No Acts & Articles mentioned in this case
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE MR. JUSTICE A. BADHARUDEEN
WEDNESDAY, THE 14
TH
DAY OF FEBRUARY 2024 / 25TH MAGHA, 1945
RSA NO. 144 OF 2023
AGAINST THE ORDER IN I.A.NO.1/2021 IN AS NO.101/2021 AND THE DECREE
AND JUDGMENT IN AS 101/2021 OF ADDITIONAL DISTRICT COURT-V, PALAKKAD
AGAINST THE DECREE AND JUDGMENT DATED 21.12.2017 IN OS 336/2005 OF
ADDITIONAL MUNSIFF COURT, PALAKKAD
APPELLANTS/APPELLANTS/DEFENDANTS:
1 THE STATE OF KERALA
REPRESENTED BY THE DISTRICT COLLECTOR
PALAKKAD, PIN - 678001
2 THE TAHSILDAR
TALUK OFFICE, PALAKKAD,
PIN - 678001
3 THE RESURVEY SUPERINTENDENT
OTTAPPALAM, PIN - 679101
BY ADV SRI.DENNY K DEVASSY, SR.GOVERNMENT PLEADER
RESPONDENT/RESPONDENT/PLAINTIFF:
K ARAVINDAKSHAN PILLAI
AGED 61 YEARS
S/O KRISHNA PILLAI , THOTTAPURA ,
MALAMPUZHA-1 VILLAGE , PALAKKAD, PIN - 678651
BY ADVS.
P.B.SUBRAMANYAN
P.B.KRISHNAN(K/1193/1994)
SABU GEORGE(K/000711/1998)
MANU VYASAN PETER(K/000652/2013)
THIS REGULAR SECOND APPEAL HAVING COME UP FOR HEARING ON
07.02.2024, THE COURT ON 14.02.2024 DELIVERED THE FOLLOWING:
2024/KER/10965
RSA NO.144 OF 2023
2
CR
JUDGMENT
Dated this the 14
th
day of February, 2024
The State of Kerala represented by the District
Collector, Palakkad and others are the appellants, who are
the defendants in O.S.No.336/2005 on the files of the
Additional Munsiff's Court, Palakkad, in this regular second
appeal filed under Section 100 read with Order XLII Rule 1 of
the Code of Civil Procedure, 1908. The sole respondent
herein is the original plaintiff.
2.Heard the learned Government Pleader appearing
for the appellants and the learned Senior Counsel appearing
for the respondent in detail.
3.I shall refer the parties in this regular second
appeal as 'plaintiff' and 'defendants' for convenience.
4.On hearing both sides, the following substantial
questions of law raised and the appeal is admitted:
2024/KER/10965
RSA NO.144 OF 2023
3
1. Whether the appellants herein established
'sufficient cause' to condone delay in filing
A.S.No.101/2021 before the District Court,
Palakkad, as contended in I.A.No.1/2021 in
the said appeal, within the mandate of
Section 5 of the Limitation Act ?
2. While considering the impact of Section 5 of
the Limitation Act, any concession or leeway
to be provided to the State where the laches
of the officials to secure unholy gains are
apparent?
5.The learned Government Pleader, appearing for
the State, would submit that admittedly, the first appeal was
filed along with I.A.No.1/2021 to condone delay of 1427 days.
According to the learned Government Pleader, the reasons
for the delay are illustrated in the affidavit in support of the
petition. It is pointed out that the present appellant, Tahsildar
(Land Records), Palakkad, took charge on 18.06.2020 and
there occurred some delay and the delay was not willful and
deliberate, and the same was the result of the incorrect
2024/KER/10965
RSA NO.144 OF 2023
4
appreciation of facts from the records made available by the
officials concerned. Accordingly, the learned Government
Pleader pressed for remanding the matter before the first
appellate court, after condoning the delay, by allowing
I.A.No.1/2021, for hearing the appeal on merits.
6.The learned Senior counsel appearing for the
plaintiff vehemently opposed condonation of delay as well as
any order upsetting the finding of the first appellate court as
well as the trial court in this appeal, mainly canvassing the
lethargy throughout the proceedings on the part of the
appellants by pointing out sequence of events starting from
28.07.2007 to 10.01.2023. The prime argument at the
instance of the learned Senior counsel is that I.A.No.1/2021
had been filed as on 15.12.2021 and about 10 months
before, exactly on 24.02.2021, the second appellant filed
counter affidavit in E.P.No.143/2018 vide E.A.No.68/2021
and also filed petition to re-call the warrant issued against
him by the execution court while proceeding to execute the
2024/KER/10965
RSA NO.144 OF 2023
5
decree in E.P.No.143/2018.
7.When the recent decision of the Apex Court
granting leeway to the Government in the matter of delay is
pointed out, the learned Senior counsel bona fidely placed
the said decision in Sheo Raj Singh (Deceased) through
legal representatives and Others v. Union of India and
Another, reported in (2023) 10 SCC 531 and referred the
earlier decisions considered by the Apex Court therein, with
particular mention to the decision in University of Delhi v.
Union of India, reported in (2020) 13 SCC 745 and also the
decision in State of Madhya Pradesh and Others v.
