As per case facts, petitioners and respondent, engaged in a Joint Venture for construction projects, encountered disputes regarding project completion and associated bank guarantees. Petitioners alleged that the respondent's consistent ...
ARB.P. 247/2026 & Other Connected Matter Page 1 of 16
$~
* IN THE HIGH COURT OF DELHI AT NEW DELHI
Reserved on: 15
th
May, 2026
Pronounced on: 26
th
May, 2026
+ ARB.P. 247/2026 & I.A. No. 11845/2026
M/S JIANGXI CONSTRUCTION ENGINEERING GROUP CO
LTD & ANR. .....Petitioners
Through: Mr. Sanjoy Ghose, Senior Advocate
with Dr. Farrukh Khan, Ms. Vidhi
Jain, Ms. Zainab Khan and Mr. Mohit
Garg, Advocates.
Mob: 8586080540
Email: vidhi@diwanadvocates.com
versus
M/S VARAHA INFRA LTD. .....Respondent
Through: Mr. Rajeev Sharma, Senior Advocate
with Mr. Abhishek Birthray, Mr.
Paras Choudhary, Mr. Nishant
Kandpal, Ms. Arunima Singh and Mr.
Kartikeya Tripathi, Advocates.
Mob: 8510018600
Email:
kartikeyatripathi@sarvagyalegal.com
+ O.M.P.(I) (COMM.) 23/2026 & I.A. Nos. 1536/2026 & 11844/2026
M/S JIANGXI CONSTRUCTION ENGINEERING GROUP CO
LTD. & ANR. .....Petitioners
Through: Mr. Sanjoy Ghose, Senior Advocate
with Dr. Farrukh Khan, Ms. Vidhi
Jain, Ms. Zainab Khan and Mr. Mohit
Garg, Advocates.
Mob: 8586080540
ARB.P. 247/2026 & Other Connected Matter Page 2 of 16
Email: vidhi@diwanadvocates.com
versus
M/S VARAHA INFRA LTD. .....Respondent
Through: Mr. Rajeev Sharma, Senior Advocate
with Mr. Abhishek Birthray, Mr.
Paras Choudhary, Mr. Nishant
Kandpal, Ms. Arunima Singh and Mr.
Kartikeya Tripathi, Advocates.
Mob: 8510018600
Email:
kartikeyatripathi@sarvagyalegal.com
CORAM:
HON'BLE MS. JUSTICE MINI PUSHKARNA
JUDGMENT
MINI PUSHKARNA, J.
1. ARB.P. 247/2026 has been filed under Section 11 of the Arbitration
and Conciliation Act, 1996 (“Arbitration Act”) seeking appointment and/or
grant of fresh mandate for the earlier Arbitrator, to adjudicate the disputes
between the parties, arising out of and in connection with the Settlement
Agreement dated 21
st
December, 2021 (“Settlement Agreement”), as
incorporated into the Consent Arbitral Award dated 23
rd
February, 2022
(“Consent Arbitral Award”) passed by the Arbitral Tribunal, including,
disputes arising from the alleged breach, non-compliance, revival of original
claims and other consequential and additional claims.
2. O.M.P.(I) (COMM.) 23/2026 has been filed under Section 9 of the
Arbitration Act, seeking interim measures for preservation of the subject
matter under the Consent Arbitral Award, read with the Settlement
ARB.P. 247/2026 & Other Connected Matter Page 3 of 16
Agreement, on the premise of the respondent’s persistent, wilful and
fundamental breach of the Settlement Agreement entered into between the
parties.
3. As per the facts, culled out from the pleadings and documents on
record, the petitioners entered into a Memorandum of Understanding
(“MoU”) with the respondent on 31
st
May, 2017, for the purposes of
forming a Joint Venture (“JV”) and for participating in tenders for various
construction works issued by the National Highways Authority of India
(“NHAI”) and State Governments.
