No Acts & Articles mentioned in this case
A
B
C
D
E
F
G
H
273
M/S. FORTUNE INFRASTRUCTURE
(NOW KNOWN AS M/S. HICON INFRASTRUCTURE) & ANR.
v.
TREVOR D’LIMA & ORS.
(Civil Appeal Nos. 3533-3534 of 2017)
MARCH 12, 2018
[N. V. RAMANA AND S. ABDUL NAZEER, JJ.]
Consumer Protection Act, 1986 :
Complaint against developer of housing project – By the
purchaser of a flat in the project – Alleging deficiency in service
and unfair trade practices for not having delivered the flat –
National Consumer Disputes Redressal Commission allowed the
complaint and directed the developers to refund the amount paid
by the complainants and also to pay compensation and cost of
litigation – On appeal, held: Contractual damages are usually
awarded to compensate an injured party to a breach of contract
for the loss of his bargain – This rule is more qualified when it
comes to real estate sector – Onus is on the seller to show his bona
fides and best efforts in discharging the obligation – Mere
unwillingness to carry out the duty could constitute bad faith
sufficient for purchaser to claim damages – In the facts of the present
case there is deficiency of service on part of the developer, which
entitles the complainant to damages/compensation – Generally
damages become due on the date when the breach of contract takes
place and assessed by the reference to the time of breach –
However, the rule is flexible which needs to be assessed in the facts
and circumstances of individual case – In the facts of the present
case the damage need not be determined from the date of breach of
contract – The compensation granted by the National Commission
has surpassed the actual-loss based damages and has entered the
domain of gain-based remedy – Since the damages for the
contractual breach is compensatory, damages awarded should not
be excessive – Court needs to take a balanced approach so as to
ensure right compensation – Therefore compensation of
Rs. 3,65,46,000/- granted by National Commission is reduced to
Rs. 2,27,20,000/- – Compensation.
[2018] 3 S.C.R. 273
273
A
B
C
D
E
F
G
H
274 SUPREME COURT REPORTS [2018] 3 S.C.R.
Damages for commercial contracts – Under the Act –
Determination of – Held: Under Consumer Protection Act damages
for commercial contracts, need to be determined as per Contract
Act – Contract Act, 1872 .
Partly allowing the appeals, the Court
HELD : 1. The contractual damages are usually awarded to
compensate an injured party to a breach of contract for the loss
of his bargain. This rule is more qualified when it comes to the
real estate sector. If the seller wants to limit their liability for
breach of contract under the aforesaid rule, they have to portray
that they have performed their obligation in a prudent manner.
The onus is on the seller to show his best efforts and bona fides
in discharging the obligation. Even in the absence of fraud, mere
unwillingness to carry out the duty could constitute bad faith
sufficient for the purchaser to claim damages. [Paras 11 and
12][280-F-H; 281-A]
2. Whenever the builder has refused to perform the
contract without valid justification, the buyer is entitled for
compensation as he has been deprived of price escalation of the
flat. Every breach of contract gives rise to an action for damages.
Such amount of damages must be proved with reasonable
certainty. [Para 19] [283-D]
3. Even under the Consumer Protection Act, 1986, the
damages for commercial contracts need to be determined as per
the Contract Act. [Para 16] [282-A]
4. In the facts and circumstances of the present case, there
is deficiency of service on the part of the appellants, which
entitles the complainant to damages/compensation. The
appellants did not give any valid reasons as to why they
transferred the property to a third party, despite their
contractual obligation to the respondents (complainants). The
obligation was on the appellants to show that he was unable to
transfer the property to the respondent. Moreover, a person
cannot be made to wait indefinitely for the possession of the flats
allotted to them and they are entitled to seek the refund of the
amount paid by them, along with compensation. Although there
was no delivery period stipulated in the agreement, a reasonable
A
B
C
D
E
F
G
H
275
time has to be taken into consideration. [Paras 14 and 15] [281-
D-F]
5. The damages become due on the date when the breach
of contract takes place, and are normally assessed by reference
to the time of breach. The aforesaid rule is based on the principle
that the injured party is presumed to be in knowledge of the breach
as soon as it is committed and at that time he can take appropriate
measures of mitigation to control the loss flowing from the breach.
