Writ Petition, Deemed Conveyance, MOFA, Housing Society, Land Dispute, Developer, High Court Bombay, Land Rights, FSI, Civil Appellate Jurisdiction
 18 Jun, 2026
Listen in 01:17 mins | Read in 40:30 mins
EN
HI

Kiran Builders Pvt. Ltd. Vs. Kalpita Enclave Co-operative Housing Society Ltd. And Ors.

  Bombay High Court WRIT PETITION NO. 9694 OF 2017
Link copied!

Case Background

As per case facts, Kiran Builders Pvt. Ltd., a developer, built several buildings, with flat purchasers forming Kalpita Enclave Co-operative Housing Society Ltd. and two other societies. A dispute arose ...

Bench

Applied Acts & Sections

No Acts & Articles mentioned in this case

Hello! How can I help you? 😊
Disclaimer: We do not store your data.
Document Text Version

Neeta Sawant                                                                                                                                     WP---9694-2017.docx   

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

CIVIL APPELLATE JURISDICTION

WRIT PETITION NO. 9694 OF 2017

Kiran Builders Pvt. Ltd. ...Petitioner

V/s.

Kalpita Enclave Co-operative

Housing Society Ltd. And Ors.

...Respondents

WITH

INTERIM APPLICATION NO. 14625 OF 2023

Panom Developers LLP ...Applicant

In the matter between :

Kiran Builders Pvt. Ltd. ...Petitioner

V/s.

Kalpita Enclave Co-operative

Housing Society Ltd. And Ors.

...Respondents

WITH

INTERIM APPLICATION NO. 1080 OF 2026

Kalpita Enclave Co-operative

Housing Society Ltd. And Ors.

...Applicants

In the matter between :

Kiran Builders Pvt. Ltd. ...Petitioner

V/s.

Kalpita Enclave Co-operative

Housing Society Ltd. And Ors.

...Respondents

Page No.    1   of    27   

18 June 2026

Neeta Sawant                                                                                                                                     WP---9694-2017.docx   

_______

Mr. Mahendra Ghelani with Ms. Nizzica Pinto and Ms. Sneha Vani, for

the Petitioner.

Dr. Birendra Saraf, Senior Advocate with Mr. Rohan Savant, Mr.

Nirmal Devmani, Mr. Aman Saraf and Mr. Abhijeet Mahadeokar i./b. Mr.

Diwakar Gond, for Respondent Nos.1 to 3.

Ms. M.S. Bane AGP, for the State.

________________

CORAM: SANDEEP V. MARNE, J.

Reserved On: 11 June 2026.

Pronounced On: 18 June 2026.

Judgment:

1) The Petitioner-Developer has challenged the Order dat ed

15 May 2017 passed by the District Deputy Registrar, Co-operative

Societies-3, Mumbai and Competent Authority (Competent Authority)

under Section 11 of the Maharashtra Ownership Flats (Regulation of the

Promotion of Construction, Sale, Management and Transfer) Act, 1963

(MOFA) granting unilateral deemed conveyance in respect of the land

admeasuring 21,736 sq. mtrs together with buildings standing thereon

in favour of Respondent Nos.1 to 3-Societies.

FACTS

2) Petitioner is a developer claiming rights in respect of the

land situated at CTS No. 69/6 (PT) and CTS No.35 of Village-Vile Parle

Page No.    2   of    27   

18 June 2026

Neeta Sawant                                                                                                                                     WP---9694-2017.docx   

admeasuring 26,000 sq.yards equivalent to 21,736 sq.mtrs. (subject

land) Petitioner undertook construction of 10 buildings bearing Nos. A

to H, J and K on the subject land. After surrendering of land required for

44 feet D.P. road forming part of the subject land, Petitioner secured

extra FSI and has also constructed buildings L and M on the subject

land. Petitioner also proposed construction of Buildings Nos. N and P

on the basis of additional FSI out of surrendered land for DP road.

However, on account of dispute relating to exact area of surrendered

land for D.P. road, Petitioner has not yet been able to construct

Building Nos. N and P on the subject land.

3) Kalpita Enclave CHSL (Respondent No.1) is formed by �at

purchasers of 10 buildings namely A to H, J and K. Respondent No.1-

Society was opposed to construction of Buildings Nos. L, M, N and P by

the Petitioner-Developer and accordingly instituted S.C. Suit No. 3226

of 1985 before the City Civil Court, Bombay and claimed conveyance of

entire land admeasuring 21,736 sq.mtrs. By judgment and decree dated

7 November 1997, the City Civil Court directed conveyance of only land

appurtenant of buildings Nos. A to H, J and K in favour of Respondent

No.1- Society. Respondent No.1-Society �led First Appeal No. 1091 of

2000 before this Court, which was admitted. In the meantime,

construction of Building Nos. L and M also got completed. The

Occupiers of �ats of Building No. ‘L’ formed Kalpita Enclave Building

No. L CHSL (Respondent No.2). Similarly, occupiers of �ats in Building

No. ‘M’ formed Kalpita Enclave Building No. M CHSL (Respondent No.

3). Respondent No.1-Society withdrew First Appeal No. 1091 of 2000 on

Page No.    3   of    27   

18 June 2026

Neeta Sawant                                                                                                                                     WP---9694-2017.docx   

16 September 2016 expressing intention to apply for dee med

conveyance.

4) After withdrawal of the First Appeal, Respondent Nos.1 to

3 jointly �led application under Section 11(3) of MOFA before the

Competent Authority seeking deemed conveyance of entire land

admeasuring 21,736 sq.mtrs. and building constructed thereon.

