As per case facts, the plaintiff filed a civil suit for recovery and injunction, arguing that the defendants improperly forfeited security deposits without proving actual damages for alleged breaches in ...
2026:HHC:38123
IN THE HIGH COURT OF HIMACHAL PRADESH, SHIMLA
RSA No. 167 of 2008
Reserved on: 27.8.2026
Date of Decision: 09.9.2026
H.P. General Industries Corporation Ltd. & anr. ...Appellants
Versus
M/s Batra Traders ...Respondent
Coram
Hon’ble Mr Justice Rakesh Kainthla, Judge.
Whether approved for reporting?
1
Yes.
For the Appellants :M/s B.B. Vaid and Hemant Vaid,
Advocates.
For the Respondent :Mr Arhant Mahajan, Advocate,
vice Mr Rahul Mahajan,
Advocate.
Rakesh Kainthla, Judge
The present appeal is directed against the judgment
and decree dated 03.01.2008, passed by the learned District
Judge, Shimla (learned Appellate Court), vide which the
judgment and decree dated 28.09.2005, passed by the learned
Civil Judge (Senior Division), Shimla (learned Trial Court), were
set aside. (The parties shall hereinafter be referred to in the same
1
Whether reporters of Local Papers may be allowed to see the judgment? Yes.
2
2026:HHC:38123
manner as they were arrayed before the learned Trial Court for
convenience).
2. Briefly stated, the facts giving rise to the present
appeal are that the plaintiff filed a civil suit for recovery of
₹2,15,600/- along with interest @ 18% per annum, and for a
permanent prohibitory injunction restraining the defendants
from forfeiting the property and appropriating the security. It
was asserted that the plaintiff is a proprietorship concern
dealing with the supply of empty bottles, gunny bags,
corrugated boxes, and all kinds of scraps. The defendants placed
an order with the plaintiff on 09.07.1991 for supply of 25,00,000
bottles of 750 ml each, 2,00,000 bottles of 375 ml each, and
2,00,000 bottles of 180 ml each. The defendants started
purchasing empty bottles from the open market. The plaintiff
objected to it, and the dispute was resolved on 31.01.1992. The
defendants extended the time for supply of the order and placed
an additional order for supply of 6,00,000 bottles of 750 ml each
at the rate of ₹25.90 per dozen.
3. The defendants floated another tender for supply of
empty liquor bottles for the year 1992. The plaintiff’s bid was
3
2026:HHC:38123
accepted, and the plaintiff was ordered to supply the empty
bottles at the rate of ₹28.25 per dozen. The plaintiff applied for
the refund of the security for the previous year’s order. The
defendants raised an additional demand instead of refunding
the security. The plaintiff sent a reply to the demand. The
defendants decreased the order by 20% for the year 1992–1993.
The plaintiff complied with the order but also served a notice
upon the defendants. There was no dispute regarding the refund
of the security for the year 1991–1992. However, the defendants
did not refund the security of ₹60,000/- and ₹5,000/-.
4. The defendants again floated a tender in the year
1993, and the plaintiff’s was accepted. Security of ₹60,000/-
and ₹15,000/- was deposited. The plaintiff supplied the bottles.
The defendants purchased the bottles from the open market. A
dispute arose between the parties, which was resolved with the
intervention of the Chief Secretary to the Government of
Himachal Pradesh. The plaintiff completed the supply, but the
defendants failed to refund the security.
5. A fresh tender was floated for the year 1994–1995,
and security was deposited. The dispute is pending before the
4
2026:HHC:38123
Arbitrator. The plaintiff requested the defendants for the refund
of the security, but the defendants failed to refund it. The
defendants served a legal notice upon the plaintiff on 03.07.1997
threatening to forfeit the security in case of non-supply of the
bottles. The defendants are not entitled to retain the security;
hence, the suit was filed seeking the reliefs mentioned above.
6. The suit was opposed by filing a written statement
taking preliminary objections regarding lack of cause of action
and maintainability, the plaintiff being estopped by his act and
conduct and acquiescence to file the suit, the suit having not
been properly instituted by a competent person, the suit being
barred by limitation, the suit not being properly valued for the
purpose of court fees and jurisdiction, and the suit being bad for
misjoinder of causes of action. The contents of the plaint were
admitted to the extent that the defendants had invited tenders
for supply of empty bottles and the plaintiff’s bid was accepted.
