1
AFR
Neutral Citation No. - 2025:AHC:43599-DB
RESERVED
Court No. - 3
Case :- WRIT - C No. - 15023 of 2024
Petitioner :- M/S Anandeshwar Agro Foods Private Ltd
Respondent :- State Of Up And 3 Others
Counsel for Petitioner :- Sr. Advocate,Utkarsh Prasad
Counsel for Respondent :- C.S.C.
Hon'ble Anjani Kumar Mishra,J.
Hon'ble Jayant Banerji,J.
(Per: Hon. Jayant Banerji,J.)
1. This writ petition has been filed seeking quashing of the
demand notice/ order dated 19.2.2024 and the order cancelling the
mining lease dated 27.2.2024 both passed by the District Magistrate,
Kanpur Dehat. Also under challenge is the order of 18.4.2024 passed
by the Special Secretary, Geology and Mining, U.P. in Revision No.
33(R)/G&M/(U.P)/2024, M/s. Anandeshwar Agro Foods Pvt. Ltd.
vs. District Magistrate, Kanpur Dehat (Annexure-1 to the writ
petition) filed by the petitioner whereby his revision has been
rejected. A further prayer seeks direction to the respondents not to
demand any monthly installments specified in the lease deed for the
months of October, November and December, 2023, and, January
and February, 2024.
2
2. An advertisement/auction notice dated 3.12.2018 was issued
by the District Magistrate, Kanpur Dehat for grant of mining leases
of sand/morrum under Chapter IV of the U.P. Minor Mineral
(Concession) Rules, 1963
1
by e-tender cum e-auction for a period of
five years for all vacant mining areas in Kanpur Dehat district. The
bid of the petitioner, in respect of plot No.58 measuring 08.275
hectares at Village-Bilaspur Kachhar, Tehsil-Sikanda, District-
Kanpur Dehat, of Rs.264 per cubic meter, being the highest bid, was
approved by the District Magistrate and a Letter of Intent was issued
to the petitioner on 5.2.2019. The petitioner applied for a mining
plan which was sanctioned by the competent authority and thereafter
the petitioner applied for obtaining an Environment Clearance
Certificate, which was granted to the petitioner on 15.1.2021.
Thereafter, a lease-deed was executed in favour of the petitioner on
12.3.2021 for a period of five years permitting winning of 1,10,057
cubic meters per annum of sand/morrum with the installments
(excluding the security amount) for the first year totaling
Rs.2,90,55,048.00 and for each successive year, the royalty payable
would be increased by 10% on the royalty payable in the previous
year. An amount of Rs.2,20,31,460.00 was deposited by the
petitioner as security.
3.It is stated that the petitioner had carried out mining operations
and paid the entire installments due upto 30.6.2023 as per the
payment schedule specified in the lease-deed. A notice dated
2.6.2023 was issued by the Additional District Magistrate
(Administration), Kanpur Dehat directing the petitioner to get the
pre-monsoon and post-monsoon replenishment study done of his
mining area. The petitioner got the replenishment study of pre-
1Rules, 1963
3
monsoon done on 25.6.2023. It is stated that even after post-
monsoon, the leased area was completely submerged and, hence, it
was not possible to carry out post-monsoon survey and no mining
operations were possible and, therefore, the petitioner moved an
application on 5.10.2023 before the District Magistrate requesting
him not to compel the petitioner to deposit the lease amount post-
monsoon till the replenishment study was done. It is stated that the
post-monsoon survey was done on 29.10.2023 and a combined
report of pre-monsoon and post-monsoon was submitted before the
District Magistrate. The Mines Officer issued a demand notice dated
25.11.2023 demanding the installment of October and November
2023. The petitioner moved an application dated 28.11.2023 stating
that the entire leased area is submerged and a very small patch of
surface was seen which belonged to the restricted area. Again, a
request was made by the petitioner to the District Magistrate to
waive off the installment for the period starting from 1.10.2023 till
actual commencement of the mining operations.
4. Again, the Mines Officer issued a demand notice to the
petitioner on 4.12.2023 demanding the due installments. The
petitioner sent an application dated 11.12.2023 to the District
Magistrate requesting him to waive off the installments for the
period with a further request that the petitioner be allowed to get the
leased area re-assessed by the competent agency for proper
compliance and verification of the actual mineable reserve.
5. By a letter dated 21.12.2023, the District Magistrate rejected
the aforesaid applications of the petitioner on the ground that it is the
responsibility of the petitioner to pay the installments stated in the
lease-deed. The petitioner again on 8.1.2024 got the leased area re-
inspected for post-monsoon replenishment study for assessing the
4
quantity of available mineral. It is stated that the new replenishment
study report of 08.01.2024 reflected no significant replenishment of
river bed mineral and the replenished mineral on the leased land on
that date was 16,380 cubic meters. The opinion in this replenishment
study was that the mineral quantity may increase in future once the
water recedes.
Thereafter, the petitioner moved an application dated
27.1.2024 indicating his willingness to initiate mining operations
provided the installments for the disrupted period from 1.10.2021 till
the actual commencement of mining operations be waived and
further installments be 're-evaluated' as per the actual mineral
recharge/replenished quantity as found in the post-monsoon
replenishment study report. This application of the petitioner was
rejected by the District Magistrate by means of a demand
notice/order dated 19.2.2024. It is stated that the impugned order
dated 27.2.2024 was received by the petitioner on 29.2.2024 by
email canceling the mining lease of the petitioner. The petitioner
then filed a revision before the State Government which was
dismissed by the impugned order dated 18.4.2024.
6.It is contended by the learned counsel for the petitioner that
the cancellation of the mining lease and the rejection of the revision
of the petitioner is without consideration of the evidence and against
the statutory provisions. It is stated that once an area is declared by
the State Government to be leased out by e-tender/e-auction/e-tender
cum e-auction, the District Officer is mandated to get that declared
area evaluated for the quality and quantity of mineral for fixing
minimum bid or offer which is to be done by the Director, Geology
and Mining, Uttar Pradesh or by an officer authorised by him; that
the replenishment study is required to be conducted as per the orders
5
of the National Green Tribunal
2
; that it was incumbent on the State
Government to make available the quantity of mineral required for
excavation on the basis of which the petitioner would pay the
installments of lease amount, otherwise the petitioner would be
entitled for refund or remission of the installments; that if the State
Government fails to provide mineral for excavation, then no lease
instalment amount is payable; and that the notice issued under Rule
59 of the U.P. Minor Mineral (Concession) Rules, 2021
3
is required
to be issued by the District Magistrate and not by the Mines Officer.
