Arbitration Act 1940, res judicata, constructive res judicata, arbitrator misconduct, counter-claims, review order, Supreme Court, K.V. George
0  05 Oct, 1989
Listen in 01:43 mins | Read in 18:00 mins
EN
HI

K.V. George Vs. Secretary To Govt., Water and Power Department, Trivandrum & Anr.

  Supreme Court Of India Civil Appeal /4209/1989
Link copied!

Case Background

As per case facts, a contractor (appellant) and the government (respondent) entered into a contract for embankment construction, which the contractor failed to complete, leading to its termination. The contractor ...

Bench

Applied Acts & Sections

No Acts & Articles mentioned in this case

Hello! How can I help you? 😊
Disclaimer: We do not store your data.
Document Text Version

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 9

PETITIONER:

K.V. GEORGE

Vs.

RESPONDENT:

SECRETARY TO GOVT., WATER AND POWERDEPARTMENT, TRIVANDRUM &

DATE OF JUDGMENT05/10/1989

BENCH:

RAY, B.C. (J)

BENCH:

RAY, B.C. (J)

MUKHARJI, SABYASACHI (J)

CITATION:

1990 AIR 53 1989 SCR Supl. (1) 398

1989 SCC (4) 595 JT 1989 (4) 166

1989 SCALE (2)822

ACT:

Arbitration Act 1940---Sections 30, 33 and 41--Arbitra-

tor to make award after considering claims and counter

claims of the parties-Failure to do so is misconduct--Prin-

ciples of res-judicata applicable to arbitration proceed-

ings.

HEADNOTE:

The appellant, a contractor had entered into a contract

with the Respondent on 22nd April 1978 for the construction

of an embankment across Musaliyar Podom between chainage

2573.5 M to 2827 M of E.B. Main conal of Kallada Irrigation

Project. Under the contract-agreement, the work was to the

completed by March 30, 1980 i.e. two years From the date of

selection notice which was dated March 30, 1978. The appel-

lant having failed to complete the work as per the terms of

the contract, the Respondent by a notice dated 26.4.80

cancelled the contract at his risk and cost. Consequent

there-to the appellant filed a claim before the named Arbi-

trator (Case No. 132 of 1980), claiming enhancement of rates

in respect of the earth work involved in the contract. He

also claimed interest on delayed payment and costs. The

respondent resisted the claim and urged that the appellant

was not entitled to any enhancement, as the appellant should

have visualised and assessed the position before entering

into work contract which was to be completed within 2 years.

According to respondent the appellant had not even completed

35% of the work. Respondent, No. 2, therefore, filed a

counter-claim for Rs.28,84,000.

The Arbitrator made the award on 22.1.1981 in respect of

claim No. 1 thereby directing the Respondents to pay 35 per

cent increase in the agreed rate for the item of earth work.

However claim regarding interest on delayed payment was

disallowed. As regards the counterclaim filed by the Re-

spondent, the Arbitrator ordered that those issues will be

considered separately and thus no award in respect thereof

was made. The appellant thereupon filed O.P. (Arbitrator) 81

of 1981 before the Sub-Judge Trivandrum for making the award

a rule of the Court.

399

The Respondents having raised objection to the making of

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 9

the award a Rule of the Court, the Sub-Judge remitted the

reference to the arbitrator by his order dated 18.8.81 for

fresh consideration, as the arbitrator had failed to consid-

er the counter-claim made by the respondent. The appellant

applied for review of the said order passed by Sub-Judge.

Contemporaneously, the appellant filed another claim peti-

tion before the arbitrator (case No. 276 of 1980) in respect

of the wrongful termination of the contract and made claim

in respect of 13 items. On 29th October 1981, the arbitrator

made an award whereby he ordered that the re-arrangement of

the work should not be at the risk and cost of the appel-

lants. He also ordered 30% increase in rates for all items

of work carried out by the appellant, except however those

items, which stood covered by his earlier award. Some of the

other claims were also allowed. The appellant filed O.P.