It was asserted that the plaintiff failed to supply the bottles as
per the demand, and letters were sent to the plaintiff from time
to time. An audit objection was raised regarding the new order at
a higher rate when the old rate was prevailing. The plaintiff
repeated the violation of the terms and conditions of the tender.
5
2026:HHC:38123
The defendants suffered a loss of ₹5,70,356/-; they forfeited the
security of ₹1,70,000/-. and asked the plaintiff to deposit the
remaining amount of ₹3,05,356/-. The suit was filed without
any basis; hence, it was prayed that the suit be dismissed.
7. A replication denying the contents of the written
statement and affirming those of the plaint was filed.
8. The learned Trial Court framed the following issues
on 20.05.1999:
(i)Whether the plaintiff has performed and complied
with the terms and requirements of the contract
regarding supply of bottles which was executed
between him and defendants for the year 1991, 1992
and 1993 and is therefore entitled to refund the
security amount as alleged? OPP.
(ii)Whether the order of forfeiture of security amount
is justified and defendants are entitled to some
more amount besides the security amount on
account of alleged non-performance/breach of the
terms and conditions of the contract? OPD.
(iii)Whether the suit is barred by time? OPD.
(iv)Whether the plaintiff is estopped to sue by his acts,
deeds and conduct? OPD.
(v)Whether the suit has not been properly instituted?
OPD.
(vi)Whether the plaintiff has no enforceable cause of
action? OPD.
(vii)Whether the plaint is not properly verified, if so, its
effect? OPD.
6
2026:HHC:38123
(viii)Whether the suit is bad for mis-joinder of cause of
action? OPD.
(ix)Whether the suit has not been properly valued for
the purpose of court fee and jurisdiction? OPD.
(x)Relief.
9. The parties were called upon to produce the evidence.
The plaintiff examined B.C. Bhardwaj (PW-1), Gopal Kishan
(PW-2), Anant Ram (PW-3) and Ram Avtar (PW-4). The
defendants examined Shri B.C. Gupta (DW-1).
10. The learned Trial Court held that the plea taken by
the defendants that the plaintiff had failed to supply the bottles
as per the demand was probable. The defendants issued repeated
letters and telegrams to the plaintiff pointing out the shortfall.
The plaintiff failed to adhere to the schedule of supply. The
security amount was liable to be forfeited for breach of terms
and conditions as per Clause 9 of the agreement. The plaintiff
had completed the supply in the year 1993, and the suit was to be
filed within three years. However, it was filed after the lapse of
about five years and was barred by limitation. Hence, the learned
Trial Court answered Issue Nos. 3, 4, 6, and 7 in the affirmative,
Issue No. 2 partly in the affirmative, the rest of the issues in the
negative, and dismissed the suit.
7
2026:HHC:38123
11. Being aggrieved by the judgment and decree passed
by the learned Trial Court, the plaintiff filed an appeal, which
was decided by the learned District Judge, Shimla (learned
Appellate Court). The learned Appellate Court concurred with
the findings recorded by the learned Trial Court that the
agreement between the parties contained a penalty clause;
however, the defendants were not justified in forfeiting the
penalty without showing the extent of damages suffered by
them. The defendants claimed that there was a short supply, but
had not proved the damages suffered by them. The statement
made by Shri B.C. Gupta (DW-1) that the defendants could not
fulfill the obligation to the Excise Department was not
corroborated by any material on record. Hence, the learned First
Appellate Court allowed the appeal, set aside the judgment and
decree passed by the learned Trial Court, and decreed the suit.
12. Being aggrieved by the judgment and decree passed
by the learned First Appellate Court, the defendants have filed
the present appeal, which was admitted on the following
substantial questions of law:
(i)Whether the learned First Appellate Court was
justified in applying the provisions of Section 74 of
8
2026:HHC:38123
the Indian Contract Act when there was a breach of
the terms of the supply order, which itself rendered
the forfeiture of the security amount, moreover,
when there is no such plea of the plaintiff and still
the First Appellate Court can invoke the said
provisions?
