No Acts & Articles mentioned in this case
Neeta Sawant WP(L)-12949-2024-FC
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION
WRIT PETITION NO.(L) NO. 12949 OF 2024
M/s. Lashkaria Housing &
Infrastructure Pvt. Ltd. } ..Petitioner
: Versus :
1. Slum Rehabilitation Authority
2. Chief Executive Ofcer
3. Sarvodaya Residence SRA CHS
(Proposed)
4. Apex Grievance Redressal Committee} ..Respondent
WITH
INTERIM APPLICATION (LODG.) NO. 15499 OF 2024
IN
WRIT PETITION (LODG.) NO. 12949 OF 2024
1. Salahuddin Akid Ansari
2. Mohd. Israeel Abdul Rahid Khan
3. Mohd. Asif Noor Mohd. Khan
4. Sabera Shahid Varsi } ..Applicant/ Intervenor
(Proposed Respondent)
In the matter between :
M/s. Lashkaria Housing &
Infrastructure Pvt. Ltd. } ..Petitioner
: Versus :
Page No. 1 of 26
10 May 2024 2024:BHC-OS:7931
::: Uploaded on - 10/05/2024 ::: Downloaded on - 30/08/2025 20:51:12 :::
Neeta Sawant WP(L)-12949-2024-FC
1. Slum Rehabilitation Authority
2. Chief Executive Ofcer
3. Sarvodaya Residence SRA CHS
(Proposed)
4. Apex Grievance Redressal Committee} ..Respondent
________________________________________________
Mr. Mayur Khandeparkar, with Mr. Santosh Pathak, Mr. Chirag Thakkar
and Mr. Kailash Pathak, for the Petitioner.
Mr. Jagdish G. Aradwad (Reddy) for Respondent Nos.1 and 2.
Mr. Cherag Balsara i/by. Mr. Milind Nar, for Respondent No.3.
Ms. Uroosa Shaikh i/by. Mr. Anup Patil for AGRC, Respondent No.4.
Mr. Amogh Singh with Ms. Priya Chaturvedi i/by. Mr. Nimish Lotlikar for
Applicant in IAL-15499 of 2024.
CORAM : SANDEEP V. MARNE, J.
Reserved On : 9 MAY 2024.
Pronounced On : 10 MAY 2024.
J U D G M E N T:
1) Petitioner-Developer has fled this petition challenging the
Order dated 8 April 2024 passed by the Apex Grievance Redressal
Committee (AGRC), rejecting Petitioner’s Application No. 228 of 2023
and upholding the Order dated 28 August 2023 passed by Chief
Executive Ofcer, SRA (CEO/SRA) terminating Petitioner’s
appointment as Developer under Section 13(2) of the Maharashtra Slum
Areas (Improvement, Clearance and Redevelopment) Act, 1971 (Slum
Act).
Page No. 2 of 26
10 May 2024 ::: Uploaded on - 10/05/2024 ::: Downloaded on - 30/08/2025 20:51:12 :::
Neeta Sawant WP(L)-12949-2024-FC
2) The petition concerns implementation of Slum
Rehabilitation Scheme (SRS) in respect of Plot bearing Survey No. 41,
CTS No.1 (Pt.) of Village-Oshiwara, Taluka-Andheri, Anand Nagar,
Jogeshwari West, Mumbai- 400 012. It appears that one M/s. Hridaya
Constructions Pvt. Ltd. (Hridaya) was appointed by the slum dwellers,
through their Society named Sarvodaya Residence SRA CHS
(Proposed), as Developer for implementation of SRS on the plot. It
appears, Society also adopted a Resolution in its General Body on 25
March 2018 resolving to cancel the appointment of Hridaya and to
appoint Petitioner as new Developer to implement the subject SRA.
Accordingly, on Society’s application, CEO/SRA initiated action for
termination of appointment of Hridaya under provisions of Section 13(2)
of the Slum Act and passed order dated 26 June 2018 terminating the
appointment of Hridya and granting liberty to Society to implement the
SRS through Petitioner as per provisions of prevailing law, rules and
regulations.
3) Petitioner was accordingly appointed as a developer for
implementation of subject SRS by letter dated 13 July 2021. Letter dated
1 August 2022 was submitted on the letterhead of Respondent No.3-
Society, which was signed by 31 plus 7 persons seeking termination of
appointment of Petitioner under the provisions of Section 13(2) of the
Slum Act inter-alia on the ground that despite its appointment in the
year 2018, Petitioner did not make any progress in the scheme.
Page No. 3 of 26
10 May 2024 ::: Uploaded on - 10/05/2024 ::: Downloaded on - 30/08/2025 20:51:12 :::
Neeta Sawant WP(L)-12949-2024-FC
4) The CEO/SRA initiated proceedings under Section 13(2) of
the Slum Act in which Petitioner was heard. However, it appears that
the Chief Promoter of Respondent No.3-Society submitted letter dated
6 July 2023 before CEO/SRA questioning the authority of persons to
address letter dated 1 August 2022 on Society’s letterhead and requested
for rejection of the application. CEO/SRA, after hearing parties, passed
order dated 28 August 2023 allowing the application and terminated the
appointment of Petitioner as Developer to implement the subject SRS.
The Joint Registrar/SRA has been directed to hold the General Body
meeting for appointment of Chief Promoter and other promoters of the
Society. The Society has been granted liberty to appoint new developer
of its choice.
