As per case facts, M/s Punahchakran Private Limited's initial environmental clearances (EC) and consents (CTE) for a Bio-medical Waste Treatment Facility (CBWTF) were invalidated by the National Green Tribunal (NGT) ...
2026 INSC 956 REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO. 7367 OF 2024
M/S PUNAHCHAKRAN PRIVATE LIMITED …APPELLANT(S)
VERSUS
INDOTECH WASTE SOLUTION & ORS …RESPONDENT(S)
J U D G M E N T
Civil Appeal No. 7367 of 2024 Page 1 of 78
J.B. PARDIWALA, J.:
For the convenience of exposition, this judgment is divided into the
following parts:-
INDEX
I. FACTUAL MATRIX .................................................................................. 2
II. SUBMISSIONS OF THE PARTIES ...................................................... 17
A. Submissions on behalf of the Appellant ...................................... 17
B. Submissions on behalf of the Respondent No. 1 ........................ 19
III. ISSUES FOR CONSIDERATION ......................................................... 22
IV. ANALYSIS ................................................................................................ 23
A. Mandatory nature of the RG, 2016 and the decision of this Court
in Gulf Goans ..................................................................................... 23
i. The genesis, scope and nature of the RG, 2016 ............................... 26
ii. The requirement of authentication under Article 77 of the
Constitution .................................................................................... 31
iii. Whether the non-publication of the RG, 2016 in the Official Gazette
could be said to affect its mandatory nature ................................... 33
B. Permissibility of the grant of relaxation in land requirement 41
C. The status of land acquisition required from a project
proponent seeking to establish a CBWTF at the time of making
the Form 1 application, at the stage of appraisal of the EC and at
the time of applying for a CTE respectively ................................ 46
i. Clause 6 of the EIA, 2006 read with the O.M. dated 07.10.2014 46
ii. Clause 2 of the RG, 2016................................................................. 50
Civil Appeal No. 7367 of 2024 Page 2 of 78
iii. Applying for a CTE under the Water Act and Air Act respectively.
. ............................................................................................................................. 53
D. The grant of the second EC on the basis of the first ToR .......... 60
i. Whether the decision in Aniruda Panwar could be said to have set-
aside the first ToR ........................................................................... 60
ii. Validity period of the ToR ............................................................... 69
V. CONCLUSION ......................................................................................... 74
1. This appeal arises from the judgment and order dated 05.07.2024
passed by the National Green Tribunal, Principal Bench, New Delhi
(hereinafter, the “Tribunal”) in Appeal No. 04 of 2024 (hereinafter,
the “impugned decision”), whereby the Tribunal set-aside the
Environmental Clearance (“EC”) dated 20.12.2023 and Consent to
Establish (“CTE”) dated 20.12.2023 respectively granted in favour of
the appellant herein in connection with the establishment of a
Common Bio-medical Waste Treatment Facility (“CBWTF”).
I. FACTUAL MATRIX
2. The Environmental Impact Assessment Notification dated 14.09.2006
(“EIA, 2006”) issued by the Ministry of Environment, Forest and
Climate Change, Government of India (“MoEF&CC”) makes
provisions requiring prior EC in respect of certain
projects/activities/industries. Initially, a CBWTF did not fall within
its ambit. However, vide notification dated 17.04.2015, the expression
“bio-medical waste treatment facility” was inserted to the Schedule
Civil Appeal No. 7367 of 2024 Page 3 of 78
of the EIA, 2006, thereby adding it to the list of projects/activities
requiring a prior EC.
3. M/s Punahchakran Private Limited (hereinafter, the “appellant”)
submitted two applications dated 06.07.2021 to the Uttar Pradesh
State Industrial Development Authority (“UPSIDA”) for the
allotment of plot nos. E-25 and E-26 admeasuring 0.45 acres and 0.44
acres respectively, situated at the UPSIDC Industrial Area, Babrala,
District Sambhal, Uttar Pradesh, for the purpose of establishing a
CBWTF.
4. Before the said land could be allotted to the appellant, on 11.08.2021,
it submitted an application in Form 1 before the Uttar Pradesh State
Impact Assessment Authority (“UP SEIAA”) for the issue of Terms
of Reference (“ToR”) to commence the Environmental Impact
Assessment (“EIA”) study.
5. On 12.08.2021, the UPSIDA rejected the allotment applications made
by the appellant. In the immediate aftermath of this rejection, the
appellant submitted yet another application before the UPSIDA
seeking allotment of the same plots but for a different purpose i.e.,
for the establishment of an industrial unit for “fabrication of industrial
equipment”.
