No Acts & Articles mentioned in this case
In the High Court at Calcutta
Commercial Appellate division
Original Side
The Hon’ble Justice Sabyasachi Bhattacharyya
And
The Hon’ble Justice Uday Kumar
A.P.O.T. No.338 of 2024
Arising out of
GA (COM) 4 of 2024
In CS (COM) 544 of 2024
(Old No. CS 194 of 2023)
with
GA (COM) 1 of 2024, GA (COM) 2 of 2024
M/s Exchange and Others
Vs.
Pradip Kumar Ganeriwala and Another
For the appellants : Mr. Surajit Nath Mitra, Sr. Adv.,
Mr. Bratin Kumar Dey, Adv.,
Mrs. Anjana Banerjee, Adv.
For the respondent no.1 : Mr. Rajeev Kumar Jain, Adv.,
Mr. Saunak Sengupta, Adv.,
Mr. Kunal Shaw, Adv.,
Ms. Yamini Mahawar, Adv.
For the respondent no.2 : Mr. Sanjib Kr. Mal, Adv.,
Mr. Bimalendu Das, Adv.,
Ms. Shomrita Das, Adv.
Heard on : 12.02.2025, 19.02.2025
Hearing concluded on : 05.03.2025
Judgment on : 19.03.2025
2
Sabyasachi Bhattacharyya, J.:-
1. The present appeal under Section 37 of the Arbitration and Conciliation
Act, 1996 (hereinafter referred to as “the 1996 Act”) arises out of an
order passed in CS (COM) 544 of 2024 dismissing the application filed
by the defendant nos.1 to 4 (present appellant nos.1 to 4) under
Section 8 of the 1996 Act, bearing GA (COM) 4 of 2024, for referring the
matter to arbitration.
2. The appellants rely on Clause 12 of a deed of partnership dated August
23, 1994 entered into between defendant/appellant no.2 and
plaintiff/respondent no.1, thereby forming M/s Exchange, the
defendant/appellant no.1-partnership firm. Clause 12 is an arbitration
clause, providing that in case of any dispute arising between the
partners or their representatives, the same shall be referred for decision
of the Chief Divisional Manager of Bharat Petroleum Corporation
Limited (BPCL), the defendant no.5/respondent no.2, under whose
jurisdiction the subject retail outlet is situated, for arbitration either by
him or his nominee and that the decision of the said Arbitrator shall be
conclusive and binding on all the partners. The partnership firm was
formed for the purpose of running a petrol pump business from a retail
outlet under licence from the BPCL.
3. The dispute in the suit, as per the appellants, arises out of the said
partnership deed of 1994 and hence, being covered by the arbitration
clause therein, the matter ought to be referred to arbitration.
3
4. The learned Single Judge dismissed the application under Section 8 of
the 1996 Act primarily on the premise that defendant nos.3 to 5 in the
suit, against whom claims have been made in the plaint, were not
parties to the arbitration agreement and as such, there cannot be any
reference under Section 8.
5. Learned senior counsel for the appellants argues that BPCL is not a
necessary party to the suit, since it has already deleted the name of the
plaintiff/respondent no.1 from its records as a partner of the appellant
no.1-firm, which is the main relief sought against BPCL. As to the
deletion of the name of respondent no.1 from the records of other
departments, statutory authorities, bodies and/or institutions, it is
submitted that those authorities have not been impleaded in the suit
and the BPCL is not empowered to effect such deletion, even if required.
6. It is submitted that defendant nos. 3 and 4, also appellants herein, the
subsequently added partners after re-constitution of the partnership
firm on the retirement of respondent no.1, have given their express
consent to be subject to arbitration and, thus, the matter ought to have
been referred to arbitration. The deed by which the partnership was
reconstituted also contains an arbitration clause.
7. It is submitted that the name of the respondent no.1 as partner has
already been removed from all departments, statutory authorities,
bodies and, or institutions, although there was a slight delay in issuing
new selling license by the Department of Food and Supplies,
Government of West Bengal . In any event, the said Government
4
department having not been impleaded as a party to the suit, such
delay cannot have a material bearing on the present lis.
