As per case facts, the Applicant, an 8th partner in a redevelopment project, faced significant challenges after investing in it, including the project's acquisition by a housing authority and the ...
Megha 34_arabpl_37441_2025_fc.odt
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION
ARBITRATION APPLICATION (L) NO.37441 OF 2025
WITH
INTERIM APPLICATION (L) NO.11418 OF 2026
IN
ARBITRATION APPLICATION (L) NO.37441 OF 2025
INFRA Poonam Developers LLP ...Applicant
V/s.
Jasbir Singh s/o. Ajit Singh and Ors. ...Respondents
________________
Mr. Aman Saraf with Ms. Sakshi Agarwal i/b. Mr. Bipin J. Joshi for the
Applicant.
Mr. Ziyad Madon with Mr. Chittesh Dalmia for Respondent No.6
________________
CORAM: SANDEEP V. MARNE, J.
Judgment reserved on: 30 MARCH 2026.
Judgment pronounced on: 07 APRIL 2026.
JUDGMENT:
1)This is an Application filed by the Applicant under Section 11 of
the Arbitration and Conciliation Act, 1996 (the Arbitration Act) for
appointment of an Arbitrator for adjudication of disputes between the
parties arising out of Deed of Alteration of Partnership dated 10 April
2013. Since there is delay of 258 days in filing the Application, the
Applicant has filed Interim Application (L) No.11418 of 2026 for
condonation thereof.
Page No. 1 of 21
7 April 2026 26:BHC-OS:2
Megha 34_arabpl_37441_2025_fc.odt
2)The Applicant is a registered Limited Liability Partnership Firm.
The subject matter of dispute between the parties is the property
known as -Panwala chawl Nos. 2 and 3 situated at City Survey No.1/112
of Parel Sewri Division, Building No.75-75A and 75-B, Dr. S.S. Rao Road,
Lalbaug, Mumbai (suit property). The property originally belonged to a
private trust, which are acquired by M/s. R.B. Builders and Developers
(the Firm) pursuant to order passed by this Court. At that time, there
were 7 partners namely Respondent Nos.1 to 7 in the Firm. The
acquisition was for the purpose of redevelopment of the suit property.
The Maharashtra Housing and Area Development Authority (MHADA)
issued NOC for redevelopment of the property in the year 2008, which
was modified in the year 2010. The Municipal Corporation granted
Intimation of Disapproval (IOD) dated 4 August 2010. A Memorandum
of Understanding came to be executed between the Respondents and
sister concern of the Applicant (Poonam Infra) for transfer of
development rights for consideration of Rs.20.70 crores. It is the case of
the Applicant that its nominee made a payment of Rs.4 crores to the
Firm. Deed of Admission of Partner dated 30 April 2011 was executed,
under which Applicant’s nominee -Poonam Infra, a partnership firm
was added as 8
th
partner in the Firm having 15% profit and loss sharing
ratio. Poonam Infra was to make contribution of its share for carrying
on construction and redevelopment of the project. The Firm obtained
commencement certificate dated 9 December 2011. Construction
commenced and was completed upto the plinth level. A stop work
notice was issued in the year 2012, which was revoked in the year 2013.
According to the Applicant, it later realised that its sister concern-
Page No. 2 of 21
7 April 2026
Megha 34_arabpl_37441_2025_fc.odt
Poonam Infra cannot be a partner of another Firm and accordingly,
Deed of Alteration of Partnership Firm dated 10 April 2013 was
executed, under which the Applicant was made 8
th
Partner in the Firm.
According to the Applicant, MHADA issued show cause notice to the
Firm for revocation of NOC. On 29 December 2016 MHADA directed the
Firm to effect redevelopment work and pay rent to the tenants, which
the Firm was unable to pay. Thereafter litigation took place between the
Society, Firm and MHADA relating to the redevelopment project.