4. By way of the aforesaid MoU, it was agreed between the parties that
the respondent shall arrange only the bid security/earnest money deposit,
and upon award of any project to the JV, the petitioners shall arrange the
following:
A. Performance Bank Guarantee.
B. Additional Performance Bank Guarantee (if required).
C. Retention Bank Guarantee.
D. Mobilization or Advance Bank Guarantee.
5. It was further agreed upon by the parties that if the petitioners failed
to submit the Bank Guarantee in terms of the aforesaid, then it shall not be
entitled to receive any fee or compensation.
6. The JV between the petitioners and the respondent was awarded the
following three contracts:
“
ARB.P. 247/2026 & Other Connected Matter Page 4 of 16
”
7. With respect to the aforesaid Engineering, Procurement and
Construction Contracts (“EPC Contracts”) mentioned at serial nos. (a) and
(b), upon issuance of a Letter of Acceptance dated 01
st
December, 2017 to
the JV by the Government of Gujarat, the petitioners and the respondent
executed two separate Joint Venture Agreements dated 31
st
December, 2017,
in respect of Package-3 and Package-5 of the Gujarat Projects. As per the
said JV Agreements, the petitioner no. 1 undertook to furnish the Bank
Guarantees, as envisaged in the EPC Contracts between the Joint Venture
and Government of Gujarat.
8. With regard to the EPC Contract at serial no. (c), a Letter of
Acceptance for the Vijayawada Project was issued on 01
st
October, 2019.
Pursuant thereto, a JV Agreement was executed between the petitioners and
respondent on 06
th
December, 2019. Under this JV Agreement also,
petitioner no. 1 undertook to furnish Bank Guarantees, as per the EPC
Contract executed between the NHAI and the JV.
9. Since the aforesaid three projects could not be completed within their
respective scheduled completion dates, the JV applied for extension of time,
which was duly granted by the concerned authorities.
10. During execution of the work, various disputes arose between the
ARB.P. 247/2026 & Other Connected Matter Page 5 of 16
parties to the present petitions, and the said inter se disputes were referred to
arbitration presided by a Sole Arbitrator, mutually appointed by the parties.
During the pendency of the arbitration, the parties resolved their disputes
vide the Settlement Agreement dated 21
st
December, 2021.
11. Under the Settlement Agreement, since the petitioners apprehended
that the respondent may not be able to complete the respective projects, and
the same would result in the encashment of Bank Guarantees submitted by
petitioner no. 1, the respondent executed a Mortgage Deed dated 06
th
May,
2022, in respect of plant and machinery worth Rs. 50 Crores, based on their
invoice value as well as a Corporate Guarantee to secure all the Bank
Guarantees submitted by the petitioners.
12. Based on the said Settlement Agreement, the Consent Arbitral Award
was passed by the learned Sole Arbitrator on 23
rd
February, 2022.
13. As per Clause 13 of the Settlement Agreement, the respondent had
undertaken to complete the Gujarat projects by end of June, 2022 or such
other time as may be allowed by the Government of Gujarat. However, due
to various factors, the work was delayed beyond June, 2022, and extensions
with regard thereto were granted by the Government of Gujarat from time to
time.
14. As regards the Vijayawada Project and Package-3 of Gujarat Project,
completion certificates have already been issued, and defect liability period
is in operation.
15. As regards Package-5 of the Gujarat Project, owing to non-
availability on the work-front and continuing hindrances, the respondent
requested for descoping of the Kuvadava Flyover and Toll Plaza works from
the scope of the EPC Contract with respect to Package-5. The said request
ARB.P. 247/2026 & Other Connected Matter Page 6 of 16
for descoping is currently the subject matter of a Dispute Resolution Notice
dated 12
th
September, 2023 in terms of Clause 26 of the EPC Contract
between the JV and the Government of Gujarat.
16. The respondent has already completed the work under Package-5 of
Gujarat Project, except to the extent of the work descoped. Further, the
respondent has applied for provisional completion certificate vide letter
dated 28
th
March, 2026.