The courts may deviate from the aforesaid rule and fix
appropriate date in facts and circumstance of a case if aforesaid
presumptions could not be established or it would not be
reasonable to follow the rule. [Para 21] [283-F-H; 284-A]
6. Where a party sustains loss by reason of a breach of
contract, the damages are to be granted so as to place the
suffering party in the same position as if the contract had been
performed. In light of the above, the damages other than
consequential loss have to be measured at the time of the breach.
However, the aforesaid rule is flexible which needs to be assessed
in facts and circumstances of individual case. [Para 22] [284-C-
D]
7. Where there is non-delivery of the flat/house, and the
developer has refused to provide alternative and equivalent
accommodation, and the buyer lacks means to purchase a
substitute from the market, then in such circumstances,
damages would not be reasonable to be assessed on the breach
date. [Para 21] [284-A]
8. In the present case, the complainants (respondents) tried
to execute the agreement and sought for conveyance of the
property through the NCDRC. In these circumstances, even in
the first appeal, offers were being made on behalf of appellants to
convey alternative properties, which were refused as being
insufficient. Therefore, in the facts and circumstances of the
present case, the damage need not be determined from the date
of breach of contract. [Para 22] [284-E]
9. Appellants have produced circle rates of properties in
the vicinity of the disputed flats, which vary from Rs. 18,655 per
Sq. Ft. to Rs. 25,787/- per Sq. Ft. Whereas the respondents have
produced executed sale deeds in the nearby vicinity, which was
M/S. FORTUNE INFRASTRUCTURE & ANR. v. TREVOR
D’LIMA & ORS.
A
B
C
D
E
F
G
H
276 SUPREME COURT REPORTS [2018] 3 S.C.R.
Rs. 65,000 per Sq. ft., Rs. 69,342/- per Sq. ft., Rs. 75,000/- per
Sq. Ft. and Rs. 88,050/- per Sq. Ft.. NCDRC has taken the
minimum available market price as the reference point for
awarding compensation at the rate of Rs. 65,000/- per Sq. Ft.
Excessive reliance on the aforesaid sale deed may not be
appropriate as the present property is a redevelopment of an
earlier property. Usually the real estate rates for re-developed
properties are on the lower side instead of green-field projects.
[Para 24] [284-G-H; 285-A]
10. Thus, the claim of the respondents (complainants) as
granted by the NCDRC seems to surpass the actual-loss based
damages and enter the domain of gain-based remedy. It would
not be appropriate to grant such damages. There is no dispute
about the fact that damages for the contractual breach is
generally compensatory arising out of the breach. Therefore, the
damages awarded should not be excessive and a court/tribunal
needs to take a balanced approach so as to ensure right
compensation. [Para 25] [285-B-C]
11. It would be appropriate, just and reasonable that the
market rate be fixed at Rs. 50,000/- per Sq. Ft. (Rupees Fifty
Thousand per square feet) as the reference rate for determination
of market price prevailing in the vicinity of the disputed property.
Hence, the estimated market price would be Rs.4,14,20,000/-
instead of Rs.5,38,46,000/- as granted by the NCDRC. However,
there is no reason to interfere in respect of the compensation
granted for the parking space. [Para 26] [285-D-E]
Ghaziabad Development Authority v. Balbir Singh
(2004) 5 SCC 65 : [2004] 3 SCR 68 – relied on.
Johnson and Anr. v. Agnew [1979] 1 All ER 883 –
referred to.