Petitioner opposed the application for deemed conveyance by �ling

reply. By impugned order dated 15 May 2017, the Competent Authority

has granted Certi�cate of unilateral deemed conveyance in respect of

land admeasuring 21,736 sq.mtrs along with buildings in favour of

Respondent Nos.1 to 3-Societies. Petitioner is aggrieved by certi�cate

of unilateral deemed conveyance dated 15 May 2017 and h as

accordingly �led the present petition. By order dated 5 March 2024, this

Court admitted the petition and passed interim order restraining

Respondent Nos.1 to 3 from acting on the impugned order of the

Competent Authority.

5) Since pleadings in the Petition are complete, with the

consent of the learned counsel appearing for the parties, the petition is

taken up for �nal disposal.

SUBMISSIONS

6) Mr. Ghelani, the learned counsel appearing for the

Petitioner submits that the Competent Authority has grossly erred in

granting deemed conveyance of the land in favour of Respondent Nos.1

Page No.    4   of    27   

18 June 2026

Neeta Sawant                                                                                                                                     WP---9694-2017.docx   

to 3-Societies by ignoring the decree dated 7 November 1997 passed in

S.C. Suit No. 3226 of 1985. That the decree has attained �nality on

account of withdrawal of the First Appeal on 16 September 2016. That

decree dated 7 November 1997 conveyed only land appurtenant to

Building Nos. A to H, J and K in favour of Respondent Nos.1-Society,

whereas now the said Society is claiming rights in respect of the entire

land admeasuring 21,736 sq.mtrs alongwith Respondent Nos.2 and 3.

That the issue of title to the portion of land in the layout between the

Petitioner and Respondent No. 1 is �nally settled by the decree of the

City Civil Court and that the Competent Authority does not have

jurisdiction to pass order contrary to the City Civil Court’s decree.

7) Mr. Ghelani further submits that the Competent Authori ty

has completely ignored the position that land admeasuring 1859 sq.

mtrs is handed over to Municipal Corporation of Greater Mumbai

(MCGM) for DP road and land admeasuring 158.05 sq.mtrs is reserved

for municipal market and land admeasuring 243.07 sq.mtrs is reserved

for primary school. That therefore the said land cannot be conveyed in

favour of the Respondent-Societies. That the Competent Authority has

completely ignored this position and has erroneously granted

conveyance of entire land admeasuring 21,736 sq.mtrs.

8) Mr. Ghelani further submits that the case involves layout

development. That Petitioner has so far constructed only Building Nos.

A to H, J and K and L and M. That the Petitioner has proposed

construction of Building Nos. N and P in the layout. That plans for

construction of Building Nos. N and P were sanctioned by MCGM and

Page No.    5   of    27   

18 June 2026

Neeta Sawant                                                                                                                                     WP---9694-2017.docx   

�at purchasers of Building Nos. A to H and J and K and the members of

Respondent-Societies were always aware of Petitioner’s plan for

construction of Building Nos. N and P in the layout. He submits that

MCGM illegally reduced the area of land taken up for construction of

D.P. Road from 2200 sq.mtts to 1859 sq.mtrs putting the construction

of Buildings Nos. N and P in jeopardy. That apart from Petitioner’s right

to claim FSI in respect of DP road land of 2200 sq. mtrs., there is also

reservation of land admeasuring 158.05 sq. mtrs for municipal market

and 243.07 sq.mtrs for primary school. That for reservation of that land,

Petitioner is entitled to secure development rights. That therefore the

land for DP road is erroneously reduced, the Petitioner is bound to

secure development rights in respect of the land reserved for municipal

market and primary school. That the process of handing over of land to

municipal market and primary school is held up on account of

neighboring landowners not cooperating with the MCGM. That only

part of Petitioner’s land is reserved for the said two purposes and the

balance land reserved is owned by other neighboring land owners. That

Petitioner has always showed willingness to surrender his part of the

reserved land, but the Municipal Corporation has expressed

unwillingness to accept possession of only part of the reserved lands.

That Petitioner has always given option to Respondent-Societies to

either compensate Petitioner in respect of the development potential in

respect of Building Nos. N and P for taking conveyance of the entire

land or to exclude the lands meant for Building Nos. N and P from the

conveyance.

Page No.    6   of    27   

18 June 2026

Neeta Sawant                                                                                                                                     WP---9694-2017.docx   

9) Mr. Ghelani further submits that the land is physic ally

available for construction of Building Nos. N and P. That Petitioner has

not given up right to construct Building Nos. N and P. He submits that

the Petitioner cannot be forced to accept monitory compensation for

acquisition of reserved land. That the Petitioner can also utilize

development rights in respect of the reserved land for construction of

Building Nos. N and P. Mr. Ghelani, would accordingly submit that the

issue of conveyance would arise only after the entire layo ut

development is complete. That after construction of Building Nos. N

and P, the Petitioner is willing to grant conveyance of the appropriate

portion of land in favour of Respondent-Societies and Societies formed

by occupants of Building Nos. N and P. That if Respondent Nos.1 to 3

insist that conveyance must be granted even before completion of

construction of Building Nos. N and P, the application be remanded for

conveying only proportionate land as per built-up area utilized in

construction of buildings of Respondent Nos.1 to 3 by carving out land

meant for construction of Building Nos. N and P.