(Arbitrator) 296 of 1981 for making the second award a Rule

of the Court to which the Respondents raised objections. The

Sub-Judge by his order dated March 18, 1982 made the award a

rule of the Court dismissing the plea of res-judicata raised

by the Respondents. The Respondents being dissatisfied with

the order passed by Sub-Judge preferred two appeals before

the Kerala High Court. The High Court allowed both the

appeals holding that the Sub-Judge could not review his

order of the facts of the present case. The High Court also

held that principle of constructive res-judicata would apply

to the arbitration case. Accordingly the High Court set

aside the orders of the Sub-Judge as also the award and

directed that the arbitrator shah dispose of the Arbitration

case No. 132 of 1980 afresh in the light of the Judgment of

Sub-Judge in O.P. (Arbitrator) No. 81 of 1981 and in accord-

ance with law after taking into consideration the claim of

the appellant and the counter claim of the Respondents.

Hence these appeals by the appellant by Special Leave.

Dismissing the appeals, this Court,

HELD: It is the duty of the Arbitrator while considering

the claims of the appellants to consider also the counter

claims made on behalf of the Respondents and to make the

award after considering both the claims and counter claims.

This has not been done and the Arbitrator did not at all

consider the counter-claims of the respondents in making the

award. As such the first award dated 22.1.81 made by the

Arbitrator in Arbitration Case No. 132 of 1980 is wholly

illegal and unwarranted and the High Court was right in

holding that the Arbitrator misconducted himself and in the

proceedings by making such an award, and in setting, aside

the same and directing the Arbitrator to dispose of the

reference in accordance with law con-

400

sidering the claim of the contractor and the counter claim

of the respondent. [406F-G]

The order allowing the application for review by the

Trial Court is also had inasmuch as there was no mistake or

error apparent on the face of the order dated August 18,

1981 made O.P. (Arbitrator) No. 81 of 1981 nor any suffi-

cient reason has been made out for review of the said order.

[406H; 407A]

In the instant case, the contract was terminated by the

Respondents on April 26, 1980 and as such all the issues

arose out of the termination of the contract and they could

have been raised in the first claim petition fried before

the arbitrator by the appellant. This having not been done,

the second claim petition before the arbitrator raising the

remaining disputes is clearly barred. [407H; 408A]

Section 41 of the Arbitration Act provides that the

provisions of the Code of Civil Procedure will apply to the

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 9

Arbitration proceedings. The provisions of res-judicate are

based on the principle that there shall be no multiplicity

of proceedings and there shall be finality of proceedings.

[408B]

Muhammad Hafiz & Anr. v. Mirza Muhammad Zakaria & Ors.,

AIR 1922 (PC) 23; Darvao & Ors. v. The State of U. P. &

Ors., [1962] 1 SCR 574 at 582-83; Satish Kumar & Ors. V.

Surinder Kumar & Ors., AIR 1970 SC 833, referred to.

JUDGMENT:

CIVIL APPELLATE JURISDICTION: Civil Appeal Nos. 4209-10

of 1989.

From the Judgment and Order dated 10.4.1987 of the

Kerala High Court in M.F.A. No. 291 and 304 of 1982.

K.N. Bhat and Mukul Mudgal for the Appellant.

M.M. Abdul Khader and T.T. Kunhikanan for the Respond-

ents.

The Judgment of the Court was delivered by

RAY, J. Special leave granted.

These appeals on special leave have been filed by the con-

tractor,

401

K.V. George against the judgment and order passed on 10th

April, 1987 by the Kerala High Court in M.F.A. No. 291 and

304 of 1982 whereby the High Court set aside the judgment of

the Sub-Court, Trivandrum in O.P. (Arb.) No. 296 of 1981 as

also the award of the Arbitrator in A.C. No. 276 of 1980 and

directed that the Arbitrator will dispose of the Arbitration

case No. 132 of 1980 in the light of the judgment of the

Sub-Court in O.P. (Arb.) No. 81 of 1981 in accordance with

law considering the claim of the contractor-appellant and

the counter-claim of the respondents.

