As per case facts, Madhya Bharat Power Corporation Limited challenged an arbitration award in favor of Voith Hydro Private Limited. The dispute arose from contracts for electro-mechanical works where Voith ...
O.M.P. (COMM) 452/2019 Page 1 of 30
* IN THE HIGH COURT OF DELHI AT NEW DELHI
% Judgment Reserved on: 9
th
March, 2026
Judgment pronounced on: 26
th
May, 2026
+ O.M.P. (COMM) 452/2019 & I.A. 14761/2019
MADHYA BHARAT POWER
CORPORATION LIMITED .....Petitioner
Through: Mr. Ratan K. Singh, Senior Advocate
with Mr. Prateek Khandelwal and Mr.
Anand Murthi Rao, Advocates. Mr. M.
Rajshekhar, DGM (Legal).
Versus
VOITH HYDRO PRIVATE LIMITED .....Respondent
Through: Mr. Raj Shekhar Rao, Senior
Advocate with Mr. Omar Ahmad, Mr.
Vikram Shah, Ms. Simarjeet and Mr.
Ritik Kumar Rath, Advocates
CORAM:
HON’BLE MR. JUSTICE AMIT BANSAL
JUDGMENT
AMIT BANSAL, J.
1.The present petition has been filed under Section 34 of the Arbitration
and Conciliation Act, 1996 (‘Act’) seeking setting aside of the Award dated
31
st
July, 2019 passed by the Arbitral Tribunal (‘Award’).
2.The petitioner (respondent in the arbitration proceedings) shall
hereinafter be referred to as ‘Madhya Bharat’ or ‘the Employer’ and the
respondent (claimant in the arbitration proceedings) shall hereinafter be
referred to as ‘Voith Hydro’or ‘the Contractor’.
O.M.P. (COMM) 452/2019 Page 2 of 30
FACTUALBACKGROUND
3.Brief facts relevant for the adjudication of present dispute are as
follows.
4.Madhya Bharat entered into a Memorandum of Understanding with the
Government of Sikkim by which Rongnichu Hydro Project (‘RHEP’) in
Sikkim was allotted to Madhya Bharat.
5.Madhya Bharat had split RHEP into five different packages, one of
which was for Electro Mechanical Works (‘E&M’). Tender was floated by
Madhya Bharat for E&M in respect of which Voith Hydro submitted its bid.
A Letter of Intent was issued to Voith Hydro on 21
st
June, 2011. Thereafter,
Voith Hydro was awarded the Contract for Electro Mechanical works for the
96 MGW Rongnichu Hydro Project in the State of Sikkim.
6.On 28
th
September, 2011, Madhya Bharat and Voith Hydro entered into
two Contracts:
(a)Supply Contract for sale of electro-mechanical equipment for the
project; and
(b)Services Contract for port clearance, transportation, unloading,
storage and erection among other things.
7.The timeline agreed by the parties for the completion of the Contract
was a period thirty (30) months from the effective date of Contract. However,
within a week of signing of the Contracts, the parties amended the Contract
and revised the time of completion from thirty (30) months to forty-two (42)
months from the effective date of the Contract.
8.On 27
th
November, 2013, Voith Hydro issued a notice of suspension to
Madhya Bharat. Subsequently on 11
th
December, 2013, Voith Hydro
O.M.P. (COMM) 452/2019 Page 3 of 30
suspended the Contract in terms of Clause 41.2(b) of the General Conditions
of Contract (‘GCC’). Madhya Bharat also formally suspended the Contract on
13
th
June, 2014.
9.On 5
th
May, 2016, Voith Hydro issued a notice for settlement of dispute
under Clause 6 of the GCC, which did not materialise.Thereafter,Voith Hydro
nominated an Adjudicator for resolution of disputes, in terms of Clause 6.1 of
the GCC, however, the Adjudicator later on conveyed his unwillingness to
adjudicate the dispute.
10.Accordingly, Voith Hydro issued a notice dated 9
th
March, 2017
invoking the arbitration clause. Both the parties appointed their respective
Nominee Arbitrators who mutually appointed the Presiding Arbitrator.
OVERVIEW OF THEPROCEEDINGS BEFORE THE ARBITRALTRIBUNAL
11.Voith Hydro made the following claims in the Statement of Claim filed
before the Arbitral Tribunal on 19
th
July, 2017:
(a)Claim I: Compensation for engineering works completed
(b)Claim II: Compensation for materials manufactured
(c)Claim III: Compensation for on-site expenses
(d)Claim IV: Compensation for off-site expenses and loss of profits
(e)Claim V: Miscellaneous expenses
(f)Pre-award interest at 15% per annum; post award interest at 18% per
annum
(g)Costs
12.Statement of Defence along with Counter Claim was filed on behalf of
Madhya Bharat on 25
th
September, 2017. Counter Claims raised on behalf of
Madhya Bharat were as under:
O.M.P. (COMM) 452/2019 Page 4 of 30
(a)Return of advance amount of ₹8,18,31,444/- for Supply Contract and
₹1,29,53,966 for Service Contract.
(b)Damages on account of losses suffered (not quantified).
(c)Interest at 8% per annum from 11
th
December, 2013.
(d)Costs
13.Voith Hydro provided testimonies of four fact witnesses and one Expert
witness, Mr. Nigel Grout. For Madhya Bharat, there were three fact witnesses
and one Expert witness, Mr. John Prudhoe.
14.The Arbitral Tribunal observed that the determination of quantum
involved minute and technical scrutiny of engineering and manufacturing
aspects requiring specialised expertise, and therefore relied substantially on
the findings of the Experts in this regard. Both the appointed Experts filed
two individual reports each. After cross examination, both the Experts
prepared a Joint Expert Report on 25
th
September, 2018. In their Joint Expert
Report, the two Experts identified areas of agreement and disagreement, along
with their respective reasoning.
