1
A.F.R.
Court No.39
Case :- WRIT - C No. - 10282 of 2017
Petitioner :- Manpal Singh
Respondent :- State Of U.P. & 2 Others
Counsel for Petitioner :- Anshul Kumar Singhal,Manish Goyal
Counsel for Respondent :- C.S.C.,Anjali Upadhya
Hon'ble Dilip Gupta, J.
Hon'ble Siddhartha Varma, J.
A notification dated 24 July 2008 under Section 4(1) read with
Section 17 of the Land Acquisition Act, 1894
1
was issued for acquisition
of 105.5600 hectares of land situated in Village-Chipiyana Khurd alias
Tigri, Pargana & Tehsil Dadri for planned industrial development in
District Gautam Budh Nagar through Greater Noida Industrial
Development Authority
2
. This was followed by a declaration made on 29
January 2009 under Section 6 of the Act. The award was also made on 27
August 2011 by the Additional District Magistrate (Land Acquisition),
Greater Noida
3
. This petition has been filed for a direction upon the
respondents to declare that the acquisition proceedings have lapsed by
virtue of operation of Section 11-A of the Act. Further reliefs that have
been sought are for quashing the award dated 27 August 2011 made by
the ADM and for not only restoring the name of the petitioner in the
revenue records but also restraining the State respondents from
dispossessing the petitioner from the land admeasuring 100 sq. yards
1the Act
2Greater Noida
3the ADM
Neutralr/itationrNo(rJrqwLDbx…/b9VDDwJ;%
2
situated in Khasra Plot No.57, Village-Chipiyana Khurd, Tehsil Dadri,
District Gautam Budh Nagar.
The petitioner claims to have purchased 100 sq. yards of land
situated in Khasra Plot No.57 from Leeladhar by a registered sale deed
dated 17 January 2006. It is stated that the name of the petitioner was
entered in the revenue records on 30 January 2014. It has further been
stated that the total area of Khasra Plot No.57 was 0.7305 hectares, out of
which 0.4770 hectares was acquired by the State in 2002-03 and the
remaining area of Khasra Plot No.57 was subsequently acquired by
issuance of the notification dated 24 July 2008 under Section 4(1) of the
Act. The petitioner claims that the aforesaid acquisition proceedings
initiated on 24 July 2008 were assailed by certain tenure-holders in Writ
Petition No.41017 of 2011 which was decided with a number of Writ
Petitions by a Full Bench of this Court in Gajraj & Ors. Vs. State of
U.P. & Ors.
4
. The said petition was marked in 'Group 27'. The
acquisition was upheld by the Full Bench and the petitions were disposed
of with certain directions contained in paragraph 482 of the judgment
which is reproduced :
“3. All other writ petitions except as mentioned above
at (1) and (2) are disposed of with following
directions:
(a) The petitioners shall be entitled for payment
of additional compensation to the extent of
same ratio (i.e. 64.70%) as paid for village
Patwari in addition to the compensation
received by them under 1997 Rules/award
which payment shall be ensured by the
Authority at an early date. It may be open for
Authority to take a decision as to what
42011 (11) ADJ 1
3
proportion of additional compensation be asked
to be paid by allottees. Those petitioners who
have not yet been paid compensation may be
paid the compensation as well as additional
compensation as ordered above. The payment
of additional compensation shall be without any
prejudice to rights of land owners under section
18 of the Act, if any.
(b) All the petitioners shall be entitled for
allotment of developed Abadi plot to the extent
of 10% of their acquired land subject to
maximum of 2500 square meters. We however,
leave it open to the Authority in cases where
allotment of abadi plot to the extent of 6% or
8% have already been made either to make
allotment of the balance of the area or may
compensate the land owners by payment of the
amount equivalent to balance area as per
average rate of allotment made of developed
residential plots.
4.The Authority may also take a decision as to
whether benefit of additional compensation and
allotment of abadi plot to the extent of 10% be also
given to ;
(a) those land holders whose earlier writ petition
challenging the notifications have been
dismissed upholding the notifications; and
(b) those land holders who have not come to the
Court, relating to the notifications which are
subject matter of challenge in writ petitions
mentioned at direction No.3.”
