As per case facts, a franchise agreement between the appellant and respondent was terminated by the latter. The appellant sought compensation for investment and renewal of the agreement, filing a ...
Page 1 RFA No.44/2025
HIGH COURT OF JAMMU &KASHMIR AND LADAKH
AT JAMMU
(Through Virtual Mode)
…
RFA No.44/2025
Reserved on: 24.04.2026
Pronounced on: 04.06.2026
Uploaded on: 04.06.2026
Whether the operative part or full
Judgment is pronounced: Full
JKR Partnership Firm
through its Partner
Rajneesh Jamwal Age 34
years, Malik Market
Byepass Road, Opposite
Jamia Masjid, Jammu
…….Appellant(s)
Through: Mr. Inderjeet Gupta, Advocate
Versus
Detailing Devils India Pvt.
Ltd., A Company
incorporated under the
Companies Act 2013 and
having its Registered Office
at D-50, Sector 2 Noida,
Uttar Pradesh India -
201301 through its
Director Mr Rajat Ahooja.
……Respondent(s)
Through: Mr., Asav Rajan, Advocate
Mr. Ayjaz Lone, Advocate
Mr. Kashish Chadha,
Advocate
Mr. Devang Shrotriya,
Advocate.
Page 2 RFA No.44/2025
CORAM: HON’BLE MR JUSTICE RAJNESH OSWAL, JUDGE
HON’BLE MR JUSTICE RAHUL BHARTI, JUDGE
JUDGMENT
(Rajnesh Oswal-J)
1. This civil first appeal is addressed by the appellant, as
being an aggrieved plaintiff, against an order dated
31.07.2025 passed by the court of learned Additional
District Judge, (Commercial Court), Jammu (hereinafter
to be referred to as “the trial court”) in a civil suit titled
“PKR Partnership Firm v. Detailing Devils India Pvt.
Ltd.” wherein, in response to an application filed by the
respondent/defendant under Order VII Rule 11 of the
Code of Civil Procedure (CPC), 1908, the learned trial
court has rejected the appellant's plaint for failure to
comply with the mandatory pre-institution mediation as
envisaged under Section 12-A of the Commercial Courts
Act, 2015 (for short “the Act”).
2. Before coming to deal with the appellant’s appeal in the
context of challenge to the impugned order, a brief
resume of the civil suit preferred by the appellant needs
to be put in place here in next.
3. By virtue of a Franchise Agreement dated 25.07.2020
made by and between the respondent and the appellant,
Page 3 RFA No.44/2025
the respondent came to constitute the appellant as a
‘franchisee’ with respect to opening and operation of an
outlet (the unit, franchised unit and franchised business)
at one location only which was Detailing Devils, Jammu,
Malik Market, Bye Pass Road, Opposite Jamia Masjid,
Pin Code-180015.
4. The franchise so granted in favour of the appellant by the
respondent was a non-exclusive one with initial term and
tenure of the Franchise Agreement being three years to
expire on 3
rd anniversary of date of launch of the singular
outlet for which the franchise was being granted. There
was a clause for renewal of franchise at the option of the
appellant as a franchisee and the renewal period was also
for a period of two years provided at the time of renewal,
the appellant paid a non -refundable renewal fee of
Rs. 50,000/- by exercising option of renewal with a prior
notice of six months period to be first served by the
appellant to the respondent.
5. Thus, by the making date of franchise agreement being
25.07.2020, said agreement on its own was to expire on
24.07.2023.
6. The respondent, by way of legal notice dated 29.08.2023
came to terminate the Franchise Agreement by putting
the appellant on a caveat to desist from claiming itself to
Page 4 RFA No.44/2025
be the franchisee of the respondent with immediate
effect.
7. The said legal notice came to be responded by the
appellant by a reply to the legal notice dated 12.09.2023
wherein the appellant came to notify the respondent that
in the face of termination of the franchise agreement, the
appellant is entitled to claim an amount of Rupees Fifty
Lacs (Rs. 50,00,000/-) on account of investment made by
it. The appellant further came to seek renewal of the
Franchise Agreement for next two years.
8. It is in this backdrop that a purported cause of action
was availed by the appellant to file a civil suit on
28.10.2023 before the learned Principal District Judge,
Jammu wherefrom it came to be transferred to the court
of learned Additional District Judge (Commercial Court),
Jammu.