15.Relevant portions of the Award are set out below for ease of reference:
“147. In general, the Experts have agreed as to the approach to valuation
before and after suspension / termination. They agreed that for the period
prior to suspension / termination on 11.12.2013 (the Execution Phase), the
quantum should be a valuation of work done based on the prices in the
Contracts plus any applicable Price Adjustment. From 12.12.2013 (the
Suspension Phase), the quantum should use actual additional costs
incurred. As quantum Experts, they have disclosed their own conclusions as
to the quantum of various claims made by the Claimant and they have also
attempted to give reasons in support of their respective stand on certain
claims and / or related issues on which they have differed from each other.
148. We find no good reasons not to accept their Joint Report on the claims
/ issues on which they are in agreement. Their agreed views are fit to be
O.M.P. (COMM) 452/2019 Page 5 of 30
accepted, although some reservation has been expressed even against such
agreed views, on behalf of the Respondent. The areas where both the Experts
have differed from each other will have to be carefully examined before
deciding which view is more acceptable on the touchstone of reasons”
16.Ultimately, a unanimous Award was passed by the Arbitral Tribunal
awarding the following amounts in respect of each of the claims:
HEADS OF CLAIM INR USD EUR
Compensation for
Engineering Completed
2,57,13,2671,08,84042,249
Compensation for Material
Manufactured
6,32,09,933
Compensation for On-site
Expenses
91,71,305
Compensation for Off-site
expenses (Project manager)
51,32,518
Compensation for Off-site
overheads and Loss of
Profit on unexecuted
Contract works
8,19,42,1963,81,4211,48,057
Compensation for
Miscellaneous Expenses
NIL NIL NIL
LESS: Amount already paid
9,47,85,4104,08,8521,58,706
TOTAL 9,03,83,809.0081,409.0031,600.00
17.Counter claims made by Madhya Bharat were rejected by the Arbitral
Tribunal.
O.M.P. (COMM) 452/2019 Page 6 of 30
18.The operative directions in paragraph 277 of the Award are set out
below:
“277. The final Award is as follows:
I.The Claimant’s claim is allowed to the extent of INR 9,03,83,809.00, USD
81,409.00 and EURO 31,600.00 (after adjusting the payment already made). The
foreign currency amount will have to be paid in INR at the foreign exchange rate
prevalent on the date of the Award.
II. The Claimant is entitled to pendente-lite interest @ 8% per annum from
09.03.2017. On the foreign currency award, the interest rate would be 3% per
annum from the same date.
III. The Claimant is entitled to costs being 50% fees and expenses of the Tribunal
that had been borne by the Claimant towards its share. Towards the legal
expenses of the Solicitors, Counsel and Expert etc., the parties shall bear their
own costs.
IV. The amount to be paid to the Claimant under this award along with
interest as aforesaid should be paid to the Claimant within a period of three
months failing which the awarded amount will carry interest @ 12% per annum
from the date of the Award until the date of payment.
V. The Respondent is directed to return the papers of the bank guarantees
to the Claimant forthwith.
VI. The Counterclaim by the Respondent is rejected.”
19.Aggrieved by the Award passed by the Arbitral Tribunal, the present
petition has been filed by Madhya Bharat seeking setting aside of the
impugned Award.
20.In the order passed by this Court on 22
nd
October, 2019, it was noted
that a sum of ₹9 crores is lying with Voith Hydro. Accordingly, subject to
Madhya Bharat depositing an amount of ₹1.5 crores, the enforcement of the
impugned Award was stayed.
O.M.P. (COMM) 452/2019 Page 7 of 30
SUBMISSIONS ON BEHALF OF MADHYABHARAT
21.Mr. Ratan K. Singh, senior counsel appearing on behalf of Madhya
Bharat has made the following submissions in support of the present petition.
22.CLAIMI-COMPENSATION IN RESPECT OF ENGINEERINGPRICE FOR
THE WORKS COMPLETED
i.The Arbitral Tribunal awarded excessive value for the engineering
component for the Supply Contract. Voith Hydro claimed 6% of the
Contract value towards engineering component. It was the case of
Madhya Bharat that the actual cost could not exceed 1%, and its
Expert opined that it should not exceed 4%. The Arbitral Tribunal
nevertheless accepted 6% based on the report of the Expert of Voith
Hydro.
ii.The research paper relied upon by the Voith Hydro’s Expert states
that Engineering, Procurement and Construction management
together constitute 7%. As 4% has already been awarded towards
procurement, the balance 3% would cover engineering and
construction management. The award of 6% towards engineering is
contrary to the evidence and the material relied upon.
iii.The engineering cost forms part of the materials manufactured costs
awarded under Claim II, based on purchase orders placed by Voith
Hydro on its sub-suppliers. TheAward results in overlap and double
recovery.
23.CLAIMII–COMPENSATION FOR MATERIALSMANUFACTURED
i.Voith Hydro initially claimed that the turbine housing was ready and
available but later admitted that it had been diverted. Despite this,
O.M.P. (COMM) 452/2019 Page 8 of 30
the Arbitral Tribunal awarded ₹89,19,752/- towards its
manufacturing cost and also granted storage charges, relying on
category-wise values in the Joint Expert Report. Having declined
relief for other diverted items, the award of manufacturing and
storage costs for a diverted turbine housing is contradictory and
unsustainable.
ii.The Arbitral Tribunal awarded ₹1,67,37,958/- towards five items
(Inspection Platform, Generator Coolers, Dovetail Bars, Generator
Shafts and Stator Frames), which were admitted to be available with
Voith Hydro. However, no direction was issued for their delivery to
Madhya Bharat. The award of manufacturing cost without directing
delivery is unsustainable.
iii. A sum of ₹2,21,35,101/- was awarded, including ₹69,41,313/-
(cable system) and ₹20,48,071/- (distributor pipes), though these
were only partially complete (85% and 15%). No delivery was
directed. Further, the letter dated 22
nd
February, 2019 sent by Voith
Hydro did not confirm their availability. The award of cost without
proof of completion or direction for delivery is untenable.
24.CLAIMIII–COMPENSATION FOR ON-SITE EXPENSES
The amounts awarded by the Arbitral Tribunal under this claim were
based on ERP extracts which are unreliable in nature, in absence of
evidence of the person who printed the ERP extract.