17. On behalf of the petitioners, it is contended that owing to consistent
failure on the part of the respondent to complete the Gujarat project, the
Gujarat Authority vide Notice dated 31
st
July, 2025 has invoked Clause
11.13.2 of the EPC Contract, relating to completing the works on risk and
cost of the contractor, i.e., the JV between the petitioners and the
respondent. Thus, as per the case put forth by the petitioners, the very
invocation of the said Clause threatens the invocation of the aforesaid Bank
Guarantees, which have been submitted before the concerned Gujarat
Authority by the petitioner no. 1, on behalf of the JV.
18. Thus, the petitioners have filed the petition being O.M.P(I)(COMM.)
23/2026, thereby, seeking directions to the respondent to furnish its own
Bank Guarantees to the concerned Gujarat Authorities, and secure release of
the existing Bank Guarantees furnished by the petitioners, which are under
imminent threat of invocation.
19. Per contra, it is the case of the respondent that till the conciliation and
other contractual dispute resolution mechanisms have run their course, there
can be no crystalized or enforceable claim that could justify the interim
reliefs now sought by the petitioners. Further, no notice of invocation or
demand for payment has been issued by the concerned Gujarat Authority to
ARB.P. 247/2026 & Other Connected Matter Page 7 of 16
the petitioners or the respondent in respect of the Bank Guarantees, nor has
any quantified risk and cost claim been raised. Thus, as per the respondent,
the petition has been founded entirely on speculative apprehensions about
what the concerned Gujarat Authority may do at some uncertain future
point.
20. It is contended by the respondent that if the concerned Gujarat
Authority were to initiate action in future to encash any of the Bank
Guarantees, the petitioners would have an adequate and efficacious remedy
to challenge such action before the appropriate forum, including, by
invoking contractual dispute resolution mechanisms.
21. It is apparent that disputes have arisen between the parties with
respect to the execution of the work by the JV. On one hand, the petitioners
have alleged that the respondent has failed to honour the terms of the
Settlement Agreement and Consent Arbitral Award between the parties, in
not completing the work within the stipulated time period.
22. The respondent, on the other hand, has alleged that the petitioners are
in breach of their obligations under the Settlement Agreement and related JV
arrangements, in as much as they have failed to furnish Retention Bank
Guarantees required for release of retention money held by the concerned
Authority, despite repeated requests and follow-up by the respondent. It is
the case of the respondent that as on date, retention amounts of
approximately Rs. 2.62 Crores under Package-3 and Rs. 10.23 Crores under
Package-5, aggregating to Rs. 12.85 Crores, remain locked with the
concerned Authority, solely because the petitioners have not provided the
requisite Retention Bank Guarantees, thereby, aggravating the respondent’s
cash flow burden.
ARB.P. 247/2026 & Other Connected Matter Page 8 of 16
23. This Court notes the submission of the petitioner that the Gujarat
Authority vide letter dated 31
st
July, 2025 and other letters, has already
invoked the ‘Risk and Cost’ mechanism under Clause 11.13.1 of the EPC
Contract between the JV and the Government of Gujarat. Thus, the
petitioners have a genuine grievance that the Bank Guarantees deposited by
the petitioners are at an imminent risk of being invoked.
24. This Court also takes note of the submissions made on behalf of the
respondent that the petitioners are fully and adequately secured by the
Mortgage Deed dated 06
th
May, 2022 and the Corporate Guarantees.
However, it is the case of the petitioners that the live Bank Guarantees as
deposited by the petitioners amount to Rs. 106.71 Crores, whereas, the
Mortgage Deed secures only to the extent of Rs. 50 Crores. Further, the said
mortgage is with respect to plant and machinery, which are inherently
depreciating assets.