The appellant who is a contractor entered into a con-

tract with the respondents on April 22, 1978 in connection

with the construction of an embankment across Musaliyar

Padom between Chaniage 2573.5 M to 2827 M of E.B. Main canal

of Kallada Irrigation Project. The work was required to be

completed by 30th March, 1980 i.e. two years from the date

of selection notice which was dated 30th March, 1978. As the

appellant failed to complete the work as per the terms of

the contract, the respondents sent a notice dated April 26,

1980 to the appellant cancelling the contract at his risk

and cost. On July 2, 1980 the appellant filed a claim being

arbitration case No. 132 of 1980 before the named Arbitrator

i.e. the Chief Engineer (Arbitration), Vellayambalam, Tri-

vandrum claiming enhancement of rates in respect of the

earth work involved in the contract, interest on delayed

payments and costs. The second respondent, the Superintend-

ing Engineer, K.I.P. Circle, Karnataka filed a defence

statement stating inter alia in para 2(1) that the time of

completion of the work was fixed as 24 months from the date

of handing over site to the contractor and he could have

anticipated all such variations before quoting rates. As per

agreement the rates once agreed will not be enhanced. The

department is not bound to pay the claimant a revision of

schedule. In para 2(m) it has also been pleaded that as per

agreement the contractor is bound to carry out additional

and extra items of works that arise during execution. The

additional and extra items of works done by the contractor

are quite meagre when compared to the total volume of the

work. The extra and excess items were covered by supplemen-

tal agreement. The contractor was not able to complete even

35% of the total work within the time of completion of the

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 9

work and as such the claimant is not entitled to attributed

delay on this account. A counterclaim was filed by the

Superintending Engineer, K.I.P. Circle, Kottarakkara, the

respondent No. 2 wherein a claim of a sum of Rs.28,84,000

was made.

The Arbitrator by his order dated January 22, 1981 made the

402

award in regard to claim No. 1 directing the respondents to

pay 35% increase in the agreed rate for the item of Earth

work excavating and filling for forming the compacted em-

bankment with earth from barrow area. Claim No. 1 was thus

allowed. Claim Nos. 2 and 3 regarding interest were disal-

lowed. As regards counter-claim Nos. 1 and 2, it was ordered

that those issues will be considered separately and so no

award was made.

The appellant thereafter filed O.P. (Arb.) No. 81 of

1981 in the court of Sub-Judge, Trivandrum under section 14

of the Arbitration Act for making the award a rule of the

court. On objections being raised by the respondents, the

Court of the Sub-Judge after hearing the parties by order

dated August 18, 1981 remitted the reference to the Arbitra-

tor for fresh consideration on the ground that the Arbitra-

tor did not consider the counter claims made by the respond-

ents. The appellant thereafter filed I.A. No. 3780/81 in the

court of Sub-Judge praying that the order dated August 18,

1981 may be reviewed. In the, meantime, the appellant filed

another arbitration case No. 276 of 1980 before. the same

Arbitrator in respect of the wrongful termination of the

contract and also raised 13 items of claims therein. The

Arbitrator after going through the objections of the re-

spondent made an award on October 29, 1981 whereby he or-

dered that the re-arrangement of the work should not be at

the risk and cost of the appellant. As regards claim No. 2,

he ordered 30% increase in rates (as per original and sup-

plemental agreement) for all items of work carried out by

the appellant except on items covered by Award No. 132 of

1980 dated 22.1.1981. Claim Nos. 3 and 5 were rejected. As

regards claim No. 4 an increase of 20 per cent in the agreed

rates for these items was allowed. Claim No. 11 regarding

interest was disallowed. It was also stated in the award

inter alia that the claimant shall be entitled to the refund

of the security amount as well as refund of the retention

amounts, the claimant shall be entitled to his final bill in

terms of the Award, the counter claim for recovery of costs

of rearrangement of work and also the counter claims filed

by the respondent dated April 8, 1981 were declined. The

appellant filed O.P. (Arb) No. 296 of 1981 for making the

second award a rule of the court. A statement of defence was

filed by the respondents wherein,it has been stated inter

alia in para 6 that:

"The claims made in this petition under paras

6(ii), (iii), (iv), (v), (vi) (vii) and (viii)

are barred by resjudicata and constructive

resjudicata. No work was done by the claimant

after termination of the contract on June 24,

1980.