3)In the light of above background, the Applicant decided to
withdraw itself from the project and sought refund of amount of
Rs.29,63,67,674.97. The notice issued by the Applicant was responded
by the Respondents denying the contents therein. The Applicant
apparently filed police complaints. By notice dated 20 June 2020, the
Applicant invoked arbitration clause. Since no response was received,
the Applicant filed Arbitration Petition No.241 of 2023 under Section 9
of the Arbitration Act seeking interim measures. On 20 July 2020, this
Court granted ad-interim measures retraining the Respondents from
creating third party rights or from putting up any construction or
altering the status of the property. Statement made on behalf of the
MHADA for not taking coercive steps was also recorded. According to
the Applicant, due to outbreak of Covid-19 Pandemic, it could not make
any fruitful movement in the matter. In 2023, the Applicant started
making efforts to protect its interests in the project. It made several
representations to various authorities. In the meantime, MHADA passed
order on 11 January 2024 for acquisition of the property by blacklisting
the Firm. The Applicant filed Writ Petition No.722 of 2024 before this
Page No. 3 of 21
7 April 2026
Megha 34_arabpl_37441_2025_fc.odt
Court challenging the order of acquisition. It also filed Interim
Application (L) No.4358 of 2024 in the pending Petition (Arbitration
Petition No.241 of 2023) filed under Section 9 of the Arbitration Act
seeking restraint order against MHADA. By order dated 27 February
2024 passed in Writ Petition No.722 of 2024, the Applicant was directed
to deposit an amount of Rs.2 crores as a pre-condition for hearing of
the Petition, which amount was deposited by the Applicant. The
Petition was finally disposed of on 21 March 2024 granting liberty to the
Applicant to make representations to the State Government and
MHADA. The Applicant accordingly made representation showing
readiness and willingness to complete the project. However, the
representation was rejected by order dated 14 August 2024. The
Applicant accordingly filed Writ Petition (L)No.32243 of 2024 in this
Court, which is pending. In the meantime, by order dated 20 March
2025 the property stood acquired by MHADA.
4)In the above background, the Applicant has filed the present
Application for appointment of an Arbitrator on 15 November 2025.
After filing of the present Application, this Court disposed of Section 9
Petition (Arbitration Petition No.241 of 2023) by order dated 4 February
2026, which was withdrawn in the light of filing of Section 11
Application.
5)Since notice under Section 21 of the Arbitration Act was issued on
20 June 2020 there is delay in filing the present Application. The
Applicant however contends that the period from 15 March 2020 to 28
February 2022 is required to be excluded on account of Covid-19
pandemic. This is how the Applicant submits that delay in filing the
Page No. 4 of 21
7 April 2026
Megha 34_arabpl_37441_2025_fc.odt
Application is only of 258 days. It has accordingly filed Interim
Application for condonation of delay.
6)Mr. Aman Saraf, the learned counsel appearing for the Applicant
would contend that the delay caused in filing the Application deserves
to be condoned considering the facts and circumstances of the present
case. He submits that the Applicant was required to initiate several
litigations and correspondence with the authorities for the purpose of
preserving the subject matter of arbitration. That decision to file
Application under Section 11 of the Arbitration Act was taken only after
acquisition of the property by MHADA. Since subject matter of
arbitration was itself under cloud, the Applicant was first required to
resolve the issues relating to project and could not rush before this
Court for seeking appointment of the Arbitrator. He submits that merits
of the claim of the Applicant are also required to be borne in mind
while deciding the issue of condonation of delay. That the Applicant has
invested amount of Rs.30 crores in the project and if reference to
arbitration is not made, the Applicant would lose right to have the
disputes with the Respondents adjudicated on merits. That condoning
the delay would only result in adjudication of claims of parties against
each other on merits. On the other hand, refusal to condone the delay
would result in drastic consequences. That the Applicant would lose
investment of over Rs.30 crores in the project.
7)In support of his contention that the referral court exercising
jurisdiction under Section 11 of the Arbitration Act can condone delay
in filing of application, Mr. Saraf relies on judgment of the Hon’ble
Page No. 5 of 21
7 April 2026
Megha 34_arabpl_37441_2025_fc.odt
Supreme Court in HPCL Bio-Fuels Ltd. V/s. Shahaji Bhanudas Bhad
1
and of this Court in Tata Motors Passenger Vehicles Ltd and Another
V/s. Ghosh Brothers Automobiles and Others
2
. Mr. Saraf submits that
the Applicant has made out sufficient cause for condonation of delay in
filing the Application. In support, he relies on judgments of the Hon’ble
Supreme Court in N. Balakrishnan V/s. M. Krishnamurthy
3
and Sheo
Raj Singh (deceased) through Legal Representatives and Others V/s.
