As per case facts, MECON Limited, a contractor for SAIL, engaged sub-contractors for project work. MECON argued it wasn't required to obtain a labour licence under the Contract Labour (Regulation ...
IN THE HIGH COURT AT CALCUTTA
Constitutional Writ Jurisdiction
APPELLATE SIDE
Present:
The Hon‟ble Justice Shampa Dutt (Paul)
WPA 5494 of 2022
MECON Limited
Vs
Union of India & Ors.
For the Petitioner : Mr. Soumya Majumder, Sr. Adv.
Mr. Barnamoy Basak.
For the Respondent Nos. 1 to 3 : Mr. Indrajeet Dasgupta.
Judgment reserved on : 28.11.2025
Judgment delivered on : 20.01.2026
Shampa Dutt (Paul), J.:
1. The writ petition has been preferred praying for direction upon the
respondent nos. 3 and 4 authorities to revoke and withdraw the
communication dated 10
th
February, 2022 and 16
th
March, 2022 and
further directions to issue licence to such sub-contractors engaged by
the petitioner, who employ or will employ 20 or more workmen/contract
labour in the premises of the establishment in relation to Steel Authority
of India Limited, Durgapur Steel Plant and permit Durgapur Steel Plant
to engage contract labour of such contractors/sub-contractors.
2
2. The petitioner‟s case is that the petitioner company entered into a
contract with Steel Authority of India Limited (hereinafter referred to as
“SAIL”) for work of installation of 4
th
Stove of Blast Furnace No. 04 at
the Durgapur Steel Plant. The contract expressly permits the petitioner
to engage sub-contractors with the knowledge and consent of the
respondent no. 4. The nature of work entails several types of civil work,
mechanical, erection and electrical work. The petitioner company being
an engineering consultancy establishment can only supervise such work
which will be actually carried out by the sub-contractors engaged at the
establishment of SAIL.
3. Thus the petitioner in turn had awarded contract to other contractors
for execution of the project and such sub-contractors may be employing
20 or more workmen, or some of them may employ even less than 20
workmen.
4. The petitioner company as a contractor has not employed even a single
workman in the establishment of SAIL at Durgapur Steel Plant.
Therefore, it is stated that the petitioner company, even though a
contractor in relation to the establishment of SAIL, is not entitled and
does not qualify to obtain a licence under Section 12 of the Contract
Labour (Regulation and Abolition) Act, 1970 (hereinafter referred to as
“the said Act of 1970”).
5. Petitioner further states that the respondent no. 4 has forwarded to the
petitioner a copy of a letter dated 10
th
February, 2022 issued by the
respondent no. 3 to the respondent no. 4 wherefrom, it appears that the
respondent no. 3 had informed the respondent no. 4 that the petitioner
3
herein should obtain labour licence covering the manpower of all
sub-contractors and the sub-contractor should also obtain labour
licence accordingly.
6. The petitioner had made representation to the respondent no. 4 on 19
th
February, 2022 in respect of the aforesaid letter dated 10
th
February,
2022 enclosing copies of clarification issued by the Ministry of Steel and
Mines on 22
nd
July, 1983, whereby it was specifically clarified that the
petitioner was not required to be registered as contractor under the said
Act of 1970. The respondent No. 4 has responded to such letter dated
19
th
February, 2022 by an email dated 25.02.2022.
7. The petitioner had made another communication dated 10
th
March,
2022 to the respondent no. 4 clarifying the issue.
8. On 16
th
March, 2022, the respondent no. 2 had issued a communication
to the petitioner rejecting the contention of the petitioner and
purportedly clarifying that unless the main contractor is licensed, the
existence of sub-contractors cannot be legally established, and that the
sub-contractors are not liable to the principal employer.
9. In view of the stand taken by the authority under the Act of 1970, the
petitioner has applied for certificate from principal employer by letter
dated 18
th
March, 2022 and on 19.03.2022, a certificate has been
issued by the principal employer. The petitioner has however, not
applied for issuance of licence before the licensing authority since the
petitioner is not eligible to be licensed under the Act.