403

The claim petition in Arbitration case No.

132/80 was filed by the claimant before the

Hon'ble Arbitrator on 2.7.1980. It was open to

him to raise these claims-in that Arbitration

petition. Having not done-this raising of

these claims now which are all bogus and

imaginary is barred by constructive resjudica-

ta. He had not raised these claims before

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 9

Chief Engineer (next Superior Authority) and

also before the Hon'ble Arbitrator in his

petition dated 27.10.1980. Hence it is prayed

that the above claims may not be taken up for

arbitration and they may be rejected."

It has also been stated in sub-para (iv) of

para 6 that:

"(iv) As above. Also there had been no error

in the rates. The claimant was paid at his

agreed rates, and he had received it and also

no dispute lies on it. Claim may be rejected.

Work done was recorded as per item No. 7 of

Appl. of agreement and was paid as per agree-

ment."

The Sub-Judge by order dated March 18, 1982 made the

award a rule of the court dismissing the plea of res-judica-

ta raised by the respondents in O.P. (Arb.) No. 296 of 1981.

The respondents filed two appeals being FMA Nos. 291 of 304

of 1982 before the High Court of Kerala at Ernakulam which

held that the Arbitrator could not review its order on the

facts of the present case and so allowed F.M.A. No. 291 and

1982. The High Court also allowed F.M.A. No. 304 of 1982

holding that principles of constructive res-judicata would

apply to the arbitration case. Feeling aggrieved by the

aforesaid judgment and order passed in F.M.A. Nos. 291 and

304 of 1982, the appellant-contractor has preferred the

instant appeals on special leave.

Mr. Bhatt, learned counsel appearing on behalf of the

appellant has submitted in the first place that the High

Court was wrong in reversing the judgment and order of the

trial court without considering the provisions of Section

114 as well as Order 47, Rule 1 of the Code of Civil Proce-

dure in as much as Order 47, Rule 1 clearly provides that

review of an order may be made either on account of some

mistake or enor apparent on the face of the record, or for

any-other sufficient reason. In the instant case, the first

award was set aside by the Trial Court on the ground that

the counter claim filed on behalf of the respondents was not

considered by the Arbitrator and so it remitted the same for

consideration afresh. It has been held by the High Court

that the refusal to consider the counter claims had rendered

the prior

404

award liable to be set aside for mis-conduct of the Arbitra-

tor and the proceedings. It has been urged by the learned

counsel that the counter claim has been fully considered in

the second award made by the Arbitrator and as such the

first award cannot be set aside on the ground of non-consid-

eration of a counter claim and it cannot be treated as mis-

conduct of the Arbitrator/and the proceedings for nonconsid-

eration of the counter claim in the first award. It has been

further contended in this connection that the finding of the

High Court to the effect that the subsequent award passed by

the Arbitrator dealing with the counter claims did not have

the effect of mitigating the mis-conduct of the Arbitrator

or of condoning the error on the face of the award, is also

not sustainable in as such as the counter claim filed by the

respondents was duly considered by the Arbitrator in the

second award made by him.