10) Dr. Saraf, the learned senior advocate appearing for

Respondent Nos.1 to 3 opposes the petition. He submits that the decree

dated 7 November 1997 cannot come in the way of Competent

Authority exercising jurisdiction under Section 11 of MOFA. That the

context in which Suit was required to be �led by Respondent No.1 must

be appreciated. At that time, Respondent No1. was opposed to

construction of building Nos. L and M and wanted conveyance of entire

land to itself. However, since Building Nos. L and M got constructed in

the meantime, and since the Occupancy Certi�cate was granted during

Page No.    7   of    27   

18 June 2026

Neeta Sawant                                                                                                                                     WP---9694-2017.docx   

pendency of Suit in November 1990, the entire scenario has changed

which is the reason why Respondent No.1 withdrew First Appeal No.

1091 of 2000 and decided to seek joint conveyance in favour of

Respondent Nos.1 to 3 in respect of the entire land. That therefore the

decree passed in S.C. Suit No. 3226 of 1985 can have absolutely no

effect on the order of deemed conveyance. That Appeal is continuation

of the Suit, and that the Appeal was withdrawn with the speci�c

intention of applying for deemed conveyance.

11) Dr. Saraf further submits that so far as land surrendered for

DP Road and reserved for municipal markets and primary schools are

concerned, Respondent Nos.1 to 3 are willing to give up claims in

respect of those 3 pieces of land. Dr. Saraf goes a step further and

submits that the additional land admeasuring of 123.12 sq.mtrs is taken

over by MCGM in 2001 for widening of Sahar road and land

admeasuring 2328.41 sq.mtrs encroached by slum dwellers which is

outside the compound wall of the Society. He therefore submits that

the entire land admeasuring 4711.65 sq. mts relating to DP road,

municipal market, primary school, road widening and slum

encroachment need not be conveyed to the Respondent-Societies. That

Respondent-Societies are entitled to conveyance of entire land

admeasuring 21,736 sq.mtrs. That they are willing to restrict their

entitlement to land admeasuring 16,584.55 sq. mtrs so as to put an end

to the entire litigation.

12) Dr. Saraf further submits that the Petitioner has lost right

to construct balance Building Nos. N and P. Inviting my attention to the

Page No.    8   of    27   

18 June 2026

Neeta Sawant                                                                                                                                     WP---9694-2017.docx   

pleadings in para-9 of the Petition, Dr. Saraf submits that Building Nos.

N and P were to be constructed only on account of development rights

�owing out of land surrendered for DP road of 2200 sq. mts. That

however actually land area admeasuring 1859 sq. mtrs is ultimately

surrendered for DP road. He relies on letter dated 23 April 1991 of

MCGM to demonstrate that construction of Building Nos. N and P is not

possible on account of non-availability of balance FSI in lieu of DP

road. Dr. Saraf submits that the Petitioner cannot be permitted to

withhold conveyance for satisfying its greed of carrying out additional

constructions as and when new FSI becomes available. He relies on

judgments of this Court in Lakeview Developers Versus. Eternia Co-

operative Housing Society Ltd.

1

and Rajkumar Gulati and Ors. Versus.

S.D. Corporation Pvt. Ltd. and Ors

2

. He submits that the Petitioner can

secure monetary compensation/TDR as and when land reserved for

municipal market and primary school is acquired by the Municipal

Corporation. That TDR arising out of reserved land cannot be treated as

a development potential in respect of the land meant to be conveyed to

the Respondent-Societies. That entire development potential in respect

of the land is consumed by the Petitioner and that therefore it cannot

delay conveyance of the land for eternity. That process of surrender of

land reserved for municipal market and primary school is still not

complete. That the buildings of Respondent No.1-Societies were

constructed during 1970s and even buildings of Respondent Nos.2 and

3-Societies have received Occupancy Certi�cate in November 1990.

That period of over 46 years have passed from construction of the last

building and it is high time that conveyance of the land is granted in

1 2015 SCC Online Bom 3824

2 2025 SCC Online Bom 4370

Page No.    9   of    27   

18 June 2026

Neeta Sawant                                                                                                                                     WP---9694-2017.docx   

favour of the Societies. Dr. Saraf accordingly prays for issuance of a

direction to the Competent Authority to issue certi�cate of unilateral

deemed conveyance of land admeasuring 16584.55 sq.mtrs.

CONSIDERATION OF SUBMISSIONS

13) Petitioner undertook development of several buildings on

land admeasuring 21,736 sq.mtrs. While undertaking phase wise

development, initially Building Nos. A, B, C, D, F and G were

constructed on portions of the subject land. Thereafter, four buildings

bearing Nos. E, H, J and K were constructed on the subject land. It

appears that a portion of the said property was required for

construction of 44 feet D.P. road. Petitioner believed that the area of

land required to be surrendered for DP road out of the subject land was

2200 sq.mtrs. Accordingly, in the year 1983, Petitioner put up revised

plans for development of the total land admeasuring 21,736 sq.mtrs by

seeking development rights in respect of the land admeasuring 2200

sq.mtrs for DP road. Accordingly, Petitioner proposed to construct 4

additional building Nos. L, M, N and P in the subject land. The plans

were apparently sanctioned on 25 October 1983 which envisaged

construction of Building Nos. N and P as well. Petitioner �rst undertook

development of Building Nos. L and M and completed the same. It

appears that subsequently, the Municipal Corporation took a stand that

the actual area surrendered for DP road was only 1859 sq.mtrs. This

resulted in reduction of available built-up area making construction of

Building Nos. N and P impossible. Accordingly, Petitioner could not

construct Building Nos. N and P on the said property. The Building Nos.