Union of India and Another
4
. He would accordingly pray for condoning
the delay in filing the Application.
8) So far as merits of the Arbitration Application is concerned, Mr.
Saraf submits that existence of arbitration is not in dispute. He invites
attention of the Court to the arbitration agreement contained in clause
16 of the Deed of Alteration of Partnership Dated 10 April 2013. He
would accordingly pray for appointment of a sole Arbitrator.
9)Mr. Ziyad Madon, the learned counsel appearing for Respondent
No.6 opposes the Application submitting that the same is grossly
barred by limitation. That the cause of action for filing the Application
arose on 20 June 2020, but the Application is filed more than 5 years
later on 15 November 2025. He submits that the period of Covid-19
Pandemic cannot be excluded while computing period of limitation in
the facts of the present case as the Applicant undertook various other
litigations during pandemic period. That it secured interim measures
under Section 9 of the Arbitration Act by filing Petition right in the
middle of pandemic restrictions on 20 July 2020. That the Applicant sat
12024 SCC OnLine SC 3190
22026 SCC OnLine Bom 1100
3(1998) 7 SCC 123
4(2023) 10 SCC 531
Page No. 6 of 21
7 April 2026
Megha 34_arabpl_37441_2025_fc.odt
on relief secured under Section 9 of the Arbitration Act over 5 years and
has filed the present Application after considerable delay. That
therefore nothing prevented the Applicant from filing Application
under Section 11 of the Arbitration Act. That the Applicant has failed to
make out sufficient cause for condonation of delay. He submits that
mere length of delay is not material and cause for delay is the relevant
factor for deciding application for condonation of delay. In support, he
relies on judgment of the Supreme Court Court in Mool Chandra V/s.
Union of India and Another
5
. Mr. Madon submits that the Applicant is
seeking to infuse life into a dead claim. That qua Respondents, the
Applicant has absolutely no claims, which are capable of being
arbitrated. Not only the claims are time barred, the Application filed for
appointment of Arbitrator is also grossly barred by limitation. Mr.
Madon accordingly prays for dismissal of the Applications.
10)I have considered the submissions canvassed by the learned
counsel appearing for the rival parties.
11)The present Arbitration Application is filed by the Applicant for
appointment of Arbitrator under Section 11 (6) of the Arbitration Act.
By now, it is well settled position that the limitation period prescribed
in Article 137 of the Limitation Act, 1963 (the Limitation Act) applies to
filing of Application under Section 11(6) of the Arbitration Act. The
period of limitation prescribed under Article 137 of the Limitation Act is
three years, to be computed from the date when right to sue accrues. In
Arif Azim Co. Ltd. Vs. Aptech Ltd.
6
the Apex Court has held that the
5(2025) 1 SCC 625
6(2024) 5 SCC 313
Page No. 7 of 21
7 April 2026
Megha 34_arabpl_37441_2025_fc.odt
right to apply for appointment of an arbitrator under Section 11 of the
Arbitration Act accrues when a notice under Section 21 of the Act is
served and there is failure on the part of the opposite side in complying
with the requirements mentioned in the notice. It is held in paragraphs
56 and 62 of the judgment as under:
56. The other way of ascertaining the relevant point in time when
the limitation period for making a Section 11(6) application would
begin is by making use of the Hohfeld’s analysis of jural relations. It
is a settled position of law that the limitation period under Article
137 of the Limitation Act, 1963 will commence only after the right
to apply has accrued in favour of the applicant. As Page 31 of 58 per
Hohfeld’s scheme of jural relations, conferring of a right on one
entity must entail the vesting of a corresponding duty in another.
When an application under Section 11(6) of the Act, 1996 is made
before this Court without exhausting the mechanism prescribed
under the said sub-section, including that of invoking arbitration by
issuance of a formal notice to the other party, this Court is not duty
bound to appoint an arbitrator and can reject the application for
being premature and non-compliant with the statutory mandate.