8. The cause of actio n in the suit is primarily against the
defendant/appellant no.1-firm and its partners, and defendant
no.5/respondent no.2, the BPCL, was impleaded in the suit merely to
avoid the applicability of Section 8 of the 1996 Act.
9. It is further submitted by the appellants that the respondent no.2-
BPCL had already taken steps and deleted the name of the plaintiff
from its records much prior to the institution of the present suit, as
borne out by the trail-mail annexed to the application under Section 8
of the 1996 Act.
10. It is argued that BPCL was never a necessary party and in a previous
order passed in the present appeal, a co-ordinate Bench had granted
liberty to file an application for deletion of respondent no.2 as a party.
11. It is argued that since the claims in the suit arise in respect of disputes
regarding the respective liabilities of the partners of the partnership
firm as it stood prior to re-constitution and induction of defendant
nos.3 and 4, there cannot be any claim against the said defendants.
The plaint claims are on the basis of the position as it was on the date
of the retirement of the plaintiff/respondent no.1 and flows from the
partnership deed of 1994. Thus, the arbitration clause of the original
partnership deed of 1994 is the relevant clause which is to be looked
into.
5
12. The appellants have, by way of a supplementary affidavit, also filed a
deed of dissolution dated April 1, 2022 of the erstwhile firm which was
not disclosed by the plaintiff.
13. The plaint prayer of a decree for a sum of Rs.7,97,187.76p is against
the defendants/appellant no.1-firm towards the plaintiff’s capital
balance, which is also argued by the appellants to be a dispute arising
out of the original partnership deed dated August 23, 1994.
14. Learned senior counsel appearing for the appellants places reliance on
Lindsay International Private Limited and others v. Laxmi Niwas Mittal
and others, reported at 2022 SCC OnLine Cal 170 , a judgment of a
learned Single Judge of this Court, where it was observed that the
principle laid down by the Supreme court in Sukanya Holdings (P) Ltd.
v. Jayesh H. Pandya and another, reported at (2003) 5 SCC 531, was
rendered prior to the 2015 amendment to the 1996 Act and the position
has been reversed by N.N. Global Mercantile Private Limited v. Indo
Unique Flame Limited and others, reported at (2021) 4 SCC 379, where
it was clarified that if there is a valid arbitration agreement, the matter
is to be referred to arbitration irrespective of any court order.
15. Learned senior counsel also relies on Ajay Madhusudan Patel and
others v. Jyotrindra S. Patel and others, reported at 2024 SCC OnLine
SC 2597, in support of the proposition that even non-signatories to the
arbitration agreement can be bound by the arbitration agreement if
they consent to do so and if there is a defined legal relationship
between the signatory and non-signatory parties. The conduct of the
6
non-signatory parties could be an indicator of their consent, which in
the present case has been given by the defendant/appellant nos.3 and
4, the incoming partners of the re-constituted firm.
16. Learned counsel for the plaintiff/respondent no. 1 controverts such
submissions and argues that the judgment of the learned Single Judge
in Lindsay International Private Limited (supra) ought to be treated as
per incuriam since Sukanya Holdings (P) Ltd. (supra) is still good law
insofar as there cannot be any bifurcation of the suit into two parts,
one to be decided by the Arbitral Tribunal and the other by the Civil
Court, which would inevitably delay the proceedings and defeat the
whole purpose of speedy disposal of dispute and decreasing the cost of
litigation, which would be frustrated by such procedure.
17. Learned counsel for respondent no. 1 cites a three-Judge Bench
decision of the Supreme Court in Thomas Cook (India) Ltd. v. Beach Ark
Hotels Pvt. Ltd. and Another, reported at 2025 SCC OnLine SC 140 ,
wherein the proposition laid down in Sukanya Holdings (P) Ltd. (supra)
was relied on and applied.