L and M received Occupancy Certi�cate in November 1990 and

Page No.    10    of    27   

18 June 2026

Neeta Sawant                                                                                                                                     WP---9694-2017.docx   

thereafter apparently, no additional construction is put up by the

Petitioner-Developer due to consumption of the entire available FSI

potential based on computation of DP road land of only 1859 sq. mtrs.

14) Thus, as of now what stands on the land are Building Nos.

A to H and J to K and L and M. As observed above, occupants of

buildings A to H and J to K have formed Respondent No.1-Society

whereas occupants of Buildings Nos. L and M have formed Respondent

Nos.2 and 3-Societies respectively. All the three Societies jointly

applied to the Competent Authority for deemed conveyance of the

entire land admeasuring 21,736 sq.mtrs and by the impugned order

dated 15 May 2017, the entire land admeasuring 21,736 sq.mtrs has

been conveyed to Respondent Nos.1 to 3-Societies.

OBJECTION OF CONVEYANCE BEING CONTRARY TO CIVIL COURT’S DECREE

15) The �rst objection raised on behalf of the Petitioner to the

impugned order of deemed conveyance dated 15 May 2017 is that the

same is in the teeth of decree dated 7 November 1997 passed by the

City Civil Court in S.C. Suit No. 3226 of 1985. By decree dated 7

November 1997, the City Civil Court directed Petitioner to convey in

favour of Respondent No.1-Society sub-lease in respect of Building

Nos. A to H, J and K together with land appurtenant thereto with

common right of way and common enjoyment of recreational ground.

The operative part of decree dated 7 November 1997 reads thus:

The Plaintiffs suit is partly decreed as per following terms:-

a) The 1st defendant is ordered and directed to execute an

indenture/conveyance of sub lease in respect of buildings A to H, J

and K together with the land appurtenant thereto, with common right

Page No.    11    of    27   

18 June 2026

Neeta Sawant                                                                                                                                     WP---9694-2017.docx   

of way and common enjoyment of recreation ground of payment of

proportionate costs of maintenance.

b) The 1st defendant is also ordered and directed to submit to the

plaintiffs within six weeks from the date hereof draft of such

indenture/conveyance deed, to be executed together with a copy of

the plan to be attached thereof showing locations of the said buildings

A to H, J and K together with the land appurtenant thereof to be sub-

leased and the common right of way and recreation ground, within 4

weeks from the receipt of the said draft and the plan, and plaintiffs

shall approve the same and get engrossed and stamped and submit to

the 1st defendant for its execution. The parties to the suit will have

liberty to apply in case of disagreement between them.

c)  Upon engrossing and stamping the said sub-lease the plaintiff shall

tender the same to the 1st defendant alongwith the arrears of

proportionate lease rent payable by them as also the arrears of

outstanding payable by them to 1st defendant and the 1st defendant

shall execute the same within 2 weeks thereof. The plaintiffs shall

lodge the same for registration with Sub-Registrar of assurances and

pay the registration charges and the 1st defendant admit execution

within six weeks thereof.

Rest of the prayers are dismissed. The suit against 2nd defendant is

dismissed. The parties to bear the own costs.

Dated: 7th Nov. 1997

16) The decree dated 7 November 1997 was challenged by

Respondent No.1-Society before this Court by �ling First Appeal No.

1091 of 2000. However, the Appeal was withdrawn by Respondent No.1-

Society on 16 September 2016 expressing that the Society intended to

apply for deemed conveyance. Accordingly, the First Appeal was

permitted to be withdrawn vide order dated 16 September 2016, which

reads thus:

P.C.:

1. Not on board. Mentioned. Taken on board.

2. Learned counsel for the appellant/applicants submits that the

appellant-society does not want to proceed with the present appeal.

Page No.    12    of    27   

18 June 2026

Neeta Sawant                                                                                                                                     WP---9694-2017.docx   

The letter to that effect issued by the Secretary of the appellant-

society is produced on record and marked as Annexure-A. The

secretary of the society is also present before the Court and submits

that the society wants to withdraw the appeal as the society intends

to apply for the deemed conveyance.

3. In view thereof, the appeal stands disposed of as withdrawn. No

order as to costs.

4. In view of the disposal of the appeal, the civil application no more

survives and stands disposed of.

5. The permission is granted to apply for the original documents

produced in the case.

17) It is contended on behalf of the Petitioner that withdrawal

of the First Appeal by Respondent No.1-Society has given �nality to the

decree dated 7 November 1997. It is contended that when Civil Court

has directed conveyance of only land appurtenant to Building Nos. A to

H, J and K to Respondent No.1-Society, it was impermissible for that

Society to �le application for deemed conveyance before the

Competent Authority. What is sought to be contended on behalf of the

Petitioner may appear to be attractive in the �rst blush and ordinarily

this Court would not countenance Competent Authority exercising

jurisdiction under Section 11 of MOFA after adjudication of entitlement

for conveyance by the Civil Court. However, what needs to be

appreciated in the present case is the background in which the Suit was

�led and the decree has been passed by the Civil Court. At the time

when S.C. Suit No. 3226 of 1985 was �led, Petitioner-Developer had

completed construction of only Building Nos. A to H, J and K and

Respondent No.1-Society was formed by the �at purchasers thereof.

Petitioner proposed to construct four more Building Nos., L, M, N and P

by utilizing FSI �owing out of land surrendered for DP road.