However, once the procedure laid down under Section 11(6) of the
Act, 1996 is exhausted by the applicant and the application passes
all other tests of limited judicial scrutiny as have been evolved by
this Court over the years, this Court becomes duty-bound to appoint
an arbitrator and refer the matter to an arbitral tribunal. Thus, the
“right to apply” of the Applicant can be said to have as its jural
corelative the “duty to appoint” of this Court only after all the steps
required to be completed before instituting a Section 11(6)
application have been duly completed. Thus, the limitation period
for filing a petition under Section 11(6) of the Act, 1996 can only
commence once a valid notice invoking arbitration has been sent by
the applicant to the other party, and there has been a failure or
refusal on part of that other party in complying with the
requirements mentioned in such notice.
xxx
62. A perusal of the above shows that the request for appointment
of an arbitrator was first made by the petitioner vide notice dated
24.11.2022 and a time of one month from the date of receipt of
notice was given to the respondent to comply with the said notice.
The notice was delivered to the respondent on 29.11.2022. Hence,
the said period of one month from the date of receipt came to an
Page No. 8 of 21
7 April 2026
Megha 34_arabpl_37441_2025_fc.odt
end on 28.12.2022. Thus, it is only from this day that the clock of
limitation for filing the present petition would start to tick. The
present petition was filed by the petitioner on 19.04.2023, which is
well within the time period of 3 years provided by Article 137 of the
Limitation Act, 1963. Thus, the present petition under Section 11(6)
of the Act, 1996 cannot be said to be barred by limitation.
(emphasis added)
Thus, Application under Section 11(6) of the Arbitration Act needs to be
filed within a period of three years from the date of failure to act in
accordance with the notice invoking arbitration under Section 21 of the
Arbitration Act.
12)In the present case, the notice under Section 21 of the Arbitration
Act has been issued by the Applicant on 20 June 2020, by which the
Applicant gave time of 7 days to concur with the suggested names of
arbitrators and therefore Application for appointment of Arbitrator
under Section 11 (6) of the Arbitration Act was required to be filed on or
before 26 June 2023. The Applicant failed to apply for appointment of
arbitrator within the period of 3 years prescribed in Article 137 of the
Limitation Act. However, the Applicant cites the reason of COVID-19
pandemic related restrictions when the Notice under Section 21 was
issued on 20 June 2020 and relies on Order passed by the Hon’ble
Supreme Court in RE: Cognizance for Extension of Limitation
7
, under
which the Hon’ble Supreme Court has excluded period from 15 March
2020 to 28 February 2022 for the purpose of computation of limitation
in the light of Covid-19 pandemic. According to the Applicant, since
notice under Section 21 of the Arbitration Act was issued right during
pandemic period on 20 June 2020, the period upto 28 February 2022 is
required to be excluded. Mr. Madon contests this position and
7(2022) 1 SCC (L&S) 501
Page No. 9 of 21
7 April 2026
Megha 34_arabpl_37441_2025_fc.odt
highlights the fact the Applicant filed Petition under Section 9 of the
Arbitration Act on 20 July 2020. He submits that therefore Covid-19
pandemic restrictions could not have selectively come in the way of the
Applicant filing Application under Section 11 of the Arbitration Act.
However, all Courts in India are bound by the directions issued by the
Apex Court in RE: Cognizance for Extension of Limitation (supra) and it
is not permissible to make case specific exceptions. Once the Supreme
Court has directed exclusion of period from 15 March 2020 to 28
February 2022 for the purpose of computation of limitation, mere filing
of Section 9 Petition by the Applicant on 20 July 2020 cannot be a
reason for denying him the benefit of exclusion of Covid-19 Pandemic
period. Applicant may have filed Section 9 Petition to preserve the
subject matter of arbitration. That does not mean that there was any
compulsion for him to seek appointment of arbitrator
contemporaneously. Considering the limited functioning of Courts
during pandemic period, non-filing of Section 11 Application, involving
no urgency, was quite justified. In my view, therefore, period from 26
June 2020 to 28 February 2022 is required to be excluded while
computing period of limitation of three years under Article 137 of the
Limitation Act.
13)After excluding the period from 26 June 2020 to 28 February 2022,
the present Application ought to have been filed on or before 28
February 2025. The Application is however filed on 15 November 2025.