(ii)Whether there is misreading, misappropriation and
non-application of mind to the pleadings as well as
oral and documentary evidence?
(iii)Whether the suit of the plaintiff was within
limitation and the First Appellate Court was
justified in not giving any findings on limitation?
13. I have heard M/s B.B. Vaid and Mr Hemant Vaid,
learned counsel for the appellants/defendants, and Mr Arhant
Mahajan, learned vice counsel representing the
respondent/plaintiff.
14. Mr B.B. Vaid, learned counsel for the
appellants/defendants, submitted that the learned Trial Court
had specifically held the suit to be barred by limitation.
However, the learned Appellate Court failed to record any
finding regarding the plea of limitation, and this issue was
simply ignored. It was an admitted case of the plaintiff that the
contract was fulfilled in the year 1993; therefore, the cause of
action for filing the suit arose in the year 1993. The suit was to be
filed within three years from the accrual of the cause of action,
and the suit was hopelessly barred by limitation. Therefore, he
9
2026:HHC:38123
prayed that the present appeal be allowed, the judgment and
decree passed by the learned Appellate Court be set aside, and
the judgment and decree passed by the learned Trial Court be
restored.
15. Mr Arhant Mahajan, learned vice counsel
representing the respondent/plaintiff, submitted that time is
not the essence of the contract. The notice of forfeiture was
received on 03.07.1997, and the cause of action accrued on that
day. The suit was filed on 18.04.1998, within the period of three
years from the date of the accrual of the cause of action; hence,
the same was within limitation. The learned Appellate Court had
rightly held that the penalty clause is not sufficient to forfeit the
security, and the defendants were required to prove the actual
damage sustained by them. Since the defendants have not
proved the damages sustained by them, the learned Appellate
Court had rightly decreed the suit. There is no infirmity in the
judgment and decree passed by the learned Appellate Court;
hence, he prayed that the present appeal be dismissed. He relied
upon the following judgments in support of his submission:-
(i)Gomathinayagam Pillai vs. Palaniswami Nadar 1967
SC 868;
10
2026:HHC:38123
(ii)Maula Bux v. Union of India (AIR 1970 SC 1955)
(iii)Union of India v. Rampur Distillery and Chemical Co.
Ltd.
16. I have given considerable thought to the submissions
made at the bar and have gone through the record carefully.
Substantial Question of Law No.3:
17. The plaintiff asserted in Para 4 of the plaint that
there was no dispute between the parties, but the security for the
year 1991–1992 of ₹60,000/- and ₹5,000/- for the bottles of 180
ml. was not refunded. He stated in Para 5 of the plaint that the
supply was completed for the year 1993, but the security of
₹60,000/- and ₹15,000/- was not refunded without any
justifiable reason.
18. Shri Ram Avtar Batra (PW-4) stated that he had
deposited money by way of security twice: the amount of one
security was ₹65,000/-, and the amount of the other security
was ₹75,000/-. He made the supplies to the defendants as per
their demand, but the defendants failed to refund the security
despite his performance of the agreement by him. He stated in
his cross-examination that he had stopped making supplies to
the defendants during the year 1991–1992 because the
11
2026:HHC:38123
defendants had started making purchases from other sources.
He admitted that he had received telegraphic reminders from
the defendants for supply of bottles, and volunteered to state
that the defendants had not accepted the supply.
19. Therefore, as per the admitted version of the
plaintiff, the plaintiff had completed the supply, but the
defendants had failed to return the security deposited by him.
20. It was laid down by the High Court of Bombay in
Shankar Moreshwar Kulkarni Chinchwadkar v. State of
Maharashtra, 1968 SCC OnLine Bom 52: AIR 1970 Bom 8: 1969 Mah
LJ 677 that the suit for the recovery of security has to be filed
within three years from the completion of the contract. It was
observed at page 9:
“9. Where money is deposited by way of security for the
due performance of a contract or otherwise under the
terms of a contract and is refundable after the completion
of the contract, in our opinion, Article 62 is not applicable
to the suit for refund as the money was not received by
the defendant for the plaintiff's use. Such suit would be
governed by the residuary Article 120 of the Indian
Limitation Act, 1908.
11. Our attention was invited to the judgment of a Division
Bench of this Court in the case of Dhanraj Mills Ltd. v.