9. In its civil suit, the appellant claimed a decree for
compensation of amount of Rupees Fifty Lacs
(Rs. 50,00,000/-) and also a declaration with respect to
termination notice dated 29.08.2023 being illegal, null
and void and inoperative with mandatory injunction
directing the respondent to allow the appellant to operate
the franchise agreement and perpetually restraining the
Page 5 RFA No.44/2025
respondent from allocating the franchise to any other
person in Jammu province.
10. The aforesaid civil suit of the appellant was also
accompanied with an application for grant of temporary
injunction of staying the operation of the termination
notice and also restraining the respondent from
allocating the franchise agreement to any other person.
The appellant also sought an interim relief so as to
continue to conduct the business as per franchise
agreement.
11. The respondent from its end came forward with an
application under Order VII Rule 11 of the CPC by citing
the judgment of Hon’ble Supreme Court of India in the
case of M/s Patil Automation Pvt. Ltd and Ors Vs.
Rakheja Engineers Pvt. Ltd. [(2022) 10 SCC 1]. In its
said application, the respondent came to assert that the
appellant identifies and introduces itself as a firm acting
through its partner Rajneesh Jamwal but without any
certificate of registration of partnership being on record
thereby rendering the suit liable to be rejected. The
respondent further cited that as per the terms and
conditions of the franchise agreement, the jurisdiction to
adjudicate the dispute only vested with the courts in
Delhi. In addition the respondents stated that the suit
Page 6 RFA No.44/2025
reliefs are cognizable by the Commercial Court in terms
of the Commercial Courts Act, 201 5 whereas the
appellant has nomenclated its suit as a civil suit before a
civil court of original jurisdiction.
12. The appellant from its end came forward with a reply to
the said application of the respondent. The appellant
intended to salvage the maintainability of the suit by
citing that in terms of Section 12-A of the Act in the event
of plaintiff seeking urgent relief, exemption is available
for maintaining the civil suit without initiating pre-
litigation mediation.
13. In this regard, the appellant also came to rely upon
M/s Patil Automation Pvt. Ltd judgment of the Hon’ble
Supreme Court of India (supra) by referring to its paras
54 and 72. In addition, the appellant also cited Ganga
Taro Vazirani Vs. Deepak Raheja, 202 0 SCC Online
Bombay 9015 to impress the point that section 12-A of
the Act is a procedural provision and when an urgent
relief is sought in a civil suit, the procedure under
Section 12-A of the Act needs not to be undergone.
14. The appellant further came in response to refer to a fact
that it received a notice from the Secretary North DLSA
Delhi by reference to a pre-mediation application filed by
the respondent before the North District Legal Services
Page 7 RFA No.44/2025
Authority, Rohini Courts, Delhi and apprised the said
Authority about the fact of civil suit having been filed by
the appellant against the respondent which resulted in
closure of the pre-mediation process at the end of the
North District Legal Services Authority.
15. In addition, the respondent also filed written statement
dated 18.11.2023 to the plaint.
16. It is said application of the respondent which came to
earn its adjudication in the form of impugned order dated
31.07.2025 from the trial court whereby the suit of the
appellant was held non-maintainable being in breach of
mandate of section 12-A of the Act and, thus, rejecting
the plaint as per M/s Patil Automation Pvt. Ltd
judgment.
17. The learned trial court came to pose a solitary question
for its consideration as to whether statutory pre-litigation
mediation under Section 12-A of the Act is mandatory
and in this regard referred itself to the judgment of the
Hon’ble Supreme court of India in the case of M/s Patil
Automation Pvt. Ltd & Ors Vs. Rakheja Engineers
Private Ltd.
18. The appellant challenges the impugned order primarily
on the ground that the main suit was accompanied by an
application for urgent ad-interim relief so, therefore, its
Page 8 RFA No.44/2025
suit was maintainable without suffering any disability by
reference to section 12-A of the Act.
19. The appellant contends that owing to this manifest
urgency, the requirement of pre-institution mediation
under Section 12-A of the Act was fully exempted.
20. It is submitted that the learned trial court erred in law by
ignoring settled Apex Court’s precedents which mandate
that courts must deeply examine the pleadings as a
whole to determine if an urgent interim relief is genuinely
made out so as to dispense with mediation.