4
10. The petitioner states that SAIL is the principal employer in relation to
the establishment and it has obtained C ertificate of Registration in
terms of Section 7 of the said Act of 1970 from the Registering Officer.
11. The petitioner further states that application for licence by a contractor
has to be made in terms of Rule 21 of the Contract Labour (Regulation
and Abolition) Central Rules, 1971 read with Form No. II (earlier form
IV) whereunder, amongst others, particulars of establishment where
contract labour is to be employed, and the particulars of contract labour
are to be mentioned.
12. Such application for grant of licence is to be accompanied by a
certificate of a principal employer in Form No. III (earlier form V) to the
effect that the applicant contractor has been employed by the principal
employer as a contractor in relation to the establishment of the principal
employer and that the principal employer undertakes to be bound by all
the provisions of the Act and the Rules made thereunder insofar as the
provisions are applicable to the principal employer in respect of the
employment of contract labour by the applicant contractor.
13. It is further stated that the licensing authority of the jurisdictional area
has already issued contract licence to one sub contractor in relation to
the establishment. The sub contractor for whom licence has been
withheld by the concerned authority is M/s. Mahalakshmi Udyog. The
licensing authority has already issued licence in favour of M/s. Edifice
Engineering. The other sub-contractors have been told that they will not
be issued certificates by the principal employer in view of the notices
dated 10
th
February 2022 and 16
th
March 2022.
5
14. The petitioner states that by reason of the communication dated 10
th
February, 2022 and 16
th
March, 2022, the respondent no. 4 will not be
in a position to issue gate passes to the employees of the sub
contractors and in fact no licence will be granted to any sub contractor
intending to execute the work of the project at the establishment of the
respondent no. 4. A project of national importance is therefore likely to
suffer.
15. It is further stated that the petitioner has not employed any contract
labour at the establishment of the respondent no. 4. It is therefore not a
contractor which is required to obtain licence under the said Act of
1970. Within the meaning of the said Act of 1970, a sub-contractor is
also a contractor and such contractors/sub -contractors, which
expression has been interchangeably used in the statute are required to
obtain labour licence, if they employ 20 or more workmen in the
establishment of the respondent no. 4.
16. The respondents in the ir affidavit-in-opposition have stated as
follows:-
The respondents deny the statement that the contract expressly permits
the petitioner to engage sub-contractors. In fact, Article 7 of the
Contract restricts the use of Sub-contractors without the approval of
the Employer (Respondent No. 4). The said Article specifically states
that such approval shall not relieve the Contractor from any of its
obligations, the duties or responsibilities under the contract. The
respondents deny the statement that the petitioner company being an
engineering consultancy establishment can only supervise the work
6
which will actually be carried out by the sub-contractors. It is further
stated that from the Contract as well as the Work Order it will be
evident that the obligation to carry out the work of installation of 4th
Stove of Blast Furnace No. 04 at Durgapur Steel Plant and t he
contractual obligations as per the agreement are not supervisory in
nature.
17. The respondents further state that the petitioner has engaged sub-
contractors to execute the contract work in the establishment of the
principal employer. The sub-contractors engage contract labour who are
working in the establishment of the principal employer. But there is no
contractual obligation between the principal emplo yer and the sub-
contractor of the petitioner /contractor. Therefore, the
petitioner/contractor is required to obtain licence in respect of all the
contract labour engaged by them as well as engaged by their sub -
contractors to establish relationship between principal employer and
contract labour for enforcement of labour laws in respect of these poor
unorganized contract labour. That engagement of subcontractors by the
contractor resulting in distribution of the number of contract workers
across several subcontractors does not and cannot extricate the
contractor from the application of the Act.
18. The respondents further state that the petitioner has decided to apply
for licence vide their letter no. 11.51.kp027U/11/03 dated 31.03.2022,
which has already been issued to the contractor (Petitioner).
