No Acts & Articles mentioned in this case
Page No. 1/52
THE GAUHATI HIGH COURT
(THE HIGH COURT OF ASSAM, NAGALAND, MIZORAM & ARUNACHAL PRADESH)
WRIT PETITION (C) NO. 6446/2023
Jayanta Khaund, Class 1 [A] Contractor,
Guwahati Diagnostic Centre Building, 2
nd
Floor, G.S. Road, Bhangagarh, Guwahati –
781008.
………………Petitioner
- VERSUS-
1. The Assam Power Distribution Company
Limited [APDCL] [A Successor Company of
Assam State Electricity Board, represented
by its Chairman, 1
st
Floor, Bijulee Bhawan,
Paltanbazar, Guwahati – 781001.
2. The Managing Director, Assam Power
Distribution Company Limited [APDCL],
Bijulee Bhawan, Paltanbazar, Guwahati –
781001.
3. The Chief General Manager [PP&D], Assam
Power Distribution Company Limited
[APDCL], Bijulee Bhawan, Guwahati – 1.
GAHC010267942023
Page No. 1/52
THE GAUHATI HIGH COURT
(THE HIGH COURT OF ASSAM, NAGALAND, MIZORAM & ARUNACHAL PRADESH)
WRIT PETITION (C) NO. 6446/2023
Jayanta Khaund, Class 1 [A] Contractor,
Guwahati Diagnostic Centre Building, 2
nd
Floor, G.S. Road, Bhangagarh, Guwahati –
781008.
………………Petitioner
- VERSUS-
1. The Assam Power Distribution Company
Limited [APDCL] [A Successor Company of
Assam State Electricity Board, represented
by its Chairman, 1
st
Floor, Bijulee Bhawan,
Paltanbazar, Guwahati – 781001.
2. The Managing Director, Assam Power
Distribution Company Limited [APDCL],
Bijulee Bhawan, Paltanbazar, Guwahati –
781001.
3. The Chief General Manager [PP&D], Assam
Power Distribution Company Limited
[APDCL], Bijulee Bhawan, Guwahati – 1.
GAHC010267942023
Page No. 2/52
4. The Chief General Manager [NRE], Assam
Power Distribution Company Limited
[APDCL], Bijulee Bhawan, Guwahati – 1.
5. The Senior Manager, Federal Bank Limited,
Paltan Bazar Branch, Ramanand Tower, G.S.
Road, Guwahati – 08.
……………….Respondents
Advocates :
Petitioner : Mr. K.N. Choudhury, Senior Advocate
Mr. J. Patowary, Advocate
Respondent nos. 1 – 4 : Mr. I. Chowdhury, Senior Advocate
Mr. K.P. Pathak, Standing Counsel,
APDCL
Respondent no. 5 : Mr. M. Sharma, Advocate
Date of Hearing : 19.01.2024, 22.01.2024 & 23.01.2024
Date of Judgment & Order : 24.01.2024
BEFORE
HON’BLE MR. JUSTICE MANISH CHOUDHURY
JUDGMENT & ORDER [CAV]
The petitioner has instituted the present writ petition under Article 226 of the
Constitution of India seeking the following reliefs/directions :-
[a] Certiorari shall not be issued to set aside and quash the impugned letter
bearing No. APDCL/CGM[PP&D]/NRE-146/2019-20/787 dated 01.11.2023
issued by the CGM [NRE], APDCL [Annexure-10] whereby the bank
guarantees of the petitioner is sought to be liquidated and
Page No. 3/52
[b] Certiorari shall not be issued to set aside and quash the impugned letter dated
04.11.2023 vide which it has been decided to encash the petitioner’s bank
guarantees despite extension of time granted and
[c] Mandamus shall not be issued directing the respondent authorities comply
with the extension of time granted vide letter No. APDCL/CGM[PP&D]/NRE-
146/2019-20/789 dated 02.11.2023 [Annexure-12] and,
[d] Mandamus directing the respondent authorities to refrain from invoking the
Bank guarantees of the petitioner during the pendency of the present petition
and, upon causes being shown be further pleased to make the Rule absolute
and/or pass such other order[s] as Your Lordships may deem fit and proper to
grant adequate relief to the petitioner
-AND-
Pending disposal of the Rule be further pleased to pass appropriate interim
order[s] so as to give adequate interim relief to the petitioner by staying the
operation of letter dated 01.11.2023 and 04.11.2023 and by further directing the
authorities to maintain status quo in the matter and/or pass any other orders as
Your Lordships may deem fit and proper.
2. When the writ petition was moved on 08.11.2023, the Court while issuing notice,
had provided, as an ad-interim measure, that if the Bank Guarantees furnished by
the petitioner had already expired on the dates indicated in a letter dated
29.01.2021 and the validity of the same had not been extended, then in that
event, the same shall not be encashed without the leave of the Court. Seeking
vacation/modification of the said Order dated 08.11.2023, the respondent Assam
Power Distribution Company Limited [‘the APDCL’, for short] authorities have
preferred an interlocutory application, which has been registered and numbered
as I.A.[C] no. 3499/2023. In the course of the proceedings, the respondent
APDCL authorities have preferred another interlocutory application seeking a
direction to the petitioner and the respondent no. 5 in the writ petition, W.P.[C]
no. 6446/2023, that is, Federal Bank Ltd. to extend the validity of the three Bank
Guarantees or to provide adequate alternative security and the said interlocutory
application has been registered and numbered as I.A.[C] no. 163/2024.
Page No. 4/52
3. The parties have exchanged a number of pleadings and the learned counsel for
the parties have submitted that the exchange of pleadings between the parties is
complete.
4. In order to understand the nature of challenges made and to appreciate the
issues raised and involved in the writ petition, a narration of facts in sequence,
shorn of unnecessary details, appears necessary at this stage.
4.1. The office of the Chief General Manager [PP&D], APDCL, Guwahati [the
respondent no. 3] published a Request for Proposal [RFP] on 18.06.2020 to invite
interested Bidders to participate in an online bidding process for procurement of
power from Grid Connected Solar Photovoltaic [PV] Power Projects through Tariff
Based Competitive Bidding Process for total 25 MWAC capacity for a number of
Regions including Region-2 [hereinafter referred to as ‘the Region-2 Project’, for
easy reference], in the State of Assam on ‘Build-Own-Operate’ basis. It was
informed that the bidder would be selected through an Open Competitive Bidding
process in accordance with the procedure set out in the Request for Selection
[RFS] and it would be the responsibility of the Successful Bidder[s] to supply
power to the Procurer as per the terms and conditions of the RFS Document. One
of such Regions is Region-2, covering the districts of Goalpara, Bongaigaon,
Barpeta, Nalbari, Kamrup – Metro & Kamrup – Rural. The petitioner herein was a
Bidder for Region-2.
4.2. As per the Bid Information Sheet contained in the RFS Document, the time-lines
were set out as follows :- [i] 23.06.2020 : Date of issue of the RFS Document &
the Draft Power Purchase Agreement; [ii] 13.07.2020 : Last date of receipt of Pre-
Bid queries from the Bidders; [iii] 17.07.2020 : Pre-Bid Meeting; [iv] 19.08.2020 :
Due date for online submission of ‘Techno-Commercial Bid’ and ‘Price Bid’ as per
the RFS; [v] 20.08.2020 : Due date for hard copy submission of ‘Techno-
Commercial Bid’ as per the RFS; and [vi] 22.08.2020 : Due date for ‘Techno-
Commercial Bid’ opening [except ‘Price Bid’]. The date of Price Bid opening was to
be intimated to the qualified bidders later on.
Page No. 5/52
4.3. As per the RFP, the Bidding Document comprised of two volumes, that is,
Volume-I : Request for Selection [RFS] and Volume-II : Power Purchase
Agreement [PPA]. As per the Bidding Document, a Bidder was to submit Bid
Security [EMD] for an amount of Rs. 6,72,000/- per MWAC and the validity of the
Bid Security was to be of 180 days from the original Due date for online
submission of ‘Techno-Commercial Bid’ and ‘Price Bid’ as per the RFS. It was
further indicated that a Successful Bidder would be required to submit
Performance Security/Contract Performance guarantee for an amount of Rs.
16,80,000/- per MWAC.
4.4. As per the Brief Scope mentioned therein, the Power Producer Companies/Solar
Developers shall be responsible for development of Grid Connected Ground
Mounted Solar Photovoltaic [PV] Projects to be implemented in the Regions
including Region-2 [Goalpara, Bongaigaon, Barpeta, Nalbari, Kamrup – Metro &
Kamrup – Rural], in the State of Assam on ‘Build-Own-Operate’ basis only for the
procurement of Solar Power by the APDCL for a period of 25 years and the Ceiling
Tariff was mentioned at Rs. 4.00 per unit. The bidding process was a single stage
two envelops bidding process, followed by the E-Reverse Auction Process,
adopted by the APDCL for the award of the Projects to the Successful Bidder[s],
as per the terms set out in the RFS Document. After selection of the Successful
Bidder[s], Power Purchase Agreement[s] was/were to be signed between the
Procurer, that is, the APDCL and the Successful Bidder[s]. The responsibility of
the Successful Bidder[s] is to supply power to the Procurer as per the terms and
conditions of the RFS Document and the Procurer would pay to the Seller the
Quoted Fixed Tariff which has been arrived from single fixed tariff quoted by the
Successful Bidder in the Price Bid followed by E-Reverse Auction, as per the terms
and conditions of the Power Purchase Agreement [PPA].
4.5. The Solar Power Developer, as per the RFS Document and the Draft Power
Purchase Agreement [PPA], would be responsible for design, financing,
‘acquisition’ or ‘leasing’ of land, detailed engineering, procurement, construction,
Page No. 6/52
erection, testing, synchronizing, commissioning, operating and maintaining the
Project[s] in accordance with the provisions of the Power Purchase Agreement
[PPA] to be entered into between the Solar Power Developer/Successful Bidder
and the APDCL, which is to be further vetted and concurred by the Assam
Electricity Regulatory Commission [AERC].
5. In response to the RFS, the petitioner herein submitted his bid in respect of the
Region-2 Project. On emergence of the petitioner as the Successful Bidder in
respect of the Region-2 Project, a Letter of Award [LoA] bearing no.
APDCL/CGM[PP&D]/NRE-146/2019-20/532 was issued on 04.01.2021 in favour of
the petitioner informing him that Tariff quoted at Rs. 3.99 only per unit for
development of 25 MWAC Grid Connected Solar Photovoltaic [PV] Project in
Region-2 [Goalpara, Bongaigaon, Barpeta, Nalbari, Kamrup – Metro & Kamrup –
Rural], as specified in the RFS had been accepted. It was further informed that
the acceptance of the petitioner’s offer would be subject to the following terms
and conditions :-
[a] In terms of RFS, Power Purchase Agreement [PPA] is to be signed within
thirty [30] days from the date of issuance of this LOA. Copy of the PPA is
enclosed herewith as Annexure-I.
[b] In terms of RFS & PPA, Performance Bank Guarantee [PBG] for Rs.
16,80,000.00 [Indian Rupees Sixteen Lakh Eighty Thousand only] per MW
aggregating to Rs. 4,20,00,000.00 [Rupees Four Crore twenty lakhs] only is
to be submitted prior to signing of PPA. The Performance Security shall be
furnished in the form of three [3] Bank Guarantees as mentioned below in
favour of “Chief General Manager [Comm. & EE]”, APDCL payable at
Guwahati as per the format provided in Schedule 3 of PPA and having
validity up to twenty two [22] months from the Date of Signing of PPA.
[i] PBG for an amount of Rs. 84,00,000.00 [Rupees Eighty Four Lakhs]
having validity up to twenty two [22] months from the Date of Signing
of PPA
Page No. 7/52
[ii] PBG for an amount of Rs. 1,68,00,000.00 [Rupees One Crore Sixty
Eight Lakhs] having validity up to twenty two [22] months from the
Date of Signing of PPA
[iii] PBG for an amount of Rs. 1,68,00,000.00 [Rupess One Crore Sixty
Eight Lakhs] having validity up to twenty two [22] months from the
Date of Signing of PPA.