In this view of the matter, it is contended that the District Magistrate
having given the last notice on 19.2.2024, and the order canceling
the lease having been passed on 27.2.2024, there is violation of Rule
59 of the Rules, 2021 which mandates 30+15 days notice.
In support of his contentions, learned counsel for the petitioner
has relied upon the judgment of the Supreme Court in Dharmendra
Kumar Singh vs. State of Uttar Pradesh
4
; a judgment dated
10.4.2018 passed by the Supreme Court in the case of M/s. Planet
Steel Pvt. Ltd. vs. The State of Haryana & Ors.
5
; a decision of a
coordinate Bench of this Court dated 11.1.2021 in the case of Vipul
Tyagi vs. State of U.P. & 6 Ors.
6
and a decision of this Court dated
24.10.2019 in the case of Ranjana Singh vs. State of U.P. & Ors.
7
.
7.A counter affidavit has been filed on behalf of the respondents
stating that the lease-deed was executed on 12.3.2021 in respect of
the leased area for excavation of 110057 cubic meters of
sand/morrum per annum at the rate of Rs.264/-. The amount of
security, the annual amount payable and the installments due and
2NGT
3Rules, 2021
4(2021) 1 SCC 93
5Petition for Special Leave to Appeal (C) Nos.19619-19620/2017
6Writ-C No.17258 of 2020
7Writ-C No.32486 of 2019
6
payable were specified in the lease-deed itself. It has been stated that
material facts have been concealed in the instant writ petition
inasmuch as Writ-C No.9186 of 2022 was filed by the petitioner
before the Lucknow Bench of this Court seeking the following
reliefs:-
“1. issue a writ, order or direction in the nature of certiorari
quashing the Government Order dated 9.11.2022 issued by
the State Government i.e. Respondent no.1, contained as
Annexure No.1 to this writ petition.
2. Issue a writ, order or direction in the nature of
mandamus directing the respondents to waive of the liability
of deposit of the royalty amount of the month of October
2022 & November 2022 so far it relates to the mining lease
of the petitioner and do not compel to the petitioner to
deposit the royalty amount for the aforesaid two months as
no mining activity has taken place in the aforesaid months.
3. to issue any other writ, order or direction which this
Hon'ble Court may deem fit and proper in the circumstances
of the case.
4.to award cost of the petition to the petitioner.”
In response to aforesaid petition, a counter affidavit was filed
by the respondents opposing the writ petition and that petition is
pending before the Lucknow Bench of this Court.
8.It is stated in the counter affidavit to the present petition that
the notices dated 25.11.2023 and 4.12.2023 as well as the notices
dated 21.12.2023 and 19.2.2024 were issued to the petitioner; that
the representations filed by the petitioner were rejected on
21.12.2023 on the ground that nine months' time was available to the
petitioner for mining for excavating the annual quantity of sand and
sell it as per the market rate available and accordingly upload Form
eMM-11 to the extent of the carried forward quantity in the
preceding month that could not have been mined; that the pre-
monsoon and post-monsoon replenishment study reports are
7
contradictory and cannot be relied upon for any purpose by this
Court; that post-monsoon replenishment report reflects a quantity of
16380 cubic meters of mineral available for mining which may
further increase in future; that the amount of mineral could be
excavated by the petitioner but he chose not to carry out any mining
operations; that a surrender application for surrendering the mining
lease as per Rule 30 of the Rules 2021 could have been filed by him
but no such application was filed; that the petitioner has not brought
on record the inspection report dated 13.2.2023; that illegal mining
was being done in violation of Rule 42h(1) of the Rules, 2021,
whereafter a notice dated 21.2.2023 was given to the petitioner
imposing a penalty of Rs.5 lacs which notice has not been replied by
the petitioner. In paragraph nos.18 and 19 of the counter affidavit, it
is stated as follows:-
“18. That it is humbly submitted before this Hon'ble Court
that in case the lease holder is unable to extract the quantity
of sand in a particular month then upon payment of the
royalty amount the quantity not excavated is carried forward
on the portal of the department automatically. It is also
submitted herein that the practice and procedure is that in
case the lease holder is to extract an additional quantity of
sand, that he is unable to in a particular month, he has to pay
the royalty amount of the succeeding month and extract the
carried forward quantity (that was not extracted) of sand to
be excavated in the next month. The said amount of sand has
to be excavated keeping in view the annual quantity of sand
to be extracted as per the amount mentioned in the
Environmental Clearance Certificate.
19. That in the facts of the present case the amount of sand
that could have been extracted in a particular year by the
petitioner herein is 1,10,0057 cubic meter (sic, 110057) and
12,228.55 cubic meter per month. If the amount of
12,228.55 cubic meter could not be extracted by the
petitioner in a particular month then the left over amount
could be carried forward by him in the next month and
extracted accordingly. The petitioner herein from Jan. 2023
to June 2023 has extracted sand in excess of 12,228.55 cubic
meter and the generated EMM-11 form alongwith the
8
production quantity bearing lease ID No. 313623 bearing
Lease ID No. 313623090133 is being brought on record and
is being filed herewith and marked as Annexure No.CA-9 to
this Affidavit.”
9.In the enclosure mentioned in paragraph no.19 of the counter
affidavit, a table showing the production month, generated eMM-11
form and the production quantity in cubic meters is reflected, which
has not been denied in the rejoinder affidavit and is as follows:-
Sr.
No.
Lease Holder
Name
Production
Month
Generated
eMM 11
Production
Quantity
(Cubic
meter)
01
Sunil Kumar
Gupta
Lease ID-
313623090133
January, 2023711 14750
02 February, 2023769 15926
03 March, 2023581 11907
04 April 826 16990
05 May, 2023 707 13864
06 June, 2023605 12373
It is, therefore, contended that the orders passed by the District
Magistrate as well as the State Government are justified.
10.In the rejoinder affidavit, the petitioner has relied upon a
Government Order dated 12.11.2021 while stating that the relaxation
was granted by the State Government in the payment of the lease
amount proportionate to the quantity of mineral which the petitioner
could not lift and the Government Order directed that the quantity
which could not be lifted could be deducted from the annual quantity.
