As per case facts, the petitioner challenged an arbitral award stemming from a work contract awarded in 2006. Initially, in 2012, the Arbitral Tribunal considered only one of four claims, ...
Arb.O.P.(Com.Div.)No.134 of 2022
1/24
In the High Court of Judicature at Madras
Reserved on
17.12.2025
Delivered on:
02.1.2026
Coram:
The Honourable Mr.Justice N.ANAND VENKATESH
Arbitration O.P.(Com.Div.) No.134 of 2022
Mr.K.Satyanarayana Raju,
M/s.Om Spun Pipes & Concrete
Works, B-43, Sterling Ganges,
Kattupakkam, Chennai-58. ...Petitioner
Vs
The Union of India, rep.by its
Divisional Railway Manager/
Works, Southern Railways,
Park Town, Chennai-3. ...Respondent
PETITION under Section 34(2)(a)(v) and (b)(ii) of the Arbitration
and Conciliation Act, 1996 praying to set aside the award passed by
the Arbitral Tribunal dated 08.2.2021 and to direct the respondent to
pay the costs.
For Petitioner : Mr.A.Vikash
For Respondent : Mr.P.T.Ramkumar,
Standing Counsel https://www.mhc.tn.gov.in/judis
Arb.O.P.(Com.Div.)No.134 of 2022
2/24
ORDER
The claimant before the Arbitral Tribunal is the petitioner before
this Court and he has assailed the award dated 08.2.2021 passed by
the Arbitral Tribunal.
2. Heard both.
3. The case of the petitioner is as follows:
(i) The respondent called for tenders involving the work for
standardisation of cutting including pitching and construction of side
drain and the work was awarded on 29.12.2006 by issuing a letter of
acceptance.
(ii) Disputes arose between the parties and an Arbitral Tribunal
was constituted on 21.12.2012. At that point of time, even though the
petitioner had raised four claims, the respondent referred only one
claim in the terms of reference and issued a letter dated 04.2.2013 to
the effect that the other three claims were excepted matters and could
not be included in the arbitration proceedings. In the meantime, the
petitioner wrote a letter dated 16.1.2013 to the General Manager of
the respondent to refer all the claims made by the petitioner. The https://www.mhc.tn.gov.in/judis
Arb.O.P.(Com.Div.)No.134 of 2022
3/24
communication made by the petitioner to the Arbitral Tribunal also did
not evoke any response.
(iii) Under such circumstances, the petitioner filed O.P.No.832
of 2014 before this Court seeking to appoint an arbitral tribunal to
decide all the claims of the petitioner and in that, an order was passed
on 28.4.2015 with a direction to refer all the claims to the same
Arbitral Tribunal, which has already been constituted and it was further
made clear that the Arbitral Tribunal would deal with the issue of
maintainability of those claims, which were brought within the
excepted matters by the respondent.
(iv) Pursuant to that, the respondent issued an addendum
dated 26.11.2015 following the said order passed by this Court and
referring all the claims of the petitioner to the Arbitral Tribunal for
adjudication.
(v) After the said addendum was issued, there was a change in
the panel of Arbitrators and on 15.3.2016, the petitioner made a
communication to the Arbitral Tribunal to commence the proceedings
and also to inspect the work site to ascertain the real position while
deciding the disputes between the parties. https://www.mhc.tn.gov.in/judis
Arb.O.P.(Com.Div.)No.134 of 2022
4/24
(vi) Even thereafter, there was absolutely no response from the
Arbitral Tribunal and only on 21.3.2018, a communication was
received from the respondent intimating that there was a change in
the constitution of of the Arbitral Tribunal and a new co-arbitrator has
been appointed. The petitioner had also taken a stand that from
26.11.2015 to 25.2.2020, almost for a period of more than four years,
no proceedings were held before the Arbitral Tribunal. Thus, the
dispute, which started in the year 2012, did not see any progress till
the year 2020. Ultimately, on 25.2.2020, the hearing commenced
before the Arbitral Tribunal. The next hearing was conducted on
22.12.2020 and this was the only physical hearing that took place.
(vii) In the meantime, before the Arbitral Tribunal, the
petitioner filed the claim statement on 20.2.2020. Later, the
respondent filed a counter containing counter claims also. Two hearing
were conducted through online mode on 05.1.2021 and 21.1.2021.