It has also been submitted by the learned counsel for

the appellant that the principles of res-judicata and con-

structive res-judicata are not applicable to the award made

in Arbitration case No. 291 of 1981 in as much as the dis-

putes that were raised were not ripe for being referred to

Arbitration in view of the terms of the contract that the

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 9

contractor had to raise the dispute before the Superintend-

ing Engineer and thereafter before the Chief Engineer and

had to wait till the end of the stipulated period. It has

been further submitted that since the period was not over,

the claims that have been raised subsequently in the second

claim petition before the Arbitrator could not be raised in

the first claim petition before the Arbitrator and as such

the second award made by the arbitrator cannot be said to

have been barred by res-judicata as provided in Section 11

of the Code of Civil Procedure or by the rules of construc-

tive res-judicata. The judgment and order of the High Court

in allowing F.M.A. No. 304 of 1982 setting aside the award

made in Arbitration case No. 296 of 1981 is unwarranted and

as such it is not sustainable. It has also been contended

that the claim made in the second claim petition before the

Arbitrator is not barred by order 2, rule 2 of the Code of

Civil Procedure in as much as the disputes raised in the

second claim petition before the Arbitrator were not ripe

for reference as the appellant had to wait till the end of

the stipulated period in accordance with the terms of the

contract. The judgment and order of the High Court in allow-

ing the F.M.A. No. 304 of 1982 is not legal and valid and is

liable to be set aside.

Mr. Abdul Khadir, learned counsel appearing on behalf of

the respondents on the other hand urged before this Court

that the SubJudge acted legally in directing the Arbitrator

to dispose of the arbitra-

405

tion case No. 132/80 in the light of the judgment of the

Sub-Court in O.P. (Arb.) No. 81 of 1981 and in setting aside

the order of review because no case for review nor any

sufficient cause has been made out for exercising the power

of review under Section 114 read with Order 47, Rule 1 of

the Code of Civil Procedure. The High Court, it has been

submitted, was right in holding that the order of review was

unwarranted and in setting aside the same and directing the

Arbitrator to dispose of the reference in accordance with

law considering the claim of the contractor-appellant and

the counter claim of the respondents. It has been further

submitted by Mr. Abdul Khadir that in view of the provisions

of Section 41 of the Arbitration Act which specifically

provides that the provisions of the Code of Civil Procedure

shall apply to arbitration proceedings, the principles of

res-judicata or of constructive res-judicata will apply to

arbitration proceeding. The appellantcontractor having not

raised all his claims in his first claim petition made to

the Arbitrator for decision and award having been made

thereon, the second claim petition before the Arbitrator

making certain other claims in Arbitration Case No. 276 of

1980 is barred by the principles of constructive res-judica-

ta in as much as on the termination of the contract by order

dated April 26, 1980 the contractor could have raised all

his disputes arising out of the contract at that time, but

the appellant chose to take only some of the issues arising

from the said breach of contract before the Arbitrator. The

second claim petition raising some issues before the Arbi-

trator is therefore, hit by the principles of constructive

res-judicata and the High Court rightly allowed the appeal

setting aside the award made in Arbitration Case No. 276 of

1980. It has also been submitted that the provisions of

Order 2, Rule 2 of the Code of Civil Procedure apply to the

arbitration case and the appellant having not sought refer-

ence of all the issues, he should be deemed to have surren-

dered those issues and he is debarred from raising those

issues in a subsequent claim petition made before the Arbi-

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 9

traror. In this connection, he has cited the ruling in

Muhammad Hafiz and Anr. v. Mirza Muhammad Zakaria and Ors.,

AIR 1922 (PC) 23. The learned counsel drew our attention to

para 2(i) of the objections filed by the respondents in

Arbitration Case No. 132 of 1980 wherein it has been stated

that:

" ........ As per agreement the rates once

agreed will not be enhanced. The department is

not bound to pay the claimant a revision of

schedule."

It has been further submitted by the learned counsel on

behalf of the respondents that the appellant was not enti-

tled to an increase in

406

the rates as he claimed increase with the agreement and the

claim that has been made is untenable.

It has been lastly submitted on behalf of the respond-

ents that the Arbitrator has mis-conducted himself and the

proceedings by not deciding the counter claim filed by the

Government while considering the claim filed by the appel-

lant and making a award. The High Court has rightly held

that the Arbitrator mis-conducted himself and the proceed-

ings and allowed the appeal, setting aside the second award

made by the Arbitrator in Arbitration Case No. 276 of 1980.

