REPORTABLE

IN THE SUPREME COURT OF INDIA

CIVIL APPELLATE JURISDICTION

CIVIL APPEAL NO.684 OF 2021

MAHARASHTRA STATE ELECTRICITY

DISTRIBUTION COMPANY LIMITED ...APPELLANT (S)

VERSUS

ADANI POWER MAHARASHTRA LIMITED

& ORS. ...RESPONDENT (S)

WITH

CIVIL APPEAL NO.6927 OF 2021

INDEX

I. INTRODUCTION…………………………………………….. Paras 1 and 2

II. FACTS IN CIVIL APPEAL NO.684 OF 2021……………. Paras 3 to 29

III. FACTS IN CIVIL APPEAL NO.6927 OF 2021…………. Paras 30 to 3 9

IV. SUBMISSIONS ON BEHALF OF THE DISCOMS

………

Paras 43

V. SUBMISSIONS ON BEHALF OF THE GENERATING

COMPANIES …………………………………………..

………

Paras 44 and 45

V. RELEVANT DOCUMENTS…………………………………. Paras 46 to 83

VI. JUDGMENTS CITED……………………………………….. Paras 84 to 93

VII.STATUTORY PROVISIONS WITH REGARD TO

REGULATORY MECHANISM……………………………….

Paras 94 to 104

VIII. CONSIDERATIONS…………………………………………. Para 105 onwards

1

Digitally signed by

Narendra Prasad

Date: 2023.03.03

12:45:11 IST

Reason:

Signature Not Verified 2023 INSC 208

List of abbreviations:

1. ACQ - Annual Contracted Quantity

2. APML - Adani Power Maharashtra Limited

3. APTEL - Appellate Tribunal for Electricity

4. C&AG - Comptroller and Auditor General of India

5. CCEA - Cabinet Committee on Economic A�airs

6. CERC - Central Electricity Regulatory Commission

7. CIL - Coal India Limited

8. CPP - Captive Power Plants

9. DISCOMS - Distribution Companies

10. FSA - Fuel Supply Agreement

11. GCV - Gross Calori�c Value

12. GMR - GMR Warora Energy Ltd.

13. GMRETL- GMR Energy Trading Limited

14. IPPs - Independent Power Producers

15. LoA - Letter of Assurance

16. MERC - Maharashtra Electricity Regulatory Commission

17. MoC - Ministry of Coal

18. MoP - Ministry of Power

19. MSEDCL - Maharashtra State Electricity Distribution Compan y Limited

20. NCDP - New Coal Distributional Policy

21. PLF - Plant Load Factor

22. PPAs - Power Purchase Agreements

23. PSA - Power Sale Agreement

24. RFP - Request for Proposal

25. SECL - South Eastern Coal Limited

26. SHR - Station Heat Rate

27. TPPs - Thermal Power Stations

28. UHBVNL- Uttar Haryana Bijli Vitran Nigam Limited

29. WCL - Western Coal Limited

J U D G M E N T

2

B.R. GAVAI, J.

INTRODUCTION

1.The questions involved in both these appeals, as in several

other appeals, are common.

2.Three of the issues involved in the present appeals are also

involved in the other appeals which were listed along with these

two appeals. However, the other appeals also involve some

other ancillary and incidental issues. As such, at the request of

the learned counsel for the parties, we have heard the present

appeals. We have also heard the learned counsel appearing in

the other appeals on the three questions which are common.

FACTS IN CIVIL APPEAL NO. 684 OF 2021

3.The facts, in brief, which arise in Civil Appeal No.684 of

2021 are thus:

4.The appellant-Maharashtra State Electricity Distribution

Company Limited (hereinafter referred to as “MSEDCL”) has

entered into a long-term Power Purchase Agreements (“PPAs” for

3

short) with Adani Power Maharashtra Limited (hereinafter

referred to as “APML”). The �rst of the PPAs is dated 8

th

September 2008 for 1320 MW (“1320 MW PPA” for short); the

second one is dated 31

st

March 2010 for 1200 MW (“1200 MW

PPA” for short); the third one is dated 9

th

August 2010 for 125

MW (“125 MW PPA” for short); and the fourth one is dated 16

th

February 2013 for 440 MW (“440 MW PPA” for short). These

PPAs were entered into in pursuance of the competitive bidding

processes conducted by the appellant-MSEDCL under Section

63 of the Electricity Act, 2003 (hereinafter referred to as “the

Electricity Act”) read with the Standard Bidding Guidelines

issued by the Ministry of Power (“MoP” for short).

5.Article 10 of the 1200 MW PPA dated 31

st

March 2010

entered into between the appellant-MSEDCL and respondent

No.1-APML deals with “Change in Law”.

6.Article 10.1.2 de�nes the term “Change in Law”.

7.Article 10.2 deals with the application and principles for

computing the impact of Change in Law. Article 10.2.1 provides

4

that while determining the consequence of a Change in Law

under Article 10, due regard has to be given to the principle,

that to compensate the Party a�ected by such Change in Law is

to restore through monthly Tari� Payment, to the extent

contemplated in Article 10, the a�ected Party to the same

economic position as if such Change in Law has not occurred.

8.Article 10.3 deals with “Relief for Change in Law”. Article

10.3.1 provides relief for Change in Law during the

Construction Period, whereas Article 10.3.2 provides for

compensation to be paid on account of Change in Law during

Operating Period. For claiming relief on account of a Change in

Law, the Party is required to approach the Appropriate

Commission along with documentary proof of such

increase/decrease in the cost of the Power Station or

revenue/expense for establishing the impact of such Change in

Law. Article 10.3.4 provides �nality to the decision of the

Appropriate Commission with regard to compensation

determined under Articles 10.3.1 and 10.3.2.

5

9.On 18

th

October 2007, the Government of India, through

the Ministry of Coal (“MoC” for short), issued the New Coal

Distributional Policy, 2007 (hereinafter referred to as “the

NCDP, 2007”). As per the NCDP 2007, 100% of the quantity as

per the normative requirement of the consumers was to be

considered for the supply of coal, through Fuel Supply

Agreement (“FSA” for short) by Coal India Limited (“CIL” for

short) at �xed prices to be declared/noti�ed by CIL. The NCDP,

2007 also provided that to meet the domestic requirement of

coal, CIL may have to import coal as may be required from time

to time, if feasible. CIL was to adjust its overall price

accordingly. It further provided that it was the responsibility of

CIL/Coal Companies to meet the full requirement of coal under

FSAs even by resorting to imports, if necessary.

10.It is not in dispute that in accordance with the NCDP,

2007, APML had applied for coal linkage to MoC. It is also not

in dispute that Western Coal Limited (“WCL” for short) and

South Eastern Coal Limited (“SECL” for short) issued two

6

Letters of Assurance (LoAs) in favour of APML and assured

supply of coal.

11.Undisputedly, FSA was executed between APML and WCL

for domestic coal linkage. Subsequently, the FSA was amended

and the quantum of coal assured by WCL was transferred to

SECL.

12.It is also not in dispute that subsequently, on 21

st

June

2013, the Cabinet Committee on Economic A�airs (“CCEA” for

short), in view of the persistent shortage of domestic coal,

approved a revised mechanism for coal supply to power

producers.

13.Thereafter, the Government of India, through the Ministry

of Coal, issued O�ce Memorandum dated 26

th

July 2013

(hereinafter referred to as “NCDP 2013”), thereby approving a

revised arrangement for the supply of coal to the identi�ed

Thermal Power Stations (“TPPs” for short). The said O�ce

Memorandum provided that FSAs will be signed for the

domestic coal quantity of 65%, 65%, 67%, and 75% of Annual

7

Contracted Quantity (“ACQ” for short) for the remaining four

years of the 12

th

Plan for the power plants having normal coal

linkages. It further provided that to meet the balance FSA

obligations towards the requirement of the said 78,000 MW

TPPs, CIL may import coal and supply the same to the willing

power plants on a cost-plus basis. It further provided that the

power plants may also directly import coal themselves, if they

so opt, in which case, the FSA obligations on the part of CIL to

the extent of import component would be deemed to have been

discharged.

14.On 31

st

July 2013, the MoP issued a letter to the Central

Electricity Regulatory Commission (“CERC” for short) and State

Electricity Regulatory Commissions to consider as pass-through

in tari� the cost of alternate coal (procured to meet the shortfall

in supply of domestic linkage coal) on a case to case basis.

15.Contending that on account of the Change in Law, APML

was entitled to compensation, APML �led a Petition bearing

Case No.189 of 2013 on 17

th

December 2013 before the

8

Maharashtra Electricity Regulatory Commission (“MERC” for

short).

16.MERC, vide order dated 15

th

July 2014, disposed the said

Petition (i.e. Case No. 189 of 2013) by approving a framework

for determination of compensatory fuel charge, in view of the

CCEA decision of 21

st

June 2013 and the MoP’s advice dated

31

st

July 2013.

17.In compliance with the MERC’s order dated 15

th

July

2014, APML �led another Petition before the MERC bearing

Case No. 140 of 2014 on 23

rd

July 2014, inter alia, for approving

a mechanism for the determination of compensatory tari�.

18.The MERC, vide its order dated 20

th

August 2014,

formulated a mechanism for the pass-through in tari� of the

compensatory fuel charge that had been allowed in Case No.189

of 2013.

19.Subsequently, APML �led a Review Petition before the

MERC bearing Case No.159 of 2014. The same was disallowed

9

by the MERC as being devoid of merits except on the issue of

the e�ectiveness of the compensatory fuel charge.

20.On 28

th

January 2016, the MoP issued the revised Tari�

Policy. As per clause 6.1 of the revised Tari� Policy, the

Appropriate Commission was required to consider the cost of

imported/market-based e-auction coal procured for making up

the shortfall in the domestic coal for pass-through in tari� of

competitively bid projects.

21.Thereafter, on 9

th

March 2016, APML �led appeals before

the Appellate Tribunal for Electricity (hereinafter referred to as

“APTEL”), being Appeal Nos. 129 of 2016 and 130 of 2016,

challenging the orders passed by the MERC in Case Nos.189 of

2013 and 140 of 2014. MSEDCL too �led cross-appeals against

the MERC orders being Appeal Nos. 187 and 188 of 2016.

22.On 4

th

May 2017, the learned APTEL remanded the issues

raised in the cross-appeals �led by APML and MSEDCL for

fresh consideration by the MERC in the light of the judgment of

this Court in the case of Energy Watchdog v. Central

10

Electricity Regulatory Commission and others

1

which was

decided on 11

th

April 2017.

23.By order dated 7

th

March 2018, the MERC decided Case

No.189 of 2013 and 140 of 2014, wherein, while allowing the

claims of APML for relief on account of a Change in Law for

1180 MW capacity, it restricted it to the extent of the minimum

supply obligations speci�ed for the CIL subsidiaries for the last

four years of the 12

th

Five Year Plan period i.e. Financial Year

2013-14 to Financial Year 2016-17 as per the NCDP, 2013. It

further held that the alternate coal quantity for meeting the

domestic coal shortfall shall be computed based on the Station

Heat Rate (“SHR” for short) mentioned by APML in the bid

documents and the middle value of the Gross Calori�c Value

(“GCV” for short) range of assured coal grade for domestic coal

as per the FSA/LoA/MoU.

1 (2017) 14 SCC 80

11

24.Being aggrieved thereby, APML preferred appeals before

the learned APTEL. The learned APTEL framed the following

three issues:

“Issue No. 1:Whether the MERC was

correct in holding that the

net SHR submitted by the

Appellant in its bid or SHR

and Auxiliary Consumption

norms speci�ed for new

generating stations under

the MYT Regulations, 2011,

whichever is superior shall

form the basis for

computing Change in Law

compensation under the

PPAs?

Issue No. 2: Whether the MERC was

correct in holding that the

reference GCV of domestic

coal supplied by CIL shall

be the middle value of GCV

range of assured coal grade

in LoA/FSA/MoU and not

the GCV as received?

Issue No. 3: Whether the MERC was

correct in holding that for

the purpose of Change in

Law compensation for 1180

MW capacity, shortfall in

12

domestic linkage coal shall

be assessed by considering

the coal supply as the

maximum of (1) actual

quantum of coal o�ered for

o�take by CIL under the

LoA/FSA and (2) the

minimum assured quantum

in NCDP 2013 for the

respective year?”

25.On Issue No.1, the learned APTEL held that APML was

entitled to compensation on the ground of Change in Law based

on the SHR speci�ed in the MERC MYT Regulations 2011 or the

actual SHR achieved by APML, whichever is lower.

26.On Issue No.2, the learned APTEL held that the

compensation for the Change in Law approved by the MERC

shall be computed based on the actual GCV of coal received.

27.On Issue No.3, the learned APTEL held that under the

NCDP, 2007, there was an assurance of 100% coal supply and

as such, while granting compensation on the ground of Change

in Law, it was not justi�ed to restrict it to the maximum of 35%

to 25% for the respective four years of the 12

th

Plan.

13

28.The learned APTEL held that the restitution principle has

to be applied. It further held that to protect the interests of

consumers, the Generators had itself indicated that the

parameters which are more bene�cial to the consumers i.e. the

lower amongst the actual or as per the Regulations would

protect the interests of the consumers.

29.Being aggrieved thereby, the MSEDCL has approached this

Court by way of Civil Appeal No.684 of 2021.

FACTS IN CIVIL APPEAL NO.6927 OF 2021

30.In Civil Appeal No.6927 of 2021, the MSEDCL challenges

the concurrent orders passed by the CERC dated 15

th

November

2018 and the order passed by the learned APTEL dated 16

th

July 2021.

31.MSEDCL issued a Request for Proposal (RFP) on 15

th

May

2009 and initiated the competitive bidding process for

procurement of power on long-term basis. GMR Warora Energy

Ltd. (“GMR” for short) submitted its bid on 7

th

August 2009 and

emerged as one of the successful bidders with a levelized tari�

14

of Rs. 2.879/kWh. Accordingly, the PPA was executed for the

procurement of 200 MW of power on 17

th

March 2010 by

MSEDCL on long-term basis. Similarly in March 2012,

Respondent No. 2-Union Territory of Dadra & Nagar Haveli

(“DNH” for short) issued an RFP for the procurement of power

through competitive bidding and GMR emerged as one of the

successful bidders.

32.Consequently, respondent No. 1 in Civil Appeal No.6927 of

2021 i.e. GMR entered into the following long-term PPAs for the

supply of power from the Project:

(a) Supply and sale of 200 MW of power on a long-term basis

to MSEDCL in terms of PPA dated 17

th

March 2010. The cut-o�

date for this PPA is 31

st

July 2009. Supply of power in terms of

the PPA commenced from 17

th

March 2014.

(b) Supply and sale of 200 MW of power on long term basis to

Electricity Department, DNH in terms of PPA dated 21

st

March

2013. The cut-o� date of this PPA is 1

st

June 2012. Supply of

power in terms of the PPA commenced from 1

st

April 2013.

15

(c) Supply and sale of 150 MW of power on long term basis to

TANGEDCO through back-to-back arrangements as follows:

(i) Power Sale Agreement (PSA) dated 1

st

March 2013

between GMR Energy Trading Limited (GMRETL) and GMR,

based on which a bid was submitted to TANGEDCO;

(ii) PPA dated 27

th

November 2013 between GMRETL and

TANGEDCO for the supply of power from GMR to TANGEDCO.

