As per case facts, a promoter and an allottee filed cross-appeals against an Appellate Tribunal judgment concerning a flat booking. The originally planned flat became unconstructible due to revised plans. ...
Neeta Sawant SA-116 OF 2025
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CIVIL APPELLATE JURISDICTION
SECOND APPEAL NO. 116 OF 2025
WITH
INTERIM APPLICATION NO. 7688 OF 2025
JP Builders and Developers through
its Proprietor Jayant Shashikant Parikh ….. Appellant
: Versus :
Santosh Amarsingh Sandhu …. Respondent
Alongwith
SECOND APPEAL NO. 603 OF 2025
Santosh Amarsingh Sandhu ….. Appellant
: Versus :
JP Builders and Developers through
its Proprietor Jayant Shashikant Parikh ….Respondent
Mr. Vishal Kanade with Mr. Rajesh Vanzara i/b. S.K. Legal Associates
LLP, for the Appellant in Second Appeal No. 116 of 2025 and for
Respondent in Second Appeal No.603 of 2025.
Mr. Kunal R. Maskar, for the Appellant in Second Appeal No.603 of 2025
and for Respondent in Second Appeal No.116 of 2025.
CORAM : SANDEEP V. MARNE, J.
JUDGMENT RESD. ON : 16 September 2026.
JUDGMENT PRON. ON : 23 September 2026.
_____________________________________________________________________________
PAGE NOS. 1 of 30
23 September 2026
Neeta Sawant SA-116 OF 2025
JUDGMENT:
1) These are cross Appeals �led by the developer and by the
allottee challenging the judgment and order dated 22 October 2024
passed by the Maharashtra Real Estate Appellate Tribunal, Mumbai
(Appellate Tribunal) thereby dismissing the Appeal of the promoter and
partly allowing the Appeal preferred by the allottee. While upholding the
Order dated 8 October 2020 passed by the Maharashtra Real Estate
Regulatory Authority, Mumbai, (Maha RERA). The Appellate Tribunal
has also directed the promoter to pay interest to the allottee on amount
of Rs.12,30,000/- w.e.f. 12 July 2016 till the date of possession and to
adjust the amount of interest against the balance payment payable in
respect of the �at in question.
2) A brief reference to the facts of the case would be necessary.
By Agreement of Lease dated 14 May 2004, the City and Industrial
Development Corporation (CIDCO) agreed to grant lease of land bearing
Plot No.1 admeasuring 8200 sq.mts, Sector No.19, Airoli, Navi Mumbai for
a tenure of 60 years for residential use to Airoli Cooperative Housing
Society Ltd. The said Society was later divided into two distinct societies,
namely, Airoli Co-operative Housing Society Ltd. and Nilamba ri
Cooperative Housing Society Ltd., by dividing the plots into two parts,
each admeasuring 4,100 sq. m. Plot 1 remained with Airoli CHSL, which
executed Development Agreement dated 27 April 2004 with M/s. JP
Builders and Developers (promoter). The promoter accordingly
constructed building on Plot No.1 having 2 wings, Wing-C and Wing-D
and obtained Occupancy Certi�cate from Navi Mumbai Municipal
_____________________________________________________________________________
PAGE NOS. 2 of 30
23 September 2026
Neeta Sawant SA-116 OF 2025
Corporation on 17 January 2007. Despite construction of Wings C and D,
there was balance FSI of 824.00 sq.mts on Plot No. 1.
3) Airoli Cooperative Housing Society Ltd. decided to avail the
bene�t of developing and maintaining a garden on Plot No. 11B, which
was affected by High Tension Electricity Transmission Line and received
FSI in resepct of Plot No.11B to be utilized on its Plot No.1. Accordingly
CIDCO allotted additional FSI admeasuring 4313.94 sq.mts to Airoli
Cooperative Housing Society Ltd. under a scheme of transfer of FSI of
land beneath High Tension Line (Plot No.11B) for consumption on Plot
No.1 subject to condition of maintenance of a garden by the society on
Plot No.11B. It appears that the society got aggrieved by allotment of FSI
of only 4313.94 sq.mts and claimed entitlement in respect of FSI of 10,450
sq.mts and �led a Writ Petition in this Court in the year 2009. During
pendency of the Writ Petition, the promoter decided to exploit the
balance FSI of 824.00 sq.mts available on Plot No.1 and accordingly
secured Commencement Certi�cate dated 14 July 2011 for carrying out
construction to the tune of 745.472 sq.mts. The promoter also prepared a
tentative plan by taking into consideration additional FSI made available
to the Society for construction of a building comprising of ground plus 30
�oors with 2 wings, A and B during pendency of the writ petition. The
promoter commenced bookings in the year 2009-10 giving idea to the
prospective purchasers about pendency of the Writ Petition.
4) Mrs. Vandana Nagendra Kharatmol and Mr. Nagendra Piraji
Kharatmol (Kharatmols) showed interest in purchasing Flat No.502 on
the 5th �oor of the proposed A-wing building at consideration of
_____________________________________________________________________________
PAGE NOS. 3 of 30
23 September 2026
Neeta Sawant SA-116 OF 2025
Rs.48,75,000/-. They paid token amount of Rs.3,00,000/- for reserving the
�at. Accordingly, Letter of Allotment was issued to Kharatmols by the
Promoter on 28 May 2011. Kharatmols thereafter paid further sum of
Rs.9,30,000/- and by 2 March 2012 the total consideration paid by
Kharatmols was to the tune of Rs.12,30,000/-.
5) Kharatmols however lost interest in purchasing Flat No. A-
502 as construction of Building A could not commence due to pendency
of the writ petition �led by the society. It appears that some private
arrangement was made by Kharatmols with Mr. Santosh Sandhu
(allottee) for transfer of booking of Flat No. A-502. The promoter was
accordingly requested by Kharatmols to transfer the booking of Flat No.
A-502 in the name of the allottee. According to the promoter, Kharatmols
made a request for refund of amount of Rs.12,30,000/-, which was
supposed to be paid by the allottee. Accordingly, fresh allotment letter
dated 11 July 2013 was issued in favour of the allottee for Flat No. A-502
and the allottee paid an amount of Rs.12,30,000/- to the promoter.