5.1. On receipt of the Letter of Award [LoA] dated 04.01.2021, the petitioner
submitted 3 [three] nos. of Bank Guarantees to the respondent no. 3 vide his
Letter bearing reference no. JK/NLP/APDCL/SOLAR PROJECT/Region-2/L-05 dated
29.01.2021 by describing the details of the three Bank Guarantees as follows :
Sl. BG No. Date of issue Value of BG Valid Upto Issued by
1 IBG113029 25.01.2021 84,00,000.00 24.01.2023 Federal Bank
Ltd. Jorhat
Branch
2 IBG113031 25.01.2021 1,68,00,000.00 24.01.2023
3 IBG113102 27.01.2021 1,68,00,000.00 26.01.2023
5.2. The respondent no. 5, that is, Federal Bank, Jorhat Branch by its 3 [three] nos. of
letters - Dated 25.01.2021, Dated 25.01.2021 & Dated 27.01.2021 – gave
covering to the afore-mentioned three Bank Guarantees with the advise that the
APDCL, in its own interest, could verify the genuineness of the Bank Guarantees
by contacting Jorhat Branch of the Federal Bank. If IFSC of the APDCL’s Bank
would be provided to the Federal Bank, Jorhat Branch, a confirmation message
regarding the issuance of the Bank Guarantees would be sent to the APDCL’s
Bank through SFMS.
5.3. On 15.02.2021, the petitioner vide his Letter bearing Reference no.
JK/NLP/APDCL/SOLAR PROJECT/Region-2/L-06 of even date forwarded the sets of
Power Purchase Agreements [PPAs], after subscribing his signatures.
5.4. On 28.12.2022, the APDCL through the respondent no. 4, that is, the Chief
General Manager [NRE], APDCL, Guwahati issued a Show Cause Notice bearing
no. APDCL/CGM/PP&D/NRE-146/2019-20/777 asking the petitioner to show cause
Page No. 8/52
as to [i] why the contract shall not be terminated; [ii] why the petitioner should
not be declared as a non-performer; [iii] why the petitioner should not be
debarred for 3 [three] years from participating in any future bid of the APDCL;
and [iv] why Security Deposit submitted against the Region-2 Project should not
be encashed/invoked. Further reference of the Show Cause Notice would be made
at a later stage of this Order.
5.5. On receipt of the Show Cause Notice, the petitioner submitted a Reply to the said
Show Cause Notice vide Reference no. JK/NLP/APDCL/SOLAR PROJECT/Region-
2/L-18 dated 05.01.2023 giving explanation from his side as to why the actions
contemplated by the Show Cause Notice should not be taken.
6. It was thereafter the impugned Letter bearing no. APDCL/CGM[PP&D]/NRE-
146/2019-20/787 dated 01.11.2023 [Annexure-10] came to be issued by the
respondent no. 4. By addressing the Letter to the Senior Manager, Federal Bank
Ltd. [the respondent no. 5], the respondent APDCL authorities informed that they
had invoked the afore-mentioned three Bank Guarantees [IBG113029 dated
25.01.2021, IBG113031 dated 25.01.2021 and IBG113102 dated 27.01.2021] as
the petitioner had failed to fulfill the terms and conditions of the contract and
requested the respondent no. 5 Bank to encash the same and to transfer the
proceeds therefrom in the bank account of the APDCL maintained at New
Guwahati Branch of the State Bank of India. The original copies of the said three
Bank Guarantees were also forwarded with the impugned Letter dated
01.11.2023. A copy of the said impugned Letter dated 01.11.2023 was also
forwarded to the petitioner for his information.
6.1. On receipt of the copy of the impugned Letter dated 01.11.2023 addressed to
him, the petitioner wrote a Letter bearing Reference no. JK/NLP/APDCL/SOLAR
PROJECT/Region-2/L-19 on 02.11.2023 to the respondent no. 4 with the request
to review the decision regarding invocation of the Bank Guarantees and not to
revoke the Bank Guarantees for at least 1 [one] month from 02.11.2023.
Page No. 9/52
6.2. On receipt of the said Letter bearing no. JK/NLP/APDCL/SOLAR PROJECT/Region-
2/L-19 dated 02.11.2023 from the petitioner, the respondent no. 4 wrote to the
respondent no. 5 a Letter bearing no. APDCL/CGM[PP&D]/NRE-146/2019-20/789
on 02.11.2023, referred to in Prayer no. C in the writ petition. By referring to the
said Letter bearing no. JK/NLP/APDCL/SOLAR PROJECT/Region-2/L-19 dated
02.11.2023 of the petitioner wherein the petitioner made the request not to
invoke the Bank Guarantees for at least 1 [one] month, the respondent no. 4
requested the respondent no. 5 to keep the three Bank Guarantees amounting to
Rs. 4,20,00,000/- on hold for a period of 1 [one] month and until further order.
6.3. On 02.11.2023, the petitioner addressed a Letter bearing Reference no.
JK/NLP/APDCL/SOLAR PROJECT/Region-2/L-20 to the Managing Director, APDCL
[the respondent no. 2] with the request to foreclose the contract as areas of land
for the proposed 25MWAC Solar Project in Region-2 could not be arranged. It was
further requested to review the decision of the APDCL to invoke the three Bank
Guarantees.
6.4. It was in the afore-said backdrop, the APDCL through the respondent no. 4
addressed its Letter bearing Reference no. APDCL/CGM[PP&D]/NRE-146/2019-
20/790 to the respondent no. 5 on 06.11.2023. By the said Letter dated
06.11.2023, the respondent no. 4 by referring to his earlier Letter bearing
Reference no. APDCL/CGM[PP&D]/NRE-146/2019-20/789 dated 02.11.2023
whereby the respondent no. 5 was requested to keep the three Bank Guarantees
[IBG113029 dated 25.01.2021, IBG113031 dated 25.01.2021 and IBG113102
dated 27.01.2021] on hold, had informed the respondent no. 5 that his said Letter
bearing Reference no. APDCL/CGM[PP&D]/NRE-146/2019-20/789 dated
02.11.2023 should be treated as cancelled and withdrawn. The respondent no. 5
was thereby requested to proceed as per the earlier instruction given in the Letter
bearing Reference no. APDCL/CGM[PP&D]/NRE-146/2019-20/789 dated
02.11.2023. Meaning thereby, the respondent no. 4 by his Letter dated
06.11.2023 had sought invocation of the three Bank Guarantees with the further
instruction to transfer the proceeds to the concerned bank account of the
Page No. 10/52
respondent APDCL. Though in the writ petition the petitioner has made reference
to and challenged a Letter dated 04.11.2023 stating that by the said Letter, the
respondent APDCL authorities had invoked the Bank Guarantees but no copy of
such Letter dated 04.11.2023, impugned as per the prayers made in the writ
petition, has been brought on the records of the case. By an additional affidavit
filed later, the petitioner has brought the Letter bearing no.
APDCL/CGM[PP&D]/NRE-146/2019-20/790 dated 06.11.2023 on record.
7. Assailing mainly the action on the part of the respondent APDCL authorities to
encash the afore-mentioned three Bank Guarantees [IBG113029 dated
25.01.2021, IBG113031 dated 25.01.2021 and IBG113102 dated 27.01.2021], the
petitioner has instituted the present writ petition by seeking to invoke the extra-
ordinary, discretionary and equitable jurisdiction under Article 226 of the
Constitution of India of this Court for the reliefs/directions, mentioned above.
8. I have heard Mr. K.N. Choudhury, learned Senior Counsel assisted by Mr. J.
Patowary, learned counsel for the petitioner; Mr. I. Chowdhury, learned Senior
Counsel assisted by MR. K.P. Pathak, learned Standing Counsel, APDCL for the
respondent nos. 1 – 4; and Mr. M. Sharma, learned counsel for the respondent
no. 5 Bank.
9. Mr. K.N. Choudhury, learned Senior Counsel appearing for the petitioner has
submitted that despite the petitioner’s earnest endeavour to find around 500
Bighas of land for the Region-2 Project, the same could not be arranged in due
time because of the restrictions in holding such large chunks of land by any
individual/entity under the extant land laws. He has alleged arbitrariness on the
part of the respondent APDCL authorities in seeking to invoke and encash the
Bank Guarantees despite earlier agreeing to provide 1 [one] month time on
02.11.2023 in terms of the petitioner’s request made on 02.11.2023. It is his
submission that Clause 5.7.1 of the Power Purchase Agreement [PPA] has
provided for extension of time on certain grounds in the event the Solar Power
Developer is prevented from achieving the progress within the stipulated time
Page No. 11/52
period. In the case in hand, the petitioner is affected by force majeure and as
such, the agencies of the State ought to have come in aid of the petitioner in
arrangement of required areas of land for the Project. He has, thus, contended
that in such backdrop, the decision on the part of the respondent APDCL
authorities to invoke and encash the Bank Guarantees by the impugned Letters –
dated 01.11.2023 & dated 06.11.2023 – is clearly arbitrary and unjust. If in that
manner the Bank Guarantees are invoked and encashed, the petitioner will suffer
severe loss and the same would cause immense prejudice to the business of the
petitioner. It has further been contended that in a Bank Guarantee, the validity
period and the claim period have to be one and the same ordinarily, unless any
agreement to the contrary. But in the three Bank Guarantees under reference, the
respondent no. 5 Bank had unilaterally incorporated a condition therein, thereby,
extending the claim period by 1 [one] year, beyond the validity period of the Bank
Guarantees. The Bank Guarantees, as per Clause 4.4 of the Power Purchase
Agreement [PPA], were required to be in the format provided in Schedule 3. As
the incorporation of a claim period beyond the validity period in the Bank
Guarantees was at the behest of the respondent no. 5 Bank, behind the back of
the petitioner and without insistence from the respondent APDCL, the respondent
APDCL cannot be permitted to take advantage from such extended claim period.
In addition, a reference has been made to the provisions of Section 28 r/w
Exception 3 thereof of the Indian Contract Act, 1872 [‘the Contract Act’, for short]
to contend and to raise an issue of impermissibility regarding incorporation of
such clause in the Bank Guarantees. As regards the law laid down in respect of
Bank Guarantees, reference has been made to a decision of the Hon’ble Supreme
Court of India, U.P. State Sugar Corporation vs. Sumac International Limited,
reported in [1997] 1 SCC 568.
10. Au contraire, Mr. I. Chowdhury, learned Senior Counsel appearing for the
respondent APDCL authorities has submitted that from the Bank Guarantees, it is
evidently clear that the Bank Guarantees are irrevocable and unconditional ones.
In view of Bank Guarantees of such nature, the ground taken by the petitioner as
regards non-availability of required areas of land to establish the Project in
Page No. 12/52
Region-2 is immaterial. He has contended that since a Bank Guarantee is an
independent contract between the Guarantor Bank and the Beneficiary, that is,
the respondent no. 5 Bank and the APDCL respectively in the case in hand, any
such dispute, even if raised, by the petitioner at whose instance the respondent
no. 5 Bank has provided the Bank Guarantees is of no consequence. It is not the
case of the petitioner that there is either any fraud of an egregious nature or any
irretrievable injustice would occur. In the absence of any such pleas, a writ
petition to restrain invocation and encashment of such Bank Guarantees is not to
be entertained. He has further contended that the Bank Guarantees have
provided for a claim period different from the validity period. It is his submission
that on a reading of the clause which incorporated an extended claim period in
the Bank Guarantees, it is discernible that the same cannot be, by any stretch,
relatable to the provisions of Section 28 and Exception 3 thereof of the Contract
Act. It is his further contention that Exception 3 of Section 28 is in connection
with legal proceedings and not with regard to any claim period. It has been
submitted that it has been a consistent practice of the Banks to incorporate a
claim period in a Bank Guarantee, beyond the validity period of the Bank
Guarantee and there being no illegality, the petitioner who himself had submitted
those Bank Guarantees to the APDCL authorities on 29.01.2021, is precluded from
raising any issue with regard to such Clause regarding extended claim period, that
too, belatedly by feigning ignorance. Mr. Pathak, learned Standing Counsel,
APDCL has placed two decisions – Himadri Chemicals Industries Limited vs. Coal Tar
Refining Company, reported in [2007] 8 SCC 110 and Vinitec Electronics Private
Limited vs. HCL Infosystems Limited, reported in [2008] 1 SCC 544, to buttress the
submissions.