19. Licence in respect of sub-contractor namely M/s Mahalaxmi Udyog has
also been granted on 18.04.2022.
7
20. That proper licensing of the contractor of sub-contractors is mandatory
as per statute, and as the petitioner as contractor as per contract
document engaged the contractor labour through sub-contractors, they
have to obtain licence if the total number of contract labour is more
than 20.
21. The respondents rely upon the judgment in Gammon India Ltd. v.
Union of India (1974) 1 SCC 596, wherein the Supreme Court held as
follows:-
“17. A contractor under the Act in relation to an
establishment is a person who undertakes to produce a
given result for the establishment through contract labour.
A contractor is a person who supplies contract labour for
any work of the establishment. The entire context shows
that the work of the establishment is the work site. The
work site is an establishment and belongs to the principal
employer who has a right of supervision and control, who is
the owner of the premises and the end product and from
whom the contract labour receives its payment either
directly or through a contractor. It is the place where the
establishment intends to carry on its business, trade,
industry, manufacture, occupation after the construction is
complete.
18. According to the petitioners, the contract labour
employed by their sub-contractors will be within the
provision of the Act but when the petitioners will be
engaged by a trade, or industry, with the petitioners will
not be a contractor and the workmen directly employed by
the petitioners will not be contract labour. This is a strange
and anomalous submission. The Act must be construed as
a whole. The Act must apply to contract labour in
8
connection with the work of an establishment when the
contract labour is hired by the contractor or by the sub-
contractor of the contractor."
22. As such it is submitted that s ince the petitioner is engaged as
“contractor” by the respondent no. 4, the petitioner has to obtain licence
if the total number of contract labour engaged by them directly and/or
through sub-contractor is 20 or more.
23. The respondent relies upon Section 1 (4) of the said Act, which clearly
states that, “It applies to:-
a) to every establishment in which twenty or more workmen
are employed or were employed on any day of the preceding
twelve months as contract labour,
(b) to every contractor who employs or who employed on any
day of the preceding twelve months twenty or more workmen.”
24. It is stated that Clause (a) clearly makes it applicable to an
establishment in which twenty or more workmen are employed on any
day of the preceding twelve months as contract labour. The petitioner is
trying to make out a case that clause (b) above is an exemption in its
favour since the petitioner as a contractor has not engaged more than
20 workmen in the said establishment. Such interpretation of the
petitioner is obviously incorrect since the petitioner would come within
the scope of clause 4 if it has on any day of the preceding twelve months
employed twenty or more workmen.
25. The respondents further state that the interpretation of applicability of
the act, as contended by the petitioner, by looking only at Clause (b)
Sub-section (4) of the said Act and ignoring all other provisions of the
9
said Act cannot be accepted in as much as, such narrow
interpretation would allow all contractors to engage less than 20
workers and engage sub -contractors, who would in turn again
engage less than 20 workers without obtaining licence, thereby
frustrating the whole purpose of the act. The rejection of the writ
petition is prayed for.
26. Notes of argument have been filed by both sides.
27. The petitioner‟s argument in this case is :
i. The contract between SAIL and Mecon Limited permits the
contractor to engage sub-contractors.
ii. The office of the Labour Commissioner instructed Mecon Limited
to obtain labour licence under the Contract Labour (Regulation &
Abolition) Act, 1970.
iii. Simultaneously the Government had granted licen ce to another
sub-contractor.
iv. Objection of the petitioner is founded on the Ministry's
clarification of 1983 wherein the Ministry has clarified in similar
circumstances at hand that sub-contractors are to be licensed
and not the contractor.
v. As a contractor, the petitioner cannot obtain licence unless it
employs 20 or more persons in the establishment, where the work
is being executed (Section 1(4)(b) of the Contract Labour
(Regulation & Abolition) Act, 1970).