25.CLAIMIV–COMPENSATION FOR OFF-SITE EXPENSES AND LOSS OF
PROFITS
i.Loss of profit was awarded without any proof. TheArbitral Tribunal
accepted non-disclosure on grounds of confidentiality, though a
O.M.P. (COMM) 452/2019 Page 9 of 30
claimant must substantiate actual loss. Even the Society of
Construction Law Delay and Disruption Protocol, 2017 recognises
that confidentiality may have to be sacrificed to prove such claims.
Loss of profit on unexecuted work cannot be granted in absence of
proof.
ii.Voith Hydro had earlier set up a case of suspension of the Contract.
It was only in rejoinder, that Voith Hydro changed its case to that of
termination. Therefore, theArbitral tribunal could not have awarded
loss of profits on the premise that the Contract stood terminated.
26.INTEREST
i.The Arbitral Tribunal has awarded post-award interest at a higher
rate of 12% per annum without furnishing any reasons for the same.
27.COSTS
i.The Arbitral Tribunal awarded the entire costs of arbitration to
Voith Hydro solely on the basis that it partly succeeded and that
Madhya Bharat’s counterclaims were rejected. Costs must be
awarded on a reasoned consideration of conduct and circumstances;
partial success alone does not justify grant of entire costs.
SUBMISSIONS ON BEHALF OF VOITHHYDRO
28.Mr. Rajshekhar Rao, senior counsel appearing on behalf of Voith
Hydro, counters the aforesaid submissions by submitting as under:
29.CLAIMI-COMPENSATION IN RESPECT OF ENGINEERINGPRICE FOR
THE WORKS COMPLETED
i.Contention of Madhya Bharat that the Arbitral Tribunal awarded
price of engineering component at 6% by solely relying on the claim
O.M.P. (COMM) 452/2019 Page 10 of 30
by Voith Hydro and its expert report is misconceived. Report
submitted by Experts of both the parties stated that the percentage
of engineering costs ranged from 4% to 6%. The Arbitral Tribunal
assessed the evidence including the Experts’ reports, as well as cross
examination of the said Experts to arrive at the figure of 6%.
ii.Insofar as the objection of Madhya Bharat with regard to the
duplication in awarding engineering costs is concerned, the claim
for engineering costs cannot be clubbed with the costs of materials
manufactured. The cost for manufacturing and engineering was
different under the Contract and therefore there exists no duplication
of costs.
30.CLAIMII–COMPENSATION FOR MATERIALSMANUFACTURED
i.The record demonstrated continuous execution activity including
technical meetings, progress reports, purchase orders, inspection
calls and manufacturing updates which was without objection from
Madhya Bharat. Critical components were ready for inspection, yet
Madhya Bharat neither sought inspection nor delivery, despite being
informed of storage constraints and financial implications.
ii.The plea for delivery of the materials arose belatedly after it
emerged in cross-examination that part of the Contract had been
awarded to a third party. Both Experts had already discounted
storage and recommissioning costs, and directing delivery after
nearly a decade would generate fresh disputes.
O.M.P. (COMM) 452/2019 Page 11 of 30
31.CLAIMIII–COMPENSATION FOR ON-SITE EXPENSES
i.The contention that the Award is contrary to the evidence on record,
as the identity of the person who generated the ERP extracts was not
established, essentially seeks a reappreciation of evidence, which is
impermissible in proceedings under Section 34 of the Act. In any
case, the ERP extracts had been verified by the project team of Voith
Hydro, and the same stood confirmed during the cross-examination
of the witness of Voith Hydro, Mr. Sundararaman.
32.CLAIMIV–COMPENSATION FOR OFF-SITE EXPENSES AND LOSS OF
PROFITS
i.The Arbitral Tribunal awarded loss of profit after a detailed, fact-
specific analysis based on Expert evidence. Two quantum Experts
were appointed, reports and a joint report were exchanged and oral
evidence was led. The quantification was thus grounded in evidence
and not made on a notional or automatic basis.
ii.Reliance placed onMcDermott International Inc.v.Burn
Standard Co. Ltd.
1
(‘McDermott International’)andNTPC
Limited v. Voith Hydro JV,OMP (COMM) 16/2017decided on2
nd
July, 2019(‘NTPC Limited’), to submit that quantification of
damages and choice of methodology fall within the domain of the
Arbitral Tribunal and do not warrant interference.
33.INTEREST
1
(2006) 11 SCC 181.
O.M.P. (COMM) 452/2019 Page 12 of 30
i.The Arbitral Tribunal has awarded interest in accordance with
prevailing commercial rates. A Court exercising jurisdiction under
Section 34 of the Act would ordinarily not interfere with the rate of
interest awarded unless the same is contrary to the terms of the
Contract, or shocks the conscience of the Court.
34.COSTS
i.TheArbitral Tribunal is vested with discretion under Section 31Aof
the Act to determine the allocation of costs. In view of the settled
legal position, the award of costs cannot be assailed in the present
proceedings.
ANALYSIS ANDFINDINGS
35.I have heard counsel for the parties and perused the material on record.
36.The Supreme Court has defined the scope of interference by courts in
a petition challenging an Award passed by theArbitral Tribunal under Section
34 of the Act in a plethora of judgments.
37.InAssociate Buildersv.Delhi Development Authority
2
(‘Associate
Builders’), the Supreme Court made the following observations:
“31.The third juristic principle is that a decision which is perverse or so
irrational that no reasonable person would have arrived at the same is
important and requires some degree of explanation. It is settled law that where:
(i) a finding is based on no evidence; or
(ii) an Arbitral Tribunal takes into account something irrelevant to the decision
which it arrives at; or
(iii) ignores vital evidence in arriving at its decision, such decision would
necessarily be perverse.”
[emphasis supplied]
2
(2015) 3 SCC 49.