11. Mr. Sharma, learned counsel appearing for the respondent no. 5 Bank has
submitted that there is no legal bar to have one validity period and a different
claim period beyond such validity period, in a Bank Guarantee. He has submitted
that in a Bank Guarantee, it is necessary to provide a claim period, slightly longer
than the validity period of the guarantee. A longer claim period is necessitated for
the reason that if the Principal Debtor commits a default on the last day of the
Page No. 13/52
validity period, then the beneficiary can at the earliest invoke the same only on
the next day. Referring to a circular being Circular no. 10349/CRD/IRMDC34/20-
21 dated 17.06.2020, issued by the Credit Risk Division of the Federal Bank, he
has submitted that thereby, a policy decision has been taken by the respondent
no. 5 Bank to include one year claim period in all guarantees issued by the Bank.
He has submitted that such extended claim period has consistently been
incorporated in Bank Guarantees in view of circulars issued by Indian Banks
Association [IBA]. As per practice prevalent in the banking sector, the claim
period in a Bank Guarantee is a grace period awarded beyond the validity period
of the Bank Guarantee to make a demand on the Guarantor Bank for a default,
which occurred during the validity period of the Bank Guarantee. He has
submitted that though it has been contended that the direction contained in the
circulars issued by the IBA to have a claim period in the Bank Guarantee beyond
the validity period is relatable to Exception 3 of Section 28 of the Contract Act but
in the case in hand, it is the clause in issue in the three Bank Guarantees over
which the parties have crossed swords, is to be read for the purpose of deciding
the issue. He has referred to a decision of the Hon’ble Delhi High Court rendered,
on 28.07.2021, in a writ petition, Writ Petition no. 7677/2019 [Larsen and Toubro
Limited vs. Punjab National Bank and another], wherein the Exception 3 to
Section 28 of the Contract Act came up for consideration. He has also referred to
a decision of the Hon’ble Supreme Court of India in Union of India and another vs.
Indusind Bank Limited and another, reported in [2016] 9 SCC 720.
12. Mr. Choudhury, learned Senior Counsel appearing for the petitioner in his reply
submissions, has submitted that there was no instructions from the petitioner’s
side to incorporate any clause of non-obstante nature for any claim period other
than the agreed validity period, in the Bank Guarantees, which is beyond the
validity period of the Bank Guarantees. He has also contended that the petitioner
was neither a party to the Bank Guarantees nor privy to the said clause at the
time of issuance of the same. It has, thus, been sought to articulate that insertion
of such clause amounts to committing fraud upon the petitioner and the same
Page No. 14/52
would cause irretrievable loss and injury to the petitioner not only to the extent of
the amount involved in the Bank Guarantees but much beyond.
13. I have given due consideration to the rival submissions advanced by the learned
counsel for the parties.
13.1. I have also gone through the materials brought on record by the parties through
their pleadings which are in the forms of [i] the Writ Petition; [ii] an Additional
Affidavit filed, on 07.11.2023, on behalf of the petitioner; [iii] an Affidavit filed, on
21.11.2023, on behalf of the petitioner; [iv] the Affidavit-in-Opposition filed, on
29.11.2023, on behalf of the respondent nos. 1 – 4; [v] an Additional Affidavit
filed, on 10.01.2024, filed on behalf of the respondent nos. 1 – 4; [vi] a synopsis
of written submissions on behalf of the respondent Bank along with a circular
being Circular no. 10349/CRD/IRMDC34/20-21 dated 17.06.2020, issued by the
Credit Risk Division of the Federal Bank; [vii] the Interlocutory Application, I.A.[C]
no. 3499/2023 filed, on 29.11.2023, by the respondent APDCL as applicant
seeking vacation/modification of the Order dated 08.11.2023; [viii] the Affidavit-
in-Opposition filed, on 13.12.2023, on behalf of the petitioner as the opposite
party in I.A.[C] no. 3499/2023; and [ix] the Interlocutory Application, I.A.[C] no.
163/2024 filed, on 18.01.2024, by the respondent APDCL as applicant.
14. As have been mentioned herein above, as per the Bidding Document including the
RFS Document, the Successful Bidder/Solar Power Developer has inter alia been
made responsible for ‘acquisition’ or ‘leasing’ of land, procurement, construction,
erection, testing, synchronizing, commissioning, operating and maintaining the
Region-2 Project on ‘Build-Own-Operate’ basis. As per Clause 1.5 : ‘Site
Identification and Land Acquisition’ of the RFS Document, the Project land shall
have to be arranged by the Successful Bidder/Solar Power Developer. At the time
of submission of Bid, a bidder was required to provide evidence that the required
Land for project development @ 2 Ha/MWAC was under clear possession of the
bidder whereon the bidder would install the required capacity. For ready
Page No. 15/52
reference, Clause 1.5 : ‘Site Identification and Land Acquisition’ of the RFS is
quoted herein below :-
1.5. Site Identification and Land Acquisition
The Project Land shall be arranged by the SPD in the region as mentioned in
clause 1.1.1. At the time of submission of bid, the bidder would provide
evidence that the required Land for project development @ 2 ha/MW is
under clear possession of the bidder which the bidder wishes to install the
required capacity.
In this regard the Bidder shall be required to furnish the following
documentary evidence :-
1.5.1. Identification of 100% [hundred per cent] land at the time of bid
submission. Within 12 months of the effective date of the PPA,
submission of documents/Lease Agreement to establish
possession/right to use 100% [hundred per cent] of the required land
in the name of the SPD or its Affiliate. In case the land is in the name of
Affiliate, the land should be transferred in the name of SPD prior to
Scheduled Commissioning Date [SCD].
RFS for Procurement of 25 MW [AC] Solar Power from projects to be
developed in Region – 3 through Competitive Bidding Process
[Followed by E-Reverse Action]
In case of identification of 100% land at the time of submission of Bid,
following documentary evidence has to be submitted by the bidder :
[i] General Declarations and Undertaking [Appendix – X]
[ii] Memorandum of Undertaking [Appendix – XI]
1.5.2. Wherever leasing of private land is involved, the lease should allow
transfer of land to the lenders or Procurer, in case of default of the
SPD.
Page No. 16/52
1.5.3. Requisite documents from the concerned and competent
revenue/registration authority for the acquisition/ownership/vesting
of land in the name of SPD and in case private land converted for
industrial use.
In case of non-availability of land with the bidder at the time of submission
of Bid, an undertaking has to be submitted that the documentary evidence
will be produced by the bidder of the availability of the land within 12
[twelve] months of signing of PPA. The undertaking can be provided in the
Appendix – IX.
Note :
a. Change in the location of land for setting up the project from one place
to other location is not permitted after 12 months from the signing of
PPA or at financial closure, whichever is earlier.
b. The land for setting up the project should be free from all
encumbrances.
c. The land should neither have been proposed for other purposes & nor
should have been mortgaged.
14.1. Clause 1.3 : ‘Commissioning, Part Commissioning and Delay in Commissioning of
the Project’ of the RFS has mentioned about the period within which the
concerned Project like the Region-2 Project is to be commissioned. For the
purpose of easy reference, the contents of Clause 1.3 are also extracted herein
below :-
1.3. Commissioning, Part Commissioning and Delay in Commissioning
of the Projects
1.3.1. Commissioning
The Successful Bidders shall be required to sign PPAs with APDCL which shall
form the part of the Project Agreements.
Page No. 17/52
The Projects shall be Commissioned within a maximum period of 18
[eighteen] Months [“Scheduled Commissioning Period”] from Date of
Execution of PPA [as defined out in PPA], which is termed as the ‘Scheduled
COD’.
Delay in Project Commissioning, beyond the date of Scheduled COD shall
involve imposition of Delay Liquidated Damages on the Solar Power
Developer, as detailed out in PPA. The Solar Power Developer shall be
permitted to achieve the Project COD, even prior to the Scheduled COD; in
such cases, APDCL shall purchase the generated energy at PPA Tariff only.
1.3.2. Part Commissioning
A Solar Power Developer can be allowed to achieve Part Commissioning of a
Project awarded to it by commissioning a threshold capacity of 15 MW and
can achieve further Part Commissioning in minimum steps of 5 MW till full
Commissioning of the Project is achieved, subject to the acceptance by
APDCL. However, the Scheduled COD shall not get altered due to Part
Commissioning of the Project. Irrespective of dates of Part Commissioning,
the PPA shall remain in force for the PPA Term only. The Solar Power
Developer shall be permitted to achieve the Part Commissioning for the
Project only prior to the Scheduled COD.
In cases of Part Commissioning, till Project COD, the purchase of such solar
energy generation shall be settled by APDCL, as per the provisions mentioned
in the PPA.
1.3.3. Early Commissioning
The SPD shall be permitted for full commissioning as well as part
commissioning of the Project even prior to the SCD. In case of early part –
commissioning, till SCD, APDCL may purchase generation RFS for
Procurement of 25 MW [AC] Solar Power from projects to be developed in
Page No. 18/52
Region – 3 through Competitive Bidding Process [Followed by E – Reverse
Auction] till SCD, at 75% [seventy – five percent] of the PPA tariff. However,
in case the entire capacity is commissioned prior to SCD, APDCL may
purchase generation at PPA tariff.
1.3.4. Delay in Commissioning
As per draft PPA,
Failure to achieve the Project COD on or before the Scheduled COD by the
Bidder shall attract encashment and invocation of Performance Security
followed by imposition of Delay Liquidated Damages, as mentioned below :-
Delay up to one [1] Month from SCOD Twenty percent [20%] of the Performance
Security
Delay of more than one [1] Month and
up to two [2] Months from SCOD
Forty percent [40%] of the Performance
Security
Delay of more than two [2] Months and
up to three [3] Months from SCOD
Forty percent [40%] of the Performance
Security
In case the achievement of Project COD is delayed beyond three [3] Months
from the date of Scheduled COD; the tariff discovered after reverse auction
shall be reduced at the rate of INR 0.15/kWh [0.5 Paisa per unit] per day of
delay for the delay in such remaining capacity which is not commissioned
subject to a maximum period of 30 days. The maximum time period allowed
for commissioning of the full Project Capacity with encashment of
Performance Bank Guarantee and reduction in the fixed tariff shall be limited
to 22 months from the Date of execution of PPA [as defined in the Draft PPA];
in case of further delay in achieving the Project COD beyond twenty-two [22]
Months period from Execution Date [as defined in the Draft PPA] would
amount to termination of PPA. The normative CUF of 19% [nineteen per cent]
or committed CUF, whichever is lower shall be taken for the purpose of
calculation of generation loss as well as reduced tariff.
Page No. 19/52
15. In the writ petition, the petitioner has averred that as per the land laws of Assam,
an individual cannot possess 500 Bighas of land and since the petitioner did not
possess 500 Bighas of land at the time of submission of his bid, he had to submit
an undertaking to make available the areas of land required for the Region-2
Project. The petitioner has stated that the petitioner made a request to the Assam
Industrial Development Corporation [AIDC] Limited to allot 500 Bighas of land to
him for the Project. But the AIDC Limited vide its Letter dated 02.11.2021
informed the petitioner to the effect that it did not have any such land for
allotment in the districts of Goalpara, Bongaigaon, Barpeta, Nalbari, Kamrup –
Metro and Kamrup – Rural. The petitioner was also informed by the AIDC Limited
that the petitioner could apply for allotment of land at other locations of the AIDC
Limited in Assam. The petitioner has further stated that vide his Letter dated
03.11.2021, the petitioner had informed the respondent no. 4 to the effect that
though he had identified private patta lands but the land owners refused to sell
those lands. By informing about the inability of the AIDC Limited to allot required
areas of land for the Region-2 Project in the districts mentioned above, the
petitioner through his Letter dated 03.11.2021 requested the respondent APDCL
authorities either to arrange for the areas of land required for the Region-2
Project or to change the Region of the petitioner, that is, Region-2 so as to enable
him to search for land for the Project at other locations. The petitioner has further
averred that despite his sincere endeavour to find 500 Bighas of land for
establishing the Project in Region-2, no positive result yielded. When the
petitioner was served with the Show Cause Notice dated 28.12.2022, the
petitioner once again brought the matter of non-availability of land in Region-2 in
his Reply dated 05.01.2023. It was in such obtaining fact situation, the impugned
Letter bearing no. APDCL/CGM[PP&D]/NRE-146/2019-20/787 dated 01.11.2023
was issued by the respondent no. 4 mentioning default on the part of the
petitioner. The petitioner has challenged the decision taken by the respondent
APDCL authorities to invoke the three Bank Guarantees in such manner as
arbitrary and unjust. The petitioner has contended that when the extant Laws of
the State do not allow an individual/entity to possess an area of 500 Bighas of
land, it becomes the responsibility of the State agencies to come in aid of the
Page No. 20/52
petitioner to provide such large areas like 500 Bighas of land to enable the
petitioner to fulfill the prescription contained in Clause 1.5 of the RFS Document.