As regards the table filed alongwith the counter affidavit
showing the Form eMM-11 generated by the petitioner and the
amount of production of the mineral, it has been stated that the
calculations were for the period from January 2023 to June 2023,
when there was sufficient mineral available in the mining area and
9
the petitioner had paid the entire lease amount uptil June. It is stated
that in the present case, the entire area was submerged and,
therefore, there was no occasion for carrying forward the minerals to
be excavated. The dispute relates to the period commencing October
2023.
ANALYSIS
11.The emphasis of the petitioner is on the loss being suffered by
the petitioner despite his every attempt to bonafide work the mining
lease granted to him, due to lack of proper evaluation of the mining
area and want of preparation of a District Survey Report
8
which is
mandated to be prepared after a replenishment study is conducted as
per the Sustainable Sand Mining Management Guidelines-2016
9
,
which was supplemented with the Enforcement and Monitoring
Guidelines for Sand Mining-2020
10
. It has also been stated that the
State Level Environment Impact Assessment Authority, Uttar
Pradesh, in its meeting held on 31.12.2022, had directed the Mines
Department to ensure that no mining is carried out beyond the
quantity mentioned in the replenishment study report.
12.The EMGSM-2020 was formulated by the Ministry of
Environment, Forest and Climate Change, Government of India. The
Ministry had earlier formulated the SSMMG-2016 which focuses on
the management of sand mining in the country. However, while
observing in the EMGSM-2020 that apart from management and
systematic mining practices, there is an urgent need to have
guidelines for effective enforcement of regulatory provisions and
their monitoring, the rampant and illegal mining, transportation and
storage of minerals were noted with concern. The guidelines focus
8DSR
9SSMMG-2016
10EMGSM-2020
10
on the effective monitoring of sand mining from identification of
sand mineral sources, its dispatch and end-use by consumers and the
general public. It was felt necessary to identify the minimum
requirements across all geographical regions to have a uniform
protocol for monitoring and enforcement of regulatory provision
prescribed for sustainable sand and gravel mining.
13.After noting various directions issued by the NGT and the
Supreme Court from time to time, the EMGSM-2020 narrates the
necessity of complying with the directions of the NGT. Though
several requirements for monitoring and enforcement are mentioned,
however, certain important requirements are extracted below:-
“ii) The mining lease auctioned by State government as
per their Minor Mineral Concession Rules are granted of
Letter of Intent (Lol), but it has been observed that many of
the sites are not suitable w.r.t environmental aspects. In most
of the cases, the unplanned grant of mining lease leads to
formation of cluster and/or contiguous cluster of small
mining leases which sometimes is difficult to regulate and
monitor. In order to address such issues, more emphasis is
required on the preparation of District Survey Report and its
format for reporting.
iii) Mining Plan is an important document to assist the
mine owner to operate the mine in a scientific manner. States
have their own format for preparation of mining plan and it
is observed that recording of the initial level of mining lease
at shorter interval say 25m X 25 m grid interval is not
present.
iv) There is no practice for regular replenishment study
to ascertain the rate of depositing, plan and section needs to
be prepared based on the restrictions provided in letter of
intent and provisions of Sustainable Sand Mining
Management Guidelines 2016.
v) Environmental Clearance is a process wherein the
regulatory authorities after considering the potential
11
environment impact of mining clearance is granted with a
set of specific & standard conditions to carry out mining
operations, but often it is observed that letter of intent is
granted for a location which has less potential for mining
and not feasible for environment-friendly mining. This leads
to an unnecessary financial burden on the mine owners and
litigations. Thus, Lol should be preferably granted for those
locations which have the least possibility of an impact on the
environment and nearby habitation.
vi) It is the responsibility of the mine owner to obtain all
the statutory clearance and comply with the conditions
stipulated in the clearance letter. Mining should be carried
out within the mining lease area as per approved mining plan
or mining plan concurred by other regulatory authorities.
…..................
viii) The river reaches with sand provide the resource and
thus it is necessary to ascertain the rate of replenishment of
the mineral. Regular replenishment study needs to be carried
out to keep a balance between deposition and extraction.
This document provides the procedure to be followed for
conducting replenishment study.
14.The EMGSM-2020 highlights that preparation of the DSR is a
very important step and that sustainable sand mining in any part of
the country would depend on the quality of DSR. The DSR is
required to be prepared under the SSMMG-2016. The guidelines
emphasize detailed procedure to be followed for the purpose of
identification of areas of aggradation/deposition where mining can
be allowed and identification of areas of erosion and proximity to
infrastructural structures and installation where mining should be
prohibited. Calculation of annual rate of replenishment, allowing
time for replenishment after mining, identification of ways of
scientific and systematic mining; identifying measures for protection
of environment and ecology and determining measures for protection
of bank erosion, bench mark (BM) with respect to Mean Sea Level
12
(MSL) should be made essential in mining channel reaches (MCR)
below which no mining would be allowed. The judgment of the
NGT of 8.12.2017 in the matter of Anjani Kumar vs. State of U.P.
& Ors.
11
is referred in the guidelines in this regard, in which
judgment/order the following observation was made:
“It states that the main object of preparation of District Survey
Report is to ensure identification of areas of aggradation/deposition
where mining can be allowed and identification of areas of erosion
and proximity to infrastructural structures and installation where
mining should be prohibited and calculation of annual rate of
replenishment and allowing time for replenishment after mining
area. Thus, the environmental protection requires a strictly
regulated mining in terms of area, quantity as well as most
importantly replenishment thereof.”
Then, inter alia, the following order/direction was passed:
“The data collection and declared for preparation of DSR shall take
precedence over other data and would form the foundation for
providing mining lease in terms of Appendix- x to the Notification
dated 15th January 2016 must be prepared by the statutory
authority stated therein i.e. DEIAA prior to awarding of permits for
carrying on mining activity in any part of the State of UP.”
(emphasis supplied)
15.Considering the importance of DSR, for purpose of
preparation of comprehensive DSR for sand mining, certain
guidelines were formulated, which are encapsulated below :-
(a)District Survey Report for sand mining shall be
prepared before the auction/e-auction/grant of the mining
lease/Letter of Intent (LoI) by Mining department or
department dealing the mining activity in respective states.
(b)The first step is to develop the inventory of the River
Bed Material and Other sand sources in the District. In order
to make the inventory of River Bed Material, a detailed survey
of the district needs to be carried out, to identify the source of
River Bed Material and alternative source of sand (M-Sand).
11Original Application No. 557 of 2017
13
The source will include rivers, de-siltation of reservoir/dams,
Patta lands/Khatedari Land, M-sand etc. It was proposed that
for preparation of district survey report, the auditing of rivers
needs to be carried out.
