As per case facts, the petitioner, Krishan Mohan Rathod, challenged land acquisition proceedings initiated by the State Government for industrial development by RIICO. He argued that the acquisition notification incorrectly ...
No Acts & Articles mentioned in this case
In a significant ruling concerning Land Acquisition Proceedings Lapse, the Rajasthan High Court recently delivered a pivotal judgment in the case of Krishan Mohan Rathod (Teli) vs. State of Rajasthan & Others, S.B. Civil Writ Petition No. 2804/1992, decided on July 31, 2026. This authoritative decision, a key reference for understanding Section 24(2) of the Act of 2013, is now thoroughly analyzed and available on CaseOn, providing deep insights into its implications.
The petitioner, Krishan Mohan Rathod (Teli), along with others, was a Khatedar-tenant of land bearing Khasra No. 44 (0.65 hectares) in Village Rajiyali, District Baran. The State Government initiated acquisition proceedings for industrial development by RIICO, issuing a notification under Section 4 of the Land Acquisition Act, 1894 (the ‘1894 Act’) on April 26, 1991. The petitioner challenged these proceedings, alleging various irregularities, including improper notification, non-issuance of a Section 6 declaration, and the absence of a lawful award. Furthermore, the petitioner contended that the acquisition had lapsed under Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 (the ‘2013 Act’), as neither compensation was paid nor possession taken.
The central issue before the Rajasthan High Court was whether the land acquisition proceedings, initiated under the 1894 Act, had lapsed in light of Section 24(2) of the 2013 Act, particularly considering the validity of compensation payment and possession-taking procedures by the respondent authorities.
The Court's analysis primarily hinged on Section 24(2) of the 2013 Act, which stipulates that if an award under the 1894 Act was made five years or more prior to the commencement of the 2013 Act (January 1, 2014), and either compensation has not been paid nor physical possession has been taken, the acquisition proceedings shall lapse. The interpretation of "or" as "nor" was authoritatively settled by the Supreme Court in Indore Development Authority vs. Manoharlal & Others, (2020) 8 SCC 129. This means both conditions—non-payment of compensation AND non-taking of possession—must coexist for the lapse provision to apply.
The Court referred to established precedents, including Banda Development Authority, Banda vs Moti Lal Agrawal & Others, (2011) 5 SCC 394 and Raghbir Singh Sehrawat vs. State of Haryana & Others, (2012) 1 SCC 792, which outline the legitimate procedures for taking possession:
The emphasis is on actual physical possession where applicable, and not merely paper possession. It is important to note that CaseOn.in's 2-minute audio briefs provide quick, comprehensive overviews of these complex procedural rulings, helping legal professionals quickly grasp the nuances of judgments like Indore Development Authority and Banda Development Authority to assist in analyzing these specific rulings effectively.
The Court also considered what constitutes a valid tender of compensation. It was highlighted that compensation must be paid or legally tendered. The issuance of a joint cheque for multiple khatedars, particularly without proof of a joint bank account and when returned by the beneficiaries, would not be considered a valid tender or payment.
The High Court meticulously examined the facts against the legal principles:
The crucial aspect was whether both conditions for lapse under Section 24(2) of the 2013 Act were met:
Since both critical conditions under Section 24(2) of the 2013 Act—neither valid payment/tender of compensation nor legitimate taking of possession—were met, the Court found that the acquisition proceedings had lapsed.
The Rajasthan High Court unequivocally held that the land acquisition proceedings concerning Khasra No. 44 in Village Rajiyali had lapsed. The Court quashed the Section 4 notification dated April 26, 1991, the Section 6 declaration dated January 18, 1992, and the award dated October 3, 1992. Consequently, the respondents are restrained from interfering with the petitioner's possession of the land.
This judgment addresses a writ petition challenging land acquisition proceedings under the 1894 Act. The petitioner sought to quash the acquisition, arguing it lapsed under the 2013 Act because possession was not taken and compensation was not paid. The Court found that while the initial procedural steps (Section 4 notification, Section 6 declaration, and award within timeline) under the 1894 Act were valid, the subsequent requirements for compensation and possession were not met. Specifically, a joint compensation cheque was returned, and no valid alternative payment/tender was made. Furthermore, the Court invalidated the 'Dakhalanama' relied upon by the respondents for possession, citing a lack of legitimate process and an uncontroverted affidavit from the alleged independent witness denying involvement. Therefore, satisfying both conditions of Section 24(2) of the 2013 Act, the Court declared the acquisition lapsed.
This judgment serves as a critical reference for several reasons:
All information provided in this article is for informational purposes only and does not constitute legal advice. Readers are advised to consult with a qualified legal professional for advice on specific legal issues.
Legal Notes
Add a Note....