As per case facts, the petitioner's contract was terminated, and they were blacklisted for two years without a specific show-cause notice, despite a performance notice being issued. The petitioner argued ...
1
CGHC010271272026 2026:CGHC:30849-DB
NAFR
HIGH COURT OF CHHATTISGARH AT BILASPUR
WPC No. 3783 of 2026
M/s. Dynami Enterprises A Registered Partnership Firm Having Office At -
65, Globus Town Ship, Near Indralok Nagar, Ratlam, Madhya Pradesh
Represented Through Its Partner, Shri Shivram Meena Aged About 62
Years, Having Office At 65- Globas Township, Near Indralok Nagar,
Ratlam (Madhya Pradesh)
... Petitioner
versus
1 - Union Of India Represented Through Its General Manager, South East
Central Railways, Bilaspur, Chhattisgarh
2 - Senior Divisional Mechanical Engineer (Freight) , Bhilai, South East
Central Railway, Raipur, Chhattisgarh
3 - Senior Divisional Mechanical Engineer (Freight ), Bhilai, South East
Central Railway, Bhilai, Chhattisgarh
... Respondents
(Cause-title taken from Case Information System)
For Petitioner :Mr. Abhishek Vinod Deshmukh, Advocate
For Respondents :Mr. Ramakant Mishra, Deputy Solicitor
General
Hon'ble Shri Ramesh Sinha, Chief Justice
Hon'ble Shri Ravindra Kumar Agrawal , Judge
Order on Board
Per Ramesh Sinha , Chief Justice
21.07.2026
1.Heard Mr. Abhishek Vinod Deshmukh, learned counsel for the
petitioner as well as Mr. Ramakant Mishra, learned Deputy
Solicitor General, appearing for the respondents.
2
2.Though the matter is listed as a fresh case, considering the
submission of learned counsel appearing for the respondents that
no reply is required to be filed in the present matter as the
agreement contains an arbitration clause and that no show-cause
notice has been issued to the petitioner, accordingly, with the
consent of learned counsel for the parties, the matter is heard
finally at the admission stage itself.
3.By filing the present petition under Article 226 of the Constitution of
India, the petitioner calls in question the termination letter dated
01.04.2026, whereby its contract has been terminated and it has
also been debarred/blacklisted from participating in future tenders
for a period of two years. The petitioner has prayed for following
relief(s) :-
“1] That, this Hon'ble Court may kindly be
pleased to writ/writs, order/orders,
direction/directions quashing the termination
notice dated 01.04.2026 issued by the
Respondent No. 3, whereby the Contract of the
Petitioner has been terminated and the Petitioner
has been debarred for a period of 2 years from
participating in the bids;
2] That, this Hon'ble Court may kindly be pleased
to grant any other relief(s), which is deemed fit
and proper in the aforesaid facts and
circumstances of the case.”
4.Briefly stated, the petitioner is a partnership firm engaged in
providing services to the Indian Railways. The respondents issued
3
a Notice Inviting Tender for hiring two diesel-operated 3T forklifts
along with operators at ROH Depot, PP Yard, Bhilai for a period of
two years. The petitioner participated in the tender process and,
having emerged as the successful bidder, was awarded the
contract vide agreement dated 26.05.2025 for execution of the said
work.
5.Pursuant to the award of the contract, the petitioner deployed the
requisite machinery, operators and supervisory staff and
commenced execution of the work. According to the petitioner, it
kept the respondents informed regarding deployment of equipment,
appointment of personnel, readiness to commence operations and
other operational requirements. It is further the petitioner's case
that whenever any difficulty arose during execution of the contract,
including repair of machinery or submission of requisite documents,
the same was duly intimated to the respondents and necessary
permissions were sought. The petitioner also claims to have
brought to the notice of the respondents instances of unauthorized
use of the deployed vehicles and sought permission to install CCTV
cameras for effective monitoring.
6.It is the petitioner's case that while the contract was being
performed, the respondents issued a performance notice dated
27.02.2026 alleging deficiencies in execution of the work.