Thereafter, the petitioner filed O.P.No.174 of 2021 before this Court
for termination of the mandate of the Arbitral Tribunal under Section
14 of the Act, on 10.2.2021. When O.P.No.174 of 2021 came up for
hearing on 18.3.2021, it was informed to this Court that the Arbitral
Tribunal already passed an award on 08.2.2021 itself and therefore, https://www.mhc.tn.gov.in/judis
Arb.O.P.(Com.Div.)No.134 of 2022
5/24
O.P.No.174 of 2021 was closed as infructuous.
(viii) The petitioner thereafter issued two legal notices dated
17.6.2021 and 15.7.2021 to the Arbitrators, who formed part of the
Arbitral Tribunal, seeking to send a signed original copy of the award.
On receipt of the said legal notices, a copy of the impugned award was
furnished to the petitioner under a covering letter dated 23.7.2021.
Pursuant to the same, the present original petition came to be filed
before this Court.
(ix) By the impugned award, though the petitioner made four
claims before the Arbitral Tribunal, the first three claims came to be
rejected. Based on the stand taken by the respondent, the earnest
money deposit for a value of Rs.2,07,300/-, the performance bank
guarantee for an amount of Rs.7,00,212/-, the security deposit for a
sum of Rs.4,92,912/- and a further sum of Rs.3,43,740/- towards
additional works done, were allowed and the amounts were directed to
be paid with interest at the rate of 8% per annum in case the amount
was not paid within 60 days from the date of receipt of the copy of the
award.
(x) Further, the counter claim made by the respondent for
forfeiture of the earnest money deposit and the security deposit came https://www.mhc.tn.gov.in/judis
Arb.O.P.(Com.Div.)No.134 of 2022
6/24
to be rejected. Challenging the award passed by the Arbitral Tribunal,
the petitioner is before this Court.
4. The main focus of the submissions on the side of the
petitioner was on the issue of the enormous delay in conducting the
arbitration proceedings and passing the final award. According to the
learned counsel for the petitioner, the delay, by itself, vitiates the
entire proceedings and as a result, the claim made by the petitioner
towards the additional works, which were available at the site, was not
even able to be inspected by the Arbitral Tribunal due to lapse of more
than 10 years. Hence, it was contended that the award is liable to be
set aside on this ground alone.
5. At the outset, this Court will focus on the above issue that
has been raised on the side of the petitioner. The finding on this issue
will determine as to whether this Court has to go into the other issues
touching upon the rejection of three claims made by the petitioner.
6. On the ground of delay in passing the award, it will be
relevant to take note of the judgment in Lancor Holdings Ltd. Vs. https://www.mhc.tn.gov.in/judis
Arb.O.P.(Com.Div.)No.134 of 2022
7/24
Prem Kumar Menon [reported in 2025 SCC OnLine SC 2319], in
which, the Hon’ble Apex Court was dealing with the specific issue as to
the effect of undue and unexplained delay in the pronouncement of an
arbitral award and how far it would vitiate its validity.
7. The learned counsel for the petitioner, by relying upon the
said judgment of the Hon’ble Apex Court, submitted that the ratio in
the said judgment will apply to the facts of the present case and that
the award passed by the Arbitral Tribunal is liable to be interfered on
the sole ground of delay.
8. The relevant portions in the decision of the Hon’ble Supreme
Court in Lancor Holdings Ltd., read thus:
“18. Similarly, on ‘Duty to act promptly’ in
Chapter 5, titled ‘Powers, Duties, and Jurisdiction
of an Arbitral Tribunal’, Redfern and Hunter
Redfern and Hunter on International Arbitration,
7
th
Edition (Paras 5.74 and 5.75) states thus:
‘An arbitral tribunal has an obvious moral
obligation to carry out its task with due diligence.
Justice delayed is justice denied. Some systems of
law endeavour to ensure that an arbitration is
carried out with reasonable speed by setting a time https://www.mhc.tn.gov.in/judis
Arb.O.P.(Com.Div.)No.134 of 2022
8/24
limit within which an arbitral tribunal must make its
award. The time limit fixed is sometimes as short
as six months (as in the ICC rules), although
generally it may be extended by consent of the
parties, or at the initiative of the institution or the
tribunal. If an award is not made within the time
allowed, the authority of the arbitral tribunal may
be regarded as having terminated, with the risk
that any award will be null and void. Some systems
of law provide that an arbitrator who fails to
proceed with reasonable speed in conducting the
arbitration and making his or her award may be
removed by a competent court, and deprived of
any entitlement to remuneration. The Model Law
provides that the mandate of an arbitrator
terminates if he or she ‘fails to act without undue
delay’.