16. The matters regarding ‘acquisition’ or ‘leasing’ of land for the projects in various
Regions including Region-2, have been delineated in the Bidding Document
comprising of Volume-I : Request for Selection [RFS] and Volume-II : Power
Purchase Agreement [PPA]. From Clause 1.5 of the RFS Document, it is clear that
the responsibility to arrange for the areas of land required to construct and
commission the Region-2 Project, that is, 25 MWAC Grid Connected Solar
Photovoltaic Project on ‘Build-Own-Operate’ basis was entirely of the Successful
Bidder/Solar Power Developer. As per the definition provided in the RFS, ‘COD’,
with respect to the Project/unit shall mean the date on which the project/unit is
commissioned [certified by RLDC/SLDC/DISCOM] and available for commercial
operation and such date as specified in a written notice given at least 10 days in
advance by the power producer to APDCL. As per Clause 1.3.4 : ‘Delay in
Commissioning’, failure to achieve the Project COD on or before the scheduled
COD by the bidder shall attract encashment and invocation of Performance
Security followed by imposition of Delay Liquidated Damages. It was stipulated in
Clause 7.1.4. of the RFP Document to the effect that if a bidder was declared as
the Successful Bidder, then the Bid Security of such Successful Bidder was to be
returned upon signing the Power Purchase Agreement [PPA] with the APDCL and
submission of the Performance Security or Performance Guarantee or equivalent
in the form of Bank Guarantees, in accordance with the timelines and provisions
mentioned in the Project Power Purchase Agreement [PPA].
17. In the Show Cause Notice issued on 28.12.2022, it was reiterated that the Letter
of Award [LoA] was issued for the Region-2 Project, that is, 25 MWAC Grid
Connected Solar Photovoltaic Project on 04.01.2021. It was further brought to the
notice of the petitioner that by its Order dated 09.11.2021, the Assam Electricity
Regulatory Commission [AERC] had provisionally approved the Tariff @ Rs. 3.99
per unit for the Region-2 Project for a period of 5 [five] years subject to the
conditions that [i] the possession of land by the Successful Bidder/Solar Power
Page No. 21/52
Developer should be completed within 3 [three] months from the date of the
Order; and [ii] the APDCL shall monitor fortnightly and documentary evidence of
possession of land shall be submitted to the AERC within the period allowed, else
the approval shall stand cancelled. The Show Cause Notice had further mentioned
that despite repeated reminders and despite elapse of more than 23 [twenty
three] months from the date of acceptance of the Letter of Award [LoA] the
petitioner was not able to submit any documentary evidence in respect of the
petitioner’s possession of land for the Region-2 Project. The petitioner was
informed that such situation had given rise a situation for the APDCL to take
necessary action against the petitioner by way of termination of the contract by
declaring him as a non-performer and also by invoking the Bank Guarantees
amounting to Rs. 4,20,00,000/- furnished towards Performance Security. The
petitioner was thereby, asked to show cause by 31.12.2022 as to [i] why the
contract shall not be terminated; [ii] why the petitioner should not be declared as
non-performer; [iii] why the petitioner should not be debarred for 3 [three] years
from participating in any future bid of the APDCL; and [iv] why Security Deposit
submitted against the Region-2 Project should not be encashed/invoked. The
petitioner in his Reply to the Show Cause Notice submitted on 05.01.2023,
mentioned about non availability of land and also about escalation of costs, in the
meantime.
18. The matters regarding Performance Security, Appropriation of Performance
Security and Release of Performance Security are also specifically set forth in
Clause 4.4[a] : ‘Performance Security’, Clause 4.4[b] : ‘Appropriation of
Performance Security’ and Clause 4.4[c] : ‘Release of Performance Security’ in the
following manner :-
4.4. Performance Security
[a] For due and punctual performance of its obligations under this
Agreement, relating to the Project, the Solar Power Developer has
delivered to APDCL, simultaneously with the execution of this
Agreement, an irrevocable and unconditional bank guarantees from a
scheduled bank acceptable to APDCL for an amount of INR
Page No. 22/52
42000000.00 [Rupees Four Crore and Twenty Lakh only]
[“Performance Security”], calculated as INR 16,80,000/- [Indian Rupees
Sixteen Lakh Eighty Thousand only] per MW basis. The Performance
Security is furnished to APDCL in the form of three [3] Bank Guarantees
in favor of “Chief General Manager [Comm. & EE]” of APDCL as per the
format provided in Schedule 3 and having validity up to twenty two [22]
months from the Date of Signing of PPA. The details of the bank
guarantees furnished towards the Performance Security are given below
:
[i] Bank Guarantee No. IBG113029 dated 25.01.2021 for an amount of
INR 84,00,000.00 [Rupees Eighty Four Lakh] [This amount shall
be equivalent to 20% of total Performance Security]
[ii] Bank Guarantee No. IBG113031 dated 25.01.2021 for an amount of
INR 1,68,00,000.00 [Rupees One Crore Sixty Eight Lakh only] This
amount shall be equivalent to 40% of total Performance Security]
[iii] Bank Guarantee No. IBG113102 dated 27.01.2021 for an amount of
INR 1,68,00,000.00 [Rupees One Crore Sixty Eight Lakh only]
[This amount shall be equivalent to 40% of total Performance
Security]
[b] Appropriation of Performance Security
Upon occurrence of a Solar Power Developer Default or failure to meet
the Conditions Precedent by the Solar Power Developer, APDCL shall,
without prejudice to its other rights and remedies hereunder or in law,
shall be entitled to encash and appropriate the relevant amounts from
the Performance Security as Damages for such Solar Power Developer
Default or Conditions Precedent. Upon such encashment and
appropriation from the Performance Security, the Solar Power
Developer shall, within 30 [thirty] days thereof, replenish, in case of
partial appropriation, to its original level the Performance Security, and
in case of appropriation of the entire Performance Security provide a
fresh Performance Security, as the case may be, and the Solar Power
Developer shall, within the time so granted, replenish or furnish fresh
Performance Security as aforesaid failing which APDCL shall be entitled
Page No. 23/52
to terminate this Agreement in accordance with Article 16. Any penalty
paid so, shall be returned to the SPD without any interest on
achievement of successful commissioning within the SCD.
[c] Release of Performance Security
Subject to other provisions of this Agreement, APDCL shall release the
Performance Security, if any after eighteen [18] from the Scheduled
Commissioning Date.
The release of the Performance Security shall be without prejudice to
other rights of APDCL under this Agreement.
19. From the above Clauses in the Power Purchase Agreement [PPA], also found
similarly mentioned in the RFS document and the Draft Power Purchase
Agreement [PPA], it is clear that the Bank Guarantees are to be submitted in the
format provided in Schedule 3 and such Bank Guarantees should have validity
upto 22 [twenty-two] months from the date of signing of the Power Purchase
Agreement [PPA]. Discretion has been vested to the APDCL to encash and
appropriate the relevant amounts from such Performance Security as Damages
upon occurrence of Default on the part of the Successful Bidder/Solar Power
Developer or in the event of failure to meet the Conditions Precedents by the
Successful Bidder/Solar Power Developer, without prejudice to the APDCL’s other
rights and remedies under or in law.
20. The law regarding Bank Guarantee/Letter of Credit are well settled by a series of
judgments of the Hon’ble Supreme Court of India and of this Court. In order to
appreciate the law regarding the nature of Bank Guarantees, their invocation and
in what situations the Court can pass an order of injunction/stay restraining
encashment of a Bank Guarantee/Letter of Credit, the following decisions of the
Hon’ble Supreme Court of India can be referred to.
20.1. In U.P. State Sugar Corporation vs. Sumac International Limited, reported in [1997] 1
SCC 568, it has been observed as under :-
Page No. 24/52
12. The law relating to invocation of such bank guarantees is by now well settled.
When in the course of commercial dealings an unconditional bank guarantee
is given or accepted, the beneficiary is entitled to realize such a bank
guarantee in terms thereof irrespective of any pending disputes. The bank
giving such a guarantee is bound to honour it as per its terms irrespective of
any dispute raised by its customer. The very purpose of giving such a bank
guarantee would otherwise be defeated. The courts should, therefore, be slow
in granting an injunction to restrain the realization of such a bank guarantee.
The courts have carved out only two exceptions. A fraud in connection with
such a bank guarantee would vitiate the very foundation of such a bank
guarantee. Hence if there is such a fraud of which the beneficiary seeks to
take advantage, he can be restrained from doing so. The second exception
relates to cases where allowing the encashment of an unconditional bank
guarantee would result in irretrievable harm or injustice to one of the parties
concerned. Since in most cases payment of money under such a bank
guarantee would adversely affect the bank and its customer at whose
instance the guarantee is given, the harm or injustice contemplated under
this head must be of such an exceptional and irretrievable nature as would
override the terms of the guarantee and the adverse effect of such an
injunction on commercial dealings in the country. The two grounds are not
necessarily connected, though both may co-exist in some cases. In the case of
U.P. Cooperative Federation Ltd. vs. Singh Consultants and Engineers [P]
Ltd., [1988] 1 SCC 174, which was the case of a works contract where the
performance guarantee given under the contract was sought to be invoked,
this Court, after referring extensively to English and Indian cases on the
subject, said that the guarantee must be honoured in accordance with its
terms. The bank which gives the guarantee is not concerned in the least with
the relations between the supplier and the customer; nor with the question
whether the supplier has performed his contractual obligation or not, nor
with the question whether the supplier is in default or not. The bank must
pay according to the tenor of its guarantee on demand without proof or
condition. There are only two exceptions to this rule. The first exception is a
case when there is a clear fraud of which the bank has notice. The fraud must
Page No. 25/52
be of an agregious nature such as to vitiate the entire underlying transaction.
Explaining the kind of fraud that may absolve a bank from honouring its
guarantee, this Court in the above case quoted with approval the
observations of Sir John Donaldson, M.R. in Bolivinter Oil SA vs. Chase
Manhattan Bank NA, [1984] 1 AIIER 351 :
“The wholly exceptional case where an injunction may be granted is
where it is proved that the bank knows that any demand for payment
already made or which may thereafter be made will clearly be
fraudulent. But the evidence must be clear both as to the fact of fraud
and as to the bank’s knowledge. It would certainly not normally be
sufficient that this rests on the uncorroborated statement of the
customer, for irreparable damage can be done to a bank’s credit in the
relatively brief time which must elapse between the granting of such an
injunction and an application by the bank to have it charged".
This Court set aside an injunction granted by the High Court to restrain the
realisation of the bank guarantee.
13. The same question came up for consideration before this Court in Svenska
Handelsbanken vs. M/s. Indian Charge Chrome & Others, [1994] 1 SCC
502. This Court once again reiterated that a confirmed bank
guarantee/irrevocable letter of credit cannot be interfered with unless there
is established fraud or irretrievable injustice involved in the case.
Irretrievable injury has to be of the nature noticed in the case of Itek
Corporation vs. The First National Bank of Boston etc., 566 Fed Supp 1210.
On the question of fraud this Court confirmed the observations made in the
case of U.P. Cooperative Federation Ltd. [supra] and stated that the fraud
must be that of the beneficiary, and not the fraud of anyone else.
20.2. In Himadri Chemicals Industries Limited vs. Coal Tar Refining Company, reported in
[2007] 8 SCC 110, it has been observed as under :-
Page No. 26/52
10. The law relating to grant or refusal to grant injunction in the matter of
invocation of a bank guarantee or a letter of credit is now well settled by a
plethora of decisions not only of this Court but also of the different High
Courts in India. In U.P. State Sugar Corporation vs. Sumac International
Ltd., [1997] 1 SCC 568, this court considered its various earlier decisions. In
this decision, the principle that has been laid down clearly on the
enforcement of a Bank guarantee or a letter of credit is that in respect of a
bank guarantee or a letter of credit which is sought to be encashed by a
beneficiary, the bank giving such a guarantee is bound to honour it as per its
terms irrespective of any dispute raised by its customer. Accordingly this
Court held that the courts should be slow in granting an order of injunction
to restrain the realization of such a bank guarantee. It has also been held by
this Court in that decision that the existence of any dispute between the
parties to the contract is not a ground to restrain the enforcement of bank
guarantees or letters of credit. However this Court made two exceptions for
grant of an order of injunction to restrain the enforcement of a bank
guarantee or a letter of credit : [i] Fraud committed in the notice of the bank
which would vitiate the very foundation of guarantee; and [ii] injustice of the
kind which would make it impossible for the guarantor to reimburse himself.