Thereafter, without issuing the mandatory seven days' notice
contemplated under the General Conditions of Contract and without
affording any opportunity to explain the alleged deficiencies or to
4
show cause against the proposed debarment/blacklisting, the
respondents issued the impugned termination letter dated
01.04.2026, whereby the contract of the petitioner was terminated
and the petitioner was debarred/blacklisted from participating in any
tender floated by the concerned Railway Division for a period of two
years.
7.Learned counsel for the petitioner submits that the impugned order
of termination coupled with the order of debarment/blacklisting is ex
facie arbitrary, illegal and violative of the principles of natural
justice. It is contended that the respondents have acted in complete
disregard of the procedure prescribed under the General
Conditions of Contract. Though a performance notice dated
27.02.2026 was issued, the mandatory seven days' notice
contemplated under Clause 7.4.2 of the Contract was never served
upon the petitioner before issuance of the final termination order. It
is, therefore, submitted that the termination itself is contrary to the
contractual stipulations and is liable to be set aside.
8.It is further submitted that the respondents have also
debarred/blacklisted the petitioner for a period of two years without
issuing any specific show-cause notice proposing such action or
affording an effective opportunity of hearing. Learned counsel
argues that blacklisting visits a contractor with serious civil and
commercial consequences and, therefore, strict adherence to the
principles of natural justice is mandatory. In support of the said
contention, reliance is placed upon the decisions of the Hon'ble
5
Supreme Court in Gorkha Security Services v. Government
(NCT of Delhi), (2014) 9 SCC 105 and UMC Technologies (P)
Ltd. v. Food Corporation of India, (2021) 2 SCC 551, wherein it
has been held that a valid show-cause notice must specifically
indicate the proposed action of blacklisting and an order travelling
beyond the scope of such notice is unsustainable in law.
9.Learned counsel lastly submits that although the dispute arises out
of a contract, the writ petition is maintainable as the respondents,
being instrumentalities of the State within the meaning of Article 12
of the Constitution of India, are required to act fairly, reasonably
and in accordance with law. It is argued that where the decision-
making process is arbitrary, unreasonable or violative of the
principles of natural justice, this Court, in exercise of its jurisdiction
under Article 226 of the Constitution of India, can judicially review
such action notwithstanding the contractual relationship between
the parties.
10.On the other hand, learned counsel appearing for the respondents
opposes the writ petition and submits that the impugned action has
been taken strictly in accordance with the terms and conditions
governing the contract. It is contended that the petitioner had failed
to perform its contractual obligations satisfactorily and committed
repeated defaults during execution of the work, which adversely
affected the functioning of the Railway administration. It is
submitted that despite being afforded sufficient opportunities to
rectify the deficiencies, the petitioner failed to improve its
6
performance, compelling the competent authority to invoke the
relevant clauses of the contract and pass the impugned order of
termination. It is argued that the decision has been taken after due
consideration of the petitioner's overall performance and does not
warrant interference in exercise of writ jurisdiction.
11.Learned counsel further submits that the relationship between the
parties is purely contractual and the rights and obligations of the
parties are regulated by the terms of the agreement. The petitioner
seeks adjudication of disputed questions of fact relating to
performance of contractual obligations, which cannot conveniently
be examined in proceedings under Article 226 of the Constitution of
India. It is argued that judicial review in contractual matters is
limited to examining the decision-making process and not the
merits of the decision itself. In the absence of any allegation of
mala fides, arbitrariness or violation of any statutory provision, no
interference is called for with the impugned action.
12.It is further submitted that the dispute arises out of a contract
containing an arbitration clause and, therefore, the writ petition is
not maintainable. It is also submitted that no show-cause notice
has been issued to the petitioner. Learned counsel further submits
that the order debarring the petitioner from participating in future
tenders has been passed by the competent authority keeping in
view the petitioner's unsatisfactory performance and in larger public
interest so as to ensure efficient execution of public contracts. It is
contended that the respondents have acted fairly, reasonably and
7
within the four corners of the contract, and the impugned order
neither suffers from any procedural infirmity nor violates the
principles of natural justice.