O.M.P. (COMM) 452/2019 Page 13 of 30
38.The findings inAssociate Builders(supra) were reaffirmed by the
Supreme Court inSsangyong Engineering and Construction Company
Limitedv.National Highways Authority of India (NHAI)
3
(‘Ssangyong’).
Relevant observations of the Supreme Court inSsangyong(supra) are set out
below:
37. Insofar as domestic awards made in India are concerned, an additional
ground is now available under sub-section (2-A), added by the Amendment Act,
2015, to Section 34.Here, there must be patent illegality appearing on the face
of the award, which refers to such illegality as goes to the root of the matter
but which does not amount to mere erroneous application of the law.In short,
what is not subsumed within “the fundamental policy of Indian law”, namely,
the contravention of a statute not linked to public policy or public interest,
cannot be brought in by the backdoor when it comes to setting aside an award
on the ground of patent illegality.
38. Secondly,it is also made clear that reappreciation of evidence, which is
what an appellate court is permitted to do, cannot be permitted under the
ground of patent illegality appearing on the face of the award.
[emphasis supplied]
39.The Supreme Court has reiterated the same principles recently inOPG
Power Generation Private Limitedv.Enexio Power Cooling Solutions India
Private Limited
4
.
“Scope of interference with an arbitral award
74. The aforesaid judicial precedents make it clear that while exercising power
under Section 34 of the 1996 Act the Court does not sit in appeal over the arbitral
award. Interference with an arbitral award is only on limited grounds as set out
in Section 34 of the 1996 Act.A possible view by the arbitrator on facts is to be
respected as the arbitrator is the ultimate master of the quantity and quality of
evidence to be relied upon. It is only when an arbitral award could be
categorized as perverse, that on an error of fact an arbitral award may be set
aside.Further, a mere erroneous application of the law or wrong appreciation
3
(2019) 15 SCC 131.
4
(2025) 2 SCC 417.
O.M.P. (COMM) 452/2019 Page 14 of 30
of evidence by itself is not a ground to set aside an award as is clear from the
provisions of sub-section (2-A) of Section 34 of the 1996 Act.”
[emphasis supplied]
40.On the aspect of determination of damages, the Supreme Court in
McDermott International(supra), has held that the method to compute
damages and quantum thereof squarely falls within the domain of theArbitral
Tribunal. Paragraphs 109 and 110 from the said judgment are set out below:
“109. Sections 55 and 73 of the Indian Contract Act do not lay down the mode
and manner as to how and in what manner the computation of damages or
compensation has to be made. There is nothing in Indian law to show that any
of the formulae adopted in other countries is prohibited in law or the same would
be inconsistent with the law prevailing in India.
110.As computation depends on circumstances and methods to compute
damages, how the quantum thereof should be determined is a matter which
would fall for the decision of the arbitrator.We, however, see no reason to
interfere with that part of the award in view of the fact that the aforementioned
formula evolved over the years, is accepted internationally and, therefore,
cannot be said to be wholly contrary to the provisions of the Indian law.”
[emphasis supplied]
41.Similarly, the Coordinate Bench of this Court inNTPC Limited(supra),
has held that where the Tribunal has evaluated evidence and materials
produced before it determining the quantum of compensation on the basis of
expert evidence, the Court in exercise of jurisdiction under Section 34 of the
Act cannot re-appreciate evidence. Paragraph 73 is set out below:
“73. This Court finds no infirmity with the aforesaid view, which would warrant
any interference in these proceedings. Apart from the above, it is also seen that
the Tribunal had evaluated the evidence and materials produced before it for
determining the quantum of compensation. It had also relied on the expert
evidence led by the Claimants in this regard.The scope of the present
proceedings does not entail reappreciation of evidence.Suffice it to state that
the impugned award is based on sufficient material and evidence and, therefore,
the same cannot be interfered with in these proceedings.”
[emphasis supplied]
42.The appeal against the aforesaid judgment has been dismissed by the
O.M.P. (COMM) 452/2019 Page 15 of 30
Division Bench and subsequently, the Special Leave Petition has also been
dismissed by the Supreme Court.
43.With this background, I shall now proceed to apply the aforesaid
principles in the facts and circumstances of the present case to deal with the
objections raised in each of the claims.
CLAIMI-COMPENSATION FOR ENGINEERINGWORKSCOMPLETED
44.Under this Claim, Voith Hydro sought compensation for (i) executed
engineering, (ii) cost of unused engineering workforce during suspension of
the project, along with price adjustment.
45.The amounts claimed by Voith Hydro and amounts awarded by the
Arbitral Tribunal under Claim I are tabulated below:
INR USD EUR
Amounts Claimed 3,11,82,3391,08,921 42281
Amounts Awarded 2,57,13,2671,08,840 42249
46.It was an admitted position that the Contract in the present case did not
provide any cost break-up for the engineering component. Voith Hydro sought
remuneration for the engineering works executed till November, 2013 by
claiming the engineering component to be 6% of the total Supply Contract
value, based on the opinion of its Expert, Mr. Nigel Grout.
47.Per Contra, the Expert of Madhya Bharat, Mr. John Prudhoe, opined
that engineering component should not be more than 4% of the total value of
the Contract.
48.TheArbitral Tribunal accepted the value of 6% given on behalf of Voith
Hydro and on that basis, awarded amounts in favour of Voith Hydro.
O.M.P. (COMM) 452/2019 Page 16 of 30
49.On behalf of Madhya Bharat, it is contended that the Arbitral Tribunal
has wrongly accepted the engineering component at 6% of the Contract value.
50.In paragraph 1.30 of the Report given by the Expert of Voith Hydro,
Mr. Nigel Grout, on 25
th
February, 2018, he has opined that after deduction of
procurement and management charges of 3-4%, the engineering element
would be to the tune of 6% of the total value of the Contract. Mr. Nigel Grout
has placed reliance on three research papers to come to conclusion that 6%
would be reasonable consideration of the engineering component. Mr. Nigel
Grout was cross-examined by counsel for Madhya Bharat and in the cross-
examination, he has maintained his stand that the engineering component
should be at 6% of the total Contract value.