The petitioner asserts that he had not filed any writ petition to
challenge the said acquisition proceedings and the petitioner acquired
knowledge of the award only on 24 November 2016 when some
documents were filed in Original Suit No.101 of 2014 that had been
instituted by Harpyari against the petitioner in the Court of Civil Judge
(Senior Division), Ghaziabad for grant of mandatory injunction. It is
4
stated that an affidavit was filed in said Original Suit on 10 January 2017
that the land had been acquired in the year 2009 and the name of the
petitioner had been expunged. Subsequently, the petitioner obtained
copies of the records on 20 January 2017 and found that the entries dated
30 January 2014 and 23 May 2014 made in favour of the petitioner in the
revenue records had been expunged on 30 May 2015 and 28 December
2016. It is, therefore, asserted that the petitioner came to know only on 24
November 2016 that the award had been made.
Sri Manish Goyal, learned counsel appearing for the petitioner has
placed reliance upon Section 11-A of the Act and has submitted that since
the award was not made within a period of two years from the date of
publication of the declaration under Section 6 of the Act, the entire
acquisition proceedings lapse. In support of his contention, learned
counsel has placed reliance upon the judgments of the Supreme Court in
Laxmi Devi Vs. State of Bihar & Ors.
5
, Laxman Pandya & Ors. Vs.
State of U.P. & Ors.
6
and Kunwar Pal Singh (dead) through LRs Vs.
State of U.P. & Ors.
7
and also on Division Bench judgments of this
Court in Ram Jiyawan Vs. State of U.P. & Ors.
8
and Veer Singh &
Ors. Vs. State of U.P. & Ors.
9
Learned Standing Counsel appearing for the State respondents and
Sri R.P. Singh, learned counsel appearing for Greater Noida have,
however, submitted that since the provisions of sub-sections (1) and (4)
5(2015) 10 SCC 241
6(2011) 14 SCC 94
7(2007) 5 SCC 85
8AIR 1994 Allahabad 38
9Writ-C No.64718 of 2008, decided on 4 March 2016
5
of Section 17 were made applicable, the acquisition proceedings would
not lapse under Section 11-A of the Act and in support of this contention,
learned counsel for Greater Noida has placed reliance upon the decisions
of the Supreme Court in Satendra Prasad Jain & Ors. Vs. State of U.P.
& Ors.
10
, Awadh Bihari Yadav & Ors. Vs. State of Bihar & Ors.
11
and
New Okhla Industrial Development Authority Vs. Harkishan (dead)
through LRs. & Ors.
12
.
We have considered the submissions advanced by learned counsel
for the parties.
In order to appreciate the contentions advanced by learned counsel
for the parties, it would be appropriate to refer to the relevant provisions
of Sections 4(1), 6, 11(1), 11-A and 17 of the Act. They are reproduced
below:
“4. Publication of preliminary notification and
powers of officers thereupon: (1) Whenever it
appears to the
appropriate Government that land in
any locality
is needed or is likely to be needed for any
public purpose
or for a company, a notification to that
effect shall be published in the Official Gazette
and in
two daily newspapers circulating in that locality of
which at least one shall be in the regional language
and the Collector shall cause public notice of the
substance of such notification to be given at
convenient places in the said locality the last of the
dates of such publication and the giving of such public
notice, being hereinafter referred to as the date of
publication of the notification.
…..........................
6. Declaration that land is required for a public
purpose: (1) Subject to the provisions of Part VII of
this Act, when the appropriate Government is satisfied
after considering the report, if any, made under section
5A, sub-section (2), that any particular land is needed
10(1993) 4 SCC 369
11(1995) 6 SCC 31
12Civil Appeal No.5170 of 2010, decided on 27 January 2017
6
for a public purpose, or for a Company, a declaration
shall be made to that effect under the signature of a
Secretary to such Government or of some officer duly
authorised to certify its orders and different
declarations may be made from time to time in respect
of different parcels of any land covered by the same
notification under section 4, sub-section (1),
irrespective of whether one report or different reports
has or have been made wherever required under
section 5A, sub-section (2)
….............