The cut-o� date of this PPA is 27

th

February 2013.

(iii) PPA dated 3

rd

May 2014 between GMR and GMRETL

recording the terms and conditions in accordance with PPA

between GMRETL and TANGEDCO. The supply of power under

the PPA commenced on 22

nd

October 2015.

33.Petition No. 8/MP/2014 was �led by GMR claiming

compensation on account of the impact of the Change in Law

events during the Operation period and Construction period

under MSEDCL and DNH PPAs. The Commission, by order

dated 1

st

February 2017, had allowed some of the claims of GMR

on the ground of Change in law. Vide the said order, it has also

16

disallowed some of the claims. Aggrieved by the said order,

GMR �led Appeal No. 111 of 2017 before the learned APTEL in

respect of the compensation claims disallowed by the

Commission. Similarly, Appeal No. 290/2017 was �led by DNH

Power Distribution Company Ltd against the said order dated

1

st

February 2017 disputing the compensation claims allowed to

GMR under some Change in Law events.

34.During the pendency of the above said appeals, GMR has

�led Petition (i.e. Petition No.88/MP/2018) seeking the following

reliefs:

“(a) Con�rms that the following operational

parameters which are imperative of

calculation of compensation due to the

Petitioner on account of change in law

events, are to be considered on actuals:

(i) Auxiliary Power Consumption

(ii) Station Heat Rate

(iii) Gross calori�c Value

(b) Con�rm that levy of Service Tax &

Swachh Bharat Cess on coal transportation

is on all components as per rail invoice;

17

(c) Release of amounts due to the Petitioner

from Respondent No. 1, MSEDCL in light of

the Commission’s order dated 1.2.2017 in

Petition No. 8/MP/2014.”

35. Two of the issues involved in the present appeals with

regard to SHR and GCV also fell for consideration before the

CERC.

36.The CERC found that the CERC norms applicable for the

period 2009-14 and 2014-19 do not provide the norms for 300

MW units. It further found that the CERC norms provide for a

degradation factor of 6.5% and 4.5% respectively towards Heat

Rate over and above the Design Heat Rate. It found that since

the Design Heat Rate is 2211 kcal/kWh, the gross Heat Rate

works out to 2355 kcal/kWh and 2310 kcal/kWh for the period

2009-14 and 2014-19 respectively. It directed that the SHR of

2355 kcal/kWh during the period 2009-14 and 2310 kcal/kWh

during the period 2014-19 or the actual SHR, whichever was

lower, shall be considered for calculating the coal consumption

for compensation under the Change in Law.

18

37.Insofar as the GCV is concerned, the CERC found that in

the 2014 Tari� Regulations of the Commission, the

measurement of GCV has been speci�ed on “as received” basis.

It, therefore, found that it would be appropriate if the GCV on

“as received” basis is considered for computation of

compensation for Change in Law.

38.Being aggrieved by the order passed by the CERC dated

15

th

November 2018, the MSEDCL preferred an appeal being

Appeal No.342 of 2019 before the learned APTEL. The learned

APTEL did not �nd merit in the submission of the MSEDCL and

as such, dismissed the appeal by judgment and order dated 16

th

July 2021.

39.Being aggrieved thereby, MSEDCL has approached this

Court by way of Civil Appeal No.6927 of 2021.

40.The arguments on behalf of the appellant-MSEDCL in Civil

Appeal No.684 of 2021 were advanced by Shri Gopal Jain,

learned Senior Counsel, whereas arguments in Civil Appeal

19

No.6927 of 2021 were advanced by Shri G. Sai Kumar, learned

counsel.

41.We have also heard Shri Balbir Singh, learned Additional

Solicitor General and Shri M.G. Ramachandran, learned Senior

Counsel appearing for some of the State Electricity Distribution

Companies, whose matters are not being decided by this

judgment, but wherein the aforesaid three questions/issues are

common.

42.On behalf of the respondent-APML as well as the

respondent-GMR, Dr. Abhishek Manu Singhvi, learned Senior

Counsel advanced the arguments. His arguments were

supplemented by Shri Vishrov Mukherjee, learned Counsel.

SUBMISSIONS ON BEHALF OF THE DISCOMS

43.The main arguments that were advanced on behalf of the

Distribution Companies (hereinafter referred to “DISCOMS”) are

as under:

(i) The SHR and GCV value are declared in the bid

document and it is not permissible for the

20

Generating Companies to claim advantage on

the basis of SHR value which is di�erent than

the one quoted i.e. the SHR value as provided in

the Tari� Regulations or the actual. It is their

submission that the declaration of operational

parameters i.e. SHR and GCV were the mandate

of the bid in case of Case-1 competitive bidding

process. It is submitted that if deviation from

such declared bid parameters for compensating

the bidder/ Generating Companies/ Generators

under the PPA on the ground of Change in Law

is permitted, it will take away the very sanctity

of the bid.

(ii) It is submitted that to ensure serious

participation in the bid process and for timely

completion of commencement of supply of

power, the Competitive Bidding Guidelines 2005

itself mandates the

21

bidder/generator/Generating Companies to

have a ‘�rm’ fuel arrangement. It is their

submission that it is mandatory for the

bidder/generator to declare the ‘quantity’ of fuel

required to generate power for the entire term of

the PPA. The DISCOMS argued that the

quantity of fuel can only be ascertained by

applying the SHR and GCV components as

declared in the bid.

(iii) It is submitted that the RFP itself mandated the

participating bidders/generators to submit

documentary evidence with regard to the

‘quantity’ of fuel required to generate power for

the entire term of 25 years of the PPA.

(iv) It is submitted that for ascertaining the

‘quantity’, it was also necessary for the

bidder/generator to provide ‘supporting

22

computation’ by declaring the SHR and GCV

value applicable for the entire term of the PPA.

(v) It is the contention on behalf of the DISCOMS

that the bidder/generator, while submitting

his/its bids, is required to submit the bids by

taking into consideration all factors, including

risks regarding �uctuations, availability of

fuel/coal, etc. It is submitted that if there is

any change with regard to the availability of fuel

or the rate at which a bidder/generator is

required to procure the coal, then the

bidder/generator has to su�er the

consequences thereof as he/it has submitted

his/its bid with eyes open.

(vi) The thrust of the argument of the DISCOMS is

that in a competitive bid based PPA under

Section 63 of the Electricity Act, the quoted

tari� is sacrosanct and it is not open for the

23

respondent/generator to seek higher tari� or

extra compensation under the PPA, except as

per Article 13 of the PPA dealing with impact of

Change in Law. It is submitted that the reliance

placed by the learned APTEL on the judgment of

this Court in the Case of Energy Watchdog

(supra) is totally misconceived.

(vii) It is, therefore, submitted that the relief for the

impact of NCDP 2013 is admissible only to the

extent of the changes brought about by the

NCDP 2013 and not in excess thereof. It is

submitted that the Change in Law made by the

Central Government on 31

st

July 2013 was vis-

à-vis the NCDP 2007 which was in force as on

the cut-o� date provided in Article 13.1 of the

PPA i.e. 7 days before the bid submission date.

It is submitted that the very purpose of

compensating the party a�ected by Change in

24

Law is to restore, through monthly tari�

payments, the a�ected party to the same

economic position as if the Change in Law had

not occurred.

(viii) It is submitted that as per para 2.2 of the NCDP

2007 read with para 5.2, CIL was entitled to

meet the shortfall in the availability of domestic

coal by importing coal. In such event, the

Generators were required to pay the higher cost

of imported coal to CIL. It is submitted that

while submitting the bids, the

bidders/generators, therefore, had submitted

their bids for supply of electricity to the

DISCOMS knowing the position that they will

not be compensated for higher cost of imported

coal separately, over and above the quoted

tari� /quoted energy charges, in the event of

supply of imported coal by CIL.

25

(ix) It is contended that, if in the event the

Generator could have procured the fuel/coal at

a lesser price, then the bene�t which would

have occurred to him/it on account of such

saving in procurement would have gone to

him/it. On the same analogy, if the Generator is

required to obtain the fuel/coal at a higher price

then he/it cannot be heard to say that he/it

should be compensated for the same.

(x) It is submitted that, as a matter of fact, till 31

st

July 2013 i.e. when the NCDP 2013 was

brought into e�ect, there could have been no

claims from the Generators for increase in tari�

to be allowed for higher coal cost on account of

imported coal supply. It is submitted that if the

NCDP 2013 had not brought about a Change in

Law, the position as prevalent before would

have continued. It is submitted that this Court

26

has consistently held that an unprecedented

increase in input cost cannot be a ground for a

supplier not to perform the obligations under a

binding contract or seek higher price or

compensation for such performance.

(xi) It is the submission of the DISCOMS that the

bene�t on account of the Change in Law

brought into e�ect by the NCDP 2013 has to be

restricted only to the extent of shortfall as

provided by the said policy. It is submitted that

if it was the intention of the NCDP 2013 to

provide for relief through the Change in

Law/policy decision for the shortfall even below

the speci�ed percentages i.e. for entire shortfall

on actual basis, then there was no rationale in

specifying the percentages in the NCDP 2013.

(xii) It is further contended by the DISCOMS that

the contention of the Generating Companies

27

that Shakti Policy 2017 was a continuation of

NCDP 2013 is incorrect. It is submitted that

the �rst part under (A) of the Shakti Policy 2017

deals with the old regime of LoA/FSA which is

the NCDP aspect. The second part under (B)

deals with the new transparent coal allocation

policy called SHAKTI. It is submitted that, as a

matter of fact, SHAKTI and allocation of coal

thereunder was admissible only to Entities

which did not have any LoA/FSA under the

NCDP 2007 or the NCDP 2013. Reliance in this

respect has been placed on the judgment of this

Court in the case of Jaipur Vidyut Vitaran

Nigam Ltd. and others v. Adani Power

Rajasthan Limited and another

2

(hereinafter

referred to as “Adani Rajasthan case”)

2 2020 SCC Online SC 697

28

(xiii) It is submitted that the law laid down by this

Court in the case of Energy Watchdog (supra)

has been applied by the learned APTEL in a

patently erroneous and perverse manner.

(xiv) It is submitted that the total quantum of coal

required is to be computed not in an abstract

manner but is to be necessarily based on the

SHR of the power station. It is submitted that

the SHR has nothing to do with coal quality or

GCV of coal. It is submitted that the SHR is the

boiler and turbine characteristic of a thermal

power station and, therefore, indicative of the

quality and e�ciency of the machine. It is

submitted that the quantum of coal requirement

is less with lower SHR and increases with

higher SHR, inasmuch as it relates to the ability

and e�ciency of the machines to extract heat

29

energy from coal to produce per unit of

electricity.

(xv) It is submitted that in Case 2 bidding, the net

SHR is a bidding parameter as coal linkage is

arranged by the entity inviting bids, and actual

cost of coal is allowed as a pass-through in the

tari� as per the formula speci�ed. It is their

submission that there are no quoted energy

charges in Case 2 bidding but only quoted �xed

charges. It is submitted that, whereas, in Case

1 bidding, SHR may not, as such, be the criteria

for selection but is a necessary requirement/

condition to be given for identifying the

quantum of coal required to generate electricity

over the length of the PPA. While submitting

his/its bid and quoting energy charges, the

bidder/generator was required to take into

consideration the quantum of coal requirement

30

which, in turn, is based on the SHR and

auxiliary consumption parameters to be given

by the bidder/generator. It is submitted that

the coal Supply Agreement for quantum of coal

is signed by CIL only for the quantum as

determined above, based on the SHR and

operating parameters provided by the

bidder/generator. It is submitted that the view

taken by the learned APTEL is contrary to the

view taken by it between the same parties in its

judgment dated 13

th

April 2018 in Appeal No.

210 of 2017.

(xvi) It is submitted that if the SHR which is higher

than the one quoted by the bidder/generator is

to be taken into consideration, then it will

amount to granting premium to the Generator

for its ine�ciency. It is submitted that if the

coal consumption increases on account of

31

highest SHR, the excess expenditure on

quantum of coal is to be borne by the

Generator.

(xvii) It is submitted that if the bid assumed SHR is

2200 kcal/kg and actual SHR is 2300 kcal/kg,

when the quoted tari� is based on the SHR of

2200 kcal/kg, for Change in Law impact, SHR

of 2300 kcal/kg cannot be permitted to be used

for computation of compensation for Change in

Law.

(xviii) It is submitted that the impugned judgment

permitting the actual SHR or the SHR given in

Tari� Regulations, whichever is lower, if upheld,

would amount to converting the scope of

Section 63 tari� determination into a Section 62

cost plus tari� determination. It is submitted

that this is impermissible in a competitive bid

based PPA.

32

(xix) It is further submitted that the MERC Tari�

Regulations expressly provides that the Tari�

Regulations will have no application to Section

63 tari� determination and the same is

governed by the guidelines of the Central

Government under Section 63 of the Electricity

Act.

(xx) It is submitted that perusal of Regulation 2(2)(a)

of the Central Electricity Regulatory

Commission (Terms and Conditions of Tari�)

Regulations, 2019 would reveal that they are

not applicable where the tari� has been

discovered through tari� based competitive

bidding in accordance with the guidelines

issued by the Central Government and adopted

by the Commission under Section 63 of the

Electricity Act.

33

(xxi) It is submitted that when admittedly there is bid

assumed SHR as per bidding conditions, the

learned APTEL cannot ignore the same on the

purported ground of equity and provide for an

alternate parameter for computational purpose

of actual SHR with the ceiling as under the

Tari� Regulations. It is submitted that this will

result in changing the bidding terms and

conditions after the bid was accepted and

became �nal.

(xxii) It is further submitted that the �nding that the

GCV computation is to be made on ‘as received’

basis, is also patently erroneous. It is

submitted that the real purpose behind relying

on the said methodology of computation is to

recover the grade slippage in the coal grade

actually supplied as against the coal grade

billed by the Coal Company and all the losses in

34

the heat value of the coal during the time period

when the coal is taken delivery from the coal

mines and transported to the Power Plant and

unloading at the Power Plant site.

(xxiii) It is submitted that the evaluation of GCV on air

dried basis by Coal Company was well

known/existing even prior to bidding and the

Generators were very much aware of it.

Accordingly, the same has already been factored

into while the Generators submitted their bids.

As such, if the computation of GCV is permitted

on ‘as received’ basis, the Generators will be

doubly compensated. In any case, it is

submitted that if the Generators had any issues

with regard to the grade of coal i.e. GCV range

and quantum, then that is an issue between the

Generators and the respective Coal Companies,

which is required to be resolved under the FSA

35

between them. The DISCOMS cannot be roped

into for the resolution of such disputes between

the Generators/Generating Companies and the

Coal Companies.

(xxiv) Lastly, it is submitted that since the letter of the

MoP, which has been considered as a Change in

Law event, is dated 31

st

July 2013, the learned

APTEL could not have given e�ect to the same

from 1

st

April 2013. It is submitted that this

would permit giving the bene�t of compensation

with retrospective e�ect.

(xxv) Insofar as the reliance placed by the Generating

Companies on the judgment of this Court in

Adani Rajasthan case is concerned, it is

submitted that the said judgment would not be

applicable to the facts of the present case. It is

submitted that in the said case, there was no

36

FSA and the State Government had undertaken

to supply the entire coal quantum.