Case Law Reference
[1979] 1 All ER 883 referred to Para 11
[2004] 3 SCR 68 relied on Para 18
A
B
C
D
E
F
G
H
277
CIVIL APPELLATE JURISDICTION : Civil Appeal Nos. 3533-
3534 of 2017.
From the Judgment and Order dated 08.09.2016 and final Order
dated 03.11.2016 of the National Consumer Disputes Redressal
Commission, New Delhi in Consumer Complaint No. 636 of 2015 and in
Review Application No.273 of 2016 in Consumer Complaint No.636 of
2015 respectively.
Raju Ramachandran, Sachin Dutta, Sr. Advs, Rishi Agrawala,
Ms. Swati Sinha, Ms. Manisha Ambwani (for E.C. Agrawala), Advs
for the Appellants.
Abir Phukan, Ms. Marilyn Khakha (for V. Shyamohan), Advs
for the Respondents.
The Judgment of the Court was delivered by
N. V. RAMANA, J. 1. These appeals are filed against the
impugned orders, dated 08.09.2016 and 03.11.2016, passed by the National
Consumer Disputes Redressal Commission [hereinafter ‘NCDRC’ for
brevity], in Consumer Complaint No. 636 of 2015 and Review Application
No. 273 of 2016 in the Consumer Complaint No. 636 of 2015.
2. A few facts which are necessary for the disposal of this matter
are that the appellants, in the year 2011, launched a residential housing
project by name ‘Hicons Onyx’, renamed as Fortune Residency, which
was a re-development of Mohammadi House. The respondents booked
a flat bearing no. 202, 2
nd
Floor in ‘A’ wing, admeasuring 828.40 Sq. Ft.
with one unit of parking-space. The total consideration for the flat was
Rs. 1,93,00,000/-. It is alleged by the appellants, that due to increase in
the cost beyond what was expected, they transferred the project to
another company being M/s. Zoy Shelcon Pvt. Ltd. It is to be noted that
the respondents have paid a sale consideration of Rs. 1,87,00,000/-.
3. In 2015, aggrieved by the fact that appellants were not willing
to deliver the flat to them, the respondents approached NCDRC through
a consumer complaint, being CC No. 636 of 2015, with following prayers-
a. To hold and declare the Opposite Parties to be guilty of
deficiency in service and unfair trade practices as per the
provisions of the Consumer Protection Act, 1986
M/S. FORTUNE INFRASTRUCTURE & ANR. v. TREVOR
D’LIMA & ORS.
A
B
C
D
E
F
G
H
278 SUPREME COURT REPORTS [2018] 3 S.C.R.
b. To direct the Opposite Parties 1 to 4 to comply with their
statutory obligations and to execute and register the Agreement
for Sale with the complainants in respect of flat No. 202 on the
2
nd
floor admeasuring 828.40 Sq. Ft. with one car parking in the
building known as Hicon Onyx and since re-named as Fortune
residency situated at plot no. F/1116-A, Village Bandra, St.
Martins Road Bandra (West), Mumbai 400 050 (Maharashtra).
c. To direct the Opposite Parties no. 1 to 4 to complete the
construction of the building known as ‘Hicons Onyx’ since
renamed as ‘Fortune residency’ and to hand over to the
complainants vacant and peaceful possession of the Flat No.
202 on the 2
nd
floor admeasuring 828.40 Sq. Ft. with one car
parking in the building known as Hicons Onyx and since
renamed as Fortune residency situated at plot no. F/1116-A,
Village Bandra, St. Martins road Bandra (West), Mumbai 400
050 (Maharashtra) on receiving the balance consideration
amount of Rs. 6,00,000/-from the complainants
Alternatively
In the event of the Opposite Parties no. 1 to 4 having created
third party interests in favour of the Opposite Party no. 5, to
direct the Opposite parties no. 1 to 4 to hand over to the
complainants any other flat of the same size quality and
specifications with one car parking in the same building ‘Hicons
Onyx’ since re-named as ‘Fortune Residency’ or any flat of the
same size, quality and specifications with one car parking in the
same locality of the present building Hicons Onyx or Fortune
Residency.
x x x x x
x x x x x
f. To direct the Opposite Parties No. 1 to 4 jointly and severally
pay to the complainants Rs.5,00,000/- (Rupees Five lakhs only)
towards compensation for the inconvenience and mental agony
suffered by the complainants due to the enormous delay in
construction of the building, negligence and deficiency in
service of the Opposite Parties No. 1 to 4.