5) Aggrieved by CEO/SRA’s order dated 28 August 2023,
Petitioner fled Application No. 228/2023 before AGRC. During
pendency of the application, AGRC stayed the order of CEO/SRA.
After hearing parties, AGRC has proceeded to dismiss Petitioner’s
application.
6) Petitioner has accordingly fled the present petition
challenging Orders passed by AGRC and CEO/SRA. By order dated 17
April 2024, this Court has continued the stay granted by AGRC.
7) I have heard Mr. Mayur Khandeparkar, the learned counsel
appearing for the Petitioner. He would question the locus of signatories
to the application dated 1 August 2022 to maintain an action seeking
Page No. 4 of 26
10 May 2024 ::: Uploaded on - 10/05/2024 ::: Downloaded on - 30/08/2025 20:51:12 :::
Neeta Sawant WP(L)-12949-2024-FC
termination of appointment of Petitioner. He would submit that
Society’s Chief Promoter, alone can represent it, who did not seek
termination of Petitioner and infact sought dismissal of application fled
by unauthorised persons. Relying on judgment of Division Bench in
Nirman Realtors and Developers Ltd. Versus Slum Rehabilitation
Authority
1
, he would submit that slum dwellers in their individual
capacity cannot seek termination of developer under Section 13(2) of the
Slum Act.
8)He would submit that the CEO/SRA has erred in terminating the
appointment of Petitioner without appreciating the fact that there has
been no delay on the part of the Petitioner in implementing the subject
SRS. That Petitioner’s proposal came to be accepted by SRA on 13 July
2021. That the project involves rehabilitation of approximately 432
hutments divided over three parts of land. That the frst part of the land
belongs to MCGM, which has 210 structures and in respect of which
Annexure-II has been issued on 16 March 2005 declaring 138 slum
dwellers eligible and 72 ineligible. The second part of the land is owned
by MHADA, on which there are 120 structures and in Annexure-II
issued on 21 December 2005, 66 slum dwellers are held eligible and 54
ineligible. That the third portion of land is owned by MHADA, on
which there are 97 structures and that Annexure-II in respect of that
portion of the land is yet to be fnalised and is at draft stage. He would
invite my attention to public notice dated 25 February 2022 issued by
MHADA for conduct of bio-metric survey of slum structures on the
1
2017 SCC OnLine Bom 9201.
Page No. 5 of 26
10 May 2024 ::: Uploaded on - 10/05/2024 ::: Downloaded on - 30/08/2025 20:51:12 :::
Neeta Sawant WP(L)-12949-2024-FC
third portion of the land. That it is for MHADA to fnalise Annexure-II
in respect of third part of land, in absence of which, Petitioner cannot fle
a proposal for issuance of Letter of Intent (LOI). He would rely upon
order passed by this Court in Adarsh SRA Sahakari Gruhanirman
Sanstha Ltd. and Anr. V/s. Slum Rehabilitation Authority and Ors.
2
holding that developer cannot be held responsible in absence of pending
eligibility of slum dwellers. He would rely upon survey conducted at the
instance of District Superintendent of Land Records, SRA vide letter
dated 24 February 2023. He would invite my attention to Survey Map
indicating overlapping requiring further permissions/approvals from
Competent Authorities. That another Developer is unauthorisedly
constructing structure on the DP road, about which complaints are fled
by the Society. That Letter dated 23 February 2023 is challenged by
M/s. Sunil Constructions in this Court to prevent conduct of survey. He
would submit that if above circumstances are taken into consideration, it
cannot be contended that there is any delay on the part of the Petitioner
in implementing the subject SRS.
9) Mr. Khandeparkar would submit that the CEO/SRA has
not applied his mind objectively to the above circumstances and has
proceeded to allow application of unauthorised persons in a mechanical
manner. That AGRC has failed to correct the error committed by CEO/
SRA by not appreciating that non-fnalisation of Annexure-II in respect
of third portion of the land is not attributable to Petitioner in any
manner.
2
Writ Petition (Lodg.) No. 11493 of 2023 decided on 4 December 2023.
Page No. 6 of 26
10 May 2024 ::: Uploaded on - 10/05/2024 ::: Downloaded on - 30/08/2025 20:51:12 :::
Neeta Sawant WP(L)-12949-2024-FC
10) Respondent No.3-Society is apparently split into two parts
and Mr. Cherag Balsara as well as Mr. Amogh Singh claim right to
represent it. While Mr. Balsara opposes the petition, Mr. Singh supports
it.
11) Mr. Balsara would submit that the CEO/SRA has rightly
terminated the appointment of Petitioner, who has been simply sitting
over the scheme ever since his appointment by the Society. That instead
of proceeding ahead with implementation of slum scheme in respect of
second portion of land comprising 120 slum structures, Petitioner has
been deliberately delaying the same with a view to expand the ambit of
the scheme by incorporating the frst and third portions of the land in the
scheme. That Petitioner was allotted only second portion of land
comprising 120 slum structures and that in his quest to expand the slum
scheme, it has deliberately delayed issuance of LOI till all the problems
concerning frst and third portions of land are sorted out. That the slum
dwellers of frst and third portions of land do not desire implementation
of their schemes through Petitioner. That another developer named
M/s. Sunil Constructions is claiming rights in respect of frst portion of
land and has fled petition in this Court challenging actions of the
Petitioner for amalgamation of that land in the slum scheme of 120
structures. That the slum society on third portion of land comprising of
97 structures have complained to SRA about their opposition to include
the third portion of land in the slum scheme allotted to Petitioner. That
Petitioner has thus created complications in implementation of the slum
scheme allotted to it to satisfy its greed to implement the scheme in
Page No. 7 of 26
10 May 2024 ::: Uploaded on - 10/05/2024 ::: Downloaded on - 30/08/2025 20:51:12 :::
Neeta Sawant WP(L)-12949-2024-FC
respect of larger portions of land. That though Hridaya was earlier
granted permission to develop 433 slum structures, the scheme allotted
to Petitioner is only in respect of second portion of land covering 120
slum structures. That the AGRC has rightly appreciated the fact that
Petitioner has neither secured consent of slum dwellers on adjoining
plots nor has made any progress towards implementation of SRS allotted
to him. He would pray for dismissal of the petition.