The learned authors pointed out that
though the above sanctions may act as a spur to
the indolent arbitrator, they do not compensate a
party who suffered financial loss as a result of
delay in the conduct of the arbitration. It was noted
that delay in the conduct of an arbitration may
have serious financial consequences as awards of
interest rarely compensate a party for the financial
loss suffered in the interim. It was pointed out that
faced with increasing delays in the conduct of
arbitrations, major institutions revised their rules to
improve the speed and efficiency of arbitrations. https://www.mhc.tn.gov.in/judis
Arb.O.P.(Com.Div.)No.134 of 2022
9/24
Though the above observations were made in the
context of international arbitrations, the same
principle would hold good for domestic arbitrations
also. Therefore, when the Arbitrator presently took
years together to deliver the Award, the least that
the parties would expect is a quietus being given to
their disputes instead of being relegated to another
round of arbitration/litigation. The Arbitrator,
therefore, failed to live up to that minimal
expectation reposed in him by law and by the
parties themselves.
19. However, the undeniable fact remains
that Section 34 of the Act of 1996 does not
postulate delay in the delivery of an arbitral award
as a ground, in itself, to set it aside. There is no
gainsaying the fact that inordinate delay in the
pronouncement of an arbitral award has several
deleterious effects. Passage of time invariably
debilitates frail human memory and it would be
well-nigh impossible for an arbitrator to have total
recall of the oral evidence, if any, adduced by
witnesses; and the submissions and arguments
advanced by the parties or their learned counsel.
Even if detailed notes were made by the arbitrator
during the process, they would be a poor substitute
to what is fresh in the mind immediately after
conclusion of the hearings in the case. More
importantly, such delay, if unexplained, would give
rise to unnecessary and wholly avoidable https://www.mhc.tn.gov.in/judis
Arb.O.P.(Com.Div.)No.134 of 2022
10/24
speculation and suspicion in the minds of the
parties. Absolute faith and trust in the system is
essential to make it work the way it is intended to.
Once that belief is shaken, it would lead to a
breakdown of that system itself. A situation that is
to be eschewed at all costs.
20. That being said, we must also
recognize that, in the usual course, long delay in
the passing of arbitral awards is not the norm.
However, when an instance of undue delay in the
delivery of an arbitral award occasionally crops up,
given the weighty preponderance of judicial
thought on the issue with which we are in
respectful agreement, we are of the considered
opinion that each case would have to be examined
on its own individual facts to ascertain whether the
delay was of such import and impact on the final
decision of the arbitral tribunal, whereby that
award would stand vitiated due to the lapses
committed by the arbitral tribunal owing to such
delay. We are also conscious of the fact that there
must be a balance between the pace of the
arbitration, culminating in an arbitral award, and
the satisfactory meaningful content thereof. In this
regard, in his seminal article, titled ‘Arbitrators and
Accuracy’ Journal of International Dispute
Settlement (February, 2010), Professor William W
Park says thus: https://www.mhc.tn.gov.in/judis
Arb.O.P.(Com.Div.)No.134 of 2022
11/24
‘Although good case management values
speed and economy, it does so with respect for the
parties' interest in correct decisions. The parties
have no less interest in correct decisions than in
efficient proceedings. An arbitrator who makes the
effort to listen before deciding will enhance both
the prospect of accuracy and satisfaction of the
litigants' taste for fairness. In the long run, little
satisfaction will come from awards that are quick
and cheap at the price of being systematically
wrong.’
Therefore, keeping in mind these competing
interests, it is only in cases where the negative
effect of the delay in the delivery of an arbitral
award is explicit and adversely reflects on the
findings in the said award, that such delay, and
more so, if it remains unexplained, can be
construed to be a factor to set aside that award.
Once all the requirements, referred to supra, are
fulfilled in a given case and the arbitral award
therein is clearly riddled with the damaging effects
of the delay, it can be construed to be in conflict
with the public policy of India, thereby attracting
Section 34(2)(b)(ii) of the Act of 1996, or Section
34(2A) thereof as it may also be vitiated by patent
illegality. Further, it would not be necessary for an
aggrieved party to invoke the remedy under
Section 14(2) of the Act of 1996 as a condition
precedent to laying a challenge to a delayed and https://www.mhc.tn.gov.in/judis
Arb.O.P.(Com.Div.)No.134 of 2022
12/24
tainted award under Section 34 thereof. Both
provisions would operate independently as the
latter is not dependent on the former. This being
the legal position, we would have to examine
whether the present arbitral award suffers from
any such malady owing to the delay, whereby its
very validity would stand vitiated. Further, we
would also have to see whether the award is liable
to be set aside for falling short, as it did not resolve
the disputes between the parties but their positions
stood altered irreversibly owing to the interim
orders passed during the arbitral proceedings.