Laxmi Cotton Traders, Bombay, 60 Bom LR 1295 : (AIR 1960
Bom 404). In that case it was merely held that Article 145
12
2026:HHC:38123
was not applicable to the facts which were similar to the
facts of this case, but it was not decided as to which of the
articles in the first schedule of the Indian Limitation Act
was applicable. In an earlier Bombay case, namely,
Lingangouda v. Lingangouda, ILR (1953) Bom 214 : (AIR
1953 Bom 79) —Chagla C.J. had taken the view that Article
120 was applicable in a similar matter. The reason given
in the judgment was that Article 62 should not apply to a
case where the terms of the article were not literally
complied with. It was observed that such a construction
would result in plaintiffs losing a large number of cases
on the ground of limitation, whereas if Article 120 was
held to be applicable, the plaintiffs would be safe. The
reasoning of this decision was not approved of by the
Supreme Court in (1965) 2 SCR 577 (AIR 1965 SC 1773),
referred to hereinabove. We are, however, bound by the
judgment of the Supreme Court on the point that Article
62 was not applicable. The only article with which we are
left is Article 120. In our opinion, Article 120 is applicable,
being the residuary article.
21. Similarly, the Rajasthan High Court also held in State
of Rajasthan v. Anand Construction Co., 1971 SCC OnLine Raj 7: AIR
1972 Raj 101 that in case of refund of the security deposit, the
obligation to refund the security arises on the completion of the
contract, and a period of three years would apply. It was
observed at page 102: -
10. In Nasiruddin v. Abdullah Mian, 1959 Raj LW 317 where
a tenant had deposited money with the landlord as a
security for the due fulfilment of the stipulation to do all
repairs which may be necessary at the termination of the
lease, and that if the tenant did not do so, the landlord
would be entitled to do it and deduct the cost out of the
13
2026:HHC:38123
said deposit, the suit was filed for the refund of the
deposit and it was held that as there was no specific
article applicable to the case of this nature, Article 120 of
the Limitation Act of 1908 would apply. Reliance was
placed on Upendra Lal Mukhopadhya v. The Collector of
Rajshaye, (1886) ILR 12 Cal 113.
11. In Harij Gram Panchayat v. Thakkar Lakhiram Ramji,
AIR 1962 Guj 14, it was held that in a suit brought for the
refund of deposit by way of security for the due
performance of the contract, neither Art. 62 nor Art. 60
nor Article 97 of the Act of 1908 applies, and in the
absence of any specific Article application to the suit,
Article 120 applies.
12. The same view was taken by the Bombay High Court in
Shankar v. State, AIR 1970 Bom 8. It was held there that:
“Where money is deposited by way of security for
the due performance of a contract or otherwise
under the terms of a contract and is refundable
after the completion of the contract, Article 62 is
not applicable to the suit for refund as the money
was not received by the defendant for the plaintiff's
use. The right to refund did not arise immediately
on receipt by the defendant. The suit not being a
suit against a depository or pawnee to recover
movable property deposited or pawned, Article 145
also would not be applicable. Such suit would be
governed by the residuary Article 120.”
13. The Calcutta High Court in G.D. and Co. v. W.I. Theatres,
(1961) 65 Cal WN 504 came to the decision that to such
suits Article 146 of the Indian Limitation Act of 1908
would be applicable and if for any reason, this article is
not applicable, there is no doubt that Article 120 is
applicable. This was also a case for the refund of the
deposit made by the contractor. Bose J. in that case
observed that:
14
2026:HHC:38123
“A deposit made as security for due performance of
a contract is refundable whether it is coupled with a
promise or agreement to repay it or not. Even if
nothing is agreed as to its repayment at the time
the deposit is made, the obligation to repay arises
upon the proper performance of the engagement by
reason of the very nature of the transaction of
deposit. If an express agreement is entered into for
repayment of the deposit, the transaction remains a
deposit, and its nature is not thereby altered. The
essence of the causes of action for a suit for refund
of a deposit is not the breach of the contract to
repay it, but the fact that the transaction is a
deposit which by its very nature is refundable.