6. On 17.08.2021, the UP SEIAA issued a standard ToR (hereinafter, the
“first ToR”) to the appellant, thereby commencing the process for an
EIA study.
Civil Appeal No. 7367 of 2024 Page 4 of 78
7. On 15.09.2021, the appellant’s land allotment application for
establishing an industrial equipment fabrication unit was allowed by
the UPSIDA.
8. Thereafter, the appellant approached the Uttar Pradesh Pollution
Control Board (hereinafter, the “UPPCB”) and submitted an
application dated 27.09.2021 seeking the grant of a Consent to
Establish (“CTE”) for the CBWTF under the provisions of the Water
(Prevention and Control of Pollution) Act, 1974 (“Water Act”) and
the Air (Prevention and Control of Pollution) Act, 1981 (“Air Act”)
respectively. Plots E-25 and E-26 respectively of the UPSIDC
Industrial Area were indicated to be the land in which the CBWTF
was proposed to be set-up.
9. It is pertinent to note that as per the O.M. dated 27.04.2018 the
requirement of a public hearing under Paragraph
7(i)(III)Stage(3)(i)(b) of the EIA, 2006 was exempted since the site was
located in an industrial area. Therefore, on 18.02.2022, after obtaining
the EIA study report, the appellant submitted its proposal to the UP
SEIAA for grant of prior EC.
10. On 26.04.2022, the UPPCB had granted a conditional CTE
(hereinafter, the “first CTE”) to the appellant.
11. On 03.06.2022, in compliance with Clause 2 of the Revised Guidelines
for Common Bio-Medical Waste Treatment and Disposal Facilities,
2016, (hereinafter, the “RG, 2016”), a GAP Analysis Report was
Civil Appeal No. 7367 of 2024 Page 5 of 78
submitted to the UP SEAC by the Member, Secretary, UPPCB. This
report indicated the details of the bio-medical waste generated in the
eight nearby districts along with the proposed/operating CBWTFs in
the concerned areas as under:
S.
No
.
District Bedded,
HCF
Non-
Bedded
HCF
No
Beds
Covered Facility
1 Muradabad 481 707 6699 • Sushila Bio-
Medical
(Operated)
• Bhagwatsaran
(Proposed)
2 Sambhal 111 252 1034 • M/s
Punahchakran
Pvt. Ltd.
(Proposed)
3 Badayu 147 30 1988 -
4 Aligarh 474 387 9512 -
5 Hathras 148 207 1822 -
6 Etah 122 128 1319 -
7 Kasganj 81 102 1043 -
8 Bulandsheha 293 243 4482 -
Total Beds 1857 2056 27899
Amount of Bio-Medical
Waste in Kg
102.8
Kg
6974.75
Kg
Total – 7080.55
Kg
12. Upon a consideration of the GAP Report and taking into account all
the other details, the UP SEAC in its 663
rd meeting dated 16.06.2022
recommended the grant of EC to the appellant. Thereafter, on
05.07.2022, the UP SEIAA in its 625
th meeting expressed agreement
Civil Appeal No. 7367 of 2024 Page 6 of 78
with the recommendation of the UP SEAC. As a consequence, the EC
(hereinafter, the “first EC”) was issued to the appellant on 13.07.2022.
13. However, on 19.08.2022, the first CTE and first EC granted in favour
of the appellant by the UPPCB and UP SEIAA respectively were
challenged before the Tribunal in Original Application No. 622 of
2022 titled Aniruda Panwar and Anr. v. Ministry of Environment,
Forests and Climate Change and Ors.
14. After obtaining the first CTE and the first EC and after the institution
of the aforesaid O.A., the appellant approached the UPSIDA through
its online application dated 15.09.2022 requesting consent for a
change in the nature of use and category of industry being proposed
to be set-up in the allotted plots i.e., from “fabrication of industrial
equipment” to “CBWTF”. This change was allowed by the UPSIDA
vide letter dated 19.09.2022.
15. Indotech Waste Solution (hereinafter, the “respondent no. 1”)
situated in the District Kasganj is also engaged in the business of
treatment and disposal of bio-medical waste generated by health care
facilities. It had similarly made a Form 1 application sometime in the
year 2021 to establish a CBWTF. The UP SEAC and UP SEIAA
respectively are said to have also arrived at a decision to issue an EC
to the respondent no. 1 in their meetings dated 19.10.2022 and
14.11.2022 respectively i.e., after the first EC was already issued to the
appellant. However, it is admitted that a consequent order of EC was
not issued in favour of the respondent no. 1.