18. It is argued that there is no illegality or perversity in the impugned
judgment dated August 9, 2024. It is next argued by the respondent
no.1 that Order I Rule 10(2) of the Code of Civil Procedure applies only
at the juncture of the filing of the suit and subsequent action taken by
the BPCL/respondent no.5 cannot be an occasion for the court to
suo motu delete the name of the said defendant. Since reliefs have been
claimed against the defendant no.5 as well as defendant nos.3 and 4 in
7
the suit, none of whom were parties to the arbitral proceedings, there is
no scope of reference to arbitration.
19. Learned counsel for the respondent no.1 further contends that unless a
“party”, as defined in the 1996 Act, is a party to the arbitration
agreement, there cannot be a reference under Section 8 of the 1996
Act. It is argued that there continues to be a cause of action against
defendant no.5/respondent no.2 and in any event, the said question
has to be decided on a full-fledged trial and not at this premature stage.
20. Learned counsel next contends that the judgme nt in N.N. Global
Mercantile Private Limited (supra) relied on in Lindsay International
Private Limited (supra), has been reversed in a subsequent Constitution
Bench decision of a seven-Judge Bench of the Supreme Court in the
matter of Interplay Between Arbitration Agreement Under Arbitration and
Conciliation Act, 1996 and Stamp Act, 1899, reported at (2024) 6 SCC 1.
21. In Ajay Madhusudan Patel’s case the Supreme was considering a case
where the doctrine of group of companies was being considered, as
opposed to the present case.
22. Lastly, it is contended that the appellants are seeking to avoid the
consequences of failure to file their written statement in the suit in time
and having forfeited their defence within the contemplation of the
Commercial Courts Act, 2015, by having a reference to arbitration.
23. Learned counsel for the BPCL contends that the name of the BPCL be
expunged, since even before the filing of the suit, the BPCL had deleted
the name of the plaintiff/respondent no.1 from its records and there is
8
no subsisting cause of action against the said party. Learned counsel
also highlights the liberty given for seeking deletion of its name in the
Order dated November 20, 2024, passed in the present appeal by a co-
ordinate Bench.
24. It is submitted that the defendant no.5-BPCL also entered into an
agreement independently with the partnership firm which carries an
arbitration clause as well.
25. Heard learned counsel for the parties.
26. The issues involved in the case have various facets which are discussed
below.
Scope of Section 8 of the 1996 Act
27. In order to fully appreciate the nuances of the present case, the scope
of Section 8 of the 1996 Act is required to be understood. The only
comparable provision in the 1996 Act is Section 11 of the said Act,
where a reference to arbitration is also contemplated. However, there is
a difference in scope between the two Sections which, though subtle,
cannot be overlooked.
28. In a Section 11 scenario, the scope of enquiry of the High Court is
limited to whether there is a valid arbitration agreement and the
dispute is covered by the same. Of course, in ex facie deadwood claims,
the court might stay its hands in referring the matter since it would be
a futile exercise.
9
29. On the other hand, in a Section 8 consideration, the court is not merely
an instrumentality under the 1996 Act, akin to the role of the High
Court under Section 11. There is already a pending civil suit in an
otherwise competent Civil Court which is already in seisin of the suit
when the application under Section 8 is filed. The court, while dealing
with an application under Section 8, apart from considering the validity
of the agreement, also has to read the plaint and the pleadings of the
parties, including the written statement, if filed, and/or the application
under Section 8 itself, in a holistic and meaningful manner to arrive at
the conclusion whether the reliefs claimed in the suit come within the
ambit of the arbitration agreement/clause. It is also to be kept in mind
that Section 8 does not create an absolute legal bar to the court in
taking up and deciding the suit, in the sense that the right to have a
reference under Section 8 can be waived by the defendant simply by not
filing a proper application under Section 8. In such a case, the suit
would proceed, despite the existence of the arbitration clause, in its
normal course.
30. Thus, while exercising its jurisdiction under Section 8 of the 1996 Act,
the Civil Court acts in a dual capacity, as a Civil Court taking up the
suit as well as an authority under the 1996 Act, although if there is a
valid arbitration agreement and the dispute involved in the suit and the
reliefs claimed therein come within the ambit of the arbitration clause,
there is no option of the court to refuse reference to arbitration, if the
10
defendant chooses to file an application under Section 8 in proper
format.