12) Mr. Singh, the learned counsel appearing for rival part of
Respondent No.3-Society represented by Mr. Salahuddin Akeen Ansari
(Chief Promoter) and other co-promoters, would support the petition.
They have fled Interim Application (L) No. 15499/2024 to support the
petition on behalf of Respondent No.3-Society. Mr. Singh would submit
that implementation of the subject SRS involves all the three portions of
land comprising of 432 slum structures.
13) Mr. Aradwad (Reddy), the learned counsel appearing for
Respondent Nos.1 and 2-SRA would oppose the petition and submit that
the factual position as captured in the order of the CEO/SRA would
undoubtedly indicate that the slum scheme allotted to Petitioner is only
in respect of 120 structures and not in respect of 432 structures, as
falsely claimed by Petitioner. Supporting the Order of CEO/SRA, he
would therefore pray for dismissal of the petition.
14) Rival contentions of the parties now fall for my
consideration.
Page No. 8 of 26
10 May 2024 ::: Uploaded on - 10/05/2024 ::: Downloaded on - 30/08/2025 20:51:12 :::
Neeta Sawant WP(L)-12949-2024-FC
15) It must be observed at the very outset that, the present
petition is full of confusion on multiple aspects. Firstly, there is a
confusion as to who can represent Respondent No.3-Society as both Mr.
Balsara as well as Mr. Singh claim right of representation on its behalf.
This is something which is not very uncommon in SRA societies where
rival groups of slum dwellers are often formed, who are usually backed
by rival developers. I am not surprised that in the present case also two
rival groups claim to represent the society. The second confusion, which
to my mind, goes to the root of the matter and clarifcation of which
provides an answer to the issue involved in the present petition, relates
to the exact land on which Petitioner was allotted SRS for
implementation. While answer to the frst confusion is useful for
deciding preliminary objection of Mr. Khandeparkar about locus to
maintain action under Section 13(2) of the Slum Act, clarity about
second confusion leads to answer on merits of the petition.
16) Before proceeding to decide merits of the orders passed by
the CEO/SRA and AGRC, it would be necessary to frst deal with the
objection raised by Mr. Khandeparkar about locus of signatories to the
complaint dated 1 August 2022 to maintain an action for termination of
developer under Section 13(2) of the Slum Act. No doubt, the law on the
subject is well settled that application for seeking termination of
developer under Section 13(2) of the Slum Act cannot be initiated by an
individual slum dweller. This obviously is the position because the
decision to choose the Developer is collectively taken by the society of
slum dwellers. Once the society collectively chooses a developer, whose
Page No. 9 of 26
10 May 2024 ::: Uploaded on - 10/05/2024 ::: Downloaded on - 30/08/2025 20:51:12 :::
Neeta Sawant WP(L)-12949-2024-FC
proposal is accepted by SRA for implementation of SRS in question,
ordinarily only that collective body viz. Society can maintain an action
under Section 13(2) of the Slum Act for removal of the developer. Mr.
Khandeparkar’s reliance on judgment of Division Bench of this Court in
Nirman Realtors (supra) in this regard is apposite. This Court held in
para-20, 21 and 24 of the judgment as under:
20. Undisputedly, the application under Section 13(2) of the Slum Act
was fled by the Respondent No. 3 in her individual capacity as a slum
dweller. It is well settled that an individual slum dweller or the
proposed society of the slum dwellers cannot seek removal of the
developer, who was appointed by the registered society after obtaining
consent of 70% of the slum dwellers. This being the case the
application under Section 13(2) of the Slum Act fled by an individual
slum dweller was not maintainable.
21. There is no dispute that a Developer who has been appointed by a
Cooperative Society is under obligation to fulfll the mandate of DCR
33(10). When the Developer develops the land in contravention of
plan or contravenes any restrictions or conditions or does not
implement the scheme within the time, Section 13(2) of the Slum Act
confers powers on the Competent Authority to remove the errant
Developers and replace by any other competent agency.
24. It is also to be noted that the High Power Committee has observed
that the Petitioner has failed to pay rent of transit accommodation to
the eligible slum dwellers. Non-payment of rent was one of the
grounds for removal of the Petitioner as a Developer. It is to be noted
that the show cause notice issued to the Petitioner in Section 13(2)
proceedings does not refer to removal on the ground of non-payment
of rent. The decision to remove the Petitioner as Developer on the
ground of non-payment of rent is beyond the allegations contained in
the show cause notice and is therefore breach of principles of natural
justice.