21. Precisely stated, the contention of the appellant is that
the learned trial court failed to appreciate the true import
of the interim relief sought which squarely qualifies as
'urgent interim relief' within the meaning of Section 12-A
of the Act. Learned counsel for the appellant submits
that the suit was accompanied by an application for
interim relief, which clearly established the urgent nature
of the matter. Consequently, the Trial Court could not
have invoked Section 12-A of the Act to reject the plaint.
22. To buttress its argument, the appellant relies on the
Hon’ble Supreme Court's judgment in “ Novenco
Building and Industry vs. Xero Energy Engineering
Solutions Pvt. Ltd. & Anr”, 2025 SCC Online SC 2278
to contend that a prayer for temporary injunction is
Page 9 RFA No.44/2025
sufficient to demonstrate the urgency required to bypass
pre-institution mediation.
23. On the other hand, Mr. Asav Rajan, learned counsel
representing the respondent, appearing and arguing
virtually, contended that a bare reading of the plaint
reveals a feigned urgency designed solely to bypass the
mandatory pre-institution mediation required by Section
12-A of the Act. He further argued that the appellant’s
own conduct belies any claim of urgency; the appellant
remained completely indolent, took no steps to seek a
renewal of the franchise agreement under the relevant
renewal clause, as such, the learned Trial Court has
rightly passed the order impugned.
24. Heard and perused the record.
25. The appellant claims that it had consistently paid the
contractually mandated royalties and had communicated
its intent to renew the franchise. However, on
29.08.2023, the respondent issued the termination
notice. The appellant avers that this notice was issued
without any prior warning or opportunity to respond to
the allegations, thereby demonstrating mala fide.
Denying any breach of the franchise terms, the appellant
filed the suit before the learned trial court on 28.10.2023
for the following reliefs:
Page 10 RFA No.44/2025
“a) Civil Suit for recovery of Rs.50,00,000/-;
b) Suit for Declaration declaring Termination Notice
dated 29.08.2023 as illegal, null and void
inoperative and non-est in the eyes of law;
c) Mandatory Injunction directing the defendant to
allow the plaintiff to operate the Franchisee
Agreement dated 25.07.020;
d) Permanent Prohibitory Injunction restraining the
defendant from allotting the Franchisee to any other
person in Jammu Province.”
26. The respondent has pleaded that because the dispute is a
commercial one, the suit is barred due to non-compliance
with Section 12-A of the Act relying on the Hon’ble
Supreme Court's ruling in “M/s Patil Automation Pvt.
Ltd. & Ors v. Rakheja Engineers Pvt. Ltd” [(2022) 10
SCC 1].
27. The appellant has countered that the requirement of pre-
institution mediation stands dispensed and waived
because the suit explicitly sought an urgent interim
relief.
28. Disagreeing with the appellant, the learned trial court
allowed the respondent's application and rejected the
plaint on the ground that the mandate of Section 12-A
had not been followed.
29. It is the contention of the appellant that the submission
of an application for temporary injunction per se
evidenced the urgency of the relief prayed for, thereby
exempting the suit from the threshold requirement of
Page 11 RFA No.44/2025
pre-institution mediation envisioned by Section 12-A of
the Act.
30. In M/s Patil Automation Pvt Ltd and others v.
Rakheja Engineers Pvt. Ltd., [(2022) 10 SCC 1], the
Hon’ble Apex Court has held :
“94. On a consideration of the scheme of Orders 4, 5
and 7CPC, we arrive at the following conclusions:
94.1. A suit is commenced by presentation of a
plaint. The date of the presentation in terms of
Section 3(2) of the Limitation Act, 1963 is the date of
presentation for the purpose of the said Act. By
virtue of Order 4 Rule 1(3), institution of the plaint,
however, is complete only when the plaint is in
conformity with the requirement of Order 6 and
Order 7.
94.2. When the court decides the question as to
issue of summons under Order 5 Rule 1, what the
court must consider is whether a suit has been duly
instituted.