Page No.    13    of    27   

18 June 2026

Neeta Sawant                                                                                                                                     WP---9694-2017.docx   

Respondent No.1-Society was opposed to the said plans of the

Developer and accordingly �led S.C. Suit No. 3226 of 1985 before the

City Civil Court. The Suit was �led essentially to prevent the Petitioner

from putting up construction of four additional budlings. No doubt, the

Suit was also for claiming conveyance of the entire land in favour of

Respondent No. 1 Society. Thus the �rst Respondent Society believed

that the development potential in the layout was complete after

construction of Building Nos. A to H, J and K and that therefore the

entire land admeasuring 21736 sq. mtrs must be conveyed to it.

18) However, during pendency of the suit, Petitioner was

successful in constructing Building Nos. L and M and the Occupancy

Certi�cate in respect thereof was issued in November 1990. Thus, by

the time decree dated 7 November 1997 was passed, two more Building

Nos. L and M were already constructed by the Petitioner on the land of

which conveyance was sought by Respondent No.1-Society. It appears

that the City Civil Court took into consideration the fact that two more

buildings had come up on the land and accordingly directed conveyance

of only land appurtenant to Building Nos. A to H, J and K in favour of

Respondent No.1-Society. Respondent No.1 got aggrieved by

conveyance of only limited land in its favour and accordingly �led First

Appeal No. 1091 of 2000 in this Court. By the year 2016, the position

that existed was that two more buildings had come up on the land in

respect of which Respondent Nos.2 and 3 Societies were formed. At this

stage the �rst Respondent Society changed its original stance and

agreed that even the societies formed in respect of Building Nos. L and

M are also entitled to conveyance of portion of land and that the entire

Page No.    14    of    27   

18 June 2026

Neeta Sawant                                                                                                                                     WP---9694-2017.docx   

land cannot be conveyed only in favour of Respondent No. 1-Society.

Therefore, all the three Societies came together and decided to seek

joint conveyance of the entire land in their favour rather than �ghting

amongst each other. In my view, this was a correct decision taken by

the three Societies rather than seeking to divide the lands amongst

each other. Respondent Nos.2 and 3-Societies were not parties to S.C.

Suit No. 3226 of 1985 and to First Appeal No. 1091 of 2000. Therefore,

First Appeal could not have been effectively decided in absence of

Respondent Nos.2 and 3-Societies. It would have been dif�cult for the

Appellate Court to decide land entitlement of Respondent No.1 without

hearing Respondent Nos.2 and 3-Societies. Appreciating this dif�culty,

Respondent No.1-Society decided to join hands with Respondent Nos.2

and 3 and claimed conveyance of the entire land.

19) After having decided to seek joint conveyance of the entire

subject land in favour of the three societies, two options were open to

Respondent No.1 Society. The �rst option was to secure conveyance

through the Court. Accordingly, Respondent No. 1 could have applied

for amendment of the Plaint at appellate stage or could have withdrawn

the Appeal with liberty to �le a fresh suit seeking conveyance of entire

land in favour of the three societies. However, provisions of Section 11

of MOFA were amended and a faster and swifter remedy of deemed

conveyance was provided during pendency of the First Appeal. Thus

second option became available for the Respondent Societies and

accordingly they decided to �le application for deemed conveyance.

This is a reason why First Appeal No. 1091 of 2000 was withdrawn

expressing intention to �le application for deemed conveyance.

Page No.    15    of    27   

18 June 2026

Neeta Sawant                                                                                                                                     WP---9694-2017.docx   

20) Considering the above position, it is dif�cult to hold that

decree dated 7 November 1997 came in the way of Competent Authority

deciding an altogether different prayer made by Respondent Nos.1 to 3

Societies for deemed conveyance. Instead of impleading Respondent

Nos.2 and 3 to First Appeal No.1091 of 2000, Respondent No.1-Society

thought it appropriate to �le a joint application for deemed conveyance

along with Respondent Nos.2 and 3. It is well settled that an Appeal is a

continuation of the Suit. What can be done during pendency of Suit can

also be done during pendency of the Appeal. It is always open for a

party to withdraw a conveyance suit and �le application for deemed

conveyance. Legislature has consciously provided for a quicker and

swifter remedy to the Societies to secure conveyance of land.

Therefore, merely because a suit is instituted, the same does not

prevent a Society from applying for deemed conveyance by withdrawing

the suit. In the present case, the Suit was �led when there was no

provision in MOFA for deemed conveyance. Since S.C. Suit No. 3226 of

1985 could have been withdrawn by Respondent No.1-Society with

liberty to �le joint application for deemed conveyance with Respondent

Nos.2 and 3-Societies, the same course of action could be adopted even

during pendency of the First Appeal.

21) In my view, therefore the objection sought to be raised by

the Petitioner about impermissibility for Competent Authority to

decide application for deemed conveyance after withdrawal of the

Appeal is completely misplaced. The objection of res-judicata can also

not be raised since the Appeal was withdrawn expressing intention to

Page No.    16    of    27   

18 June 2026

Neeta Sawant                                                                                                                                     WP---9694-2017.docx   

�le application for deemed conveyance. The objection in this regard

sought to be raised on behalf of the Petitioner is accordingly repelled.

ERROR COMMITTED BY THE COMPETENT AUTHORITY IN CONVEYING LAND

ADMEASURING 21,736 SQ.MTS.

22) It is sought to be contended on behalf of the Petitioner that

the entire land admeasuring 21,736 sq.mts cannot be conveyed in

favour of Respondent Nos.1 to 3 on account of surrender of land for DP

road and reservation of lands for municipal market and primary school.

