HIGH COURT OF JAMMU & KASHMIR AND LADAKH
AT JAMMU
OWP No. 747/2005
Reserved on: 04.04.2025
Pronounced on: 17.07.2025
Jammu Municipal Corporation
and another
…. Petitioner/Appellant(s)
Through:- Mr. S.S. Nanda, Sr. AAG
V/s
Apurab Mahajan and others …..Respondent(s)
Through:- Mr. Gagan Oswal, Advocate
CORAM: HON’BLE MRS. JUSTICE SINDHU SHARMA, JUDGE
JUDGMENT
1. This petition has been preferred under Article 226 of the
Constitution of India by the Jammu Municipal Corporation, seeking
quashing of order dated 08.09.2005, passed by the J&K Special
Tribunal in appeal titled “Sanjay Mahajan (deceased through LRs)
and another v. Jammu Municipality and others”.
2. The respondents sought permission for construction of commercial
complex at Samdian Land, below Gumat Jammu, comprising of
ground floor, first floor and second floor, with a built-up area of
1080 sft., which was granted vide permission No. No. 271 dated
25.10.1998. It is submitted that the construction was raised in
violation of the sanctioned plan, resulting in proceeding against the
respondents for violation under Section 7(1) of Control of Building
Operations Act for unauthorisedly construction against the
approved plan. Thereafter, notice under Section 7(3) was issued to 2025:JKLHC-JMU:1892
OWP No. 747/2005______ Page 2 of 8
the respondents directing to demolish the unauthorized construction
within a period of five days from the date of the service of notice.
3. The respondents filed an appeal against the demolition notice dated
30.10.2000.
4. The Tribunal vide order dated 08.12.2000, issued a notice and
called for the record and sought the report from the Jammu
Municipality on the following grounds: -
i. Nature and extent of violation showing setback, roads,
lanes etc and distance thereof from the allegedly
offending structure;
ii. Map to scale;
iii. Whether there is any violation of Municipal Bye-laws,
prevention of Ribbon Development Act, Town Planning
Act or Zoning Regulations applicable to that area.
5. The contention of the respondents in the appeal was that they are in
possession of a banquet hall and they have raised construction
strictly as per duly approved sanctioned plan issued by the JMC.
There is no violation of Municipal Bye-laws and respondent No. 3
was well within her right to raise the construction as per her choice.
6. In the objections before the Tribunal, the petitioners (hereinafter
referred as JMC) submitted that the construction has been raised
against the sanctioned plan. There are major violations as instead of
built up area of 1080 sq. feet in each floor, he has raised
construction of 4720 sq. feet in ground floor and first floor. The
respondents have failed to keep 15 feet set back at front and back
and 10 feet rear, but no set backs have been kept which is a major 2025:JKLHC-JMU:1892
OWP No. 747/2005______ Page 3 of 8
violation of the sanctioned plan. The respondents have also
constructed over hanging balcony and basement floor of
dimensions of 19x06x25 against the sanctioned plan.
7. The JMC in their report submitted that the construction raised
against sanctioned plan and violation chart was as under: -
S. No. Type of floor Built up area
as per the
sanctioned
plan
Built up area
as per actual
construction
raised at site
Excess over
the sanctioned
plan
1 Basement floor __ 543 sft 543 sft
2 Ground floor 1080 sft 4720 sft 3640 sft
3 First floor 1080 sft 4720 sft 3640 sft
4 Balcony projection __ 236 sft 236 sft
8. The respondent has constructed basement floor without any
permission and did not keep setback of 15 feet front, 10 feet on
both sides and 10 feet rear setbacks as per the sanctioned plan,
which constituted major violation. Besides this, there is also
balcony projection overhanging over the road.