6) On 13 January 2016, Writ Petition No. 4325 of 2009 was
�nally decided by this Court. It appears that the Society was unsuccessful
in securing higher FSI, and accordingly, CIDCO executed a Supplementary
Agreement dated 7 April 2017, permitting consumption of FSI of Plot No.
11B on Plot No. 1 and the construction of a garden by the Society on Plot
No. 11B. Accordingly, the Municipal Corporation issued revised
Commencement Certi�cate dated 26 April 2019 for construction of
building of ground plus 19 �oors consisting of 93 residential units.
According to the promoter, originally planned A-502 could not be
constructed due to change in the plans.
_____________________________________________________________________________
PAGE NOS. 4 of 30
23 September 2026
Neeta Sawant SA-116 OF 2025
7) After coming into effect of the Real Estate (Regulation and
Development) Act, 2016, (RERA) the promoter registered the Project on
31 July 2017. After securing revised Commencement Certi�cate, the
promoter issued letter dated 3 May 2019 to the allottee calling him upon
to pay stamp duty and registration charges for execution of Agreement for
Sale. The allottee was also called upon to choose any other �at in the
building. The allottee chose Flat No.1208 on 12th �oor of the building
which the promoter agreed to allot subject to payment of �oor rise
charges of Rs.1,75,000/-. The promoter issued one more letter dated 28
May 2019 to the allottee for payment of stamp duty and registration
charges for execution of the Agreement for Sale. It appears that the
allottee was facing �nancial crunch and was not in a position to pay the
stamp duty. He requested the promoter to bear the stamp duty with a
promise to return the same upon disbursal of loan. The promoter however
did not accept the request. The promoter �nally terminated the
transaction by notice dated 30 July 2019.
8) The allottee �led complaint before the Maharashtra Real
Estate Regulatory Authority in November 2019. By order dated 6 March
2020, Maha RERA granted interim relief in favour of the allottee directing
promoter to execute registered Agreement for Sale with the allottee. By
�nal order dated 8 October 2020, Maha RERA disposed of the Complaint
directing implementation of the interim order.
9) Both the promoter, as well as the allottee got aggrieved by
�nal order dated 8 October 2020 passed by the Maha RERA and preferred
their respective Appeals before the Appellate Tribunal. By common
judgment and order dated 22 October 2024, the Appellate Tribunal has
_____________________________________________________________________________
PAGE NOS. 5 of 30
23 September 2026
Neeta Sawant SA-116 OF 2025
dismissed the Appeal preferred by the promoter and has partly allowed
the Appeal preferred by the allottee. While upholding the order of the
Maha RERA, the Appellate Tribunal has directed the promoter to pay
interest to the allottee on amount of Rs.12,30,000/- at the rate of SBI
Marginal Cost Lending Rate (MCLR) plus 2% w.e.f. 12 July 2016 till the
date of possession. The Appellate Tribunal has directed adjustment of the
interest amount against the balance consideration payable by the allottee
at the time of handing over possession of the �at. The promoter is
directed to hand over possession of the �at chosen by the allottee upon
completion of the Project. The promoter is restrained from creating any
third party rights and interest in the subject �at. The promoter is also
restrained from charging any amount on account of �oor rise.
10) Though the allottee has, by and large, succeeded before the
Appellate Tribunal, he is also aggrieved by the order of the Appellate
Tribunal and has accordingly �led Second Appeal No.603 of 2025. The
promoter has �led Second Appeal No.116 of 2025 challenging the order of
the Appellate Authority.
11) By order dated 16 September 2026, this Court has admitted
the Appeals by formulating the following questions of law :
(i) Whether the allottee proved before Maha RERA and the Appellate
Tribunal that he had paid the requisite stamp duty for execution and
registration of the agreement?
(ii) Whether the developer was justi�ed in terminating the allotment of
�at by notice dated 30 July 2019?
(iii) Whether the Maha RERA and the Appellate Tribunal are justi�ed in
directing execution of agreement by the developer in favour of the
allottee in respect of the �at of choice of allottees?
_____________________________________________________________________________
PAGE NOS. 6 of 30
23 September 2026
Neeta Sawant SA-116 OF 2025
(iv) Whether the Appellate Tribunal is justi�ed in directing payment of
interest on amount of Rs. 12,30,000/- and adjustment of interest amount
against balance amount payable by the allottee?
(v) Whether the Maha RERA and Appellate Tribunal are justi�ed in
rejecting allottee’s in contention that the consideration paid by the
earlier allotees – Vandana Nagendra Kharotmal and Nagen dra
Kharotmal ought to be adjusted in the transaction entered into by the
allottee with the developer?
12) Mr. Kanade, the learned counsel appearing for the promoter
submits that both Maha RERA, as well as the Appellate Tribunal have
grossly erred in directing the promoter to execute Agreement for Sale and
to allot a �at of choice to the allottee. He submits that the Agreement for
Sale could not be executed on account of failure to pay stamp duty and
registration charges by the allottee. He takes me through various
correspondence before issuance of termination notice dated 30 July 2019.
He submits that by email dated 30 June 2019, the all ottee had
emphatically expressed inability to pay the stamp duty due to �nancial
dif�culties. That the promoter was always ready and willing to execute
the Agreement for Sale. That on account of non-cooperation by the
allottee, the transaction was required to be terminated vide notice dated
30 July 2019. That the promoter refunded the amount of Rs.11,07,000/-
after deducting amount of Rs.1,23,000/- towards earnest money deposit.
That the allottee failed to encash the cheques towards refund of booking
amount. That in such circumstances, the promoter cannot be held
responsible for non-execution of the agreement. That therefore both
interim as well as �nal orders passed by the Maha RERA are clearly
perverse since both the orders do not even take into consideration the
factual situation indicating absence of interest on the part of the allottee
_____________________________________________________________________________
PAGE NOS. 7 of 30
23 September 2026
Neeta Sawant SA-116 OF 2025
to complete the transaction. That the Maha RERA and Appellate Tribunal
erroneously exercised jurisdiction in the present case. That in absence of
Agreement for Sale, direction for payment of interest could not have been
issued by the Appellate Tribunal. That having refused to avail allotment
of alternate �at, the allottee could not have been granted relief by Maha
RERA and by the Appellate Tribunal. That both the orders are passed in
gross ignorance of the material available on record and are accordingly
perverse. He prays for setting aside the orders passed by the Maha RERA
and by the Appellate Tribunal.
