenged or while

considering challenge to only one of the awards also proceed to set

aside the remaining awards which are not under challenge before it?

131.In contrast, there can be a situation where the arbitral tribunal

deals with number of distinct and independent claims by passing a

single composite award. In such a case, there is also a possibility that

certain claims are allowed while the others are rejected. The party,

some of whose claims have been rejected, may challenge part of the

award by filing objections under Section 34 of the Act. Again, can the

court in such a case decline to examine the challenge on the ground that

the entire award being not under challenge, the objections would not be

maintainable as it is not having power to set aside only part of the

award? There can also be a case where several and distinct claims arise

out of the same contract at different point in time. This can give rise to

Arbitration Appeal No.219 of 2022

85.

more than one reference, there being no impediment in this regard.

Resultantly, it would result in multiple awards and which could give

rise to multiple challenges under Section 34 of the Act. In such a case,

it could result in some award(s) being upheld while other(s) being set

aside. The same fact situation can give rise to one reference, where a

party waits till the completion of contract and seeks reference

combining all the claims. In such a scenario, there may be one final

award dealing with separate and distinct claims. If we apply the law as

interpreted by the court below, it would result in apparent anomalies in

the ultimate outcome, dependent upon the fact situation. While in the

first case, where there are multiple awards and proceedings under

Section 34 of the Act arising out of same contract, the court under

Section 34 may set aside one of the awards while upholding the other

which is/are separate award(s). In the latter situation, as there is one

composite award, then notwithstanding that only part of the award

pertaining to one or more independent claims alone is under challenge,

the entire award would have to be set aside, as has been done in the

instant case.

132. The above paradox can be resolved if we keep in mind the

scheme of the Act noted above. In cases where there are separate and

distinct claims, not related or dependent upon other claims, then

irrespective of whether they are decided by the arbitral tribunal by an

Arbitration Appeal No.219 of 2022

86.

interim award(s), final award or additional award, the decision of the

arbitral tribunal in respect of each such claim is an independent award

in the eyes of law. Thus, a final award can be an amalgamation or a

bundle of several awards given in respect of separate and distinct

claims. When Section 34 confers power in the court to set aside an

award, the power could be exercised to set aside any or all such awards,

whether composite, interim, final or additional. We cannot loose sight

of the fact that the new Act was enacted with the object of giving the

parties freedom to decide the forum through which they want their

disputes to be decided so as to facilitate ease of doing business. Albeit,

the Act prescribes timelines for various proceedings but it is matter of

common knowledge that the said object has not been achieved and it

takes long in getting the dispute decided even through the arbitral

tribunal. In case the view taken by the court below is upheld and

claims which have been found to be valid and enforceable, are set at

naught on misconception of law that the award has to be set aside as a

whole, it would result in grave injustice to such party apart from

forcing the parties to another round of litigation. Such an interpretation

if given, would be a complete antithesis to the objectives of the Act.

133.The view taken by the court below, if taken to its logical

conclusion, would result in a situation not contemplated under law.

Some of the claims allowed by the arbitral tribunal, have also been

Arbitration Appeal No.219 of 2022

87.

upheld by the court below. There is no occasion for this court to

interfere with the findings recorded in respect of these issues. These

claims are not dependent for their survival on the findings in respect of

claim relating to damages during the period of suspension of work

(Clause No.2 - Issue No. 14). Now if we are to uphold the operative

part of the order of the court below setting aside the entire award while

upholding the findings on various claims with which the court below

has not interfered and assuming a fact situation where the appellant,

subject to law of limitation, starts fresh arbitration proceedings, will

the arbitral tribunal be competent to record contrary findings in respect

of these issues. The principles of issue estopple will preclude the

parties from raising the issues already decided. Similarly, the principles

of res judicata will bind the arbitral tribunal to the finding recorded in

the initial round of litigation.

134. The Supreme Court in Secretary to Govt. Department of

Education (Primary) and others Vs. Bheemesh Alias Bheemappa

30

,

while interpreting a scheme of compassionate appointment of the Bank,

held that “a rule of interpretation which produces different results,

depending upon what the individuals do or do not do, is inconceivable.”

135.The golden rule of interpretation is to take a view which advances

the object of the Act, harmonises every provision of the statute and

30 2022 AIR (SC 402

Arbitration Appeal No.219 of 2022

88.

does not result in any inconsistency or absurdity. The view taken by us

that the award in the instant case is an amalgamation or bundle of

several awards in respect of separate and distinct claims rules out all

possibilities of inconsistencies and contradictions and also efficiently

achieves the object of the Act.

136.Thus there would be no difficulty in case a party prefers to assail

only a particular award and not the other one in a case where there are

more than one award or files objection only against part of the award

pertaining to an independent and separate claim which is severable

from the others, without affecting the decision in respect of the

remaining claims.