(xxvi) It is further submitted that the judgment of this

Court in the case of Nabha Power Limited

(NPL) v. Punjab State Power Corporation

Limited (PSPCL) and another

3

would also not

be applicable to the facts of the present case

inasmuch as the said case was under Case-2.

(xxvii) It is submitted that the inability of a Generator

to seek su�cient relief from the Coal Companies

cannot be a reason to claim relief from the

Distribution Licensees/DISCOMS or the

consumers. The DISCOMS cannot be penalized

on account of failure by the Coal Companies of

supplying su�cient coal.

(xxviii) An additional ground in Civil Appeal No.6927 of

2021 raised is that CERC has erred in holding

3 (2018) 11 SCC 508

37

that the principle of late payment surcharge

envisaged in Articles 8.3.5 and 8.8.3 of the PPA

is applicable towards payment of the balance

amounts by MSEDCL in respect of the relief

under Change in Law.

SUBMISSIONS ON BEHALF OF THE GENERATING

COMPANIES

44.As against this, it is submitted on behalf of the Generating

Companies as under:

(i) It is submitted that under the NCDP 2007,

100% normative coal requirement of Generating

Companies was assured to be supplied by the

CIL. However, by NCDP 2013, the responsibility

of CIL to supply coal was reduced to 65%, 65%,

67% and 75% of ACQ for the remaining years of

the 12

th

Five Year Plan i.e. Financial Year 2013-

14 to Financial Year 2016-17.

38

(ii) It is submitted that the NCDP has been held to

be a law for the purposes of the Electricity Act.

It is, therefore, submitted that the Generating

Companies are entitled to compensation for the

shortfall of coal in terms of NCDP 2013 and the

same has to be paid on actuals, i.e. to the

extent the shortfall in coal supply actually

exists.

(iii) It is submitted that the said issue is no more

res integra and is covered by the judgment of

this Court in the case of Energy Watchdog

(supra) and in Adani Rajasthan case (supra).

(iv) It is submitted that, as per the guideless issued

by the MoP, for Case-1 bidding, SHR and GCV

are not bid parameters. The SHR and GCV

mentioned in the bid is part of technical

information and is not relevant for computing

Change in Law compensation. It is submitted

39

that there are substantial distinctions between

Case-1 and Case-2 bid. The �rst one is that in

Case-1 bid, SHR and GCV are not bid

parameters, whereas in Case-2, SHR and GCV

are bid parameters. Secondly, in Case-1

bidding, energy charge is not computed since

the energy charge forms part of quoted tari�,

whereas in Case-2 bidding, energy charge is

computed based on the net heat rate quoted in

the �nancial bid. Thirdly, in Case-1 bidding, the

PPA has no de�nition of quoted Net Heat

Rate/SHR, whereas in Case-2 bid, the PPA

de�nes quoted Net Heat Rate/SHR. It is,

therefore, submitted that in Case-1 bid there is

no consideration of SHR and GCV in the

formula of energy charge, whereas in Case-2

bid, these two parameters provide the formula

for computing energy charge.

40

(v) It is submitted that the learned APTEL in the

case of Wardha Power v. Reliance

Infrastructure & Ors.

4

has held that if SHR

and GCV as submitted in the bid are considered

for Change in Law compensation, it may result

in over or under recovery and should be

considered only on ‘actuals’. It is submitted

that the said judgment in Wardha Power

(supra) has not been challenged/appealed

against and has thus attained �nality.

(vi) The Generators further rely on the judgment of

this Court in Adani Rajasthan case (supra). It

is submitted that in the said case, the learned

APTEL had held that operational parameters

(like SHR and Auxiliary consumption) must be

considered as per ‘normative’ value, and this

view has been upheld by this Court.

4 Appeal No.288 of 2013

41

(vii) It is further submitted that the MERC in its

order dated 7

th

March 2018 in Case No.123 of

2017 (JSW v. MSEDCL) has held that the lower

of actual or normative parameter for Auxiliary

consumption (an operational parameter like

SHR) has to be considered for Change in Law

compensation. It is submitted that the

MSEDCL has not challenged the said judgment,

which has thus attained �nality.

(viii) It is submitted that the SHR is continuously

being monitored and its actual value, as

certi�ed by Energy Auditors, is submitted to

MSEDCL along with claims. As such, ‘actuals’

can be ascertained and veri�ed for computation

purposes.

(ix) It is submitted that, equally, the GCV of coal is

certi�ed by third party sampling agencies. A

GCV certi�cate is submitted to MSEDCL for

42

each railway rake separately, along with claim.

Such ‘actuals’ on ‘as received’ basis can be

ascertained/veri�ed for computational

purposes.

(x) It is further submitted that some of the

DISCOMS in the proceedings before the CERC

have contended that the SHR shall be

considered after ascertaining actual design heat

rate and margin as per CERC Regulations from

time to time. They have further taken a stand

that Auxiliary Consumption shall be considered

as per CERC Regulations. On a�davit, it is also

stated that GCV of alternate coal shall be as

certi�ed by a Third Party Sampling Agency, for

which the Commission should provide

appropriate guideline. It is, however, submitted

that now the DISCOMS are taking a U-turn by

43

contending that the SHR should be based on

bid assumed parameters.

(xi) It is submitted that, in any case, to maintain

balance, APML had itself o�ered for the bene�t

to be granted on the lower of ‘actual’ or

‘normative’ SHR as per Regulations. The same

has been accepted by the learned APTEL. It is

submitted that this will ensure that no

ine�ciency is passed on to consumers and, at

the same time, the Generator is restituted.

(xii) It is submitted that had there been no

occurrence of Change in Law event, i.e. there

was no shortfall in coal supply, the tari�

payment to the Generating Companies would

have been based on quoted energy charge. In

such a situation, SHR and GCV of coal would

not have come into the picture. However, when

there is an occurrence of Change in Law event,

44

the principle of ‘Restitution’ comes into play. It

is submitted that ‘restitution’ can take place

only with consideration of ‘actual’ parameters.

(xiii) It is submitted that taking this into

consideration, expert bodies like the CERC and

APTEL have allowed the SHR and GCV to be

determined on ‘actual’ basis.

(xiv) It is submitted that the SHR indicated in the bid

as part of technical information does not

conform to the mandate of restitution as it

cannot put the Generator back to the same

economic position had Change in Law event not

occurred.

(xv) It is submitted as per the NCDP 2007, 100%

normative requirement of coal was to be

supplied by the CIL. However, due to shortfall

of coal in the country, the responsibility of CIL

to supply coal was reduced to 65%, 65%, 67%

45

and 75% of the ACQ. The shortfall in coal was

to be met either by the CIL or by the Generating

Companies/Generators by importing coal. It is

submitted that the higher cost of such imported

coal was allowed to be a pass-through.

(xvi) It is submitted that a conjoint reading of CERC

statutory advice dated 20

th

May 2013, CCEA

decision dated 21

st

June 2013, MoP letter dated

31

st

July 2013, and clause 6.1 of the Tari�

Policy 2016 issued by the MoP would reveal that

pass-through of the higher cost of quantity of

shortfall in coal procured from alternate sources

was to be allowed. It is submitted that this

position has been upheld by the judgments of

this Court in the case of Energy Watchdog

(supra) and Adani Rajasthan case (supra).

(xvii) It is submitted that this pass-through is by way

of restitution due to shortfall in 100% assured

46

quantity of coal and it cannot be limited to the

percentages/trigger levels speci�ed in the NCDP

2013. It is submitted that the principle of

restitution would require the pass-through to

the extent the supply from CIL was cut down. It

is submitted that an argument to the contrary

has already been rejected by this Court in the

case of Adani Rajasthan case (supra).

(xviii) In addition to the judgments of this Court in the

cases of Energy Watchdog (supra) and Adani

Rajasthan case (supra), the Generating

Companies also rely on the judgment of this

court in the case of Uttar Haryana Bijli Vitran

Nigam Limited (UHBVNL) and another v.

Adani Power Limited and others

5

.

(xix) It is also submitted that the contention on the

part of the DISCOMS that Adani Rajasthan

5 (2019) 5 SCC 325

47

case (supra) would not be applicable to the

facts of the present case, inasmuch as there

was no FSA scenario, is also factually incorrect.

45.In addition to the aforesaid submissions, the respondent

in Civil Appeal No.6927 of 2021 i.e. GMR, the following

submissions have been made.

(i) That Schedule 10 of the PPA executed between

GMR and MSEDCL clearly mentions that the

levelized tari� will be as per CERC Regulations.

(ii) It is submitted that the normative SHR as

mentioned in the bid is computed assuming

power plant is operating at 85% of the Plant

Load Factor (“PLF” for short). It is, however,

submitted that the PLF is at the sole discretion

of the procurer-DISCOMS as they decide the

quantum of power to o�-take.

(iii) It is submitted that the SHR is a real-time

operating parameter which varies from time to

48

time, and it is computed by working out the

total electricity generated from the amount of

coal consumed in heat value (kCal) terms.

(iv) It is further submitted that the GCV of coal

actually delivered at site and fed to the boiler

varies from wagon to wagon. It cannot be a

homogeneous value.

(v) It is further submitted that the details given in

the bid with regard to SHR and GCV were only

indicative of the coal linkage to show that GMR

had the necessary means to supply power on

sustained basis and was a serious bidder, and

to further demonstrate its meeting of the

eligibility requirement prescribed under the

RFP.

(vi) It is submitted that the supporting

documents/information regarding fuel only

provides the quantity of coal required for the

49

project at Normative PLF and SHR computed as

per CERC norms, which is 2355 kCal/kWh. It

is submitted that MSEDCL is now insisting on

Design Gross Heat Rate of 2211 kCal/kWh,

which was not considered even for computation

of quantum of coal at the time of bid

submission.

(vii) It is further submitted that the Central

Electricity Authority, vide Noti�cations dated

17

th

October 2017 and 18

th

October 2017, has

even allowed for loss in GCV from ‘as received

basis’ to ‘as �red basis’ and as such, there is no

reason as to why GCV could not be computed

on ‘as received basis’.

(viii) It is further submitted that the MSEDCL cannot

be permitted to equate GMR’s case with APML

and Rattan India Power Limited inasmuch as

GMR falls under the jurisdiction of CERC,

50

whereas the other two fall under the jurisdiction

of MERC.

(ix) Insofar as late payment charges are concerned,

it is submitted that MSEDCL had unilaterally

deducted the amount, which is contrary to the

provisions of the PPA and as such, both CERC

and learned APTEL have rightly held that GMR

was entitled to late payment surcharge in terms

of Article 8.3.5. Reliance in this respect is

placed on the judgment of this Court in the case

of Maharashtra State Electricity

Distribution Company Limited v.

Maharashtra Electricity Regulatory

Commission and others

6

and Tamil Nadu

Generation & Distribution Corporation

6 (2022) 4 SCC 657

51

Limited v. PPN Power Generating Company

Private Limited

7

RELEVANT DOCUMENTS

46.For considering the rival submissions, it will be relevant to

refer to certain documents placed on record.

47.The MoP noti�ed the Competitive Bidding Guidelines,

2005 (hereinafter referred to as “the said Guidelines”) on 19

th

January 2005. The said Guidelines were framed under Section

63 of the Electricity Act. It will be relevant to refer to the

following part of the preamble of the said Guidelines.

“1. Preamble

………..

These guidelines have been framed under

the above provisions of section 63 of the Act.

The speci�c objectives of these guidelines are

as follows:

1. Promote competitive procurement of

electricity by distribution licensees;

2. Facilitate transparency and fairness in

procurement processes;

3. Facilitate reduction of information

asymmetries for various bidders;

7 (2014) 11 SCC 53

52

4. Protect consumer interests by

facilitating competitive conditions in

procurement of electricity;

5. Enhance standardization and reduce

ambiguity and hence time for

materialization of projects;

6. Provide �exibility to suppliers on

internal operations while ensuring

certainty on availability of power and

tari�s for buyers.”

48.Paragraph 2 of the said Guidelines deals with the scope of

the Guidelines. Para 2.2 of the said Guidelines reads thus:

“2.2.The guidelines shall apply for

procurement of base-load, peak-load and

seasonal power requirements through

competitive bidding, through the

following mechanisms:

(i) Where the location,

technology, or fuel is not

speci�ed by the procurer

(Case 1);

(ii)For hydro-power projects, load

center projects or other

location speci�c projects with

speci�c fuel allocation such as

captive mines available, which

the procurer intends to set up

under tari� based bidding

process (Case 2).

53

However separate RFP shall be used for

procuring base load or peak load or

seasonal load requirements as the case

may be.”

49.It can thus be seen that Para 2.2 distinguishes two types

of cases, viz., Case-1 and Case-2. Case-1 deals with the case

where the location, technology, or fuel is not speci�ed by the

procurer. Case-2 deals with hydro-power projects, load center

projects or other location speci�c projects with speci�c fuel

allocation such as captive mines available, which the procurer

intends to set up under tari� based bidding process.

50.Paragraph 3 of the said Guidelines deals with preparation

for inviting bids. Clause (I) of Para 3.2 deals with Case-2,

whereas clause (II) of Para 3.2 deals with Case-1. Sub-clause (i)

of clause (II) of Para 3.2 requires the bidder to undertake site

identi�cation and land acquisition. The bidder is required to

submit a copy of noti�cation issued for the land in question

under Section 4 of the Land Acquisition Act, 1894. For the part

of land excluding that which is to be acquired under the Land

54

Acquisition Act, 1894, the bidder is required to furnish

documentary evidence to establish allotment/ lease/

ownership/ vesting of at least one-third area of the said land.

Under sub-clause (ii), the bidder is required to submit

environmental clearance for the power station. Under sub-

clause (iii), the bidder is required to supply forest clearance, if

applicable, for the land for the power station. Sub-clause (iv) is

the most important for the resolution of the present dispute,

which reads thus:

“3. Preparation for inviting bids

3.1 …………

3.2 (I) ……………

(II) ………………

(i) ………………

(ii) ………………

(iii) ………………

iv) Fuel Arrangements: (a) In the

following cases fuel arrangements

shall have to be made for the quantity

of fuel required to generate power

from the phase of the power station

from which power is proposed to be

55

supplied at Normative Availability for

the term of the PPA.

In case of domestic coal, the

Bidder shall have made �rm

arrangements for fuel tie up

either by way of coal block

allocation or fuel linkage

In case of domestic gas, the

Bidder shall have made �rm

arrangements for fuel tie up by

way of long term fuel supply

agreement for the term &

quantity as per Government of

India gas allocation policy

b) Fuel arrangements in the following

cases shall have to be made for the

quantity of fuel required to generate

power from the power station for the

total installed capacity.

In case of imported coal, the

Bidder shall have either

acquired mines having proven

reserves for at least 50% of the

quantity of coal required OR

shall have a fuel supply

agreement for at least 50% of

the quantity of coal required for

a term of at least �ve (5) years

or the term of the PPA,

whichever is less.

In case of RLNG, the Bidder

shall have made �rm

arrangements for fuel tie up by

56

way of fuel supply agreement for

at least 50% of the quantity of

fuel required for a term of at

least �ve (5) years or the term of

the PPA, whichever is less.

Blending of Imported and Domestic

coal may be used in which case,

criteria for imported and domestic

coal shall be met separately in the

ratio of blending.”