(c)District Survey Report is to be prepared in such a way
that it not only identifies the mineral-bearing area but also
define the mining and no mining zones considering various
environmental and social factors.
(d)Identification of the source of Sand & M-Sand. The
sources may be from Rivers, Lakes, Ponds, Dams, De-silting
locations, Patta land/Khatedari lands.
(e)Defining the sources of Sand/M-Sand in the district is
the next step for identification of the potential area of
deposition/aggradation wherein mining lease could be granted.
Detailed survey needs to be carried out for quantification of
minerals. The purpose of mining in the river bed is for
channelization of rivers so as to avoid the possibility of
flooding and to maintain the flow of the rivers. For this, the
entire river stretch needs to be surveyed and original ground
level (OGL) to be recorded and area of aggradation/deposition
needs to be ascertained by comparing the level difference
between the outside riverbed OGL and water level.
(f)The permanent boundary pillars need to be erected after
identification of an area of aggradation and deposition outside
the bank of the river at a safe location for future surveying.
The distance between boundary pillars on each side of the
bank shall not be more than 100 meters.
(g)Identifying the mining and no mining zone shall follow
with defining the area of sensitivity by ascertaining the
distance of the mining area from the protected area, forest,
14
bridges, important structures, habitation etc. and based on the
sensitivity the area needs to be defined in sensitive and non-
sensitive area.
(h)Demand and supply of the Riverbed Material through
market survey needs to be carried out. In addition to this
future demand for the next 5 years also needs to be
considered.
(i)It is suggested that as far as possible the sensitive areas
should be avoided for mining, unless local safety condition
arises. Such deviation shall be temporary & shall not be a
permanent feature.
(j)The final area selected for the mining should be then
divided into mining lease as per the requirement of State
Government. It is suggested the mining lease area should be so
selected as to cover the entire deposition area. Dividing a large
area of deposition/aggradation into smaller mining leases
should be avoided as it leads to loss of mineral and indirectly
promote illegal mining.
(k)Cluster situation shall be examined. A cluster is formed
when one mining lease of homogenous mineral is within 500
meters of the other mining lease. In order to reduce the cluster
formation mining lease size should be defined in such a way
that distance between any two clusters preferably should not
be less than 2.5 Km. Mining lease should be defined in such a
way that the total area of the mining leases in a cluster should
not be more than 10 Ha.
(l)The number of a contiguous cluster needs to be
ascertained. Contiguous cluster is formed when one cluster is
at a distance of 2.5 Km from the other cluster.
(m)The mining outside the riverbed on Patta land/Khatedari
15
land be granted when there is possibility of replenishment of
material. In case, there is no replenishment then mining lease
shall only be granted when there is no riverbed mining
possibility within 5 KM of the Patta land/Khatedari land. For
government projects, mining could be allowed on Patta
land/Khatedari land but the mining should only be done by the
Government agency and material should not be used for sale
in the open market. Cluster situation as mentioned in para k
above is also applicable for the mining in Patta land/Khatedari
land.
(n)The State Government should define the transportation
route from the mining lease considering the maximum
production from the mines as at this stage the size of mining
leases, their location, the quantity of mineral that can be mined
safely etc. is available with the State Government. It is
suggested that the transportation route should be selected in
such a way that the movement of trucks/tippers/tractors from
the villages having habitation should be avoided. The
transportation route so selected should be verified by the State
Government for its carrying capacity.
(o) Potential site for mining having its impact on the forest,
protected area, habitation, bridges etc, shall be avoided. For
this, a sub-divisional committee may be formed which after
the site visit shall decide its suitability for mining.
(p)Public consultation-The comments of the various
stakeholders may be sought on the list of mining lease to be
auctioned. The State Government shall give an advertisement
in the local and national newspaper for seeking comments of
the general public on the list of mining lease included in the
DSR.
16
16.Para 4.2 of the EMGSM-2020 relates to grant of Letter of
Intent to those mining leases which are falling in potential mining
zones. It reads as under :-
“The State Government shall issue letter of intent as per
procedure laid down in their Minor Mineral Concession
Rules with due consideration of final district survey report.
The State Government shall ensure that all the letter of intent
shall have complete details of the mining lease including
geo- coordinate of the corner points, the involvement of
forest land, distance from the forest land, distance from the
protected area, distance from other sites of archaeological
importance, details of the cluster situation etc. The
demarcation of the boundaries of LoI/Lease area shall be
placed in public domain along with LoI/lease deed details.
The LOI should not be granted for mining area falling
on both riverbed and outside riverbed. Therefore, in the
same lease, both types of area should not be included.
The authority responsible for grant of lease for sand
mining shall ensure that annual audit of the sand mining
process, production and compliance of the imposed
conditions by regulatory authority (Environmental clearance
or mine plan) shall be one of the essential condition of the
lease agreement. The annual audit report shall be submitted
to the district administration, which shall be put in public
domain through the district website. Any deviation observed
shall be appropriately and in accordance with applicable law
shall be dealt by the concerned authority and corrective
measures shall also be taken to restoration of
ecological/environmental damage, if observed.”
17.Para 4.3 deals with preparation of mining plan which reads as
follows:-
“The preparation of Mining Plan is also very
important. The mining plan should include the original
ground level recorded at an interval not more than 10M x
10M along & across the length of the river. In addition to
this levels, outside the mining lease and bank of the river up
to meters needs to be recorded. In the mining plan, there
should be 3 plates for each year production & development
planning (pre-monsoon, monsoon and post-monsoon). The
time period of monsoon should be defined in the DSR. At
the time of review of the mining plan, the details of the
replenishment study conducted for all the years needs to be
included in the mining plan. The Mining Plan should include
17
the certificate from PCCF on forest land, distance from the
protected area, past production details for mining leases
seeking expansion.”
18.The considerations that are required to be kept in mind for
sand/gravel mining for approving mining plan have been specified,
relevant provisions of which, for purpose of this case are mentioned
below:-
(i)Parts of the river reach that experience deposition or
aggradation shall be identified. The Leaseholder/
Environmental Clearance holder may be allowed to extract the
sand and gravel deposit in these locations to manage
aggradation problem.
(ii) The distance between sites for sand and gravel mining
shall depend on the replenishment rate of the river. Sediment
rating curve for the potential sites shall be developed and
checked against the extracted volumes of sand and gravel.
(iii)Sand and gravel may be extracted across the entire
active channel during the dry season.