This is how there is delay of 258 days in filing Application under Section
11(6) of the Arbitration Act. In HPCL Bio-Fuels (supra) the Apex Court
has ruled that benefit under Section 5 of the Limitation Act is available
Page No. 10 of 21
7 April 2026
Megha 34_arabpl_37441_2025_fc.odt
in respect of the application filed for appointment of arbitrator under
Section 11(6) of the Arbitration Act. However, the Apex Court has held
that discretion for condonation of delay under Section 5 of the
Limitation Act can be exercised only in exceptional cases where very
strong case is made out by the Applicant for condonation of delay in
filing Application under Section 11(6) of the Arbitration Act. The Apex
Court held in paragraphs 121 to 124 of the judgment in HPCL Bio-Fuels
as under:
121. The position of law that emerges from the aforesaid discussion is
that the benefit under Section 5 of the Limitation Act is available in
respect of the applications filed for appointment of arbitrator under
Section 11(6) of the Act, 1996. Further, the requirement of filing an
application under Section 5 of the Limitation Act is not a mandatory
prerequisite for a court to exercise its discretion under the said
provision and condone the delay in institution of an application or
appeal. Thus, the only question that remains to be considered is
whether in the facts of the present case, the respondent could be said
to have made out a case for condonation of delay in instituting the
fresh Section 11(6) application.
122. As discussed, the respondent took a conscious decision to
abandon its first Section 11(6) application with a view to pursue
proceedings under Section 9 of the IBC. The respondent made such
choice despite a specific objection raised by the appellant in its reply
to the statutory demand notice that there were pre-existing disputes
between the parties. In view of this, maximisation of the chances of
getting the application under Section 9 of the IBC admitted by the
NCLT seems to have been the only reason for the abandonment of the
first Section 11(6) application by the respondent. In light of such
conduct on the part of the respondent, we are of the view that the
present case does not warrant the exercise of our discretion under
Section 5 of the Limitation Act.
123. The primary intent behind Section 5 of the Limitation Act is not
to permit litigants to exploit procedural loopholes and continue with
the legal proceedings in multiple forums. Rather, it aims to provide a
safeguard for genuinely deserving applicants who might have missed a
deadline due to unavoidable circumstances. This provision reflects the
intent of the legislature to balance the principles of justice and
fairness, ensuring that procedural delays do not hinder the pursuit of
Page No. 11 of 21
7 April 2026
Megha 34_arabpl_37441_2025_fc.odt
substantive justice. Section 5 of the Limitation Act embodies the
principle that genuine delay should not be a bar access to justice, thus
allowing flexibility in the interest of equity, while simultaneously
deterring abuse of this leniency to prolong litigation unnecessarily.
124. The legislative intent of expeditious dispute resolution under the
Act, 1996 must also be kept in mind by the courts while considering an
application for condonation of delay in the filing of an application for
appointment of arbitrator under Section 11(6). Thus, the court should
exercise its discretion under Section 5 of the Limitation Act only in
exceptional cases where a very strong case is made by the applicant for
the condonation of delay in filing a Section 11(6) application.
(emphasis and underlining added)
14)As a matter of fact, in HPCL Bio-Fuels, the Apex Court, while
recognising the principle of application of Section 5 of the Limitation
Act to filing of an Application under Section 11(6) of the Arbitration
Act, has gone a step further by holding that filing of Application under
Section 5 of the Limitation Act is not a mandatory prerequisite for the
Court to exercise its discretion and that Court can condone the delay in
institution of an Application even without any formal Application for
condonation of delay.