14. The person who holds the deposit and the person on
whose behalf or for whose benefit the deposit is held as
security are liable to refund it because it is a deposit. They
are both in the position of depositories. Accordingly, the
article applicable is Article 145 of the Indian Limitation
Act, and if for any reason this article is not applicable,
there is no doubt that Article 120 is applicable to the
present case.”
15. Thus there is sufficient authority for the view I have
taken in the matter. The contracts in this case were
completed on 27-1-1958, and the suit has been filed
within six years of that date. Although, on behalf of the
defendant, the Engineer-in-charge has deposed that the
amount of security deposit was refundable six months
after the completion of the contract, but no such period is
fixed in the agreement and in its absence the time will
begin to run from the date of the completion of the
contract. But in any case, the suit was instituted within
six years of the completion of the contract
15
2026:HHC:38123
22. A similar view was taken by the High Court of
Allahabad in State of U.P. v. Chandra Gupta & Co., 1976 SCC OnLine
All 159: 1976 All LJ 426 wherein it was observed at page 434
“22. Article 56, quoted above, will show that it prescribes
a period of three years for a suit for the price of work done
by the plaintiff for the defendant at his request, where no
time has been fixed for payment. In this eventuality, the
period of limitation starts running from the date when
the work is done. In the instant case, however, we find
that Clause 7 of the Conditions of Contract provides for
payment on intermediate certificate to be regarded as
advances. Under this limitation clause, a contractor is
entitled to receive a monthly payment proportionate to
the part thereof that is approved for such purpose by the
Engineer-in-Charge. Similarly, a provision for final
payment has also been made in Clause 6. Accordingly, as
the contract provides for the time when the payment is to
be made, Art. 56 of the old Limitation Act would not be
applicable to the claim for the extra work. The other
Articles which were relied upon by the plaintiff were Arts.
120 and 115 of the said Act. Art. 115 will apply to a claim of
compensation for breach of any contract, express or
implied. The period of limitation in such cases is three
years, and it commences to run when the contract is
broken. Although it was vehemently urged by Sri Radha
Krishna that the correct Article applicable to the claim for
the extra work was Art. 120, we find that even applying
Art. 115, the suit of the plaintiff is within time; we do not
think it necessary to examine the question as to whether
Art. 120 applies. The facts of the case, stated above, would
show that the claim of the plaintiff was rejected by the
State of U.P. on 15-3-1959, whereas the suit was filed by
the plaintiff on 16-5-1962. The plaintiff, having given
two months' notice to the State of U.P., was entitled to the
exclusion of this period of two months, and as 15th of
May, 1962, was a public holiday, the plaintiff could,
16
2026:HHC:38123
therefore, file the suit on 16-5-1962. Accordingly, the suit
filed by the plaintiff on the aforesaid date was within
time. This view of ours is supported by a decision of a
Division Bench of this Court in State of U.P. v. Suraj Prasad
Gupta [ F.A. No. 351 of 1968, decided on 3-2-1976]. In this
case also it was held that to a claim like the present, the
applicable provision is that provided by Art. 115 of the old
Limitation Act.
23. There remains to be considered the question as to
whether the claim made by the plaintiff for the refund of
the security deposit forfeited by the State was within
time. The real question in this case is about the character
of the deposit made by the plaintiff as a contractor. The
amount was deposited as security for the performance of
the contract. The question of limitation as to the refund of
the security amount came up for consideration before a
Division Bench of the Punjab and Haryana High Court in
(Zila Parishad, Ambala v. Banarsi Dass [A.I.R. 1973 Pun. and
Har. 276.] ). The Bench observed that a suit for return of
security deposit is not for compensation for the breach of
any contract; the deposit remains a deposit whether the
depositor has a right to deduct anything therefrom or not.
Thus, the suit would be governed either by Art. 145 or 120
of the Limitation Act. In Datt Singh v. Srihar Singh [1955
N.U.C. 3551], a learned Single Judge was also required to
consider a similar controversy. The commentator has
digested the observations made by the learned Judge in
the following terms:
“The claim for a return of the deposit money cannot by
any stretch of the language of Art. 115 be considered as
a suit for compensation for breach of any contract.
When an employee makes a deposit for due
performance of the duties, the deposit is in the nature
of a trust, and the proper Article in such a case is Art.