9. The Tribunal after considering the submissions decided the appeal
vide order dated 08.09.2005 and held as under: -
“As admitted by both the learned counsels for the parties, it is
fact that 90% commercial activities in the area and there are
huge commercial complexes have come up in the area, so in
my considered view, there is no violation of Master plan or
zoning regulation applicable to the area. The appellant has
made some deviations from the sanctioned plan which was
sanctioned for commercial purposes, so in my considered
view, the case can safely be compounded. I would also like to
comment that Shri Sanjay Mahajan expired during his prime
life leaving behind his widow, Smt. Anita Mahajan and two
minor children as brought to the notice of this bench by the
advocate for the appellant and this is an unfortunate affair. In
my considered view, at this stage if the respondents are
allowed to remove the alleged unauthorized structure raised
by the appellant, it will cause irreparable loss and injury to
the legal representatives of the deceased. So in fact and
circumstances of the case, it hereby, order the composition of
the unauthorized structure. The appellant has raised total
9983 sft structure out of which an area of 2160 sft is a
sanctioned one. So there is an area of 7823 sft. @ Rs. 25/- sft.
Apart for the above the appellant has also raised balcony 2025:JKLHC-JMU:1892
OWP No. 747/2005______ Page 4 of 8
projection of 236 sft., which is also regularized and for that
the appellant shall pay compounding fee @ Rs. 30/- sft. The
appellants shall deposit the compounding fee with the
respondents within a period of 30 days failing which the
appeal filed by the appellant shall be deemed to have been
dismissed.”
10. The petitioners are aggrieved of the impugned order on the ground
that the Tribunal without deciding the fact whether the violations
committed by the respondents are major or minor has compounded
the construction raised unauthorisedly. The compounding of
construction raised unauthorisedly is provided in Clause 10 and 11
of the Jammu and Kashmir Control of Building Operations
Regulations, 1998. These clauses read as under:-
10.Appeals. ––(1) An appeal against the order of the Authority
made under section 5 and 7 of the Act shall lie before the
Chairman of the J&K Special Tribunal or such other Member of
the said Tribunal as may be decided by the same Chairman.
11. Compounding of offence
(1) The appellant authority may compound the offence of minor
nature specified in sub-clause 2 of the Regulation.
Provided that the compounding fee shall be worked out on the
basis of rates to be notified by the Government.
(2) For the purpose of this regulation, an offence of a minor nature
shall include an erection or re-erection of the building, which has
taken place in violation of permission referred in Section 4 of the
Act, or deemed permission as referred to in sub-clause 2 of
clause 7 of the Regulation, provided that such erection or re-
erection: -
(i) Does not violate the approved land use of the area as
notified in the Master Plan or Town Planning
Scheme;
(ii) Does not violate permissible front, rear, or side
setbacks prescribed in the bye-laws;
(iii) Does not violate by more than 10% the permissible
ground coverage as prescribed in the bye-laws; and
(iv) Does not violate the permissible height of the
building as prescribed in the bye-laws.
11. In terms of these clauses, only minor violations can be
compounded. Major and serious violations cannot be compounded.
These regulations do not violate the approved land use of the area, 2025:JKLHC-JMU:1892
OWP No. 747/2005______ Page 5 of 8
as notified. The violations of front, rear or side setbacks and
permissible ground coverage exceeding 10% does not fall in the
category of minor offences and are non compoundable. The
respondents as per the report of the municipality were allowed to
raise construction of a built up area of 1080 sft. on each floor as per
the sanctioned plan. The respondents, however, have raised the
built up area of 4270 sft, which is a major violation and could not
be compounded. As per the sanctioned plan, the respondents have
failed to keep the requisite setbacks of 15 feet front, 10 feet both
sides and 10 feet rear, which has resulted in major violations, which
could not be compounded.
12. The respondents were also not permitted to raise balcony projection
which they have raised in unauthorized manner and have also
constructed basement which was not approved in the sanctioned
plan. Thus, the ground floor which was exclusively meant for
parking purpose is used for commercial purposes in violation of
sanctioned plan and master plan.
13. The respondents submits that Tribunal has returned a finding and
every order made by it is fine and a specific statutory bar exists
against challenging such orders, the maintainability of any petition
seeking to question the order, particularly on disputed questions of
fact is not permitted in law.