137.This would bring us the doctrine of severability, which in our

opinion is not foreign to the new Act. One such situation is

contemplated under the proviso to Section 34(2)(a)(iv) which provides

that if the decisions on matters submitted to arbitration can be separated

from those not so submitted, only that part of the arbitral award which

contains decisions on matters not submitted to arbitration may be set

aside.

138.The contention of counsel for the respondent that the doctrine of

severability is applicable only to the cases falling under the proviso

does not appeal to us. The situation contemplated under the proviso is

only an instance where the doctrine of severability has been explicitly

Arbitration Appeal No.219 of 2022

89.

made applicable by the legislature. It rather reinforces an interpretation

that power to sever bad from good, which inheres in every court

invested with power of judicial review, would also be available to a

court dealing with objections under Section 34 of the Act. The mere

fact that such a power is not specifically paraphrased in other clauses of

sub-section (2) and (2-A) of Section 34, will not detract from the legal

position noted above. We find support in our view in a number of

precedents which we note herein after.

139.The first case is precisely concerning the issue relating to

applicability of doctrine of severability of an arbitral award emanating

from a challenge under Section 34 of the Act. A Full Bench of Bombay

High Court is R.S. Jiwani (M/s.) Mumbai Vs. Ircone International

Ltd. Mumbai

31

, after a detailed consideration of doctrine of

severability, held that the new Act does not in any manner prohibit the

court to apply the said doctrine. The relevant observations are as

follows :-

30. If the principles of severability can be applied to a

contract on one hand and even to a statute on the other

hand, we fail to see any reason why it cannot be applied to

a judgment or an award containing resolution of the

disputes of the parties providing them such relief as they

may be entitled to in the facts of the case. It will be more

so, when there is no statutory prohibition to apply principle

of severability.

We are unable to contribute to the view that the power

vested in the Court under Section 34 (1) and (2) should be

31 2009 SCC OnLine Bom 2021

Arbitration Appeal No.219 of 2022

90.

construed rigidly and restrictedly so that the Court would

have no power to set aside an award partially. The word

"set aside" cannot be construed as to `only to set aside an

award wholly', as it will neither be permissible nor proper

for the Court to add these words to the language of Section

which had vested discretion in the Court. Absence of a

specific language further supported by the fact that the very

purpose and object of the Act is expeditious disposal of the

arbitration cases by not delaying the proceedings before the

Court would support our view otherwise the object of

Arbitration Act would stand defeated and frustrated.

31.Rival submissions have been made before us with

regard to operation and effect of proviso to sub-clause (iv)

of clause (a) of Section 34. According to the appellants the

proviso applies to the entire section while according to the

respondent, its operation is limited to sub-clause (iv) alone.

There seems to be some merit in the contention of the

respondent inasmuch as the language of the proviso is

directly referable to the section itself and, thus, must take

its colour from the principal section viz. 34(2)(iv). A

reading of the proviso shows that where severability is

possible, the court in the class of the cases falling under

sub-clause (iv) is expected to set aside the award partially.

In other words, a greater obligation is placed upon the court

to adopt such an approach when the case in hand is covered

under the provisions of sub-clause (iv). This contention will

not have any adverse effect on the interpretation and scope

of Section 34 as a whole. It is a settled rule of interpretation

that the statutory provision should be read as a whole to

find out the real legislative intent and that provision should

be read by keeping in mind the scheme of the Act as well as

the object which is sought to be achieved by the Legislation

while enacting such a law.

There is nothing in the proviso or in the language of

Section 34 which has an impact or effect to restrict the

power of the court as contemplated under Section 34 (1)

read with the opening words of sub-sections (2) and (4) of

Section 34 the Act. Est boni judicis ampliare jurisdictionem

is a settled canon of law courts should expand and amplify

jurisdiction to achieve the ends of justice and not

unnecessarily restrict its discretion particularly when the

Arbitration Appeal No.219 of 2022

91.

later approach would lead to frustrate the very object of the

Act.

32. The cases or illustrations indicated in the proviso in

fact, should be read to construe that in such other cases

where it is so necessary the court should exercise its

discretion and apply the principle of severability rather than

compel the parties to undergo the entire arbitration

proceedings all over again or be satisfied with the rejection

of their claim despite the fact that the Arbitral Tribunal has

upon due appreciation of evidence and in accordance with

law has granted relief to them. It will not only be

appropriate but even permissible to read the proviso to add

to the discretion and power of the court vested in it by the

Legislature by using the expression "may".