13.We have heard learned counsel for the parties at length,
considered their rival submissions with due care and perused the
pleadings and documents available on record.
14.The controversy involved in the present writ petition lies in a narrow
compass. The petitioner calls in question the order dated
01.04.2026 whereby the respondents have terminated the contract
awarded in favour of the petitioner for hiring two diesel-operated
forklifts at ROH Depot, PP Yard, Bhilai and have simultaneously
debarred/blacklisted the petitioner from participating in future
tenders of the Railway Division for a period of two years. The
principal contention of the petitioner is that though a performance
notice dated 27.02.2026 was issued, the respondents, without
adhering to the contractual procedure prescribed under the General
Conditions of Contract and without issuing any specific show-cause
notice proposing blacklisting, proceeded to terminate the contract
and impose the additional penalty of debarment. The respondents,
on the other hand, contend that the petitioner committed repeated
defaults in performance and, therefore, the competent authority
was fully justified in invoking the contractual provisions and passing
the impugned order.
15.Before adverting to the rival submissions on merits, it is necessary
8
to deal with the preliminary objection regarding maintainability of
the writ petition. Learned counsel appearing for the respondents
submits that Clause 8.2 of the agreement provides for resolution of
disputes through arbitration and, therefore, the petitioner ought to
be relegated to the contractual remedy. It is true that where parties
have consciously agreed upon an arbitral mechanism, the Court
would ordinarily decline to exercise its extraordinary jurisdiction
under Article 226 of the Constitution in matters arising purely out of
contractual obligations. However, it is equally well settled that the
existence of an arbitration clause does not by itself operate as an
absolute bar to the exercise of writ jurisdiction where the action of
the State or its instrumentalities is alleged to be arbitrary,
unreasonable, violative of the principles of natural justice or where
the challenge is directed to the decision-making process rather
than to the merits of the contractual dispute. The Supreme Court
has consistently held that contractual dealings of the State continue
to possess a public law element requiring fairness and non-
arbitrariness and, therefore, judicial review under Article 226 is not
completely excluded merely because the contract contains an
arbitration clause.
16.Tested on the aforesaid principles, this Court finds that the present
petition cannot be rejected at the threshold solely on the basis of
Clause 8.2 of the agreement. The grievance of the petitioner is not
confined merely to enforcement of contractual rights. The challenge
is directed against the manner in which the respondents have
9
exercised their power by terminating the contract and
simultaneously blacklisting the petitioner for a period of two years.
The latter consequence undoubtedly visits the petitioner with
serious civil and commercial consequences extending far beyond
the four corners of the contract. The issue, therefore, involves
examination of compliance with the principles of natural justice and
fairness in administrative action, which squarely falls within the
ambit of judicial review under Article 226 notwithstanding the
availability of an arbitral remedy. The arbitration clause may govern
disputes arising out of performance of contractual obligations, but it
cannot be construed as excluding judicial scrutiny where the
impugned action is alleged to be arbitrary or violative of
fundamental procedural safeguards.
17.Having held that the writ petition is maintainable to the aforesaid
extent, the challenge to the impugned order deserves to be
examined under two distinct heads, namely, (i) termination of the
contract, and (ii) debarment/blacklisting of the petitioner for a period
of two years. Though both consequences have been incorporated
in a composite order dated 01.04.2026, they stand on different legal
footings and require independent examination. While termination of
the contract is essentially governed by the contractual stipulations
agreed between the parties, the order of blacklisting carries
independent penal and stigmatic consequences affecting the
petitioner's right to participate in future Government contracts and,
therefore, must satisfy the requirements of fairness and natural
10
justice recognised by law.
18.At the outset, this Court deems it appropriate to consider the
objection regarding maintainability of the writ petition in view of the
existence of an arbitration clause contained in Clause 8.2 of the
agreement. It is true that disputes arising purely out of contractual
obligations are ordinarily required to be resolved through the
dispute resolution mechanism agreed upon between the parties.