51.It can thus be seen that in case of domestic coal, the

bidder is required to make �rm arrangements for fuel tie up

either by way of coal block allocation or fuel linkage.

52.Clause (b) of sub-clause (iv) of clause (II) of Para 3.2 deals

with imported coal, in which case the bidder shall have either

acquired mines having proven reserves for at least 50% of the

quantity of coal required OR shall have a fuel supply agreement

for at least 50% of the quantity of coal required for a term of at

least �ve years or the term of the PPA, whichever is less.

57

53.Paragraph 4 of the said Guidelines deals with Tari�

Structure. It will be relevant to refer to Para 4.2, which reads

thus:

“4. Tari� Structure

4.1 ……..

4.2. In case of long term procurement

with speci�c fuel allocation (Case 2), the

procurer shall invite bids on the basis of

capacity charge and net quoted heat

rate. The net heat rate shall be ex-bus

taking into account internal power

consumption of the power station. The

energy charges shall be payable as per

the following formula:

Energy Charges = Net quoted heat rate X

Scheduled Generation X Monthly

Weighted Average Price of Fuel/Monthly

Average Gross Calori�c Value of Fuel

If the price of the fuel has not been

determined by the Government of India,

government approved mechanism or the

Fuel Regulator, the same shall have to

be approved by the appropriate

Regulatory Commission.

In case of coal/lignite fuel, the cost of

secondary fuel oil shall be factored in the

capacity charges.”

58

54.It can thus be seen that insofar as Case-2 is concerned,

the procurer is required to invite bids on the basis of capacity

charge and net quoted heat rate. The net heat rate is required

to be ex-bus taking into account internal power consumption of

the power station. It further provides that if the price of the fuel

is not determined by the Government of India, government

approved mechanism or the Fuel Regulator, the same shall

have to be approved by the appropriate Regulatory Commission.

55.Para 4.4 provides that the capacity charge shall be paid

based on actual availability, as per charges quoted in Rs./kwh

and shall be limited to the normative availability. It further

provides that the normative availability for Case-1 and thermal

stations under Case-2 shall be a maximum of 85%.

56.Para 4.7 is another important clause for the resolution of

the present dispute, which reads thus:

“4.7. Any change in law impacting cost

or revenue from the business of selling

electricity to the procurer with respect to

59

the law applicable on the date which is 7

days before the last date for RFP bid

submission shall be adjusted separately.

In case of any dispute regarding the

impact of any change in law, the

decision of the Appropriate Commission

shall apply.”

57.It can thus be seen that any Change in Law impacting cost

or revenue from the business of selling electricity to the

procurer with respect to the law applicable on the date which is

7 days before the last date for RFP bid submission shall be

adjusted separately. It provides that in case of any dispute

regarding the impact of any Change in Law, the decision of the

Appropriate Commission shall apply.

58.It will also be relevant to refer to Para 4.12, which reads

thus:

“4.12 No adjustment shall be provided for

heat rate degradation of the generating

stations. Even in case of bids based on net

heat rate, the bidder shall factor in site

conditions, loading conditions, frequency

variations etc and no adjustment shall be

allowed on the quoted net heat rate for the

duration of the contract.”

60

59.It can thus be seen that no adjustment is to be provided

for heat rate degradation of the generating stations. Even in

case of bids based on net heat rate, the bidder shall factor in

site conditions, loading conditions, frequency variations etc.

and no adjustment shall be allowed on the quoted net heat rate

for the duration of the contract.

60.The NCDP 2007 would be of vital importance. Clause 2.2

thereof deals with Power Utilities including Independent Power

Producers (IPPs)/Captive Power Plants (CPPs) and Fertilizer

Sector. Clause 2.2 reads thus:

“2. Distribution and Pricing of coal

to di�erent consumers/sector(s):

2.1.………………

2.2 Power Utilities including

Independent Power Producers

(IPPs)/Captive Power Plants(CPPs) and

Fertilizer Sector

100% of the quantity as per the

normative requirement of the consumers

would be considered for supply of coal,

61

through Fuel Supply Agreement (FSA) by

Coal India Limited (CIL) at �xed prices to

be declared/noti�ed by CIL. The

units/power plants, which are yet to be

commissioned but whose coal

requirements has already been assessed

and accepted by Ministry of Coal and

linkage/Letter of Assurance (LoA)

approved as well as future commitments

would also be covered accordingly.”

61.It can thus be seen that the NCDP 2007 assured 100% of

the quantity as per the normative requirement of the consumers

for supply of coal, through FSA by CIL at �xed prices to be

declared/noti�ed by CIL. It further provided that the

units/power plants, which are yet to be commissioned but

whose coal requirements has already been assessed and

accepted by MoC and linkage/Letter of Assurance (LoA)

approved as well as future commitments would also be covered

in accordance therewith.

62.It will also be relevant to note the following part of clause

5.2 of the NCDP 2007.

“5. Policy for New Consumers

62

5.1. ……………

5.2. …………… In order to meet the

domestic requirement of coal, CIL may

have to import coal as may be required

from time to time, if feasible. CIL may

adjust its overall price accordingly.

Thus, it will be the responsibility of

CIL/Coal companies to meet full

requirement of coal under FSAs even by

resorting to imports, if necessary.”

63.It can thus be seen that clause 5.2 of the NCDP 2007

provides that in order to meet the domestic requirement of coal,

CIL may have to import coal as may be required from time to

time, if feasible. It further provided that CIL would adjust its

overall price accordingly. The NCDP 2007 emphasizes the

responsibility of CIL/Coal Companies to meet full requirement

of coal under FSAs even by resorting to imports, if necessary.

64.It will also be relevant to refer to the communication

addressed by the MoP dated 9

th

May 2013 to the Secretary,

CERC.

63

“Subject: Impact on tari� on the

concluded PPAs due to domestic coal

availability.

Sir,

Coal linkages have been granted for

power projects under the New Coal

Distribution Policy 2007 (NCDP), which

mandates that CIL will meet 100% of

normative requirement of power sector.

Para 5.2 of NCDP provides that “In order

to meet the domestic requirement of coal,

CIL may have to import coal as may be

required from time to time, if feasible. CIL

may adjust its overall price accordingly.

Thus, it will be the responsibility of

CIL/Coal companies to meet full

requirement of coal under FSAs even by

resorting to imports, if necessary”. Post

NCDP MoC granted linkages between

2008-2010 with the assumption that it

would meet coal requirement at around

85% PLF. On this basis LoAs were

issued by coal companies, after getting

commitment guarantees in the form of

Bank Guarantee from the developers

thereby undertaking an explicit

obligation to supply coal to the extent of

the speci�ed quantity to the power

developer. Having obtained the LOA the

developers would have proceeded on the

assumption of getting the requisite

quantity of domestic coal with the

disincentive trigger of 90% of LoA

64

quantity prevailing under the then Fuel

Supply Agreement (FSA) with a provision

for CIL resorting to import of coal to

bridge the gap, if any. It is assumed

that the power producers would have

factored this assurance regarding coal

supply while submitting their bids in

response to Case 1 and Case 2

competitive bidding for long term power

purchase agreements. Thus, while the

fuel price risk would have been taken

into account and factored in the

escalable component of energy charges,

it is assumed that no fuel availability

risk would have been taken into

consideration on account of the LOAs

given by CIL.

2. It now transpires that on account

of the limited availability of coal Ministry

of Col has indicated that CIL may not be

in a position to supply more than 60 to

65% of ACQ to those power producers

who had been earlier issued LOAs of

normative quantities corresponding to

85% PLF. Simultaneously, it has been

proposed that the disincentive trigger for

coal supply would be brought down from

90% to 60 to 65% by CIL in the new fuel

supply agreements to be signed with

these power producers. This obviously

would create a situation where the power

producers would have to arrange fuel

from open market including imports

either through CIL or directly. In view of

65

this scenario, PPAs which are already

concluded between the developers and

discoms as a result of competitive

bidding in the last few years based on

domestic coal linkage (LOA) may have to

use imported coal to bridge the shortage

of domestic coal in order to ful�l that

contractual obligations. The Association

of Power Producers represented on this

issue of shortage of domestic coal and its

consequential e�ect on the concluded

PPAs through competitive bidding route.

3. The Cabinet Committee on

Economic A�airs (CCEA) has also

considered the situation arising out of

the inadequate availability of coal

leading to this non-ful�lment of the LOA

commitments on the part of CIL. CCEA

has decided the following guidelines in

its meeting held on 06.02.2013 in

respect of generating plants

commissioned/to be commissioned

during the period 1.4.09 to 31.03.15:

i) CIL will provide imported coal on

cost plus basis to all producers

willing to take such cost;

ii) That the higher cost of imported

coal will be allowed as a pass

through.

3. In view of the circumstances stated

above CERC is requested to advice the

Government on the manner in which the

66

issue of fuel availability risk arising out

of CIL’s inability to meet its LOA

commitments could be addressed with

regard to power producers who have

already entered into long term PPAs with

distribution companies based on such

commitments and the feasibility of

passing on the additional cost of

procuring market fuel incurred by the

power developers on account of the

circumstances stated in the aforesaid

paras. CERC is also requested to suggest

appropriate ways for issuing advisory to

SERCs/State Governments which may

necessitated to be issued by MoP for the

implementation of the above.

4. CERC’s considered advice is

requested in this matter at the earliest.

5. This issues with the approval of

MOSP (I/C).”

65.Perusal of the communication dated 9

th

May 2013 would

clearly show that the NCDP 2007 mandates that CIL will meet

100% of normative requirement of power sector. It states that,

post NCDP 2007, MoC has granted linkages between 2008-2010

with the assumption that it would meet coal requirement at

around 85% of the PLF. On that basis, the LoAs were issued by

67

Coal Companies, after getting commitment guarantees in the

form of Bank Guarantees from the developers, thereby

undertaking an explicit obligation to supply coal to the extent of

the speci�ed quantify to the power developer. It further states

that having obtained the LoA, the developers would have

proceeded on the assumption of getting the requisite quantity of

domestic coal with the disincentive trigger of 90% of LoA

quantity prevailing under the then FSA with a provision for CIL

resorting to import of coal to bridge the gap, if any. It

speci�cally mentions that the power producers would have

factored in this assurance regarding coal supply while

submitting their bids in response to Case-1 and Case-2

competitive bidding for long-term PPAs.

66.The said communication further records that it now

transpires that on account of the limited availability of coal,

MoC has indicated that CIL may not be in a position to supply

more than 60 to 65% of ACQ to those power producers who had

been earlier issued LoAs of normative quantities corresponding

68

to 85% of the PLF. It was proposed that the disincentive trigger

for coal supply would be brought down from 90% to 60 to 65%

by CIL in the new FSAs to be signed with these power

producers. It further states that in view of this scenario, PPAs

which are already concluded between the developers and the

DISCOMS as a result of competitive bidding in the last few

years based on domestic coal linkage (LoA) may have to use

imported coal to bridge the shortage of domestic coal in order to

ful�l their contractual obligations.

67.The communication further records that the CCEA has

also considered the situation arising out of the inadequate

availability of coal leading to the non-ful�lment of its LOA

commitments on the part of the CIL. The CCEA, therefore, in

its meeting held on 6

th

February 2013 has decided the following

guidelines in respect of generating plants commissioned/to be

commissioned during the period 1

st

April 2009 to 31

st

March

2015:

69

ii) That CIL will provide imported coal on cost plus basis

to all producers willing to take such cost;

iii) That the higher cost of imported coal will be allowed as

a pass-through.

68.The communication therefore requested the CERC to

advise the Government on the manner in which the issue of fuel

availability risk, arising out of CIL’s inability to meet its LOA

commitments, could be addressed. The CERC was also

requested to suggest appropriate ways for issuing advisories to

SERCs/State Governments by the MoP, which may be

necessitated for the implementation of the above.

69.In pursuance of the aforesaid Communication dated 9

th

May 2013, the CERC issued Statutory Advice on 20

th

May 2013

under Section 79(2) of the Electricity Act regarding impact on

tari� of the concluded PPAs due to domestic coal availability. It

will be relevant to refer to the following part of the said

statutory advice.

70

“2. The matter was considered in the

Commission. The Commission appreciates

the need for securing fuel supply for various

projects in order to ensure optimum

generation from the power plants in the

country. Non-availability of adequate

quantum of coal has posed serious challenge

to power generation as re�ected in the data

compiled by the Central Electricity Authority

(CEA): the Plant Load Factor (PLF) of the

generating stations across the country has

been severely a�ected for want of adequate

coal supply by CIL/Coal Companies.

3. The proposal to make CIL supply imported

coal on cost plus basis to all power projects

commissioned or to be commissioned during

the period 1.4.2009 to 31.3.2015 and willing

to take such coal would require appropriate

change in the NCDP, as at present it is the

full responsibility of CIL to meet full

requirement of coal under FSAs even by

resorting to import; if necessary. As a follow

up, the FSAs between the CIL/its

subsidiaries and the power producers will

have to be modi�ed through Supplementary

Agreements.”

70.It can thus clearly be seen that the CERC has noted that

the non-availability of adequate quantum of coal has posed

serious challenge to power generation as re�ected in the data

compiled by the Central Electricity Authority (CEA). It further

71

noted that the PLF of the generating stations across the country

has been severely a�ected for want of adequate coal supply by

CIL/Coal Companies. It further records that to give e�ect to the

proposal to make CIL supply imported coal on cost plus basis to

all power projects commissioned or to be commissioned during

the period from 1

st

April 2009 to 31

st

March 2015 and willing to

take such coal, would require appropriate change in the NCDP,

as at present it is the full responsibility of CIL to meet full

requirement of coal under FSAs even by resorting to import, if

necessary. It further states that as a follow up, the FSAs

between the CIL/its subsidiaries and the power producers will

have to be modi�ed through Supplementary Agreements.

71.After referring to clause 10.1.1 of the Standard PPA for

Procurement of Power under Case-1 Bidding Procedure, which

deals with ‘Change in Law’, the statutory advice states thus:

“For claiming any bene�ts under change in

law, the Project Developer would have to

move the appropriate Commission and the

decision of that Commission in this regard

would be �nal, in terms of the provisions

72

of Articles 10.3.3 and 10.3.4 of the

Standard PPA. The appropriate

Commissions are expected to take

decisions on the merits of each case

including the claims of the Project

Developers for compensation on account of

imported coal after consultation with the

stakeholders.”

72.It can thus be seen that the CERC states that for claiming

any bene�ts under the Change in Law, the Project Developer

would have to move the appropriate Commission. It further

records that the appropriate Commissions are expected to take

decisions on the merits of each case including the claims of the

Project Developers for compensation on account of imported

coal after consultation with the stakeholders.

73.Subsequent to the aforesaid communication, the MoC

issued a Press Release on 21

st

June 2013. It will be relevant to

refer to the following part of the said Press Release.

“The Cabinet Committee on Economic

A�airs (CCEA) today approved the

following mechanism for supply of coal

to power producers:

73

(i) Coal India Ltd. (CIL) to sign Fuel

Supply Agreements (FSA) for a total

capacity of 78000 MW including cases of

tapering linkage, which are likely to be

commissioned by 31.03.2015. Actual

coal supplies would however commence

when long term Power Purchase

Agreements (PPAs) are tied up.