13) So far as the Appeal preferred by the allottee is concerned,
Mr. Kanade submits that Kharatmols had requested for refund of the
booking amount paid and that the same has been rightly refunded by the
promoters to Kharatmols. That so far as promoter is concerned, there was
no agreement for adjustment of amount paid by Kharatmols w hile
transferring booking of �at in the name of the allottee. That a fresh and
new allotment vide letter dated 11 July 2013 was made in the name of the
allottee having no connection with the transaction of Kharatmols. That
therefore the Appeal preferred by the allottee deserves to be dismissed by
taking into consideration the concurrent �ndings of facts recorded by
Maha RERA and by the Appellate Tribunal.
14) Per-contra, Mr. Maskar the learned counsel appearing for the
allottee opposes the appeal preferred by the promoter. He submits that
the Appellate Tribunal has rightly appreciated the position that the
promoter failed to execute the Agreement for Sale with the allottee
thereby violating the provisions of Section 13 of the RERA. That the
demand for payment of further consideration by the promoter without
_____________________________________________________________________________
PAGE NOS. 8 of 30
23 September 2026
Neeta Sawant SA-116 OF 2025
executing Agreement for Sale was clearly illegal. That the allotment is
ultimately cancelled for non-payment of further amount of consideration.
Mr. Maskar further submits that the allottee paid the stamp duty of
Rs.4,35,000/- and registration charges of Rs.30,000/- and intimated the
same to the promoter by email dated 9 July 2019. That the promoter has
erroneously terminated the transaction by falsely recording that the
payment was not made available to it. He submits that by email dated 9
July 2019, the payment receipts were forwarded to the promoter. That
termination of transaction by the promoter is therefore rightly held to be
erroneous by Maha RERA and the Appellate Tribunal. He therefore
submits that there is no warrant for interference in the order passed by
the Appellate Tribunal in the appeal preferred by the Promoter. He prays
for dismissal of the promoter’s appeal.
15) So far as the appeal preferred by the allottee is concerned,
Mr. Maskar submits that there was clear understanding between the
allottee and Kharatmols for adjustment of consideration paid by
Kharatmols to the promoter against purchase transaction executed by the
allottee. He submits that under the MOU, the allottee paid various
amounts from time to time to Kharatmols totally aggregating to Rs.
34,55,000/-. That therefore the allottee is entitled to adjustment of entire
amount of Rs.12,30,000/- paid by Kharatmols to the Promoter. That the
allottee has stepped into the shoes of Kharatmols and is entitled to all
rights of Kharatmols. In support, he relies on judgment of the Apex Court
in Laureate Buildwell Private Limited Versus. Charanjeet Singh
1
. That
therefore the total amount paid by the allottee to the promoter in respect
1 (2021) 20 SCC 401
_____________________________________________________________________________
PAGE NOS. 9 of 30
23 September 2026
Neeta Sawant SA-116 OF 2025
of the transaction is Rs.28,75,281/-. He submits that to this extent, the
order passed by the Arbitral Tribunal is clearly erroneous and deserves to
be set aside.
16) Rival contentions urged on behalf of the parties now fall for
my consideration.
17) The case involves a failed transaction of purchase of �at by
the allottee from the promoter. From the history narrated above, it is
clear that the promoter was expecting allotment of additional FSI
admeasuring 10,450 sq.mts to Airoli CHSL from CIDCO and accordingly
had made plans for construction of 30 storey building. Based on those
plans, the promoter entered into transaction with Kharatmols for sale of
Flat No.502 on 5th �oor in A-Wing for consideration of Rs. 48,75,000/-.
Kharatmols paid amount of Rs. 12,30,000/- to the promoter, who issued
Letter of Allotment dated 28 May 2011. Since Kharatmols lost interest in
purchasing the �at on account of non-progress of construction of the
building due to pendency of Writ Petition No.4325 of 2009, it appears that
the allottee stepped in and showed interest in purchasing Flat No.A-502.
18) The allottee relies on MOU dated 27 June 2013 executed with
Kharatmols under which he claims that he had agreed to pay amount of
Rs.29,00,000/- to Kharatmols for transfer of rights under allotment letter
dated 28 May 2011 in respect of Flat No.A-502. An MOU dated 27 June
2013 is claimed to have been executed between the allottee and
Kharatmols under which an amount of Rs.6,80,000/- was to be paid in
cheque and amount of Rs.22,20,000/- was to be paid in c ash to
_____________________________________________________________________________
PAGE NOS. 10 of 30
23 September 2026
Neeta Sawant SA-116 OF 2025
Kharatmols. The allottee claims to have paid various amounts to
Kharatmols totaling to Rs.34,55,000/-.
19) After the allottee approached the promoter for transfer of the
booking, the Promoter issued a fresh allotment letter dated 11 July 2013
in favour of the allottee agreeing to allot Flat No. A-502 for consideration
of Rs.48,75,000/-. The allotment letter records payment of amount of
Rs.12,30,000/- by the allottee to the promoter.
20) As observed above, the originally planned building of ground
plus 30 storey could not be constructed on account of society not securing
rights in respect of higher FSI and accordingly the building was required
to be scaled down to ground plus 19 �oors. Thus, Flat No. A-502 which
was earlier allotted to Kharatmols and later allotted to the allottee has
actually not been constructed. The promoter called upon the allottee to
select some other �at and called upon the allottee to pay stamp duty and
registration charges. There is dispute amongst the parties as to whether
the allottee paid the stamp duty and registration charges or not. Alleging
non-payment of stamp duty and registration charges, the promoter has
cancelled the transaction by notice dated 30 July 2019.
