As per case facts, Jsc Golla Engineering Private Limited challenged a contract termination and blacklisting notice by Oil And Natural Gas Corporation Limited. The termination cited reasons like director disqualification, ...
Date on which judgment was reserved : 09.03.2026
Date on which judgment was pronounced : 08.05.2026
Date on which judgment was uploaded
on the website of the High Court : 08.05.2026
APHC010434182024
IN THE HIGH COURT OF ANDHRA PRADESH
AT AMARAVATI
(Special Original Jurisdiction)
[3327]
FRIDAY,THE EIGHTH DAY OF MAY
TWO THOUSAND AND TWENTY SIX
PRESENT
THE HONOURABLE SRI JUSTICE K SREENIVASA REDDY
WRIT PETITION NO: 22088/2024
Between:
Jsc Golla Engineering Private Limited and Others ...PETITIONER(S)
AND
Oil And Natural Gas Corporation Limited and
Others
...RESPONDENT(S)
Counsel for the Petitioner(S):
1. M/S INDUS LAW FIRM
Counsel for the Respondent(S):
1. The Advocate General for Sri D S SIVADARSHAN
2
THE HON‟BLE SRI JUSTICE K. SREENIVASA REDDY
WRIT PETITION No.22088 of 2024
ORDER :
This Writ Petition is filed seeking to declare the action
of respondent No.1 in issuing termination Order dated
03.08.2024 under Section 3 Part(1) of the Integrity Pact and
Clause 8.3.4 of the Agreement dated 7.11.2022 and the
subsequent actions of issuance of Notice of Enquiry dated
09.08.2024 for blacklisting the petitioner company by
putting it on a „holiday‟, without any ground of violation
being made out, in terms of the Integrity Pact, or without
conducting an enquiry into the said matter, including in
terms of the Integrity Pact, or without even duly considering
the reply of the petitioner dated 23.07.2024 regarding the
alleged infractions, as being illegal and arbitrary and
consequently set aside the same.
2. Pursuant to a Tender Notice issued by 1
st
respondent for the purpose of carrying out the work of
surveys, design, detailed engineering, procurement,
transportation, fabrication, installation/erection, laying,
3
hook up, hydro -testing, testing, pre-commissioning,
commissioning along with associated terminal facilities and
systems for „creation of gas dehydration and DPD facilities
at (a) Tatipaka and Mandapeta GCS of Rajahmundry asset
(„Group A contract‟) and (b) Ramnad GCS of Cauvery asset
(„Group B contract‟) of LSTK basis, and subsequent
Operations and Management responsibility for the created
facilities for 7 years, 1
st petitioner company submitted its
offer dated 16.02.2022. The offer submitted by 1
st petitioner
company was accepted and 1
st respondent issued two
Letters of Intent, both dated 05.07.2022, and two
agreements, both dated 07.11.2022, were entered into
between 1
st petitioner company and 1
st respondent in
respect of the Group A and Group B contracts.
Majority shareholder in 1
st petitioner company is one
Jondishapour Company, which is a company registered
under the Laws of Iran, holding 51% of the shareholding.
In terms of the tender conditions itself, the bidding entity is
entitled to provide details of „supporting company‟ for
fulfilling the necessary criteria of financial and technical
4
eligibilities listed therein. At the time of submitting its
offer, 1
st petitioner company furnished details of 1
st
petitioner company along with agreements and
undertakings by its supporting company viz. Jondishapour
Company. In fact, on evaluation of the technical and
financial eligibility conditions and after satisfying that the
technical and financial eligibility conditions are fulfilled by
the supporting company, the contracts were awarded by
respondent No.1 to 1
st petitioner company.
As per the Notification of Intent, 1
st petitioner and the
supporting company were to issue Performance Bank
Guarantee (PBG) for due performance of the contract, for
3% each, totalling 6% of the total contract price, for each of
the contracts. As the supporting company has no office of
establishment in India, since it was incorporated in the
State of Iran, no Bank in India came forward to issue Bank
Guarantee at its behest. Therefore, 1
st petitioner itself
issued both the PBGs for the entire requisite amount as
required under the Notification of Award, and the same was
accepted by 1
st respondent and the same is recorded as
5
part of the Contracts dated 07.11.2022. Pursuant to the
same, the work was awarded and 1
st petitioner started
undertaking the works after incurring huge costs.
3. It is stated in the writ affidavit that after 298
days of accepting the PBGs for the entire value from 1
st
petitioner, 1
st respondent issued a letter dated 11.08.2023
to 1
st petitioner company seeking additional PBGs directly
to be provided by the supporting company . Though 1
st
petitioner company made endeavours to obtain PBG from
the supporting company, due to sanctions in place against
the State of Iran, it could not obtain the same. The same
was duly explained by 1
st petitioner company in its letter
dated 18.10.2023 addressed to 1
st respondent, to which
letters issued by the Banks regarding their inability to issue
PBGs in the name of the supporting company were
enclosed, and offered to provide Demand Draft for the said
entire guarantee amounts which the supporting company
was to provide, to secure the interest of 1
st respondent,
which is in line with the guidelines issued by the Ministry
of Finance. 1
st petitioner company also explained that it
6
had already issued Purchase Orders for majority of items
and construction was also under progress, and thus,
requested not to take any adverse action, as, anyway, PBGs
for the entire requisite amounts were already provided to
secure interest of 1
st respondent. Pursuant to the
explanation and undertakings, 1
st petitioner company was
given to understand that only upon acceptance of the said
explanation, pending payments receivable to 1
st petitioner
company were released.
It is stated that in terms of Clause 6.3.1.1 of the
Agreements, the scheduled completion date of the works is
5.5.2024 i.e. 22 months from the date of issue of
Notification of Award. In view of various reasons beyond
the control of 1
st petitioner company, including the delay
caused by 1
st respondent in providing access of the site to
the petitioners and delay in approval of equipment designs
and drawing by 1
st respondent, the works could not be
completed by the said date, and so, vide letter dated
12.04.2024, 1
st petitioner company sought extension till
31.3.2025. Considering the same and without seeking any
7
further explanation, 1
st respondent extended the contract
period up to 04.08.2024 and sought to extend the validity
of the Bank Guarantees, without even any mention of
requirement of additional PBGs directly to be provided by
the supporting company. Thus, till April, 2024, there was
no whisper of any alleged violation by 1
st petitioner
company and the works undertaken were in full swing.
It is further stated that after 22 months of issuance of
the Notification of Award, 1
st petitioner company received a
letter dated 23.05.2024 from 1
st respondent whereunder
the following 3 clarifications were sought viz. (i) in relation
to the regulatory filings being completed for the invested
amount by 1
st petitioner‟s supporting company at the time
of incorporation of the petitioner; (ii)regarding the prior
disqualifications of Mr. Siva Kumar Golla, who is one of the
Directors of 1
st petitioner company, and (iii) copy of the
power of attorney/authorization granted to Mr. Siva Kumar
Golla by the Iranian supporting company , and it was
requested to provide the information by 27.5.2024. 1
st
petitioner company, vide letter dated 27.05.2024, sought
8
extension of time till 10.06.2024, for providing the
information. 1
st respondent gave reply dated 28.5.2024,
extending time therefor till 29.05.2024. 1
st petitioner
company sent clarifications vide e-mail dated 29.05.2024
and sought 10 days‟ time till 10.06.2024, to provide further
information with respect to filing of Form FC-GPR. The
petitioner applied for the same and was awaiting issuance
of the same from the RBI. 1
st respondent sent an e-mail
dated 01.06.2024, rejecting the request for the additional
time, without indicating whether the information provided
was insufficient or irrelevant. 1
st Petitioner company
received e-mail dated 03.06.2024 from Bank of
Maharashtra regarding invocation of the PGBs, attaching
letter dated 03.06.2024 issued by the respondents to the
Bank seeking to invoke and encash the subject PGBs. On
05.06.2024, it came to the knowledge of 1
st petitioner
company that a Letter of Termination dated 03.06.2024,
was e-mailed to 1
st petitioner company at late hours on
03.06.2024, whereby the respondents sought to terminate
the Contract both in terms of Clause 8.3.4 of the General
9
Conditions of Contract and Paragraph (1) of Section 3 of the
Integrity Pact. Challenging the same, 1
st petitioner company
filed Writ Petition No.12243 of 2024 before this Court, and
vide Order dated 09.07.2024, this Court disposed of the
said Writ Petition, directing to treat the Letter of
Termination dated 03.06.2024 as show -cause notice, to
which 1
st petitioner company was asked to submit reply
within a period of two weeks. Accordingly, 1
st petitioner
company submitted reply dated 23.07.2024. But, without
considering the explanation that there is no illegality
committed with respect to the manner of incorporation of
1
st petitioner company, the respondents, as a part of their
premeditated scheme, passed the impugned Letter of
Termination dated 03.08.2024, terminating the contract, in
terms of Clause 8.3.4 of the General Conditions of Contract
and Paragraph (1) of Section 3 of the Integrity Pact, on the
following grounds.