145, which provides for a greater period of limitation
than Art. 120. Even if Art. 145 is not applied, there is no
escape from the conclusion that the other Article
applicable to a case of this type is Art. 120.”
17
2026:HHC:38123
24. For the reasons given above, we find that a suit
relating to a deposit would fall under the residuary Art.
120 of the Act. The period provided under this Article is
six years. Applying this period, we find that the suit is
within time and, therefore, the claim of the plaintiff for
the refund of the security deposit cannot be defeated on
the ground of limitation.”
23. These judgments were followed by this Court in M/s
Kumar & Company v. State of H.P., Civil Suit No. 33 of 1990, decided
on 03.06.2000.
24. In the present case also, the agreement for the year
1991–1992 came to an end in the year 1992, and the agreement
for the year 1993 came to an end in the year 1993. This is also
evident from the fact that, as per the plaint, a fresh tender was
floated in the year 1994–1995 and there was a dispute regarding
the same, which is the subject matter of the arbitration. Hence,
the learned Trial Court had rightly held that the suit was to be
filed within three years, and the learned Appellate Court erred in
ignoring these findings.
25. Mr Arhant Mahajan, learned counsel for the plaintiff,
referred to the performance report (Ext. PB) and stated that
orders were being placed in the year 1994–1995, and the
contract had not come to an end. This submission cannot help
the plaintiff. It is undisputed that different tenders were floated
18
2026:HHC:38123
for different years, and merely because orders were placed in
different years cannot mean that those were referable to the
tenders for the years 1991–1992 and 1993–1994, for which the
security is being claimed. Therefore, not much advantage can be
derived from the performance report.
26. It was submitted that a notice (Ext. PA) was issued to
the plaintiff for forfeiting the security amount, which would
furnish a cause of action. This submission can also not help the
plaintiff, because the plaintiff has not challenged the order of
forfeiture but has claimed the refund of the security deposited
by him, and any order of forfeiture will not have the effect of
extending the period of limitation in the present case.
27. It was further submitted that time is not the essence
of the contract and the suit cannot be said to be barred by
limitation. This submission is only stated to be rejected. This
principle cannot apply to the refund of security, which becomes
due after the completion of the contract.
28. It is an admitted version that different tenders were
being floated for different years; therefore, the tender came to
an end once a new tender was floated, and the plaintiff cannot
19
2026:HHC:38123
claim that time was not the essence of the contract when the
period of limitation started running from the expiry of the
previous tender.
29. The judgment in Gomathinayagam Pillai (supra) and
Hind Construction (supra) related to the performance of the
contract and not the refund of the security, and will not help the
plaintiff.
30. A reference was made to the letter dated 01.06.1992
(Ext. P-9), vide which the plaintiff had demanded the refund of
the security. This letter will not help the plaintiff because it
would show that the demand for the refund was made on
01.06.1992, and a cause of action arose from that date. The
plaintiff was required to file the suit within three years, but
failed to do so.
31. Thus, the learned Trial Court had rightly held that
the suit was barred by limitation, and the learned First Appellate
Court erred in not recording any finding regarding this issue.
Hence, this substantial question of law is answered accordingly.
20
2026:HHC:38123
Substantial Question of Law No. 1:
32. The learned First Appellate Court had rightly held
that the security amount could not be forfeited simply because
of default, and Section 74 of the Indian Contract Act will apply to
the refund of the security deposit. It was laid down by the
Hon’ble Supreme Court in Maula Bux v. Union of India, (1969) 2
SCC 554: 1969 SCC OnLine SC 291 that the security could not be
forfeited simply because of breach of the contract unless the
damages are shown. It was observed at page 557:-
4. Under the terms of the agreements the amounts
deposited by the plaintiff as security for due performance
of the contracts were to stand forfeited in case the
plaintiff neglected to perform his part of the contract. The
High Court observed that the deposits so made may be
regarded as earnest money. But that view cannot be
accepted. According to Earl Jowitt in Dictionary of English
Law at p. 689: “Giving an earnest or earnest-money is a
mode of signifying assent to a contract of sale or the like,
by giving to the vendor a nominal sum (e.g. a shilling) as a
token that the parties are in earnest or have made up their
minds”. As observed by the Judicial Committee in
Chiranjit Singh v. Har Swarup: [1925 SCC OnLine PC 63: AIR
1926 PC 1]
“Earnest money is part of the purchase price when
the transaction goes forward; it is forfeited when
the transaction falls through, by reason of the fault
or failure of the vendee.”