21) In the light of the above factual position, Maha RERA initially
passed interim order dated 6 March 2020 directing the promoter to
execute Agreement for Sale with the allotteee. The interim order is
thereafter made absolute on 8 October 2020 while disposing of the
Complaint, which envisages allottee to choose the �at and the Promoter
to execute the Agreement for Sale in respect thereof. The Appellate
Tribunal has bettered the relief granted by Maha RERA in favour of the
_____________________________________________________________________________
PAGE NOS. 11 of 30
23 September 2026
Neeta Sawant SA-116 OF 2025
allottee by directing payment of interest on the amount of Rs.12,30,000/-
and adjustment thereof against balance consideration.
22) I now proceed to decide the �ve questions framed at the time
of admission of the appeals.
Question No.1
23) The promoter claims that the allottee did not pay stamp duty
and registration charges and that therefore the promoter was justi�ed in
terminating the transaction vide notice dated 30 July 2019. It is
contended on behalf of the promoter that both Maha RERA, as well as
Appellate Tribunal have grossly erred in holding that the transaction is
cancelled on account of failure to pay further consideration by the
allottee. Mr. Kanade submits that the real reason for termination is
refusal by the allottee to pay stamp duty and registration charges. On the
other hand, Mr. Maskar has contended that stamp duty of Rs.4,35,000/-
and registration fees of Rs.30,000/- was infact paid by the allottee. My
attention is invited to the email dated 9 July 2019 by which the allottee
apparently forwarded the payment receipts in respect of payments made
towards stamp duty of Rs.4,35,000/- and registration fees of Rs.30,000/-
and called upon the promoter to complete the registration process within
3 days. He also requested to add his mother's name in the agreement. The
email dated 9 July 2019 contains four attachments, including two
documents relating to payment of stamp duty.
24) On the other hand, Mr. Kanade has invited my attention to
termination notice dated 30 July 2019 in which it was contended as under:
_____________________________________________________________________________
PAGE NOS. 12 of 30
23 September 2026
Neeta Sawant SA-116 OF 2025
Your Client was given 15 days' time to pay the balance consideration of
Rs. 12,95,000/- as per the schedule of MahaRERA and also to execute the
Agreement for Sale by paying the stamp duty and registration charges. It
appears that your Client has not made the payment to my Client,
although in your Reply you have mentioned that your Client has made
the payment of Rs.4,65,000/- towards stamp duty. However, no payment
advice has been made available to my Client so far.
25) It is therefore sought to be suggested on behalf of the
promoter that though email dated 9 July 2019 claimed payment of stamp
duty and registration charges, proof thereof was never submitted to the
promoter. However, Mr. Maskar has placed on record an additional
compilation containing four documents. The �rst document is an extract
of account of the allottee with Punjab National Bank (PNB), from which it
appears that the amount towards stamp duty or registration charges was
transferred to the concerned account of the PNB from where the challans
were to be generated. The second document is again account statement of
the allottee which indicates transfer of amount of Rs.4,65,000/- to the
concerned account of PNB. Based on these two documents, the allottee
claims that the said entry is for payment of stamp duty and registration
charges of Rs.4,65,000/-.
26) The third document however makes it clear that the amount
was never credited in the account of Stamp Authority and Registration
Authority and the amount remained with the bank itself. On 18 January
2020, the allottee submitted following letter to his bank :
I SANTOSH AMARSINGH SANDHU, HAS DONE NEFT TRANSACTION
OF RS. 4,65,000.00/- ( FOUR LAKHS SIXTY FIVE THOUSAND) ON
09/07/2019 TO YOUR ACCOUNT NUMBER 413800MG00000011, BANK
NAME : PUNJAB NATIONAL BANK, BRANCH CBD, BELAPUR (4138)
FOR PAYMENT OF STAMP DUTY AND REGISTRATION CHARGES. BUT I
WAS UNAWARE ABOUT GENERATING CHALLAN BASED ON WHICH E-
_____________________________________________________________________________
PAGE NOS. 13 of 30
23 September 2026
Neeta Sawant SA-116 OF 2025
SBTR WILL BE GENERATED. SO WHEN I VISITED YOUR BRANCH
TODAY, I WAS INFORMED THAT YOUR BRANCH HAS STOPPED
ISSUING E-SBTR. SO I REQUEST YOU TO REFUND THE ABOVE
AMOUNT TO MY ACCOUNT NO. 5894000100026669 (AIROLI BRANCH ).
I SHALL DO NEFT FROM THE AIROLI BRANCH TO THE MAHA GOVT
STATUTORY E-PAYMENT ACCOUNT.
27) Thus, letter dated 18 January 2020 itself contains a clear
admission that the challan itself was not generated nor e-payment receipt
was generated. The allottee requested for transferring the amount back to
his account. The bank accordingly re-transferred the amount of
Rs.4,65,000/- to the allottee by reversing the challan amount, which is
clear from the fourth document in the compilation.
28) Thus, from the documents placed on record, it becomes
dif�cult to hold that the allottee actually ever paid stamp duty or
registration charges to the concerned authorities as claimed in the email
dated 9 July 2019. If stamp duty and registration charges were paid,
speci�c challans to that effect would have been generated which are
required to be attached with the Agreement for Sale at the time of
execution and registration thereof.
29) On 9 July 2019 itself, the promoter’s advocate had issued
notice to the allottee alleging non-payment of stamp duty. The advocate
of the allottee gave response on 19 July 2019 vaguely stating that the
allottee had already paid stamp duty. In the termination notice dated 30
July 2019, the promoter emphatically stated that no proof of payment was
made available to it evidencing payment of Rs. 4,65,000/- towards stamp
duty and registration charges. After receipt of termination notice, as well
as after receipt of cheques towards refund of amount of Rs.11,07,000/- the
_____________________________________________________________________________
PAGE NOS. 14 of 30
23 September 2026
Neeta Sawant SA-116 OF 2025
allottee responded vide letter dated 30 October 2019 in which he failed to
produce any evidence of actual payment of stamp duty and registration
charges.