25. It is to be noted that the JV Agreements between the petitioners and
respondent provides for a dispute resolution mechanism through the process
of arbitration. The said Arbitration Clause, i.e., Clause 17 of the JV
Agreements, is reproduced as under:
“xxx xxx xxx
xxx xxx xxx”
ARB.P. 247/2026 & Other Connected Matter Page 9 of 16
26. The petitioners vide Legal Notice dated 19
th
December, 2025 have
already sent notice to the respondent bringing forth the various material
breaches in terms of the Settlement Agreement dated 21
st
December, 2021
read with the Consent Arbitral Award dated 23
rd
February, 2022, and for
proceeding in accordance with law, including, execution of the Consent
Arbitral Award under the Arbitration Act.
27. This Court rejects the submission of the respondent that no notice
under Section 21 of the Arbitration Act has been issued by the petitioner. It
is to be noted that the petitioner had issued a formal notice of arbitration on
06
th
August, 2020, pursuant to which the earlier arbitration proceedings were
conducted. Hence, a fresh notice under Section 21 of the Arbitration Act is
not needed. In this regard reference may be made to the judgment in the case
of Sriram Cables Pvt. Ltd. Versus Union of India, 2024 SCC OnLine Del
5794, wherein, it has been categorically held that the law does not envisage
repeated notices under Section 21 of the Arbitration Act. Thus, it was held
as under:
“xxx xxx xxx
14. There can be no cavil with this proposition as the 1996 Act does
not envisage repeated notices under Section 21. In the present case the
notice dated 18 May 2017 was clearly a notice under Section 21 of the
1996 Act inviting the respondent to refer the dispute to arbitration. That
being so, no fresh notice under Section 21 is required to be issued by the
petitioner.
xxx xxx xxx”
(Emphasis Supplied)
28. In any event, as noted above, a further notice was issued by the
petitioners on 19
th
December, 2025, wherein, the essential elements of notice
under Section 21 are fully envisaged and covered. Furthermore, it is to be
noted that the Supreme Court in the case of Bhagheeratha Engineering Ltd.
ARB.P. 247/2026 & Other Connected Matter Page 10 of 16
Versus State of Kerala, 2026 SCC OnLine SC 5, has held that a notice
under Section 21 of Arbitration Act is not a mandatory pre-condition in all
arbitration contexts. Thus, it has been held as under:
“xxx xxx xxx
16. Secondly, the object of Section 21 of A&C Act, is only for the
purpose of commencement of arbitral proceedings is also well settled.
Section 21 is concerned only with determining the commencement of the
dispute for the purpose of reckoning limitation. There is no mandatory
prerequisite for issuance of a Section 21 notice prior to the
commencement of Arbitration. Issuance of a Section 21 notice may
come to the aid of parties and the arbitrator in determining the limitation
for the claim. Failure to issue a Section 21 notice would not be fatal to a
party in Arbitration if the claim is otherwise valid and the disputes
arbitrable. …
xxx xxx xxx”
(Emphasis Supplied)
29. Further, this Court takes note of the submission made on behalf of the
respondent that by way of an E-mail dated 06
th
May, 2026, the respondent
has also invoked Clause 12.1 of the Mortgage Deed dated 06
th
May, 2022,
which contains the Arbitration Clause for referring the disputes between the
parties for arbitration. The related portions from the reply of the respondent
in O.M.P.(I) (COMM) 23/2026, are extracted as below:
“xxx xxx xxx
ARB.P. 247/2026 & Other Connected Matter Page 11 of 16
xxx xxx xxx
xxx xxx xxx”
30. Clause 12.1 of the Mortgage Deed dated 06
th
May, 2022 between the
petitioner and respondent containing the Arbitration Clause, is reproduced as
under:
ARB.P. 247/2026 & Other Connected Matter Page 12 of 16
“
”
31. Thus, the respondent has already invoked the Arbitration Clause
under the Mortgage Deed dated 06
th
May, 2022 vide E-mail dated 06
th
May,
2026.
32. This Court notes that the parties has initially entered into a Mortgage
Deed dated 21
st
December, 2021, and the same forms an integral part of the
Settlement Agreement, and was placed before the earlier Arbitral Tribunal,
and expressly recorded as Annexure-B to the Settlement Agreement in the
Consent Arbitral Award.