15)In Tata Motors Passenger Vehicles Ltd. (supra) I have condoned
the delay of 76 and 91 days in filing Applications under Section 11 of
the Arbitration Act in absence of filing of a formal Application for
condonation of delay. This Court held in paragraph 38 of the judgment
as under:
38) Thus the Apex Court has ruled in HPCL Bio-Fuels (supra) that
benefit under Section 5 of the Limitation Act is available in respect
of the application filed for appointment of arbitrator under Section
11(6) of the Arbitration Act. The Apex Court has gone a step further
and has held that the requirement of filing application under
Section 5 of the Limitation Act is not a mandatory pre-requisite for
a Court to exercise its discretion under the said provision and
Page No. 12 of 21
7 April 2026
Megha 34_arabpl_37441_2025_fc.odt
condone the delay in institution of the application. Thus, the delay
in filing application under Section 11(6) can be condoned by the
Court, in a given case, even in absence of a formal application for
condonation of delay. In the present case, the delay is of 76 and 91
days. Considering the peculiar facts and circumstances of the case
where appointment of substitute arbitrator is necessitated
essentially for carriage of the reference and for its logical
conclusion, in my view, delay of 76 and 91 days in filing the present
application deserves to be condoned. The Applicants have been
taking requisite steps for having the disputes adjudicated. The
situation has arisen essentially on account of earlier arbitrator
withdrawing from arbitral proceedings and the Institute (BCCI)
failing to appoint the arbitrator despite repeated requests by the
Applicants. It is Applicants’ case that the liability to pay the
demanded amount is admitted by the Respondents. It is not
necessary to delve deeper into that aspect at this stage. However,
suffice it to observe that an opportunity needs to be granted to the
Applicants to have their disputes adjudicated on merits. I am
therefore inclined to condone the delay of about 76 and 91 days in
filing the present Applications.
(emphasis added)
16)Thus, this Court is invested with power to condone the delay in
filing application under Section 11(6) of the Arbitration Act on account
of applicability of provisions of Section 5 of the Limitation Act. Though
filing of formal application for condonation of delay is not a
prerequisite, the Applicant has, in the present case, filed Interim
Application (L) No.11418 of 2026 seeking condonation of delay of 258
days. The issue for consideration is whether the Applicant has made out
sufficient cause as well as exceptional case for condonation of delay of
258 days. While Courts need to adopt liberal approach while
considering condonation of delay in usual cases, the approach while
considering the issue of condonation of delay in filing application under
Section 11(6) needs to be different. The discretion under Section 5 of
the Limitation Act is not to be exercised routinely and by adopting a
liberal approach. The Applicant needs to make out a very strong case for
Page No. 13 of 21
7 April 2026
Megha 34_arabpl_37441_2025_fc.odt
condonation of delay in filing Section 11(6) Application and the
reference Court needs to be satisfied that the case is exceptional one. I
accordingly proceed to examine whether the Applicant has made out a
sufficient cause keeping in mind the caveat prescribed by the Apex
Court in HPCL Biofuels that the delay can be condoned only in
exceptional case where very strong case is made out by the Applicant,
17)From narration of facts, it is seen that the Applicant has entered
as the 8
th
partner in the Partnership Firm where the Respondents were
the original partners. The Firm was entrusted with the project of
redevelopment of Panwala Chawl at Lalbaug in Mumbai. It is
Applicant’s case that it has invested amount of Rs.30 crores in the
project. The initial investments were through its sister concern Poonam
Infra and later, the Applicant is admitted as the partner in the Firm. It
appears that the project is taken away from the Firm by MHADA by
acquisition of property vide order dated 20 March 2025. The Petitioner
therefore wants back the invested amounts from the Firm and
accordingly seeks adjudication of disputes through arbitration.
18)The Applicant is thus desirous of seeking adjudication of its claim
against the other 7 partners on account of losses suffered by it by
investing amount of Rs.30 crores in the project. Though the Applicant
has invoked arbitration by issuing notice dated 20 June 2020, it was first
required to secure and preserve the subject matter of arbitration, which
was in the danger of being wasted. The subject matter of arbitration in
the present case is the redevelopment project and the Applicant was
required to make efforts and engage into a maze of litigation to save
and preserve the project. On account of the rift amongst the partners,
Page No. 14 of 21
7 April 2026
Megha 34_arabpl_37441_2025_fc.odt
the society members were complaining to MHADA, who wanted to take
away the project from the Firm. The Applicant was first required to file
Arbitration Petition No.241 of 2023 on 10 July 2020 for securing interim
measures against the Respondents. By order dated 20 July 2020, this
Court restrained the Respondents from creating any third-party rights,
parting with possession or putting up any construction altering the
status or condition of the property. More importantly, this Court also
made interim measures against MHADA from taking coercive actions in
respect of the project. This is how the Applicant was required to take
steps for preserving the subject matter of arbitration. On account of
Covid-19 Pandemic, no development took place in respect of the project
for some time. In May-2023, the Applicant started making the
representations to various authorities such as Chief Minister,
Additional Chief Secretary of Housing Department, MHADA, etc. It also
made representation on 12 July 2023 to president of MHADA.