30) From the documents on record, it becomes dif�cult to believe
that the allottee actually made payment of stamp duty and registration
charges. Mere making provision for stamp duty and registration charges
and transfer of the amount to the banker does not mean that stamp duty
and registration charges were actually paid by the allottee. He did not pay
stamp duty and registration charges to the promoter nor there is any
evidence of transfer of amount of Rs.4,65,000/- to the accounts of the
concerned authorities. Atleast after receipt of advocates' notice dated 9
July 2019 alleging non-payment of stamp duty and registration charges,
the allottee ought to have approached the bank to verify whether the
necessary challans were generated and ought to have produced copies of
such challans to the Promoter. In the absence of proof of payment of the
stamp duty and registration charges to be annexed to the Agreement for
Sale, the promoter was left with no alternative but to refrain from
proceeding with the registration of the Agreement for Sale.
31) The conduct of the allottee also makes it dif�cult to believe
that he had actually paid the stamp duty and registration charges. After
sending email dated 9 July 2019 stating that 'I have done payment to
MAHA GOVT STATUTORY EPAYMENT....' and after receipt of notice
dated 9 July 2019, the allottee did not make any efforts to ensure that
necessary proof of payment of stamp duty is generated. He never
approached the bank to �nd out whether the challan is issued. He instead
approached the advocate for issuing reply to the notice on 19 July 2019.
_____________________________________________________________________________
PAGE NOS. 15 of 30
23 September 2026
Neeta Sawant SA-116 OF 2025
The ordinary conduct would have been to approach the of�ce of the
promoter by producing challans for payment of stamp duty an d
registration charges and to secure draft of the Agreement for Sale for
further processing and registration thereof. None of these actions were
undertaken by the allottee, who merely waited for the promoter to take
the necessary steps, leaving the promoter with no alternative but to
terminate the transaction on 30 July 2019. Even after 30 July 2019, the
allottee made no efforts to �nd out as to whether the challans of stamp
duty and registration charges are in fact generated or not. He approached
the bank only on 18 January 2020 seeking refund of the amount stating
that he would do NEFT from Airoli Branch to Maharashtra Government
Statutory e-payment account. However, he failed to act in accordance
with the letter dated 18 January 2020, and there is nothing on record to
indicate that after 18 January 2020, he made any payment towards stamp
duty, despite allegedly having received a refund.
32) Maha RERA as well as Appellate Tribunal failed to conduct
enquiry into the aspect as to whether the stamp duty and registration
charges were indeed paid by the allottee or not. In the entire orders of
Maha RERA and the Appellate Tribunal, there is no discussion on the
issue of payment of stamp duty and registration charges by the allottee.
33) Issue No.1 is accordingly answered by holding that the
allottee did not make payment of stamp duty and registration charges
before 30 July 2019 when the sale transaction was terminated by the
Promoter.
_____________________________________________________________________________
PAGE NOS. 16 of 30
23 September 2026
Neeta Sawant SA-116 OF 2025
Question Nos. 2 and 3
34) Maha RERA and the Appellate Tribunal have directed the
promoter to execute in favour of the allottee, an agreement in respect of
the �at chosen by the allottee. The initial direction in this regard was
through interim order dated 6 March 2020 passed by Maha RERA. In that
order, the Maha RERA referred to provisions of Section 13 of RERA and
held that since more than 10% of the agreed amount of consideration was
paid by the allottee and since Agreement for Sale was not executed, the
promoter had the liability under Section 13 to execute a registered
Agreement for Sale. Accordingly, Maha RERA directed in paragraph 4 of
order dated 6 March 2020 as under:
4. The MahaRERA has examined the arguments advanced by both the
parties as well as the record. In the present case, the complainant is
seeking relief under section-13 of the RERA for execution of agreement
for sale and admittedly more than 10% amount has been paid by the
complainant for purchase of the said �at and till date, no agreement for
sale has been executed. Therefore, the MahaRERA feels that as per the
provisions of section-13 of the RERA, the respondent is liable to execute
the registered agreement for sale with the complainant under the
provision of section-13 of the RERA. Hence, the MahaRERA directs the
respondent to execute the registered agreement for sale with the
complainant for another �at having equal area as per the choice of the
complainant within a period of 30 days.
35) In the �nal order dated 8 October 2020, Maha RERA did not
record detailed reasons. After recording submissions canvassed by the
rival parties, Maha RERA referred to interim order dated 6 March 2020
and held that since the interim order was not challenged by the promoter,
_____________________________________________________________________________
PAGE NOS. 17 of 30
23 September 2026
Neeta Sawant SA-116 OF 2025
it directed the promoter to comply with the order within 30 days. Maha
RERA held in paragraph 5 of the order as under:
5. MahaRERA has examined the arguments advanced by both the parties
as well as the records. In the present case, prima facie it appears that
there is an interim order passed on 06-03-2020 passed by MahaRERA
wherein speci�c direction was given to the respondent to execute the
agreement for sale with the complainant within a period of 30 days with
respect of another �at having equal area as per the choice of the
complainant. However, the said direction has not yet been complied
with by the respondent. The MahaRERA is also observed that the said
direction was issued after considering the submissions made by both the
parties as well as after perusing the records. Therefore, these averments
made by both the parties need not to be reconsidered. Moreover,
nothing has been brought on record of MahaRERA by either party to get
review of the said interim order. Further after passing of the said order
by MahaRERA there was lockdown declared by the Government due to
Covid-19 pandemic. Therefore, within 30 days period the direction could
not have been complied with by the respondent. Moreover , the
respondent has not challenged the said interim order passed on 6-03-
2020. Therefore, considering all these facts brought on record of
MahaRERA, MahaRERA directs the respondent to comply with the
directions issued by MahaRERA vide interim order dated 06 March 2020
within 30 days from this order.
36) The Appellate Tribunal again referred to provisions of
Section 13 of RERA and held the promoter was not entitled to recover
further payments form the allottee without �rst executing the Agreement
for Sale.
37) The issues of validity of termination of allotment of �at by
notice dated 30 July 2019 and the liability of the promoter to execute the
agreement in favour of the allottee are interconnected. If termination is
held to be valid, there is no question of executing the Agreement for Sale
by the promoter with the allottee. I accordingly proceed to examine
whether termination of transaction vide notice dated 30 July 2019 by the
_____________________________________________________________________________
PAGE NOS. 18 of 30
23 September 2026
Neeta Sawant SA-116 OF 2025
promoter is valid or otherwise. While answering Issue No.1, this Court has
held that the allottee failed to pay stamp duty and registration charges for
execution of the Agreement for Sale. One needs to understand the
background leading to termination notice dated 30 July 2019.