17) While it is well settled that application for termination of
developer cannot be fled by individual slum dwellers under Section
Page No. 10 of 26
10 May 2024 ::: Uploaded on - 10/05/2024 ::: Downloaded on - 30/08/2025 20:51:12 :::
Neeta Sawant WP(L)-12949-2024-FC
13(2) of the Slum Act, it is equally true that initiation of action under
Section 13(2) does not need a trigger of an application by the society.
Infact, sub-section (2) of Section 13 is couched in such manner that, it
vests jurisdiction in the Competent Authority to withdraw a slum
scheme from owner or developer. All that is needed for passing an order
under Section 13(2) is ‘satisfaction’ of the Competent Authority.
Section 13 of the Slum Act provides thus:
13. Power of Competent Authority to redevelop clearance area
(1) Notwithstanding anything contained in sub-section (1) of section
12 the Competent Authority may, at any time after the land has been
cleared of buildings in accordance with a clearance order, but before
the work of redevelopment of that land has been commenced by the
owner, by order, determine to redevelop the land at its own cost, if
that Authority is satisfed that it is necessary in the public interest to
do so.
(2) Where land has been cleared of the buildings in accordance with a
clearance order, the Competent Authority, if it is satisfed that the
land has been, or is being, redeveloped by the owner thereof in
contravention of plans duly approved, or any restrictions or conditions
imposed under sub-section (10) of Section 12, or has not been
redeveloped within the time, if any, specifed under such conditions,
may, by order, determine to redevelop the land at its own cost:
Provided that, before passing such order, the owner shall be given
a reasonable opportunity of showing cause why the order should not
be passed.
18) The scope of power of Competent Authority under Section
13(2) of the Slum Act has been explained by the Apex Court in Susme
Builders Private Limited Vs. Chief Executive Ofcer, Slum
Rehabilitation Authority
3
in which the Apex Court has held as under:
3
(2018) 2 SCC 230
Page No. 11 of 26
10 May 2024 ::: Uploaded on - 10/05/2024 ::: Downloaded on - 30/08/2025 20:51:12 :::
Neeta Sawant WP(L)-12949-2024-FC
45. We cannot accept such a wide submission. According to us, under
Section 13(2) of the Slum Act, the SRA has the authority to take
action and hand over the development of land to some other
recognised agency under three circumstances:
(i) When there is contravention of the plans duly
approved;
(ii) When there is contravention of any restriction or
condition imposed under sub-section (10) of Section 12 of the
Slum Act; and
(iii) When the development has not taken place within
time, if any, specifed.
46. The requirement to complete the development within time may be
there in the letter of intent issued by the SRA or may be in the
agreement entered into between the owner/developer with the slum-
dwellers. Such condition, if violated, would attract the provisions of
Section 13(2) of the Slum Act. Over and above that, when a clearance
order is passed, then in terms of sub-section (10) of Section 12, the
competent authority can include a condition with regard to the time
within which the development should be completed and, in that case,
also Section 13(2) would be attracted. We are not, however, able to
accept the very wide argument that in case of delay, the condition that
is violated must be laid down under Section 12(10) of the Slum Act.
47. There may be cases where the slum-dwellers do not ofer any
resistance and willingly consent to move into transit accommodation
provided by the owner/developer. Therefore, the conditions laid
down under Section 12(10) will come into play only when there is a
clearance order, but in case there is no clearance order, then under
Section 13(2), the SRA would be empowered to take action when
there is violation of any plan or when there is violation of any
condition relating to developing the project within time. The time-
limit can, some time, be provided in the letter of intent, in the
agreement or even in the regulations.
Whether the SRA has any other power to remove the developer
51. Even if we were to assume that the SRA did not enjoy this power
under Section 13(2) of the Slum Act, we are of the considered view
that since it was the SRA which issued this letter of intent, it
necessarily must have the power to cancel the same. The SRA can
also derive this power under clauses (c) and (d) of sub-section (3) of
Section 3-A of the Slum Act, which read as under:
Page No. 12 of 26
10 May 2024 ::: Uploaded on - 10/05/2024 ::: Downloaded on - 30/08/2025 20:51:12 :::
Neeta Sawant WP(L)-12949-2024-FC
“3-A. Slum Rehabilitation Authority for implementing
Slum Rehabilitation Scheme.—(1) Notwithstanding
anything contained in the foregoing provisions, the State
Government may, by notifcation in the Ofcial Gazette,
appoint an authority to be called the Slum Rehabilitation
Authority for such area or areas as may be specifed in the
notifcation; and diferent authorities may be appointed for
diferent areas.
***
(3) The powers, duties and functions of the Slum
Rehabilitation Authority shall be—
***
(c) to get the Slum Rehabilitation Scheme implemented;
(d) to do all such other acts and things as may be necessary
for achieving the objects of rehabilitation of slums.”
52. A bare reading of these provisions shows that in terms of clauses
(c) and (d) of sub-section (3) of Section 3-A of the Slum Act, the SRA
not only has the power, but it is duty-bound to get the slum
rehabilitation scheme implemented and to do all such other acts and
things as will be necessary for achieving the object of rehabilitation of
slums. In this case, the SRA was faced with a situation where the
slum-dwellers were sufering for more than 25 years and, therefore the
action taken by SRA to remove Susme for the unjustifed delay was
totally justifed.
53. A perusal of the various provisions of the Slum Act would show
that normally in a case falling under the Slum Act, it is the owner of
the land, whether it be the Government, a statutory authority or a
private person, who will be interested in the development work.