The law is well settled that where parties have consciously
incorporated an arbitration clause, the Court would normally be
slow in exercising jurisdiction under Article 226 of the Constitution
of India in matters involving adjudication of disputed questions of
fact relating to performance of contractual obligations. At the same
time, it is equally settled that the existence of an arbitration clause
does not operate as an absolute bar to the exercise of writ
jurisdiction where the action of the State or its instrumentalities is
alleged to be arbitrary, unreasonable, violative of the principles of
natural justice, or where the challenge is directed to the decision-
making process itself.
19.Tested on the aforesaid principles, this Court finds that the
challenge raised by the petitioner requires examination under two
distinct compartments, namely, (i) termination of the contract, and
(ii) debarment/blacklisting of the petitioner for a period of two years.
Though both consequences have been incorporated in the
composite order dated 01.04.2026, they stand on different legal
footings. Termination of the contract is essentially governed by the
11
terms and conditions of the agreement and disputes relating
thereto may ordinarily fall within the ambit of Clause 8.2 of the
agreement. However, the order of debarment/blacklisting is not
merely a contractual consequence; it carries independent penal
and stigmatic civil consequences affecting the petitioner's future
right to participate in Government contracts. Therefore,
proceedings relating to termination and blacklisting cannot be
conflated and each action must satisfy its own legal requirements.
The Supreme Court has recently reiterated that blacklisting
proceedings stand on a distinct footing and demand stricter
adherence to the principles of natural justice.
20.Insofar as the termination of the contract is concerned, the
respondents contend that the petitioner failed to satisfactorily
perform its obligations and, therefore, the competent authority was
justified in invoking the relevant contractual provisions. The
petitioner, on the other hand, disputes the allegations and asserts
that the mandatory procedure prescribed under the General
Conditions of Contract was not followed, inasmuch as after
issuance of the performance notice dated 27.02.2026, no seven
days' notice as contemplated under the contract was issued before
passing the final order dated 01.04.2026. Such disputes, involving
interpretation of contractual clauses and determination of factual
aspects relating to performance of obligations, ordinarily fall within
the realm of contractual adjudication and are amenable to the
mechanism contemplated under Clause 8.2 of the agreement. This
12
Court, while exercising jurisdiction under Article 226 of the
Constitution, would ordinarily refrain from entering into disputed
questions relating purely to performance of contractual obligations,
particularly when an agreed arbitral mechanism is available to the
parties.
21.The position, however, stands on a substantially different footing
insofar as the order of debarment/blacklisting is concerned.
Blacklisting is not a mere administrative formality or an incidental
consequence of termination of a contract. It is a serious punitive
measure having the effect of debarring a person from participating
in future Government contracts and casts a stigma on the
commercial reputation of the contractor. The Supreme Court in
Gorkha Security Services (supra) and thereafter in UMC
Technologies Private Limited (supra), has held that blacklisting
entails grave civil consequences and that a valid show-cause
notice must specifically disclose not only the allegations but also
the proposed action of blacklisting so as to afford an effective
opportunity of hearing. The Supreme Court has described
blacklisting as being akin to “civil death” inasmuch as it deprives a
person of the opportunity to participate in Government contracts.
22.In the case at hand, the material placed on record indicates that
though a performance notice dated 27.02.2026 alleging
deficiencies in execution of the contract was issued, there is
nothing on record to demonstrate that the petitioner was ever
specifically put to notice that debarment/blacklisting for a period of
13
two years was one of the proposed actions. A notice alleging
deficiencies in performance or proposing termination of the contract
cannot, by itself, be treated as a substitute for a notice proposing
blacklisting unless such penal consequence is specifically
disclosed therein. The requirement of a specific and unambiguous
notice is not an empty formality but a substantive safeguard
intended to ensure fairness in administrative action. In absence of
such notice, the petitioner was deprived of a meaningful opportunity
to explain why the extreme consequence of debarment ought not to
be imposed.