(ii) Taking into account the overall

domestic availability and actual

requirements, FSAs to be signed for

domestic coal quantity of 65 percent, 65

percent, 67 percent and 75 percent of

Annual Contracted Quantity (ACQ) for

the running four years of the 12th Five

Year Plan.

(iii) To meet its balance FSA obligations,

CIL may import coal and supply the

same to the willing Thermal Power

Plants (TPSs) on cost plus basis. TPPs

may also import coal themselves. MoC to

issue suitable instructions.

(iv) Higher cost of imported coal to be

considered for pass through as per

modalities suggested by CERC. MoC to

issue suitable orders supplementing the

New Coal Distribution Policy (NCDP).

MoP to issue appropriate advisory to

CERC/SERCs including modi�cations if

any in the bidding guidelines to enable

the appropriate Commissions to decide

74

the pass through of higher cost of

imported coal on case to case basis.”

74.It is thus clear that taking into account the overall

domestic availability and actual requirements, FSAs were to be

signed for domestic coal quantity of 65%, 65%, 67% and 75% of

ACQ for the running/remaining four years of the 12th Five Year

Plan. It can further be seen that the CCEA has also taken a

decision that CIL may import coal to meet its balance FSA

obligations and supply the same to the willing TPPs on cost plus

basis. TPPs may also be permitted to import coal themselves. It

further provided that the higher cost of imported coal was to be

considered for pass-through as per the modalities suggested by

the CERC.

75.In pursuance thereof, the Government of India, through

MoC, issued O�ce Memorandum dated 26

th

July 2013. The

said O�ce Memorandum reads thus:

“Sub: New Coal Distribution Policy -

further instructions regarding

implementation thereof.

75

The New Coal Distribution Policy

(NCDP) was issued vide this Ministry's

O�ce Memorandum NO. 23011/4/2007-

CPD dated 18.10.2007, laying down the

guidelines for distribution and pricing of

coal to various sectors. As per para 2.2 of

the said policy, Power Utilities including

Independent Power Producer were to be

supplied 100 per cent of the quantity as

per their normative requirement through

Fuel Supply Agreement(s) (FSAs) by Coal

India Limited (CIL) at �xed prices to be

declared/noti�ed by CIL. As per para 5.2,

in order to meet the domestic requirement,

CIL was to import coal as required from

time to time, if feasible and adjust the

overall price accordingly.

2. Government has now approved a

revised arrangement for supply of coal to

the identi�ed Thermal Power Stations

(TPPs) of 78,000 MW capacity

commissioned or likely to be

commissioned during the period from

01.04.2009 to 31.03.2015. Taking into

account the overall domestic availability

and the likely actual requirements of these

TPPs, it has been decided that FSAs will be

signed for the domestic coal quantity of

65%, 65%, 67% and 75% of ACQ for the

remaining four years of the 12th Plan for

the power plants having normal coal

linkages. Cases of tapering linkage would

get coal supplies as per the Tapering

76

Linkage Police. To meet its balance FSA

obligations towards the requirement of the

said 78,000 MW TPPs, CIL may import

coal and supply the same to the willing

power plants on cost plus basis. Power

plants may also directly import coal

themselves, if they so opt, in which case,

the FSA obligations on the part of CIL to

the extent of import component would be

deemed to have been discharged.

3. Para 2.2 and 5.2 of the New Coal

Distribution Policy issued vide OM No.

23011/4/2007-CPD dated 18.10.2007

stand modi�ed to the above extent.

4. The above guidelines will also be

applicable to the distribution of coal from

Singreni Collieries Company Limited

(SCCL).

5. CIL and its subsidiaries and SCCL

are advised to take further action

accordingly.”

76.It can thus be seen that the NCDP 2013 also speci�cally

states that, as per NCDP 2007 and speci�cally paragraph 2.2

thereof, Power Utilities, including IPPs, were to be supplied

100% of the quantity as per their normative requirement

through FSAs by CIL at �xed prices to be declared/noti�ed by

77

CIL. It further reiterates that, as per para 5.2, in order to meet

the domestic requirement, CIL was to import coal as required

from time to time, if feasible, and adjust the overall price

accordingly.

77.Para 2 of the NCDP 2013 states that the Government has

now approved a revised arrangement for supply of coal to the

identi�ed TPPs of 78,000 MW capacity commissioned or likely

to be commissioned during the period from 1

st

April 2009 to 31

st

March 2015. It states that, taking into account the overall

domestic availability and the likely actual requirements of these

TPPs, it was decided that FSAs will be signed for the domestic

coal quantity of 65%, 65%, 67% and 75% of ACQ for the

remaining four years of the 12

th

Plan for the power plants

having normal coal linkages. It further states that to meet the

balance FSA obligations towards the requirement of the said

78,000 MW TPPs, CIL may import coal and supply the same to

the willing power plants on cost plus basis. It further states

that the power plants may also directly import coal themselves,

78

if they so opt, in which case, the FSA obligations on the part of

CIL to the extent of import component would be deemed to have

been discharged.

78.Immediately thereafter, on 31

st

July 2013, the MoP

addressed a communication to the Secretary, CERC. It will be

relevant to refer to Para 2 of the said communication, which

reads thus:

“2. After considering all aspects and the

advice of CERC in this regard, Government

has decided the following in June, 2013:

i) taking into account the overall

domestic availability and actual

requirements, FSAs to be signed

for domestic coal component for

the levy of disincentive at the

quantity of 65%, 65%, 67% and

75% of Annual Contracted

Quantity (ACQ) for the

remaining four years of the 12

th

Plan.

ii)to meet its balance FSA

obligations, CIL may import coal

and supply the same to the

willing TPPs on cost plus basis.

79

TPPs may also import coal

themselves if they so opt.

iii)higher cost of imported coal to

be considered for pass through

as per modalities suggested by

CERC.”

79.It can thus clearly be seen that the Government, after

considering all aspects and the advice of CERC in this regard,

decided that the higher cost of imported coal was to be

considered for pass-through as per modalities suggested by the

CERC.

80.It will also be relevant to refer to Para 4 of the said

communication, which reads thus:

“4. As per decision of the Government, the

higher cost of import/market based e-

auction coal be considered for being made a

pass through on a case to case basis by

CERC/SERC to the extent of shortfall in the

quantity indicated in the LoA/FSA and the

CIL supply of domestic coal which would be

minimum of 65%, 65%, 67% and 75% of LoA

for the remaining four years of the 12th Plan

for the already concluded PPAs based on

tari� based competitive bidding.”

80

81.Perusal of para 4 would clearly reveal that the higher cost

of import/market based e-auction coal was to be considered for

being made a pass-through on a case to case basis by

CERC/SERC to the extent of shortfall in the quantity indicated

in the LoA/FSA. It further reiterates that CIL may supply

domestic coal which would be minimum of 65%, 65%, 67% and

75% of LoA for the remaining four years of the 12th Plan for the

already concluded PPAs based on tari� based competitive

bidding.

82.The MoP thereafter vide Resolution dated 28

th

January

2016 noti�ed the ‘Tari� Policy’. It will be relevant to refer to

clause 6.1 of the said Policy, which reads thus:

“6.0 GENERATION

………………

6.1 Procurement of power

As stipulated in para 5.1, power

procurement for future requirements

should be through a transparent

competitive bidding mechanism using the

guidelines issued by the Central

Government from time to time. These

guidelines provide for procurement of

81

electricity separately for base load

requirements and for peak load

requirements. This would facilitate setting

up of generation capacities speci�cally for

meeting such requirements.

However, some of the competitively bid

projects as per the guidelines dated 19

th

January, 2005 have experienced

di�culties in getting the required quantity

of coal from Coal India Limited (CIL). In

case of reduced quantity of domestic coal

supplied by CIL, vis-a-vis the assured

quantity or quantity indicated in Letter of

Assurance/FSA the cost of

imported/market based e-auction coal

procured for making up the shortfall, shall

be considered for being made a pass

through by Appropriate Commission on a

case to case basis, as per advisory issued

by Ministry of Power vide OM No. FU-

12/2011-IPC (Voi-IJI) dated 31.7.2013.”

83.It is thus clear that the Tari� Policy dated 28

th

January

2016 provided that the power procurement for future

requirements should be through a transparent competitive

bidding mechanism using the guidelines issued by the Central

Government from time to time. It further provides the

guidelines for procurement of electricity separately for base load

82

requirements and for peak load requirements. It further notes

that some of the competitively bid projects as per the guidelines

dated 19

th

January, 2005 have experienced di�culties in getting

the required quantity of coal from CIL. It further provides that

in case of reduced quantity of domestic coal supplied by CIL vis-

à-vis the assured quantity or quantity indicated in LoA/FSA,

the cost of imported/market based e-auction coal procured for

making up the shortfall shall be considered for being made a

pass-through by Appropriate Commission on a case to case

basis. This is in pursuance of the advisory issued by Ministry of

Power dated 31

st

July 2013.

JUDGMENTS CITED

84.Having considered these documents, we will now consider

the judgments which are relied on by both the parties.

85.In the case of Energy Watchdog (supra), after several

rounds of litigation, the learned APTEL held that generation and

sale of power by Adani Power to GUVNL and Haryana Utilities

was a composite scheme within the meaning of Section 79(1)(b)

83

of the Electricity Act and, therefore, the CERC would have

jurisdiction to proceed further in the matter. It further held

that force majeure was made out on the facts of the said cases

and reversed the CERC’s/Commission’s order on that score. It

also held that the Change in Law provisions do not apply to

foreign law and, therefore, changes in Indonesian law did not

come within the scope of the provisions. Insofar as changes in

Indian law were concerned, it held that the government policies

that were relied upon did not constitute “law”. The said

decision of the learned APTEL was assailed before this Court.

This Court while rejecting the argument on the ground of force

majeure observed thus:

“42. It is clear from the above that the

doctrine of frustration cannot apply to

these cases as the fundamental basis of

the PPAs remains unaltered. Nowhere do

the PPAs state that coal is to be procured

only from Indonesia at a particular price.

In fact, it is clear on a reading of the PPA

as a whole that the price payable for the

supply of coal is entirely for the person

who sets up the power plant to bear. The

fact that the fuel supply agreement has to

84

be appended to the PPA is only to indicate

that the raw material for the working of the

plant is there and is in order. It is clear

that an unexpected rise in the price of coal

will not absolve the generating companies

from performing their part of the contract

for the very good reason that when they

submitted their bids, this was a risk they

knowingly took. We are of the view that the

mere fact that the bid may be non-

escalable does not mean that the

respondents are precluded from raising the

plea of frustration, if otherwise it is

available in law and can be pleaded by

them. But the fact that a non-escalable

tari� has been paid for, for example, in the

Adani case, is a factor which may be taken

into account only to show that the risk of

supplying electricity at the tari� indicated

was upon the generating company.”

86.This Court, thereafter, considered as to whether any

Change in Law could be stretched to mean “all laws”. This

Court held that Clause 4.7 read with Clause 5.17 of the

Guidelines would reveal that it would not include changes in

Indonesian law, being foreign and not Indian law.

87.In Energy Watchdog (supra), this Court also had an

occasion to consider the MoP communication dated 31

st

July

85

2013, the relevant part of which has already been reproduced

by us herein above. This Court observed thus:

“56. However, insofar as the applicability of

Clause 13 to a change in Indian law is

concerned, the respondents are on �rm

ground. It will be seen that under Clause

13.1.1 if there is a change in any consent,

approval or licence available or obtained for

the project, otherwise than for the default of

the seller, which results in any change in any

cost of the business of selling electricity, then

the said seller will be governed under Clause

13.1.1. It is clear from a reading of the

Resolution dated 21-6-2013, which resulted

in the letter of 31-7-2013, issued by the

Ministry of Power, that the earlier coal

distribution policy contained in the letter

dated 18-3-2007 stands modi�ed as the

Government has now approved a revised

arrangement for supply of coal. It has been

decided that, seeing the overall domestic

availability and the likely requirement of

power projects, the power projects will only

be entitled to a certain percentage of what

was earlier allowable. This being the case, on

31-7-2013…..”

88.This Court, thereafter, referred to the Tari� Policy dated

28

th

January 2016, the relevant part of which has already been

reproduced by us herein above. This Court observed thus:

86

“57. Both the letter dated 31-7-2013 and the

revised Tari� Policy are statutory documents

being issued under Section 3 of the Act and

have the force of law. This being so, it is clear

that so far as the procurement of Indian coal

is concerned, to the extent that the supply

from Coal India and other Indian sources is

cut down, the PPA read with these

documents provides in Clause 13.2 that while

determining the consequences of change in

law, parties shall have due regard to the

principle that the purpose of compensating

the party a�ected by such change in law is to

restore, through monthly tari� payments, the

a�ected party to the economic position as if

such change in law has not occurred.

Further, for the operation period of the PPA,

compensation for any increase/decrease in

cost to the seller shall be determined and be

e�ective from such date as decided by the

Central Electricity Regulation Commission.

This being the case, we are of the view that

though change in Indonesian law would not

qualify as a change in law under the

guidelines read with the PPA, change in

Indian law certainly would.”

89.It can thus clearly be seen that insofar as the arguments

with regard to e�ect of the Change in Law being given on the

basis of ACQ is concerned, the same stands speci�cally

rejected.

87

90.A bench of three learned Judges of this Court in Adani

Rajasthan case (supra) also had an occasion to consider a

similar issue. An argument which is sought to be advanced

before us that the Change in Law claim may be con�ned only to

35 to 40% was also advanced in the said case. Rejecting the

said contention, this Court observed thus:

“50. Shri C. Aryama Sundaram argued that

the FSA related approximately 61 per cent

of the fuel requirement. Thus, the change in

law claim may be con�ned to 35 to 40 per

cent. The argument cannot be accepted as

bidding was not based on dual fuel, but was

evaluated on domestic coal. There was no

such stipulation that evaluation of bidding

was done on domestic basis; the tari� was

to be worked out in the aforesaid ratio of

60 : 40 per cent of imported coal and

domestic coal respectively. Apart from that,

we �nd from the order of the APTEL, that

change in law provision would be limited to

a shortfall in the supply of domestic linkage

coal......

51. It was clari�ed that APRL would be

entitled to relief under the change in law

provision to the extent of shortage in supply

in domestic linkage coal. Thus, we �nd no

merit in the submission raised. We �nd the

88

�ndings of the APTEL to be reasonable,

proper, and unexceptional.”

91.In the said case (i.e. Adani Rajasthan case) also, the

provision with regard to the Change in Law was similar to the

one that falls for consideration in the present case. This Court

observed thus:

“59. The change in policy and in the terms

and conditions prescribed for obtaining any

consents, clearances and permits or the

inclusion of any new terms or conditions for

obtaining such consents, clearances, and

permits are also included. The submission

raised on behalf of appellant that there is no

question seeking bene�t due to change in

foreign law is based on wrong factual

premise. The relief was not claimed on the

basis of change in foreign law. Apart from

that, admission has been relied upon

change in law. The PPA was based on the

domestic law and there was a change in

domestic law. Thus, consequences must

follow. The Government of Rajasthan

entered into a MoU with APRL with respect

to coal linkage in 2008 to provide coal

linkage or coal from other sources.

89

60. We �nd similarity in the present case as

well as the Energy Watchdog. The factual

matrix was similar with the present case.