Normally, the occupiers will be encroachers of slum land. Therefore,
there will be a confict of interest between the occupiers and the
owner. The owner, in turn, will always engage a developer/builder to
carry out the development work. In case the owner gives a power of
attorney to the developer, as in the present case, the developer now
has two identities — (i) the power-of-attorney holder of the owner,
and (ii) the developer. As far as the present case is concerned, the
Society is made up of the members who are occupiers and this Society
has given power of attorney to the developer Susme. Therefore, the
developer Susme is actually having a dual role of owner and developer.
Both the letters of intent have been issued in favour of the Society,
Susme and the architects of Susme. Susme could not have carried out
the development work on the basis of its agreement with the Society.
Page No. 13 of 26
10 May 2024 ::: Uploaded on - 10/05/2024 ::: Downloaded on - 30/08/2025 20:51:12 :::
Neeta Sawant WP(L)-12949-2024-FC
It needed the permission of the SRA. Therefore, SRA can obviously
revoke such permission.
19) Thus, as held by the Apex Court in Susme Builders, for
efective implementation of SRS under Section 3A(3) of Slum Act, the
Competent Authority is vested with necessary jurisdiction to take such
steps as may be necessary in the facts of each case. Thus, the Competent
Authority can initiate suo-moto action for termination of developer under
Section 13(2) of the Slum Act. While Mr. Khandeparkar does not
dispute this position, he would submit that in the present case, the power
is not exercised suo-moto and is triggered by an application fled by
unauthorized persons. That CEO/SRA never thought it necessary on its
own to initiate suo-moto action and the action initiated on the basis of
unauthorised application cannot be subsequently justifed on the basis of
permissibility to initiate suo-moto action. I am unable to agree with the
submissions of Mr. Khandeparkar. As observed above, all that is needed
for exercise of jurisdiction under Section 13(2) is recording of
‘satisfaction’ by CEO/SRA about existence of eventualities enumerated
under the provision. Considering the objective behind conferring the
power under Section 13(2), coupled with vesting of power to take ‘all
necessary steps’ for efective implementation of SRS under Section
3A(3), I am of the view that order passed by CEO/SRA after recording
his ‘satisfaction’ cannot be rendered invalid only on account of the fact
that the initial trigger for the action was by person(s) not authorised to
maintain an application under Section 13(2). I am therefore not inclined
to interfere in the impugned order of the CEO/SRA on this count.
Page No. 14 of 26
10 May 2024 ::: Uploaded on - 10/05/2024 ::: Downloaded on - 30/08/2025 20:51:12 :::
Neeta Sawant WP(L)-12949-2024-FC
20) Coming to the merits of the decisions of CEO/SRA and of
AGRC, Petitioner claims that its proposal for implementation of subject
SRS is accepted in respect of larger portion of land admeasuring
6,295.30 sq. mtrs comprising of 432 odd slum structures. In para-8 of the
petition, Petitioner has given following sub-division of the entire land on
which it believes it has right to implement the slum scheme:
8. The Competent Authority, being the MHADA on 21
st
December
2005 and MCGM on 16
th
March 2005, the land owners had forwarded
the Annexure II (list of eligible slum dwellers who would be entitled
for a permanent tenement under the re-development) in respect of the
very slum.
Sr.
Nos.
Date of
Issuance
Land
Owned by
Total Slum
Structure
EligibleNon-
Eligible
116
th
March
2005
MCGM 210 138 72
2 21
st
December
2005
MHADA 120 66 54
3 2022 Draft
Annexure II
issued by
MHADA
97
21) There is a debate amongst the parties about the exact land
and the exact number of slum structures in respect of which, the slum
scheme has been sanctioned. The above three portions of land are
indicated by Petitioner on ‘superimposed plan’ annexed at Exhibit-F to the
petition which is as under:
Page No. 15 of 26
10 May 2024 ::: Uploaded on - 10/05/2024 ::: Downloaded on - 30/08/2025 20:51:12 :::
Neeta Sawant WP(L)-12949-2024-FC
22)According to the Petitioner, while the scheme is ready to be
implemented in the frst and second portion of the land on account of
certifcation of Annexure-II in respect of structures thereon in the year
2005, it is non-certifcation of Annexure-II by MHADA on the third
portion of land comprising of 97 structures (indicated in pink portion in
the map) , which is holding up further progress in the scheme. On the
contrary, it is Mr. Balsara’s contention that Petitioner has nothing to do
with frst and third portions of land and the scheme allotted to it is
restricted only in respect of second portion of land comprising of 120
structures.
Page No. 16 of 26
10 May 2024 ::: Uploaded on - 10/05/2024 ::: Downloaded on - 30/08/2025 20:51:12 :::
Neeta Sawant WP(L)-12949-2024-FC
23) Petitioner’s claim of acceptance of proposal of all three
portions of land is premised on various documents such as the order
passed by CEO/SRA on 26 June 2018 terminating Hridaya’s
appointment and accepting its appointment, Note dated 14 October
2020 of District Superintendent of Land Records giving NOC in respect
of land admeasuring 6,295.33 sq.mtrs., refection of 433 slum structures
in report of Co-operative Department dated 17 January 2019, Resolution
adopted by Society on 25 March 2018 etc. I have minutely considered all
the documents on record and I must say that it is really unfortunate that
this Court is required to institute a microscopic enquiry to fnd out the
exact land in respect of which slum scheme has been handed over to the
Petitioner. Better clarity in this respect would have saved valuable
judicial time. However, since validity of orders passed by CEO/SRA and
AGRC hinge squarely on this debate, I am left with no other alternative
but to embark upon such enquiry.