(i) Mr. Siva Kumar Golla, while being appointed as
Director of M/s. JSC Golla Engineering Private
Limited, was a defaulting Director under Section
10
164 (2) (a) of the Companies Act, 2013 and was
disqualified from 01.11.2016 to 31.10.2021;
(ii) Non-compliance of statutory provisions related
to NDI Rules and FC GPR putting the reliability
and credibility of Contractor in question;
(iii) Non-submission of PBG by supporting
company M/s. Jondishapour Company, Tehran,
Iran;
(iv)Very minimal progress of 31.64% as on date.
Challenging the same, the present Writ Petition is
filed.
4. (a) Respondents filed counter affidavit denying
the material averments in the writ affidavit and contending
inter alia that the parties to the subject contract agreed that
all disputes or differences arising out of the subject
contract, are amenable to the Courts in Delhi, and in view
of the same, this Court has no jurisdiction to entertain the
Writ Petition; that a Writ Petition under Article 226 of the
Constitution of India is not maintainable in a private
contractual matter like the present one, wherein the
11
respondents acted solely in accordance with the terms of a
private contract entered into, between the parties.
(b) It is further stated that M/s. Jondishapour
Company, an Iranian Com pany, is majority shareholder,
holding 51% share in 1
st petitioner company, and 1
st
petitioner company relied on technical and financial
credentials of the said company for fulfilment of the bidding
criteria set out in the present tender process, but the
statutory auditors of ONGC made certain observations that
the 51% shareholding of 1
st petitioner company subscribed
by the Iranian Company was not subscribed through
remittance of funds from foreign sources, rather the
remittance was made from Indian source s i.e. by Ms.
Jasmi, as is evident from e-form 20A and the bank
statement available in public domain. ONGC referred the
issue to internal committee, Fraud & Risk Management
Committee (FRMC) under „Audit Committee‟ of the Board of
Directors of ONGC, for further examination. The FRMC
requested 1
st petitioner company to provide documents to
support its case that the Iranian Company made relevant
12
inward remittance of foreign funds for acquisition of the
shareholding of the petitioner company, and that Mr. Siva
Kumar Golla, Director of the company was not disqualified
under Section 164 of the Companies Act, 2013 at the time
of his appointment as Director of 1
st petitioner company.
Upon reviewing the information provided by 1
st petitioner
company, it was concluded that there are no supporting
documents to support version of 1
st petitioner company and
therefore it was recommended for termination of the
contract. Accordingly, termination order dated 03.06.2024
was issued terminating the contract inter alia on the
ground of element of fraud arising in subscription of the
shareholding of 1
st petitioner company by the Iranian
Company. Challenging the same, the petitioners filed W.P.
No. 12243 of 2024 before this Court, and pursuant to the
Order dated 09.07.2024 pa ssed by this Court in
W.P.No.12243 of 2024, ONGC, on receipt of reply dated
23.07.2024, passed the impugned termination order. The
impugned termination order was issued after considering
13
all the contentions of 1
st petitioner company in detail in
accordance with the settled principles of law.
(c) As regards the 2
nd ground of termination, it is
further stated that 1
st petitioner company admitted that as
per the Foreign Exchange Management (Non -debt
Instruments) Rules, 2019, it was required to file FC-GPR
within 30 days of subscription of the Iranian Company
shares as the Iranian Company qualifies as a non-resident
shareholder as per the NDI Rules, but it had inadvertently
missed filing of Form-FC-GPR post subscription of the
Iranian Company shares. After receipt of letter dated
23.05.2024 from ONGC, 1
st petitioner company filed an
application for submission of Form FC -GPR with its
authorized dealer bank along with late fee submission
payable under the Guidelines issued by the RBI and it is
awaiting the acknowledgement of submission of the said
Form, from the RBI.
As per Rule 3 of the NDI Rules, except as provided in
the Foreign Exchange Management Act, 1999 (FEMA) or the
Rules and Regulations made thereunder, no person
14
residing outside India will make any investment in India,
and as per Paragraph 1 (d) (iii) of Schedule I read with Rule
6 of the NDI Rules, a non-resident is permitted to subscribe
to the equity shares of an Indian company incorporated by
it against the pre-incorporation expenses incurred by the
non-resident for incorporation of the Indian company
subject to the Rules and Guidelines issued by the
Government of India and with the approval of the RBI.
The directions issued by the RBI do not prescribe
guidelines for issuance of equity shares by a company
incorporated in India to a non-resident entity, and such
issuance of equity shares is governed solely by the
provisions of the NDI Rules and the FDI Policy read with
FEMA. If the shares were allotted to the Iranian Company
against its alleged pre-incorporation expenses, petitioner
should have provided proof of such subscription at the time
of filing INC 20A. Therefore, issuance of equity shares by
1
st petitioner company to the Iranian Company will not be
considered as „remittance to a non-resident‟ under the
aforementioned directions. Issuance of shares to the
15
Iranian Company will be required to comply with the
provisions of the NDI Rules and the FDI Policy, and in view
of the above, the issuance of the shares by the JSC Golla to
the Iranian Company is in contravention of the NDI Rules
and the FEMA.
Initially, when petitioner No.1 was asked to produce
FC-GPR, on one hand, it requested time till 10.06.2024 to
furnish a copy of FG-GPR, but even after so many days
thereafter the petitioners did not provide the said
document, and on the other hand, it furnished a copy of
the opinion issued by a Company Secretary along with the
Writ Petition, wherein it was stated that the investment
from the foreign entity did not occur in the foreign money.
This shows that the petitioners do not have FC-GPR and
they approached this Court with unclean hands. These
factors put credibility and reliability of 1
st petitioner
company in question, and continuance of the contract with
such a company is undoubtedly harmful to the execution of
the contract and requires immediate termination.
16
(d) As regards 1
st ground of termination, it is stated
that the list of disqualified Directors for the financial years
2013-14, 2014-15 and 2015-16 issued by the Registrar of
Companies, Hyderabad shows the period of disqualification
of the Director from 1.11.2016 till 31.10.2021, and the date
of incorporation of 1
st petitioner company is on 17.08.2021,
by which date Mr. Siva Kumar Golla was disqualified under
Section 164 (2) (a) of the Companies Act, 2013. As per the
publicly available records, the Ministry of Corporate Affairs
(MCA) has not issued any Notification on its web portal
removing the Director from the list of disqualified Directors
under Section 164 (2) (a) of the Companies Act, 2013.
Therefore, the documents submitted by the petitioners
along with the reply, are not sufficient to prove that the
Director was not disqualified under Section 164 (2) (a) of
the Companies Act, 2013.
(e) As regards the 3
rd ground of termination, it is sated
that although the PBGs furnished by 1
st petitioner company
was momentarily recorded in the agreement, ONGC never
waived requirement of furnishing the PBGs by the Iranian
17
foreign entity. In fact, ONGC asked the petitioner No.1
company on multiple occasions after the agreement, to
furnish such bank guarantee, but the petitioner failed to do
so. It is a justifiable reason for terminating the contract.
(f) As regards 4
th ground of termination, it is stated
that the petitioners completed only 31.64% of the work
under the contract for Group A, but not 60%, as contended
by the petitioners. The extension of time given to 1
st
petitioner company was only until 04.08.2024, by reserving
the right of the ONGC to levy liquidated damages. Though
ONGC requested the petitioner No.1 company to expedite
completion of the works and complete the project within the
stipulated date of completion, it failed to do so within the
scheduled date of completion of the project.
(g) It is further stated that Clause 8.3.7 of the Tender
as well as the Contract contemplates initiation of the
inquiry proceedings consequent upon termination of a
contract, and pending such inquiry proceedings, the
defaulting party would be subject to temporary holiday
proceedings. The petitioners did not raise any objection to
18
such clauses at the time of entering into the contract or
during the tender process. Now, the petitioners cannot
challenge the validity of the clauses, after they have been
duly invoked by the ONGC. When the inquiry proceedings
are ongoing, the defaulting party will not be allowed to
participate in tender proceedings. The petitioners have a
suitable alternative remedy in terms of the contract to claim
suitable damages in the event they are able to establish
that the termination is illegal. Instead of participating in
the process of inquiry, the petitioners chose to approach
this Court. The Writ Petition is premature. Hence, it is
prayed to dismiss the Writ Petition.