94.3. Order 7 Rule 11 does not provide that the
court is to discharge its duty of rejecting the plaint
only on an application. Order 7 Rule 11 is, in fact,
silent about any such requirement. Since summon is
to be issued in a duly instituted suit, in a case where
the plaint is barred under Order 7 Rule 11(d), the
stage begins at that time when the court can reject
the plaint under Order 7 Rule 11. No doubt it would
take a clear case where the court is satisfied. The
Court has to hear the plaintiff before it invokes its
power besides giving reasons under Order 7 Rule 12.
In a clear case, where on allegations in the suit, it is
found that the suit is barred by any law, as would be
the case, where the plaintiff in a suit under the Act
does not plead circumstances to take his case out of
the requirement of Section 12-A, the plaint should
be rejected without issuing summons. Undoubtedly,
on issuing summons it will be always open to the
defendant to make an application as well under
Order 7 Rule 11. In other words, the power under
Order 7 Rule 11 is available to the court to be
exercised suo motu.
xx xxxxxxxxxxxx
113. Having regard to all these circumstances, we
would dispose of the matters in the following
manner:
113.1. We declare that Section 12-A of the Act is
mandatory and hold that any suit instituted
Page 12 RFA No.44/2025
violating the mandate of Section 12 -A must be
visited with rejection of the plaint under Order 7
Rule 11. This power can be exercised even suo motu
by the court as explained earlier in the judgment.
We, however, make this declaration effective from
20-8-2022 so that stakeholders concerned become
sufficiently informed.
113.2. Still further, we however direct that in case
plaints have been already rejected and no steps have
been taken within the period of limitation, the
matter cannot be reopened on the basis of this
declaration. Still further, if the order of rejection of
the plaint has been acted upon by filing a fresh suit,
the declaration of prospective effect will not avail the
plaintiff.
113.3. Finally, if the plaint is filed violating Section
12-A after the jurisdictional High Court has declared
Section 12-A mandatory also, the plaintiff will not be
entitled to the relief.
31. In Yamini Manohar v. T.K.D. Keerthi , [(2024) 5 SCC
815], the Hon’ble Apex Court has held as under:
“10. We are of the opinion that when a plaint is filed
under the CC Act, with a prayer for an urgent
interim relief, the commercial court should examine
the nature and the subject-matter of the suit, the
cause of action, and the prayer for interim relief. The
prayer for urgent interim relief should not be a
disguise or mask to wriggle out of and get over
Section 12-A of the CC Act. The facts and
circumstances of the case have to be considered
holistically from the standpoint of the plaintiff. Non-
grant of interim relief at the ad interim stage, when
the plaint is taken up for registration/admission and
examination, will not justify dismissal of the
commercial suit under Order 7 Rule 11 of the Code;
at times, interim relief is granted after issuance of
notice. Nor can the suit be dismissed under Order 7
Rule 11 of the Code, because the interim relief, post
the arguments, is denied on merits and on
examination of the three principles, namely : (i)
prima facie case, (ii) irreparable harm and injury,
and (iii) balance of convenience. The fact that the
court issued notice and/or granted interim stay may
Page 13 RFA No.44/2025
indicate that the court is inclined to entertain the
plaint.
11. Having stated so, it is difficult to agree with the
proposition that the plaintiff has the absolute choice
and right to paralyse Section 12-A of the CC Act by
making a prayer for urgent interim relief.
Camouflage and guise to bypass the statutory
mandate of pre-litigation mediation should be
checked when deception and falsity is apparent or
established. The proposition that the commercial
courts do have a role, albeit a limited one, should be
accepted, otherwise it would be up to the plaintiff
alone to decide whether to resort to the procedure
under Section 12-A of the CC Act. An “absolute and
unfettered right” approach is not justified if the pre-
institution mediation under Section 12-A of the CC
Act is mandatory, as held by this Court in Patil
Automation [Patil Automation (P) Ltd. v. Rakheja
Engineers (P) Ltd., (2022) 10 SCC 1 : (2023) 1 SCC
(Civ) 545] .
12. The words “contemplate any urgent interim relief”
in Section 12-A(1) of the CC Act, with reference to
the suit, should be read as conferring power on the
court to be satisfied. They suggest that the suit must
“contemplate”, which means the plaint, documents
and facts should show and indicate the need for an
urgent interim relief. This is the precise and limited
exercise that the commercial courts will undertake,
the contours of which have been explained in the
earlier paragraph(s). This will be sufficient to keep in
check and ensure that the legislative object/intent
behind the enactment of Section 12-A of the CC Act
is not defeated.”