vi. Section 2(1)(c) of the Act of 1970, while defining "contractor”
includes sub-contractor, therefore, for the purpose of the Contract
10
Labour (Regulation & Abolition) Act, 1970, a sub-contractor is
also to be reckoned as a contractor, and therefore, required to
have a licence under Section 7 thereof.
vii. The liability of the contractor to pay wages for contract labour
employed by it and the statutory duties of the contractor to
provide facilities and conditions of work for the contract labourers
cannot be split into two tiers, namely, the contractor and the sub-
contractor. The object of the statute is to bind the licensee
contractor into statutory obligations as regards the conditions of
work and benefits of the contract labourers. This is possible only
in a direct master servant relationship. In this case, the
relationship exists between the sub -contractors and the
contract labourers.
viii. The object of the Contract Labour (Regulation & Abolition) Act,
1970 is inter-alia, to regulate the employment of contract labour
in certain establishments. The employment of contract labour is
done by the sub-contractors in the instant case. Therefore, all
statutory duties and responsibilities dischargeable by the
contractor, in the given case would mean, that of the sub-
contractors.
ix. The Act does not envisage three different tiers (a) principal
employer, (b) contractor and (c) sub-contractor, for the
purpose of certain conditions of work and facilities of
contract labourers.
11
x. To eradicate such doubt, the legislators thought it fit that the
definition of "contractor" would include a sub-contractor. Thus,
there is no concept of a contractor and a sub-contractor existing
simultaneously in the premises of the principal employer, for the
purpose of licensing. The condition for renewal of licence by the
contractor under Rule 25 of the Contract Labour (Regulation and
Abolition) Central Rules, 1971 gives support to the mandate of the
principal Act in this respect.
xi. When the principal employer takes registration under Section 12
of the Contract Labour (Regulation & Abolition) Act, 1970, it only
mentions about the deployment of contractors (w hich includes
sub-contractors).
xii. In the given case, the Government had issued labour licence to
the sub-contractor as well.
xiii. Petitioner cannot be reckoned as a „contractor‟ since it does
not employ 20 employees in relation to the establishment of
the project work.
xiv. It is argued that the judgment in Gammon India Ltd. (Supra)
(Para 10 & 11) relied upon by the respondents is not applicable in
the present case. Wherein the respondents also relying upon the
same judgment have stressed on Para 17 and 18 therein:-
“…………..This is a strange and anomalous submission.
The Act must be construed as a whole. The Act must apply
to contract labour in connection with the work of an
establishment when the contract labour is hired by the
contractor or by the sub-contractor of the contractor.”
12
28. The respondents in their written notes have reiterated their
statements in their affidavit-in-opposition.
29. On hearing the parties and considering the pleadings on record the
following is evident:-
a) Article 7.1 in the „contract agreement‟ between the respondent
no. 4 and the petitioner provides as follows:-
“7.1. Sub-contracting
The Contractor shall not sub-contract the work either in full or
in part without prior approval of Employer and shall engage
only those Sub-Contractors who are appro ved by the
Employer. Such approval by the Employer for any of the
Sub-Contractors/Vendors shall not relieve the
Contractor from any of its obligations, duties or
responsibilities under the Contract.”
b) Vide the letter under challenge dated 10.02.2022 the As sistant
Labour Commissioner (Central) Raniganj at Durgapur advised the
respondent no. 4 as follows :-
“it is very clear that M/s. Mecon Ltd. is the contractor
and M/s Edifice Engineering Enterprise Pvt. Ltd. is the
sub-contractor who are working in your establishment.
The provision of the act and rule are much applicable on
them. The Mecon Ltd. should obtain labour licence
covering the manpower of all sub-contractors engaged by
them. The sub-contractor should also obtain labour
licence accordingly.”
c) The petitioner herein relies upon the document at page 104 wherein
the petitioner had been informed by the D epartment of Labour,
Govt. of India about the clarification regarding the definitions of the
13
term “Contractor” under the provisions of the Contract Labour (R &
A) Act, 1970. The relevant extract is as follows :-
“1. MECON would not be a contractor as the entire work
has been sub-let and no worker is stated to have been
employed by it.