5. Petitioners filed reply affidavit to the counter
affidavit filed by the respondents, denying the material
averments in the counter affidavit and stating inter alia as
follows:
(a) The Writ Petition is filed challenging the arbitrary
and unjust action of the respondents, which ar e public
entities, and the same is maintainable even in the
contractual field. The main subject contract of which the
19
Integrity Pact is also to be read as part and parcel, is in
relation to the works being undertaken at places of
Tatipaka and Mandapet of Dr. B.R. Ambedkar Konaseema
District, which is also being supervised and performed in
the State of AP. The petitioners are challenging the
arbitrary manner in which the termination was carried out
by the respondents, being an instrumentality of State, and
notwithstanding the claim for damages and availability of
alternative remedies, the Writ Petition is maintainable.
(b) As regards non-filing or delay in filing of FC-GPR, it
is stated that as per the extant law, non-filing of FC-GPR
(Foreign Currency-Gross Provisional Return) is a curable
defect and the violation is compoundable even when there
is delay, and non-filing thereof does not make the actual
investment illegal or the shareholding illegal. The said
reporting infraction does not amount to contravention of
the provisions of the Integrity Pac t. There is no
misrepresentation or suppression by the petitioners, as the
same is by oversight. The delay in its issuance is that
because sanctions are in place against the State of Iran, the
20
Authorized Dealer Bank, which has to process the said FC-
GPR on behalf of the RBI, is taking more time, and the
petitioners escalated the issues with FDI Cell (Foreign
Investment Facilitation Portal), and after processing the
same, the Ministry of Petroleum and Oil & Na tural Gas
conveyed through OEM that the investment is in line with
the FDI Policy and indicated that since the FC -GPR is
compliance issues, advised the petitioners to approach the
RBI directly. Accordingly, the petitioners approached the
RBI and the same is under active consideration. The
respondents raised the issue of FC-GPR after nearly 2 years
of the Award of the Contract, and even without
understanding the nitty-grittys that are associated with the
filing of the FC-GPR, the contract was terminated b y
attributing the violation of Integrity Pact. The respondents
appear to pre-determined to terminate the contract.
Further, INC-20A form is filed to signify the
commencement of business but it does not mean that the
transactions mentioned therein are reflective of the
subscription amount.
21
(c) As regards disqualification of Mr. Siva Kumar
Golla, it is stated that there was no disqualification
attached to Mr. Siva Kumar Golla at the time of
incorporation of the company and to the said effect, the
Registrar of Companies issued a letter of good standing.
DIR No.3, INC-9 or DIR-8, DIR-9 or DIR-10 forms need not
even be provided to the ONGC as the query regarding
Sivakumar Golla‟s disqualification at the time of
incorporation of the petitioner company, was already
answered. When ROC, after ensuring all compliances, duly
incorporated the petitioner company, the respondents are
raising frivolous objections when no such objections or
compliance related issues were ever raised by the
ROC/Ministry of Corporate Affairs, which is the competent
authority.
(d) As regards furnishing of PBGs, it is stated that the
PBGs were accepted by the respondents and the same were
recorded in the agreement and thus not they cannot
contend that the same were not provided in the manner as
required under the NOA. After having accepted the PBGs,
22
recording the same in the agreement and also after legally
invoking the same and receiving the amounts, the
respondents cannot allege the same to be a justifiable
reason for termination of the contract.
The respondents are unable to conclusively state if the
present dispute is a breach of contractual terms or a
violation of Integrity Pact, which has nothing to do with the
performance of the contract, and having admitted that the
termination was primarily based on the alleged breach of
Integrity Pact, they cannot now seek to rely on the alleged
breach of the terms of the contract.
(e) As regards delay, it is stated that multiple delays
were caused at the instance of the respondents and it was
due to such delay that the execution of the contract got
delayed. The conduct of the respondents is mala fide,
arbitrary and against the principles of natural justice. The
petitioners undertook the work at the site by employing its
men and machinery by incurring huge amounts, and there
is no loss or injury whatsoever caused to the respondents.
The petitioners placed huge orders for purchase of
23
exclusive/customised machinery and necessary equipment,
and they are in an advanced stage of manufacturing and
some are ready to be delivered at the site as they were
imported and lying at Mumbai Port, and some are ready for
despatch from vendor works and some are ready for final
inspection, and at that stage, ONGC stopped responding.
Hence, it is prayed to allow the Writ Petition.
6. The 1
st petitioner filed an additional affidavit
stating inter alia that the respondents filed Transfer Petition
(Civil) No.3360 of 2024, seeking transfer of the present Writ
Petition to the High Court of Delhi, primarily in view of
jurisdiction clause as specified under the Integrity Pact
annexed to the Agreement dated 07.11.2022, and also filed
another Transfer Petition seeking transfer of a Writ Petition
pending before the Madurai Bench of Madras High Court,
and the Hon‟ble Supreme Court vide Order dated 27.3.2025
dismissed the Transfer Petitions.
It is further stated that during pendency of the Writ
Petition, the petitioner, vide letter dated 08.12.2024,
requested resolution of the matter through mediation by
24
the Outside Expert Committee, but the same was rejected
by the respondents on 02.01.2025. It is further stated
that even thereafter, the petitioner, without prejudice to the
contentions raised in the present Writ Petition, filed a claim
vide letter dated 21.01.2025, for amicable settlement of the
dispute, pursuant to which, several meetings took place,
but as on date, there is no concrete resolution. It is
further stated that as of now, the works have come to a
complete stand still, and had the petitioners allowed to
continue the works, the works would have been completed
by now and the same would have become functional as of
date. It is stated that the entire termination process and
the manner in which the same was issued is fraught with
arbitrariness and mala fides, and the same is unjust and
illegal. As a result of the same and in view of the illegal
encashment of the bank guarantees, the petitioners had
fallen in huge debt trap and is in severe financial and legal
distress, as it had already placed purchase orders towards
fulfilment and performance of the contract, and the
25
requisite equipment is now made ready to be used.
Hence, it is prayed to allow the Writ Petition.
7. Heard the learned counsel for the petitioners
and the learned Advocate Gene ral appearing for the
respondents. Perused the record.
8. Learned counsel for the petitioners contended
that the grounds on which the impugned termination order
dated 03.08.2024 was passed by the respondents are
fraught with arbitrariness and mala fides. He submits that
the first ground that Mr.Siva Kumar Golla was a defaulting
Director by the date of incorporation of 1
st petitioner
company does not stand, in view of the intimation dated
04.09.2024, issuing „Certificate of Good Standing‟ by the
Registrar of Companies, Telangana, Hyderabad; that the
second ground with regard to non-filing of FC-GPR form
with the Reserve Bank of India for subscription of the
supporting Iranian copany, is permitted to be compounded
by the Reserve Bank of India and the petit ioners paid
penalty therefor, as such, the same is not a ground to
26
terminate the contract; that 51% shareholding to the
supporting Iranian company was issued as against the pre-
incorporation expenses incurred by the said company, and
the amount involved therein is far less than the expenses
incurred by the supporting Iranian company towards pre-
incorporation expenses.
It is his submission that reason for non-submission of
the PBGs by the supporting Iranian company was explained
by the petitioners, and the petitioners furnished PBGs for
the entire requisite amount, including the amounts of PBGs
to be provided by the supporting Iranian company, and the
same was incorporated in the contract agreement dated
07.11.2022, pursuant to which 1
st petitioner company
commenced the work. He submits that in fact, the time for
execution of the works was extended by the respondents,
without there being any such condition, but only
instructing to extend the validity of the existing PBGs, and
in fact, the respondents invoked and encashed the PBGs
pursuant to the earlier letter of termination dated
03.06.2024, and therefore, at this stage, the respondents
27
are estopped from raising the said ground as a reason for
termination of the contract. He submits that the other
ground with regard to very minimal progress, is not
tenable, as the petitioners completed more than 60% work,
but not 31.64% as contended by the respondents, and had
it been allowed to continue the work, the same would have
been completed by now. He submits that the entire action
of respondents is tainted with arbitrariness and mala fides
and hence, he prayed to set aside the impugned order.
9. On the other hand, the learned Advocate General
appearing for the respondents contended that existence of
arbitration clause is a bar to entertain the Writ Petition,
and in view of Clause 1.3.2 of the General Conditions of
Contract annexed to the contract agreement dated
7.11.2022, the parties agreed to resolve the disputes
through arbitration. He submits that the petitioners failed
to complete the subject work within the scheduled
completion date and they only completed 31.64% of work,
and ONGC is not fault for the delay in execution of the
work by the petitioners. He submits that 51%
28
shareholding subscribed by the su pporting Iranian
company was not funded through foreign remittance, it was
funded through Indian sources, through intermediary
agency Ms.Jasmi, and the same is non-compliance with the
said statutory requirement, and hence, issuance of equity
shares by 1
st petitioner company to the supporting Iranian
company will not be considered as remittance to a non -
resident, and the same is violation of Integrity Pact. It is
his further submission that the respondents never waived
the requirement of furnishing of Additional PBG by the
supporting Iranian company, and mere recording the PBGs
furnished by 1
st petitioner company in the contract
agreement dated 07.11.2022 does not amount of waiver of
the said requirement, which is incorporated not merely to
secure monetary obligations, but to ensure the genuine
participation and commitment of the supporting Iranian
company in execution of the contract. Considering these
aspects, the contract of 1
st petitioner company was rightly
terminated by the respondents vide the impugn ed
29
termination order dated 03.08.2024, and there are no
grounds to interfere with the same. `
10. Now, the point that arises for consideration in
this Writ Petition is whether the grounds on which the
impugned termination order dated 03.08.2024 was passed
by the respondents are sustainable in the eye of law and
whether the same requires interference in exercise of
judicial review by this Court under Article 226 of the
Constitution of India ?