The first question that falls for consideration in this

case is whether the finding of the High Court setting aside

the order of review made in I.A. No. 3780 of 1981 and set-

ting arise the order made in O.P. (Arb.) No. 81 of 1981

dated August 18, 1981 whereby the case was remanded to the

Arbitrator is sustainable or not. Admittedly, the appellant

filed a claim petition being Arbitration Case No. 132 of

1980 making certain claims before the Arbitrator. The re-

spondents filed the counter claims. The Arbitrator without

considering the counter claims kept the counter claims for

subsequent consideration and made an award. The Trial Court

set aside the award and remitted the same to the Arbitrator

for making a fresh award considering the claims and

counter-claims filed by the parties. On an application for

review, the Trial Court set aside the order and passed a

decree in terms of the award. It is not disputed that the

Arbitrator did not at all consider the counter claims and

kept the same for consideration subsequently while making

award in respect of the claims filed by the appellant.

Undoubtedly, this award made by the Arbitrator is not sus-

tainable in law and the Arbitrator has mis-conducted himself

and in the proceedings by making such an award. It is the

duty of the Arbitrator while considering the claims of the

appellant to consider also the counter claims made on behalf

of the respondents and to make the award after considering

both the claims and counter claims. This has not been done

and the Arbitrator did not at all consider the counter

claims of the respondents in making the award. As such the

first award dated January 22, 1981 made by the Arbitrator in

Arbitration Case No. 132 of 1980 is wholly illegal and

unwarranted and the High Court was right in holding that the

Arbitrator mis-conducted himself and the proceedings in

making such an award and in setting aside the same and

directing the Arbitrator to dispose of the reference in

accordance with law considering the claim of the contractor

and the counter claim of the respondents. The order allowing

the application for review by the Trial Court is also bad in

as much as there was no mistake or error

407

apparent on the face of the order dated August 18, 1981 made

in O.P. .(Arb.) No. 81 of 1981 nor any sufficient reason has

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 8 of 9

been made out for review of the said order. The order dated

August 18, 1981 is legal and valid order and the order dated

March 18, 1982 allowing the, application for review being

I.A. No. 3780 of 1981 and setting aside the order in O.P.

(Arb.) 81 of 1981 dated August 18, 1981 is, therefore, bad

and unsustainable.

With regard to the submission that the issues that have

been raised in the second claim petition before the Arbitra-

tor is barred under the provisions of Order 2, Rule 2 of the

Code of Civil Procedure, it is convenient to refer to a

passage in Mulla's Code of Civil Procedure (Volume II,

Fourteenth Edition) at page 894:

" .... This rule does not require that when

several causes of action arise from one trans-

action, the plaintiff should sue for all of

them in one suit. What the rule lays down is

that where there is one entire cause of ac-

tion, the plaintiff cannot split the cause of

action into parts so as to bring separate

suits in respect of those parts."

It is pertinent to refer in this connection to the

decision in Muhammad Hafiz and Anr. v. Mirza Muhammad Zaka-

riya and Ors., AIR 1922 (PC) 23 wherein a mortgage deed

provided that if the interest was not paid for six months

the creditor should be competent to realise either the

unpaid amount of the interest due to him or the amount of

principal and interest, by bringing a suit in court without

waiting for the expiration of the time fixed, and the Plain-

tiff, more than 3 years after (i.e. time fixed), brought a

suit for interest alone and got a decree. It was held that

the second suit for principal and arrears of interest was

not maintainable as under Order 2, Rule 2, C.P.C. he must be

deemed to have relinquished his claim for further relief, he

having exercised the option of suing for interest alone. It

was further held that the cause of action referred to in the

rule is the case of action which gives occasion to, and

forms the foundation of, the suit, and if that cause enables

a man to seek for larger and wider relief than that to which

he limits his claim, he cannot afterwards seek to recover

the balance by independent proceedings.