Bherulal, reported in (2020) 10 SCC 654.
8.On perusal of the above decision, the Apex Court
considered challenge against condonation of delay of 479
days in filing an appeal against a reference under Section 18
of the Land Acquisition Act, 1894, at the instance of the
Union of India. In the said case, the High Court condoned the
delay and the same was challenged before the Apex Court.
2024/KER/10965
RSA NO.144 OF 2023
6
The Apex Court justified condonation of delay after referring
the three Bench decision in University of Delhi's case
(supra) and set out principles governing consideration of the
expression ‘sufficient cause’ and in paragraph 35, the
principles have been summarised as under:
“35.1. The law of limitation was founded on
public policy, and that some lapse on the part of a
litigant, by itself, would not be sufficient to deny
condonation of delay as the same could cause
miscarriage of justice.
35.2. The expression "sufficient cauşe" is elastic
enough for courts to do substantial justice.
Further, when substantial justice and technical
considerations are pitted against one another, the
former would prevail.
35.3. It is upon the courts to consider the
sufficiency of cause shown for the delay, and the
length of delay is not always decisive while
exercising discretion in such matters if the delay is
properly explained. Further, the merits of a claim
were also to be considered when deciding such
applications for condonation of delay.
2024/KER/10965
RSA NO.144 OF 2023
7
35.4. Further, a distinction should be drawn
between inordinate unexplained delay and
explained delay, where in the present case, the
first respondent had sufficiently explained the
delay on account of negligence on part of the
government functionaries and the government
counsel on record before the Reference Court.
35.5. The officer responsible for the negligence
would be liable to suffer and not public interest
through the State. The High Court felt inclined to
take a pragmatic view since the negligence therein
did not border on callousness.”
9.It was observed in paragraph 41 of the decision in
Sheo Raj's case (supra) as under:
“As the aforementioned judgments have shown,
such an exercise of discretion does, at times, call
for a liberal and justice-oriented approach by the
courts, where certain leeway could be provided to
the State. The hidden forces that are at work in
preventing an appeal by the State being
presented within the prescribed period of limitation
so as not to allow a higher court to pronounce
upon the legality and validity of an order of a lower
2024/KER/10965
RSA NO.144 OF 2023
8
court and thereby secure unholy gains, can hardly
be ignored. Impediments in the working of the
grand scheme of governmental functions have to
be removed by taking a pragmatic view on
balancing of the competing interests.”
10.The learned Senior counsel has given much
emphasis to paragraph 5 of the decision in State of Madhya
Pradesh and Others v. Bherulal's case (supra) and the
same as under:
“5. A preposterous proposition is sought to
be propounded that if there is some merit in the
case, the period of delay is to be given a go-by. If
a case is good on merits, it will succeed in any
case. It is really a bar of limitation which can even
shut out good cases. This does not, of course,
take away the jurisdiction of the Court in an
appropriate case to condone the delay.”
11.Whereas it is submitted by the learned
Government Pleader that, on merits, the appellants have a
good case to argue before the first appellate court and
meritorious disposal of the first appeal may be facilitated by
2024/KER/10965
RSA NO.144 OF 2023
9
allowing the delay condonation petition and remanding the
matter before the first appellate court. The learned
Government Pleader also placed a Division Bench decision
of this Court in Abdul Khader v. Rapheal T.George,
reported in 2023 KHC 9094, where this Court dealt with
matters to be considered under Section 5 of the Limitation
Act and held as under:
“It is well settled that the Law of Limitation is
founded on public policy to ensure that the
parties to a litigation do not resort to dilatory
tactics and seek legal remedy without delay. In
an application filed under S.5 of the Limitation
Act, the court has to condone the delay if
sufficient cause is shown. Adopting a liberal
approach in condoning the delay is one of the
guiding principles, but such liberal approach
cannot be equated with a licence to approach
the court-at-will disregarding the time limit fixed
by the relevant statute. The acts of negligence
or inaction on the part of a litigant do not
constitute sufficient cause for condonation of
delay. Therefore, in the matter of condonation
2024/KER/10965
RSA NO.144 OF 2023
10
of delay, sufficient cause is required to be
shown, thereby explaining the sequence of
events and the circumstances that led to the
delay.”
12.Insofar as the question as to condonation of delay
by resorting to Section 5 of the Limitation Act is concerned,
delay can be condoned if 'sufficient cause' is shown and the
approach of the courts should be liberal guided by legal
principles. At the same time, dilatory tactics, if borne out from
materials, shall be treated sternly and liberal approach
cannot be extended to those persons. However, it is noticed
that the State and its instrumentalities used to file litigations,
including appeals, second appeals, revisions, etc., with
prayer to condone delay/long delay and in almost all the
cases of the said nature, except a few, reading between the
lines, the hands of the hidden forces, who had worked in
preventing timely filing of litigations, could be decipherable.