11. The factual matrix is not in dispute. Pursuant
to the Tender Notice issued by 1
st respondent for the Group
A and Group B contracts, the offer submitted by 1
st
petitioner company was accepted and 1
st respondent issued
two Letters of Intent, both dated 05.07.2022, and two
agreements, both dated 07.11.2022, were en tered into
between 1
st petitioner company and 1
st respondent in
respect of the Group A and Group B contracts. Majority
shareholder in 1
st petitioner company is one Jondishapour
Company, which is a company registered under the Laws of
30
Iran, holding 51% of the shareholding. 1
st petitioner issued
the PBGs for the entire requisite amount as required under
the Notification of Award, and the same was accepted by 1
st
respondent and the same is recorded as part of the contract
agreement dated 07.11.2022, pursuant to which 1
st
petitioner started undertaking the works. Thereafter, 1
st
respondent issued a letter dated 11.08.2023 to 1
st
petitioner company seeking additional PBGs directly to be
provided by the supporting company. 1
st petitioner
informed 1
st respondent through letter dated 18.10.2023
that though 1
st petitioner company made endeavours to
obtain PBG from the supporting company, due to sanctions
in place against the State of Iran, it could not obtain the
same. In terms of Clause 6.3.1.1 of the Agreements, the
scheduled completion date of the works is 5.5.2024 i.e. 22
months from the date of issue of Notification of Award. It
is stated by the petitioners that in view of various reasons
beyond the control of 1
st petitioner company, including the
delay caused by 1
st respondent in providing access of the
site to the petitioners and delay in approval of equipment
31
designs and drawing by 1
st respondent, the works could not
be completed by the said date, and so, vide letter dated
12.04.2024, 1
st petitioner company sought extension till
31.3.2025. Pursuant to the said request, 1
st respondent
extended the contract period up to 04.08.2024 and sought
to extend the validity of the Bank Guarantees. 1
st
petitioner company received a letter dated 23.05.2024 from
1
st respondent whereunder the following 3 clarifications
were sought viz. (i) in relation to the regulatory filings being
completed for the invested amount by 1
st petitioner‟s
supporting company at the time of incorporation of the
petitioner; (ii)regarding the prior disqualifications of Mr.
Siva Kumar Golla, who is one of the Directors of 1
st
petitioner company, and (iii) copy of the power of
attorney/authorization granted to Mr. Siva Kumar Golla by
the Iranian supporting company. 1
st Petitioner company
received e-mail dated 03.06.2024 from Bank of
Maharashtra regarding invocation of the PGBs, attaching
letter dated 03.06.2024 issued by the respondents to the
Bank seeking to invoke and encash the subject PGBs. 1
st
32
respondent issued Letter of Termination dated 03.06.2024,
to 1
st petitioner company. Challenging the same, 1
st
petitioner company filed Writ Petition No.12243 of 2024
before this Court, and vide Order dated 09.07.2024, this
Court disposed of the said Writ Petition, directing to treat
the Letter of Termination dated 03.06.2024 as show-cause
notice, to which 1
st petitioner company was asked to
submit reply within a period of two weeks. Accordingly, 1
st
petitioner company submitted reply dated 23.07.2024.
Thereafter, the respondents passed the impugne d
termination Order dated 03.08.2024. Hence, the present
Writ Petition.
12. The first ground on which the impugned
termination order dated 03.08.2024 was passed by the
respondents is that Mr. Siva Kumar Golla, while being
appointed as Director of the 1
st petitioner company, was a
defaulting Director under Section 164 (2) (a) of the
Companies Act, 2013, and was disqualified from
01.01.2016 to 31.10.2021. According to the respondents,
the list of disqualified Directors for the Financial Years
33
2013-14, 2014-15 and 2015-16, issued by the Registrar of
Companies, Hyderabad, shows that the period of
disqualification of the said Director was from 01.11.2016 to
31.10.2021, and the Ministry of Corporate Affairs has not
issued any Notification on its web portal removing the said
Director from the disqualified Directors, and as such, by
the date of incorporation of the 1
st petitioner company on
17.08.2021, he was disqualified under Section 164 (2) (a) of
the Companies Act, 2013. On the other hand, it is the
contention of learned counsel for petitioners that there was
no disqualification attached to the said Mr. Siva Kumar
Golla, at the time of incorporation of the 1
st petitioner
company and that when the Registrar of Companies duly
incorporated 1
st petitioner company, after ensuring all
compliances, it is not open to the respondents to raise such
a query. A perusal of the material on record discloses that
the Registrar of Companies, after observing all necessary
statutory compliances, issued the Certificate of
Incorporation in respect of the 1
st petitioner company.
Further, on a perusal of the intimation vide File No.
34
MISC/ROCH/00520922/1317, dated 04.09.2024, issued
by the office of the Registrar of Companies, Telangana,
Hyderabad, whereby „Certificate of Good Stand ing‟ was
issued to the said Mr. Siva Kumar Golla, it is clear that as
per the records maintained by the said office, Mr. Siva
Kumar Golla, who digitally signed Form INC 35 and INC 9
for the process of incorporation of the 1
st petitioner
company, which was incorporated on 17.08.2021, had valid
DIN (00520922) which was approved. It is further clear
from the said Intimation that as per the MCA Portal, the
present status of the DIN: 00520922 of Mr. Siva Kumar
Golla, is approved. In view of the intimation given by the
Registrar of Companies that Mr. Siva Kumar Golla had
valid DIN which was approved, by the date of the 1
st
petitioner company, the said ground is unfounded and not
tenable.
13. The second ground on which the impugned
termination order dated 03.08.2024 was issued is with
regard to non-filing of FC-GPR form with RBI for
35
subscription of shares by Jondishapour Company (Iranian
Company) in 1
st petitioner Company.
It is the case of the petitioners that non-compliance of
filing of FC-GPR is a curable defect and cannot be deemed
to be a statutory violation leading to termination of the
contract. He further submits that pursuant to the
application made by the petitioners, the Reserve Bank of
India passed order dated 25.02.2026, compounding the
said contravention, and in view of the same, the second
ground for termination does not stand to the legal scrutiny.
14. FC-GPR (Foreign Currency -Gross Provisional
Return) is a form which has to be filled with the Reserve
Bank of India to report receipt of Foreign Direct Investment
into a company when the said company issues shares to a
foreign entity. As per the Foreign Exchange Management
(Non-debt Instruments) Rules, 2019, 1
st petitioner company
was required to file FC-GPR within 30 days of subscription
by the Iranian Company shares, as the Iranian Company
(supporting company) is a non-resident shareholder as per
the NDI Rules. In the event of non-reporting within the
36
time, it can be done with delay and the contravention is
compoundable.
15. Regulation 4 (1) of the Notification No. FEMA
395/2019-RB dated 17.10.2019 , an Indian company
issuing equity instruments to a person resident outside
India in accordance with the said Regulations, shall submit
to the Reserve Bank of India, a report in Form FC-GPR,
along with documents prescribed therein, within a period of
30 days from the date of issue of the equity instruments.
In the case on hand, there is a contravention of the said
Regulation by the petitioners whereby 1
st petitioner
company failed to submit the report in Form FC-GPR in
respect of issue/allotment of 5,100 equity shares, worth
Rs.51,000/- in favour of the supporting Iranian Company
viz. Jondishapour Company, Iran on 22.11.2021. The
same was reported on 19.12.2025 with a delay of 3 years
11 months and 27 days. In terms of Section 15 of the
Foreign Exchange Management Act, 1999, a person
committing any contravention under Section 13 of the said
Act, shall be eligible to be compounded upon submission of
37
an application and as prescribed under the Compounding
Proceedings Rules, 2024. Pursuant to the application
dated 20.12.2025 submitted by 1
st petitioner company, the
Reserve Bank of India passed Order dated 25.02.2026, in
exercise of the powers conferred under section 15 (1) of the
Foreign Exchange Management Act, 1999 (FEMA) and the
Rules/ Regulations/ Notifications made thereunder, stating
that the contravention i.e. delay in submission of FC-GPR
after issue of shares to a person resident outside India,
shall be compounded by payment of penalty amount of
Rs. 6,375/-. A copy of the said Order dated 25.02.2026
passed by the Reserve Bank of India, along with online
payment receipt of the penalty amount, has been filed by
the petitioners before this Court, along with a Memo (vide
WP SR 25321 of 2026), on 26.02.2026. The same is placed
on record. Admittedly, the same is a curable defect and
the same is permitted to be compounded by virtue of the
Order passed by the Reserve Bank of India. Therefore, it
cannot, under any stretch of imagination, be a ground to
terminate the contract.