23.This Court also finds that the impugned order is a composite order
whereby two distinct consequences, namely termination of the
contract and debarment/blacklisting for a period of two years, have
been imposed simultaneously. However, the order does not
disclose any independent reasoning as to why the petitioner's
conduct was of such gravity as to warrant the penal consequence
of blacklisting. Proceedings for termination of contract and
proceedings for blacklisting operate in different fields. While
termination is primarily governed by contractual stipulations,
blacklisting carries wider civil consequences and requires an
objective assessment, independent application of mind and stricter
compliance with the principles of natural justice. The absence of
such consideration renders the order vulnerable to judicial review to
the extent of the penal consequence of debarment.
24.In view of the aforesaid discussion, this Court is of the considered
14
opinion that disputes relating to termination of the contract,
involving questions of contractual performance and interpretation of
contractual clauses, may appropriately be agitated by the petitioner
by resorting to the remedy available under Clause 8.2 of the
agreement. However, insofar as the order debarring/blacklisting the
petitioner for a period of two years is concerned, the same cannot
be sustained in law for want of a specific show-cause notice and
non-compliance with the principles of natural justice. Consequently,
while leaving it open to the petitioner to avail the contractual
remedy in respect of termination of the contract, the portion of the
impugned order relating to debarment/blacklisting deserves to be
and is accordingly set aside.
25.Consequently, the writ petition succeeds in part. The challenge to
the impugned order dated 01.04.2026, insofar as it relates to
termination of the contract, is not entertained in exercise of the
extraordinary jurisdiction of this Court under Article 226 of the
Constitution of India, as the dispute pertains to enforcement of
contractual obligations and the agreement contains an arbitration
clause under Clause 8.2, providing an efficacious alternative
remedy. It is, however, made clear that this Court has expressed no
opinion on the merits of the rival claims relating to termination of
the contract, and it shall be open to the petitioner to invoke the
remedy available under Clause 8.2 of the agreement. In the event
such proceedings are initiated, the same shall be decided
independently and uninfluenced by any observations made in this
15
order.
26.However, insofar as the impugned order debarring/blacklisting the
petitioner for a period of two years is concerned, this Court finds
that the same has been passed in violation of the principles of
natural justice, as admittedly no specific show-cause notice
proposing the penalty of blacklisting was ever issued to the
petitioner. The order of debarment, therefore, cannot be sustained
in law and is accordingly quashed. Nevertheless, this order shall
not preclude the respondents from initiating fresh proceedings for
debarment/blacklisting, if so advised, strictly in accordance with
law, after issuing an appropriate show-cause notice specifically
indicating the proposed action and after affording the petitioner a
reasonable opportunity of hearing.
27.Resultantly, the writ petition is partly allowed in the aforesaid
terms. The impugned order dated 01.04.2026 is upheld to the
extent it terminates the contract, leaving it open to the petitioner to
avail the contractual remedy under Clause 8.2 of the agreement.
However, the impugned order is set aside to the extent it
debars/blacklists the petitioner for a period of two years.
28.No order as to costs.
Sd/- Sd/-
(Ravindra Kumar Agrawal) (Ramesh Sinha)
Judge Chief Justice
Anu
In a significant ruling, the High Court of Chhattisgarh judgment has provided crucial clarity on the distinction between contract termination and blacklisting, particularly in cases involving an arbitration clause writ petition. This detailed analysis, now readily available on CaseOn, highlights the court’s rigorous application of natural justice principles even within contractual disputes.
The case, WPC No. 3783 of 2026, involves M/s. Dynami Enterprises challenging an order from the Union of India (South East Central Railways) that simultaneously terminated their contract and debarred them from future tenders for two years. The petitioner argued violations of natural justice and procedural irregularities, while the respondents cited unsatisfactory performance and the existence of an arbitration clause.