Whether the reliefs claimed against defendant nos.3 and 4 come
within the ambit of Section 8 of the 1996 Act
31. Section 7 of the 1996 Act is wide in its scope. Whereas the term “party”
has been defined in Section 2 (1) (h) of the said Act to be a party to an
arbitration agreement, Section 7(1) provides that “arbitration
agreement” means an agreement by the parties to submit to arbitration
all or certain disputes which have arisen or which may arise between
them in respect of a defined legal relationship whether contractual or
not.
32. Again, Section 8 provides that a reference to arbitration shall be made if
a party to the arbitration agreement or any party claiming through or
under him applies under the said provision.
33. The key word in Section 7(1) is “defined legal relationship” which
broadens the definition of “arbitration agreement” itself beyond the
contract entered into between the parties. The dispute between the
parties need not be confined to disputes arising of the contract alone
but may also arise out of a defined jural relationship between them.
34. In the present case, although the dispute springs up from the partition
deed dated August 23, 1994, it also pertains to the jural relationship
between the plaintiff/respondent no.1 and the defendants/appellant
11
nos. 2, 3 and 4, all of whom are partners of the defendant/appellant
no.1-partnership firm.
35. Hence, read in the context of Section 7(1), the dispute involved in the
suit relates to a dispute between the plaintiff on the strength of his
previous status as a partner of the defendant no.1-firm and the relief
sought is against the partnership firm as well as its present partners
after the re-constitution, out of whom defendant nos.3 and 4 were
subsequently inducted and defendant no.2 has continued as a partner
from the pre-reconstitution period. Thus, the expression “a party to the
arbitration agreement or any person claiming through or under him” as
used in Section 8, read in conjunction with Section 7 of the 1996 Act,
takes within its ambit defendant nos.1 to 4, all of whom are either the
partnership firm or parties coming within the defined legal relationship
of partners within the contemplation of the arbitration clause in 1994
the deed.
36. Again, Section 7(4) provides that an arbitration agreement has to be in
writing, which can be in a rainbow of situations. The expression “a
document signed by the parties”, in Clause (a) of sub-section (4) of
Section 7 can also include the application under Section 8 itself as well
as the memorandum of the present appeal and the connected stay
application where, by impleading themselves as parties and seeking a
reference to arbitration on the strength of the arbitration clause
contained in the 1994 document, as well as challenging as co-
12
appellants the refusal to so refer, the defendant nos.3 and 4 have also
subjected themselves to such proposed arbitration.
37. Clause (c) of sub-section (4) of Section 7 includes an exchange of
statement of claim and defence in which the existence of the agreement
is alleged by one party and not denied by the other, which can also
include the plaint, read with the application under Section 8 and/or
the proposed written statement (which was not permitted to be filed by
the defendants but which refusal has been assailed in an appeal which
is now pending).
38. Hence, the defendant nos.3 and 4 have unequivocally consented to
being subject to the arbitration sought in the Section 8 application.
39. Even after the reconstitution of the partnership firm, the defined legal
relationship of partnership continues inter se the defendant nos. 2, 3
and 4 and the claims made in the suit by the plaintiff, who himself was
an erstwhile partner, are based on disputes arising out of such legal
relationship among the parties.
40. The ratio laid down in Ajay Madhusudan Patel (supra), relying on Cox &
Kings Limited v. SAP India Private Limited and another, reported at
(2024) 4 SCC 1, has to be read in the above backdrop. In the said
judgment, the Supreme Court, in unequivocal terms, observed that the
courts and tribunals should not adopt a conservative approach to
exclude all person or entities who intended to be bound by the
underlying contract containing the arbitration clause through their
conduct and relationship with the signatory parties. The mutual intent
13
of the parties, relationship of the non-signatory to a signatory, the
commonality of the subject -matter, composite nature of the
transactions and performance of the contract, it was held, are all
factors that signify the intention of the non-signatory to be bound by
the arbitration agreement.