140.The Full Bench while taking the above view, duly took into

account the judgement of the Supreme Court in McDermott

International Inc. (supra) as well as the provisions of the Old Act and

observed as under :-

“35. The Supreme Court was primarily stating the

principles which have been kept in mind by the courts

while interfering with the award of the Arbitral Tribunal

that it was to outline the supervisory role of the courts

within the ambit and scope of section 34. It is true that the

court like a court of appeal cannot correct the errors of

arbitrator. It can set aside the award wholly or partially in

its discretion depending on the facts of a given case and can

even invoke its power under section 34(4). It is not

expected of a party to make a separate application under

section 34(4) as the provisions open with the language "on

receipt of application under sub-section (1), the court

may.........." which obviously means that application would

be one for setting aside the arbitral award to be made under

section 34(1)on the grounds of reasons stated in section

34(2) and has to be filed within the period of limitation as

stated as reply under section 34(3). The court may if it

deems appropriate can pass orders as required under section

34(4). In other words, the provisions of section 34(4) have

Arbitration Appeal No.219 of 2022

92.

to be read with section 34(1) and 34(2) to enlarge the

jurisdiction of the court in order to do justice between the

parties and to ensure that the proceedings before the

Arbitral Tribunal or before the award are not prolonged for

unnecessarily. In our humble view, the Division Bench

appears to have placed entire reliance on para 52 by reading

the same out of the context and findings which have been

recorded by the Supreme Court in subsequent paragraphs. It

is also true that there are no pari materia provisions like

sections 15 and 16of the Act of 1940 in the 1996 Act but

still the provisions of section 34 read together, sufficiently

indicate vesting of vast powers in the court to set aside an

award and even to adjourn a matter and such acts and deeds

by the Arbitral Tribunal at the instance of the party which

would help in removing the grounds of attack for setting

aside the arbitral award. We see no reason as to why these

powers vested in the court should be construed so strictly

which it would practically frustrate the very object of the

Act. Thus, in our view, the principle of law stated by the

Division Bench is not in line with the legislative intent

which seeks to achieve the object of the Act and also not in

line with accepted norms of interpretation of statute.”

141. The Full Bench also considered the issue from the aspect of

hardship and inconvenience to the parties and observed thus :-

37. The interpretation put forward by the respondents is

bound to cause greater hardship, inconvenience and even

injustice to some extent to the parties. The process of

arbitration even under 1996 Act encumbersome process

which concludes after considerable lapse of time. To

compel the parties, particularly a party who had succeeded

to undergo the arbitral process all over again does not

appear to be in conformity with the scheme of the Act. The

provisions of section 34 are quite pari materia to the

provisions of Article 34 of the Model Law except that the

proviso and explanation have been added to section 34(2)

(iv). The attempt under the Model Law and the Indian Law

appears to circumscribe the jurisdiction of the court to set

aside an award. There is nothing in the provisions of the Act

and for that matter absolutely nothing in the Model Law

which can debar the court from applying the principle of

Arbitration Appeal No.219 of 2022

93.

severability provided it is otherwise called for in the facts

and circumstances of the case and in accordance with law.

The courts will not get into the merits of the dispute. Thus,

the interpretation which should be accepted by the court

should be the one which will tilt in favour of the Model

Laws, scheme of the Act and the objects sought to be

achieved by the Act of 1996.

142. The Full Bench concluded as follows :-

1. The judicial discretion vested in the court in terms of

the provisions of section 34 of the Arbitration and

Conciliation Act, 1996 takes within its ambit power to set

aside an award partly or wholly depending on the facts and

circumstances of the given case. In our view, the provisions

of section 34 read as a whole and in particular section 34(2)

do not admit of interpretation which will divest the court of

competent jurisdiction to apply the principle of severability

to the award of the Arbitral Tribunal, legality of which is

questioned before the court.

The Legislature has vested wide discretion in the court to

set aside an award wholly or partly, of course, within the

strict limitations stated in the said provisions. The scheme

of the Act, the language of the provisions and the legislative

intent does not support the view that judicial discretion of

the court is intended to be whittled down by these

provisions.

143.In J.G. Engineers Pvt. Ltd. Vs. Union of India and another

32

the Supreme Court applied the doctrine of severability and upheld some

of the claims which were separate and distinct and did not suffer from

any infirmity while setting aside the remaining part of the award. The

relevant part is quoted below :-

It is now well- settled that if an award deals with and

decides several claims separately and distinctly, even if the

court finds that the award in regard to some items is bad,

32 (2011) 5 SCC 758,

Arbitration Appeal No.219 of 2022

94.

the court will segregate the award on items which did not

suffer from any infirmity and uphold the award to that

extent. As the awards on items 2, 4, 6, 7, 8 and 9 were

upheld by the civil court and as the High Court in appeal

did not find any infirmity in regard to the award on those

claims, the judgment of the High Court setting aside the

award in regard to claims 2,4,6,7,8 and 9 of the appellant,

cannot be sustained. The judgment to that extent is liable to

be set aside and the award has to be upheld in regard to

claims 2, 4, 6, 7, 8 and 9.