11. Except under these circumstances, the courts should not readily issue
injunction to restrain the realization of a bank guarantee or a letter of credit.
So far as the first exception is concerned, i.e. of fraud, one has to satisfy the
court that the fraud in connection with the bank guarantee or letter of credit
would vitiate the very foundation of such a bank guarantee or letter of credit.
So far as the second exception is concerned, this court has held in that
decision that it relates to cases where allowing encashment of an
unconditional bank guarantee would result in irretrievable harm or injustice
to one of the parties concerned. While dealing with the case of fraud, this
court in the case of U.P. Coop. Federation Ltd. vs. Singh Consultants and
Engineers [P] Ltd., [1988] 1 SCC 174, held as follows : [SCC p. 197, para 53]
The fraud must be of an egregious nature such as to vitiate the entire
underlying transaction.
Page No. 27/52
[Emphasis supplied]
While coming to a conclusion as to what constitutes fraud, this court in the
above case quoted [at SCC p. 197, para 54] with approval the observations of
Sir John Donaldson, M.R. in Bolivinter Oil SA vs. Chase Manhattan Bank,
[1984] 1 All ER 351 [CA], at p. 352g-h, which is as follows :
The wholly exceptional case where an injunction may be granted is
where it is proved that the bank knows that any demand for payment
already made or which may thereafter be made will clearly be
fraudulent. But the evidence must be clear both as to the fact of fraud
and as to the bank’s knowledge. It would certainly not normally be
sufficient that this rests on the uncorroborated statement of the
customer, for irreparable damage can be done to a bank’s Credit in the
relatively brief time which must elapse between the granting of such an
injunction and an application by the bank to have it discharged.
[Emphasis supplied]
12. In Svenska Handelsbanken vs. Indian Charge Chrome, [1994] 1 SCC 502, it
has also been held that a confirmed bank guarantee/irrevocable letter of
credit cannot be interfered with unless there is established fraud or
irretrievable injustice involved in the case. In fact, on the question of fraud,
this decision approved the observations made by this court in the case of
U.P. Coop. Federation Ltd vs. Singh Consultants and Engineers [P] Ltd.,
[1988] 1 SCC 174.
* * * * * * * * *
14. From the discussions made hereinabove relating to the principles for grant
or refusal to grant of injunction to restrain enforcement of a Bank Guarantee
or a Letter of Credit, we find that the following principles should be noted in
the matter of injunction to restrain the encashment of a Bank Guarantee or a
Letter of Credit :-
Page No. 28/52
[i] While dealing with an application for injunction in the course of
commercial dealings, and when an unconditional bank guarantee or
letter of credit is given or accepted, the beneficiary is entitled to realize
such a bank guarantee or a letter of credit in terms thereof irrespective of
any pending disputes relating to the terms of the contract.
[ii] The bank giving such guarantee is bound to honour it as per its terms
irrespective of any dispute raised by its customer.
[iii] The Courts should be slow in granting an order of injunction to restrain
the realization of a bank guarantee or a letter of credit.
[iv] Since a bank guarantee or a letter of credit is an independent and a
separate contract and is absolute in nature, the existence of any dispute
between the parties to the contract is not a ground for issuing an order of
injunction to restrain enforcement of bank guarantees or letters of
credit.
[v] Fraud of an egregious nature which would vitiate the very foundation of
such a bank guarantee or letter of credit and the beneficiary seeks to take
advantage of the situation.
[vi] Allowing encashment of an unconditional bank guarantee or a letter of
credit would result in irretrievable harm or injustice to one of the parties
concerned.
20.3. The following observations are made in Vinitec Electronics Private Limited vs. HCL
Infosystems Limited, reported in [2008] 1 SCC 544 :
2. The dispute between the parties relates to invocation of the bank guarantee
furnished by the appellant to the respondent.
* * * * * * * * *
12. It is equally well settled in law that bank guarantee is an independent contract
between bank and the beneficiary thereof. The bank is always obliged to
honour its guarantee as long as it is an unconditional and irrevocable one. The
dispute between the beneficiary and the party at whose instance the bank has
given the guarantee is immaterial and of no consequence. In BSES Limited
Page No. 29/52
[Now Reliance Energy Ltd.] vs. Fenner India Limited and another, [2006] 2
SCC 728, this court held :
“10. There are, however, two exceptions to this Rule. The first is when there is a
clear fraud of which the Bank has notice and a fraud of the beneficiary
from which it seeks to benefit. The fraud must be of an egregious nature as
to vitiate the entire underlying transaction. The second exception to the
general rule of non-intervention is when there are special equities in
favour of injunction, such as when irretrievable injury or irretrievable
injustice would occur if such an injunction were not granted. The general
rule and its exceptions has been reiterated in so many judgments of this
court, that in U.P. State Sugar Corporation. vs. Sumac International
Ltd., [1997] 1 SCC 568 [hereinafter U.P. State Sugar Corporation], this
Court, correctly declared that the law was ‘settled’.
* * * * * * * * *
14. In Mahatama Gandhi Sahakra Sakkare Karkhane vs. National Heavy Engg.
Coop. Ltd and another, [2007] 6 SCC 417, this Court observed [SCC p. 471 b-d]
:-
“If the bank guarantee furnished is an unconditional and irrevocable
one, it is not open to the bank to raise any objection whatsoever to pay
the amounts under the guarantee. The person in whose favour the
guarantee is furnished by the bank cannot be prevented by way of an
injunction from enforcing the guarantee on the pretext that the
condition for enforcing the bank guarantee in terms of the agreement
entered between the parties has not been fulfilled. Such a course is
impermissible. The seller cannot raise the dispute of whatsoever nature
and prevent the purchaser from enforcing the bank guarantee by way of
injunction except on the ground of fraud and irretrievable injury.
What is relevant are the terms incorporated in the guarantee executed by
the bank. On careful analysis of the terms and conditions of the
guarantee in the present case, it is found that the guarantee is an
unconditional one. The respondent, therefore, cannot be allowed to raise
Page No. 30/52
any dispute and prevent the appellant from encashing the bank
guarantee. The mere fact that the bank guarantee refers to the principal
agreement without referring to any specific clause in the preamble of the
deed of guarantee does not make the guarantee furnished by the bank to
be a conditional one.”
[Emphasis Supplied]
21. It has been set forth in Clause 4.4 : ‘Performance Security’ of the Draft Power
Purchase Agreement [PPA] that the Successful Bidder had to furnish the
Performance Security in the form of three Bank Guarantees in favour of the
APDCL as per the format provided in Schedule 3 thereof. Since the format
provided in Schedule 3 is also of import in the lis, the format in Schedule 3 is
extracted hereinbelow in its entirety :-
SCHEDULE 3
PERFORMANCE SECURITY
[PROFORMA OF BANK GUARANTEE]
THIS DEED OF GUARANTEE executed on this the ________________ day
of _________________ at ______________ by _________________
[Name of the Bank] having its Head / Registered office at ______________
hereinafter referred to as “the Guarantor” which expression shall unless it be
repugnant to the subject or context thereof include successors and assigns;
In favour of ________, a Company Incorporated under the Indian Companies
Act, 1956 having its registered office at __________ [hereinafter referred to as
“APDCL”, which expression shall, unless it be repugnant to the context or
meaning thereof, include its administrators, successors, and assigns];
WHEREAS
A. By the Power Purchase Agreement [the "Agreement"] being entered into
between APDCL and __________, a company incorporated under the
provisions of the Companies At, 1956/, having its registered office/permanent
Page No. 31/52
address at _______________ [hereinafter referred as “Solar Power
Developer”], has been granted the right to development of _____________
MW Solar PV Power Plant an hereinafter referred to as the Project.
B. In terms of Article 4.4 of the Agreement, the Solar Power Developer is
required to furnish to APDCL, an unconditional and irrevocable bank
guarantee for an amount of INR ___________/- [Rupees ________ Only]
as security for due and punctual performance/discharge of its obligations
under the Agreement.
At the request of the Solar Power Developer, the Guarantor has agreed to provide
guarantee, being these presents guaranteeing the due and punctual
performance/discharge by the Company of its obligations under the Agreement
relating to the Project.
NOW THEREFORE THIS DEED WITNESSETH AS FOLLOWS:
Capitalized terms used herein but not defined shall have the meaning assigned to
them respectively in the Agreement.
1. The Guarantor hereby irrevocably guarantees the due and punctual
performance by M/s. ____________ of all its obligations relating to the
Project under the Agreement.
2. The Guarantor as primary obligator shall, without demur, pay to APDCL
sums not exceeding in aggregate INR _______/- [Rupees ________ Only),
within one working day of receipt of a written demand thereof from APDCL
stating that the Solar Power Developer has failed to meet its performance
obligations under the Agreement. The Guarantor shall not go into the veracity
of any breach or failure on the part of the Solar Power Developer or validity of
demand so made by APDCL and shall pay the amount specified in the
demand notwithstanding any direction to the contrary given or any dispute
whatsoever raised by the Solar Power Developer or any other Person. The
Guarantor's obligations hereunder shall subsist until all such demands are
duly met and discharged in accordance with the provisions hereof. In order to
Page No. 32/52
give effect to this Guarantee, APDCL shall be entitled to treat the Guarantor
as the principal debtor. The obligations of the Guarantor shall not be affected
by any variations in the terms and conditions of the Agreement or other
documents or by the extension of time for performance granted to the
Company or postponement/non exercise/ delayed exercise of any of its rights
by APDCL or any Indulgence shown by APDCL to the Solar Power Developer
and the Guarantor shall not be relieved from its obligations under this
Guarantee on account of any such variation, extension, postponement, non-
exercise, delayed exercise of any of its rights by APDCL or any indulgence
shown by APDCL provided nothing contained herein shall enlarge the
Guarantor's obligation hereunder.
3. This Guarantee shall be irrevocable and shall remain in full force and effect
for a period of twenty-two [22] months from the date of signing of PPA unless
discharged /released earlier by APDCL on accordance with the provisions of
the Agreement. The Guarantor's liability in aggregate is limited to a sum of
INR ______/- (Rupees ________ Only).
4. This Guarantee shall not be affected by any change in the constitution or
winding up of the Solar Power Developer/the Guarantor or any absorption,
merger or amalgamation of the Solar Power Developer/the Guarantor with
any other Person.
The Guarantor has power to issue this guarantee and discharge the obligations
contemplated herein, and the undersigned Is duly authorized to execute this
Guarantee pursuant to the power granted under____________.
IN WITNESS WHEREOF THE GUARANTOR HAS SET ITS HANDS
HEREUNTO ON THE DAY, MONTH AND YEAR FIRST HEREINABOVE
WRITTEN
SIGNED AND DELIVERED
by __________ Bank
Page No. 33/52
by the hand of Shri _________ its _____ and
Authorised official.
22. As is stated above, it was on 29.01.2021 the petitioner submitted the three nos.
of Bank Guarantees for amounts, indicated in paragraph 5.1 above, to the
respondent APDCL in the format provided in Schedule 3. As the contestation of
the parties is with regard to the said three Bank Guarantees, which are similarly
worded, save and except a difference in the validity period, it is also apposite to
extract the contents of one of such Bank Guarantees hereinbelow :-
SCHEDULE 3
PERFORMANCE SECURITY
[PROFORMA OF BANK GUARANTEE]
THIS DEED OF GUARANTEE executed on this the 25
th
day of January, 2021 at
Jorhat by The Federal Bank Ltd., M.G. Road, Jorhat-785001 of India having its
Head / Registered office at Aluva, Kerala. Hereinafter referred to as “the
Guarantor” which expression shall unless it be repugnant to the subject or
context thereof include successors and assigns;
In favour of Assam Power Distribution Company Limited a Company
Incorporated under the Indian Companies Act, 1956 having its registered office
at _____ [hereinafter referred to as “APDCL”, which expression shall, unless it
be repugnant to the context or meaning thereof, include its administrators,
successors, and assigns];
WHEREAS
A. By the Power Purchase Agreement [the "Agreement"] being entered into
between APDCL and Jayanta Khaund a company incorporated under the
provisions of the Companies At, 1956/, having its registered office/permanent
address at K.B. Road, North Lakhimpur, Assam [hereinafter referred as
Page No. 34/52
“Solar Power Developer”, has been granted the right to development of MW
Solar PV Power Plant an hereinafter referred to as the Project.