41. It was further highlighted in the said judgment that the important
determination for courts in case of non-signatory parties is whether
such persons or entities intended or consented to be bound by the
arbitration agreement or the underlying contract and it was held that
the requirement of a written arbitration agreement does not exclude
possibilities of binding non-signatory parties if there is a defined legal
relationship between the signatory and non-signatory parties.
42. The Supreme Court further highlighted, by relying on Cox & Kings
Limited (supra) that by being actively involved in the performance of a
contract, a non-signatory may create an appearance that it is a
veritable party to the contract containing the arbitration agreement,
and secondly, the conduct of the non-signatory may be in harmony
with the conduct of the other members of the group, leading to the
other party to legitimately believe that the non-signatory was a veritable
party to the contract.
43. We may further add to such ratio that in a Section 8 scenario, the
nature of the reliefs claimed in the plaint are to be looked into and
where the relief sought in the suit against non-signatories to the
arbitration agreement is in harmony with the reliefs sought against the
14
signatories, particularly when the legal relationship between the
signatories and the non-signatories are on the same platform vis-à-vis
the cause of action of the suit and the reliefs claimed, the non-
signatories may very well be brought within the purview of the
arbitration agreement. Thus, there cannot be any manner of doubt
that the defendants/appellant nos.3 and 4, although incoming partners
after the re-constitution of the firm, come within the ambit of the
arbitration agreement.
44. The principal relief claimed in the suit, relief (a), is a decree for
declaration that the plaintiff/respondent no. 1 is not a partner of the
defendant/appellant no.1-firm on and from April 1, 2022. April 1,
2022 is chosen as the cut-off date, since the partnership firm created
by the partnership deed dated August 23, 1994 was allegedly dissolved
on that date and subsequently re-constituted. The claim of the plaintiff
in the suit is entirely based on his capacity as a partner during the
period prior to his retirement, thus, solely on the strength of the
partnership deed dated August 23, 1994 and the jural relationship
flowing therefrom.
45. The other ancillary relief sought against the firm and defendant nos.3
and 4 are in the context of the defendant nos.3 and 4 having inherited
the liabilities of the defendant no.1-firm, which is not an independent
liability of the defendant nos.3 and 4 but a carry -over from the
liabilities of defendant no.1-firm and defendant no.2 under the original
partnership deed dated August 23, 1994.
15
46. The two major components of the cause of action of the suit, as per the
plaint, are that the entire reliefs sought are on the basis of the plaintiff
having been a partner of the defendant no. l-firm at the relevant period
on the basis of and during subsistence of the partnership deed dated
August 23, 1994 and the liabilities of the partnership firm arising out of
the said agreement, all of which happened prior to the retirement of the
plaintiff from the said firm.
47. Thus, the pseudo-liabilities of the defendant nos.3 and 4, insofar as the
frame of the suit and its cause of action are concerned, are not new
liabilities springing from any independent contract but are all based on
the rights of the plaintiff as claimed on the strength of the partnership
deed dated August 23, 1994 and during its subsistence and the
liabilities flowing from such deed. The defendant nos. 3 and 4 have
been embroiled in the suit only in the capacity of partners of the firm,
because they have inherited the legacy of alleged liabilities of the
defendant no. 1-firm and the defendant no.2, its continuing partner,
left over from the pre-dissolution era of the partnership firm, which
liabilities and the proclaimed rights of the plaintiff all flow from the
deed of 1994, containing the arbitration clause. Hence, the reliefs
claimed even against the defendant nos.3 and 4 are relatable to the
deed of 1994 and not independent claims arising after the dissolution
of the erstwhile firm or the retirement of the plaintiff therefrom.
48. Hence, defendant nos.3 and 4 squarely come within the ambit of the
dispute covered by the arbitration clause of the 1994 partnership deed.
16
49. In addition, since the re-constitution deed also contains an arbitration
clause, the parties thereto (including the newly inducted defendant nos.