Dr. Saraf fairly admits that the land admeasuring 1859 sq.mtts is

surrendered for DP road and lands admeasuring 158.05 sq.mtrs and

243.07 sq.mtrs are reserved for municipal market and primary school

respectively. With a view to put an end to the litigation, he fairly

concedes that the said three portions of land need not be conveyed to

Respondent -Societies though in law the Societies may be justi�ed in

seeking conveyance of bene�ts �owing through the said lands. To this

extent, there appears to be an error in the order passed by the

Competent Authority in directing conveyance of entire land

admeasuring 21,736 sq.mtrs.

23) In fact, Dr. Saraf walks a step further and submits that in

addition to exclusion of 3 portions of land surrendered for DP road and

reserved for municipal market and primary school, there is certain more

portion of land which is incapable of being conveyed in favour of

Respondent-Societies. He has submitted that the land admeasuring

123.12 sq.mtrs has been taken over by MCGM for widening of Sahar

road. Similarly, portion of land falling outside Societies’ compound

admeasuring 2328.41 sq.mtrs is encumbered by slum and is not in

Page No.    17    of    27   

18 June 2026

Neeta Sawant                                                                                                                                     WP---9694-2017.docx   

physical possession of the society. It is submitted that societies are not

interested in seeking conveyance of land admeasuring 2328.41 sq.mtrs

encumbered by slum. This is how Respondent Nos.1 to 3 societies are

willing to given up claims in respect of the total land admeasuring

4711.65 sq.mtrs and conveyance is insisted only in respect of land

admeasuring 16584.55 sq.mtrs. The statement showing the above

calculations, which is presented by Respondent Nos.1 to 3 is as under:

Description SQ. MTS.

AREA OF PLOT AS PER 7/12 EXTRACT AS PER APPROVED

LAYOUT PLAN

21,296.20

LESS

A AREA OF PLOT HANDED OVER BY KIRAN BUILDERS TO

BMC FOR DP ROAD

1859.00

B MARKET RESERVATION OF DP 158.05

C PRIMARY SCHOOL RESERVATION 243.07

AREA OF PLOT LESS (A+B+C) 19,522.22

D AREA TAKEN OVER BY BMC IN 2001 FOR WIDENING OF

SAHAR ROAD (5 FEET)

123.12

E AREA ENCUMBERED BY SLUMS AND NOT IN PHYSICAL

POSSESSION (outside compound wall)

2,328.41

TOTAL DEDUCTION ( A+B+C+D+E) 4,711.65

AREA OF PLOT LESS ( A+B+C+D+E) 16,584.65

AREA OF PLOT THAT SOCIETIES ARE SEEKING REVISED

CONVEYANCE OF

16,584.55

24) Thus, there appears to be an error in the order of the

Competent Authority in directing conveyance of entire land

admeasuring 21,736 sq.mtrs and that error can be corrected by this

Page No.   18    of    27   

18 June 2026

Neeta Sawant                                                                                                                                     WP---9694-2017.docx   

Court. The manner in which such correction can be effected is being

discussed in the latter part of the judgment.

PETITIONER’S RIGHT TO CONSTRUCT BUILDING NOS. N AND P AND TO

DELAY CONVEYANCE TILL COMPLETION OF ENTIRE LAYOUT

25) It is contended by the Petitioner that it is ent itled to

construct Building Nos. N and P as per plans sanctioned in the year

1983 and that therefore conveyance of even land admeasuring 16584.55

sq. mtrs., which is claimed to be in physical possession of the Societies,

cannot be granted. It is contended that Building Nos. N and P would

come up on land admeasuring 16584.55 sq.mtrs and this is how

conveyance of even land of 16584.55 sq. mtrs. is also opposed by the

Petitioner.

26) As observed above, after completion of construction of

Building Nos. A to H, J and K, Petitioner proposed construction of four

more Building Nos. L, M, N and P on the land. Construction of the said

four buildings was apparently premised on Petitioner’s belief that the

area of land surrendered for DP road was 2200 sq.mtrs. However, it

latter transpired that the actual land surrendered for DP road was only

1859 sq.mts. Accordingly, the development rights �owing out of

surrendered land for DP road got reduced and Petitioner was prevented

from constructing Building Nos. N and P. He could construct only

Building Nos. L and M out of development rights secured through

surrender of land for DP road. This position is admitted by the

Petitioner in para-9 of the Petition wherein it is averred as under:

Page No.    19    of    27   

18 June 2026

Neeta Sawant                                                                                                                                     WP---9694-2017.docx   

9. Occupation certi�cate of Buildings L and M were issued by MCGM

in November 1990 but construction of building nos. N and P had to be

deferred because on actual demarcation and survey of the DP road

land on site, the area was ascertained to be 1859 sq.mts., instead of

2200 sq.mts., thereby restricting the construction of buildings of N

and P due to de�cit of FSI. The buildings N and P have been approved

in the layout plan and can be constructed in lieu of development

rights but due to matters pending before the Hon'ble court, the

Petitioner has so far refrained from carrying out any remaining

further construction activities on the proposed land.

27) Thus, construction of Building Nos. N and P could not be

carried out by the Petitioner only on account of dispute relating to area

of land surrendered for DP road. For the last 46 long years (after receipt

of OC for Building Nos. L and M) Petitioner has not been able to resolve

the said area dispute. On the other hand, Municipal Corporation has

emphatically informed the Petitioner way back on 23 April 1991 that

there was no balance FSI in lieu of DP road and that construction of

Building Nos. N and P was not possible. The letter dated 23 April 1991

reads thus:

23 APR 1991

M/s. Kiran Builders Pvt. Ltd.;

17, Kamer Building, 

2nd �oor, 38 Cawasji Patel Street, 

Bombay 400023.