B. In terms of Article 4.4 of the Agreement, the Solar Power Developer is
required to furnish to APDCL, an unconditional and irrevocable bank
guarantee for an amount of INR 84,00,000/- [Rupees Eighty Four Lakhs
Only] as security for due and punctual performance/discharge of its
obligations under the Agreement.
At the request of the Solar Power Developer, the Guarantor has agreed to provide
guarantee, being these presents guaranteeing the due and punctual
performance/discharge by the Company of its obligations under the Agreement
relating to the Project.
NOW THEREFORE THIS DEED WITNESSETH AS FOLLOWS:
Capitalized terms used herein but not defined shall have the meaning assigned to
them respectively in the Agreement.
1. The Guarantor hereby irrevocably guarantees the due and punctual
performance by Jayanta Khound of all its obligations relating to the Project
under the Agreement.
2. The Guarantor as primary obligator shall, without demur, pay to APDCL
sums not exceeding in aggregate INR 84,00,000/- [Rupees Eighty Four
Lakhs Only), within one working day of receipt of a written demand thereof
from APDCL stating that the Solar Power Developer has failed to meet its
performance obligations under the Agreement. The Guarantor shall not go
into the veracity of any breach or failure on the part of the Solar Power
Developer or validity of demand so made by APDCL and shall pay the amount
specified in the demand notwithstanding any direction to the contrary given
or any dispute whatsoever raised by the Solar Power Developer or any other
Person. The Guarantor's obligations hereunder shall subsist until all such
demands are duly met and discharged in accordance with the provisions
hereof. In order to give effect to this Guarantee, APDCL shall be entitled to
Page No. 35/52
treat the Guarantor as the principal debtor. The obligations of the Guarantor
shall not be affected by any variations in the terms and conditions of the
Agreement or other documents or by the extension of time for performance
granted to the Company or postponement/non exercise/delayed exercise of
any of its rights by APDCL or any Indulgence shown by APDCL to the Solar
Power Developer and the Guarantor shall not be relieved from its obligations
under this Guarantee on account of any such variation, extension,
postponement, non-exercise, delayed exercise of any of its rights by APDCL
or any indulgence shown by APDCL provided nothing contained herein shall
enlarge the Guarantor's obligation hereunder.
3. This Guarantee shall be irrevocable and shall remain in full force and effect
for a period of twenty two [22] months from the date of signing of PPA unless
discharged/released earlier by APDCL on accordance with the provisions of
the Agreement. The Guarantor's liability in aggregate is limited to a sum of
INR 84,00,000/- (Rupees Eighty Four Lakhs Only).
4. This Guarantee shall not be affected by any change in the constitution or
winding up of the Solar Power Developer/the Guarantor or any absorption,
merger or amalgamation of the Solar Power Developer/the Guarantor with
any other Person.
The Guarantor has power to issue this guarantee and discharge the obligations
contemplated herein, and the undersigned is duly authorized to execute this
Guarantee pursuant to the power granted under APDCL.
Notwithstanding anything to the contrary contained herein –
[i] Our Liability under this Guarantee shall not exceed Rs. 84,00,000/-
[Rupees Eighty Four Lakhs Only].
[ii] This Bank Guarantee shall be valid upto 24.01.2023.
[iii] We are liable to pay the guarantee amount only and only if we receive
from you at our address stated below, a written claim or demand no
later than 1 Year from the said expiry, failing which all your rights
under this guarantee shall extinguish and we shall stand completely
discharged.
Page No. 36/52
[Emphasis supplied in bold]
Address for service of Claim/Demand :
The Federal Bank Limited
Operations Department Trade Finance Division,
Fed Serv, 4
th
Floor, Thapasya Building, Infopark,
Kakkanad, Ernakulam, Kerala, India – 682042
IN WITNESS WHEREOF THE GUARANTOR HAS SET ITS HANDS
HEREUNTO ON THE DAY, MONTH AND YEAR FIRST HEREINABOVE
WRITTEN
SIGNED AND DELIVERED
By ____________ Bank
By the hand of Shri _________ its ______ and
Sd/- Illegible
Authorised Official.
Signature and Seal.
23. At this stage, it is apposite to find out about the nature of the three Bank
Guarantees submitted by the petitioner. Each of the Bank Guarantees mention
that in terms of Article 4.4 of the Agreement [that is, the Power Purchase
Agreement (PPA)], the Solar Power Developer is required to furnish to the APDCL,
an unconditional and irrevocable Bank Guarantees for a definite amount as
security for due and punctual performance/discharge of its obligations under the
Agreement. The Bank Guarantees also mention that the respondent Bank has
agreed to provide the Bank Guarantees at the request of the Solar Power
Developer, that is, the petitioner. Thus, the respondent Bank has irrevocably
guaranteed due and punctual performance by the petitioner of all its obligations
relating to the Project under the Agreement. The respondent Bank as the primary
obligator has stated that it shall, without demur, pay to the APDCL the amounts
not exceeding in aggregate mentioned in each of the three Bank Guarantees,
Page No. 37/52
within one working day of receipt of a written demand thereof from the APDCL
stating that the Solar Power Developer, that is, the petitioner has failed to meet
its performance obligations under the Agreement. The Bank Guarantees further
mention that the respondent Bank as the Guarantor shall not go into the veracity
of any breach or failure on the part of the Solar Power Developer, that is, the
petitioner or validity of demand so made by the APDCL and shall pay the amount
specified in the demand, notwithstanding any direction to the contrary given or
any dispute whatsoever raised by the Solar Power Developer, that is, the
petitioner or any other person. The Bank Guarantees also mention that the Bank’s
obligations as Guarantor under the Bank Guarantees shall subsist until all such
demands are duly made and discharged in accordance with the provisions of the
Bank Guarantees and in order to give effect to the Bank Guarantees, the APDCL
shall be entitled to treat the Guarantor Bank as the Principal Debtor. The Bank
Guarantees stipulate that they shall remain in full force and effect for the period
of 22 [twenty-two] months from the date of signing of the Power Purchase
Agreement [PPA]. The Bank Guarantees though mention about Clause 4.4 of the
Power Purchase Agreement [PPA] the same does not go to change the nature of
the Bank Guarantees from unconditional and irrevocable Bank Guarantees to
conditional ones as mere mention of Clause 4.4 of the Power Purchase Agreement
[PPA] in the Preamble of the Bank Guarantees does not control the operative
parts of the Bank Guarantees. It is clear from the Bank Guarantees that the
APDCL is the best judge to decide as to whether the Solar Power Developer, that
is, the petitioner has failed to meet its performance obligations or not. In the
event of receipt of a written demand from the APDCL mentioning that the APDCL
wants to invoke and encash the Bank Guarantees due to failure on the part of the
Solar Power Developer, that is, the petitioner to meet its performance obligations,
the Guarantor Bank is not required to go into the veracity of such demand made
by the APDCL. Meaning thereby, it is not open for the Guarantor Bank to enquire
as to whether there is due performance of or there is failure to perform the
obligations under the Principal Agreement, that is, the Power Purchase Agreement
[PPA] on the part of the petitioner. As per the Bank Guarantees, the Guarantor
Bank on receipt of a written demand for encashment of the Bank Guarantees from
Page No. 38/52
the APDCL, shall have to pay the amounts specified in the demand without any
demur. It has been clearly stipulated in the Bank Guarantees that any dispute
between the APDCL and the Solar Power Developer, that is, the petitioner at
whose instance the Guarantor Bank has given the Bank Guarantees, is immaterial
and is of no consequence. Having gone through the terms and conditions of the
three Bank Guarantees, by keeping the principles enunciated in the decisions cited
above, this Court is of the unhesitant view that the three Bank Guarantees are
unconditional and irrevocable in nature. The petitioner has stated that the
petitioner had signed the Power Purchase Agreement [PPA] on 15.02.2021.
24. On perusal of the three Bank Guarantees, all similarly worded and one of which
has been extracted hereinabove, it is also noticed that the Bank Guarantees have
two different time-periods/dates. One is the validity period [Expiry Date]
indicating the date till which the particular Bank Guarantee would remain valid
and the other is the claim period which indicates a period beyond the validity
period of the Bank Guarantee to make a written claim or demand to the Bank
against a default. For example, the Bank Guarantee bearing no. IBG113029 dated
25.01.2021 for a guarantee amount of Rs. 84,00,000/- has mentioned that the
Bank Guarantee shall be valid upto 24.01.2023 and the Bank shall be liable to pay
the guarantee amount only and only if the Bank receives from the beneficiary [the
APDCL], a written claim or demand no later than 1 [one] year from the expiry
date, meaning thereby, the claim period would be upto 24.01.2024. If such
validity period of the Bank Guarantee upto 24.01.2023 and the claim period upto
24.01.2024 are found to be sustainable then the claim or demand made by the
APDCL to the respondent no. 5 Bank on 01.11.2023 by the impugned Letter
bearing no. APDCL/CGM[PP&D]/NRE-146/2019-20/787 dated 01.11.2023 and/or
on 06.11.2023 by the impugned Letter bearing no. APDCL/CGM[PP&D]/NRE-
146/2019-20/790 dated 06.11.2023 would, in turn, have to be regarded as a
written claim or demand made within time.
25. The learned counsel for all the parties are in general agreement that a Standard
Bank Guarantee would usually contain the three terms :- [a] Expiry Period/Validity
Page No. 39/52
Period; [b] Claim Period; and [c] Enforcement Period. They are also in consensus
ad item to the expositions provided to the said three terms in Larsen and Toubro
Limited [supra] in the following manner :-
[a] Expiry Period/Validity Period : A bank guarantee would prescribe a specific
date by which a bank guarantee would expire. This is a time determined by
the Principal Debtor and the Creditor. The right to invoke the bank guarantee
is only for a default of the Principal Debtor which occurs during the validity
period of the bank guarantee.
[b] Claim Period : This is a time period contractually agreed between the Creditor
and the Principal Debtor which provides a grace period beyond the validity
period to make a demand on the bank for a default which has occurred
during the validity period. A claim period may or may not exist in the bank
guarantee. The guarantor again has no role to play.
[c] Enforcement Period : The enforcement period is a time period within which
the Creditor can enforce his accrued rights pursuant to a demand made by
him within the validity period or the claim period before a competent court of
law.
26. Section 126 of the Indian Contract Act, 1872 has provided for the definitions of
‘Contract of Guarantee’, ‘Surety’, ‘Principal Debtor’ and ‘Creditor’. As per Section
126, a ‘Contract of Guarantee’ is a contract to perform the promise, or discharge
the liability, of a third person in case of his default. The person who gives the
guarantee is called the ‘Surety’; the person in respect of whose default the
guarantee is given is called ‘Surety’; the person in respect of whose default the
guarantee is given is called the ‘Principal Debtor’, and the person to whom the
guarantee is given is called the ‘Creditor’. A guarantee may be either oral or
written.
27. As submissions have been advanced in reference to Section 28 of the Indian
Contract Act, 1872, it appears necessary to find out the provisions contained in
Page No. 40/52
the original Section 28 and in the subsequent amendments. Originally, Section 28
read as under :-
28. Agreements in restraint of legal proceeding, void. –
Every agreement, by which any party thereto is restricted absolutely from
enforcing his rights under or in respect of any contract, by the usual legal
proceedings in the ordinary tribunals, or which limits the time within which
he may thus enforce his rights, is void to that extent.
After an amendment given into effect from 08.01.1997, Section 28 was in the
following form :-
28. Agreements in restraint of legal proceeding, void. - Every agreement
[a] by which any party thereto is restricted absolutely from enforcing his rights
under or in respect of any contract, by the usual legal proceedings in the
ordinary tribunals, or which limits the time within which he may thus
enforce his rights, or
[b] which extinguishes the rights of any party thereto, or discharges any party
thereto, from any liability, under or in respect of any contract on the expiry
of a specified period so as to restrict any party from enforcing his rights,
is void to that extent.