3 and 4) have agreed to submit to arbitration in case of disputes arising
in respect of the defined legal relationship of partners of the defendant
no. 1-firm, without any distinction being drawn in regard to liabilities of
the firm either in its previous form or its reconstituted avatar.
50. Hence, this issue is held in favour of the defendants/appellants. The
defendant nos.3 and 4 are very mu ch amenable to reference to
arbitration under Section 8 of the 1996 Act as well.
Whether the reliefs claimed against defendant no.5/respondent
no.2 come within the ambit of Section 8 of the 1996 Act
51. The respondent no.2-BPCL, impleaded as defendant no.5 in the suit,
has sought the expunging of its name from the array of parties on the
ground that it had deleted the name of the plaintiff/respondent no.1
from its records even prior to the institution of the suit, as evinced by a
trail-mail which is prior to the suit and annexed to the supplementary
affidavit filed by the appellants herein.
52. The matter can be approached from two different perspectives, which
are discussed below:
First perspective:
53. Vide Order dated September 18, 2023 passed in the suit from which
the present appeal arises, the learned Single Judge recorded a
17
submission of defendant no.5/respondent no.2-BPCL that the dispute
is inter se between the partnership and its partners and that BPCL has
nothing to do with the license issued by the Department of Food and
Supplies, Government of West Bengal. BPCL only issues licence for the
products which are supplied by it or being sold by the defendant no.1
at the petrol pump. The learned Single Judge observed, considering
the said submissions, that the parties with the assistance of their
respective advocates can, in the meantime, sit and decide on the
modalities by which the plaintiff’s name can be expunged from the
licence issued by the Department of Food and Supplies so that the
plaintiff is not hauled up for any untoward incident despite having
ceased to be a partner of the defendant no.1.
54. In an order dated December 4, 2023 passed in the suit, it was recorded
that the defendant nos.1 to 4 submitted that a fresh licence in the
name of the defendant nos.2 to 4 had been issued by eliminating the
name of the plaintiff who had retired from the partnership and a copy
of the licence issued by the Director, Consumer Goods, Food and
Supplies Department, Government of West Bengal on December 1,
2023 was also placed on record before the court.
55. Even in the present appeal, a co-ordinate Bench, vide order dated
November 20, 2024, had recorded the submission of learned counsel
for BPCL that the name of the plaintiff had been deleted from all
records and the respondent no.2 had approved the re-constituted
partnership firm pursuant to the request made and , as such, the
18
presence of the respondent no.2 was not at all necessary. The co-
ordinate Bench, on the basis of such submission, observed that it
would be open for the said respondent to file an application for deletion
of its name in the proceeding.
56. Thus, even without any bifurcation of the cause of action in the suit,
the learned Single Judge had an option to expunge the name of the
defendant no.5/ present respondent no.2 as a defendant in the suit.
Learned counsel for the plaintiff/respondent no.1 argues that the
power of the court under Order I Rule 10(2) has to be exercised on the
basis of the position as it stood on the date of filing of the suit. Even
from such viewpoint, the BPCL has produced documents and claims
that it had already deleted the name of the plaintiff from its records
before institution of the suit and issued a fresh licence subsequently in
the favour of the re-constituted firm.
57. Even otherwise, a plain reading of Rule 10(2) of Order I of the Code of
Civil Procedure shows that the court may suo motu pass an order
striking out the name of a plaintiff or defendant at any stage of the
proceedings. The parameter for invoking such jurisdiction is that the
said party must be “improperly joined”. The “impropriety” has not been
fixed to the date of institution of the suit, particularly read in
conjunction with the expression “may at any stage of the proceedings”
used in the earlier part of the said sub-rule. Hence, if the court is of
the opinion that a party has been improperly joined and the joinder has
19
been rendered improper even subsequently after filing of the suit, it has
suo motu jurisdiction to strike out the name of the party.