33. Reference may be made to the relevant terms of the Mortgage Deed
dated 21
st
December, 2021, executed between petitioner no. 1 and
respondent, which read as under:
ARB.P. 247/2026 & Other Connected Matter Page 13 of 16
“xxx xxx xxx
xxx xxx xxx”
34. Reference is also made to the relevant terms of the Mortgage Deed
dated 06
th
May, 2022, which read as under:
“xxx xxx xxx
ARB.P. 247/2026 & Other Connected Matter Page 14 of 16
xxx xxx xxx”
35. Reference to the aforesaid Mortgage Deeds, makes it evident that the
execution of the Mortgage Deed dated 06
th
May, 2022 was in terms of the
earlier Mortgage Deed dated 21
st
December, 2021, and the former also
forms an essential part of the larger settlement between the parties.
36. Thus, the disputes as raised by the petitioners with regard to non-
compliance of the terms of the Settlement Agreement and Consent Arbitral
Award and the disputes with regard to the Mortgage Deed dated 06
th
May,
2022, are intertwined.
37. Accordingly, all the disputes raised by the petitioners in terms of the
JV Agreements between the parties, for violation of the terms of the
Settlement Agreement and Consent Arbitral Award and all the disputes in
terms of the Mortgage Deed between the parties, in terms of the invocation
of the Arbitration Clause by the respondent, are to be referred for
adjudication before an Arbitral Tribunal.
38. While the petitioners seek reference of the disputes to the same
Arbitrator as earlier, however, learned Senior Counsel appearing for the
respondent has expressed reservations for reference of the disputes to the
same arbitrator. Nonetheless, learned Senior Counsel appearing for the
respondent submits that all disputes between the parties can be referred to
ARB.P. 247/2026 & Other Connected Matter Page 15 of 16
some other Arbitrator.
39. Though this Court finds no reason to not refer the disputes that have
arisen between the parties, to the same Arbitrator who had earlier
adjudicated the disputes between them, however, considering the
submissions made by learned Senior Counsel appearing for the respondent,
this Court proceeds to appoint another Arbitrator.
40. Accordingly, considering the detailed discussion hereinabove, the
following directions are issued:
I. Justice (Retired) Jayant Nath, Former Judge of this Court,
(M:8527959494), is appointed as Sole Arbitrator to adjudicate
disputes between the parties.
II. All the disputes between the parties under the JV Agreements, the
Mortgage Deed, the Settlement Agreement, and the Consent Arbitral
Award, are referred to the learned Arbitrator.
III. The petition under Section 9 of the Arbitration Act is referred before
the learned Arbitrator to be taken up as an application under Section
17 of the Arbitration Act.
IV. The remuneration of the Arbitrator shall be in terms of Schedule IV of
the Arbitration Act.
V. The Arbitrator is requested to furnish a declaration in terms of Section
12 of the Arbitration Act prior to entering into the reference. In the
event there is any impediment to the Arbitrator’s appointment on that
count, the parties are given liberty to file an appropriate application
before this Court.
VI. It shall be open to the respondent to raise counter-claims, if any, in the
arbitration proceedings.
ARB.P. 247/2026 & Other Connected Matter Page 16 of 16
VII. It is made clear that all the rights and contentions of the parties,
including, the arbitrability of any of the claims and/or counter-claims,
any other preliminary objection, as well as claims on merits of the
dispute of either of the parties, are left open for adjudication by the
learned Arbitrator.
VIII. The parties shall approach the Arbitrator within two (2) weeks from
today.
41. It is made clear that this Court has not expressed any opinion on the
merits of the case.
42. Accordingly, the present petitions, along with the pending
applications, are disposed of in the aforesaid terms.
43. The Registry is directed to send a copy of this order to the learned
Arbitrator, for information and compliance.
MINI PUSHKARNA
(JUDGE)
MAY 26, 2026/ak
Legal Notes
Add a Note....