In the instant case, the contract was terminated by the

respondents on April 26, 1980 and as such all the issues

arised out of the termination of the contract and they could

have been raised in the first claim petition filed before

the Arbitrator by the appellant. This having

408

not been done the second claim petition before the Arbitra-

tor raising the remaining disputes is clearly barred.

With regard to the submission as to the applicability of

the principles of res-judicata as provided in Section 11 of

the Code of Civil Procedure to arbitration case, it is to be

noted that Section 41. of the Arbitration case provides that

the provisions of the Code of Civil Procedure will apply to

the Arbitration proceedings. The provisions of res-judicata

are based on the principles that there shall be no multi-

plicity of proceedings and there shall be finality of pro-

ceedings. This is applicable to the arbitration proceedings

as well. It is convenient to refer to the decision in Daryao

and Ors. v. The State of U.P. & Ors., [1962] 1 SCR 574 at

582-83 wherein it has been held that the principles of res-

judicata will apply even to proceedings under Article 32 and

226 of the Constitution of India. It has been observed that:

"Now, the rule of res-judicata as indicated in

s. 11 of the Code of Civil Procedure has no

doubt some technical aspects, for instance the

http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 9 of 9

rule of constructive res-judicata may be said

to be technical; but the basis on which the

said rule rests is rounded on considerations

of public policy. It is in the interest of the

public at large that a finality should attach

to the binding decisions pronounced by Courts

of competent jurisdiction, and it is also in

the public interest that individuals should

not be vexed twice over with the same kind of

litigation. If these two principles form the

foundation of the general rule of res-judicata

they cannot be treated as irrelevant or inad-

missible even in dealing with fundamental

rights in petitions filed under Art. 32."

In Satish Kumar and Ors. v. Surinder Kumar

and Ors,, AIR 1970 (SC) 833 it has been ob-

served that:

"The true legal position in regard to the

effect of an award is not in dispute. It is

well settled that as a general rule, all

claims which are the subject-matter of a

reference to arbitration merge in the award

which is pronounced in the proceedings before

the arbitrator and that after an award has

been pronounced, the rights and liabilities of

the parties in respect of the said claims can

be determined only on the basis of the said

award. After an award is pronounced, no action

can be started on the original claim which had

been the subject-matter of the

reference ........... This con-

409

clusion, according to the learned Judge, is

based upon the elementary principle that, as

between the parties and their privies, an

award is entitled to that respect which is due

to judgment of a court of last resort. There-

fore, if the award which has been pronounced

between the parties has in fact, or can, in

law, be deemed to have dealt with the present

dispute, the second reference would be incom-

petent. This position also has not been and

cannot be seriously disputed."

Considering the above observations of this Court in the

aforesaid cases we hold that the principle of res judicata

or for that the principles of constructive res judicata

apply to arbitration proceedings and as such the award made

in the second arbitration proceeding being Arbitration Case

No. 276 of 1980 cannot be sustained and is therefore, set

aside. The High Court has rightly allowed the F.M.A. No.304

of 1982 holding that the appellant-contractor was precluded

from seeking-the second reference. No other points have

raised before us by the appellant.

In the premises aforesaid, we dismiss these appeals with

costs quantified at Rs.5,000 and affirm the judgment and

order dated April 10, 1987 made by the High Court.

Y. Lal Appeals dismissed.

410

Reference cases

Description

Legal Notes

Add a Note....

Advance Search Tool

💡 How to Get the Best Legal Answers:

1. Keep it simple: Frame your question in plain language.

2. Add scope: Tag @ a court, judge, year, or act section for accurate results.

3. Attach files: Upload a PDF only if you are using a private document.

🌍 Ask in your language: English • Hindi • Assamese • Bangla • Gujarati • Kannada • Malayalam • Marathi • Odia • Punjabi • Tamil • Telugu • Urdu


💡 New Advocate? Don’t worry! Working without senior support today? Turn on Client Advisory to get instant legal strategies, practical angles, and precedent-backed options for your client.

Add research context Type to filter