51.Mr. Ratan Singh, Senior Counsel appearing for Madhya Bharat has
drawn attention of the Court to questions 92 to 94 of the cross examination of
Mr. Nigel Grout and the responses thereto. For the sake of convenience, the
said questions from the cross-examination are set out below:
“Q.92. What is the percentage of your total assessment for engineering,
procurement and construction management?
Ans.I have made an assessment of 6% for the engineering. I will have to check
about procurement and construction management.
Q.93Is it correct that in the Joint Report you have assessed 15% for
procurement alone (Sl. No. 13 of Joint Report)?
Ans.15% you are referring to is taken from the price variation formula in the
Contract and is not an assessment by me. That 15% has been merely used for the
calculation of materials manufactured.
Q.94Therefore this is still an assessment by you for procurement, isn’t it?
Ans.No. 15% that you have referred to is purely a percentage shown in cost
adjustment formula. The assessment I have made with relation to the engineering
percentage has already been deducted for procurement and construction
management. Even after these deductions, the engineering percentage from the
studies shows engineering percentage in the region of 6%. The procurement and
O.M.P. (COMM) 452/2019 Page 17 of 30
management percentage deductions amount to 3% to 4% in the studies that have
been referred to.”
52.A perusal of the aforesaid cross-examination makes it abundantly clear
that in the opinion of Mr. Nigel Grout, the Expert of Voith Hydro, the
assessment of 6% is in respect of the engineering costs, excluding
procurement and construction management.
53.In this regard, the finding of the Arbitral Tribunal given in paragraphs
182 and 183 are set out below:
182. The reason for disagreement by the Respondent’s expert is “in the absence
of disclosed documents to show what the actual engineering component is in the
Supply Contract Price, JP believes the percentage is less than 6% particularly
of the engineering on the Rongnichu project is similar to other projects of the
Claimant which would reduce the engineering man hours”. When both parties
that the contract did not contain a separate break up for engineering, then it is
a matter of estimation. There is no admission by the Claimant that its tender
breakup would have contained the engineering component separately. When it
is not separately identified in the contract, then it is also reasonable to assume
that it would not have been part of the tender break up. The Claimant’s argument
that engineering is recoverable as part of the price and not separately provided
is also not questioned by the Respondent. While the Respondent accepts 4% but
does not agree to 6% also on the ground that the present project is similar to the
other projects of the Claimant and thus due to overlap of engineering work, the
percentage is lesser. This argument is attractive, but cannot be accepted.There
is no admission by the Claimant that the other projects are similar to the
present project and there is also evidence lead to that effect. All Hydro Power
projects are unique and are governed by specificities like water levels (head),
water flow conditions including seasonal variations etc., water conditions e.g.
silt/impurities contents etc., topographical, geological, hydrological conditions
as well as operational regime of the power plant e.g. base load or peak load
operations, specific site conditions e.g. cavern type or surface type etc. Thus,
equipment requires tailor made engineering to the specific requirements.
183. Even if there is some overlap of Engineering work between its project and
other works, the fact also is that the hydropower projects are very topographic
specific.The overall engineering of a hydropower project would have to be
done keeping in mind the specific topography, the need and the size of the
project.It cannot be assumed that the overlap would be to the extent that it
O.M.P. (COMM) 452/2019 Page 18 of 30
would reduce the engineering percentage from 6 to 4%.Therefore, the
Tribunal accepts the Engineering percentage at 6%.On this basis and on the
admitted percentage completed of 47.04%, the Tribunalholds the engineering
value of work completed to beINR 18,476,885/-, USD 92,316 & EUR 35,834
towards claim for completed engineering in the following manner:
Supply Contract
Value (A)
Engg
Component
(in %) (B)
Contract Engg
Value in (%)
(C = A*B)
Engg Work
Completion
(in %) (D)
Value of
Completed
Engg work (E
= D*C)
INR 65,46,51,553.000.06 3,92,79,093.180.47 1,84,76,885.43
USD 32,70,819.00 0.06 1,96,249.14 0.47 92,237.10
EURO 12,69,646.00 0.06 76,178.76 0.47 35,804.02
[emphasis supplied]
54.The Arbitral Tribunal has given a categorical finding that different
hydro power projects are unique and topography specific, therefore, it cannot
be said that there would be an overlap of the engineering works. The Arbitral
Tribunal has also noted that both the Experts in their Joint Expert Report have
accepted that 47.04% of the engineering works had been completed at the
time of suspension of the Contract by Voith Hydro.
55.The Arbitral Tribunal has, after carefully analysing the evidence of the
parties and reports given by both the Experts, concluded that engineering
component would be 6%. The Arbitral Tribunal has given cogent reasons for
agreeing with the report of Voith Hydro’s Expert and disagreeing with
Madhya Bharat’s Expert in the paragraphs set out above.
56.It is a settled position of law that the Arbitral Tribunal is the master of
evidence. This Court in exercise of jurisdiction under Section 34 of the Act
cannot reassess or reappreciate the evidence led before the Arbitral Tribunal.
57.The next objection raised by Madhya Bharat is that the awarded amount
towards engineering component is already covered under Claim II, in respect
of the costs of material manufactured, which is inclusive of the costs of
O.M.P. (COMM) 452/2019 Page 19 of 30
engineering.
58.There is nothing to show from the record that claim for engineering
costs has been clubbed with the claim of costs of materials manufactured.
Therefore, it cannot be said that engineering costs, which are the subject
matter of Claim I, have also been awarded as a part of the costs of materials
manufactured under Claim II.
59.In view of the discussion above, I do not find any infirmity in the
findings of the Arbitral Tribunal in respect of Claim I.
CLAIMII – MATERIALSMANUFACTURED
60.Under this claim, Voith Hydro sought compensation for (i) material
manufactured or partly manufactured, (ii) cost incurred in storage, handling,
preserving and scrapping of such material, along with price adjustment.