32. In M/s Dhanbad Fuels Private Ltd. v. Union of India,
[(2025) 9 SCC 424 ], the Hon’ble Apex Court has
observed as under:
“71. In light of the aforesaid discussion, we
summarise our findings as under:
Page 14 RFA No.44/2025
71.1. The decision of this Court in Patil
Automation [Patil Automation (P) Ltd. v. Rakheja
Engineers (P) Ltd., lays down the correct position of
law as regards Section 12-A of the 2015 Act by
holding it to be mandatory in nature.
71.2. As held in para 104 of the decision in Patil
Automation , the declaration of the mandatory
nature of Section 12-A of the 2015 Act relates back
to the date of the amending Act.
71.3. As held in para 113.1 of the decision in Patil
Automation, any suit which is instituted under the
2015 Act without complying with Section 12 -A is
liable to be rejected under Order 7 Rule 11.
However, this declaration applies prospectively to
suits instituted on or after 20-8-2022.
71.4. A suit which contemplates an urgent interim
relief may be filed under the 2015 Act without first
resorting to mediation as prescribed under Section
12-A of the 2015 Act.
71.5. Unlike Section 80(2)CPC, leave of the court is
not required to be obtained before filing a suit
without complying with Section 12-A of the 2015
Act.
71.6. The test for “urgent interim relief” is if on an
examination of the nature and the subject-matter of
the suit and the cause of action, the prayer of urgent
interim relief by the plaintiff could be said to be
contemplable when the matter is seen from the
standpoint of the plaintiff.
71.7. The Courts must also be wary of the fact that
the urgent interim relief must not be merely an
unfounded excuse by the plaintiff to bypass the
mandatory requirement of Section 12-A of the 2015
Act.
71.8. Even if the urgent interim relief ultimately
comes to be denied, the suit of the plaintiff may be
proceeded with without compliance with Section 12-
A if the test for “urgent interim relief” is satisfied
notwithstanding the actual outcome on merits.
71.9. Suits instituted without complying with
Section 12-A of the 2015 Act prior to 20-8-2022
cannot be rejected under Order 7 Rule 11 on the
ground of non-compliance with Section 12-A unless
Page 15 RFA No.44/2025
they fall within the exceptions stipulated in paras
113.2 and 113.3 of the decision in Patil Automation.
71.10. In suits instituted without complying with
Section 12-A of the 2015 Act prior to 20-8-2022
which are pending adjudication before the trial
court, the court shall keep the suit in abeyance and
refer the parties to time-bound mediation in
accordance with Section 12-A of the 2015 Act if an
objection is raised by the defendant by filing an
application under Order 7 Rule 11, or in cases where
any of the parties expresses an intent to resolve the
dispute by mediation.”
33. In Novenco Building and Industry v. Xero Energy
Engineering Solutions Private Ltd. and another
reported in 2025 SCC OnLine Sc 2278 , relied upon by
learned counsel for appellant, the Hon’ble Supreme Court
has laid down guidelines for the Trial Courts for rejection
of a plaint while considering the compliance of Section
12-A of the Act. The relevant paragraph is extracted as
under:
“20. The legal test distilled from the aforesaid
decisions for the purposes of rejection of the plaint
and for adjudication of interim relief can be culled
out as follows:
(i) Section 12A mandatorily requires pre-institution
mediation for commercial suits, non-compliance of
which would ordinarily render the plaint
institutionally defective.
(ii) A plaintiff can be exempted from the requirement
of Section 12A only when the plaint and the
documents attached with it clearly show a real need
for urgent interim intervention. A wholesome reading
of the plaint and the material annexed to the plaint
ought to disclose the need for urgent relief.
(iii) The court must look at the plaint, pleadings and
supporting documents to decide whether urgent
interim relief is genuinely contemplated. The court
may also look for immediacy of the peril, irreparable
harm, risk of losing rights/assets, statutory
timelines, perishable subject-matter, or where delay
would render eventual relief ineffective.
Page 16 RFA No.44/2025
(iv) A proforma or anticipatory prayer for urgent
relief used as a device to skip mediation will be
ignored and the court can require the parties to
comply with Section 12A of the Act.