24) It appears that Hridaya was allotted slum scheme in respect
of 432 slum structures which is clear from following observations made
by CEO/SRA in order dated 26 June 2018 :
Proposal for preparing Annexure-II was forwarded by MHADA
on 19/8/2005. Chief Ofcer, Mumbai Road, MHADA informed
SRA by its letter dated 21/12/2005 that 122 out of 432 slums
structures are on MHADA land and that therefore Annexure-II
will be issued for the same, whereas remaining slum structures
out of 432 are on MCGM land and therefore Annexure-II should
be obtained from MCGM for the same...”
Page No. 17 of 26
10 May 2024 ::: Uploaded on - 10/05/2024 ::: Downloaded on - 30/08/2025 20:51:12 :::
Neeta Sawant WP(L)-12949-2024-FC
25)It thus appears that Hridaya was apparently allotted slum scheme
in respect of much larger portion comprising of 432 slum structures
which could possibly cover all the three portions of land described above.
Hridaya’s appointment was terminated by CEO/SRA by order dated 26
June 2018, which also refers to General Body Meeting of Society held on
25 March 2018 resolving to cancel appointment of Hridaya and
proposing to appoint Petitioner as Developer. It appears that Hridaya
had given NOC for appointment of Petitioner as developer as Hridaya
was unable to process the subject SRS due to its personal reasons. CEO/
SRA terminated appointment of Hridya and granted liberty to Society to
implement the SRS through their new developer as per the provisions of
prevailing law, rules and regulations. Para-2 of the operative portion of
the order of CEO/SRA dated 26 June 2018 reads thus:
2. The slum dwellers society viz. Sarvodaya Residence SRA
CHS is at liberty to implement the SR Scheme. Further through
their new developer M/s. Lashkaria Housing & Infrastructure
Pvt. Ltd. as per the provisions of prevailing law, rules and
regulations.’
26) Though it is sought to be contended by Mr. Khandeparkar
and Mr. Singh that the entire scheme got transferred from Hridaya to
Petitioner by Order dated 26 June 2018, I am unable to accept the said
contention. The CEO/SRA merely granted liberty to the Society to
implement SRS through Petitioner ‘as per provisions of prevailing law,
rules and regulations’. The actions initiated after passing of order dated 26
June 2018 makes this position clearer. After termination of Hridaya’s
appointment by order dated 26 June 2018, one Anand Nagar Sarvoday
Page No. 18 of 26
10 May 2024 ::: Uploaded on - 10/05/2024 ::: Downloaded on - 30/08/2025 20:51:12 :::
Neeta Sawant WP(L)-12949-2024-FC
Residence SRA Co-operative Housing Society addressed letter dated
4 July 2018 to the Co-operative Department of SRA requesting
convening of General Body Meeting of the Society for appointment of
Developer. Accordingly, the Co-operative Department convened
meeting of General Body of the Society on 26 October 2018 by
nominating Assistant Registrar to oversee the same. Notices were
published in local newspapers for holding the meeting. Due to objection
raised by Respondent No.3-Society, the meeting convened at the
instance of Anand Nagar Sarvoday Residence SRA CHS was cancelled
and a fresh meeting was scheduled to be held on 31 October 2018 by
publishing notices in newspaper. In the meeting held on 31 October
2018, Subject No.1 was for appointment of developer, in which slum
dwellers were supposed to cast their votes in respect of two developers
viz. Petitioner and M/s. Sitara Realties Pvt. Ltd. The meeting was held
only in respect of 120 slum structures and only 66 slum dwellers who
were held eligible in Annexure-II certifed on 21 December 2005 were
permitted to vote. Thus, the meeting held on 31 October 2018 was only
in respect of 120 slum structures located on second portion of the land.
Out of the 66 eligible slum dwellers, 44 remained present for the meeting
and Petitioner secured 24 votes whereas M/s. Sitara Realtors received
20 votes. Accordingly, Petitioner was declared successful in the voting
process. The second subject was about appointment of Managing
Committee in which Mr. Ansari Salahuddin Akid was declared as Chief
Promoter of the society in addition to other promoters. Report of the
minutes of the Meeting was prepared by Co-operative Ofcer, SRA
Page No. 19 of 26
10 May 2024 ::: Uploaded on - 10/05/2024 ::: Downloaded on - 30/08/2025 20:51:12 :::
Neeta Sawant WP(L)-12949-2024-FC
which was approved by Joint Registrar, Secretary SRA and fnally by
CEO/SRA.
27) Appointment of the Petitioner for implementation of the
slum scheme is processed on the basis of the above report of the Co-
operative Department as approved by CEO/SRA. It is thus apparently
clear that though Hridaya’s appointment was in respect of larger portion
of slum scheme comprising 432 slum structures, after liberty was
granted to the Society for appointment of new developer, appointment
of Petitioner is made only in respect of second portion of land
comprising of 120 slum structures.