19)It appears that the subject matter of arbitration came under real
threat when MHADA made application before the Housing Department
seeking acquisition of the property for effecting redevelopment of the
chawl. The Housing Department accepted MHADA’s Application and
permitted MHADA to pursue the application by blacklisting the
Partnership Firm on 11 January 2024. On account of this development,
the Applicant was required to file Writ Petition No.722 of 2024 for
setting aside the order of acquisition. Simultaneously, the Applicant
also filed Interim Application in Section 9 Petition for securing the
interim measures against MHADA. According to the Applicant, this
Court issued oral directions to MHADA not to take any coercive steps on
Page No. 15 of 21
7 April 2026
Megha 34_arabpl_37441_2025_fc.odt
12 February 2024. As a pre-condition for entertainment of Writ Petition
No.722 of 2024, this Court directed the Applicant to deposit an amount
of Rs.2 crores, possibly towards arrears of transit rent of 80 members of
the Chawl-Society. It is the Applicant, who complied with the said order
and deposited amount of Rs.2 crores in this Court to preserve the
subject matter of arbitration. According to the Applicant, it was the
responsibility of Respondent No.6 to pay the transit rent, but for saving
the project, it was required to make the deposit. Writ Petition No.722 of
2024 was thereafter entertained and disposed of with liberty to the
Applicant to make representation to the State Government and to
MHADA. The Applicant accordingly made representation in April 2024
showing readiness and willingness to pay outstanding transit rent and
to complete the project. Representations were heard in July 2024 and
were finally rejected on 14 August 2024. The Applicant was required to
file Writ Petition (L)No.32243 of 2024 challenging the order dated 14
August 2024, which is pending. While the Applicant was taking above
steps for preserving the subject matter of arbitration, the period of
three years for filing Application under Section 11(6) of the Arbitration
Act came to an end on 1 March 2022. However, on 20 March 2025
MHADA completed acquisition proceedings and property vested in
MHADA. The Applicant called upon the Respondents to appear in
Section 9 Petition for securing appropriate interim measures, but the
Respondents failed to show any interest. After learning that the
Respondents were not showing any interest in the project and that the
entire investment made by the Applicant would go waste, he has
ultimately filed Application under Section 11(6) of the Arbitration Act
on 15 November 2025.
Page No. 16 of 21
7 April 2026
Megha 34_arabpl_37441_2025_fc.odt
20)The Applicant was thus required to take several steps for ensuring
preservation of the subject matter of arbitration, before it could seek
adjudication of disputes with other partners of the Firm.
21)Considering the above position, in my view, an exceptional and
strong case is made out by the Applicant for condonation of delay in
filing Application under Section 11(6) of the Arbitration Act. The case
involves peculiar circumstances, where taking of steps for preservation
of subject matter of arbitration was more important than seeking
adjudication of disputes with the other partners. If the Applicant was
successful in securing the project, the very perspective of the disputes
between the Applicant and other partners would have changed. In the
facts of the present case, the Applicant thought it more prudent, and in
my view rightly, to first take steps to prevent the property being
acquired by MHADA. It was required to litigate repeatedly for ensuring
that the Firm does not lose the project. The real cause for seeking
arbitration against the Respondents has occurred only after MHADA
acquired the property and the Firm has lost the possession. It now
appears that the Applicant does not have much hopes left in securing
back the investment allegedly made by it in the project by completing
the same and it desires to seek recovery of the same from other partners
(Respondents).
22)Considering the above unique circumstances, in my view delay in
filing the Application deserves to be condoned. The Applicant has made
out sufficient cause as well as a strong and exceptional case for
Page No. 17 of 21
7 April 2026
Megha 34_arabpl_37441_2025_fc.odt
condonation of delay. All the three decisions relied upon by rival parties
in N. Balakrishnan, Sheo Raj Singh (deceased) through Legal
Representatives and Mool Chandra (supra) discuss the principles
governing the approach and methodology to be adopted by the Courts
in deciding applications for condonation of delay in cases other than
application under Section 11(6) of the Arbitration Act and are therefore
not relevant for deciding the present application. In the present case,
length of delay is not inordinate. There is a strong cause shown by the
Applicant, who is not found to be dormant or negligent in respect of its
remedy. Its remedy of seeking appointment of arbitrator was also
dependent, to a great extent, on preserving the subject matter of
arbitration. This Court is satisfied with the justification for delay since
the Applicant was required to take several steps for preserving the
subject matter of arbitration. Therefore, it cannot be inferred that the
Applicant was negligent or indolent in respect of its right to seek
adjudication of disputes through arbitration.