38
16. According to the respondents, 51% shareholding
subscribed by the supporting company was not funded
through foreign remittances, but it was done through
Indian sources i.e. payments made by one Ms. Jasmi
through IMPS from IDFC Bank as reflected in Form INC
20A and bank statements available in the public domain.
Even in respect of allotment of the shares to a non-resident
against pre-incorporation expenses, it is the contention of
the respondents that as per the FDI Policy, only a wholly
owned subsidiary is permitted to issue shares against the
pre-incorporation expenses to non -resident parent
company, and further, the value of the equity shares issued
by the Indian company to the non -resident against pre-
incorporation expenses cannot exceed 5% of the paid up
share capital of the Indian Company or USD 5,00,000,
whichever is lower.
17. Whereas it is the contention of the petitioners
that the receipt of share subscription amount in foreign
currency is not mandatory for issuance of shares by an
Indian Company, but shares can be issued against pre -
39
incorporation expenses undertaken by the said non -
resident/foreign company; that in the case on hand, in
respect of the pre-incorporation expenses incurred by the
supporting company, the shares were allotted to the
supporting company and that the amount involved is
nominal i.e. Rs. 51,000/- which is far less than the
expenses incurred by the supporting company.
18. The learned counsel places reliance on
Paragraph 6 (ii) of the Consolidated FDI Policy Circular of
2020 issued by the Department of Promotion of Industry
and Internal Trade (FDI Division), Ministry of Commerce
and Industry, Government of India. Paragraph 6 of the
Circular deals with „Conversion of ECB/Lump sum
Fee/Royalty, etc. into Equity‟. Paragraph 6 (ii) reads that
general permission is also available for issue of
shares/preference shares against lumpsum technical
know-how fee, royalty due for payment, subject to entry
route, sectoral cap and pricing guidelines (as per the
provision of para 2 above) and compliance with applicable
tax laws. It also makes it clear that issue of equity shares
40
against any other funds payable by the investee company,
remittance of which does not require prior permission of
the Government of India or Reserve Bank of India under
FEMA, 1999 or any Rules/Regulations framed or directions
issued thereunder, or has been permitted by the Reserve
Bank under the Act or the Rules and Regulations framed or
directions issued thereunder is permitted. Further, a
perusal of clause (iii) of the General Conditions mentioned
under the said Paragraph makes it clear that for sectors
under automatic route, issue of equity shares against
import of capital goods/machinery/ equipment (excluding
second-hand machinery) and pre -operative/pre-
incorporation expenses (including payments of rent, etc.) is
permitted under automatic route subject to compliance
with respective conditions mentioned above, and reporting
to RBI in Form FC-GPR as per the prescribed under the FDI
Policy. Admittedly, in the case on hand, the contravention
of non-filing of Form FC-GPR is compounded by the
competent authority viz. Reserve Bank of India, vide the
Order dated 25.02.2026, referred supra. Therefore, from
41
the recitals in Paragraph 6 (ii) read with clause (iii) of the
General Conditions mentioned thereunder, of the
Consolidated FDI Policy Circular of 2020 issued by the
Department of Promotion of Industry and Internal Trade
(FDI Division), Ministry of Commerce and Industry,
Government of India, coupled with the compounding Order
dated 25.02.2026 passed by the Reserve Bank of India,
general permission is also available for issue of
shares/preference shares against the amounts mentioned
therein, including pre-incorporation expenses. As such,
the contention of the learned Advocate General on this
aspect is untenable and not sustainable.
19. The other ground on which the impugned order
of termination dated 03.08.2024 was issued is non-
submission of PBGs by the supporting company. 1
st
petitioner company was incorporated as a Joint Venture
Company between Jondishapour Company, an Iranian
Company, with 51% stake, and Mr. Venkatachalam
Gedupudi, who was the promoting Director and promoter.
The paid-up capital of 1
st petitioner company is Rs.
42
1,00,000/-, with 51% (Rs. 51,000/-) held by the Iranian
Company and 49% held by the said promoter Director, Mr.
Venkatachalam. Admlittedly, 1
st petitioner participated in
the subject tender process and was issued Group A
Contract and Group B con tract vide separate Letters of
Intent dated 05.07.2022 and two agreement, both dated
07.11.2022, were entered into, between 1
st petitioner
company and 1
st respondent Corporation in respect of
Group A and Group B contracts. As per the Notification of
Intent, 1
st petitioner company and the supporting Iranian
company have to submit PBGs for 3% each, totalling 6% of
the total contract price, for each of the contracts, for due
performance of the contract. In view of the fact that the
supporting company was incorporated in the State of Iran
and as no bank in India came forward to issue Bank
Guarantee at its behest, 1
st petitioner company furnished
PBGs for the entire requisite amount as required under the
Notification of Award. 1
st respondent Corporation accepted
the PBGs furnished by the 1
st petitioner company for the
entire amount to a tune of Rs. 9.72 Crores and the same
43
was recorded in the said contracts. Clause 3.3 of the
General Conditions of the Contract annexed to Contract
Agreement dated 07.11.2022 , which deals with
Performance Guarantee, reads as under:
“3.3. Performance Guarantee:
3.1.1. The Contractor has furnished to the company
the following Performance Bank Guarantee (PBG) for
due performance of the contract:
a) PBG NO. 0200222IPG011396, dated
19.10.2022, for Rs. 4,86,08,548.00 issued by
Bank of Maharashtra, Miyapur Branch, Telangana
valid up to 05.07.2025.
b) PBG NO. 0200222IPG011379, dated
19.10.2022, for Rs. 4,86,08,548.00 issued by
Bank of Maharashtra, Miyapur Branch, Telangana
valid up to 05.07.2025.
On successful commissioning and at start of O & M
contract, the contractor shall be required to submit
another PBG valid for 7 years + 60 days duration and
of the value of 3% average annualised O & M contract
value within 15 days from the date of completion of 72
hrs. PGTR.”
44
20. The reason offered by the 1
st petitioner company
for not providing the PBG by the supporting company is
that the supporting company was incorporated in Iran and
in view of the sanctions, the Banks in India did not come
forward to provide PBG on behalf of the said supporting
company in spite of best efforts being made, and in view of
the same, 1
st petitioner furnished the PBGs for the entire
requisite amount by including the amount of PBG to be
furnished by the supporting company. Admittedly, no
objection was raised for the same by the 1
st respondent
Corporation and the same was incorporated in the contract
entered into between the parties, pursuant to which the 1
st
petitioner company started executing the contract work.
About 10 months thereafter, 1
st respondent Corporation
issued a letter dated 11.08.2023 to the 1
st petitioner
company, seeking additional PBGs from the supporting
Iranian company. It is the case of the petitioners that they
could not obtain PBGs on behalf of the supporting Iranian
company in view of the sanctions in place against the State
of Iran, and that they explained the same to 1
st respondent
45
Corporation vide letter dated 18.10.2023, duly supported
by the letters issued by the Banks expressing their inability
to issue PBGs. It is their further case that they offered to
provide even demand drafts for the entire amount which
the supporting Iranian company, was asked to provide by
way of PBGs, to the respondent No.1 Corporation, in line
with the guidelines of the Ministry of Finance on PBGs. It
is their further case that on the issue of the PBGs, 1
st
respondent Corporation stopped allowing the petitioners to
execute the project from August, 2023 to December, 2023,
and in the month of December, 2023, the petitioners were
allowed to continue to execute the project without raising
any issue regarding PBGs.
21. It is the further case of the petitioners that as
the schedule date of completion of project in terms of
Clause 6.3.1.1. of the contract was coming to an end by
05.05.2024, the petitioners addressed letter dated
12.04.2024, to extend the time for completion of the project
till 31.03.2025, for which 1
st respondent Corporation, vide
46
letter dated 29.04.2024, extended the time for completion
of the works till 04.08.2024. The said letter reads thus:
“You failed to complete the entire work within the
contract completion period. In your letter under
reference, you have asked for extension of time for
completion. In view of the circumstances stated in
your above referred letter, the time for completion
is extended from 05.05.2024 to 04.08.2024,
reserving ONGC‟s right to levy liquidated damages
from you for delay in the completion of work after
the expiry of the contract completion period as
mentioned in clause 6.3.2 for the extended period,
notwithstanding the grant of this extension.