58. Importantly, as opposed to Section 11 of the 1996 Act, where the High
Court acts merely as a functionary under the said Act and not as an
independent civil court, in a Section 8 situation there is already a civil
suit pending before a competent civil court and it is such civil court, in
its dual capacity as such and as a functionary under the 1996 Act,
refers the matter to arbitration. Thus, nothing prevented the learned
Single Judge from expunging the name of BPCL by taking on record the
materials before it, simultaneously with adjudication of the application
under Section 8, which would have eliminated BPCL from the suit
altogether.
59. If we carefully consider the reliefs (a), (b), (d), (e), (f) and (g) of the plaint,
neither of those are against the defendant no.5/respondent no.2 but
against the appellant no.1-firm and its partners. Relief (c) is the only
claim against the defendant no.5 -BPCL which is for perpetual
injunction restraining the defendant no.5 from supply or re-sell
petroleum products and/or licensed essential commodities to the
defendant no.1-firm till the time the name of the Plaintiff is removed
and/or deleted from each and every Determent and/or authority and/or
body and/or establishment where the name of the Plaintiff appears as
the partner of the Defendant No.1.
60. Insofar as the other departments and/or authorities and/or bodies
and/or establishments are concerned, no other authority has been
20
impleaded in the suit apart from defendant no.5. Defendant no.5 has
no authority or jurisdiction, and consequentially any liability, to delete
the name of the plaintiff from the records of other authorities. It can at
best take steps in that regard which it has pleaded to have already
taken. Thus, the relief against defendant no.5, as framed in prayer (c)
of the plaint, is a sham relief merely to embroil the defendant no.5 and
avoid arbitration. Notably, the said relief does not claim the deletion of
the name of the plaintiff from the record of the defendant
no.5/respondent no.2 itself but from other departments and authorities
and/or bodies or establishments, which is entirely beyond the authority
of the BPCL. The other such authorities having not been impleaded,
such relief, ex facie, is bad for non-joinder of necessary parties and
cannot be granted. Hence, no cause of action has been shown against
the BPCL in the suit and as such, the BPCL/defendant no.5 ought to
have been expunged/deleted from the array of parties by the learned
Single Judge by exercise of its suo motu powers under Order I Rule
10(2) of the Civil Procedure Code.
Second Perspective:
61. The second viewpoint from which the present issue can be looked at is
that the BPCL agreement with the original partnership, formed by the
deed of 1994, also contains an arbitration clause, being Clause 19 of
the said agreement dated July 30, 2020. Clause 19 provides that any
dispute or difference “whatsoever” arising out or in connection with the
21
said agreement, including any question regarding its existence, validity,
construction, interpretation, application, meaning, scope, operation or
effect of the contract or termination thereof shall be referred to and
finally resolved through arbitration as per the procedure mentioned
thereinbelow.
62. The expressions “application”, “operation”, “effect” and “termination”
are all inextricably linked with the partnership deed by which the
defendant/appellant no.1 was formed on August 23, 1994.
63. The BPCL agreement with the original partnership firm is replete with
references to the partnership deed dated August 23, 1994.
64. For example, Clause 10(s) of the BPCL agreement prevents the change
of constitution of the licensee firm (defendant no.1-firm) or to dissolve
the partnership or admit any new member as partner or allow any
member to withdraw from the partnership without o btaining the
previous consent from the company.
65. Again, Clause 13(b) of the BPCL agreement provides inter alia that on
the retirement of any partner of the said partnership firm, the BPCL
may at its option at once determine the agreement and if the option
shall not be exercised, the agreement shall continue as between the
company and the surviving or continuing partners of the licensees.
66. Thus, as per the contemplation of the BPCL agreement with the
partnership firm, the scope of operation, effect and
perpetuation/termination of the said agreement was intertwined with
and dependent on the dissolution of the partnership firm, admission of
22
new members thereto and even withdrawal of a partner from the said
partnership, all of which are specifically the subject-matter of the
present suit.