28) Though Mr. Khandeparkar and Mr. Singh have sought to
rely upon Resolution adopted in General Body Meeting held on 25
March 2018, in my view, the said Resolution is meaningless as fresh
process was required to be implemented for appointment of developer
after Hridaya’s appointment was terminated. Appreciating this position,
Respondent No.3-Society held meeting on 31 October 2018 and adopted
Resolution for appointment of Petitioner after conducting voting by
secret ballot between two developers. Interestingly, the Chief Promoter
and other promoters to whom Mr. Singh represents and who support the
Petitioner not just participated in that meeting but their election as Chief
Promoter and Co-promoters is an outcome of Resolutions adopted in the
said meeting. Having passed a Resolution for appointment of Developer
to implement slum scheme for only 120 slum structures, it is highly
objectionable on the part of clients of Mr. Singh to turn around and
Page No. 20 of 26
10 May 2024 ::: Uploaded on - 10/05/2024 ::: Downloaded on - 30/08/2025 20:51:12 :::
Neeta Sawant WP(L)-12949-2024-FC
contend that Petitioner is appointed for implementation of slum scheme
for 432 structures. The conduct of clients of Mr. Singh in taking a stand
contrary to the Resolutions adopted in the General Body Meeting held
on 31 October 2018 is deprecated. In fact, the entire confusion about the
land and the number of structures in respect of which Petitioner is
appointed got created on account of such irresponsible stand taken by
Petitioner and by clients of Mr. Singh leading to wastage of judicial time.
29) Petitioner’s reliance on File Note dated 14 October 2020 of
District Superintendent of Land Records-SRA does not cut any ice. True
it is that, the said authority has granted NOC from ownership point of
view for implementation of slum scheme in respect of land admeasuring
6,295.33 sq.mtrs. However, the said document does not and cannot be
read to mean as if acceptance of proposal of Petitioner by letter dated 13
July 2021 is in respect of the said portion of land or 432 slum structures.
When only 120 slum structures were considered for determining
majority for appointment of developer, the scheme cannot be for
rehabilitation of 432 slum structures. This is because the majority is
calculated only in respect of 66 eligible slum dwellers out of 120 slum
structures. If Petitioner contends that it is entitled to implement slum
scheme for 432 slum structures, its appointment would be rendered ab-
initio void. I am therefore of the view that Petitioner’s appointment is
only in respect of second portion of the land comprising 120 slum
structures.
Page No. 21 of 26
10 May 2024 ::: Uploaded on - 10/05/2024 ::: Downloaded on - 30/08/2025 20:51:12 :::
Neeta Sawant WP(L)-12949-2024-FC
30) Once the clarity is achieved about the exact number of slum
structures for which Petitioner is appointed to implement the scheme,
appreciation of reasons recorded by CEO/SRA and AGRC for
termination of Petitioner’s appointment becomes easy. It is an admitted
position that Petitioner wants to implement slum scheme in respect of all
three portions of land. However, record indicates that there is not just
stif opposition for execution of SRS in respect of frst and third portions
of land through Petitioner, but Petitioner has also not been able to secure
necessary clearances/approvals in respect of frst and third portions of
land. M/s. Sunil Constructions apparently claims rights in respect of
frst portion of land comprising of 210 structures and is opposing
implementation of SRS by Petitioners. It has fled Writ Petition (St.) No.
9361 of 2023 in this Court challenging letter dated 24 February 2023 by
which District Superintendent of Land Records has directed conduct of
survey of overlap area of SRS of M/s. Sunil Constructions and SRS of
Petitioner for verifcation of actual number of slum structures. It
appears that another society named Hindu Muslim Ekta CHS
(Proposed) is formed in respect of frst portion of the land. Thus, Sunil
Constructions not just claims rights in respect of frst portion of the land
but is clearly opposed to amalgamation of the two SRS.
31) Similarly in respect of slum structures located in the third
portion of the land, another society is formed which is opposed to
Petitioner implementing SRS in respect of 97 slum structures located
thereon. The record thus clearly indicates that far from Petitioner
securing consent as well as approvals for integration/amalgamation of
Page No. 22 of 26
10 May 2024 ::: Uploaded on - 10/05/2024 ::: Downloaded on - 30/08/2025 20:51:12 :::
Neeta Sawant WP(L)-12949-2024-FC
slum scheme relating to frst and third portions of land, he is facing stif
opposition from various quarters from persons/entities interested in
those schemes/slum structures.
32) Thus, instead of concentrating on implementing the slum
scheme of 120 slum structures in respect of which Petitioner is
appointed as developer, it appears to be more interested in expanding the
scope of its appointment by securing rights in respect of frst and third
portions of the land. Both CEO/SRA and AGRC have rightly
appreciated this position that Petitioner is more interested in
amalgamating the subject SRS with adjoining slum schemes without the
consent of the slum dwellers.
33) Petitioner’s appointment as developer is made in General
Body Meeting held on 31 October 2018. By now, period of about six long
years has elapsed. Even if period upto CEO’s order of 28 August 2023 is
considered time of fve long years had elapsed and Petitioner had not
even secured LOI for commencing construction at the site by clearing
the slums. One of the pretexts raised by Petitioner to explain delay was
COVID-19 pandemic. However, Petitioner’s appointment was made on
31 October 2018 much before the advent of COVID-19 pandemic.
Despite passage of fve/six years after its appointment, Petitioner has
made no progress in implementation of the subject SRS. Petitioner
appears to be more interested in securing rights in respect of adjoining
slums for higher proftability. Useful reference in this regard can be
made to the observation of Single judge of this Court (G. S. Kulkarni J.)
Page No. 23 of 26
10 May 2024 ::: Uploaded on - 10/05/2024 ::: Downloaded on - 30/08/2025 20:51:12 :::
Neeta Sawant WP(L)-12949-2024-FC
in Galaxy Enterprises Vs. State of Maharashtra
4
has held that delay
even prior to issuance of LOI can be taken into consideration for exercise
of power of termination of developer under Section 13(2) of Slum Act.