A
B
C
D
E
F
G
H
279
g. To direct the opposite Parties No. 1 to 4 jointly and severally to
pay to the complainants the sum of Rs. 1,00,000/- (Rupees One
Lakh only) being the Legal and other incidental expenses
incurred by the complainants.
h. For such other and further relief as this Hon’ble Commission
may deem fit and proper in the nature and circumstances of the
above numbered complaint.
4. The NCDRC has allowed the complaint and directed the
appellants: 1. To refund the amount of Rs. 1,87,00,000/- which they have
received from the complainants, within six weeks from the day of the
impugned judgment; 2. The appellants were further directed to pay a
sum of Rs. 3,65,46,000/- as compensation and Rs. 10,000/- as cost of
litigation to the complainants within six weeks from the day of the
impugned judgment; 3. The aforesaid amount was ordered to be paid at
10% per annum from the date of the order till the actual date of
payment. It may be noted that even the review against the aforesaid
order was dismissed by the NCDRC vide order dated 03.11.2016.
5. Having dissatisfied with the impugned orders passed by the
NCDRC, appellants approached this Court through these civil appeals.
6. At the threshold it was brought to our notice that on 08.09.2016,
when the matter was argued, on most of the other dates the appellants
remained unrepresented before NCDRC. Further the counsels
representing the appellants stated that their counsel appointed for the
forum below did not file necessary pleadings except for a proforma
reply. Keeping in view of the above, they argued that this case should be
remanded back to the NCDRC for fresh consideration. However, on
careful consideration of facts of this case, we are of the opinion that a
remand may not be required at this stage. To put a quietus to the
litigation, the controversy can be adjudicated by this Court.
7. Learned counsel for the appellants, primarily submitted that
the present appellants have transferred the project to a different
company thereby they should be discharged from any liability for not
handing over the disputed property to the answering respondents
(Complainants). He further argued that, the present circle rate of the
disputed property is pegged at approximately half the price awarded by
the NCDRC. Lastly, he urged before this Court to consider the
M/S. FORTUNE INFRASTRUCTURE & ANR. v. TREVOR
D’LIMA & ORS. [N.V. RAMANA, J.]
A
B
C
D
E
F
G
H
280 SUPREME COURT REPORTS [2018] 3 S.C.R.
downward trends shown in the real estate market which mandates a
lesser compensation, compared to the one awarded by the NCDRC.
8.Per Contra, the learned counsel appearing on behalf of the
answering respondents (Complainants) fully supported the reasoning of
the NCDRC in coming to a conclusion that, the appellants herein
provided deficient service by delaying the handing over of the flat to the
complainants. In all fairness, learned counsel for answering respondents
have admitted that prices as contemplated under the impugned order of
NCDRC are not reflective of the true market rates for similar flats
available in the near vicinity of the disputed flats.
9. It would not be out of context to mention that during the
hearing of this case, many attempts were made by both parties to
amicably settle the issue concerning the quantum of compensation which
could not fructify. Further we requested Shri. Raju Ramachandran,
learned senior advocate, to use his good office to persuade parties to
settle the matter. Such an endeavour also could not impress upon the
parties and therefore this court was called upon to adjudicate the matter.
10. Having heard learned counsels on either side and perusing the
materials available on record, the issue that fall for consideration is
whether there is deficiency of service on the part of the appellants? If
so, what is just and reasonable compensation?