Exception 1.— Saving of contract to refer to arbitration dispute that may arise.
This section shall not render illegal a contract, by which two or more persons agree
that any dispute which may arise between them in respect of any subject or class of
subjects shall be referred to arbitration, and that only the amount awarded in such
arbitration shall be recoverable in respect of the dispute so referred.
Exception 2.— Saving of contract to refer questions that have already arisen.
Nor shall this section render illegal any contract in writing, by which two or more
persons agree to refer to arbitration any question between them which has already
arisen, or affect any provision of any law in force for the time being as to references
to arbitration.
Page No. 41/52
28. The Law Commission in its Report submitted in the year, 1984 recommended
changes in Section 28 and the same led to an amendment in Section 28 with
insertion of Exception 3 therein in the year, 2012. The Statement of Objects and
Reasons of the Amendment Acts read as under :-
The Statement of Objects and Reasons
1. The Law Commission of India has recommended in its 97
th
Report that Section
28 of the Indian Contract Act, 1872 may be amended so that the anomalous
situation created by the existing section may be rectified. It has been held by the
courts that the said Section 28 shall invalidate only a clause in any agreement
which restricts any party thereto from enforcing his rights absolutely or which
limits the time within which he may enforce his rights absolutely or which limits
the time within which he may enforce his rights. The courts have, however, held
that this section shall not come into operation when the contractual term spells
out an extinction of the right of a party to sue or spells out the discharge of a
party from all liability in respect of the claim. What is thus hit by Section 28 is an
agreement relinquishing the remedy only i.e. where the time-limit specified in
the agreement is assumed to exist between remedy and right and this distinction
is the basis of the present position under which a clause barring a remedy is void,
but a clause extinguishing the rights is valid. This approach may be sound in
theory but, in practice, it causes serious hardship and might even be abused.
2. It is felt that Section 28 of the India Contract Act, 1872 should be amended as it
harms the interests of the consumer dealing with big corporations and causes
serious hardship to those who are economically disadvantaged.
3. The Bill seeks to achieve the above objects.
28.1. Subsequent to insertion of Exception 3 in Section 28 by the Banking Laws
[Amendment] Act, 2012, Section 28 in the present form reads as under :-
28. Agreements in restraint of legal proceedings, void.— Every agreement,—
[a] by which any party thereto is restricted absolutely from enforcing his rights
under or in respect of any contract, by the usual legal proceedings in the
Page No. 42/52
ordinary tribunals, or which limits the time within which he may thus enforce
his rights; or
[b] which extinguishes the rights of any party thereto, or discharges any party
thereto, from any liability, under or in respect of any contract on the expiry of a
specified period so as to restrict any party from enforcing his rights,
is void to the extent.
Exception 1.— Saving of contract to refer to arbitration dispute that may arise.
This section shall not render illegal a contract, by which two or more persons agree
that any dispute which may arise between them in respect of any subject or class of
subjects shall be referred to arbitration, and that only the amount awarded in such
arbitration shall be recoverable in respect of the dispute so referred.
Exception 2.— Saving of contract to refer questions that have already arisen.
Nor shall this section render illegal any contract in writing, by which two or more
persons agree to refer to arbitration any question between them which has already
arisen, or affect any provision of any law in force for the time being as to references
to arbitration.
Exception 3.— Saving of a guarantee agreement of a bank or a financial
institution. This section shall not render illegal a contract in writing by which any
bank or financial institution stipulate a term in a guarantee or any agreement
making a provision for guarantee for extinguishment of the rights or discharge of
any party thereto from any liability under or in respect of such guarantee or
agreement on the expiry of a specified period which is not less than one year from
the date of occurring or non-occurring of a specified event for extinguishment or
discharge of such party from the said liability.
29. On reading of the heading of Section 28, ‘Agreements in restraint of legal
proceedings, void’ and the substantive parts of Section 28 contained in Clause [a]
and Clause [b] thereof with Exception 3 together, it is discernible that since the
heading and the substantive parts of the provisions contained in Section 28 state
that agreements which inter alia contain a clause indicating a time limit thereby
restricting a party to enforce his rights under such contract within the time limit, is
void to that extent, Exception 3 is, thus, to be read in the same context in respect
of a Bank Guarantee which is also a contract in writing. Exception 3 has provided
Page No. 43/52
that substantive provision of Section 28 shall not render illegal a contract in
writing by which a bank stipulates a term in a guarantee or any agreement
making a provision for guarantee for extinguishment of the rights or by which any
party thereto is discharged from any liability under or in respect of such guarantee
or agreement on the expiry of a specified period, which is not less than 1 [one]
year from the date of occurring or non-occurring of a specified event for
extinguishment or discharge of such party from the said liability.
30. In Larsen and Toubro Limited [supra], the writ petitioner was M/s Larsen and
Toubro Limited. Stating that it was one of the largest construction companies in
India, the writ petition was instituted arraigning the Guarantor Bank, Punjab
National Bank as party-respondent no. 1, M/s Indian Banks Association as party-
respondent no. 2 and the Reserve Bank of India [RBI] as party-respondent no. 3.
It was contended that the petitioner had a number of contracts with Government
bodies and Public Sector Undertakings and to participate in the bidding processes/
to execute contract-works awarded to it, it required to submit bid securities/
performance securities in the form of Bank Guarantees. On the basis of circulars
issued by the respondent no. 2 which is an association of banks, the respondent
no. 1 Bank by its communications, impugned therein, insisted that the Bank
Guarantees should have a claim period of twelve months and any claim period
lesser than twelve months, would effectively increase the claim period in respect
of the Bank Guarantees to three years under the Limitation Act, 1963. The
respondent no. 3, the RBI in its counter affidavit filed therein had taken a stand
that Bank Guarantees were structured according to the terms of the agreements
and the terms were decided mutually between the parties, that is, the Surety, the
Principal Debtor and the Creditor. It was further clarified that the RBI had not
prescribed any terms to be incorporated in the Bank Guarantees and the terms of
the Bank Guarantees to be issued by the Guarantor Banks were decided in terms
of the respective policy of the concerned banks and on the basis of the
contractual arrangements between the parties. In so far as the advises contained
in the circulars of the party-respondent no. 2 therein, that is, the Indian Banks
Association [IBA] were concerned, it was found out that the IBA had advised that
Page No. 44/52
if the banks would issue Bank Guarantees with a claim period of less than one
year then such Bank Guarantees would not have the benefit of Exception 3 to
Section 28 and would stand exposed to the period of limitation under the
Limitation Act, 1963. The IBA had, thus, advised the banks to issue every Bank
Guarantee with a minimum claim period of one year beyond the validity period of
the Bank Guarantee. It is pertinent to mention that the limitation period
prescribed under the Limitation Act, 1963 is thirty years where the claimant is the
Government and the period is three years in respect of others. The learned Single
Judge of the Hon’ble Delhi High Court after considering the history of the
amendments carried out in Section 28 of the Contract Act, 1872, has held that
Exception 3 to Section 28 of the Contract Act, 1872 is with regard to the rights of
a Creditor to enforce his rights under a Bank Guarantee after happening of a
specified event and Exception 3 does not deal with the claim period within which
the Creditor is entitled to lodge his claim with the bank/guarantor. It has been
held that the respondent Bank and the IBA erred in interpreting the scope of
Exception 3 to Section 28. It has been further held that there is no mandatory
requirement that the claim period for a Bank Guarantee has to be for minimum
twelve months.
31. The issues involved in Indusind Bank Limited [supra], were with regard to Bank
Guarantees which were required to be kept valid upto six months with a provision
for claims for an additional three months. The Bank Guarantees involved therein
had clauses as follows :- [i] ‘… Unless a demand or claim under this guarantee is
made against us within three months from the above date [i.e. on or before
30.04.1997], all your rights under the said guarantee will be forfeited and we shall
be relieved and discharged from all liabilities hereunder’; and [ii] ‘… Provided
however, unless a demand or claim under this guarantee is made on us in writing
within 3 months from the date of expiry of this guarantee in respect of export of
XXXXX, we shall be discharged from all liability under this guarantee thereafter’.
In that context, the Hon’ble Supreme Court has held that neither of the clauses
has purportedly limited the time within which rights are to be enforced. It has
been observed that none of the aforesaid clauses purports to curtail the period of
limitation within which a suit can be brought to enforce the Bank Guarantees.
Page No. 45/52
32. Assertion of right under a contract in the form of a claim or demand is different
from enforcing it in a Court of law by way of any legal proceedings. On a plain
reading of the recitals in the three Bank Guarantees involved herein, as extracted
in bold letters in paragraph 22 above, as regards the validity period/expiry date
and the claim period, it does not go to indicate that it has dealt with any matter
relating to enforcement of right to claim by way of Legal proceedings in a court of
law. It has only dealt with assertion of claim of the guaranteed amount within a
year beyond the validity period of the Bank Guarantees. To be more precise, it
emerges, on a plain reading, that though Bank Guarantees bearing no.
IBG113029 dated 25.01.2021 would be valid only upto 24.01.2023, the
beneficiary/Creditor [the APDCL] would have the advantage of a claim period of 1
[one] year beyond the validity period upto 24.01.2023, that is, upto 24.01.2024 to
make a claim or demand, in writing, to the Guarantor Bank to invoke and encash
the said Bank Guarantee. Similarly, the Bank Guarantee bearing no. IBG113031
dated 25.01.2021 for a guarantee amount of Rs. 1,68,00,000/- has its expiry date
as 24.01.2023 and a claim period of 1 [one] year beyond 24.01.2023. The third
Bank Guarantee bearing no. IBG113102 dated 27.01.2021 for a guarantee
amount of Rs. 1,68,00,000/- has its expiry date as 26.01.2023 and a claim period
of 1 [one] year beyond 26.01.2023. The manner of making such claim for the
amounts under the Bank Guarantees is governed by the agreements itself i.e. the
three Bank Guarantees which have stipulated that a claim or demand in writing is
to be received by the respondent no. 5 Bank from the beneficiary, APDCL within 1
[one] year from the respective expiry date. It is not disputed by the respondent
no. 5 Bank that it did not receive the impugned Letter dated 01.11.2023 and the
impugned Letter dated 06.11.2023 from the APDCL containing the claim to invoke
the Bank Guarantees and the request to transfer the amounts thereof to the bank
account of the APDCL after encashment. Considered from that angle, it is found
that the claim for invocation and encashment of the three Bank Guarantees was
made within the respective claim period, though it was beyond the validity period
of the Bank Guarantees.
Page No. 46/52
33. Prior to the policy decision taken by the respondent Federal Bank, as contained in
Circular no. 10349/CRD/IRMDC34/20-21 dated 17.06.2020, claim period of one
year was not mandatorily insisted by the Federal Bank while issuing guarantees.
As per the Circular dated 17.06.2020 [supra], the Federal Bank had taken a policy
decision to include one year claim period in all guarantees issued by the Bank.
Consequent to such inclusion of one year claim period, norms pertaining to
release of securities and collection of Bank Guarantee [BG] Commission were also
set forth as follows :- [i] Bank shall not release the cash margin and securities
charged to the BG until Bank is discharged from the liability i.e. till the expiry of
claim period; and [ii] BG Commission shall be collected for the additional period of
one year i.e. till the expiry of the claim period.