We �nd that the RERC and the APTEL have

recorded the concurrent �nding on facts. We

�nd no ground to interfere. No substantial

question of law is involved. It was held

in Energy Watchdog, that change in law was

brought about in the NCDP of 2007 by the

decision of 26.7.2013. It is provided in

Article 10.2.1 how the change in law is to be

applied to compensate for the impact.”

92.In the case of Uttar Haryana Bijli Vitran Nigam Limited

(UHBVNL) (supra), this Court observed thus:

“13. A reading of Article 13 as a whole,

therefore, leads to the position that

subject to restitutionary principles

contained in Article 13.2, the adjustment

in monthly tari� payment, in the facts of

the present case, has to be from the date

of the withdrawal of exemption which was

done by administrative orders dated 6-4-

2015 and 16-2-2016. The present case,

therefore, falls within Article 13.4.1(i).

This being the case, it is clear that the

adjustment in monthly tari� payment has

to be e�ected from the date on which the

exemptions given were withdrawn. This

being the case, monthly invoices to be

90

raised by the seller after such change in

tari� are to appropriately re�ect the

changed tari�. On the facts of the present

case, it is clear that the respondents were

entitled to adjustment in their monthly

tari� payment from the date on which the

exemption noti�cations became e�ective.

This being the case, the restitutionary

principle contained in Article 13.2 would

kick in for the simple reason that it is

only after the order dated 4-5-2017

[Adani Power Ltd. v. Uttar Haryana Bijli

Vitran Nigam Ltd., 2017 SCC OnLine

CERC 66] that CERC held that the

respondents were entitled to claim added

costs on account of change in law w.e.f.

1-4-2015. This being the case, it would

be fallacious to say that the respondents

would be claiming this restitutionary

amount on some general principle of

equity outside the PPA. Since it is clear

that this amount of carrying cost is only

relatable to Article 13 of the PPA, we �nd

no reason to interfere with the judgment

of the Appellate Tribunal.

93.This Court speci�cally rejected the contention of the

DISCOMS that the Generator was claiming the restitutionary

amount on some general principle of equity outside the PPA.

This Court held that the amount of carrying cost was relatable

to Article 13 of the PPA.

91

STATUTORY PROVISIONS WITH REGARD TO REGULATORY

MECHANISM

94.We will now consider the relevant provisions of the

Electricity Act.

95.Section 70 of the Electricity Act deals with constitution of

the Central Electricity Authority (“CEA”). The CEA shall consist

of not more than 14 Members (including its Chairperson) of

whom not more than 8 are required to be full-time Members to

be appointed by the Central Government. It will be relevant to

refer to sub-section (5) of Section 70 of the Electricity Act,

which reads thus:

“(5) The Members of the Authority shall

be appointed from amongst persons of

ability, integrity and standing who have

knowledge of, and adequate experience

and capacity in, dealing with problems

relating to engineering, �nance,

commerce, economics or industrial

matters, and at least one Member shall

be appointed from each of the following

categories, namely:—

(a) engineering with specialisation in

design, construction, operation

92

and maintenance of generating

stations;

(b) engineering with specialisation in

transmission and supply of

electricity;

(c) applied research in the �eld of

electricity;

(d) applied economics, accounting,

commerce or �nance.”

96.It can thus clearly be seen that the Members of the CEA

are required to be persons who have adequate experience and

capacity in dealing with problems relating to engineering,

�nance, commerce, economics or industrial matters. Four of the

Members are required to be from the categories as mentioned in

clauses (a) to (d). One of them has to be an engineer with

specialization in design, construction, operation and

maintenance of generating stations. One of them has to be an

engineer with specialization in transmission and supply of

electricity; one has to be a person who is expert in applied

research in the �eld of electricity; one of them has to be an

expert in applied economics, accounting, commerce or �nance.

93

97.Section 73 of the Electricity Act deals with functions and

duties of the CEA. The CEA is required to advise the Central

Government on various matters with regard to generation,

transmission, trading, distribution and utilization of electricity.

It is also required to advise the Central Government on any

matter on which its advice is sought or make recommendation

to that Government on any matter if, in the opinion of the CEA,

the recommendation would help in improving the generation,

transmission, trading, distribution and utilization of electricity.

98.Section 76 of the Electricity Act provides for constitution of

the CERC. The CERC is a �ve member body which consists of a

Chairperson and three other Members, and the Chairperson of

the CEA who shall be the ex o�cio Member. A high-level

Selection Committee consisting of 6 high o�cials selects the

Members of the CERC and the learned APTEL.

99.Section 77 of the Electricity Act provides for quali�cations

for appointment of Members of the CERC. Sub-section (1) of

Section 77 provides that Chairperson and the Members of the

94

CERC shall be persons having adequate knowledge of, or

experience in, or shown capacity in, dealing with, problems

relating to engineering, law, economics, commerce, �nance or

management. It further requires that one person to be

appointed must be having quali�cations and experience in the

�eld of engineering with specialization in generation,

transmission or distribution of electricity. One person to be

appointed has the quali�cations and experience in the �eld of

�nance. Clause (c) of sub-section (1) of Section 77 of the

Electricity Act requires that two persons are required to have

quali�cations and experience in the �eld of economics,

commerce, law or management. The proviso to sub-section (1)

of the Section 77 of the Electricity Act provides that not more

than one Member shall be appointed under the same category

under clause (c).

100.Sub-section (2) of Section 77 of the Electricity Act, which

is a non-obstante clause, empowers the Central Government to

appoint any person as the Chairperson from amongst persons

95

who is, or has been, a Judge of the Supreme Court or the Chief

Justice of a High Court notwithstanding anything contained in

sub-section (1). However, such appointment cannot be made

except after consultation with the Chief Justice of India.

101.Section 79 of the Electricity Act deals with the functions of

the CERC. One of the functions of the CERC under clause (a) of

sub-section (1) of Section 79 is to regulate the tari� of

generating companies owned or controlled by the Central

Government. Clause (b) requires it to regulate the tari� of

generating companies other than those owned or controlled by

the Central Government speci�ed in clause (a), if such

generating companies enter into or otherwise have a composite

scheme for generation and sale of electricity in more than one

State.

102.Similarly, Section 82 of the Electricity Act deals with

constitution of a State Commission. Section 83 of the

Electricity Act permits a Joint Commission to be constituted by

an agreement between two or more Governments of States. It

96

also permits the Central Government to constitute a Joint

Commission in respect of one or more Union Territories, and

one or more Governments of States. Under Section 84, the

persons to be appointed as the Chairperson and the Members of

the State Commission are required to have adequate knowledge

of, and have shown capacity in, dealing with problems relating

to engineering, �nance, commerce, economics, law or

management. Sub-section (2) of Section 84 of the Electricity

Act permits the State Government to appoint any person as the

Chairperson from amongst persons who is, or has been, a

Judge of a High Court. However, such an appointment can be

made only after consultation with the Chief Justice of that High

Court. A high-level Selection Committee under the

Chairmanship of a person who has been a Judge of the High

Court, the Chief Secretary of the concerned State and the

Chairperson of the CEA or the Chairperson of the CERC selects

the Chairperson and the Members of the State Commission.

Analogous to Section 79, Section 86 of the Electricity Act

97

de�nes the functions of the State Commission. Clause (b) of

sub-section (1) of Section 86 of the Electricity Act requires the

State Commission to regulate electricity purchase and

procurement process of distribution licensees including the

price at which electricity shall be procured from the generating

companies or licensees or from other sources through

agreements for purchase of power for distribution and supply

within the State.

103.Section 110 of the Electricity Act provides for

establishment of the Appellate Tribunal. Section 111 of the

Electricity Act provides for appeal to Appellate Tribunal by any

person aggrieved by an order made by an adjudicating o�cer

under the said Act (except under Section 127) or an order made

by the Appropriate Commission. Section 112 deals with

composition of the Appellate Tribunal. It provides that it shall

consist of a Chairperson and three other Members. Section 113

provides for quali�cations for appointment of Chairperson and

Members of Appellate Tribunal. Only a person who is, or has

98

been a Judge of the Supreme Court or the Chief Justice of a

High Court is entitled to be the Chairperson of the Appellate

Tribunal. For being a Member of the Appellate Tribunal,

following three categories have been provided for:

(i)A person is, or has been, or is quali�ed to be, a Judge of

a High Court; or

(ii)A person is, or has been, a Secretary for at least one

year in the Ministry or Department of the Central

Government dealing with economic a�airs or matters or

infrastructure; or

(iii)A person is, or has been, a person of ability and

standing, having adequate knowledge or experience in

dealing with the matters relating to electricity

generation, transmission and distribution and

regulation or economics, commerce, law or

management.

104.It can thus be seen that the CEA, CERC and learned

APTEL are bodies consisting of experts in the �eld.

99

CONSIDERATIONS

105.The issues with regard to SHR and GCV have been

considered by the CERC in its order dated 15

th

November 2018

in the case of GMR Warora Energy Limited v. Maharashtra

State Electricity Distribution Company Limited & Anr

8

. It

will be relevant to reproduce the relevant part of the CERC’s

order dated 15

th

November 2018, which reads thus:

“29. The submissions regarding SHR and

GCV have been considered. The APTEL in its

judgement dated 12.9.2014 in Appeal No.

288 of 2013 (M/s Wardha Power Company

Limited V Reliance Infrastructure Limited &

anr) has ruled that compensation under

Change in Law cannot be correlated with the

price of coal computed from the energy

charge and the technical parameters like the

Heat Rate and gross GCV of coal given in the

bid documents for establishing the coal

requirement. The relevant observations of

APTEL are extracted as under:

“26. The price bid given by the

Seller for �xed and variable charges

both escalable and non-escalable is

based on the Appellant’s perception

of risks and estimates of

expenditure at the time of

8 Petition No.88/MP/2018

100

submitting the bid. The energy

charge as quoted in the bid may

not match with the actual energy

charge corresponding to the actual

landed price of fuel. The seller in its

bid has also not quoted the price of

coal. Therefore, it is not correct to

co-relate the compensation on

account of Change in Law due to

change in cess/excise duty on coal,

to the coal price computed from the

quoted energy charges in the

Financial bid and the heat rate and

Gross Calori�c value of Coal given

in the bidding documents by the

bidder for the purpose of

establishing the coal requirement.

The coal price so calculated will not

be equal to the actual price of coal

and therefore, compensation for

Change in Law computed on such

price of coal will not restore the

economic position of the Seller to

the same level as if such Change in

Law has not occurred.”

30. In the light of the above observations, the

technical parameters such as Heat Rate and

GCV of coal as per the bidding document

cannot be considered for deciding the coal

requirement for the purpose of calculating

the relief under Change in law. Therefore,

the submissions of the Respondent,

MSEDCL to consider the bid parameters are

not acceptable. The Respondent has also

101

relied on MERC order with regard to GCV. As

regards SHR, it was also suggested by MERC

that net SHR as submitted in the bid or SHR

norms speci�ed for new thermal stations as

per MYT Regulations, whichever is superior,

shall be applicable. In our view, the decision

in the said order has been given in the facts

of the case and does not have any binding

e�ect in case of the projects regulated by this

Commission. Moreover, the SHR given in the

bid are under test conditions and may vary

from actual SHR. The Commission after

extensive stakeholders‟ consultation has

speci�ed the SHR norms in the 2014 Tari�

Regulations. Therefore, it would be

appropriate to take SHR speci�ed in the

Regulations as a reference point instead of

other parameters as suggested by MSEDCL.

31. In the present case, the Petitioner has

considered SHR of 2355 kcal/Kwh whereas,

the Respondent MSEDCL has considered the

Design Heat Rate of 2211 kcal/kWh as

submitted in the RFP. It is pertinent to

mention that the CERC norms applicable for

the period 2009-14 and 2014-19 do not

provide the norms for 300 MW units, but

provide for a degradation factor of 6.5% and

4.5% respectively towards Heat Rate over

and above the Design Heat Rate. As the

Design Heat Rate is 2211 kcal/kWh, the

gross Heat Rate works out to 2355 kcal/kWh

(2211 x 1.065)and 2310 kcal/kWh (2211 x

1.045) for the period 2009- 14 and 2014-19

respectively. Accordingly, we direct that the

102

SHR of 2355 kcal/kWh during the period

2009-14 and 2310 kcal/kwh during the

period 2014- 19 or the actual SHR whichever

is lower, shall be considered for calculating

the coal consumption for the purpose of

compensation under change in law. The

Petitioner and the Respondent MSEDCL are

directed to carry out reconciliation on

account of these claims annually.

32. In case of GCV, the Respondent has

submitted that it should be mid value of

GCV band which should be applied on GCV

measured on ‘as billed’ basis. In our view, on

account of the grade slippage of the coal

supplied by CIL, it would not be appropriate

to consider GCV on ‘as billed’ basis. In the

2014 Tari� Regulations of the Commission,

the measurement of GCV has been speci�ed

as on ‘as received’ basis. Therefore, it will be

appropriate if the GCV on ‘as received’ basis

is considered for computation of

compensation for Change in law.”

106.The CERC has referred to the judgment of the learned

APTEL dated 12

th

September 2014 in Appeal No. 288 of 2013 in

the case of M/s Wardha Power Company Limited v. Reliance

Infrastructure Limited & anr. wherein the learned APTEL has

held that it is not correct to co-relate the compensation on

account of Change in Law due to change in cess/excise duty on

103

coal to the coal price computed from the quoted energy charges

in the �nancial bid and the heat rate and GCV of coal given in

the bidding documents by the bidder for the purpose of

establishing the coal requirement. The learned APTEL has held

that the coal price so calculated will not be equal to the actual

price of coal and therefore, compensation for Change in Law

computed on such price of coal will not restore the economic

position of the seller to the same level as if such Change in Law

had not occurred.

107.The CERC has further found that the SHR given in the bid

are under test conditions and may vary from actual SHR. The

CERC has speci�cally observed that after extensive

stakeholders’ consultation, the CERC has speci�ed the SHR

norms in the 2014 Tari� Regulations. It, therefore, found that

it will be appropriate to take SHR speci�ed in the Regulations

as a reference point instead of other parameters as suggested

by MSEDCL.

104

108.The CERC further found that the CERC norms applicable

to the period 2009-14 and 2014-19 do not provide the norms

for 300 MW units, but provide for a degradation factor of 6.5%

and 4.5% respectively towards Heat Rate over and above the

Design Heat Rate. The CERC found that since the Design Heat

Rate was 2211 kcal/kWh, the gross Heat Rate worked out to

2355 kcal/kWh (2211 x 1.065) and 2310 kcal/kWh (2211 x

1.045) for the period 2009-14 and 2014-19 respectively. The

CERC, therefore, directed that the SHR of 2355 kcal/kWh

during the period 2009-14 and 2310 kcal/kwh during the

period 2014-19 or the actual SHR, whichever is lower, shall be

considered for calculating the coal consumption for the purpose

of compensation under the Change in Law.

109.These �ndings of the CERC are a�rmed by the learned

APTEL in its Judgment dated 16

th

July 2021. The learned

APTEL observed thus:

“8.8 We are in agreement with the

observations made by the CERC.

Relegating the Appellant to the

105

contractual remedy under the FSA when

the genesis of the Appellant’s claim is

Change in Law under the PPA would not

be appropriate. It is, however, made

clear that if the Appellant were to receive

any disincentive or compensation from

the coal company on account of short

supply or grade slippage, such

compensation will be adjusted/credited

against the Change in Law compensation

payable by the Respondent, MSEDCL.”