The above extension of completion date shall also
be subject to the right of ONGC to claim a
reduction in prices on account of reduction in
statutory duties/taxes, etc. which may take place
during the extended period of completion.
However, increase in prices during extended
completion period on account of increase in
statutory duties/taxes, etc. admissible under
Change in Law clause of this work order/contract
shall be granted, only if extension is due to delay
on the part of ONGC.
47
In view of above, validity date of all the Bank
Guarantees submitted under contract be extended
accordingly and submitted at the earliest.”
A perusal of the recitals of the aforesaid letter goes to
show that 2
nd respondent extended the time for completion
of project, from 05.05.2024 to 04.08.2024, reserving
ONGC‟s right to levy liquidated damages for the delay in
completion of work as mentioned under Clause 6.3.2 of the
contract, and making it clear that the same is subject to
right of ONGC to claim reduction in prices on account of
reduction in statutory duties, taxes, etc., which may take
place during the extended period of completion. It is also
stated in the said letter that validity date of all the Bank
Guarantees submitted under the contract shall be extended
accordingly by the petitioners. A perusal of the said letter
goes to show that even at the time of extending the period
of contract after completion of the original scheduled
completion date, nowhere in the said letter it is mentioned
about the additional PBGs directly to be furnished by the
supporting Iranian company. Therefore, without there
being any objection raised with regard to replacement of the
48
PBGs already furnished or with regard to furnishing of
additional PBGs directly by the supporting company, the
respondents extended the time for completion of the
contract from 05.05.2024 to 04.08.2024, but the only
condition laid with regard to Bank Guarantee is that the
petitioners shall extend validity date of all the Bank
Guarantees submitted under the contract.
22. A perusal of the material on record further goes
to show that 1
st respondent Corporation addressed letter
dated 23.05.2024 to the 1
st petitioner company seeking
clarification on three aspects viz. (i) in relation to the
regulatory filings being completed for the invested amount
by 1
st petitioner‟s supporting company at the time of
incorporation of the petitioner; (ii) regarding the prior
disqualifications of Mr. Siva Kumar Golla, who is one of the
Directors of 1
st petitioner company, and (iii) copy of the
power of attorney/authorization granted to Mr. Siva Kumar
Golla by the Iranian supporting company. The said
information was sought to be furnished by 27.05.2024, and
on the request of the petitioners, the time of extended till
49
29.05.2024. the petitioners sent reply dated 29.05.2024,
furnishing certain information and sought time till
10.06.2024 to provide further information with respect to
filing of Form FC-GPR. Vide Email dated 01.06.2024, 1
st
respondent rejected the request for granting of further time
and thereafter issued a letter dated 03.06.2024,
terminating the contract and also invoked the PBGs
furnished by the petitioners and encashed the same. So,
from the material on record, it is clear that the respondents
have already encashed the PBGs furnished by the
petitioners for the entire requisite amounts, including the
share of the supporting Iranian company. Thereafter, as
stated supra, the petitioners filed W.P. No. 12243 of 2024
before this Court challenging the termination letter dated
03.06.2024 and this court, vide order dated 09.07.2024,
disposed of the said Writ Petition, directing to treat the
Letter of Termination dated 03.06.2024 as show -cause
notice and directing the petitioners to furnish explanation
therefor within two weeks. Pursuant to the explanation
submitted by the petitioners, the impugned termination
50
letter dated 03.08.2024 came to be passed by the
respondents leading to filing of the present Writ Petition.
23. There cannot be any dispute that Clause 6.0 of
the Notification of Award (NOA) dated 05.07.2022 issued by
the 2
nd respondent stipulates that 1st petitioner company
has to furnish unconditional and irrevocable PBG for due
performance of the contract as per the provisions and
proforma as mentioned in Clause 3.3 of GCC, for a sum of
Rs. 4,86,08,548/- which is equivalent to 3% of the total
contract price. Clause 6.1 of the said NOA stipulates that
since 1
st petitioner company took financial support from the
supporting Iranian company for meeting the financial
parameters of the tender, the supporting company was
required to furnish additional PBG for Rs. 2,43,04,274/-,
which is equivalent to 50% of the PBG to be furnished by
the 1
st petitioner company. Clause 6.2 of the said NOA
stipulates that since 1
st petitioner company took technical
support from the supporting Iranian company for meeting
the technical experience criteria of the tender, the
supporting company was required to furnish add itional
51
PBG for Rs. 2,43,04,274/-, which is equivalent to 50% of
the PBG to be furnished by the 1
st petitioner company.
However, the material on record makes it clear that 1
st
petitioner company furnished the PBGs for the entire
amount viz. Rs. 9,72,17,096/-, as stipulated supra, and the
same was incorporated in the Clause 3.3 of the General
Conditions of the Contract annexed to Contract Agreement
dated 07.11.2022. The reason offered by the petitioners for
not providing PBG by the supporting company is that the
said company is incorporated in Iran and no Bank in India
came forward to provide PBG for the said company. The
respondents did not object at the initial stage, for providing
PBGs by the 1
st petitioner company for the entire requisite
amount, and allowed the petitioners to execute the work
without raising any issue regarding providing PBGs by the
supporting company. If really submission of the PBGs by
the supporting Iranian company is so essential, the
respondents ought not to have entered into the contract
agreement with 1
st petitioner company at the earliest point
of time. Further, when the petitioners requested for
52
extension of time for completion of works till 31.03.2025,
vide their letter dated 12.04.2023, respondents, vide letter
dated 29.04.2024, extended time for completion of works
till 04.08.2024. In the said letter dated 29.04.2024,
extending the time for completion of the work, there is no
mention or condition or stipulation, with regard to
providing PBGs by the supporting Iranian Comp any. As
observed supra, without there being any reference or
insistence with regard to replacement of the PBGs already
furnished or with regard to furnishing of additional PBGs
directly by the Iranian company, time for completion of
work was extended by the respondents by way of letter
dated 29.04.2024, i.e. nearly one and half year after
execution of the contract agreement dated 07.11.2022.
24. On this aspect, it is the contention of the learned
counsel for the petitioners that as per Clauses „b‟ and „c‟ of
the contract agreement dated 07.11.2022, the terms of the
contract supersede the terms of the Notification of Award as
the terms of the contract have the priority over the NoA.
53
He relied on a decision in JSIW Infrastructure Pvt. Ltd. v
ONGC Ltd.,
1 wherein it is held thus: (paragraphs 29 to 33)
“29. Annexure A, containing the General Conditions
of Contract (GCC), explicitly supersedes and prevails
over Annexure B, in case of any discrepancy,
conflict, dispute between the two. Consequently,
clause 3.4.1.5 of the GCC, a provision within the
Annexure A, should have taken precedence over any
potentially conflicting language contained within the
letter dated 27.08.2008, a document within
Annexure B. The priority accorded in the Contract
itself, as reproduced aforesaid, has not even been
noticed in the impugned award.
30. Moreover, reliance on pre -contractual
communications by the learned arbitrator to
interpret clause 3.4.1.5 results in contravention of
clause 1.2.5 of the GCC, which states:
“1.2.5 Entire Agreement
The Contract constitutes the entire agreement between
the Company and the Contractor with respect to the
subject matter of the Contract and supersedes all
communication, negotiations and agreement (whether
written or oral) of the parties with respect thereto
made prior to the date of this Agreement.”
31. This provision of the GCC, explicitly declaring
the contract as an entire agreement, has not even
been noticed in the impugned award. By prioritizing
pre-contractual communications, the arbitrator
disregards the fundamental principle that all prior
discussions and agreements would stand
superseded, as expressly agreed to by the parties in
clause 1.2.5 of the GCC.
1
2023 SCC Online Delhi 8172
54
32. The judgments cited by the respondent are of no
avail and do not detract from the above position.
While there is no quarrel with the proposition that an
interpretation considering both the express terms of
the contract and the surrounding circumstances can
sometimes be necessitated, the same does not apply
when no ambiguity exists in the first place. Resorting
to external factors/correspondence in the absence of
ambiguity would be unwarranted and undermine the
sanctity of contract. Additionally, as already stated
above, in the present case, clause 1.2.5 of the GCC
specifically states that the contract supersedes all
communication, negotiations and agreement made
prior to the date of the contract. Therefore, the
unambiguous contractual provision/s would prevail
over any contrary understanding as may be
discernible during the contract formation stage.
Further as noticed hereinabove, as per stipulation (b)
of the contract, clause 3.4.1.5 of the GCC and the
direct implication flowing therefrom, has precedence
over the letter dated 27.08.2008. As such the
judgments cited by the respondent are cl early
distinguishable.
33. In the circumstances, the impugned arbitral
awards are set aside. Accordingly, the present
petitions stand allowed. All pending applications also
stand disposed of.”