(2) Every declaration shall be published in the Official
Gazette and in two daily newspapers circulating in the
locality in which the land is situate of which at least
one shall be in the regional language, and the
Collector shall cause public notice of the substance of
such declaration to be given at convenient places in
the said locality the last of the date of such publication
and the giving of such public notice, being hereinafter
referred to as the date of publication of the
declaration, and such declaration shall state the district
or other territorial division in which the land is situate,
the purpose for which it is needed, its approximate
area, and where a plan shall have been made of the
land, the place where such plan may be inspected.
(3) The said declaration shall be conclusive evidence
that the land is needed for a public purpose or for a
Company, as the case may be; and, after making such
declaration the appropriate Government may acquire
the land in a manner hereinafter appearing.
…....................
11. Enquiry and award by Collector. (1) On the day
so fixed, or on any of other day to which the enquiry
has been adjourned, the Collector shall proceed to
enquire into the objections, if any, which any person
interested has stated pursuant to a notice given under
section 9 to the measurements made under section 8,
and into the value of the land at the date of the
publication of the notification under section 4, sub-
section (1), and into the respective interests of the
persons claiming the compensation and shall make an
award under his hand of
(i) the true are of the land;
(ii) the compensation which in his opinion should be
allowed for the land; and
(iii) the apportionment of the said compensation
among all the persons known or believed to be
interested in the land, of whom, or of whose claims, he
7
has information, whether or not they have respectively
appeared before him:
Provided that no award shall be made by the
Collector under this section without the previous
approval of the appropriate Government or of such
officer as the appropriate Government may authorise
in this behalf:
Provided further that it shall be competent to the
appropriate Government to direct that the Collector
may make such award without such approval in such
class of cases as the appropriate Government may
specify in this behalf.
…..............
11A Period within which an award shall be made.
(1) The Collector shall make an award under section
11 within a period of two years from the date of the
publication of the declaration and if no award is made
within that period, the entire proceedings for the
acquisition of the land shall lapse:
Provided that in a case where the said
declaration has been published before the
commencement of the Land Acquisition (Amendment)
Act, 1984, the award shall be made within a period of
two years from such commencement.
Explanation. In computing the period of two years
referred to in this section, the period during which any
action or proceeding to be taken in pursuance of the
said declaration is stayed by an order of a Court shall
be excluded.
…..............
17.Special powers in cases of urgency.
(1) In cases of urgency, whenever the
appropriate
Government so directs, the Collector, though no such
award has been made, may, on the expiration of
fifteen days from the publication of the notice
mentioned in section 9, sub-section (1),
take
possession of any land needed for a public purpose.
Such land shall thereupon
vest absolutely in the
Government, free from all encumbrances.
….........
(4)In the case of any land to which, in the opinion
of the
appropriate Government, the provisions of sub-
section (1) or sub-section (2) are applicable, the
appropriate Government may direct that the provisions
of section 5A shall not apply, and, if it does so direct,
a declaration may be made under section 6 in respect
of the land at any time
after the date of the publication
of the notification under section 4, sub-section (1).”
8
The award made under Section 11 of the Act gives reference of the
various dates relating to acquisition proceedings and they are as follows:
24 July 2008Date of Section 4(1)/17 notification
24 July 2008Date of publication in Official Gazette
8 August 2008Date of publication in two newspapers
28 July 2008Date of causing public notice of the substance of
the notification at convenient places in the locality
29 January 2009Date of publication of Section 6 declaration
29 January 2009Date of publication in Official Gazette
20 February 2009Date of publication in two newspapers
18 February 2009Date of causing public notice of the substance of
the notification at convenient places in the locality
7 March 2009Date of hearing under Section 9
9 March 2009Date of taking possession
27 August 2011Date of award under Section 11
Section 11-A of the Act provides that the Collector shall make the
award under Section 11 within a period of two years from the date of
publication of the declaration and if no award is made within that period,
the entire proceedings for the acquisition of the land shall lapse. The
dates referred to above would indicate that the date of publication of the
declaration under Section 6 of the Act is 20 February 2009 since it is the
last date of the publication and the giving of the public notice. The award
was made on 27 August 2011. It is beyond two year years from the date
of the declaration under Section 6 of the Act.