(iv)Abandoned stream channels on the terrace and inactive
floodplains be preferred rather than active channels and their
deltas and flood plains. Stream should not be diverted to form
inactive channel.
(v)Layers of sand and gravel which could be removed from
the river bed shall depend on the width of the river and
replenishment rate of the river.
(vi)The sediment sampling should include the bed material
and bed material load before, during and after the extraction
period. Develop a sediment rating curve at the upstream end of
the potential reach using the surveyed cross-section. Using the
historical or gauged flow rating curve, determine the suitable
period of high flow that can replenish the extracted volume.
18
Calculate the extraction volume based on the sediment rating
curve and high flow period after determining the allowable
mining depth.
(vii)Mining depth should be restricted to 3 meters and
distance from the bank should be 1/4
th
or river width and
should not be less than 7.5 meters.
19. Para 5 of the EMGSM-2020 provides for replenishment study,
which reads as follows:-
“5.0 Replenishment Study
The need for replenishment study for river bed sand is
required in order to nullify the adverse impacts arising due
to excessing sand extraction. Mining within or near riverbed
has a direct impact on the stream's physical characteristics,
such as channel geometry, bed elevation, substratum
composition and stability, in-stream roughness of the bed,
flow velocity, discharge capacity, sediment transport
capacity, turbidity, temperature etc. Alteration or
modification of the above attributes may cause an impact on
the ecological equilibrium of the riverine regime,
disturbance in channel configuration and flow-paths. This
may also cause an adverse impact on in-stream biota and
riparian habitats. It is assumed that the riparian habitat
disturbance is minimum if the replenishment is equal to
excavation for a given stretch. Therefore, to minimize the
adverse impact arising out of sand mining in a given river
stretch, it is imperative to have a study of replenishment of
material during the defined period.
5.1Generic Structure of Replenishment Study
Initially replenishment study requires four surveys.
The first survey needs to be carried out in the month of April
for recording the level of mining lease before the monsoon.
The second survey is at the time of closing of mines for
monsoon season. This survey will provide the quantity of the
material excavated before the offset of monsoon. The third
survey needs to be carried out after the monsoon to know the
quantum of material deposited/replenished in the mining
lease. The fourth survey at the end of March to know the
quantity of material excavated during the financial year. For
the subsequent years, there will be a requirement of only
three surveys. The results of year-wise surveys help the state
government to establish the replenishment rate of the river.
Based on the replenishment rate future auction may be
19
planned.
The replenishment period may vary on nature of the
channel and season of deposition arising due to variation in
the flow. Such period and season may vary on the
geographical and precipitation characteristic of the region
and requires to be defined by the local agencies preferable
with the help of the Central Water Commission and Indian
Meteorological Department. The excavation will, therefore,
be limited to estimated replenishment estimated with
consideration of other regulatory provisions.”
(emphasis supplied)
20.Paragraph 6 of the EMGSM-2020 provides for enforcement.
The mining operation and post environment clearance monitoring
are being below for purpose of this case :-
“6.1 Mining Operation:
The mining operations should be strictly carried out
in accordance with the approved mining plan and after
complying with all the conditions stipulated in
Environmental & Other Statutory Clearance. Mine owner
shall follow the operational procedure (for sale, dispatch,
storage, reserve reconciliation and transportation) as may be
defined by the concerned state government in its monitoring
guidelines. Mine owner should comply with the
recommendation and suggestion made by the High Power
Committee as applicable.
6.2 Post Environment Clearance Monitoring:
It's the responsibility of the EC Holder to comply
with the Environmental Clearance conditions and upload the
six-monthly EC compliance report on the website of the
Ministry. For the category, ‘A' mines (>100 Ha individual &
cluster) Regional Office of the MoEF&CC are entrusted to
carry out EC Monitoring and for the Category ‘B' Mines by
SEIAA. The monitoring shall be carried out as per the
procedure/schedule suggested by MoEF&CC from time to
time. MOEF&CC vide its notification S.O. 637(E) dated
28.02.2014 has delegated the power to State/Union Territory
Environmental Impact Assessment Authority to issue show
cause notice to project proponent in case of violation of
Conditions of Environmental Clearance issued by the said
authority and to issue direction for keeping the said EC in
abeyance or withdrawing it. Thus, for category ‘B’ (0 to 100
Ha) projects SEIAAs are responsible for EC monitoring.
21.Paragraph 8, and particularly Paragraph 8.1 deal with the
20
general approach to sustainable sand mining and prerequisite for
starting sand mining operation and are as follows:-
“8.0General Approach to Sustainable Sand Mining
8.1Pre-requisite for starting sand mining operation
i)All district to prepare a comprehensive mining plan
for the district as per the provision of District Survey Report.
These reports shall be put on the website of District
Administration. No mining shall be allowed in the area
which has not been identified in the comprehensive mining
plan of the District.
ii)Replenishment study should be conducted on regular
basis.
iii)All potential rivers mining zone/area shall be
identified and put for auction with proper geo-tagged details
by the auctioning authority concerned.
iv)The latitude and longitude of each mining lease shall
be clearly mentioned in Letter of Intent issued to the
potential mine lease. Such information shall be provided on
the website of the district administration.
v)The provision of these guidelines shall be considered
while identifying the potential stretches /locations and
boundaries of the leases for the minable area.
vi)The LoI holder shall seek Environmental Clearance
as per the provision of EIA Notification, and the regulatory
authority shall ensure that the provision suggested in
“Sustainable Sand Mining & Management 2016" and in this
documents, as applicable are part of the clearance
conditions.
vii)There shall be no river bed mining operation allowed
in monsoon period. The period as defined by IMD Nagpur
for each state shall be adhered with.
viii) The monitoring infrastructures including weighbridge
and adequate fencing of the lease area, CCTV, Transport
permits, etc, as suggested in this document shall be ensured
in order to reduce unrecorded dispatch.
ix) Regular monitoring of mined minerals and its
transportation and storage shall be ensured and all
information shall be captured at centralized database so that
easy tracking of illegal material can be done.
x) Annual audit of each mining lease shall be carried out
wherein three independent member of repute, nominated by
District administration shall also participate.”
22.Thus, perusal of the EMGSM-2020 guidelines reflects that the
Central Government has made provisions for undertaking detailed
21
exercise by taking into account several environmental factors with
regard to enforcement and monitoring of sand mining.