38) After revised Commencement Certi�cate dated 26 April 2019
was issued by Navi Mumbai Municipal Corporation, the promoter issued
notice dated 3 May 2019 to the allottee intimating that the plans were
sanctioned for construction of the building upto 19
th
�oor. Referring to
provisions of RERA, the promoter highlighted the need to execute
registered Agreement for Sale. Accordingly, the promoter called upon the
allottee to execute Agreement for Sale by completing the process of
payment of stamp duty. There was no response from the allottee.
Therefore, a reminder letter dated 28 May 2019 was issued by the
promoter. Again, there was no response from the allottee. Therefore, a
�nal notice dated 24 June 2019 was issued by the promoter to the allottee
granting time of one week to pay the stamp duty and registration charges.
This time, the allottee responded by sending email dated 30 June 2019 in
which he expressed inability to pay the stamp duty as he did not have the
required funds for payment of stamp duty. Instead, he suggested that he
was availing loan of Rs.40 lakhs as against balance liability of only Rs.33
odd lakhs and that therefore payment of stamp duty and registration
charges could be arranged through the loan amount. The allottee
therefore gave two options to the promoter. In option-1, he requested the
promoter to wait for 3 months for arranging the funds for payment of
stamp duty and registration charges. In the second option, he requested
the promoter to bear the stamp duty and registration charges through
_____________________________________________________________________________
PAGE NOS. 19 of 30
23 September 2026
Neeta Sawant SA-116 OF 2025
home loan, which the allottee was going to avail. The relevant portion of
email dated 30 June 2019 reads thus:
Instead I had shown you the sanction letter from SBI Bank Wherein Bank
has agreed to grant me loan of Rs. 40 lakhs which shows that I am
preparing for processing the required formalities for the home for which
I am waiting since years. I am attaching the SBI Sanction letter with this
letter.
Also, to inform you I have to pay you only 33 lakhs(approx.) out of the
agreement value of 48.75 lakhs but I am availing 40 lakhs loan so as to
cover the stamp duty and Registration charges. Now the question arises
of paying the stamp duty.
I clearly explained you that currently I am not having the required cash
for paying the stamp duty, but I gave you 2 options which are as follows:
1. If you are ready to wait for 3 months, I shall manage the funds for
Stamp duty and registration and complete all the required formalities.
2. The 2nd option was if you can't wait for 3 months, and you are in very
much need of money, then you be kind enough to bear the stamp duty
and registration charges from your pocket and claim the same from the
Home loan through your demand letter to the bank from which I am
availing Loan (the process you might be aware of demand request money
from bank).
3. The Bank will disburse the required money only in your name as per
the demand letter. Since all the sanctioned Loan amount will be directly
paid to you there is no question that you will have to suffer, or your
money will be blocked. As soon as you make demand request you will get
your money.
As currently I am short of funds but at the same time Lam ready to get
the amount from bank and even Bank has agreed to grant me loan.
39) The promoter responded by email dated 2 July 2019 calling
upon to the allotte pay the stamp duty and registration charges in the
indicated account.
_____________________________________________________________________________
PAGE NOS. 20 of 30
23 September 2026
Neeta Sawant SA-116 OF 2025
40) As discussed above, though the allottee attempted to pay the
stamp duty, the same remained in the bank account of Punjab National
Bank and never really got transferred to the stamp authorities. The
promoter accordingly served advocate’s notice dated 9 July 2019 granting
last opportunity of 15 days to pay stamp duty and registration charges.
When the promoter had emphatically stated that the stamp duty was not
paid and that the necessary documents to indicate payment of stamp duty
were not provided, the natural conduct of the allottee would have been to
approach the bank and inquire as to why the challans are not generated.
Instead of doing so, the allottee opted to issue advocate’s reply dated 19
July 2019. Since the promoter did not receive any evidence of generation
of challans for payment of stamp duty and registration charges, it
proceeded to issue termination notice dated 30 July 2019. After receipt of
termination notice dated 30 July 2019, the allottee maintained silence for
the next 3 long months, which is the most unusual conduct of a person
who is accused of non-payment of stamp duty. The promoter refunded
the booking amount of Rs. 11,07,000/- after deducting earnest money
deposit of Rs.1,23,000/-. Only after receiving the refund cheque, the
allottee sent response dated 30 October 2019 which is totally silent about
payment of stamp duty and registration charges. After sending response
dated 30 October 2019, there was again a stoic silence by the allottee, who
made no efforts to inquire about non-generation of challans by the Bank.
As observed above, the next action initiated by the allottee is directly on
18 January 2020, when he wrote to the bank for return of amount of
Rs.4,65,000/-. Importantly, even after receiving the return of the amount
_____________________________________________________________________________
PAGE NOS. 21 of 30
23 September 2026
Neeta Sawant SA-116 OF 2025
from the Bank, the allottee made no attempt to pay stamp duty or
registration charges.
41) Considering the above chronology of events, in my view, the
promoter was clearly justi�ed in terminating the transaction by notice
dated 30 July 2019. Both Maha RERA as well as Appellate Tribunal, turned
blind eye to the events that transpired before issuance of termination
notice. They mechanically referred to the provisions of Section 13 of
RERA for holding the promoter responsible for non-execution of the
agreement, ignoring the position that the promoter was always ready and
willing to execute Agreement for Sale. In the present case, the transaction
of booking the �at took place before the advent of RERA. The project got
registered under RERA in 2017. However, there was absence of clarity
about construction of the building and the clarity was achieved only on 26
April 2019 when plans were sanctioned by Navi Mumbai Mu nicipal
Corporation. Immediately after sanction of plans on 26 April 2019, the
promoter wrote to the allottee on 3 May 2019 calling him upon to execute
registered Agreement for Sale. At this juncture there was no demand by
the promoter for payment of further consideration. The promoter issued
three notices dated 3 May 2019, 28 May 2019 and 24 June 2019 requesting
the allottee to execute the Agreement for Sale by paying the stamp duty
and registration charges. Instead of complying with the requisition, the
allottee expressed inability to arrange the funds for payment of stamp
duty and registration charges. Thus, opportunity to execute and register
Agreement for Sale was not availed by the allottee and both Maha RERA
and Appellate Tribunal have egregiously erred in holding the promoter
responsible for non-execution of Agreement for Sale. The promoter
_____________________________________________________________________________
PAGE NOS. 22 of 30
23 September 2026
Neeta Sawant SA-116 OF 2025
thereafter issued further notices on 2 July 2019 and 9 July 2019 again
calling upon the allottee to pay stamp duty and get the Agreement for
Sale executed. Thus, as against 5 notices sent by the promoter for
registration of the agreement, there is one response by the allottee
expressing inability to pay stamp duty and thereafter a false picture being
created about payment of stamp duty vide email dated 9 July 2019.