Lastly, if the award is liable to be set aside, the
relief to be granted.”
9. A careful reading of the above dictum brings out a ratio that
whenever there is an undue delay in delivery of an arbitral award,
that, by itself, is not a ground to interfere with the award and each
case must be examined on its own individual facts to ascertain as to
whether the delay was of such import and impact on the final decision
of the Arbitral Tribunal, whereby that award would stand vitiated due
to the lapses committed by the Arbitral Tribunal owing to such delay,
that it is only in cases where the negative effect of the delay in the
delivery of an arbitral award is explicit and adversely reflects on the https://www.mhc.tn.gov.in/judis
Arb.O.P.(Com.Div.)No.134 of 2022
13/24
findings in the said award, that if such delay remains unexplained, it
can be construed to be a factor to set aside that award and that in
such a case, the award can be construed to be one in conflict with the
public policy of India and is vitiated by patent illegality attracting
Section 34(2)(b)(ii) and Section 34(2A) of the Act.
10. In the case in hand, the letter of acceptance was issued by
the respondent on 29.12.2006 and the work was awarded for
standardization of cutting including pitching and construction of side
drain in SSE/P.Way/PUT Section. A period of nine months was fixed for
completion of the work i.e by 28.9.2007. But, the work was not
completed within the prescribed time and extensions were granted. On
24.9.2007, the parties entered into a contract. It is also seen from the
records that certain additional items of work were done by the
petitioner and those went on till November 2011.
11. The petitioner issued a trigger notice on 17.10.2011 by
referring four claims to the Arbitral Tribunal. It was followed up by two
more letters on the side of the petitioner on 10.11.2011 and
24.3.2012. A reply was received from the respondent on 18.5.2012 https://www.mhc.tn.gov.in/judis
Arb.O.P.(Com.Div.)No.134 of 2022
14/24
suggesting the panel arbitrators. The petitioner had chosen the names
of the arbitrators and the nomination letter dated 27.8.2012 was
issued constituting the Arbitral Tribunal.
12. Even though the petitioner made four claims, the terms of
reference were issued by the respondent on 21.12.2012 by referring to
only one claim and also the counter claim made by the respondent.
The respondent took a stand that claim Nos.2, 3 and 4 made by the
petitioner were excepted matters and that they could not be referred
to the Arbitral Tribunal. In the meantime, two co-arbitrators were
changed on 25.11.2013.
13. Since all the claims were not referred to the Arbitral
Tribunal, the petitioner approached this Court by filing O.P.No.832 of
2014 and this Court, by order dated 28.4.2015, directed the Arbitral
Tribunal to examine the issue of maintainability of all the four claims.
After the said order was passed, the petitioner, by letter dated
08.9.2015, informed the respondent to take immediate action and the
respondent, by addendum dated 26.11.2015, included all the claims of
the petitioner before the Arbitral Tribunal. But, there was no progress https://www.mhc.tn.gov.in/judis
Arb.O.P.(Com.Div.)No.134 of 2022
15/24
before the Arbitral Tribunal and hence, on 15.3.2016, the petitioner
sent a letter requesting the Arbitral Tribunal to conduct the
proceedings and also to inspect the work site to demonstrate the real
position, which would enable the Arbitral Tribunal to effectively deal
with the claim.
14. Once again, there was a lull for nearly two years and on
21.3.2018, the respondent sent a communication for the change of co-
arbitrators. The Arbitral Tribunal, for the first time on 07.2.2020, sent
a communication to the petitioner stating that after the issuance of the
addendum by the respondent, the petitioner did not file the claim
statement and therefore, the Arbitral Tribunal was not able to proceed
further. Accordingly, the petitioner was informed that the Arbitral
Tribunal proposed to hold the hearing on 25.2.2020. On receipt this
notice, the petitioner filed the claim statement on 20.2.2020. The
pleadings were complete by December 2020 and the proceedings were
conducted by the Arbitral Tribunal through online mode since the
covid-19 pandemic had set in by then. https://www.mhc.tn.gov.in/judis
Arb.O.P.(Com.Div.)No.134 of 2022
16/24
15. The petitioner, by letter dated 25.1.2021, informed the
Arbitral Tribunal that they wanted the proceedings to be terminated
and that the petitioner also took steps to file a petition for termination
of the mandate of the Arbitral Tribunal. By that time the petition came
up for hearing before this Court, the award was passed by the Arbitral
Tribunal on 08.2.2021.