23.The concerns of the Central Government as reflected in the
aforesaid guidelines also find echo in Rules 10, 17 of Chapter II,
Rule 23 of Chapter IV, Rules 35, 36, 37, 38, 41, 42, 45 of Chapter V
and other provisions of Rules, 2021. It is pertinent to mention here
that the State Government also made the U.P. Minerals (Prevention
of Illegal Mining, Transportation and Storage) Rules, 2018.
24.It is pertinent to mention here that a defining moment for
environmentally sustainable and socially responsible mining of sand
and gravel occurred when the Supreme Court expressed its opinion
in this regard in the case of Deepak Kumar & Ors. vs. State of
Haryana & Ors.
12
wherein a direction was issued to the State
Governments to follow the guidelines issued by the Central
Government by framing appropriate rules. Pursuant to the order in
Deepak Kumar, after extended deliberations and study, a draft
Notification
13
was issued by the Ministry of Environment, Forest and
Climate Change on 15.1.2016 bearing S.O. 141(E) under the
provision of sub-section (1) and clause (v) of sub-section (2) of
Section 3 of the Environment (Protection) Act, 1986. This draft
Notification of 2016 was for the express purpose for making certain
amendments to the Environmental Impact Assessment Notification,
2006 issued vide number S.O. 1533(E) dated 14.9.2006 which was
published under sub-rule (3) of Rule 5 of the Environment (Protection)
Rules, 1986 vide number S.O. 2588(E) dated 22.9.2015. The aforesaid
Notification was also issued in compliance of certain observations
made by the National Green Tribunal vide its order dated 13.1.2015
in the matter of sand mining wherein a direction was issued for
12(2012) 4 SCC 629
13Notification of 2016
22
making a policy on environmental clearance for mining leases in
cluster for minor mineral.
25.It is important to note that in the case of Deepak Kumar
(supra), a Committee was directed by the Supreme Court to examine
whether there had been an attempt to flout the aforesaid Notification
dated 14.9.2006 by breaking the homogeneous area into pieces of
less than 5 hectares, and that whether the activities going on in that
area had any adverse environmental impact.
The Supreme Court recorded a finding that it was without
conducting any study on the possible environmental impact on/in the
river beds and elsewhere, the auction notices had been issued. The
Supreme Court was of the considered view that when faced with a
situation where extraction of alluvial material within or near a river
bed has an impact on the river’s physical habitat characteristics, like
river stability, flood risk, environmental degradation, loss of habitat,
decline in biodiversity, it was not an answer to say that the extraction
(of sand etc.) was in blocks of less than 5 hectares, separated by 1
km., because their collective impact may be significant, hence
necessity of a proper environmental assessment plan.
26.In the case of Deepak Kumar (supra), the issues and
recommendations made by the Ministry were considered which
provided for, inter alia, that the States and Union Territories would
see that mining of minor minerals is subjected to simpler but strict
regulatory regime after taking into account the various factors. For
evolving model guidelines, draft Model Guidelines regarding
Environmental Aspect of Quarrying and of Minor Minerals was sent
by a communication from the Ministry of Mines, calling for inputs.
Accordingly, directions were issued to the Central and States
Governments regarding compliance to the recommendations made
23
by the Ministry in its report of March 2010 and the Model
Guidelines framed by the Ministry of Mines.
27.By the Notification of 2016, an amendment was sought to be
incorporated in the Notification of 2006 regarding preparation of
DSR for sand mining or river bed mining and mining of other minor
minerals. An elaborate procedure prescribed for preparation of DSR
for sand mining or river bed mining and mining of other minor
minerals\ has been given in Appendix X thereof.
Needless to state that the Notification of 2016 issued by the
Ministry is binding on the State Government.
28.In view of the aforesaid background, after a declaration has
been made by the State Government under sub-rule (1) of Rule 23 of
the Rules, 2021, the District Officer is mandatorily required to get
the area or areas so declared evaluated for quality and quantity of
minerals for fixing the minimum bid or offer by the Director,
Geology and Mining, Uttar Pradesh or by an officer authorised by
him before the date fixed for e-tender/e-auction/e tender-cum-e
auction. Such an evaluation is mandatory and has to be done after
taking into account the various factors mentioned in Rule 10 of the
Rules, 2021. The guidelines in the EMGSM-2020 for preparation of
DSR are also factors for such evaluation.
29.As stated above, pre- & post- monsoon replenishment studies
are mandated in the EMGSM-2020 guidelines and the same are an
extension of the survey, demarcation and evaluation of the area or
areas declared under Rule 23. The purpose of the survey and the
evaluation that are requisites under the provisions of Chapter II and
Chapter IV of the Rules, 2021 are to inform the prospective bidders
at the auction/tender mining leases for minor minerals (sand and
24
morrum in this case) so that the prospective bidders are well aware
as to the quantity and quality of the minerals available in the
declared area before they place their bids. The State Government
cannot put the onus on the prospective bidders by stating that it is the
bidders who should undertake an inspection of the area and satisfy
themselves as to the quality and quantity of the minerals available at
the area proposed to be leased, when the Rules, 2021 and the
EMGSM-2020 guidelines require the State Government to undertake
that exercise.
30.The guidelines contained in the SSMMG-2016 and in the
EMGSM-2020 have been framed taking into account the judgments
of the Supreme Court, the High Courts and the NGT. These
guidelines appear to have been issued by the Central Government in
purported exercise of power to issue directions under Section 20-A
of the Mines and Minerals (Regulation and Development) Act,
1957
14
. The importance of the survey/evaluation by the State
authorities in the interest of the ecology and environment in respect
of the areas proposed to be leased under the Rules, 2021 cannot be
over-emphasized. It is the only available and prescribed manner by
which the State Government can make a realistic assessment as to
the extent to which mining can be permitted in the leased area after
taking into account the fragility of the ecology, the flora and fauna
and the rivers, as well as the impact on the environment.
31.As mentioned above, both a pre-monsoon survey and a post-
monsoon survey were got done by the petitioner as per the
instructions received from the State authorities. Without getting the
replenishment studies done, the petitioner could not re-commence
mining operations. As a matter of fact, the petitioner had submitted a
14Act, 1957
25
second post-monsoon replenishment study report on 8.1.2024 that
reflected replenished minerals on the said lease as 16380 cubic
meters. It was also stated in that replenishment study report that this
mineral quantity may increase in future once water recedes down
(sic). The State-respondents, in their counter affidavit, have sought
to dismiss a replenishment study report by a baseless statement, in
their counter affidavit, that analysis and conclusion of the
replenishment study report dated 29.10.2023 that no mining activity
can be done at all, is unworthy of being relied upon.
