IN THE HIGH COURT OF ANDHRA PRADESH: AMARAVATI
WRIT PETITION No.25317 OF 2011
% Dated 31.12.2024
#W.P.No.25317 OF 2011
M/s. Lanco Kondapalli Power Limited,
Plot No.4, Softsol Building,
Software Units Layout,
Hitec City, Madhapur
Hyderabad – 500 081 and another
….. Petitioners
Vs.
$
Andhra Pradesh Power Coordination Committee,
Vidyut Soudha, Hyderabad
Rep by its Chief Engineer (Commercial) & 6 others
…....Respondents
JUDGMENT PRONOUNCED ON: 31.12.2024
THE HON’BLE SRI JUSTICE VENKATESWARLU NIMMAGADDA
Whether Reporters of Local newspapers
may be allowed to see the Judgments?
Whether the copies of judgment may be marked to Law
Reporters/Journals
Whether Their Ladyship/Lordship wish to see the fair
copy of the Judgment?
2
NV,J
W.P.No.25317 of 2011
* THE HON’BLE SRI JUSTICE VENKATESWARLU NIMMAGADDA
+ WRIT PETITION No.25317 OF 2011
% Dated 31.12.2024
#W.P.No.25317 OF 2011
M/s. Lanco Kondapalli Power Limited,
Plot No.4, Softsol Building,
Software Units Layout,
Hitec City, Madhapur
Hyderabad – 500 081 and another
….. Petitioners
Vs.
$
Andhra Pradesh Power Coordination Committee,
Vidyut Soudha, Hyderabad
Rep by its Chief Engineer (Commercial) & 6 others
…....Respondents
! Counsel for the petitioner : Sri D.S. Sivadarshan
^ Counsel for the respondent :
1. Learned Advocate General
2. Sri V.R. Reddy Kovvuri
3. Sri Anup Kowshik Karavadi
<GIST:
> HEAD NOTE:
? Cases referred
1. 2008 ELR (SC) 0001
2. CA (AT) (Insol) No.650 of 2020 dated 25.02.2022
3
NV,J
W.P.No.25317 of 2011
THE HON’BLE SRI JUSTICE VENKATESWARLU NIMMAGADDA
WRIT PETITION No.25317 OF 2011
ORDER:-
1. The writ petition is filed challenging the action of the respondents
in limiting the installed capacity of the 1
st
petitioner company’s project to
361.92 MW as against 368.144 MW pending adjudication of the issue by
competent forum and making the monthly payment basing on the
reduced installed capacity as arbitrary, illegal, in violation of Principles of
Natual Justice besides violating the rights guaranteed under Articles 14
and 19(1)(g) of Constitution of India.
2. The 1
st
Petitioner is a company, initially incorporated as M/s. Lanco
Power Limited and later renamed multiple times, engaged in electricity
generation. It entered into a Power Purchase Agreement (PPA) with the
A.P. State Electricity Board for a power project at Kondapalli Village,
Krishna District. The PPA was later reentered and later constituted with
various government utilities under the Andhra Pradesh Electricity
Reforms Act, 1998.
4
NV,J
W.P.No.25317 of 2011
3. The Petitioner owns and operates a 368.144 MW power project at
Kondapalli, which commenced operations in October 2000. Despite
initial delays, the respondents began purchasing power from the
Petitioner in January 2001. The installed capacity was tested and
confirmed to be 368.144 MW, which was accepted by the 2nd
Respondent. However, in 2003, the 2
nd
Respondent sought to reduce
the installed capacity, proposing adjustments based on ISO standards
and tolerance limits. The Petitioner objected, arguing that the installed
capacity had been agreed upon in 2001 and could not be re-examined.
4. The dispute escalated when the 2
nd
Respondent threatened to
revise the capacity and related payments. The Petitioner filed a Civil
Court case in 2003 under the Arbitration and Conciliation Act, which
resulted in an order in its favor in 2008. The respondents appealed, and
the case remains pending.
5. Meanwhile, the 2
nd
Respondent approached the A.P. Electricity
Regulatory Commission (APERC) in 2004 to resolve the dispute,
bypassing the dispute resolution mechanism outlined in the PPA. The
5
NV,J
W.P.No.25317 of 2011
Petitioner subsequently filed a writ petition in 2004 challenging APERC’s
jurisdiction, and the case is ongoing.
6. The Andhra Pradesh Government constituted a committee in 2008
to resolve the issue, which referred the matter to the Central Electricity
Authority (CEA). The CEA’s report in 2010 said that an installed capacity
of 361.92 MW, for which the Respondents issued subsequent billings.
The Petitioner contested this, arguing that the CEA report ignored
certain technical aspects, and requested the Government to reconsider
the issue of its production capacity
7. Despite the pending disputes, the Respondents unilaterally
reduced the installed capacity in 2011, which the Petitioner challenged
as illegal and in violation of court orders. The reduction led to short
payments, and the Petitioner faced severe financial difficulties. The
Petitioner seeks interim relief, including the restoration of the original
installed capacity and the payment of the full amounts owed, pending
the final resolution of the dispute.