11. It is now well established that the contractual damages are
usually awarded to compensate an injured party to a breach of contract
for the loss of his bargain. In the case of Johnson and Anr. V. Agnew,
[1979] 1 All ER 883, the aforesaid case has clearly held as under-
The general principle for the assessment of damages is
compensatory, i.e. that the innocent party is to be placed, so far
as money can do so, in the same position as if the contract had
been performed.
12. The aforesaid proposition remains to hold the field and has
been applied consistently. This rule is more qualified when it comes to
the real estate sector. If the seller wants to limit their liability for breach
of contract under the aforesaid rule, they have to portray that they have
performed their obligation in a prudent manner. It may be noted that the
onus is on the seller to show his best efforts and bona fides in
discharging the obligation. It may be noted that even in the absence of
A
B
C
D
E
F
G
H
281
fraud, mere unwillingness to carry out the duty could constitute bad faith
sufficient for the purchaser to claim damages.
13. To decide whether the respondent ought to be awarded
compensation because of deficiency of service, it is important to
consider the meaning of deficiency as provided under Section 2(1)(g) of
the Consumer Protection Act, 1986.
(g) “deficiency” means any fault, imperfection, shortcoming or
inadequacy in the quality, nature and manner of performance which is
required to be maintained by or under any law for the time being in force
or has been undertaken to be performed by a person in pursuance of a
contract or otherwise in relation to any service;
In light of the above definition, we have to examine whether there
is any deficiency in service, which entitles the complainant to damages/
compensation.
14. In the present case, the appellants did not give any valid
reasons as to why they transferred the property to a third party, despite
their contractual obligation to the respondents (complainants). The
obligation was on the appellants to show that he was unable to transfer
the property to the respondent.
15. Moreover, a person cannot be made to wait indefinitely for
the possession of the flats allotted to them and they are entitled to seek
the refund of the amount paid by them, along with compensation.
Although we are aware of the fact that when there was no delivery
period stipulated in the agreement, a reasonable time has to be taken
into consideration. In the facts and circumstances of this case, a time
period of 3 years would have been reasonable for completion of the
contract i.e., the possession was required to be given by last quarter of
2014. Further there is no dispute as to the fact that until now there is no
redevelopment of the property. Hence, in view of the above discussion,
which draw us to an irresistible conclusion that there is deficiency of
service on the part of the appellants and accordingly the issue is
answered. When once this Court comes to the conclusion that, there is
deficiency of services, then the question is what compensation the
respondents/complainants is entitled to ?
16. Before we come to the aspect of quantum of compensation,
it would be appropriate to look at the settled legal position concerning
M/S. FORTUNE INFRASTRUCTURE & ANR. v. TREVOR
D’LIMA & ORS. [N.V. RAMANA, J.]
A
B
C
D
E
F
G
H
282 SUPREME COURT REPORTS [2018] 3 S.C.R.
the same. At the outset, we may note that even under the Consumer
Protection Act, 1986, the damages for commercial contracts need to be
determined as per the Indian Contract Act.
17. It would be pertinent to note that in common law, claim for
damages is the rule and specific performance is an exception, while in
civil law front, specific performance has traditionally been a prime
remedy for the breach of contract.
1
18. This Court in Ghaziabad Development Authority v. Balbir
Singh, (2004) 5 SCC 65, has observed that there is no fixed formula for
fixing damages in the following manner-
8. However, the power and duty to award compensation does not
mean that irrespective of facts of the case compensation can be
awarded in all matters at a uniform rate of 18% per annum. As
seen above, what is being awarded is compensation i.e. a
recompense for the loss or injury. It therefore necessarily
has to be based on a finding of loss or injury and has to
correlate with the amount of loss or injury. Thus, the Forum
or the Commission must determine that there has been deficiency
in service and/or misfeasance in public office which has resulted
in loss or injury. No hard-and-fast rule can be laid down, however,
a few examples would be where an allotment is made, price is
received/paid but possession is not given within the period set out
in the brochure. The Commission/Forum would then need to
determine the loss. Loss could be determined on basis of loss of
rent which could have been earned if possession was given and
the premises let out or if the consumer has had to stay in rented
premises then on basis of rent actually paid by him. Along with
recompensing the loss the Commission/Forum may also
compensate for harassment/injury, both mental and physical.