There may be deliberate or intentional omissions so as to go
2024/KER/10965
RSA NO.144 OF 2023
11
in hands with the opposite parties with ulterior motives. The
same practically would become detrimental and causing loss
to public property and public money. So, if delay is sought to
be condoned by the State and its instrumentalities, wherein
hidden forces and materials of such nature are apparent, in
order to prevent timely filing of litigations, the same also to be
taken note of, as held by the Apex Court in Sheo Raj’s case
(supra). Therefore, at times when the materials would show
that hidden forces in the form of officials behind the curtain
meddled in not filing the litigations within time or without
much delay, as part of liberal and justice-oriented approach
by the courts, some sort of leeway or concession could be
provided to the State, in order to protect the interest of the
public at large and to avoid unlawful enrichment by the
opposite side.
13.The learned Senior counsel for the plaintiff has
given much emphasis to the Apex Court decision in State of
2024/KER/10965
RSA NO.144 OF 2023
12
Madhya Pradesh and Others V. Bherulal (supra) to contend
that if there is merit in the case, bar of limitation is to be given
a go-by, and when the case lacks merit, the bar of limitation
is to be shut out.
14.However, in State of Madhya Pradesh and Others
V. Bherulal (supra), though the Apex Court observed so, it was
held that the same did not, of course, take away the jurisdiction
of the court in an appropriate case to condone the delay.
Further, the said decision in no way laid a ratio that in cases
having merits, condonation of delay is either mandatory or in
deviation of the statutory sanction under Section 5 of the
Limitation Act.
15.The learned Senior counsel argued a little on the
merits of the matter and the ordeals suffered by the plaintiff
starting from 2005 onwards to address his grievance, wherein
the lethargic attitude on the part of the defendants stands in the
way of having a quietus to the lis.
2024/KER/10965
RSA NO.144 OF 2023
13
16.Whereas it is submitted by the learned
Government Pleader that in this case, the identification of
property was done at the instance of the municipal surveyor
and the property was not properly identified with the old
survey number. Instead, the property was identified on the
basis of the re-survey number and in the re-survey, there
was mistake. Therefore, the first appeal requires
consideration on merits by the first appellate court, for which
the delay is to be condoned in the case at hand where delay
on the part of the officials in taking follow up steps is cited as
the reason for condonation of delay.
17.The inevitable conclusion of the above discussion
is that since the State is the appellant and the delay is the
outcome of deficiency and derelictions on the part of the
officials in acting in time, some concession or leeway to be
given to the Government. Accordingly, the delay petition
I.A.No.1/2021 stands allowed, subject to payment of cost of
2024/KER/10965
RSA NO.144 OF 2023
14
Rs.5,000/- (Rupees five thousand only) to the plaintiff within
a period of four weeks by the defendants from the date of
appearance of the parties before the first appellate court and
accordingly, the order in I.A.No.1/2021 stands set aside and
I.A.No.1/2021 stands allowed. Consequently, dismissal of the
first appeal also stands set aside.
18.In the result, this regular second appeal stands
allowed and the matter remitted back to the first appellate
court for hearing the appeal on merits, subject to payment of
cost, as ordered herein above.
19.The first appellate court is directed to hear and
dispose of the appeal within a period of one month from the
date of payment of cost, if the cost is paid as directed and on
failure to pay the cost, the delay petition I.A.No.1/2021 will
stand dismissed. If so, the dismissal of the first appeal by the
first appellate court also will stand revived.
20.Before parting, as an addendum, this Court is
2024/KER/10965
RSA NO.144 OF 2023
15
inclined to look into the unfortunate consequences of delay
on the part of the Sate Officials in conducting the litigations
timely and properly. It is shocking to note that there is
callous negligence or lackadaisical attitude on the part of the
officials of the Government to conduct litigations, timely and
properly, to protect the interest of the State, in fact, the
property and money of the public at large, though they are
duty bound to be vigilant in this regard. Invariably, when
State is a party, the other party would succeed in the
litigations mainly because of the laches on the part of the
officials, though on merits State has good reason to win the
cases. Such instances noted with extreme displeasure,
utmost anxiety and seriousness and there should be some
effective mechanism to realize the loss caused to the
Government due to inaction and dereliction by the officials.
Therefore, the appropriate Governments are hereby
requested to consider enactment of an exhaustive legislation
to deal with this menace to avoid losing government property
2024/KER/10965
RSA NO.144 OF 2023
16
and money/ public property and money due to the lethargy
on the part of the officials, without much delay, adverting to
the interest of the public at large.
21.The parties are directed to appear before the first
appellate court on 26.02.2024.
22.All interlocutory orders stand vacated and all
interlocutory applications pending in this regular second
appeal stand dismissed.
Registry is directed to forward a copy of this judgment
to the trial court and the first appellate court for information
and compliance.
Registry is also directed to forward copies of this
judgment to the Law Secretary to the Union of India and the
Chief Secretary, State of Kerala for information and further
action, if any.
Sd/-
A. BADHARUDEEN
JUDGE
nkr
2024/KER/10965
RSA NO.144 OF 2023
17
APPENDIX OF RSA 144/2023
PETITIONER ANNEXURES
Annexure1 ANNEXURE A1-DELAY CONDONATION
PETITION AND AFFIDAVIT FILED IN AS
NO. 101/2021
2024/KER/10965
Legal Notes
Add a Note....