67. Also, as per Clause 13(b), the agreement is to continue between the
company and the surviving or continuing partners of the licensee firm,
which covers within its ambit the reconstituted firm and defendant no.2
(surviving partner) and defendant nos.3 and 4 (“continuing partners” in
the sense of deriving liability, as per the plaint case, from the previous
liabilities of the erstwhile firm created by the partnership deed dated
August 23, 1994). Since all of those and the previous consent of the
BPCL for such actions by the erstwhile partnership firm are the
subject-matter of dispute coming within the ambit of Clause 19 of the
BPCL agreement, which is further specified by the use of expressions
such as “application, operation, effect and termination”, the arbitration
clause (Clause 19) of the BPCL agreement with the partnership firm
(defendant no.1) clearly refers to the vital clauses of the partnership
deed dated August 23, 1994, which includes the arbitration clause
therein, and intends the same to be a part of the BPCL agreement as
well. Thus, the provisions of Section 7(5) of the 1996 Act, which
envisage the reference in a contract to a document containing an
arbitration clause to constitute an arbitration agreement if the contract
is in writing and the reference to it is such as to make such arbitration
clause part of the contract, are attracted, thereby bringing the
arbitration clause in the agreement dated July 30, 2020 between the
23
BPCL and the erstwhile firm within the ambit of the disputes of the
suit. In such a case, separate references to arbitration between the
plaintiff and the BPCL and the plaintiff and the defendant nos.1 to 4
would be an unnecessary, futile and dilatory exercise, specifically
intended to be curbed by the 1996 Act as expressed in its Statement of
Objects and Reasons. Speedy disposal by alternative dispute resolution
is the spirit of the 1996 Act and as such, the said intention of the
Legislature behind promulgating the statute has to be honoured while
interpreting any of its provisions.
68. Thus, even if we accept the second perspective above, the reliefs sought
in the suit are also covered by the arbitration clause of the BPCL
agreement, thus, facilitating a reference to arbitration of the entire
dispute involved in the suit, be it between the plaintiff and the
defendant nos.1 to 4 or between the plaintiff and the defendant no.5, to
a composite arbitration.
69. Since it is arguable as to whether the first or the second perspective is
more acceptable in law, the only option before the civil court was to
refer the matter to arbitration lock, stock and barrel and leave it to the
arbitral tribunal to decide such questions.
70. Hence, this issue is also decided in the positive, holding that the reliefs
sought against the defendant no. 5/ respondent no. 2 also come within
the purview of Section 8 of the 1996 Act.
71. In view of the above findings, there cannot be any manner of doubt that
the above aspects of the matter were not brought to the notice of the
24
learned Single Judge and were not adverted to at all in the impugned
order. Thus, the impugned order is de hors the law and the facts of the
case and as such cannot stand the scrutiny of an appeal under Section
37 of the Arbitration and Conciliation Act, 1996.
72. In such view of the matter, A.P.O.T. No.338 of 2024 is allowed on
contest, thereby setting aside the impugned judgment and order dated
August 9, 2024 passed in respect of GA (COM) 4 of 2024 in CS (COM)
544 of 2024.
73. GA (COM) 4 of 2024 is, thus, allowed, directing the dispute raised in
the suit being CS (COM) 544 of 2024 to be referred to arbitration.
74. The parties shall take necessary steps accordingly.
75. It is, however, made clear that the above observations have been
rendered in the context of the limited consideration under Sections 8
and 37 of the Arbitration and Conciliation Act, 1996 and shall not be
binding on the Arbitral Tribunal taking up the matter. All questions,
including the question of jurisdiction of the Arbitral Tribunal applying
the kompetenz-kompetenz principle, are kept open to be urged before
and decided by the Tribunal independently on merits, without the
Tribunal being unnecessarily influenced in any manner by the above
observations so far as merits are concerned.
76. GA (COM) 1 of 2024 and GA (COM) 2 of 2024, filed in connection with
the present appeal are consequentially disposed of as well.
77. There will be no order as costs.
25
78. Urgent certified server copies, if applied for, be issued to the parties
upon compliance of due formalities.
(Sabyasachi Bhattacharyya, J.)
I agree.
(Uday Kumar, J.)
Legal Notes
Add a Note....