8. The Petitioner requests a writ to declare the Respondents' actions
as unlawful and to restrain them from making deductions based on the
6
NV,J
W.P.No.25317 of 2011
disputed CEA report, pending the outcome of the proceedings before the
competent authorities.
9. The Respondents deny the Petitioner's claims, asserting that the
installed capacity of the Petitioner’s project is 351.49 MW, not the
claimed 368.144 MW. They explain that in 2001, due to an error, the
capacity was mistakenly considered as 368.144 MW, which was later
corrected in 2003, and the Petitioner was notified of this mistake. They
contend that their actions were neither arbitrary nor illegal and that the
Petitioner is estopped from disputing the CEA report dated 12-01-2010.
Regarding the Commercial Operation Date (COD), the Respondents
argue that the date and capacity determination are disputed, with the
capacity initially overstated due to an incorrect calculation in 2001, and
the correct capacity should be 351.49 MW.
10. The Respondents further assert that the dispute should be
adjudicated by APERC, following the dismissal of the Petitioner’s
arbitration application, and that the dispute resolution mechanism in the
PPA does not apply. Concerning the CEA report, the Respondents
clarify that the report dated 12-01-2010, which sets the installed capacity
7
NV,J
W.P.No.25317 of 2011
at 361.92 MW, was issued at the Petitioner’s request, and they are
willing to adopt this figure temporarily until APERC’s final decision. The
Respondents argue that the Petitioner cannot contest the CEA report
since it was initiated by the Petitioner.
11. The Respondents also defend their action of revising the capacity
to 361.92 MW, stating that it was not unilateral or in violation of natural
justice. The revision was made after consulting the Petitioner and was
necessary to correct the earlier error, which led to the Petitioner
receiving excess payments. They emphasize that the revision was in the
public interest, as the Petitioner had been overpaid by over Rs. 1 crore
per month, and continuing with these payments would cause significant
financial burden to public exchequer.
12. Finally, the Respondents request that the Petition should be
dismissed, arguing that any interim relief in favor of the Petitioner would
burden the consumers, and that the balance of convenience is in favour
of the Respondents.
8
NV,J
W.P.No.25317 of 2011
13. During hearing, learned counsel for the petitioner submits that the
writ petition is liable to be dismissed as infructuous, in view of the orders
passed in C.M.A.No.1284 of 2008 by the Division Bench of Hon’ble High
Court of Telangana.
14. On the other hand, learned Advocate General appearing for the
respondents opposed the contention of the learned counsel for the
petitioner and submits that, the claim of the respondents did not become
infructuous, for the reason that, in view of the ratio laid down by the
Hon’ble Supreme Court in Gujarat Urja Vikash Nigam Limited vs.
Essar Power Limited
1
, conferring the jurisdiction of Andhra Pradesh
Electricity Regulatory Commission (for short hereinafter referred as
APERC’) in respect of disputes between the state power utilities and
licensees/power generating companies, as per the provisions of the
Electricity Act, 2003.
15. He submits that, in consonance with the ratio laid down by the
Hon’ble Apex Court in Essar Power Limited case, the 2
nd
respondent
invoked the jurisdiction of APERC in respect of the installed capacity of
1
2008 ELR (SC) 0001
9
NV,J
W.P.No.25317 of 2011
the project of the petitioners by way of O.P (SR) No.10 of 2004 before
the Hon’ble APERC. He further submits that, the order in O.P.(SR)
No.10 of 2004 have attained finality and the said order was assailed in
W.P.No.738 of 2004, challenging the vires of the Electricity Act, 2003, as
unconstitutional and sought relief to declare that APERC has no
jurisdiction.
16. He submits that, initially, Hon’ble High Court of Telangana granted
interim order directing APERC not to proceed with O.P.(SR) No.10 of
2004, as such the same is still pending for further consideration. He
further submits that, considering the project installed capacity as 351.49
MW, the excess payment made to the petitioner comes to Rs.145 crores
from the year 2001 and by considering 361.92 MW as capacity of
project, as per the second report of Central Electricity Authority, the
excess payment made is Rs.53.00 crores, thereby the said excess
amount needs to be recovered. Therefore, the impugned proceedings in
the writ petition did not become infructuous, as contended by the learned
counsel for the petitioner, in view of the fact that the petitioner underwent
IBC and in view of the orders passed by NCLT, as mentioned above.
10
NV,J
W.P.No.25317 of 2011
17. Heard learned Senior Counsel for the petitioner, learned Advocate
General for the respondents and perused the material available on
record.