The issue that arises for consideration is whether the acquisition
proceedings would lapse when the provisions of Section 17 of the Act are
made applicable but before that it needs to be remembered that the
petitioner purchased land from Leeladhar on 17 January 2006 and the
9
name of the petitioner was mutated in the revenue records only on 30
January 2014. It was, however, subsequently expunged on 30 May 2015
and the name of Greater Noida was entered.
In the instant case, the fact reveals that the possession was taken by
the State on 9 March 2009. Possession can be taken under Section 16 of
the Act only when the Collector has made the award under Section 11 of
the Act. Section 17(1) of the Act provides that in cases of urgency,
whenever the
appropriate Government so directs, the Collector, though no
such award has been made, may, on the expiration of fifteen days from
the publication of the notice mentioned in Section 9, sub-section (1),
take
possession of any land needed for a public purpose and such land shall
thereupon
vest absolutely in the
Government free from all encumbrances.
In the instant case, possession could be taken because the provisions of
sub-sections (1) and (4) of Section 17 were made applicable. After the
notice under Section 9(1) of the Act was issued, objections were heard on
7 March 2009 and possession of 105.5600 hectares of land was taken on
9 March 2009. On such possession having been taken, the land vested in
the State free from all encumbrances.
It has, therefore, to be considered whether in such circumstances,
the acquisition proceedings would lapse if the award was made beyond
two years from the date of publication of the declaration under Section 6
of the Act.
10
This issue was examined by the Supreme Court in Satendra
Prasad Jain. After referring to the provisions of Section 11-A and
Section 17 of the Act, the Supreme Court observed as follows:
“15. Ordinarily, the Government can take possession
of the land proposed to be acquired only after an
award of compensation in respect thereof has been
made under Section 11. Upon the taking of possession
the land vests in the Government that is to say, the
owner of the land loses to the Government the title to
it. This is what Section 16 states. The provisions of
Section 11-A are intended to benefit the land owner
and ensure that the award is made within a period of
two years from the date of Section 6 declaration. In
the ordinary case, therefore, when Government fails to
make an award within two years of the declaration
under Section 6, the land has still not vested in the
Government and its title remains with the owner, the
acquisition proceedings are still pending and, by virtue
of the provisions of Section 11-A, lapse. When
Section 17(1) is applied by reason of urgency,
Government takes possession of the land prior to the
making of the award under Section 11 and thereupon
the owner is divested of the title to the land which is
vested in the Government. Section 17(1) states so in
unmistakable terms. Clearly, Section 11-A can have
no application to cases of acquisition under Section 17
because the lands have already vested in the
Government and there is no provision in the said Act
by which land statutorily vested in the Government
can revert to the owner.
16. Further, Section 17(3-A) postulates that the owner
will be offered an amount equivalent to 80 per cent of
the estimated compensation for the land before the
Government takes possession of it under Section
17(1). Section 11-A cannot be so construed as to leave
the Government holding title to the land without the
obligation to determine compensation, make an award
and pay to the owner the difference between the
amount of the award and the amount of 80 per cent of
the estimated compensation.”
11
This decision was relied upon by the Supreme Court in Awadh
Bihari Yadav and it was held :
10. …........... It was contended that in view of Section
11-A of the Act the entire land acquisition
proceedings lapsed as no award under Section 11 had
been made within 2 years from the date of
commencement of the Land Acquisition Amendment
Act, 1984. We are of the view that the above plea has
no force. In this case, the Government had taken
possession of the land in question under Section 17(1)
of the Act. It is not open to the Government to
withdraw from the acquisition (Section 48 of the Act).
In such a case, Section 11-A of the Act is not attracted
and the acquisition proceedings would not lapse, even
if it is assumed that no award was made within the
period prescribed by Section 11-A of the Act.