Similarly, compensation can be given if after allotment is
made there has been cancellation of scheme without any
justifiable cause.
9. That compensation cannot be uniform and can best be
illustrated by considering cases where possession is being directed
to be delivered and cases where only monies are directed to be
returned. In cases where possession is being directed to be
1
Apparent from the study of French Civil Code (FCC) and German Civil Code
(BGB).
A
B
C
D
E
F
G
H
283
delivered the compensation for harassment will necessarily have
to be less because in a way that party is being compensated by
increase in the value of the property he is getting. But in cases
where monies are being simply returned then the party is
suffering a loss inasmuch as he had deposited the money in
the hope of getting a flat/plot. He is being deprived of that
flat/plot. He has been deprived of the benefit of escalation
of the price of that flat/plot. Therefore, the compensation
in such cases would necessarily have to be higher.…We
clarify that the above are mere examples. They are not
exhaustive. The above shows that compensation cannot be
the same in all cases irrespective of the type of loss or
injury suffered by the consumer.
(emphasis supplied)
19. It must be noted that the law is well settled in this regard.
Whenever the builder has refused to perform the contract without valid
justification, the buyer is entitled for compensation as he has been
deprived of price escalation of the flat. Every breach of contract gives
rise to an action for damages. Such amount of damages must be proved
with reasonable certainty.
20. Before we assess the damages, another important issue to be
delved upon is the reckoning date for the purpose of the assessing the
damages. Whether should it be from the date on which the breach took
place or should it be from the date of judgment?
21. Learned counsel for the appellants, with some vehemence,
argued that the rates of the property have considerably slumped due to
downfall in the real-estate market. Such submissions are to be tested as
per the established principles of law. As per the settled law, the damages
become due on the date when the breach of contract takes place, and
are normally assessed by the reference to the time of breach. The
aforesaid rule is based on the principle that the injured party is presumed
to be in knowledge of the breach as soon as it is committed and at that
time he can take appropriate measures of mitigation to control the loss
flowing from the breach. The courts may deviate from the aforesaid
rule and fix appropriate date in facts and circumstance of a case if
aforesaid presumptions could not be established or it would not be
M/S. FORTUNE INFRASTRUCTURE & ANR. v. TREVOR
D’LIMA & ORS. [N.V. RAMANA, J.]
A
B
C
D
E
F
G
H
284 SUPREME COURT REPORTS [2018] 3 S.C.R.
reasonable to follow the rule. It may be noted that where there is non-
delivery of the flat/house, and the developer has refused to provide
alternative and equivalent accommodation, and the buyer lacks means
to purchase a substitute from the market, then in such circumstances,
damages would not be reasonable to be assessed on the breach date.
22. We have already noted that the appellants were to perform
the contract within a reasonable period of three years from the date of
the agreement i.e., by the last quarter of 2014. Aggrieved by the delay in
handing over the possession, the respondents (complainants) approached
the NCDRC for conveyance and in alternative prayed for damages. It
is now settled that where a party sustains loss by reason of a breach of
contract, the damages are to be granted so as to place the suffering
party in the same position as if the contract had been performed. In light
of the above, the damages other than consequential loss have to be
measured at the time of the breach. However, the aforesaid rule is
flexible which needs to be assessed in facts and circumstances of
individual case. In this case at hand the respondents tried to execute the
agreement and sought for conveyance of the property through the
NCDRC. In these circumstances we may note that, even in the first
appeal, offers were being made on behalf of appellants to convey
alternative properties, which were refused as being insufficient.