In the present case, the deposit was made not as a sum of
money by the purchaser to be applied towards part
21
2026:HHC:38123
payment of the price when the contract was completed
and till then as evidencing an intention on the part of the
purchaser to buy property or goods. Here the plaintiff had
deposited the amounts claimed as security for
guaranteeing due performance of the contracts. Such
deposits cannot be regarded as earnest money.
Section 74 of the Contract Act provides;
“When a contract has been broken, if a sum is
named in the contract as the amount to be paid in
case of such breach, or if the contract contains any
other stipulation by way of penalty, the party
complaining of the breach is entitled, whether or
not actual damage or loss is proved to have been
caused thereby, to receive from the party who has
broken the contract reasonable compensation not
exceeding the amount so named or, as the case may
be, the penalty stipulated for.
1.***”
2.There is authority, no doubt coloured by the view which
was taken in English cases, that Section 74 of the Contract
Act has no application to cases of deposit for due
performance of a contract which is stipulated to be
forfeited for breach, Natesa Aiyar v. Appayu Padayachi
[1913 SCC OnLine Mad 208: ILR (1915) 38 Mad 178]; Singer
Manufacturing Company v. Raja Prosad [ ILR (1909) 36 Cal
960]; Manian Pattar v. Madras Railway Company. [1905 SCC
OnLine Mad 88: ILR (1906) 29 Mad 118] But this view is no
longer good law in view of the judgment of this Court in
Fateh Chand case (supra). This Court observed at p. 526:
“‘Section 74 of the Indian Contract Act deals with
the measure of damages in two classes of cases: (i)
where the contract names a sum to be paid in case
of breach, and (ii) where the contract contains any
other stipulation by way of penalty…,’ ‘The
measure of damages in the case of breach of a
stipulation by way of penalty is by Section 74,
22
2026:HHC:38123
reasonable compensation not exceeding the penalty
stipulated for.’”
The Court also observed:
“It was urged that the section deals in terms with
the right to receive from the party who has broken
the contract reasonable compensation and not the
right to forfeit what has already been received by
the party aggrieved. There is, however, no warrant
for the assumption made by some of the High
Courts in India that Section 74 applies only to cases
where the aggrieved party is seeking to receive
some amount on breach of contract and not to cases
whereupon breach of contract an amount received
under the contract is sought to be forfeited. In our
judgment, the expression “the contract contains
any other stipulation by way of penalty”
comprehensively applies to every covenant
involving a penalty whether it is for payment on
breach of contract of money or delivery of property
in future, or for forfeiture of right to money or
other property already delivered. Duty not to
enforce the penalty clause but only to award
reasonable compensation is statutorily imposed
upon courts by Section 74. In all cases, therefore,
where there is a stipulation in the nature of penalty
for forfeiture of an amount deposited pursuant to
the terms of contract which expressly provides for
forfeiture, the court has jurisdiction to award such
sum only as it considers reasonable, but not
exceeding the amount specified in the contract as
liable to forfeiture, and that,
“There is no ground for holding that the expression
‘contract contains any other stipulation by way of
penalty’ is limited to cases of stipulation in the nature of
an agreement to pay money or deliver property on breach
and does not comprehend covenants under which
23
2026:HHC:38123
amounts paid or property delivered under the contract,
which by the terms of the contract expressly or by clear
implication are liable to be forfeited.”
5. Forfeiture of earnest money under a contract for sale of
property — Movable or immovable — If the amount is
reasonable, does not fall within Section 74. That has been
decided in several cases: Chiranjit Singh v. Har Swarup;
Roshan Lal v. Delhi Cloth and General Mills Company Ltd.
Delhi [1910 SCC OnLine All 98: ILR (1911) 33 All 166]; Mohd
Habibullah v. Mohd Shafi [1919 SCC OnLine All 87: ILR 41 All
324]; Bishan Chand v. Radhakishan Das. [1897 SCC OnLine
All 52: ILR (1897) 19 All 490] These cases are easily
explained, for forfeiture of a reasonable amount paid as
earnest money does not amount to imposing a penalty.