32.It is is not the case of the respondents that the replenishment
studies that were got done by the petitioner were by an agency not
accredited to NAPET/QCI, or that the agency was not empanelled as
an Exploration Agency by the Department, or that the replenishment
studies were made contrary to guidelines. It has also not been stated
that the DSR/ evaluation for the leased area was available for being
accessed by the petitioner. As a matter of fact the EMGSM-2020
guidelines reflect that often it is observed that letter of intent is
granted for a location which has less potential for mining and not
feasible for environment-friendly mining; that this leads to
unnecessary financial burden on the mine owners and litigations;
that thus, letter of intent should be preferably granted for those
locations which have the least possibility of an impact on the
environment and nearby habitation.
33.In the counter affidavit, the respondents have also stated that
the petitioner could have surrendered the lease under the provisions
of Rule 30 of the Rules, 2021 which it did not do. In our opinion,
such objections and defences cannot be taken by the respondents to
gloss over their inability in producing any evidence before this Court
that a survey and evaluation was undertaken in respect of the area
26
granted for mining lease to the petitioner and a DSR relating to the
area of mining lease to the petitioner was made by the respondents in
compliance of the Notification of 2016/SSMMG-2016 / EMGSM-
2020 which DSR was accessible to the petitioner prior to submitting
its bid.
34.Moreover, the notice of the Officer Incharge, Mines dated
2.6.2023 that is enclosed as Annexure No. 6 to the writ petition gives
a categorical direction to the petitioner to get the requisite
replenishment studies done and submit the same, failing which legal
proceedings would be initiated against the petitioner. It is not
demonstrated by the respondents that the petitioner did not intend to
work the mines under the mining lease.
35.In paragraph 39 of the writ petition, the petitioner has stated
that without the replenishment study report, no mining can be
conducted in the mining area after monsoon and, moreover, the first
post-monsoon replenishment study report clearly showed that the
mining area was submerged.
Further, in paragraph 40 of the writ petition, it has been stated
that the revisional authority as well as the District Magistrate had
failed to consider that the quantity of mineral to be excavated during
the period of lease is fixed by the State Government and the
petitioner has no control over the quantity and, therefore, it is the
State Government which fixes the quality and quantity to be
excavated by the lease-holder during the period of lease.
36.In reply to the aforesaid paragraphs of the writ petitions, the
respondents have referred to the statutory provisions referred
elsewhere in the counter affidavit and the conditions of lease-deed as
well as the obligation of the lease-holder to perform his part of the
contract. It has been stated that the petitioner cannot change or alter
27
the terms of the lease-deed according to his own convenience
thereby causing loss to the State exchequer.
Moreover, this Court finds that in the reply, references have
only been made to the Rule 29 of the Rules, 1963 and to Rule 30 of
the Rules, 2021. Rule 29 of the Rules, 1963 deals with the execution
of the lease-deed, while Section 30 of the Rules, 2021 deals with
surrender of the mining lease. We fail to understand how this meets
the submissions made on behalf of the petitioner. The respondents
allege that the petitioner is trying to “wriggle out of a contract at his
own mood swings, inasmuch as according to the own replenishment
report to the petitioner at one place he says that no amount of sand
is available for mining purposes and on the other hand in the second
report estimates 16380 cubic meter is available for mining
purposes”. Such a statement, in our opinion, is misplaced, uncalled
for and without proper understanding of the EMGSM-2020.
37.In paragraph 44 of the writ petition, it is stated as follows:-
“44.That, in the above-mentioned guidelines it was clearly
stated that the object and purpose of DSR was to identify a
minable area and thereby assessment of the minable quantity
and quality of the minerals, which was supposed to be
ascertained prior to the invitation to offer (E-auction/E-
tender /Advertisement) which was not acted in compliance
by the respondent authority.”
38.In reply thereto, it has been stated in the counter affidavit as
follows:-
“32. That the averments made in paragraph no. 43, 44, 45,
46, 47, 48, 49 and 50 of the writ petition are legal in nature
and hence need no specific reply however it is humbly
submitted that the said cases as cited by the petitioner are
not applicable in the facts and circumstances of the present
case and shall be duly distinguished at the time of hearing of
the present writ petition. The principles laid down in the writ
petition are based on mis-appreciation of facts and the legal
28
principles and do not provide for and shall suitably been
distinguished at the time of hearing of the present writ
petition.”
39.It is pertinent to mention here that it has not been stated in the
counter affidavit filed by the respondents that any DSR was prepared
after due survey and evaluation of the area sought to be auctioned.
No DSR has been produced. Therefore, we cannot but conclude that
the State Government has failed to demonstrate preparation of the
DSR in due compliance of the Notification of 2016/SSMMG-2016
and EMGSM-2020 guidelines. Moreover, the respondents have
openly rejected the first post-monsoon replenishment study report
submitted by the petitioner without ascribing any cogent reason for
such rejection.
40. The object of preparation of DSR is to ensure identification of
areas of aggradation/deposition where mining can be allowed;
identification of areas of erosion and proximity to infrastructural
structures and installation where mining should be prohibited; and
calculation of annual rate of replenishment and allowing time for
replenishment after mining in the area. Thus, environmental
protection requires strictly regulated mining in terms of area,
quantity of mineral as well as, and very importantly, replenishment
thereof.
41.The mining lease was granted in the land described in Part-I of
the Schedule to the lease deed, in Village-Bilaspur Kachhar, Plot
No.58 area 8.275 hectares for which the security amount was
deposited. The boundaries of Plot No.58 are shown as follows:-
North - Remaining part of Plot No.58, river Yamuna
South - Border of Plot No.58 thereafter river Yamuna in
village -Bichhavali
29
East - Remaining part of Plot No.58, thereafter agricultural
land of Plot Nos.42 to 56 and Plot No.57
West - Remaining part of Plot No.58, river Yamuna
Though the map has not been enclosed alongwith the
photocopy of the mining lease, it appears from the boundaries that
mining area under the lease granted to the petitioner may include the
river bed of the Yamuna river.
Given the EMGSM-2020 guidelines, it is not only the
availability of mineral after its replenishment as would be reflected
in the post monsoon replenishment study, but also the fact that at
which part of the river bed/bank, has the replenishment occurred.