110.The learned APTEL in its judgment dated 14

th

September

2020 in Appeal No.182 of 2019 in the case of Adani Power

Maharashtra Limited (APML) v. Maharashtra State

Electricity Distribution Company Ltd. (impugned in Civil

Appeal No. 684 of 2021) has referred to the order of MERC

dated 7

th

March 2018 in Case No.123 of 2017 ( JSW Energy

Ltd. v. MSEDCL), wherein it held that Auxiliary Consumption

has to be considered as lower of actual or MYT norms for the

purpose of the Change in Law compensation. The learned

APTEL held that in view of its earlier order, the State

Commission, being MERC, ought to have followed the same

approach for SHR in the present case also. It has been found

106

that there is no reason for the MERC to apply two di�erent

principles for Auxiliary Consumption and SHR, when both are

operational parameters and the Commission was dealing with

the same PPA in both cases.

111.The learned APTEL has also referred to the following

observations of the CERC in its order dated 16

th

May 2019 in

the case of GMR Warora Energy Limited v. MSEDCL and

Anr. (Petition No.284/MP/2018):

“52. It is pertinent to mention that

similar submissions of the

Respondent, MSEDCL were

considered by the Commission

in Petition No.88/MP/2018

and it was observed by order

dated 15.11.2018 that SHR

given in the bid is under test

conditions and may vary from

actual SHR. Therefore, it

would only be correct to

take SHR speci�ed in the

tari� Regulations as a

reference point instead of

other parameters suggested

by MSEDCL. It was also held

that SHR as a bidding

document cannot be

considered for deciding the

107

coal requirement for the

purpose of calculating relief

under change in law…”

[emphasis supplied]

112.The learned APTEL thereafter held that the SHR submitted

in the bid was not a bid parameter as per the bidding

guidelines. It concurred with the �ndings of the CERC that the

SHR speci�ed in the Tari� Regulations was as a reference point.

It held that it cannot be used as the basis for computing the

coal shortfall requirement and, thereby, for computation of

Change in Law compensation to be awarded to the generating

company. It held that such linking of Change in Law

compensation to the SHR mentioned in the bid documents

would not restitute the a�ected party to the same economic

position as if the approved Change in Law event had not

occurred.

113.Insofar as the GCV is concerned, the CERC in the case of

GMR Warora Energy Limited (supra) has speci�cally rejected

the contention of the MSEDCL that the GCV should be taken at

108

the mid value of GCV band which should be applied on GCV

measured on ‘as billed’ basis. The CERC held that, on account

of the grade slippage of the coal supplied by CIL, it would not be

appropriate to consider GCV on ‘as billed’ basis. It has been

held that in the 2014 Tari� Regulations of the Commission, the

measurement of GCV has been speci�ed as on ‘as received’

basis. Therefore, it will be appropriate if the GCV on ‘as

received’ basis is considered for computation of compensation

for the Change in Law. This �nding of the CERC is a�rmed by

the learned APTEL.

114.The learned APTEL in the case of Adani Power

Maharashtra Limited (APML) (supra) has also considered the

issue as to whether the reference GCV of domestic coal supplied

by CIL for computing the Change in Law compensation should

be “the middle value of GCV range of assured coal grade in

LoA/FSA/MoU”. The learned APTEL observed that it was a fact

that there is no guidance in the PPAs or in the bidding

Guidelines as to the reference GCV that should be applied in

109

case of the Change in Law claims in Case 1 bid projects where

SHR or GCV is not a bid parameter. It, however, held that the

overarching principle for Change in Law compensation was that

the generating company should not be left with in a worse

economic position. It held that the GCV ‘as received’ should be

the appropriate basis to assess the quantum of shortfall in

domestic coal and calculate the Change in Law compensation

accordingly.

115.It is also relevant to note that the Comptroller and Auditor

General of India (“C&AG” for short), in its Performance Audit

Report on “Fuel Management of Coal Based Power Stations of

NTPC Limited” submitted to MoP, had observed that the ‘quality

assessment of coal has inherent as well as manmade in�rmities

due to heterogeneous nature of coal and sampling errors’. The

C&AG, therefore, recommended to the MoP that there was a

need to appropriately review the methods for energy pricing and

had requested the MoP to coordinate with CERC in light of the

audit �ndings. The MoP, therefore, addressed a communication

110

dated 28

th

June 2017 to the CEA. In the said communication,

the MoP had stated that the NTPC has highlighted the issues of

sampling error on account of change of point of sampling for

measurement of GCV from “as �red” to “as received” basis as

per the 2014 Tari� Regulations, non-homogeneous nature of

samples taken from the wagons, loss of GCV from point of “as

received” to the point of “as �red”, and di�culty with coal

sampling through ‘Augurs’. It further states that the MoP had

also sought views of the CERC on the said issue. The CERC

had, therefore, requested the MoP for consulting CEA in this

regard and accordingly the matter was referred to CEA.

116.The CEA in its communication dated 17

th

October 2017

stated thus:

“The issue has been examined in CEA. After

preliminary discussions with NTPC on the

issue on 05.09.2017, CEA has also taken

views of other specialist agencies in the �eld

of coal such as CIMFR and CPRI in the

meeting held on 21.09.2017.

It is acknowledged that there is a loss of

GCV from point of “as received” to the point

111

of “as �red” inside a power plant mainly due

to following factors:

(i) E�ect of Moisture in GCV of

coal sample taken from Wagon

Top

As stated by C&AG, there are

sampling errors on account of

heterogeneous nature of coal.

This issue was deliberated in

detail with CIMFR and CPRI. Both

CIMFR and CPRI acknowledged

the di�erence in wagon top-

bottom GCV due to heterogeneous

nature of coal, tendency of

moisture to settle at the bottom

and exposure of top layer to

atmosphere.

CEA is of the view that GCV

measurement of wagon top coal

will give comparatively higher GCV

value due to steeling of moisture

at the bottom of the wagon and

loss of moisture from wagon top

during transportation of coal,

however, loss in GCV will vary as

per seasonal variations.

(ii)Loss in GCV during coal storage

inside power plant

CEA is of the view and also

substantiated by many national

112

and international papers that

there is a loss of GCV in the coal

stock where coal is stored inside

the power plant, mainly due to

oxidation and weathering e�ect.

Further, most of the losses in GCV

during long storage of coal takes

place in the initial period of

storage, mostly due to loss in

volatile content.

(iii)Reduction in GCV during

handling inside power plant

C&AG in its Performance Audit

Report has observed that GCV of

coal progressively decreased from

‘as billed’ stage to ‘as �red’ stage.

It is acknowledged that there are

minor unavoidable losses inside

the power plant in handling the

coal starting from unloading point

to the point of bunkering. Loss in

GCV may occur mainly due to

dust suppression measures used

around coal conveyors and

transfer points, loss in volatile

matter during crushing of the coal

etc.

CEA has also examined the views taken by

various state regulators for considering such

loss for the purpose of tari� allowed to

generators. However, as the margin would

113

vary from plant to plant, season to season

and varying coal characteristics, CEA is of

the opinion that a margin of 85-100 kcal/kg

for a non-pit head station may be considered

as a loss of GCV measured at wagon top till

the point of �ring of coal in boiler.”

117. Vide Corrigendum dated 18

th

October 2017, in the last

sentence, after the words wagon top, the words “at unloading

point” were added.

118. The aforesaid advice was given by the CEA after holding

meeting on 21

st

September 2017 with specialist agencies in the

�eld of coal such as CIMFR and CPRI. It has also examined the

views taken by various state regulators for considering such

loss for the purpose of tari� allowed to generators. While

considering at what point of time the margin may be considered

as a loss of GCV, the CEA considered the views of all the

stakeholders. It, thereafter, opined that the loss of GCV should

be measured at wagon top till the point of �ring of coal in boiler.

119.As already discussed herein above, the CEA is an

independent body having Members who are experts in various

114

�elds related to electricity generation, transmission, �nance,

etc.

120.It could thus be seen that two expert bodies i.e. the CERC

and the learned APTEL have concurrently held, after examining

the material on record, that the factors of SHR and GCV should

be considered as per the Regulations or actuals, whichever is

lower. The CERC as well as the State Regulatory bodies, after

extensive consultation with the stakeholders, had speci�ed the

SHR norms in respective Tari� Regulations. In addition, insofar

as GCV is concerned, the CEA has opined that the margin of

85-100 kcal/kg for a non-pit head station may be considered as

a loss of GCV measured at wagon top till the point of �ring of

coal in boiler.

121.In this respect, we may refer to the following observations

of this Court in the case of Reliance Infrastructure Limited v.

State of Maharashtra and others

9

.

“38. MERC is an expert body which is

entrusted with the duty and function to

9 (2019) 3 SCC 352

115

frame regulations, including the terms and

conditions for the determination of tari�.

The Court, while exercising its power of

judicial review, can step in where a case of

manifest unreasonableness or

arbitrariness is made out. Similarly, where

the delegate of the legislature has failed to

follow statutory procedures or to take into

account factors which it is mandated by

the statute to consider or has founded its

determination of tari�s on extraneous

considerations, the Court in the exercise of

its power of judicial review will ensure that

the statute is not breached. However, it is

no part of the function of the Court to

substitute its own determination for a

determination which was made by an

expert body after due consideration of

material circumstances.

39. In Assn. of Industrial Electricity

Users v. State of A.P. [Assn. of Industrial

Electricity Users v. State of A.P., (2002) 3

SCC 711] a three-Judge Bench of this

Court dealt with the �xation of tari�s and

held thus : (SCC p. 717, para 11)

“11. We also agree with the High

Court [S. Bharat Kumar v. State of A.P.,

2000 SCC OnLine AP 565 : (2000) 6

ALD 217] that the judicial review in a

matter with regard to �xation of tari�

has not to be as that of an appellate

authority in exercise of its jurisdiction

116

under Article 226 of the Constitution.

All that the High Court has to be

satis�ed with is that the Commission

has followed the proper procedure and

unless it can be demonstrated that its

decision is on the face of it arbitrary or

illegal or contrary to the Act, the court

will not interfere. Fixing a tari� and

providing for cross-subsidy is essentially

a matter of policy and normally a court

would refrain from interfering with a

policy decision unless the power

exercised is arbitrary or ex facie bad in

law.”

122.As already discussed herein above, various expert bodies

including the CERC and the learned APTEL, after taking into

consideration various relevant factors, have decided the issue

with regard to SHR and GCV. Not only that, but another

expert body i.e. CEA has also advised that GCV value has to be

taken not only on ‘as received’ but on ‘as �red’ basis.

123.Recently, the Constitution Bench of this Court in the case

of Vivek Narayan Sharma v. Union of India

10

has held that

the Courts should be slow in interfering with the decisions

10 2023 SCC OnLine SC 1

117

taken by the experts in the �eld and unless it is found that the

expert bodies have failed to take into consideration the

mandatory statutory provisions or the decisions taken are

based on extraneous considerations or they are ex facie

arbitrary and illegal, it will not be appropriate for this Court to

substitute its views with that of the expert bodies.

124.That leaves us with the third issue as to whether the

MERC was correct in holding that, for the purpose of Change in

Law compensation, shortfall in domestic linkage coal shall be

assessed by considering the coal supply as the maximum of (1)

actual quantum of coal o�ered for o�take by CIL under the

LoA/FSA and (2) the minimum assured quantum in NCDP 2013

for the respective year.

125.Undisputedly, vide the NCDP 2007, insofar as the power

utilities including IPPs/CPPs and Fertilizer Sector are

concerned, the MoC had assured 100% of the quantity as per

the normative requirement of the consumers for supply of coal,

through FSA by CIL at �xed prices to be declared/noti�ed by

118

CIL. The units/power plants, which were yet to be

commissioned but whose coal requirements has already been

assessed and accepted by the MoC and linkage/LoA approved

as well as future commitments, were also to be covered by the

said Policy. Para 5.2 of the NCDP 2007 also provided that in

order to meet the domestic requirement of coal, CIL may have to

import coal as may be required from time to time, if feasible.

The CIL was to adjust its overall price accordingly. There was

an unequivocal assurance given that it will be the responsibility

of CIL/Coal Companies to meet full requirement of coal under

FSAs even by resorting to imports, if necessary.

126.However, in 2013, on account of the limited availability of

coal, the MoC had indicated that CIL may not be in a position to

supply more than 60 to 65% of ACQ. The Union of India,

therefore, realised that PPAs which are already concluded

between the developers and the DISCOMS as a result of

competitive bidding in the last few years based on domestic coal

linkage (LoA) may have to use imported coal to bridge the

119

shortage of domestic coal in order to ful�ll their contractual

obligations.

127.The CCEA considered the issue and decided that the

higher cost of imported coal will be allowed as a pass-through.

This is evident from the communication dated 9

th

May 2013

addressed by the MoP to the CERC.

128.The CERC also considered the issue. It noted that it was

the full responsibility of CIL to meet full requirement of coal

under FSAs even by resorting to import, if necessary. After

referring to the Change in Law clause, the CERC, in its advice

dated 20

th

May 2013, stated that for claiming any bene�t under

Change in Law, the Project Developer would have to move the

appropriate Commission and the appropriate Commissions are

expected to take decisions on the merits of each case including

the claims of the Project Developers for compensation on

account of imported coal. Such decisions were required to be

taken after consultation with the stakeholders.

120

129.The Government of India through MoP, in its Press Note

dated 21

st

June 2013, published the decision of the CCEA

which clearly provided that the higher cost of imported coal was

to be considered for pass-through as per the modalities

suggested by CERC.

130.The MoP, thereafter, addressed a communication dated

31

st

July 2013 to the Secretary, CERC speci�cally pointing out

the decision of the CCEA to the e�ect that the higher cost of

imported coal was to be considered for pass-through as per the

modalities suggested by CERC. The communication states that,

as per the decision of the Government, the higher cost of

import/market based e-auction coal will have to be considered

for being made a pass-through on a case to case basis by

CERC/SERC to the extent of shortfall in the quantity indicated

in the LoA/FSA.

131.The Tari� Policy dated 28

th

January 2016 issued by the

MoP in paragraph 6.1 also speci�cally notes this position and

states that, in case of reduced quantity of domestic coal

121

supplied by CIL vis-à-vis the assured quantity or quantity

indicated in LoA/FSA, the cost of imported/market based e-

auction coal procured for making up the shortfall shall be

considered for being made a pass-through by the Appropriate

Commission.

132.Undisputedly, in the case of Energy Watchdog (supra) as

well as in Adani Rajasthan case (supra) this Court has held

that on account of the Change in Law, the generating

companies were entitled to compensation so as to restore the

party to the same economic position as if such Change in Law

had not occurred. Had the Change in Law not occurred, the

generating companies would have been entitled to the supply as

assured by the CIL/Coal Companies under the FSA.

133.It is contended by the DISCOMS that in the case of

Energy Watchdog (supra), this Court has speci�cally held that

the doctrine of force majeure was not applicable if there was an

unexpected rise in the price of coal and, as such, it will not

absolve the generating companies from performing their part of

122

the contract. It is submitted that when the bidders submitted

their bids, this was a risk they knowingly took. We �nd the

said submission to be without substance. The generators are

not claiming compensation on the basis of rise in price of coal

or on the ground of force majeure. Their claims, in fact, are on

the basis of the Change in Law, which this Court, in the case of

Energy Watchdog (supra) as well as in Adani Rajasthan case

(supra), has upheld on the ground of Change in Law.