But if forfeiture is of the nature of a penalty. Section 74
applies. Where under the terms of the contract the party
in breach has undertaken to pay a sum of money or to
forfeit a sum of money which he has already paid to the
party complaining of a breach of contract, the
undertaking is of the nature of a penalty.
33. The High Court of Allahabad followed this judgment
in Chandra Gupta & Company (supra) and observed:-
20. A similar question regarding the right of the Union of
India to forfeit the security came up for consideration
before the Supreme Court in Maula Bux v. Union of India
[(1969) 2 SCC 554: A.I.R. 1970, S.C. 1955]. In that case,
Maula Bux had entered into a contract with the
Government of India for the supply of certain goods and
had deposited a certain amount of security for the due
performance of the contract. It was stipulated in the
contract that the amount of security was to stand
forfeited in case the appellant neglected to perform his
part of the contract. On Maula Bux committing default in
the supply, the government did not only rescind the
contract but also forfeit the security deposit. Holding that
24
2026:HHC:38123
a case of forfeiture of earnest money was different from
forfeiture of security deposit for due performance of the
contract, the Supreme Court held that under Sec. 74, only
a reasonable amount can be forfeited if a contract is not
performed. But, where under the terms of the contract the
party in breach has undertaken to pay a sum of money or
to forfeit a sum of money which he has already paid to the
party complaining of a breach of contract, the
undertaking is of the nature of penalty. It further held
that the amount deposited by way of security for
guaranteeing the due performance of the contract could
not be regarded as earnest money. Applying the law to the
facts of the present case, we find that as the defendant,
admittedly, did not suffer any damage, it was not entitled
to forfeit the security deposit, in as much as forfeiture of
security would amount to imposition of penalty. This case
was followed by the Supreme Court in Union of India v.
Rampur Distillery and Chemicals Limited [(1973) 1 SCC 649:
A.I.R. 1973 S.C. 1098]. It was held in this case that the party
to a contract taking security deposit from the other party
to ensure due performance of the contract is not entitled
to forfeit the security deposit on the ground of default,
when no loss is caused to him in consequence of such
default. We, accordingly, find that the learned Civil Judge
was not right in holding that the forfeiture of security by
the defendant in the instant case was justified. We,
therefore, hold that the plaintiff is entitled to get a decree
for the sum of Rs. 6,650/- under this head.
34. The defendants claimed in the written statement that
they had suffered a loss of ₹5,70,356/-; however, there was no
evidence of this fact. Shri B.C. Gupta (DW-1) stated that the
bottles were not supplied despite repeated letters and telegrams,
and the defendants could not fulfil their obligation to the Excise
25
2026:HHC:38123
Department for supply of liquor bottles to various liquor
licenses. The learned First Appellate Court had rightly pointed
out that this statement does not give the details of the loss
suffered by the defendants. The cost of the liquor bottles
purchased from the market and the difference in price vis-à-vis
the tender were not outlined to calculate the loss suffered by the
defendants. Hence, his statement was not sufficient to infer that
the defendants had sustained the loss of ₹5,70,356/-.
35. It was submitted that no party had pleaded the
applicability of Section 74 of the Indian Contract Act, and the
learned First Appellate Court erred in invoking this provision.
This submission cannot be accepted. The Court is bound to apply
the law and cannot refuse to apply the law simply because no
person has brought the law to the attention of the Court in its
pleadings. Therefore, this substantial question of law is
answered accordingly.
Substantial Question of Law No. 2:
36. The learned First Appellate Court failed to appreciate
the plea regarding limitation and record any findings. However,
it had rightly held that the security amount could not be
26
2026:HHC:38123
forfeited simply because of default. Therefore, this substantial
question of law is answered partly in the affirmative.
Final Order:
37. In view of the above, the present appeal is allowed.
The judgment and decree passed by the learned First Appellate
Court are ordered to be set aside, while those passed by the
learned Trial Court are ordered to be restored.
38. Pending application(s), if any, also stand(s) disposed
of.
39. Records of the learned Courts below be sent down
forthwith.
(Rakesh Kainthla)
Judge
9
th
September, 2026
(Chander)
Legal Notes
Add a Note....