16. All the above dates and events will have to be necessarily
considered to see if the delay in conducting the proceedings and
passing the final award had a bearing on the final award passed and
whether it adversely reflected on the findings rendered by the Arbitral
Tribunal. As already noted, this test has to be applied on a case to
case basis to ascertain as to whether the delay was of such import and
impact on the final decision rendered by the Arbitral Tribunal. As could
be seen from the above dates and events, the proceedings, which
commenced during October 2011, after issuance of the trigger notice
under Section 21 of the Act, culminated into a final award only on
08.2.2021. https://www.mhc.tn.gov.in/judis
Arb.O.P.(Com.Div.)No.134 of 2022
17/24
17. In so far as the delay is concerned, the observations made
by the Arbitral Tribunal will have a lot of significance. For proper
appreciation, the same are extracted as hereunder:
“1. After a lapse of more than ten years
after the completion of the work, the quantum of
work shown by the claimant can be assessed
based only on records available with the claimant
or respondent in this regard. The claimant has
produced the copies of M-Books in this connection.
The exact details regarding earth work lead and
stacking are not available as per records either
with the claimant or the respondent. The only
source of information available for the Tribunal are
the available records maintained by claimant and
respondent. There is no room for any guess work
in this regard since it involves payment of public
money.
2. The decision for not conducting a site
visit was taken purely by the Tribunal and not
based on any objections by the respondent. Such
a decision was taken because a visit to the site
after more than ten years after the completion of
the work would not reveal any details connected
with the disputes under discussion by the
Tribunal.
3. The Tribunal has heard both the claimant
and respondent in matters pertaining to the scope https://www.mhc.tn.gov.in/judis
Arb.O.P.(Com.Div.)No.134 of 2022
18/24
of the arbitration. However, as desired by the
claimant it is not possible and fair on the part of
the Tribunal to concede without valid reason to
the request made either by the claimant or the
respondent.
4. Regarding the delay in conduct of the
arbitration it is to be noted that after the
constitution of the Arbitral Tribunal in 12/2012,
the claimant had not attended three sittings of the
Tribunal possibly due to the fact that all the claims
raised by the claimant were not included in the
TOR. It was only after the issue of the revised
TOR during 11/2015 that the claimant started
attending arbitral sittings. It is also pertinent to
note that the claimant could not be contacted for
a major duration of time between 2015 and 2020,
in spite of repeated attempts to reach him at the
last available phone numbers. It can be clearly
seen that the Tribunal had made the utmost
sincere efforts to finalise the Award at the earliest
possible time.”
18. Before the Arbitral Tribunal, the petitioner made the
following four claims:
“Claim No.1 - Idling of labour and
machinery – Rs.2,63,65,200.00; https://www.mhc.tn.gov.in/judis
Arb.O.P.(Com.Div.)No.134 of 2022
19/24
Claim No.2 - Additional items of works not
included in the variation statement and not paid –
Rs.3,68,58,590.00;
Claim No.3 - Loss of turn over for not
arranging due payment and claimed @ 15% per
annum – Rs.2,34,97,332.00; and
Claim No.4 - Interest on the above claims @
15% per annum till payment – not quantified.”
19. The above observations made by the Arbitral Tribunal would
show that had the proceedings gone ahead immediately, it would have
had the advantage of making a site inspection and collecting the
relevant records, which, over a period of time, were not available and
that the Arbitral Tribunal certainly faced hardship due to lapse of more
than ten years. The Arbitral Tribunal had also acknowledged the fact
that there was no progress during the period between 2015 and 2020
and the reason assigned by the Arbitral Tribunal was that the
petitioner was not able to be contacted.