61.The amounts claimed by Voith Hydro and amounts awarded by the
Arbitral Tribunal under Claim II are tabulated below:
INR
Amounts Claimed 22,99,98,495
Amounts Awarded 6,32,09,933
62.As per Voith Hydro, the manufacturing of the materials commenced
soon after the effective date of Contract and majority of the material was fully
or partly manufactured in November, 2013,i.e.the date when notice of
suspension was given. Further, the material was customised for the work
package under the Contract and could not be used for another project.
63.Voith Hydro had divided this claim into seven categories depending
upon the stage of manufacturing, as stated below:
O.M.P. (COMM) 452/2019 Page 20 of 30
i.Material Status Category-I: Material completely made ready by the
Voith Hydro’s sub-supplier and available.
ii.Material Status Category-II: Material completely made ready by the
Voith Hydro’s sub-supplier and scrapped.
iii.Material Status Category-III: Material completely made ready by the
Voith Hydro’s sub-supplier and diverted.
iv.Material Status Category-IV: Material partially made by the Voith
Hydro’s sub-supplier and available.
v.Material Status Category-V: Material partially made by the Voith
Hydro’s sub-supplier and scrapped.
vi.Material Status Category-VI: Material partially made by the Voith
Hydro’s sub-supplier and diverted.
vii.Material Status Category-VII: Order placed, engineering done.
Under planning and manufacturing at sub-suppliers.
64.The Arbitral Tribunal undertook a detailed category-wise examination
of seven sub-categories of materials, including fully manufactured, scrapped
and diverted items, and evaluated methodologies submitted by both the
Experts. To adjust the said claim, the Arbitral Tribunal substantially accepted
the Purchase Order method (‘PO Method’) based valuation as recommended
by the Expert of Madhya Bharat and rejected speculative valuation under the
Billing Break-Up method (‘BBU method’) as proposed by the Expert of Voith
Hydro. For the fixed portion for procurement, the Arbitral Tribunal adopted
the rate of 4% as agreed by the Experts of the parties.
65.In paragraph 238 of the Award, the Arbitral Tribunal has summarised
the claim of Voith Hydro, assessment made by the respective Experts and the
O.M.P. (COMM) 452/2019 Page 21 of 30
amounts ultimately awarded by the Arbitral Tribunal under each of the sub-
categories, as set out below:
66.From the table above, it is manifest that the amounts awarded by the
ArbitralTribunal are substantially closer to the assessment made by the Expert
of Madhya Bharat.
67.The challenge in the present petition by Madhya Bharat is confined to
Material Status (‘MS’) Categories I, II and IV.
68.In respect of MS Category I, it is submitted that Arbitral Tribunal has
awarded a sum of ₹89,90,752/- in respect of the cost of manufacturing of
turbine housing along with storage cost, even though the same has been
diverted by Voith Hydro. Insofar as MS Category II is concerned, it is
submitted by Madhya Bharat that five items worth ₹1,67,37,958/- that were
available with Voith Hydro have not been directed to be delivered to Madhya
O.M.P. (COMM) 452/2019 Page 22 of 30
Bharat. Insofar as MS Category IV is concerned, which includes cable system
and distribution pipes, the Tribunal has awarded ₹2,21,35,101. However, the
said items were not directed to be delivered to Madhya Bharat.
69.The aforesaid objections of Madhya Bharat have been duly dealt by the
Arbitral Tribunal in paragraph 239 to 241 of the award which are set out
below:-
“239. In the course of arguments (certainly not raised in pleadings), the
Respondent prayed that if the Tribunal would be compensating the Claimant for
the materials manufactured then those materials should also be directed to given
to the Respondent. In response to this oral argument, the Claimant has submitted
that both the experts have discounted the storage, preservation and
refurbishment costs of the above items and should the Tribunal direct the
Claimant to provide the said materials to the Respondent, then the Respondent
should also be directed to bear the cost for storage, preservation and
refurbishment as well.
240. The Tribunal notices that this is a new and unpleaded case of the
Respondent. The contract is already over and the Respondent did not make any
claim on the Respondent for these goods. A relief not prayed for cannot be
granted. Since there is no pleading, there is also no evidence and it would not be
just to allow such kind of prayer to be made in oral submissions.
241. Even theoretically, liability is on the Claimant to limit its loss and it cannot
be expected to preserve those completed items and incur expenditure in storage,
security etc. If the claim of the Respondent is to be allowed, there may be other
attendant costs like transportation, security. Storage which would result in
further claims and counter claims. For these reasons also, it would not be
possible to consider this prayer of the Respondent raised during oral
submissions and is rejected.”
70.The Arbitral Tribunal has observed that the submission with regard to
delivery of the manufactured materials was made by Madhya Bharat only at
the stage of final arguments. No pleading in this regard was made, nor was
any evidence lead. The Arbitral Tribunal has correctly held that Voith Hydro
could not be expected to preserve the completed engineering items and incur
additional costs towards storage, security, etc.
O.M.P. (COMM) 452/2019 Page 23 of 30
71.The Arbitral Tribunal also notes that the amounts that were awarded in
favour of Voith Hydro were after discounting the storage, preservation and
refurbishment costs and if the aforesaid contention of Madhya Bharat was to
be accepted, Madhya Bharat would have been liable to pay not only the
storage charges but also other attendant costs like transportation and security.
72.Accordingly, I do not find any error in the findings of the Arbitral
Tribunal in respect of Claim II.
CLAIMIII–COMPENSATION FOR ON-SITEEXPENSES
73.Under this claim, Voith Hydro sought compensation towards on-site
expenses, including site man-hours and site running expenses, for both the
pre-suspension and post-suspension period.
74.The amounts claimed by Voith Hydro and amounts awarded by the
Arbitral Tribunal under Claim III are tabulated below:
INR
Amounts Claimed 1,30,57,815
Amounts Awarded 91,71,305
75.The Arbitral Tribunal after analysing the evidence came to the
conclusion that even during the suspension period Voith Hydro was required
to maintain safety infrastructure, project management teams and other
establishment staff thereby incurring actual standby expenses. The Arbitral
Tribunal calculated the cost, based on the report of the experts of the parties.