2. Accordingly, no licence is required to be taken by
MECON.”
30. It has also been clarified therein that the Steel Plant is the “Principal
Employer”.
31. The petitioner‟s contention is that it does not employ 20 or more persons
in the establishment and as the Sub-contractors engaged by them have
employed the contractual workers herein, the petitioner claims that the
relationship of Employer-Employee is between the Sub-Contractor and
its‟ contract workers and, as such, the petitioner does not require to
take any licence.
32. The relevant provisions in the present case under the Contract Labour
(Regulation and Abolition) Act 1970 are as follows :-
Section 2(b) of the Contract Labour (Regulation and Abolition) Act ,
1970, lays down:-
“Section 2(b) a workman shall be deemed to be
employed as "contract labour" in or in connection
with the work of an establishment when he is hired in or
in connection with such work by or through a contractor,
with or without the knowledge of the principal
employer.”
Section 2(c) of the Contract Labour (Regulation and Abolition) Act ,
1970, lays down:-
“Section 2(c) "contractor", in relation to an
establishment, means a person who undertakes to
produce a given result for the establishment, other than
14
a mere supply of goods or articles of manufacture to
such establishment, through contract labour or who
supplies contract labour for any work of the
establishment and includes a sub-contractor.”
33. Thus it is clear that a “Sub-Contractor” is included in the definition
of “Contractor”.
34. Provision for Sub-Contracting has also been provided for Article 7 of the
Agreement.
“7.1. Sub-contracting
The Contractor shall not sub-contract the work either in full or in
part without prior approval of Employer and shall engage only
those Sub-Contractors who are approved by the Employer. Such
approval by the Employer for any of t he Sub-
Contractors/Vendors shall not relieve the Contractor from
any of its obligations, duties or responsibilities under the
Contract.”
35. It appears that the terms and conditions in the contract , between
the respondent no. 4 and the petitioner herein, puts no
responsibility upon the sub contractors who are engaged by the
contractor/petitioner, herein to provide contract workers, who are
employed to carry out the work for the principal Employer , who
engaged the contractor/petitioner as per the agreement to provide
the same.
36. The sub-Contractors in this case have been engaged by the
petitioner/contractor for carrying out different work/projects for the
principal Employer.
37. It is the contention of the petitioner that as he does not employ more
than 20 workers, he is not liable to take licence under the Act of 1970.
15
38. The contention of the petitioner is that the Sub-Contractors herein being
included in the definition of the word “Contractor”, are responsible and
liable for the Contract workers, having engaged them and the petitioner
even though a contractor as per the agreement has no responsibility,
even though the agreement between the petitioner and the respondent
no. 4 makes it clear that the petitioner is the Contractor and the
respondent no. 4 is the principal Employer.
39. Thus from the said facts it is apparent that the principal Employer
recognizes only the “contractor” with whom he has an agreement and
none else and as such the responsibility of the Sub-Contractors along
with their contract workers becomes the responsibility of the
Contractor/petitioner herein, because the said contract workers were
engaged for the sole purpose of doing the work of the principal
employer through a contractor/petitioner via a Sub-Contractor.
40. Herein, the petitioner/contractor includes its Sub-Contractors and
their responsibility becomes a joint responsibility, but finally the
liability rests with the principal employer herein, who is bound by
an agreement of contract with the petitioner/contractor under
Section 21(4) of the Central Labour (R & A) Act, 1970.
41. The petitioner herein claims exemption relying upon the letter dated
22
nd
July, 1983, wherein the petitioner was held to be “not a Contractor”
as the entire work was „sublet‟ and no worker was engaged by it and as
such no licence was required to be taken by the petitioner.