42) More importantly, after receipt of termination notice dated
30 July 2019, the allottee maintained silence for about 6 long months and
thereafter surreptitiously approached the bank and obtained refund of
amount meant for stamp duty and appropriated the said amount for his
own needs. Though a speci�c representation was made to the bank that
the stamp duty would be paid through the speci�ed means/accounts, no
such attempt was made by the allottee. While seeking retun of the
amount from the Bank, the allottee stated in his letter that “I shall do
NEFT from the Airoli branch to the Maha Govt statutory e-payment account.’
However there is nothing on record to indicate that the allottee paid the
stamp duty after receipt of amount in his bank account. In my view
therefore, the allottee himself is responsible for non-execution of the
Agreement for Sale. The promoter was always ready and willing to
execute the Agreement for Sale. In that view of the mater, termination of
the transaction vide notice dated 30 July 2019 appears to be perfectly in
order. The promoter is not expected to wait endlessly.
43) In the facts of the present case, it appears that the allottee
was not interested in payment of stamp duty. In some cases, the �ats are
hoarded based on allotment letters and then traded in the market. The
allottee himself secured the allotment from other persons. He might be
_____________________________________________________________________________
PAGE NOS. 23 of 30
23 September 2026
Neeta Sawant SA-116 OF 2025
looking forward to similar transaction and was averse to spending monies
on payment of stamp duty and registration charges. Otherwise, the
allottee may not have the funds for making the payment of stamp duty
and registration charges as he speci�cally stated so in his email dated 30
June 2019. It is therefore not known whether the allottee was merely
interested in securing ownership of the �at in his name or was merely
hoarding the �at with the intention of transferring the allotment letter. A
genuine �at purchaser, who is stuck in a project for 6 long years, would
show the necessary alacrity for execution and registration of the
Agreement for Sale. However, in the facts of the present case, it appears
that the allottee had no interest in getting the agreement registered. He
initially showed inability to arrange funds for payment of stamp duty and
registration charges. Though he made some arrangements, the moment
the transaction was cancelled by the promoter, he happily took away the
money from the bank and appropriated the same for his own use. This
conduct on the part of the allottee shows absence of will and desire to
have the agreement executed and registered.
44) In my view therefore, the Maha RERA and Appellate Tribunal
have grossly erred in directing the promoter to execute registered
Agreement for Sale in favour of the allottee.
45) Issues Nos.2 and 3 are thus answered by holding that the
promoter is justi�ed in terminating the allotment of �at by notice dated
30 July 2019 and that the Maha RERA and Appellate Tribunal have erred
in directing execution of the agreement by the Promoter in favour of the
allottee.
_____________________________________________________________________________
PAGE NOS. 24 of 30
23 September 2026
Neeta Sawant SA-116 OF 2025
Question No.4
46) Since Issue Nos.1 to 3 are answered against the allottee and
in favour of the promoter, Issue No.4 is rendered academic in the context
of adjustment of interest amount against balance consideration. However,
though this Court has arrived at the conclusion that termination of sale
transaction by the promoter is valid, the allottee would still be entitled to
secure refund of the consideration already paid. In the present case, what
is proved is payment of consideration of Rs.12,30,000/-. The Appellate
Court has directed the promoter to pay interest on the amount of
Rs.12,30,000/- at the rate of MCLR + 2% w.e.f. 12 July 2016 till the date of
possession.
47) The promoter is not really averse to refund the amount of
consideration to the allottee. Mr. Kanade has fairly left the issue of
interest to be determined by this Court. However, he has submitted that
since the promoter had refunded the amount of Rs.11,07,000/- to the
allottee, the promoter be not burdened with liability to pay interest.
48) Though the sale transaction is validly terminated, the
promoter is not entitled to retain the booking amount of Rs.12,30,000/-.
He is also not entitled to deduct any amount towards EMD. In my view
therefore, the booking amount of Rs.12,30,000/- deserves to be returned
to the allottee.
49)Coming to the issue of interest, in my view, the allottee is
responsible for non-execution of the agreement after 30 July 2019.
Therefore, ordinarily interest would be payable from the date of allotment
upto 30 July 2019. However considering the unique fact s and
_____________________________________________________________________________
PAGE NOS. 25 of 30
23 September 2026
Neeta Sawant SA-116 OF 2025
circumstances of the case, I deem it appropriate to award interest from 12
July 2016 as directed by the Appellate Tribunal. This is done as the
allottee was made to wait for a considerable period of time for
construction of the �at. May be he was in �nancial dif�culties and was
unable to pay the stamp duty and registration charges. His need for funds
would have made him utilize the withdrawn amount. The promoter has
left it to the court to decide about interest. Awarding interest to the
allottee on booking amount of Rs.12,30,000/- would provide some solace
to him though he himself is responsible for cancellation of the sale
transaction. In my view, therefore the rate of interest awarded by the
Appellate Tribunal can be maintained (SBI’s MCLR + 2%) and the interest
can be directed to be paid from 12 July 2016 till the actual return of the
booking amount. Issue No.4 is answered accordingly.