….............”
The same observations were made by the Supreme Court in Pratap
and Anr. Vs. State of Rajasthan & Ors.
13
and Allahabad Development
Authority Vs. Nasiruzzaman & Ors.
14
.
The Supreme Court again examined this issue in Banda
Development Authority, Banda Vs. Moti Lal Agarwal & Ors.
15
. The
Allahabad High Court had allowed the writ petition that had been filed to
assail the acquisition proceedings on the ground that the award had not
been made within the time prescribed under Section 11-A of the Act. It
needs to be noticed that the provisions of sub-sections (1) and (4) of
Section 17 had been applied. The Supreme Court placing reliance upon
its earlier decisions held that since the provisions of Section 17 of the Act
had been applied and possession had been handed over to the
Development Authority on 30 June 2001, the view taken by the High
13(1996) 3 SCC 1
14(1996) 6 SCC 424
15(2011) 5 SCC 394
12
Court that acquisition provisions had lapsed due to non-compliance of
Section 11-A of the Act, could not be sustained.
The decisions in Satendra Prasad Jain and Awadh Bihari Yadav
have subsequently been followed by the Supreme Court in New Okhla
Industrial Development Authority and it has been held :
“12. There is yet another serious infirmity in the
impugned judgment. In the instant case, the land was
acquired by invoking urgency clause under Section 17
of the Act and dispensing with the requirement of
filing the objections under Section 5A of the Act. This
action on the part of the Government was upheld by
this Court in the first round of litigation. Once
possession is taken under Section 17(1) of the Act,
Section 11-A is not even attracted and, therefore,
acquisition proceedings would not lapse on failure to
make award within the period prescribed therein. This
is so held in Satendra Prasad Jain & Ors. v. State of
Uttar Pradesh & Ors., which view is affirmed in
Awadh Bihari Yadav & Ors. v. State of Bihar & Ors.”
In view of the aforesaid decisions, it has to be held that once
possession of the land admeasuring 105.5600 hectares including that of
Khasra Plot No.57 was taken on 9 March 2009, it would vest in the State
free from all encumbrances and the acquisition proceedings would not
lapse even if the award was not made within two years from the date of
publication of the declaration under Section 6 of the Act.
It also needs to be noted that the acquisition proceedings that had
been initiated by issuance of the notification dated 24 July 2008 under
Section 4(1) of the Act were also considered by the Full Bench in Gajraj
in 'Group 27'. Issue no.10 in Gajraj was whether acquisition under
challenge had lapsed under Section 11-A of the Act since the award was
13
not made within two years from the date of publication of the declaration
under Section 6 of the Act. In paragraph 376, the Full Bench observed as
follows:
“376.We have considered the submission of the
learned counsel for the parties. In Satendra Prasad
Jain's case the issue was considered and it was held by
the Apex Court that when Section 17 sub Section (1)
is applied by reason of urgency, the Government takes
possession of the land prior to the making of the
award under Section 11 and thereupon the owner is
divested of the title to the land which is vested in the
Government as laid down in paragraph 15. The said
view was reiterated by the Apex Court in Awadh
Bihari Yadav and others Vs. State of Bihar and others,
1995, 6 S.C.C. Page 31. The recent judgment of
Banda Development Authority (supra) has also
occasion to consider the said issue, relying on the
decision of Satendra Prasad Jain. The argument on the
basis of Section 11-A was repelled. In the present
bunch of cases the State Government has invoked
urgency clause under Section 17(1) and possession has
been taken in all the cases exercising urgency power.
The ratio laid down by Satendra Prasad Jain's case is
fully attracted and the submission made by the learned
counsel for the petitioners on the basis of Section 11-
A can not be accepted.”