21.07.2026
The High Court was tasked with resolving several key legal questions:
The Court’s decision was grounded in fundamental principles of administrative law and contractual interpretation:
The Court reiterated that blacklisting, being a serious punitive measure with significant civil and commercial consequences (often termed 'civil death'), mandates strict adherence to natural justice. This includes issuing a specific show-cause notice that clearly outlines the proposed blacklisting action, not just contract termination.
While courts generally defer to contractual remedies, particularly when an arbitration clause exists, writ jurisdiction under Article 226 of the Constitution is not an absolute bar. It can be exercised when actions by the State or its instrumentalities are alleged to be arbitrary, unreasonable, or violative of natural justice principles. The public law element in state contracts requires fairness and non-arbitrariness in decision-making.
The Court relied on Supreme Court judgments such as Gorkha Security Services v. Government (NCT of Delhi), (2014) 9 SCC 105, and UMC Technologies (P) Ltd. v. Food Corporation of India, (2021) 2 SCC 551. These cases established that a valid show-cause notice must specifically indicate the proposed blacklisting action, and an order exceeding the scope of such a notice is legally unsustainable.
For legal professionals analyzing complex rulings like this, CaseOn.in offers invaluable 2-minute audio briefs that distill key arguments and outcomes, making it easier to stay updated and informed.
The High Court addressed the respondents' preliminary objection regarding the arbitration clause (Clause 8.2). It clarified that while disputes purely arising from contractual obligations might be relegated to arbitration, challenges to the decision-making process involving allegations of arbitrariness or natural justice violations fall within the ambit of judicial review. The Court found the petitioner's challenge to be directed at the manner in which power was exercised, rather than merely enforcing contractual rights, thus deeming the writ petition maintainable.
A crucial aspect of the Court's analysis was the differentiation between contract termination and blacklisting. It noted that while termination is primarily governed by contractual stipulations and falls within the arbitration clause, blacklisting carries independent penal and stigmatic consequences. Blacklisting impacts a contractor's future right to participate in government contracts, requiring a higher standard of procedural fairness.
The Court found that while a performance notice was issued, there was no specific notice indicating the proposed action of debarment/blacklisting for two years. A notice alleging deficiencies or proposing termination does not automatically serve as a substitute for a notice specifically proposing blacklisting. This absence of a clear, unambiguous notice deprived the petitioner of a meaningful opportunity to explain why such an extreme penalty should not be imposed, thereby violating natural justice principles.
The High Court delivered a nuanced judgment:
The writ petition was partly allowed. The Court upheld the termination of the contract, advising the petitioner to pursue the contractual remedy, including arbitration under Clause 8.2, for disputes related to its termination. The Court explicitly stated it expressed no opinion on the merits of the termination itself.
However, the portion of the impugned order that debarred/blacklisted the petitioner for two years was set aside. This was due to the clear violation of natural justice principles, specifically the absence of a specific show-cause notice for blacklisting.
The Court clarified that its order does not prevent the respondents from initiating fresh proceedings for debarment/blacklisting, provided they do so strictly in accordance with the law, by issuing an appropriate show-cause notice and affording the petitioner a reasonable opportunity of hearing.
This judgment serves as a vital reminder of the robust application of natural justice principles, especially when State instrumentalities impose punitive measures like blacklisting. It underscores the critical distinction between contractual termination and blacklisting, highlighting that while arbitration clauses may govern the former, the latter requires stricter procedural safeguards. Lawyers must ensure that clients facing such actions are afforded full procedural fairness, including specific show-cause notices for blacklisting.
This case is an excellent study in administrative law and constitutional remedies. It illustrates the scope of judicial review under Article 226, even in contractual matters, particularly when allegations of arbitrariness or violations of natural justice arise. It also provides a practical example of applying the IRAC method to analyze how courts distinguish between different legal consequences (termination vs. blacklisting) and the specific procedural requirements each entails.
All information provided in this article is for informational purposes only and does not constitute legal advice. Readers are encouraged to consult with a qualified legal professional for advice pertaining to their specific circumstances.
Legal Notes
Add a Note....