34. It needs iteration at this juncture, even at the cost of repetition, that the
respondent APDCL authorities by the Bidding Document comprising of the RFS
Document and the Draft Power Purchase Agreement [PPA], had sought for the
Bank Guarantees in terms of Schedule 3, extracted hereinabove, from the
Successful Bidder/Solar Power Developer, that is, the petitioner. It was set forth
that such Bank Guarantees in the format provided in Schedule 3 should be
unconditional and irrevocable for due performance of the obligations required on
the part of the petitioner in terms of the Power Purchase Agreement [PPA]. After
having emerged as the Successful Bidder for the Region-2 Project the petitioner
was to obtain the Performance Security in the form of unconditional and
irrevocable Bank Guarantees strictly in terms of Clause 4.4 of the Power Purchase
Agreement [PPA] for amounts indicated therein. The respondent no. 5 Bank had
issued the three Bank Guarantees with their covering letters, addressed to the
APDCL. As per the three covering letters of the respondent no. 5 Bank – dated
25.01.2021, dated 25.01.2021 & dated 27.01.2021 – it was informed to the
APDCL that the Bank was enclosing the Bank Guarantees in favour of the APDCL
on behalf of the petitioner. Requesting for acknowledgment of receipt of the three
Bank Guarantees, the APDCL authorities were advised to verify the genuineness
of the Bank Guarantees. From the Letter bearing Ref. no. : JK/NLP/APDCL/SOLAR
PROJECT/Region-2/L-05 dated 29.01.2021 of the petitioner, addressed to the
Page No. 47/52
respondent no. 3, it is evident that the petitioner with the said Letter had
submitted the original copies of the three Bank Guarantees and the respondent
no. 3 had acknowledged the receipt thereof under seal and signature on
30.01.2021. It is, thus, not open for the petitioner to say that he was not aware
of the contents of the three Bank Guarantees or was not aware that the Bank
Guarantees were not strictly in terms of the format provided in Schedule 3. It is
also not open for the petitioner to take a plea, after instituting the writ petition, to
contend that the petitioner was not aware of the condition incorporated in the
three Bank Guarantees as regards the claim period of one year, beyond the
validity period of the Bank Guarantees. The petitioner has himself annexed the
copies of the Bank Guarantees as annexures in the writ petition and the said fact
belies any contention raised on behalf of the petitioner that the petitioner was not
aware of the condition incorporated in the Bank Guarantees regarding the claim
period during the period from 25.01.2021/27.01.2021 [the dates of issuance of
the three Bank Guarantees] and/or from 29.01.2021 [the date on which the
petitioner submitted the original copies of the three Bank Guarantees] till
06.11.2023 [the date of institution of the writ petition annexing copies of the
three Bank Guarantees and the copies of the covering letters of the respondent
no. 5 Bank as Annexure – 4-Colly].
35. Assuming, arguendo, firstly, that the beneficiary/creditor of the Bank Guarantees,
that is, the APDCL required the Bank Guarantees only in the format provided in
Schedule – 3 and it had not sought incorporation of any clause regarding claim
period of one year beyond the validity period of the Bank Guarantees; secondly,
that the Principal Debtor/the petitioner had no role in incorporation of the clause
regarding such claim period in the Bank Guarantees; and thirdly, that the
respondent no. 5 Bank, that is, the Guarantor Bank had incorporated the claim
period unilaterally in the Bank Guarantees in terms of its policy decision contained
in Circular no. 10349/CRD/IRMDC34/2020-21 dated 17.06.2020; the issue which
has fallen for consideration is whether in the fact situation obtaining in the case,
more particularly, in view of the conduct of the petitioner right from the date of
issuance of the three Bank Guarantees i.e. 25.01.2021/27.01.2021 to the date of
Page No. 48/52
issuance of the impugned Letter bearing no. APDCL/CGM[PP&D]/NRE-146/2019-
20/787 dated 01.11.2023 and/or the impugned Letter bearing no.
APDCL/CGM[PP&D]/NRE-146/2019-20/790 dated 06.11.2023 whereby the APDCL
had sought to invoke the Bank Guarantees, the petitioner as the Principal Debtor
can be granted the reliefs/directions sought for in this writ petition. It is pertinent
to note that even after the impugned Letter bearing no. APDCL/CGM[PP&D]/NRE-
146/2019-20/787 dated 01.11.2023 did not raise any issue/protest as regards the
claim period of 1 [one] year in the Bank Guarantees beyond the respective validity
period of the Bank Guarantees. In such background, this Court has to examine as
to whether such conduct of the petitioner would act to his detriment in getting the
reliefs he has sought for. Such aspect is required to be examined on the basis of
the doctrine of acquiescence. The said aspect is to be considered by taking note
of the proposition that if one party to an agreement adds any additional term in
the agreement without the consent of the other party to the agreement then such
unilateral addition is not ordinarily binding on the other party.
36. As per the Oxford Dictionary of English, 3
rd
Edition, ‘acquiesce’ means ‘to accept
something reluctantly but without protest’ and ‘acquiescence’ means ‘the reluctant
acceptance of something without protest’. In the Black’s Law Dictionary, 9
th
Edition, the meaning ascribed to ‘acquiesce’ is ‘to accept tacitly or passively; to
give implied consent to [an act]’ and to ‘acquiescence’ is ‘a person’s tacit or
passive acceptance; implied consent to an act’.
36.1. It has been observed in the decision of the Hon’ble Supreme Court of India titled
U.P. Jal Nigam and another vs. Jaswant Singh and another, reported in [2006] 11 SCC
464, acquiescence does not mean standing by while the violation of a right is in
progress, but assent after the violation has been completed and the person has
become aware of it. It is unjust to give such a person a remedy where, by his
conduct, he has done that which might fairly be regarded as equivalent to a
waiver of it; or where by his conduct and neglect, though not waiving the remedy,
he has put the other party in a position in which it would not be reasonable to
place him if the remedy were afterwards to be asserted.
Page No. 49/52
36.2. The doctrine of acquiescence has come to be considered by the Hon’ble Supreme
Court of India in Union of India and others vs. N. Murugesan and others, reported in
[2022] 2 SCC 25. It has been held that acquiescence would mean a tacit or passive
acceptance. It is implied and reluctant consent to an act. In other words, such an
action would qualify a passive assent. Thus, when acquiescence takes place, it
presupposes knowledge against a particular act. From the knowledge comes
passive acceptance, therefore instead of taking any action against any alleged
refusal to perform the original contract, despite adequate knowledge of its terms,
and instead being allowed to continue by consciously ignoring it and thereafter
proceeding further, acquiescence does takes place. As a consequence, it
reintroduces a new implied agreement between the parties. Once such a situation
arises, it is not open to the party that acquiesced itself to insist upon the
compliance of the original terms. Hence, what is essential, is the conduct of the
parties.
36.3. In Chairman, State Bank of India and another vs. M.J. James, reported in [2022] 2 SCC
301, the Hon’ble Supreme Court has observed that doctrine of acquiescence is an
equitable doctrine which applies when a party having a right stands by and sees
another dealing in a manner inconsistent with that right, while the act is in
progress and after violation is completed, which conduct reflects his assent or
accord. He cannot afterwards complain. In literal sense, the term acquiescence
means silent assent, tacit consent, concurrence, or acceptance, which denotes
conduct that is evidence of an intention of a party to abandon an equitable right
and also to denote conduct from which another party will be justified in inferring
such an intention. Acquiescence can be either direct with full knowledge and
express approbation, or indirect where a person having the right to set aside the
action stands by and sees another dealing in a manner inconsistent with that right
and in spite of the infringement takes no action mirroring acceptance.
37. When the fact situation obtaining in the case is examined qua the doctrine of
acquiescence, it is noticeable that the petitioner as per the terms and conditions
Page No. 50/52
of the RFP/RFS Document, Draft Power Purchase Agreement and Clause 4.4
thereof the Letter of Award [LoA] dated 04.01.2021, was required to submit
Performance Security in the form of Bank Guarantees, as provided in Schedule 3.
The three Bank Guarantees in question were issued by the respondent no. 5 Bank
at the instance and request of the petitioner in favour of the APDCL as the
beneficiary/creditor on the dates - 25.01.2021, 25.01.2021 & 27.01.2021. The
respondent no. 5 Bank had handed over the Bank Guarantees to the petitioner
with their covering letters on those dates. In the said Bank Guarantees, the clause
regarding claim period which was not in Schedule 3, stood incorporated,
purportedly unilaterally by the respondent no. 5 Bank on the basis of the policy
decision contained in the Circular dated 17.06.2020. The petitioner had every
opportunity to know about incorporation of the clause regarding extended claim
period in the three Bank Guarantees, beyond the respective validity period, but
without making any protest or raising any issue in respect of such incorporation of
the clause regarding extended claim period beyond the required validity period of
22 months the petitioner proceeded to hand over the original copies of the three
Bank Guarantees to the APDCL by his Letter bearing reference no.
JK/NLP/APDCL/SOLAR PROJECT/Region-2/L-05 dated 29.01.2021 to the
respondent no. 3. The matter rested in the said position until 01.11.2023 when
the APDCL by the impugned Letter bearing no. APDCL/CGM[PP&D]/NRE-
146/2019-20/787 of even date, addressed to the respondent no. 5 Bank, sought
invocation of the Bank Guarantees. The incorporation of the clause regarding
claim period of 1 [one] year beyond the validity periods of the Bank Guarantees
was not at the behest of the respondent APDCL but having received the Bank
Guarantees with such claim periods the APDCL appeared to have accepted the
same. During the entire period from 25.01.2021/27.01.2021/29.01.2021 to
01.11.2023/02.11.2023/06.11.2023, the petitioner despite having adequate
knowledge about incorporation of the clause regarding the claim period in the
Bank Guarantees, had remained silent. From the fact that the petitioner has
annexed the copies of the Bank Guarantees along with the covering letters of the
bank in the writ petition it clearly emerges that the petitioner had the knowledge
about the claim periods all along for a period of more than 30 months and in such
Page No. 51/52
situation, it is not possible to draw any other inference. When despite having
adequate knowledge of the clause regarding the claim periods in the Bank
Guarantees and when instead of making any protest or raising any issue as
regards such incorporation, the petitioner has been found to have allowed the
matter to continue which demonstrates a situation of passive acceptance and
assent. As a result of inaction on the part of the petitioner during the entire afore-
mentioned period the other parties involved with the Bank Guarantees appeared
to have proceeded accordingly. As the petitioner did not insist for the Bank
Guarantees as was originally conceived in the format provided in Schedule 3 for
such prolonged period and continued without making any protest or raising any
issue with regard to the claim period, this Court finds that the clause incorporated
in the Bank Guarantees regarding the claim period was with implied consent of
the petitioner with the operation of the doctrine of acquiescence. The doctrine of
acquiescence is clearly applicable in the case in hand as the petitioner having a
right stood by, without making any protest or raising any issue regarding the
claim period, and allowed the other parties dealing with the Bank Guarantees in a
manner which was purportedly inconsistent with the Bank Guarantees originally
conceived of, it is not open for the petitioner at this stage to make any complaint.
In the present case, it is found that it is the Bank Guarantees with clauses
incorporating the claim period of one year, beyond the validity period in the
respective Bank Guarantee, which have replaced the format provided in Schedule
3 originally contemplated and conceived of and as a result, it is to be held that the
parties involved herein are bound by such claim period.
38. As the petitioner has not raised the issues of fraud or irretrievable loss or
injustice, this Court finds it unnecessary to advert to on those issues. In any view
of the matter, there are no pleadings in the writ petition as regards commission of
fraud of egregious nature or irretrievable loss or injustice. It is trite to say that a
decision is an authority for what it decides and not what can logically be deduced
therefrom and even a slight distinction in fact or an additional or different fact
may make a lot of difference in the decision making process. An act of protest
anterior to invocation of a bank guarantee is different from an act of protest made
Order downloaded on 24-12-2024 05:27:52 PMPage No. 52/52
subsequent to invocation of a bank guarantee. Thus, the fact situation obtaining
in the case of Larsen and Toubro Limited [supra] are not found similar to the case
in hand.
39. In view of the discussion made, the findings arrived at as above and the reasons
assigned therein, this Court is of the considered view that the petitioner has not
made out a case on merits for the reliefs/directions sought for in the writ petition
within the extraordinary, discretionary and equitable jurisdiction under Article 226
of the Constitution of India. Consequently, the writ petition fails. As it merits
dismissal, it is accordingly ordered. The interim order passed earlier stands
recalled. It is, therefore, held that the Letter bearing no. APDCL/CGM[PP&D]/NRE-
146/2019-20/787 dated 01.11.2023 and the Letter bearing no.
APDCL/CGM[PP&D]/NRE-146/2019-20/790 dated 06.11.2023, addressed to the
respondent no. 5 Bank, invoking the three Bank Guarantees [IBG113029 dated
25.01.2021, IBG113031 dated 25.01.2021 and IBG113102 dated 27.01.2021] are
found to be valid as they are within the claim periods mentioned in those three
Bank Guarantees. As such, the respondent no. 5 Bank has to proceed in terms of
the said Bank Guarantees for honouring them. There shall, however, be no order
as to cost.
JUDGE
Comparing Assistant
Legal Notes
Add a Note....