76.Madhya Bharat submits that the Arbitral Tribunal has wrongly allowed
the aforesaid claim based on ERP extracts when Voith Hydro’s own witness
stated that he did not know the identity of the person who took the printout of
O.M.P. (COMM) 452/2019 Page 24 of 30
ERPextracts.Accordingly, theArbitral Tribunal has awarded on-site expenses
without any proof.
77.The objection raised on behalf of the Madhya Bharat has been
specifically dealt with by the Arbitral Tribunal in paragraph 194 of the Award
which is set out below:
“194. According to the Respondent, the Claimant can be awarded only actual
cost for the hours worked and the hours claimed are also not legally proved in
absence of the evidence of the person who printed the ERP Extract. However, in
view of evidence of Mr. K.A. Sudararaman (CW-3), there appears to be no merit
in the submission that the ERP Extract is not reliable because it is not the direct
output of the software maintaining, the ERP. CW-3 clearly stated that he does
not know who took the printout of the ERP Extract. In view of evidence of CW -
3 and the circumstances, the ERP records appear to be reliable, being the output
of the software used for maintaining the ERP.”
78.In the opinion of this Court, the Tribunal has correctly placed reliance
on ERP records produced by Voith Hydro to determine the claim for site man-
hours and site running expenses pre-suspension and post-suspension of the
Contract. Merely because Voith Hydro’s witness did not know the name of the
person who took the printout of ERP extract cannot be the basis to disregard
the evidence.
79.In the opinion of this Court, the aforesaid objection of Madhya Bharat
would require this Court to re-appreciate the evidence lead before theArbitral
Tribunal which is impermissible.
80.In view of the discussion above, no fault can be found with the findings
of the Arbitral Tribunal in respect of Claim III.
CLAIMIV-COMPENSATION FOR OFF-SITEEXPENSES ANDLOSS OFPROFIT
81.Under this claim, Voith Hydro sought compensation towards off-site
expenses and loss of profit which includes (i) project manager (‘PM’) man-
O.M.P. (COMM) 452/2019 Page 25 of 30
hours pre-suspension (ii) project manager (‘PM’) man-hours pre-suspension
(iii) license fee (iv) offsite overheads and (v) computation of loss of profits.
The amounts claimed by Voith Hydro under each of the sub categories under
this claim were as follows:
Head INR USD EUR
PM Man-hours (pre-suspension)5,385,600 - -
PM Man-hours (post-suspension)949,575 - -
Compensation for off-site
overheads, license fees and loss of
profit for the unexecuted
value/portion of the Contract
175,696,826932,760362,073
Total 182,032,001932,760362,073
82.The amounts claimed by Voith Hydro and amounts awarded by the
Arbitral Tribunal under Claim IV are tabulated below:
INR USD EUR
Amounts Claimed 18,20,32,001 9,32,760 3,62,073
Amounts Awarded 8,19,42,196 3,81,421 1,48,057
83.Madhya Bharat challenges the finding of the Arbitral Tribunal on the
ground that loss of profit has been awarded without any proof submitted by
Voith Hydro.
84.On the aspect that Voith Hydro has failed to establish that it suffered
losses, the Arbitral Tribunal has returned the finding in paragraph 143, which
is set out below:
“143. In the present case the facts are different, both on pleadings and evidence.
The Claimant has supported its case and the Respondent has not been able to
O.M.P. (COMM) 452/2019 Page 26 of 30
establish that the Claimant has not suffered any loss. Contracts and business
arrangements can be of various types and in all situations, it is not possible to
assess the loss or damage with exact certainty. In such a situation, it is quite
usual to take help of Experts for quantifying the damages / loss as has been done
in the present case.”
85.Another objection taken on behalf of Madhya Bharat is that Voith
Hydro had earlier set up a case of suspension of Contract. It was only in
rejoinder, that Voith Hydro changed its case to that of termination. Therefore,
theArbitral tribunal could not have awarded loss of profits on the premise that
the Contract stood terminated.
86.In this regard, the Arbitral Tribunal observed that it emerged only
during the cross-examination of Madhya Bharat’s witness that the Contract
had been awarded to a third party on 17
th
February, 2017 and 28
th
February,
2017, a fact which was neither disclosed in the pleadings nor in the
examination-in-chief. Noting that the Contract had remained suspended for
over five years without either party seeking specific performance, theArbitral
Tribunal has correctly concluded that the Contract was no longer subsisting.
The findings of the Arbitral Tribunal in this regard, as recorded in paragraphs
105 and 106 of the Award, are set out below:
105.In the course of trial, it emerged in the cross-examination of the
Respondent’s witness Mr. Chhanghani (cross examination on 06.08.2018) that
the Respondent has awarded the work forming part of the Claimant's contract to
a third party on 17.02.2017 and 28.02.2017 (which are prior to the date of filing
of the Statement of Defence, though not disclosed). This aspect was not revealed
either in the pleadings or in the examination in chief of the Respondent's
witnesses and the new contracts were also not brought on record.
106.The Tribunal finds that the contract has remained suspended for more
than 5 years at the time of filing of the present claim, and the Respondent having
already appointed a new contractor, it is obvious that the Respondent does not
intend to continue with the present contract with the Claimant. The appointment
of the third party contractor was done by the Respondent without notice to the
O.M.P. (COMM) 452/2019 Page 27 of 30
Claimant or formally terminating the contract. Neither party has sought specific
performance of the contract. Under such circumstances, it would be reasonable
for this Tribunal to proceed on the basis that the contract is no more surviving
any more for all practical purposes and there is no further performance either
demanded. or expected by either party. Whatever the claims of the Claimant or
the Respondent are would have to be determined on the basis of which party is
in breach of the contractual obligations and the principles of Section 73 of the
Indian Contract Act, 1872. This aspect is being also dealt with while dealing
with the quantum claims of the Claimant.”
87.Yet another objection raised by Madhya Bharat in respect of loss of
profits is that Voith Hydro withheld tender break-ups and cost account
statements by invoking confidentiality, and therefore, the quantum of
damages assessed by the experts was speculative in nature.