23)In my view, therefore, the Applicant has made out a strong and
exceptional case for condonation of delay of 258 days in filing the
Arbitration Application. In my view therefore, the delay in filing the
application deserves to be condoned.
24)So far as merits of the Application is concerned, clause 16 of the
Deed of Alteration of Partnership dated 10 April 2013 undoubtedly
contains arbitration agreement. Clause 16 reads thus:
16.If during the continuance of the said partnership or at any time
afterwards any difference shall arise between the partners and the
Page No. 18 of 21
7 April 2026
Megha 34_arabpl_37441_2025_fc.odt
heirs, executors or administrators in regard to the construction of any
of the articles herein contained or to any division, act or thing to be
made or done in pursuance hereto or to any other matter or thing
relating to the said partnership the same shall be forthwith referred to
one arbitrator if the parties agree or otherwise to two arbitrators, one
to be appointed by each party to the reference or to an Umpire to be
chosen by the Arbitrators before entering upon the reference and
every such reference shall be deemed to be an Arbitration in
accordance with and subject to the provisions of Indian Arbitration in
accordance with the subject to the provisions of Indian Arbitration
Act, 1940, or any statutory modification or re-enactment thereof for
the time being in force.
25)Mr. Madon has fairly not disputed the existence of arbitration
between the parties. The parties have also agreed for appointment of a
sole arbitrator. In my view, therefore, it would be just and proper to
constitute Arbitral Tribunal of sole Arbitrator for adjudication of
disputes and differences between the parties.
26)I accordingly proceed to pass the following order:-
(i)Delay of 258 in filing Application under Section 11(6) of the
Arbitration Act is condoned and accordingly, Interim
Application (L) No.11418 of 2026 is allowed.
(ii)Mr. Justice A. A. Sayed, former Chief Justice of Himachal
Pradesh High Court is appointed as sole Arbitrator to
adjudicate upon the disputes and differences between the
parties arising out of Deed of Alteration of Partnership
dated 10 April 2013. The contact details of the Arbitrator
are as under:-
Page No. 19 of 21
7 April 2026
Megha 34_arabpl_37441_2025_fc.odt
Office Address:-American View Bungalow, Oomer
Park (Opp. Tata Garden), Bhulabhai
Desai Road (Warden Road), Mumbai-
400 026.
Mobile No.:-982007240
Email id:-sayamjad@gmail.com
(iii)A copy of this order be communicated to the learned sole
Arbitrator by the Advocates for the Petitioner within a period of
one week from the date of uploading of this order. The Petitioner
shall provide the contact and communication particulars of the
parties to the Arbitral Tribunal alongwith a copy of this order.
(iv) The learned sole Arbitrator is requested to forward the
statutory Statement of Disclosure under Section 11(8) read with
Section 12(1) of the Act to the parties within a period of 2 weeks
from receipt of a copy of this order.
(v) The parties shall appear before the learned sole Arbitrator
on such date and at such place as indicated by him, to obtain
appropriate direction with regard to conduct of the arbitration
including fixing a schedule for pleadings, examination of
witnesses, if any, schedule of hearings etc.
(vi)The fees of the sole Arbitrator shall be as prescribed under
the Bombay High Court (Fee Payable to Arbitrators) Rules, 2018
and the arbitral costs and fees of the Arbitrator shall be borne by
the parties in equal portion and shall be subject to the final Award
that may be passed by the Tribunal.
Page No. 20 of 21
7 April 2026
Megha 34_arabpl_37441_2025_fc.odt
27) All rights and contentions of the parties are expressly kept open
to be agitated before the arbitral tribunal.
28)With the above order, Arbitration Application is allowed and
disposed of. There shall be no orders as to costs.
29) Interim Application (L) No.11418 of 2026 is disposed of.
[SANDEEP V. MARNE, J.]
Page No. 21 of 21
7 April 2026
Legal Notes
Add a Note....