134.The contention of the DISCOMS that the Adani

Rajasthan case (supra) is not applicable to the facts of the

present case inasmuch as in Adani Rajasthan case (supra),

the State of Rajasthan had assured 100% coal supply and that

it was not a case of FSA, is, in our considered view, without

substance. In the present case also, the NCDP 2007 had

assured 100% fuel/coal supply of the normative value.

135.The restitutionary principle has been stated by this Court

in the case of Uttar Haryana Bijli Vitran Nigam Limited

(UHBVNL) (supra) thus:

123

“10. Article 13.2 is an in-built

restitutionary principle which

compensates the party a�ected by such

change in law and which must restore,

through monthly tari� payments, the

a�ected party to the same economic

position as if such change in law has not

occurred. This would mean that by this

clause a �ction is created, and the party

has to be put in the same economic

position as if such change in law has not

occurred i.e. the party must be given the

bene�t of restitution as understood in

civil law. ………….”

136.Undisputedly, the claim of APML stands on the basis of

the Change in Law. The DISCOMS, which are instrumentalities

of the State, cannot be expected to argue contrary to the stand

of the Government, which clearly provides that the generators

would be entitled to pass-through for the coal required to be

imported or purchased from the open market on the ground of

Change in Law.

137.Shri M.G. Ramachandran, learned Senior Counsel has

also made a submission that though the Change in Law event is

dated 31

st

July 2013, the learned APTEL has erred in giving

124

e�ect to the same from 1

st

April 2013. In this respect, it is to be

noted that the Change in Law has been made applicable to the

remaining four years of the 12

th

Plan for power plants. The

MERC, in the case of APML, as well as the CERC, in the case of

GMR, has given e�ect to the Change in Law for the last four

�nancial years beginning from the Financial Year 2013-2014.

The �nancial year begins from 1

st

of April of every year. Apart

from that, from the perusal of the orders passed by the learned

APTEL in both the matters, it is clear that no such challenge

was made before the learned APTEL, and, even in the present

appeals, there is ground to this e�ect in the Memo of Appeals.

Only oral submissions have been sought to be made in that

regard.

138.In view of the concurrent orders of the authorities with

regard to the date on which the Change in Law compensation is

to be given, we see no reason to entertain such a plea, which

does not have a foundation in the pleadings.

125

139.Another contention raised on behalf of the DISCOMS is

that if the generators are permitted to claim compensation on

the basis of actual SHR or the SHR as per the Regulations,

whichever is lower, it will permit them to take advantage of their

ine�ciency. It is submitted that lesser the SHR, greater the

e�ciency of the machine and, therefore, higher the generation

of electricity. Per contra, when the machine is ine�cient, the

SHR is higher and the electricity generation is lower. The SHR

is not only dependent on the e�ciency of the machine but on

various other factors. One of the other factors is the PLF. In

this respect, it will be relevant to refer to the statutory advice

issued by the CERC on 20

th

May 2013, the relevant part of

which has already been reproduced hereinabove. It clearly

states that for want of adequate coal supply by CIL/Coal

Companies, the PLF of the generating stations across the

country has been severely a�ected. As such, the contention in

that regard, in our considered view, is without substance.

126

140.Apart from that, it appears that various DISCOMS are

taking self-contradictory stands. In Petition No. 97 of 2017

between M/s Adani Power Limited v. Uttar Haryana Bijli

Vitran Nigam Ltd. & Anr. , the DISCOMS have �led an

a�davit stating thus:

“a. While deciding the relief on account of

Change in Law under Article 13 of the PPA

may be pleased to consider improved

e�ciency parameters in line with CERC

Tari� Regulations such that the impact on

consumers of the Respondents in minimal

in nature.

b. Any relief (if granted), may be passed after

considering the following signi�cant

observations:

(i) The actual impact of the said period

should be calculated on the basis of

various factors namely the quantum

of requirement on normative

procedures such as the following:

i. Station Heat Rate shall be

considered after ascertaining

actual design heat rate and

margin as per CERC

regulations from time to

time.

127

ii. Similarly, Auxiliary

Consumption shall be

considered as per CERC

regulations.

iii. GCV of alternate coal shall

be as certi�ed by Third Party

Sampling Agency for which

the Hon’ble Commission

should provide appropriate

the guideline.

iv. The targeted PLF;

v. The accurate date of actual coal

utilized by the Petitioner on a

monthly and yearly basis;

vi. The quantity of coal o�ered by

the MCL which was rejected or

not taken by the Petitioner;

vii. The quantum of actual of

electricity generated by the

Petitioner

Thus, it is submitted that the

Petitioner’s claim for relief in

this regard requires to be

computed in a categorical and

systematic manner taking the

above parameters into

consideration. The Petitioner’s

computation as stated in its

petition is therefore liable to be

rejected as it is general and

vague in nature.

(ii) Further, the Petitioner has indicated

the impact limited to the past period

128

only. However, the Respondents

humbly request the Hon’ble

Commission to only approve such

claims for the past period, after

considering the above along with a

formula for the future period.”

[emphasis supplied]

141.It can thus be seen that the DISCOM-UHBVNL has itself

stated that improved e�ciency parameters in line with CERC

Tari� Regulations should be considered for deciding the relief

on account of Change in Law, such that the impact on

consumers of the respondents is minimal in nature. It has also

requested for any relief, if granted, to take into consideration

the SHR after ascertaining actual design heat rate and margin

as per CERC regulations from time to time. Similarly, it has

also requested that Auxiliary Consumption be considered as per

the CERC Regulations. Insofar as the GCV of alternate coal is

concerned, it has further stated that it has to be certi�ed by

Third Party Sampling Agency.

129

142.It is not in dispute that the SHR is required to be audited

continuously and the GCV has to be certi�ed by a Third Party

Sampling Agency.

143.It is further pertinent to note that the MERC itself in its

order dated 7

th

March 2018 in Case No.123 of 2017 ( JSW v.

MSEDCL), has taken a totally contradictory stand. It will be

relevant to refer to paragraph 19.11 of the said order dated 7

th

March 2013, which reads thus:

“19.11 In view of the above, �nancial

impact of Change in Law on the

auxiliary consumption to restore

the generator to the same

economic position as if such

Change in Law has not occurred is

allowed. The Change in Law

shall be applicable on auxiliary

consumption of the Unit as per

the Norms laid down by the

Commission or actual,

whichever is less since the

tari� of the project is based on

Competitive Bidding the

auxiliary power consumption

considered is not known.

However this auxiliary

consumption should be at a

normative value corresponding

130

to Scheduled generation only.

Moreover, this Change in Law

with respect to auxiliary

consumption shall not include

power consumption for sta�

colonies of the generating

station.”

[emphasis supplied]

144.It is, thus, di�cult to appreciate as to how the MERC, in

one case, has taken a view that Change in Law on the Auxiliary

Consumption has to be as per the Norms laid down by the

Commission or actual, whichever is less, when it has rejected

the same in the case of APML in the order dated 7

th

March

2018

11

.

145.We may gainfully refer to the stand taken by the Union of

India in the case of Energy Watchdog (supra), which reads

thus:

“15. The learned Attorney General

appearing on behalf of the Union of India,

submitted before us that he was not

interested in the ultimate outcome of the

11 Passed in Case Nos. 189 of 2013 and 140 of 2014

131

appeals before us. He was only

appearing in order to apprise us that

the electricity sector, having been

privatised, has largely ful�lled the

object sought to be achieved by the

2003 Act, which is that electricity

generation, being delicensed, should

result in production of far greater

electricity than was earlier produced.

He urged us not to disturb the delicate

balance sought to be achieved by the

Act i.e. that producers or generators

of electricity, in order that they set up

power plants, be entitled to a

reasonable margin of pro�t and a

reasonable return on their capital, so

that they are induced to set up more

and more power plants. This must be

consistent with competitiveness among

them, which then translates itself into

reasonable tari�s that are payable by

consumers of electricity. For this

purpose, he relied strongly upon Section

3 of the Electricity Act, which states that

the Central Government, shall from time

to time, prepare a National Electricity

Policy and a tari� policy in consultation

with the State Governments, and the

authority for development of the power

system, based on optimal utilisation of

natural resources. According to him,

the National Electricity Policy and

Tari� Policy that are issued from time

132

to time, being statutory in nature, are

binding on all concerned. This is, in

fact, further recognised by Section 61(i)

by which the appropriate Commission, in

specifying terms and conditions for

determination of tari�s, shall be guided

by the National Electricity Policy and

Tari� Policy. The Central Government's

role can further be seen even in

Section 63, where guidelines that are

binding on all are issued by the

Central Government in cases where

there is a transparent process of

bidding.

16. Further, according to the learned

Attorney General, Section 79(4) also

points in the same direction, stating that,

in discharge of its functions, the Central

Commission shall be guided by the

National Electricity Policy, National

Electricity Plan, and tari� policy

published under Section 3. He also

referred us to the Cabinet Committee

for Economic A�airs recognising the

overall shortfall in manufacture of

domestic coal and the new coal

distribution policy issued in July

2013 pursuant to the Cabinet

Committee which, according to him,

are in the nature of binding directions

making it clear that as generators of

electricity, who depend upon

133

indigenous coal, have been given less

coal than was anticipated, should be

allowed either to import the coal

themselves, or purchase imported coal

from Coal India Ltd., with the

di�erence in price being passed

through to them. He further referred to

and relied upon the revised tari� policy of

28-1-2016 for the same purpose.”

[emphasis supplied]

146.The submissions made by the learned Attorney General

have to be construed in reference to the purpose for which the

Electricity Act came to be enacted. Prior to the Electricity Act

coming into e�ect, matters with regard to generation,

transmission, distribution and supply of electricity were

governed by three enactments, viz., the Indian Electricity Act,

1910, the Electricity (Supply) Act, 1948 and the Electricity

Regulatory Commission Act, 1998. The Electricity (Supply) Act,

1948 mandated the creation of a State Electricity Board.

However, it was found that over a period of time, the

performance of the said Electricity Boards had deteriorated on

account of various factors. As such, it was found necessary to

134

enact a new legislation to meet various challenges. The

statement of objects and reasons would reveal that one of the

main features for enactment of the Electricity Act was

delicensing of generation and freely permitting captive

generation. As such, the learned Attorney General, in the case

of Energy Watchdog (supra), stated that the electricity sector,

having been privatized, had largely ful�lled the object sought to

be achieved by the Electricity Act. After the enactment of the

Electricity Act, delicensed electricity generation resulted in

production of far greater electricity than was earlier produced.

The learned Attorney General had further urged the Court not

to disturb the delicate balance sought to be achieved by the

Electricity Act, i.e. that producers or generators of electricity, in

order that they set up power plants, be entitled to a reasonable

margin of pro�t and a reasonable return on their capital, so

that they are induced to set up more and more power plants.

147.It is further to be noted that, though it was sought to be

contended in the case of Energy Watchdog (supra) that in a

135

case under Section 63 of the Electricity Act, the Commission

was only to adopt a tari� as determined through a transparent

process of bidding, this Court rejected the said contention. It

held that, in fact, Sections 62 and 63 of the Electricity Act deal

with ‘determination’ of tari�, which is part of ‘regulating’ tari�.

It further held in a situation where the guidelines issued by the

Central Government under Section 63 cover the situation, the

Central Commission is bound by those guidelines and must

exercise its regulatory functions.

148.It would be relevant to refer to clause 4.7 of the guidelines

issued by the Union of India, which have been held to be

binding in the case of Energy Watchdog (supra), which reads

thus:

“Clause 4.7. (amended)

Any change in law impacting cost or

revenue from the business of selling

electricity to the procurer with respect to

the law applicable on the date which is 7

days before the last date for RFP bid

submission shall be adjusted separately. In

case of any dispute regarding the impact of

136

any change in law, the decision of the

appropriate Commission shall apply.”

149.The judgment of this Court in the case of Energy

Watchdog (supra) has been approved by a three Judge Bench

of this Court in Adani Rajasthan case (supra).

150.In spite of this legal position and the stand taken by the

Union of India, the DISCOMS are taking a stand which is

contrary to the stand of the Union of India. In Energy

Watchdog (supra), it was also sought to be urged by DISCOMS

that even on account of Change in Law, adjustments would not

be permissible, which contention was outrightly rejected. We

have come across a number of matters wherein concurrent

orders passed by the Regulatory Body and the Appellate Forum

are assailed. Such a litigation would, in fact, e�ace the purpose

of the Electricity Act. As already discussed herein above, one of

the major reasons for the enactment of the Electricity Act was

the deterioration in performance of the State Electricity Boards.

137

151.In that view of the matter, we �nd that the stand taken by

the DISCOMS that, since the loss being sustained by the

generating companies is on account of non-ful�llment of

obligation by CIL/Coal Companies, they should be relegated to

the remedy available to them in law against the CIL/Coal

Companies, is totally unreasonable. The claim is based on

change of NCDP 2007 by NCDP 2013, which, undisputedly, is

covered by the term ‘Change in Law’.

152.Recently, this Court, in the case of Central Warehousing

Corporation v. Adani Ports Special Economic Zone Limited

(APSEZL) and others

12

, has deprecated the practice of di�erent

instrumentalities of the State taking contradictory/di�erent

positions/stands on the same issue.

153.In the present case, the learned APTEL has also held that

SHR and GCV has to be taken into consideration as per the

‘actual’ or the Tari� Regulations, whichever is lower and as

12 2022 SCC OnLine SC 1398

138

such, balanced the interests of generators as well as

consumers.

154.That leaves us to deal with the additional point raised in

the case of GMR (i.e. Civil Appeal No.6927 of 2021).

155.The CERC, apart from its �nding on SHR and GCV, has

also directed late payment surcharge to be paid. The same has

been a�rmed by the learned APTEL. The CERC as well as the

learned APTEL, on the interpretation of Articles 8.3.5 and 8.8.3

of the PPA, have concurrently found that the procurer had

delayed the payment by not making the payment within the due

date and, as such, GMR was entitled to late payment surcharge.

We �nd no reason to interfere with the said concurrent �ndings

of fact.

156.We, therefore, �nd no merit in the appeals. The appeals

are dismissed. There shall be no order as to costs. Pending

application, if any, shall stand disposed of.

…….........................J.

[B.R. GAVAI]

139

…….........................J.

[VIKRAM NATH]

NEW DELHI;

MARCH 03, 2023

140

Reference cases

Description

Legal Notes

Add a Note....

Advance Search Tool

💡 How to Get the Best Legal Answers:

1. Keep it simple: Frame your question in plain language.

2. Add scope: Tag @ a court, judge, year, or act section for accurate results.

3. Attach files: Upload a PDF only if you are using a private document.

🌍 Ask in your language: English • Hindi • Assamese • Bangla • Gujarati • Kannada • Malayalam • Marathi • Odia • Punjabi • Tamil • Telugu • Urdu


💡 New Advocate? Don’t worry! Working without senior support today? Turn on Client Advisory to get instant legal strategies, practical angles, and precedent-backed options for your client.

Add research context Type to filter