Learned counsel for the petitioner has, however, placed reliance on
the decision of the Supreme Court in Laxmi Devi. The notification under
Section 4(1) of the Act was issued on 24 July 2008 and the provisions of
Section 4/17 were also resorted to. The award under Section 11-A of the
Act was not made. The appellant before the Supreme Court had pleaded
that the land should revert to the appellant under Section 11-A of the Act
since the award under Section 11 had still not been made despite the
passage of almost three decades. It is in this context that the Supreme
Court observed :
14
“29. The scenario before us depicts the carelessness
and the callousness of the State, quite different from
the situation in Satendra Prasad Jain and Avinash
Sharma. The Appellants herein are being denied just
and fair compensation for their land in proceedings
which commenced in 1987, despite the directions of
the High Court passed as early as in 1988 to pass an
award within four months. The raison d’etre behind
the introduction of Section 11A was for the
landowners to have a remedy in the event of an award
not being passed expeditiously. If Satendra Prasad
Jain is interpreted to mean that Section 11A will not
apply to any acquisition under the urgency provisions,
landowners such as the Appellants before us will have
no protection, even if they are not paid full
compensation for their land for decades. This cannot
be in keeping with the legislative intent behind this
Section. Furthermore, keeping empirical evidence in
sight, we make bold to opine that circumstances
require this Court to reconsider its view that even if
the stated public interest or cause has ceased to exist,
any other cause can substitute it, especially where the
urgency provisions have been invoked.”
In the present case, as noted above, not only possession had been
taken on 9 March 2009 but the award was also made on 27 August 2011.
In Kunwar Pal Singh, the issue before the Court was regarding the
date of publication of the declaration under Section 6 of the Act. This
judgment does not decide whether the acquisition proceedings would
lapse when the provisions of sub-sections (1) and (4) of Section 17 of the
Act are made applicable to the acquisition.
The judgment in Laxman Pandya, on which reliance has been
placed by learned counsel for the petitioner, would also not be of any
benefit to the petitioner. The Supreme Court distinguished the decisions
in Satendra Prasad Jain and Awadh Bihar Yadav for the reason that
the possession of the land had not been taken within two years from the
15
date of publication of the declaration under Section 6 of the Act as is
clear from paragraph 17 of the judgment which is reproduced below:-
“17.The High Court was also not justified in
applying the ratio of Satendra Prasad Jain Vs. State of
U.P. (supra) and Awadh Bihari Yadav v. State of
Bihar (supra) for negating the appellants' prayer
because in those cases possession of the acquired land
was taken within two years of the publication of the
declaration issued under Section 6(1) and, as a result
of that the acquired land vested in the State
Government. In these cases, possession of the
acquired land was not taken within two years of
dismissal of the writ petitions. Therefore, the land
cannot be said to have vested in the State
Government.”
In the instant case, possession of the land was taken on 9 March
2009 within two months from the date of publication of the declaration
under Section 6 of the Act.
The decision of the Division Bench of this Court in Ram Jiyawan
also does not help the petitioner because of what has been stated in
paragraph 41 of the judgment which is as follows:
“41.In the present petitions the only
substantive provision which is alleged to have been
violated is Section. 11A. If Section 11A is violated the
entire acquisition proceedings will indeed lapse but
the relevant facts attracting that provision have not
been placed on record by the petitioner. As already
noticed Section 11A requires the award to be made
within a period of two years from the date of the
publication of the declaration. If the award is not made
within this period the acquisition lapses. The period of
two years is to be calculated from the date of the
publication of declaration. In the present case, as
already noticed, initially the petitioner pressed this
point but subsequently gave up. Accordingly in the
present petitions it is not possible to quash the
acquisition itself. ….........”
16
The judgment of the Division Bench of this Court in Veer Singh
would also not help the petitioner because the issue as to whether the
acquisition proceedings would lapse if sub-section (1) and (4) of Section
17 are made applicable, was not considered.
Thus, for all the reasons stated above, it is not possible to accept
the contention of learned counsel for the petitioner that the acquisition
proceedings lapse because the award has not been made within two years
from the date of publication of the declaration under Section 6 of the Act.
The writ petition is, accordingly, dismissed.
Date:07.03.2017
SK
(Dilip Gupta, J.)
(Siddhartha Varma, J.)
Legal Notes
Add a Note....