18. The contention of the learned Senior Counsel for the petitioner that
once the petitioner company underwent the process of Insolvency and
Bankruptcy Code, at any stage of pending proceedings against the
Corporate Debtor Company, as an outgoing concern, it cannot enforce
against the Corporate Debtor Company is valid and sustainable, in view
of the ratio laid down by the Hon’ble National Company Law Appellate
Tribunal, Principal Bench, New Delhi in M/s. Shiv Shakti Inter Globe
Exports Pvt. Ltd vs. M/s. KTC Foods Private Limited & another
2
,
wherein it is held as follows:
21. Adverting to the contention of the Learned Counsel for
the Appellant that the Adjudicating Authority has erred in
denying the sale of the ‘Corporate Debtor’ as a ‘going
concern’ to the Appellant without including any contingent
liabilities, we hold that it is a settled law that when the sale
proceeds of a” ‘Corporate Debtor’ are duly distributed in the
Order of priority and in the manner prescribed under Section
2
CA (AT)(Insol) No.650 of 2020 dated 25.02.2022
11
NV,J
W.P.No.25317 of 2011
53 of the Code, claims of any other Creditor cannot be
entertained contrary to the provisions entailed under Section
53; subsequent to the distribution of sale proceeds under
Section 53 no other entity including any Government entity
can claim any past unpaid or outstanding dues against the
Appellant who has purchased the ‘Corporate Debtor
Company’ as a ‘going concern’. It is significant to mention
that the second Respondent/Liquidator has specifically
submitted that even these claims by the Uttar Haryana Bijili
Vitran Nigam were not submitted in the prescribed form either
during the CIRP Process or at the Liquidation stage. We are
of the considered view that at this stage subsequent to the
sale of the ‘Corporate Debtor Company’ as a ‘going concern’,
these claims cannot be foisted upon the Appellant. The
scope and objective of the Code is to extinguish all claims
specifically the ones which were not even made during the
CIRP or in the Liquidation stage, to aid the purchaser of the
Company as a ‘going concern’ to start on a ‘clean slate’. The
Hon’ble Supreme Court in ‘Ghanshyam Mishra & Sons Pvt.
Ltd.’ Vs. ‘Edelweiss Asset Reconstruction Company Ltd. &
Ors.’, Civil Appeal No. 8129 of 2019 and in ‘CoC of Essar
Steel India Ltd.’ Vs. ‘Satish Gupta & Ors.’ (2020) 8 SCC 531
has laid down the proposition that the purchaser of the
Company even in the Liquidation stage cannot be burdened
12
NV,J
W.P.No.25317 of 2011
with past liabilities when it is not mentioned in the ‘Sale
Notice’.”
19. Therefore, the submission of the learned counsel for the petitioner
that the claim of the respondents regarding recovery of money which is
not finally determined so far and after finalization of proceedings under
IBC Code, the respondents are not entitled for any claim, more
particularly, the claim under the impugned proceedings became
infructuous, as held by the Division Bench of the Hon’ble High Court of
Telangana in C.M.A.No.1284 of 2008 is incorrect. The contention of the
petitioner that the impugned proceedings have become infructuous is
not a merit submission, since the proceedings for determination between
the parties is pending by way of O.P on the file of APERC, much before
to the proceedings invoked under IBC. Moreso, the said proceedings
were allowed at the instance of the petitioner by filing W.P.No.7838 of
2004 on the file of the Hon’ble High Court of Telangana.
20. The contention of the learned Advocate General for the
respondents that, the Central Electricity Authority submitted a report, one
in the year 2005 at the instance of the respondents holding that the
installed capacity of the petitioner is 351.49 MW only and received
13
NV,J
W.P.No.25317 of 2011
money at the rate of the installed capacity of the petitioner 368.144 MW.
But, later, at the instance of the petitioner, the Central Electricity
Authority finally submitted its another report, wherein it is held that, in the
year 2010, the installed capacity of the petitioner is only 361.92 MW.
21. From the above, it is clear and categorical that the petitioner is
under liability to the respondents for extra claim amount already received
by the petitioner, for which, the respondents invoked the jurisdiction of
APERC, which is the competent adjudicating authority for redressal of
the disputes between the respondents and the petitioners, as held in
Gujarat Urja Vikash Nigam Limited vs. Essar Power Limited, is a
valid submission and liable to be accepted.
22. Further, the adjudicatory proceedings filed for redressal of the
disputes regarding the installed capacity of the project of the petitioner
are pending on the file of the APERC did not become infructuous. Since
the claimant before the Commission is a public authority and the
petitioner received excess amount from the public exchequer. Therefore,
the question whether the respondents can recover the amount or not
14
NV,J
W.P.No.25317 of 2011
even after completion of adjudication before the APERC can be decided
by invoking appropriate proceedings before the competent authority.
23. Having considered the facts and circumstances of the case and
the legal proposition relied upon by both the counsel, liberty is granted to
the petitioner and respondents to sort out their claims by themselves,
proposing out of these legal principles pending before APERC.
24. With the above, writ petition is disposed of. No costs.
25. Consequently, miscellaneous applications pending if any, shall
stand closed.
_____________________________________
JUSTICE VENKATESWARLU NIMMAGADDA
Date: 31.12.2024
SP
15
NV,J
W.P.No.25317 of 2011
THE HON’BLE SRI JUSTICE VENKATESWARLU NIMMAGADDA
WRIT PETITION No.25317 OF 2011
Date: 31.12.2024
Note: LR copy to be marked
W
SP
Legal Notes
Add a Note....