Sub.: Certi�cate that there is no N-P building existing

since there is no balance F.S.I. on  property known as

kalpita Enclave.

Sir,

Ref.: Your letter dt. 2-4-91.

With reference to the above, I have to state that there is no

balance F.S.I. in lieu of D. P. Road under 10 (2) on property bearing C.

T. S. No. 27,31,33,35,360,361 and 362 The construction of Building

Page No.    20    of    27   

18 June 2026

Neeta Sawant                                                                                                                                     WP---9694-2017.docx   

No. N-P is not possible. The contents of your letter dated 2-4-1991 are

con�rmed.

Yours Faithfully 

Assistant Engineer Building

Property 

(W.D.) K/E Ward.

28) Faced with the dif�culty that development potential in

respect of the land surrendered for DP road is complete and that no FSI

is available for construction of Building Nos. N and P, Petitioner has

sought to suggest that it is likely to receive development rights at least

qua the land acquired for municipal market and primary school. As

observed above, land admeasuring 158.05 sq.mtrs is earmarked in the

DP for municipal market reservation and land admeasuring 243.07

sq.mtrs. is earmarked for primary school reservation. Petitioner

believes that upon acquisition of those two portions of land, it is likely

to receive development rights which it purposes to utilize for

construction of Building Nos. N and P.

29) I must observe that this novel idea of utilizing

development rights �owing out of reserved land for construction of

Building Nos. N and P now engineered by the Petitioner is preposterous

to the core. There are multiple reasons for holding so:

Firstly, there may or may not be acquisition of lands reserved in DP for

municipal market and primary school. It is not incumbent for the

Planning Authority to acquire the land reserved in the DP. If the land is

not acquired within the stipulated time, it is open for the land owner to

Page No.    21    of    27   

18 June 2026

Neeta Sawant                                                                                                                                     WP---9694-2017.docx   

issue notice under Section 127 of the Maharashtra Regional and Town

Planning Act, 1966 and get the land out of reservation. In that situation

ownership of the land would be retained with the Petitioner.

Secondly, in the event the Municipal Corporation acquiring the land

reserved for municipal market and primary school, the Petitioner would

secure compensation in respect of the acquired land. Though the

Petitioner may opt for Transferable Development Rights (TDR) in

respect of the acquired land, such TDR is issued mainly on account of

�nancial dif�culties of the planning authority in paying monitory

compensation. Thus, Petitioner’s entitlement in respect of acquired

land is towards compensation paid either in monetary terms or through

TDR.

Thirdly, in case the TDR is granted by issuance of Development Rights

Certi�cate (DRC), the FSI/TDR re�ected therein can be utilised in some

other project by the Petitioner itself or can be monetized. TDR is freely

tradable in the market. The DRC can be hoarded, or TDR can be sold in

parts or uitlised by the holder himself or sold completely as per his

desire. Thus, it is not necessary that the TDR must be utilized for

putting up additional construction on the subject land.

Fourthly, Petitioner would still be the owner in respect of the slum land,

which can be redeveloped where the TDR granted for acquired land can

be utilized.

Page No.    22    of    27   

18 June 2026

Neeta Sawant                                                                                                                                     WP---9694-2017.docx   

Fifthly, and most importantly, the compensation receivable either in

monetary terms or in the form of TDR cannot be treated as a

development potential for land to be conveyed in favour of

Respondent-Societies. Once land is acquired, it would get separated

from the layout and would have no relationship with the development

carried out in the layout. Therefore, even if Petitioner chooses to opt

for TDR in respect of the acquired land, the same cannot be treated as a

development potential for construction of Building Nos. N and P which

was envisaged out of usable FSI �owing out of land surrendered for DP

land.

Sixthly, both the lands reserved for municipal market and primary

school have not yet been acquired by the Municipal Corporation.

Petitioner itself has contended that larger lands are earmarked in the

reservations and only some part of Petitioner’s land has been reserved.

Petitioner has admitted that the Municipal Corporation has not shown

willingness to accept possession of only part of reserved land on

account of non-co-operation by the neighboring land owners. These

may be valid dif�culties for the Petitioner. However, till Municipal

Corporation acquires the land and pays compensation/TDR to the

Petitioner, conveyance of the land meant for the Societies cannot be

delayed.

30) In view of the above reasons, it is dif�cult to hold that

there is development potential left in land admeasuring 16584.55

sq.mtrs. of which conveyance is sought by the Petitioner.

Page No.   23    of    27   

18 June 2026

Neeta Sawant                                                                                                                                     WP---9694-2017.docx   

31) Even otherwise, it is well settled position of law that a

Developer cannot put up additional constructions for eternity on the

basis of FSI made available in future. The issue is well settled by

Division Bench judgment of this Court in Lakeview Developers (supra)

in which it has held in paras-55 to 56 as under:

55. In our view, therefore, from the aforesaid judgment, it is clear that

the developer cannot claim that he can continuously exploit the

building potential for eternity without conveying the land in favour of

the Society. The obligation to convey the land in favour of the Society

within a prescribed time and the obligation to make true and full

disclosure under Clauses 3 and 4 of Form V remains unfettered. If the

full development potential of the land is exhausted and the obligation

for conveyance of land in favour of the Society has arisen as per the

Act and Rules and if the developer fails to do so then any further

bene�t which would accrue to the developer on account of any

additional TDR or FSI made available, cannot be used by him for the

purpose of construction of additional buildings. For example,

recently, the Government of Maharashtra has announced that the FSI

which would be available in the City of Greater Mumbai would be

increased by 0.6. The bene�t of this announcement cannot be availed

by a developer who has not conveyed the property in favour of the

Society though he was under legal obligation to do so, having fully

developed the building potential of the land under building as per

true and full disclosure under Section 3 and 4 of the said Act and

Clauses 3 and 4 of Form V of the said Rules. He, therefore, cannot

having failed in his obligation to convey the property within the time

prescribed thereafter claim that full building potential has not been

utilized and claim right to construct further buildings.