144.The Bombay High Court in National Highways Authority of

India Vs. The Additional Commissioner, Nagpur and others

33

,

reiterated that the doctrine of severability can be applied to an award

while dealing with the objections under Section 34 of the Act. Reliance

has also been placed on the judgement of the Supreme Court in J.G.

Engineers Pvt. Ltd. (supra). The relevant observation is as follows :-

(22) Thus, it becomes clear that in a given case, the Court,

while exercising power under Section 34 of the Act of

1996, can set aside an Award partly, depending upon the

facts and circumstances of the case. In this context,

reference can also be made to the judgment of the Supreme

Court in the case of J.G. Engineers Pvt. Ltd. Vs. Union of

India and another (2011) 5 SCC 758. (23) In the said case

also, the doctrine of severability was invoked and it was

held that when the Award deals with several claims that can

be said to be separate and distinct, the Court can segregate

the Award on items that do not suffer from any infirmity

and uphold the Award to that extent. Thus, it becomes clear

that the contention raised on behalf of the appellants in the

present case, that the PDJ ought to have set aside the

arbitral Award in its entirety, is not justified.

145.Once again in John Peter Fernandes Vs. Saraswati

33 2022(5) AIR Bom R 562

Arbitration Appeal No.219 of 2022

95.

Ramchandra Ghanate and others

34

the Bombay High Court relying

on Full Bench judgement in R.S. Jiwani (M/s) Mumbai (supra)

applied the principle of severability to an arbitral award in segregating

bad part from good part. It has been held as follows :-

16. Thus, the rival contentions need to be decided on the

touchstone of jurisdiction clarified as above. It is also

relevant to refer to the Full Bench judgement of this Court

in the case of R. S. Jiwani Vs. Ircon International Limited

(supra), for the reason that the respondents have specifically

invoked the position of law clarified therein, to claim that

the impugned award can be partly set aside, restricted to the

second direction issued to the respondents for refunding

specific amount with interest. It is submitted that the first

finding or direction in the impugned award rejecting the

prayer for specific performance made by Mr. Fernandes

deserves to be confirmed and sustained. The Full Bench of

this Court in the case of R. S. Jiwani Vs. Ircon International

Limited (supra) took into consideration judgement of the

Supreme Court in the case of McDermott International Inc.

Vs. Burn Standard Company Limited and others, (2006) 11

SCC 181, wherein it was laid down that a court under

Section 34 of the said Act can only quash an award, leaving

the parties free to begin arbitration again, if they so desire.

But the Full Bench of this Court in the said Judgement

found that the principle of severability could certainly apply

to arbitral awards, so long as the objectionable part could be

segregated. This Court is convinced that the respondents are

justified in invoking the said principle and contending that

if their contentions are accepted, the impugned award could

be partially set aside. This would not amount to

modification or correction of errors of the learned arbitrator.

In this backdrop, the arbitral award needs to be examined in

the light of the contentions raised on behalf of the rival

parties.

146.We have thus, no hesitation in holding that scheme of the Act

does not put any limitation on power of the court to apply the doctrine

34 2023 SCC OnLine Bom 676

Arbitration Appeal No.219 of 2022

96.

of severability to an arbitral award while considering the objections

under Section 34 of the Act. It is well within the power of court to

segregate, severe and set aside part of the award and uphold the

remaining part. The only restriction is (i) that while exercising the

power, the court cannot proceed to modify the findings returned on any

of the issues decided by the arbitral tribunal and (ii) the remaining part

is capable of surviving on its own.

147. Coming to the facts of the instant case, we find that Claim No. 2

of Rs.35.92 crores towards liquidated damages under Clause No. 13(ii)

(b) of GCC which has been held to be unsustainable, is separate and

distinct from the remaining claims found to be valid and lawful. The

claims found to be valid are capable of surviving on their own strength,

without in any manner getting affected by severance of Claim No.2

towards liquidated damages. Therefore, applying the doctrine of

severability, the award in respect of liquidated damages (Claim No. 2)

alone is set aside. Resultantly, the award of pendenti lite and future

interest in respect of Claim No. 2 would also stand set aside, leaving

the remaining award intact.

148.As a result, the appeal stands allowed in part.

149.No order as to costs.

Order Date :- 22.09.2023

SL/Jaideep/skv

(Vikram D. Chauhan, J.) (Manoj Kumar Gupta, J.)

Reference cases

Description

Legal Notes

Add a Note....