Question No.5
50) The allottee claimed that he had made payment of
Rs.34,55,000/- to Kharatmols and therefore he was entitled to adjustment
of Rs.12,30,000/- paid by Kharatmols to the promoter. He �led Appeal
before the Appellate Tribunal for adjustment of total amount of
Rs.28,75,281/-. As per the details discussed in para-26 of the order of the
Appellate Tribunal, the Appellate Tribunal has rejected the contention of
the allottee about payment of Rs.28,75,281/- by him to the promoter by
holding in paras-26 and 27 of the order as under:
26. The Allottee has disputed the amount paid to the Promoter Allottee
has contended that he has made payment of Rs.28,75,281/- whereas the
Promoter has admitted the payment to the extent of Rs.12,30,000 only.
While referring to the memorandum of understanding dated 27.06.2013
_____________________________________________________________________________
PAGE NOS. 26 of 30
23 September 2026
Neeta Sawant SA-116 OF 2025
executed between the Allottee with the original allottees, the Allottee
has contended that he has made the payments to the Promoter as per
details given below.
Sr. No. Amount Remark
1. Rs. 12,30,000/- Paid by Mr. And Ms. Kharatmol as booking
amounts, now stands, thus paid by the
Allottee as part consideration.
2. Rs. 12,30,000/- Booking amount paid by Allottee
3. Rs. 1,25,531/- As service tax
4. Rs. 48,750/- VAT
5. Rs. 1,50,000/- Miscellaneous charges
6. Rs.36,000/- Amenities charges
7. Rs. 55,000/- CIDCO transfer charges
8. Rs. 28,75,281/- Total amount paid
27. As we have already observed that the original allottees have
surrendered the booking of the said �at to the Promoter upon which the
Promoter has returned Rs.12,30,000/- to Mr. and Ms. Kharatmol.
Therefore, the contention of the Allottee that the said amount paid by
Mr. and Ms. Kharatmol stands to have been paid by the Allottee as part
consideration cannot be accepted. Except Rs.12,30,000/- which Allottee
has paid as booking amount towards the said �at, the rest of the
amounts mentioned by the Allottee have not been admitted by the
Promoter. In the circumstances, it was incumbent on the part of Allottee
to submit cogent documentary evidence in support of the payments
made by him. However, there is nothing on record to substantiate any
payment made by the Allottee except Rs.12,30,000/- as booking amount
paid to the Promoter. In view of this, we conclude that the Allottee had
paid the Promoter only to the extent of Rs. 12,30,000/- as booking
amount towards part consideration of the subject �at. We therefore,
reject the claim of the Allottee that he has paid Rs.28,75,281/- to the
Promoter.
_____________________________________________________________________________
PAGE NOS. 27 of 30
23 September 2026
Neeta Sawant SA-116 OF 2025
51) Perusal of allotment letter dated 11 July 2013 issued to the
allottee would indicate that the allottee had agreed to pay total
consideration of Rs.48,75,000/- to the promoter and had paid an amount
of Rs.12,30,000/- to the promoter. The allotment letter does not mention
payment of any additional consideration or adjustment of consideration
paid by Kharatmols against allotment made to the allottee. More
importantly, the whole claim of payment of Rs.28,75,281/- to the
promoter got demolished on account of email of the allottee dated 30
June 2019 in which he emphatically stated that he had to pay an amount
of Rs.33 lakhs (approximately) out of agreed consideration of Rs.48.75
lakhs. If payment of Rs. 28,75,281/- had already been made, the allottee
would not have contended in the email dated 30 June 2019 that the
balance amount of consideration payable was approximately Rs. 33 lakhs
(approx).
52) In my view therefore Maha RERA and Appellate Tribunal are
justi�ed in rejecting allottee's contention that the consideration paid by
Kharatmols was required to be adjusted in the transaction entered into by
the allottee with the Promoter.
53) Reliance by Mr. Maskar on judgment of the Apex Court in
Laureate Buildwell Private Limited (supra) is inapposite. The issue before
the Apex Court was whether the timelines agreed with the earlier allottee
would bind the promoter when allotment is transferred to a new allottee.
The ratio of the judgment cannot be overstretched to mean that every
payment made by earlier allottee must be adjusted in the fresh allotment
made by the new allottee. In the present case, the earlier allottees
(Kharatmols) requested for refund of the payments made by them and the
_____________________________________________________________________________
PAGE NOS. 28 of 30
23 September 2026
Neeta Sawant SA-116 OF 2025
promoter has refunded the booking amount to Kharatmols. In the
allotment letter issued to the allottee, there is no arrangement for
adjustment of any payments made by Kharatmols. If the allottee had paid
any amount to Kharatmols and the parties had agreed that the promoter
would give credit to the allottee in respect of the amount paid by the
allottee, the same ought to have been re�ected in the allotment letter.
The ratio of the judgment of the Apex Court therefore has no application
to the facts of the present case.
54) Issue No.5 is therefore accordingly answered in the negative.
55) In view of my answers to Issues Nos.1 to 5, the orders passed
by the Maha RERA and Appellate Tribunal directing execu tion of
Agreement for Sale with the allottee in respect of the �at chosen by him
are unsustainable and liable to be set aside. I accordingly proceed to pass
the following order:
(i) Order dated 8 October 2020 passed by the Maha RERA in
Complaint No. CC006000000100328, as well as judgment and
order dated 22 October 2024 passed by the Appellate Tribunal in
Appeal No. AT00600000052787/20 and Appeal No.
AT00600000052798/20 are set aside.
(ii) The promoter shall return to the allottee amount of
Rs.12,30,000/- alongwith interest @ SBI’s MCLR + 2% w.e.f. 12
July 2016 till the date of actual payment.
_____________________________________________________________________________
PAGE NOS. 29 of 30
23 September 2026
Neeta Sawant SA-116 OF 2025
56) With the above directions, the Second Appeal No.116 of 2025
�led by the promoter is partly allowed and Second Appeal No. 603 of
2025 �led by the allottee is dismissed. Considering the facts and
circumstances of the case, there shall be no order as to costs. Pending
Interim Application disposed of.
[SANDEEP V. MARNE , J.]
_____________________________________________________________________________
PAGE NOS. 30 of 30
23 September 2026
NEETA
SHAILESH
SAWANT
Digitally signed by
NEETA SHAILESH
SAWANT
Date: 2026.09.23
19:47:53 +0530
Legal Notes
Add a Note....