56. In our view, from the facts and circumstances of the present case,

it can be seen that though the developer/promoter had fully utilized

the full FSI/potential of the land and was under an obligation to

convey the property after construction of the 10 th building on Sector

IV-A, he is now trying to construct four other buildings by claiming

additional TDR and trying to load it on the four additional buildings.

In our view, prima facie, it can be seen that full development

potential/FSI has already been utilized by the developer and his claim

that additional buildings were constructed by utilizing the additional

TDR prima facie does not appear to be correct if the layout plan

produced by the Plaintiffs/Societies is taken into consideration. 

Page No.    24    of    27   

18 June 2026

Neeta Sawant                                                                                                                                     WP---9694-2017.docx   

32) The principles are reiterated by this Court in its judgment

in Rajkumar Gulati (supra). Therefore, mere possibility of additional

FSI being made available in respect of the reserved land cannot be a

ground for not conveying the land in favour of Respondent-Societies.

CONCLUSIONS

33) In view of the above discussions, I do not �nd any in�rmity

in the Competent Authority exercising jurisdiction under Section 11 of

MOFA for grant of deemed conveyance of the land in favour of

Respondent Nos. 1 to 3-Societies. As observed above, mere passing of

decree in the suit �led by Respondent No. 1 or withdrawal of Appeal by

it does not come in the way of the Competent Authority in entertaining

and deciding the joint application made by Respondent Nos. 1 to 3

societies for deemed conveyance. The Occupancy Certi�cates in respect

of buildings of Respondent No.1-Society were issued in 1970s whereas

those in respect of buildings of Respondent Nos.2 and 3-Societies is

issued in the year 1990. Petitioner has already delayed performance of

its statutory obligation to convey its right, title and interest in the land

and buildings in favour of the Societies under Section 11 of MOFA. The

Competent Authority has rightly stepped into the shoes of the

Petitioner and has performed the act which the Petitioner was

supposed to perform. Therefore, no error can be traced in exercise of

jurisdiction by the Competent Authority.

34) However, the Competent Authority has committed a sligh t

error in conveying entire land admeasuring 21,736 sq.mtrs ignoring the

fact that certain portion of land is surrendered for D.P. road and some

Page No.    25    of    27   

18 June 2026

Neeta Sawant                                                                                                                                     WP---9694-2017.docx   

portion of land is reserved for municipal market and primary school in

the development plan. Additionally, Respondent Nos.1 to 3 have

voluntarily sought deduction of land taken over by MCGM for widening

of Sahar Road, as well as land encroached by slum dwellers. The

Societies have accordingly restricted conveyance in respect of the land

admeasuring only 16584.55 sq.mtrs. Upon conveyance of land

admeasuring 16584.55 sq.mtrs, Petitioner would be able to enjoy rights

in respect of the land admeasuring 158.05 sq.mtrs reserved for

municipal market, land admeasuring 243.07 sq.mtrs reserved for

primary school, as well as land admeasuring 123.12 sq.mtrs taken over

by MCGM for road widening and land admeasuring 2328.41 encroached

upon by slum dwellers. Petitioner can claim bene�ts in respect of the

reserved land and land taken over for road widening. Petitioner can also

carry out redevelopment in respect of the land encroached by slum

dwellers. Respondent-Societies have shown the magnanimity in not

claiming title in respect of land admeasuring 4711.65 sq.mtrs. In my

view, therefore a direction needs to be issued to the Competent

Authority for conveyance of land admeasuring 16584.55 sq.mtrs. in

favour of Respondent Nos.1 to 3-Societies.

ORDER

35) The Petition accordingly succeeds partly, and I proceed to

pass the following order:

(i) Order dated 15 May 2017 passed by the Competent

Authority as well as certi�cate of unilateral deemed

conveyance issued in pursuance thereof are set aside.

Page No.    26    of    27   

18 June 2026

Neeta Sawant                                                                                                                                     WP---9694-2017.docx   

(ii) Application No. 119 of 2016 is remanded to the

Competent Authority for the limited purpose of issuing

certi�cate of unilateral deemed conveyance in respect of

land admeasuring 16584.55 sq.mtrs in favour of

Respondent Nos.1 to 3 -Societies within a period of 3

months.

(iii) Parties shall appear before the Competent Authority

on 24 June 2026 along with copy of this order downloaded

from the website of the Court.

36) With the above directions, the petition is partly allowed.

Rule is made partly absolute. There shall be no order as to costs.

Pending interim applications, if any, are disposed of.

[SANDEEP V. MARNE, J.]

Page No.    27    of    27   

18 June 2026

NEETA

SHAILESH

SAWANT

Digitally signed by

NEETA SHAILESH

SAWANT

Date: 2026.06.18

21:25:07 +0530

Reference cases

Description

Legal Notes

Add a Note....