This Court has highlighted the efect of delay in implementation of slum
scheme by developers who sit over their proposals for years without
making any progress at the site. This Court has held:
56. On the above clear backdrop, I am not persuaded to accept any of
the submissions of Mr. Dhakephalkar learned Senior Counsel for the
petitioner. The contention that the LOI was ultimately granted on 30
May 2016, and hence there is no requirement to change the developer
as the delay stood condoned, cannot be accepted in the clear facts and
circumstances of the case. In fact, this is a clear admission on the part
of the petitioner that there was not only delay but it was inordinate. In
any case LOI sought to be obtained after about ten years of the
petitioner's appointment, would not in any manner condone the
conduct of the petitioner in delaying the scheme and the inherent lack
of diligence, rigour and earnestness which was expected. There is
another reason as to why this argument cannot be accepted, namely
that the society's application under Section 13(2) for change of
developer was prior in time, and the petitioner clearly appears to have
awakened from a deep slumber and started taking actions, with the
engineering department purporting to show of having achieved
another step, now of a LOI being obtained. These actions of the
petitioners as rightly held in both the impugned orders could not have
frustrated the society's application for change of the developer. Even
the payments which are stated to be made by the petitioner to the
SRA towards part of the land premium, would also not assist the
petitioner in the facts of the case. Such payments cannot create any
equity much less a legal right with the petitioner to continue with the
scheme in the facts as they stand. These amounts as partly being paid
are in any case being refunded to the petitioner.
57. There cannot be a myopic approach to these issues of a delay in
implementation of a slum rehabilitation scheme. Things as they stand
are required to be seen in their entirity. The only mantra for the slum
schemes to be implemented is it's time bound completion and a
machinery to be evolved by the authorities, to have efective measures
in that direction to monitor the schemes as a part of their statutory
4
(2019) 5 SCC 43
Page No. 24 of 26
10 May 2024 ::: Uploaded on - 10/05/2024 ::: Downloaded on - 30/08/2025 20:51:12 :::
Neeta Sawant WP(L)-12949-2024-FC
obligation to avoid delays. Non-commencement of the slum scheme
for long years and substantial delay in completion of the slum schemes
should be a thing of the past. In the present case, looked from any
angle there is no plausible explanation forthcoming for the delay of so
many years at the hands of the petitioner to take bare minimum steps
to commence construction.
58. The authorities should weed away and reprimand persons who are
not genuine developers and who are merely agents and dealers in slum
schemes. These persons after get themselves appointed as developers,
to ultimately deal/sell the slum schemes, as if it is a commodity. Any
loopholes in the rules to this efect, therefore, are required to be
sealed.
60. In any case, the developer cannot be said to possess a vested right
which would mandate the SRA to continue it's appointment for such
delay and when the body appointing the said developer namely the
society itself, in the given set of facts, bonafde and for an acceptable
reasons, lacks confdence in the petitioner as appointed by it. Between
the slum society and the developer, it is merely a contractual dispute.
It cannot be said that the society in adverse circumstances would have
no authority in a resolution so passed by the majority to remove a
developer. The role of the S.R.A. under law is to further the interest
of the slum scheme by exercise of it's powers in the best interest of the
slum redevelopment and pass such appropriate orders to achieve the
said object, in exercising it's powers inter alia under Section 13(2) of
the Slums Act.
34) I have therefore no hesitation in my mind in holding that
Petitioner has deliberately delayed implementation of subject SRS in its
quest to secure additional rights in respect of adjoining slums lands.
Petitioner’s appointment as developer has rightly been terminated by
CEO/SRA. AGRC has rightly rejected Petitioner’s application. I fnd the
orders of the CEO/SRA and AGRC to be unexceptional.
35)The Writ Petition must fail. As observed above apart from
conduct of Petitioner in not making any progress in implementation of
slum scheme for 5/6 years, its conduct in representing before this Court
Page No. 25 of 26
10 May 2024 ::: Uploaded on - 10/05/2024 ::: Downloaded on - 30/08/2025 20:51:12 :::
Neeta Sawant WP(L)-12949-2024-FC
that it has been allotted slum scheme for rehabilitation of all three
portions of land comprising 432 structures has been found to be
fallacious after undertaking an inquiry by this Court. This resulted in
wastage of substantial and valuable judicial time. Therefore, dismissal of
the Petition cannot be without consequences. Writ Petition is
accordingly dismissed with costs of Rs. 5,00,000/- to be paid to the Tata
Memorial Hospital within 8 weeks by producing receipt thereof before
the Prothonotary and Senior Master of this Court.
36)With the dismissal of the petition, nothing survives in the Interim
Application (L) No. 15499/2024 and the same also accordingly stands
disposed of.
SANDEEP V. MARNE, J.
37)After the judgment is pronounced, Mr. Khandeparkar would pray
for continuation of interim order passed in the petition. The prayer is
opposed by Mr. Balsara, the learned counsel appearing for Respondent
No.3. Considering the reasons recorded in the judgment, I am not
inclined to continue the interim relief. The prayer for continuation of the
interim order is accordingly rejected.
SANDEEP V. MARNE, J.
Page No. 26 of 26
10 May 2024 ::: Uploaded on - 10/05/2024 ::: Downloaded on - 30/08/2025 20:51:12 :::
Legal Notes
Add a Note....