(v) The court is not concerned with the merits of the
urgent relief, but if the relief sought seems to be
plausibly urgent from the standpoint of the plaintiff
the court can dispense with the requirement under
Section 12A of the Act.”
34. The legal position discernible from the various judgments
of the Hon’ble Supreme Court cited hereinabove is that
the mandate of pre-institution mediation under Section
12-A of the Act is absolute and compulsory. Where a
plaintiff fails to adhere to this statutory mandate with
respect to institution of suit that does not contemplate
urgent interim relief, the plaint is liable to be rejected
under Order VII Rule 11 of the CPC. In determining
whether an urgent interim relief is indeed involved and
warranted, a court is supposed to examine specific facts
pleaded and the documents appended to the plaint for
adopting a holistic approach from the plaintiff’s
perspective. Simultaneously, a duty is cast upon the
court to ensure that the mandate of Section 12-A of the
Act is not bypassed through crafty drafting or the mere
inclusion of a prayer for urgent interim relief. The
urgency contemplated by the suit must be real and
substantial, rather than superfluous or cosmetic.
Page 17 RFA No.44/2025
35. Simply stated, a prayer for interim relief must not be a
camouflage to evade the statutory obligation of
mediation.
36. We shall now examine whether the appellant has
successfully satisfied the parameters laid down by the
Apex Court as adverted to hereinabove.
37. At the risk of repetition, we reiterate that the principal
reliefs sought by the appellant in the underlying suit
include a mandatory injunction directing the respondent
to allow the appellant to operate the outlet in accordance
with franchise agreement dated 25.07.2020, alongside a
permanent prohibitory injunction restraining the
respondent from allotting the said franchise to any third
party within the Jammu Province.
38. Pursuant to the franchise agreement dated 25.07.2020,
the term of operation for franchise unit was fixed at three
years from the date of the outlet's launch. Although the
respondent terminated the appellant’s franchise vide the
termination notice dated 29.08.2023, the record indicates
that prior to that date the appellant had never served any
prior notice upon the franchisor (the respondent) seeking
to renew the operation period of the franchise unit. In
this context, clause 3.2 of the franchisee agreement is
extracted as under:
Page 18 RFA No.44/2025
“3.2Franchisee may at its option renew this
franchisee for additional period of Two (02) years
provided that at the time of the renewal,
Franchisee need to pay a non refundable
renewal fee of Rs.50,000 (fifty Thousand) which
is Exclusive of the applicable GST at the time of
renewal of this agreement:
3.2.1Franchisee gives Franchisor notice of such
election to renew not less than six (6) months
nor more than twelve (12) months prior to the
end of the initial term;”
39. Under Clause 3.2.1, the appellant was contractually
obligated to notify the respondent of its election to renew
between six and twelve months’ window period prior to
the expiry of the franchise’s initial term. No documentary
evidence has been produced to show that any such notice
was issued. In fact, learned counsel for the appellant has
fairly conceded that no such requisite notice of election to
renew was ever served from its end to the respondent.
40. If the appellant was genuinely interested in continuing
the franchise business, it should have timeously
exercised its option under the franchise agreement.
Instead, it is only after receiving the termination notice
that the appellant manufactured a superficial urgency in
the plaint to bypass the statutory mandate through an
application for interim relief.
41. We have no hesitation in holding that the appellant's
failure to exercise its renewal option under Clause 3.2.1
of the franchise agreement disentitles it to claim any
Page 19 RFA No.44/2025
urgent interim relief against the termination notice. In
fact, the plaint explicitly seeks the recovery of Rs. 50.00
Lakhs as damages for illegal termination. Given that the
appellant’s primary remedy resolves into a quantifiable
monetary claim, the injunctive reliefs sought are nothing
but an afterthought, designed to manufacture an illusion
of urgency solely to bypass the pre-institution mediation
mandated by Section 12-A of the Act.
42. Having examined the impugned order passed by the
learned Trial Court, we find no error or illegality therein
warranting our interference. The appeal, being completely
devoid of merit, is accordingly, dismissed.
(Rahul Bharti) (Rajnesh Oswal)
Judge Judge
Srinagar
04.06.2026
Ajaz Ahmad, Secy
Whether approved for reporting? Yes
Legal Notes
Add a Note....