42.Thus, the annual audit envisaged under the aforesaid
EMGSM-2020 guidelines and the replenishment study, both pre-
monsoon and post-monsoon, assume great importance keeping in
view the environment and ecology of the mining area. Mining within
or near river-beds has a direct impact on the stream's physical
characteristics, such as channel geometry, bed elevation, substratum
composition and stability, in-stream roughness of the bed, flow
velocity, discharge capacity, sediment transport capacity, turbidity,
temperature etc. Alteration or modification of the above attributes
may cause an impact on the ecological equilibrium of the riverine
regime, disturbance in channel configuration and flow-paths. This
may also cause an adverse impact on in-stream biota and riparian
habitats. It is assumed that the riparian habitat disturbance is
minimum if the replenishment is equal to excavation for a given
stretch. Therefore, the EMGSM-2020 guidelines recommends that it
is imperative to have a study of replenishment of material during the
defined period to minimize the adverse impact arising out of sand
mining in a given river stretch. The EMGSM-2020 guidelines
provides that the excavation will be limited to estimated
30
replenishment estimated with consideration of other regulatory
provisions.
43.Therefore, the fact that the second post-monsoon
replenishment study dated 8.1.2024 reflects replenishment of 16380
cubic meters of sand available for mining purpose has to be read in
light of the location where this deposit/replenishment has taken place
in the given river stretch. Then, it has to be ascertained in the light
of EMGSM-2020, whether such replenishment is minable.
44.The respondents seem to be quite oblivious of the importance
of proper replenishment, the mining plan and the DSR when they
seek to raise demands and make claims without addressing the
ecological concerns that are reflected in the EMGSM-2020
guidelines that also address the aspect of sustainable mining.
45.The respondents have sought to demonstrate the excavation of
85810 cubic meters of sand between January 2023 to June 2023
made by the petitioner during mining operations in the mining lease
area only to seek to contend that the petitioner is short by 24247
cubic meters of the total mining of 110057 cubic meters permissible
per annum under the terms of the lease which can be made good by
the petitioner once the water level of the recedes down. However,
such an assertion is made on the presumption that adequate
replenishment will take place in the area, without due regard to the
ecological aspects that require consideration during mining
operations and thereafter as reflected in the EMGSM-2020
guidelines.
46. In case no adequate replenishment takes place even after water
of river recedes down, then any advance payment of installments by
the petitioner would result in serious loss to it which eventuality is
31
neither contemplated in the lease deed nor in the Rules, 2021.
Therefore the contention sought to be made that payment of
installment should be made by the petitioner and eMM-11 forms be
uploaded to the extent of carried forward quantity of minerals which
could not have been mined in the preceding months till March 2024,
is fallacious.
47.There appears to be an effort to extract revenue from mining
operations for benefit of the State exchequer without empathy and
consideration of ecology, and sustainable mining, which aspects
have to be balanced with the imperatives of development and
earnings for the State exchequer.
48. No doubt, there is a contract, the lease-deed, entered into
between the respondents and the petitioner, the terms of which bind
them both. However, the terms of the lease-deed cannot override the
aforesaid Notification of 2016, the SSMMG-2016, EMGSM-2020
guidelines and the Act and Rules.
49.It is pertinent to mention here that in the counter affidavit, the
respondents harp on the availability of 16380 cubic meter of
replenished sand and that the second replenishment study report
reflects that after water recedes in the post-monsoon season, the
mineral quantity may increase in future once the water recedes
down.
Apart from the fact that this statement in the counter affidavit
is based upon without fully appreciating the opinion expressed in the
post monsoon replenishment study conducted on 8.1.2024 which
also stated that no significant replenishment of RBM was found as
no turbulent flooding was observed in that year, the post monsoon
replenishment study on 29.10.2023 reflects that the entire leased area
was submerged under active stream of river Yamuna and a very
32
small patch of surface was seen which belonged to the replenished
area. It was highly recommended that the lease holder shall await
receding of water for further survey. Whereafter the leased area
could be re-investigated for DGPS data in order to establish
replenished sand minerals. It was, therefore, stated that mining
activity was, therefore, not feasible in compliance of the
recommendation of SSMMG-2016.
50.Due and timely payment of installments under the terms of a
mining lease is based on winning existing minerals for which the
lease is granted which corresponds to the quality and quantity
contemplated in the DSR and the replenishment studies, particularly,
the post-monsoon replenishment study. If the post-monsoon
replenishment study does not reflect adequate replenishment in the
manner and to the extent envisaged in the EMGSM-2020, no mining
can be permitted in the area pertaining to the mining lease. As a
corollary, for want of adequate replenishment of the mineral or non-
availability of mineral in the requisite quantity in various other parts
of the area for which lease has been granted, neither can any mining
activity be permitted nor, consequently, can any claim for
installments be sustained unless there is actual replenishment or
availability. It is for these circumstances that preparation of proper
DSR and conducting audit assumes importance.
51.In the aforesaid background, we find that the case of the
petitioner has merit. The petitioner could not have been forced to
mine the relatively meagre amount of 16380 cubic meters of
replenished sand that was reflected in the last replenishment study
report submitted by the petitioner without ascertaining whether the
replenishment that had taken place in the stretch of land/river was
such that mining of the same could be permitted in the backdrop of
33
sustainable mining. There is no DSR shown to have been prepared.
52.As far as filing of Writ-C No.9186 of 2022 by the petitioner
before the Lucknow Bench of this Court is concerned, the same is
for a different cause of action. However, the petitioner’s choosing
both the Lucknow Bench of this Court as well as at Allahabad to file
different petitions, is not proper. Be that as it may.
53. For the reasons aforesaid, the impugned orders dated
18.4.2024, 27.2.2024 and 19.2.2024 cannot be sustained and are
hereby quashed.
54.However, since, by means of an affidavit filed alongwith a
stay application on 9.12.2024, we are informed that steps have been
taken by the State Government for fresh auction of the mining area
that was granted to the petitioner, we direct that the petitioner is not
liable to deposit any installment after the stoppage of mining
operations for the period from 1.7.2023 onwards. If any amount has
been deposited/recovered/confiscated by/against the petitioner, the
same shall be refunded within a period of one month from today
alongwith simple interest @ 9% per annum calculated from the date
of such deposit/recovery/confiscation till the actual payment.
55.Subject to the aforesaid observations, this writ petition is
allowed.
56.However, before parting, we deem it fit to direct the
respondents to ensure preparation of DSR in respect of every area
sought to be auctioned for mining of sand/gravel/morrum in
compliance of the Notification of 2006, as amended by the
Notification of 2016, the SSMMG-2016 and EMGSM-2020.
Order Date :- 26.3.2025
SK
Legal Notes
Add a Note....