14. Reliance is placed on the judgment of this Court in “Building
Operation Controlling Authority v. Nageen Ara”, decided on
29.08.2023, whereby, this Court has held that once finding of
compounding of construction is givne by that court, then this Court 2025:JKLHC-JMU:1892
OWP No. 747/2005______ Page 6 of 8
cannot go in to fact whether violation is major or minor. The same
reads as under: -
“…Once the Tribunal has given finding by
compounding the construction, then this Court cannot
go into the questions and reasoning which lead to the
passing of the aforesaid order, which is based on
appreciation of evidence. This Court does not have any
mechanism or yardstick to go into the question of fact
by conducting enquiry with respect to the fact whether
there is any minor or major violation, as alleged by the
petitioner. This Court, while exercising the powers
under writ jurisdiction, cannot re-appreciate the
evidence by way of an appellate authority to go into
the disputed questions of facts which have been
arrived at by the Learned Tribunal after appreciating
all the material facts and record and adducing
evidence. This Court can't assume the power/role of
Commissioner to go on spot to verify whether it is
major or minor violation, which falls within the realm
of disputed question of facts, and the Tribunal being
the arbiter in such like matters has the final authority,
and the finding recorded by the Tribunal can't be upset
in writ jurisdiction. Unauthorized construction once
compounded by the Municipal Authorities...”
15. This judgment is not applicable to the facts of the case as the
petitioners had specifically submitted that the respondents had
committed major violations while raising the construction, which
could not be compounded. The respondents in their reply to the
report of the JMC has only stated that the structure raised is not
causing any obstruction to anyone, as the entire area is full of
commercial complexes and thus did not warrant satisfaction of the
authority. Therefore, the Tribunal failed to consider this aspect.
16. Perusal of report reveals that the required setbacks were completely
encroached upon and the basement was unauthorizedly constructed.
Such violations clearly fall within the category of major infractions
and are, therefore, not compoundable under the applicable law. 2025:JKLHC-JMU:1892
OWP No. 747/2005______ Page 7 of 8
17. The respondents have, thus, committed major violation which is not
permissible in terms of Section 11 of Control of Buildings Act. This
apart, learned Tribunal while passing the impugned order has relied
upon the fact that 90 % of the building existing in the vicinity have
covered up their setbacks while raising the construction and there is
parking provision in the structure as the basement floor would be
used for parking purpose. The Tribunal has totally ignored the fact
that there was no sanction plan for basement of the building. This
apart, reliance has been placed by the learned counsel for the
petitioners with regard to the finality of the orders.
18. The Tribunal while noticing the violation has failed to return a
finding whether the violation committed by the respondents was
major or minor and has in fact exceeded the jurisdiction by
compounding the offence which being in major violation could not
be compounded by this Court, regulations and by law.
19. The learned Tribunal has failed to decide whether the violation was
major or minor and whether it had the authority to compound the
same. The Tribunal without considering this aspect has decided the
same and compounded the same which is in violation of the
mandate of Act.
20. In Pratibha Coop. Housing Society Ltd. v. State of
Maharashtra, (1991) 3 SCC 341, the Hon’ble Supreme Court has
held as under: -
“Before parting with the case we would like to observe that this
case should be a pointer to all the builders that making of
unauthorised constructions never pays and is against the interest
of the society at large. The rules, regulations and bylaws and
made by the Corporations or development authorities taking in 2025:JKLHC-JMU:1892
OWP No. 747/2005______ Page 8 of 8
view the larger public interest of the society and it is the
bounden duty of the Citizens to obey and follow such rules
which are made for their own benefits.”
21. In view of the aforesaid facts and circumstances, the impugned
order passed by the learned Tribunal is illegal and unreasonable and
does not sustain in the eyes of law and is accordingly quashed. The
mater is remitted back to the Tribunal to decide the same afresh.
The Tribunal shall proceed on the basis of material before it and
pass an order expeditiously, preferably within three months.
22. Disposed of.
(SINDHU SHARMA)
JUDGE
Jammu:
17.07.2025
Vishal Khajuria
Whether approved for reporting : Yes/No
2025:JKLHC-JMU:1892
Legal Notes
Add a Note....