88.The Arbitral Tribunal has rejected the objection and observed that the
absence of tender break-ups could not by itself defeat the claim for damages,
particularly in view of the assessment undertaken by quantum experts. The
Arbitral Tribunal observed that such tender documents were internal pre-
contract workings without any standard methodology, and therefore, reliance
on expert analysis based on available material was justified. Relevant
paragraphs 159 and 160 of the Award are set out below:
159. … The Claimant has not submitted the tender breakups or its price breakups
for claiming its losses. Even if we assume that the Claimant would have
submitted it, then it is not that the Respondent would have accepted such tender
breakup and loss computation thereof. While the Claimant is not relying upon its
tender breakup to justify a particular loss claim, the Respondent is seeking to
rely upon its absence to question the Claimant's claim. It is open to the
Respondent to question those bases of the Claimant. Such tender break up, if it
existed, would be a pre-contract internal working of the Claimant. There is no
standard format or methodology of this break up and it may be based on very
broad calculations. Mr. Prudhoe, who has an experience of acting as an expert
in many arbitrations, could cite only one example where a tender was produced
and that too it was a case, the parties did not have any other engagement
ongoing.
O.M.P. (COMM) 452/2019 Page 28 of 30
160. More so, in the present case, both parties have, presented their experts to
deal with the aspect of quantum who have given their views on the different
claims. Since the Claimant is not relying upon the tender break up for its claims,
the Tribunal would be adjudging the Claimant's claim on its own merits and by
examining the correctness of the basis on which those claims have been made by
the Claimant and greater scrutiny with due caution.
89.For determination of the claim on loss of profits, the Arbitral Tribunal
noted that in the Statement of Claim Voith Hydro has claimed 15% of profits
which has been accepted by the Expert of Voith Hydro. On the other hand, the
Expert of Madhya Bharat in his report fixed it at 5% profit. The Arbitral
Tribunal rejected the claim of 15% of profit as claimed by Voith Hydro and
awarded compensation for loss of profits at rate of 6%. Relevant extracts from
the findings of the Arbitral Tribunal are set out below:
“171. … The Tribunal also feels that in project involving competitive bidding, a
profit margin as high as 15% claimed by the Claimant is not possible,
particularly since the Tribunal takes into account the non-filing of tender
breakup by the Claimant to support its claim for profit percentage of 15% and
holds the same against 1t. Moreover, the Hon'ble Supreme Court in case of Barat
Coking Coal (Supra) has rejected the claim for loss of profit @ 15% as
unreasonable. Insofar as the objection that the loss of profit claim cannot be
granted in case of a suspension is also rejected in view of the Tribunal's decision
on the aspect relating to suspension and termination.
172. In this backdrop, the Tribunal rejects the Claim of 15% of Profit setup by
the Claimant and awards profit @6% considering it to be reasonable. Since the
claim under this head is to be calculated on unexecuted value of the Contract,
and therefore the unexecuted value of Contract is to be determined, which would
be determined in the section below”
90.As is manifest from the aforesaid extracts of the Award, the Arbitral
Tribunal has given cogent reason for awarding loss of profits at 6% of the
unexecuted part of the Contract value.
91.With respect to amounts awarded towards off-site overheads, the
O.M.P. (COMM) 452/2019 Page 29 of 30
Arbitral Tribunal analysed the report of the Expert of Voith Hydro, as well as
the Expert of Madhya Bharat. Madhya Bharat’s Expert has assessed 3%
towards off-site overheads, whereas the Expert of Voith Hydro has assessed
the same at 10%. The Arbitral Tribunal has held 6% foroff-site overheadson
the unexecuted portion of the Contract. Paragraph 263 from the Award is set
out below:
“263. Offsite-overheads
Mr. Grout in his report has supported the claim of 10% for off-site overheads.
However, Mr. Prudhoe in his report considered 10% as too high and assessed
the same as 3%. Moreover, the Tribunal feels that 3% overheads assessed by Mr.
Prudhoe is too conservative. In this backdrop, and in absence of any document
to support 10% claim of the Claimant, the Tribunal wishes to adopt middle path
and holds 6% to be a reasonable overhead. The Claimant is entitled to off-site
overheads @6% on the unexecuted portion.”
92.In view of the discussion above, I do not find any perversity or patent
illegality in the findings of the Arbitral Tribunal in respect of Claim IV.
INTEREST
93.Even though Voith Hydro had claimed pre-award interest at the rate of
12% and post-award interest at the rate of 18%, the Arbitral Tribunal has
allowed 8% pre-award interest and 12% post-award interest. It is submitted
on behalf of Madhya Bharat that 12% post-award interest awarded by the
Arbitral Tribunal is at a higher rate without any discussion or finding.
94.It is correctly pointed out on behalf of Voith Hydro that this objection
has not been raised by Madhya Bharat in the petition.
95.In the opinion of this Court, the post-award interest at the rate of 12%
per annum is not excessive and hence, does not require interference under
Section 34 of the Act.
O.M.P. (COMM) 452/2019 Page 30 of 30
COSTS
96.Insofar as the aspect of costs is concerned, theArbitral Tribunal has the
sole discretion to allocate the cost of arbitration process in terms of Section
31A of the Act.
97.In the present case, while the Arbitral Tribunal has directed that the
entire fees and expenses of the Arbitral Tribunal was payable by the Madhya
Bharat. However, insofar as the legal expenses pertaining to lawyers’fees and
fees of the experts, the Arbitral Tribunal has directed that each party would
bear its own expenses.
98.In the opinion of this Court, the aforesaid finding is just and reasonable
and no ground for interference has been made out on behalf of Madhya
Bharat.
CONCLUSION
99.In light of the discussion above, I am of the view that Madhya Bharat
has failed to make out any ground for interference with the impugned Award
under Section 34 of the Act.
100.Accordingly, the petition is dismissed.
AMIT BANSAL
(JUDGE)
MAY 26, 2026
Vivek/-
Legal Notes
Add a Note....