He also relied on a judgment of the Hon‟ble Supreme
Court of India in State of Madhya Pradesh v. M/s. Sew
Construction Limited & others
2, wherein it is held thus:
(paragraph 24)
2
judgment dated 18.11.2022 in Civil Appeal No.8571 of 2022
55
“In the context of discretion, we may reiterate this
principle. The rights and duties of the parties to the
contract subsist or perish in terms of the contract
itself. Even if a party to the contract is a government
authority, there is no place for discretion vested in the
officers administering the contract. Discretion, a
principle within the province of administrative law, has
no place in contractual matters unless, of course, the
parties have expressly incorporated it as a part of the
contract. It is the bounden duty of the court while
interpreting the terms of the contracts, to reject the
exercise of any such discretion that is entirely outside
the realm of the contract.”
25. A perusal of the averments in the contract
agreement dated 07.11.2022 entered into between the
parties goes to show that clause b) thereof reads as follows:
“b) The following documents annexed herewith
shall be taken as mutually explanatory of one
another and shall be deemed to form and be read
and construed as integral parts of this Contract
and in case of any discrepancy, conflict, dispute,
they shall be referred to in the order of priority as
cited below.
1.Agreement;
56
2.Annexure „IIA‟ General Conditions of Contract &
Annexure „IIB‟ General Conditions of Contract @
SCC (applicable for O&M portion).
....”
Clause c) of the contract agreement dated 07.11.2022
reads as under:
“The contract constitutes that entire Agreement
between the Company and the Contractor, with
respect to the subject matter of the Contract and
supersedes all communication, negotiations and
Agreement (whether written or oral) of the parties
with respect thereto made prior to the date of
Agreement”
26. A perusal of clause b) of the contract agreement
goes to show that the documents annexed therewith shall
be taken as mutually explanatory of one another and
deemed to form and be read and construed as integral
parts of the contract. It makes further clear that in case of
any discrepancy, conflict, dispute, they shall be referred to
in the order of priority given in the said clause. According
to the priority of the documents mentioned thereunder, the
terms of the agreement will have priority over the „Annexure
57
„II A‟ General Conditions of Contract & Annexure „II B‟
General Conditions of Contract and SCC‟. Further, Clause
c) of the contract agreement states that the contract
constitutes the entire agreement between the parties with
respect to the subject matter of the contract and it
supersedes all communication, negotiations and agreement
of the parties, with respect thereto made prior to the date of
the agreement. A reading of the aforesaid clauses makes it
clear that in case of discrepancy, conflict or dispute, the
terms of the Agreement will have priority over the General
Conditions of Contract. Further, the contract supersedes
all communications, negotiations and agreement of the
parties made prior to the date of the agreement.
27. On the other hand, it is the contention of the
learned Advocate General appearing for the respondents
that simply because Clause 3.3 of the Contract Agreement
records the factum of submission of PBGs by Indian
Company, it does not mean that the respondents waived off
the requirement of furnishing additional PBG by the
supporting foreign company, and that when 1
st respondent
58
Corporation, vide letter dated 11.08.2023, called upon the
petitioners to furnish additional PBG by the supporting
Iranian company, the petitioners vide letters dated
07.09.2023 and 08.10.2023 sought further time to resolve
the issue relating to furnishing of additional PBGs by the
supporting Iranian company and hence, the said condition
is not waived.
28. The explanation offered by the petitioners for its
inability to secure PBGs by the supporting Iranian company
that because of the sanctions, no bank in India came
forward to furnish the same as the said company is
incorporated in Iran, is plausible. In order to secure the
monetary obligations and secure the financial interest of
the respondents, the petitioners furnished the PBGs for the
entire requite amount. In fact, the said explanation
appears to have been accepted by the respondents and
thereby the petitioners were allowed to continue to execute
the work. The same was recorded in the contract
agreement entered into between the parties; pursuant to
the same, 1
st petitioner company was allowed to commence
59
execution of the works and as the petitioners could not
complete the works within the scheduled time under the
contract agreement, the respondents also extended the time
for the completion of the works without insisting or raising
any objection on the furnishing of PBGs by the supporting
Iranian company and in fact pursuant to the earlier
termination order dated 03.06.2024, the respondents
invoked the said PBGs furnished by the 1
st petitioner
company for the entire requisite amount, towards its share
and towards the share of the supporting Iranian company,
and encashed the Bank Guarantees. Further more, while
recording the PBGs, which are dated 19.10.2022, furnished
by 1
st petitioner for the entire requisite amount vide PBG
NO. 0200222IPG011396 for Rs. 4,86,08,548.00 and PBG NO.
0200222IPG011379 for Rs. 4,86,08,548.00, both issued by
Bank of Maharashtra, Miyapur Branch, Telangana valid up to
05.07.2025, in Clause 3.3 of the contract agreement, which
is dated 07.11.2022, admittedly, no condition was
stipulated in the said contract agreement with regard to
replacement of the PBGs with the ones issued by the
supporting Iranian company at a subsequent point of time.
60
As a matter of fact, in the letter dated 29.04.2024,
extending the time for execution of work, the respondents
directed the 1
st petitioner company to extend the validity
date of all the Bank Guarantees submitted under the
contract accordingly.
29. If really submission of the PBGs by the
supporting Iranian company is so essential, the
respondents ought not to have entered into the contract
agreement with 1
st petitioner company at the earliest point
of time. Having allowed the petitioner to execute the work
and after extending the time period for execution of the
works by the petitioners, and having waited for a period of
more than two years, issuance of the impugned termination
by respondents speaks volumes. According to the
petitioners, the reason for the respondents to terminate the
contract is that ONGC is interested in giving short-term
contracts to some other persons, on whom they are
interested and because of the said reason, the present
termination order was passed arbitrarily. Further, as
stipulated in the terms of the contract agreement viz.
61
Clauses „b‟ and „c‟, the contract supersedes all
communications, negotiations and agreement (whether
written or oral) of the parties with respect thereto, made
prior to the date of the agreement. It is stipulated in the
contract. Therefore, at this stage, after recording the PBGs
in the contract agreement, allowing the petitioners to
execute the works, extending the time for completion of the
works and after invoking and encashing the PBGs, the
respondents cannot now contend, and are estopped from
raising, the objection with regard to non-furnishing of PBGs
by the supporting Iranian company and this Court is of the
opinion that the same is nothing but arbitrary and is not a
ground to terminate the contract. Accordingly, this point is
answered.
30. The last ground for termination of the contract
is delay in execution of the contract. According to the
ONGC, the schedule date of completion of works by 1
st
petitioner company, in terms of Clause 6.3.1.1. of the
contract is 05.05.2024. At the request of 1
st petitioner
company seeking extension of time till 31.03.2025 for
62
completion of works, 1
st respondent Corporation, vide letter
dated 29.04.2024, extended the time for completion of the
works till 04.08.2024. According to the respondents, the
petitioners completed only 31.64% of work by the
scheduled completion date, and that despite repeated
communications, petitioners failed to accelerate the
progress of work so as to meet the contractual timelines. It
is the case of the respondents that they have fulfilled all
pre-requisites under the contract like notifying the
contractor multiple times to rectify the deficiencies and
speed up the progress to complete the contract within the
timeline and issuing 30 days‟ notice in writing to the
contractor, inasmuch as this Court directed vide order
dated 09.07.2024 in W.P. No. 12243 of 2024, that the
previous termination order dated 03.06.2024 be treated as
show-cause notice for which the petitioners were asked to
submit an explanation.
31. On the other hand, it is the contention of the
petitioners that as of date more than 60% of the works are
undertaken (both onsite and offsite) and the alleged delay is
63
attributable to the respondent at each stage of execution of
the project, like delay in handing over the site, delay caused
by the respondents in commencement of Engineering, in
review/ approval of designs, basic engineering documents,
issues that arose due to lack of and inefficient coordination
between the different disciplines/departments of
respondent No. 1 Corporation, etc. It is their further case
that delay in execution, as a ground for termination, was
first mentioned only when the first letter of termination was
issued on 03.06.2024. It is the further case of the
petitioners that if the termination was based on the reason
of delay in execution, 1
st respondent Corporation is
obligated to issue a 30 days‟ notice to that effect in terms of
Clause 8.3.4. of the General Conditions of Contract
annexed to Contract Agreement dated 07.11.2022.
32. This Court perused the pleadings and
documents filed by the parties to the Writ Petition. There
is variance in the pleadings of the parties with regard to
percentage of the work completed by the petitioners. In
that connection, what quantum of work done by the
64
petitioner precisely, cannot be adjudicated by this Court.