Therefore, in facts and circumstances of this case, the damage need not
be determined from the date of breach of contract.
23. Even though the appellants raised a factual issue concerning
the non-payment of part-consideration, we do not think it is necessary to
go into this aspect, as the NCDRC has given a categorical finding that
Rs. 1,87,00,000/- has been paid by the respondents (complainants).
24. Appellants have produced circle rates of properties in the
vicinity of the disputed flats. These rates vary from Rs. 18,655 per Sq.
Ft. to Rs. 25,787/- per Sq. Ft. Whereas the respondents have produced
executed sale deeds in the nearby vicinity, which was Rs. 65,000per Sq.
ft., Rs. 69,342/- per Sq. ft., Rs. 75,000/- per Sq. Ft. and Rs. 88,050/- per
Sq. Ft. NCDRC has taken the minimum available market price as the
reference point for awarding compensation at the rate of Rs. 65,000/-
per Sq. Ft.We are of the opinion that excessive reliance on the aforesaid
sale deed may not be appropriate as the present property is a
redevelopment of an earlier property. Our attention has been drawn to
A
B
C
D
E
F
G
H
285
the fact that usually the real estate rates for re-developed properties are
on the lower side instead of green-field projects.
25. In light of the above, we consider that the claim of the
respondents (complainants) as granted by the NCDRC seems to
surpass the actual-loss based damages and enter the domain of
gain-based remedy. Although we do not recognize any a priopri
limitations on such claim, but we do not think that it would be appropriate
to grant such damages in the case at hand. There is no dispute about the
fact that damages for the contractual breach is generally compensatory
arising out of the breach. Therefore, the damages awarded should not
be excessive and a court/tribunal needs to take a balanced approach so
as to ensure right compensation.
26. Taking into consideration of factual aspects involved in the
matter and on consideration of the submissions of the counsels on either
side, we deem it appropriate, just and reasonable that the market rate be
fixed at Rs.50,000/- per Sq. Ft. (Rupees Fifty Thousand per square feet)
as the reference rate for determination of market price prevailing in the
vicinity of the disputed property. Hence, the estimated market price would
be Rs.4,14,20,000/- instead of Rs.5,38,46,000/- as granted by the
NCDRC. However, we do not see any reason to interfere in respect of
the compensation granted for the parking space.
27. Therefore, the appellants are directed as under-
a. To refund the amount of Rs. 1,87,00,000/- which they have
received from the complainants.
b. To pay a sum of Rs. 2,27,20,000/- as compensation to the
complainants.
c. To pay a sum of Rs. 20,00,000/- as compensation for one unit of
parking lot.
d. The appellants shall also pay Rs. 10,000/- as the cost of
litigation to the complainants.
e. The aforesaid amount is required to be paid within six weeks
from the day of this order. If the payment in terms of this order
is not made within the time stipulated herein, it shall carry
interest of 9% per annum from the date of this order.
M/S. FORTUNE INFRASTRUCTURE & ANR. v. TREVOR
D’LIMA & ORS. [N.V. RAMANA, J.]
A
B
C
D
E
F
G
H
286 SUPREME COURT REPORTS [2018] 3 S.C.R.
28. It is to be noted that this Court vide order dated 23.02.2017,
while issuing notice, directed the appellants to deposit Rs. 2,50,00,000/-
before NCDRC as a condition precedent for hearing this case. Later it
was represented to us that the appellants as on 31.05.2017, had
deposited the aforesaid amountbefore NCDRC. In view of the above,
we allow the respondents (complainants) to withdraw the aforesaid
amount with accrued interest, if any and the same be adjusted to the
appellants’ liability as indicated above.
29. In light of the above discussions, we allow the appeals in part
to the extent indicated above. There shall be no order as to the costs.
Kalpana K. Tripathy Appeals partly allowed.
Legal Notes
Add a Note....