42. Here the contents of the letter under challenge dated 16.03.2022
becomes relevant and is as follows:-
16
“After going through the above letter, it is observed
that Mecon Limited is the main contractor of Durgapur Steel
Plant, SAIL who in turn intended to offload the work to their
sub-contractors. Being the main contractor, the Mecon
Limited has to obtain labour licence and thereafter sub-
contractors engaged by the main contractor have to be
licensed under the C.L (R&A) Act, 1970.
It is also to clarify that unless the main
contractor is licensed, the existence of sub-contractors
cannot be legally established. The sub-contractors are
not liable to response their legal obligation to the
Principal Employer since they are not directly engaged
by the Principal Employer. In case, the sub-contractors
violate any provision of C.L. (R&A) ACT, 1970 and
other labour laws, the enforcement agency cannot
force the Principal Employer to insist the sub -
contractors to comply with th e provisions laid down
under various labour laws.
In this connection, it is pertinent to mention here that as per
the Departmental Manual of Chief Labour Commissioner
(Central), New Delhi wherein at point No. 47, it is clearly
stated that “the contractor and sub-contractors are
contractors in relation to the Principal Employer’s
establishment. The main contractor as well as sub-contractor
have to be licenced separately when both the above are
contractually obliged with the Principal Employer to produce
given results separately as per CLC’s instruction 12/77
dated 28.03.1977. The decision of Bombay High Court
(Nagpur) in the case of M/s. Gammon India Ltd. vrs.
Assistant Labour Commissioner, Nagpur (1976 Labour IC
245) supports the above elaboration.
The matter of obtaining license by the main
contractor has also been discussed with the Chief Labour
17
Commissioner (Central), New Delhi who has opined that the
main contractor has to obtain license for entire work under a
single tender of contract and for entire work force to be
engaged by its sub-contractors. Main contractor cannot
get away with their legal obligation by subletting the
work to the sub-contractor(s).
In view of the above circumstances, it is hereby
advised to obtain labour license in respect of Mecon Limited
as main contractor and ensure that no contractor should be
engaged without obtaining the labour license to avoid any
legal complicacy.
Yours faithfully,
(M.K. Dhurua)
Dy. Chief Labour Commissioner (Central), Asansol”
43. In the present case there is admittedly a Contract Agreement between
the petitioner and the respondent no. 4, wherein the petitioner is
referred to as the “Contractor” and the respondent no. 4 is referred to
as “Employer”.
44. As such the clarification by the Department of Labour is prima facie not
in accordance with law. Clarification at no. 2 being based on
clarification no. 1 is also thus not in accordance with law.
45. Thus, in this case:-
(i) The petitioner is the “Contractor” as per the agreement between
the principal employer and the contractor/petitioner.
(ii) The contractor includes the sub-contractors and are to be treated
as one, under the same contract as per Section 2(i)(c) of the
Contract Labour Act, 1970.
18
(iii) The number of contract workers/employees through the sub-
contractors are to be treated as the workers of the contractor
and when/as in this case, exceeds 20 (twenty) in number, the
contractor along with its sub -contractors are to obtain
licence under the Act, 1970.
(iv) As per Section 1(4) of the Act, the petitioner/contractor
cannot avoid its liability by engaging sub-contractors to shift
its‟ liability, as the agreement is between the principal
employer and the contractor (petitioner herein) and not the
sub-contractors, who are only amenable to the contractor ,
who in turn is bound by the agreement with the principal
employer.
46. Thus, the letters dated 10
th
February, 2022 issued by the Respondent
no. 3, Assistant Labour Commissioner (Central), Raniganj, Durgapur
and 16
th
March, 2022 issued by the Respondent no. 2, Deputy Chief
Labour Commissioner (Central), Asansol, being in accordance with law,
require no interference.
47. The writ petition is thus dismissed.
48. Connected application, if any, stands disposed of.
49. Interim order, if any, stands vacated.
50. Urgent Photostat certified copy of this judgment, if applied for, be
supplied to the parties expeditiously after due compliance.
(Shampa Dutt (Paul), J.)
Legal Notes
Add a Note....