The issues with regard to delay in execution of the contract;
as to whether the petitioners completed only 31.64% of
works as on date, as contended by the respondents, or
more than 60% of the works are completed by the
petitioners (both onsite and offsite), as contended by the
petitioners, and whether the alleged delay in execution of
the works is attributable to the respondents or the
petitioners, are all disputed questions of fact which arose in
the course of the execution of works under agreement
entered into, between the petitioners and respondents
pursuant to the Notification of Intent dated 05.07.2022
issued by the respondents. They are disputed questions of
fact, which cannot be decided in a Writ Petition filed under
Article 226 of the Constitution of India. Ordinarily, this
Court will not decide, in exercise of its extraordinary
jurisdiction under Article 226 of the Constitution of India,
the disputed questions of fact. On this aspect, it is
pertinent to refer to a decision in M.P. Power Management
Company Limited, Jabalpur v. Sky Power Southeast Solar
65
India Private Limited & others,
3 wherein it is held thus:
(paragraphs 89.1 to 89.9).
“82. We may cull out our conclusions in regard to the
points, which we have framed:
82.1. It is, undoubtedly, true that the writ jurisdiction
is a public law remedy. A matter, which lies entirely
within a private realm of affairs of public body, may not
lend itself for being dealt with under the writ
jurisdiction of the Court.
82.2. The principle laid down in Bareilly Development
Authority [Bareilly Development Authority v. Ajai Pal
Singh, (1989) 2 SCC 116] that in the case of a non-
statutory contract the rights are governed only by the
terms of the contract and the decisions, which are
purported to be followed, including Radhakrishna
Agarwal [Radhakrishna Agarwal v. State of Bihar,
(1977) 3 SCC 457] , may not continue to hold good, in
the light of what has been laid down in ABL [ABL
International Ltd. v. Export Credit Guarantee Corpn. of
India Ltd., (2004) 3 SCC 553] and as followed in the
recent judgment in Sudhir Kumar Singh [State of U.P. v.
Sudhir Kumar Singh, (2021) 19 SCC 706 : 2020 SCC
OnLine SC 847] .
3
(2023) 2 SCC 703
66
82.3. The mere fact that relief is sought under a
contract which is not statutory, will not entitle the
respondent State in a case by itself to ward off scrutiny
of its action or inaction under the contract, if the
complaining party is able to establish that the
action/inaction is, per se, arbitrary.
82.4. An action will lie, undoubtedly, when the State
purports to award any largesse and, undoubtedly, this
relates to the stage prior to the contract being entered
into (see Ramana Dayaram Shetty [Ramana Dayaram
Shetty v. International Airport Authority of India, (1979)
3 SCC 489] ). This scrutiny, no doubt, would be
undertaken within the nature of the judicial review,
which has been declared in the decis ion in Tata
Cellular v. Union of India [Tata Cellular v. Union of
India, (1994) 6 SCC 651] .
82.5. After the contract is entered into, there can be a
variety of circumstances, which may provide a cause of
action to a party to the contract with the State, to seek
relief by filing a writ petition.
82.6. Without intending to be exhaustive, it may
include the relief of seeking payment of amounts due to
the aggrieved party from the State. The State can,
indeed, be called upon to honour its obligations of
making payment, unless it be that there is a serious
and genuine dispute raised relating to the liability of
the State to make the payment. Such dispute,
67
ordinarily, would include the contention that the
aggrieved party has not fulfilled its obligations and the
Court finds that such a contention by the State is not a
mere ruse or a pretence.
82.8. The existence of a provision for arbitration,
which is a forum intended to quicken the pace of
dispute resolution, is viewed as a near bar to the
entertainment of a writ petition [see in this regard, the
view of this Court even in ABL [ABL International Ltd. v.
Export Credit Guarantee Corpn. of India Ltd., (2004) 3
SCC 553] explaining how it distinguished the decision
of this Court in State of U.P. v. Bridge & Roof Co. (India)
Ltd. [State of U.P. v. Bridge & Roof Co. (India) Ltd.,
(1996) 6 SCC 22] , by its observations in SCC para 14
in ABL [ABL International Ltd. v. Export Credit
Guarantee Corpn. of India Ltd., (2004) 3 SCC 553] ].
82.7. The existence of an alternate reme dy, is,
undoubtedly, a matter to be borne in mind in declining
relief in a writ petition in a contractual matter. Again,
the question as to whether the writ petitioner must be
told off the gates, would depend upon the nature of the
claim and relief sought by the petitioner, the questions,
which would have to be decided, and, most
importantly, whether there are disputed questions of
fact, resolution of which is necessary, as an
indispensable prelude to the grant of the relief sought.
Undoubtedly, while there is no prohibition, in the writ
court even deciding disputed questions of fact,
68
particularly when the dispute surrounds demystifying
of documents only, the Court may relegate the party to
the remedy by way of a civil suit.
82.9. The need to deal with disputed questions of fact,
cannot be made a smokescreen to guillotine a genuine
claim raised in a writ petition, when actually the
resolution of a disputed question of fact is unnecessary
to grant relief to a writ applicant.”
33. According to the respondents, Clause 1.3.2 of
the General Conditions of Contract annexed to the contract
agreement dated 07.11.2022, the parties agree to resolve
the disputes through Arbitration. Clause 1.3.2 of the
General Conditions of Contract annexed to the contract
agreement dated 07.11.2022, provides for „Arbitration‟. A
perusal of the said Clause goes to show that the said
Clause provides for resolution in respect of the disputes
arose between the parties in regard to monetary claims.
The same is not apt for resolution of the issues in the case
on hand.
34. A perusal of Clause 1.3.4 of the General
Conditions of Contract annexed to the contract agreement
69
dated 07.11.2022 deals with „Resolution of disputes
through conciliation by OEC (Outside Expert Committee).
In fact, as seen from the averments in the Additional
affidavit filed by the petitioners, vide letter dated
08.12.2024, the petitioners requested resolution of the
matter through mediation by OEC. In terms of Clause
1.3.4 (2) thereof, if any dispute, difference, question or
disagreement arises between the parties hereto or their
respective representatives or assignees, in connection with
construction, meaning, operation, effect, interpretation of
the contract or breach thereof which parties are unable to
settle mutually, the same may first be referred to
conciliation through Outside Expert Committee to be
constituted by CMD, ONGC, as provided thereunder.
Therefore, there is a mechanism provided for resolution of
the subject disputes arising between the parties.
Accordingly, the parties are relegated to avail the
mechanism provided in the General Conditions of Contract
annexed to the contract agreement dated 07.11.2022 , for
resolution of the said dispute viz. the percentage of work
70
completed by the petitioners, reasons for delay in execution
of the contract, etc.. The point is answered accordingly.
35. In view of the foregoing discussion, this Court is
of the opinion that the impugned termination order dated
03.08.2024, is not sustainable on the grounds mentioned
therein and the same is liable to be set aside.
36. Accordingly, the Writ Petition is allowed, setting
aside the impugned order No. DLH/OES/MM/GDU/RJY &
CAV/X11VC21007/2021/Group A, dated 03.08.2024
issued by 2
nd respondent and all other consequential
proceedings pursuant thereto. No costs.
Miscellaneous petitions pending, if any, in the Writ
Petition shall stand closed.
(JUSTICE K. SREENIVASA REDDY)
DRK
08.05.2026
71
THE HON‟BLE SRI JUSTICE K.SREENIVASA REDDY
WRIT PETITION No. 22088 of 2024
08.05.2026
DRK
72
HIGH COURT OF ANDHRA PRADESH AT AMARAVATI
****
WRIT PETITION No.22088 of 2024
Between:
Jsc Golla Engineering Private Limited and Others ...PETITIONER(S)
AND
Oil And Natural Gas Corporation Limited and
Others
...RESPONDENT(S)
DATE OF ORDER PRONOUNCED : 08.05.2026
SUBMITTED FOR APPROVAL :
THE HONOURABLE SRI JUSTICE K. SREENIVASA REDDY
1. Whether Reporters of Local Newspapers
may be allowed to see the Order? Yes/No
2. Whether the copy of Order may be
marked to Law Reporters/Journals? Yes/No
3. Whether His Lordship wish to see the
fair copy of the Order? Yes/No
JUSTICE K.SREENIVASA REDDY
73
* HONOURABLE SRI JUSTICE K.SREENIVASA REDDY
+ WRIT PETITION No.22088 of 2024
% 08.05.2026
Between:
Jsc Golla Engineering Private Limited and Others ...PETITIONER(S)
AND
Oil And Natural Gas Corporation Limited and
Others
...RESPONDENT(S)
Counsel for the Petitioner(S):
1. M/S INDUS LAW FIRM
Counsel for the Respondent(S):
1. The Advocate General for Sri D S SIVADARSHAN
< Gist:
> Head Note:
? Cases referred:
1) 2023 SCC Online Delhi 8172
2) judgment dated 18.11.2022 in Civil Appeal No.8571 of
2022
3) (2023) 2 SCC 703
Legal Notes
Add a Note....