20. The above finding rendered by the Arbitral Tribunal is
unsustainable for the simple reason that the petitioner, after the order
was passed by this Court in O.P.No.832 of 2014 on 28.4.2015 and https://www.mhc.tn.gov.in/judis
Arb.O.P.(Com.Div.)No.134 of 2022
20/24
after the addendum was issued by the respondent on 26.11.2015, sent
a communication on 15.3.2016 to the Arbitral Tribunal to make a site
inspection before conducting the arbitration proceedings. In fact, the
letter that was addressed by the respondent on 21.3.2018 on the
change of co-arbitrator was also received by the petitioner in the same
address. Therefore, the finding of the Arbitral Tribunal to the effect
that the petitioner was not able to be contacted for the period from
2015 to 2020 is far from satisfactory and it runs contrary to the
materials available on record. It is the petitioner, who was making the
claims and therefore, there was no need for the petitioner to protract
the proceedings and evade notices.
21. The claim statement itself was not able to be filed by the
petitioner till 2020. It was filed only after the Arbitral Tribunal issued a
notice dated 07.2.2020 to the petitioner fixing the date of hearing as
25.2.2020. If this notice was able to be served on the petitioner, it
defies common sense as to why the earlier notices were not able to be
served on the petitioner in the same address for the period from 2015
to 2020. https://www.mhc.tn.gov.in/judis
Arb.O.P.(Com.Div.)No.134 of 2022
21/24
22. The Arbitral Tribunal, while dealing with claim Nos.1 and 2,
rejected them and one of the main reasons assigned is the lapse of ten
years, as a result of which, the Arbitral Tribunal was not in a position
to make a site inspection and to get the relevant records. Therefore,
claim Nos.1 and 2 were decided with the limited records available.
23. If the Arbitral Tribunal had decided the claims at the
earliest point of time, at least after the order was passed by this Court
in the year 2015 in O.P.No.832 of 2014, the Arbitral Tribunal would
have had the advantage of the relevant records and also could have
conducted the site inspection for proper appreciation of the claims
made by the petitioner. Therefore, the lapse of more than ten years
certainly had an adverse effect on the findings of the Arbitral Tribunal.
The Arbitral Tribunal, which was reconstituted in the year 2020, hardly
conducted three hearings and all these happened during the covid-19
pandemic period and the award was passed on 08.2.2021. Therefore,
the unexplained exorbitant delay in conducting the proceedings is not
attributable to the petitioner and it is purely attributable only to the
respondent, which thought it fit to keep the claims in limbo for more
than ten years. https://www.mhc.tn.gov.in/judis
Arb.O.P.(Com.Div.)No.134 of 2022
22/24
24. The whole object of resorting to arbitration proceedings is
to speed up the process of adjudication and to grant relief to the party,
which, otherwise, will be forced to spend years together before a civil
court. Unfortunately, in the case in hand, more than ten years had
lapsed before the impugned final award was passed by the Arbitral
Tribunal and the whole purpose of having an alternative dispute
resolution mechanism has been defeated. This delay in the conduct of
the arbitration proceedings seriously affects the rights of the petitioner
and at one stage, the petitioner, out of sheer frustration, sought for
termination of the mandate of the Arbitral Tribunal. However, the
award came to be passed by then.
25. In the light of the above discussions, this Court holds that
the exorbitant unexplained delay in conducting the arbitration
proceedings and passing the impugned final award has certainly
impacted the findings of the Arbitral Tribunal adversely and as a
consequence, vitiated the final decision of the Arbitral Tribunal. In view
of the same, such an award has to be construed to be in conflict with
the Public Policy of India thereby attracting Section 34(2)(b)(ii) of the
Act and is also vitiated by patent illegality under Section 34(2A) of the https://www.mhc.tn.gov.in/judis
Arb.O.P.(Com.Div.)No.134 of 2022
23/24
Act.
26. In the result, the impugned award passed by the Arbitral
Tribunal dated 08.2.2021 is hereby set aside and the above original
petition is allowed with costs of Rs.2,50,000/- (Rupees two lakhs
and fifty thousand only) payable by the respondent to the
petitioner. It is left open to the petitioner to take immediate steps to
reconstitute an arbitral tribunal by filing a proper petition before this
Court to enable the claims made by the petitioner to be referred to the
newly constituted arbitral tribunal.
02.1.2026
RS https://www.mhc.tn.gov.in/judis
Arb.O.P.(Com.Div.)No.134 of 2022
24/24
N.ANAND VENKATESH,J
RS
Arb.O.P.(Com.Div.) No.134 of 2022
02.1.2026 https://www.mhc.tn.gov.in/judis
Legal Notes
Add a Note....