Civil Appeal No. 7367 of 2024 Page 7 of 78
16. The Tribunal vide its judgment dated 31.07.2023 in Aniruda Panwar
(supra) converted the O.A. No. 622 of 2022 in Appeal, allowed the
same and declared the first CTE and first EC respectively to be illegal,
null, void and of no effect for the following reasons:
i. First, Clause 2 of the RG, 2016 unequivocally establishes that
procurement of land for the purpose of establishing a CBWTF is
a condition precedent for filing an application seeking the grant
of EC and CTE respectively.
ii. Secondly, subsequent approval of change in land use granted by
the UPSIDA could neither legalise nor validate the first CTE and
first EC respectively.
iii. Lastly, Clause 7 of the RG, 2016 requires that the CBWTF be set-
up in a plot size of not less than one acre. As an exception,
relaxation of this land requirement may be granted after the
fulfilment of certain criteria and along with the imposition of
additional control measures. Considering that the appellant’s
plot size was 0.89 acres and that the UPPCB and UP SEIAA had
not specifically granted any such relaxation or, stipulated
additional control measures or, consulted with the CPCB to do
so, the first EC and first CTE respectively could not have been
validly issued.
17. Having held so, the Tribunal nevertheless granted liberty to the
appellant to re-apply for the grant of EC and CTE respectively, either
after procuring additional land or after seeking relaxation of the land
Civil Appeal No. 7367 of 2024 Page 8 of 78
requirement in accordance with law. The operative portion of the
Tribunal’s decision in Aniruda Panwar (supra) is reproduced thus:
“78. In view of the above, the application converted to appeal is
allowed and CTE and EC being violative of CBWTF Guidelines
2016 are held to be illegal, null and void and to be of no effect.
79. However, the Applicant shall be at liberty to apply again for
grant of EC and CTE for establishment of CBWTF after
procuring additional land in Babrala Industrial Area or seek
relaxation of land requirement in accordance with law and in
case any such application is filed by Respondent no. 7 again
UPPCB and UPSEIAA shall be bound to dispose of the same
strictly not only in accordance with the statutory provisions
/environmental norms but also CPCB Guidelines.”
(Emphasis supplied)
18. It is the case of the appellant that they made earnest efforts to pursue
both the alternatives suggested by the Tribunal in Aniruda Panwar
(supra), i.e., procure additional land and apply for relaxation in land
requirement respectively. It seems to have approached the UPSIDA
for procuring the adjacent plot no. E-27 and was waiting to
participate in the bidding process. Since the EC process is site-
specific, on 07.08.2023, it also submitted a fresh Form 1 application
for the issuance of a new ToR accounting for plot E-27 along with
plots E-25, and E-26 respectively. On, 10.08.2023, a new ToR
(hereinafter, the “second ToR”) inclusive of plot E-27 was also issued
by the UP SEIAA. Parallelly, the appellant approached the UPPCB
through its representation dated 08.08.2023 seeking relaxation in the
land area requirement in consultation with the CPCB.
Civil Appeal No. 7367 of 2024 Page 9 of 78
19. While the fate of the bidding process for plot no. E-27 is unknown, it
appears that land area relaxation was granted by the CPCB as per the
proposal made by the UPPCB, with accompanying control measures
on 17.11.2023 and the same reads thus:
“It is to inform that the criteria outlined under CPCB revised
guidelines for development of new CBWTF is required to be
followed to ensure effective compliance of BMWM Rules, 2016.
However as requested by UPPCB the area criteria may be
relaxed for the proposed plot from 1.0 Acre (4046 m
2) to 0.89
Acre (3601 m
2) by adopting the following additional measures.
a. UPPCB shall assess the increased stack height with
stringent emission norms and take other measures to ensure
that the operation of CBWTF shall have minimal impact on
human health & environment around the proposed site;
b. Effluent generated shall be treated up to the standards as
prescribed under the BMWM Rules, 2016 and shall be
utilized completely for vehicle floor washing, cooling tower
make up, gardening etc. CBWTF shall maintain zero liquid
discharge from the CBWTF
c. Adequate measures shall be taken for odour control by the
CBWTF
d. OCEMS should be installed and connected with CPCB and
UPPCB server for transmission of real time data for
prescribed parameters of incinerator.
e. Initially the Operating capacity of incinerator of CBWTF
may be restricted to 2.5 ton/day. UPPCB shall monitor the
CBWTF for six months and based on its performance
operational capacity may be increased accordingly with prior
information to CPCB.
Civil Appeal No. 7367 of 2024 Page 10 of 78
This is issued with the approval of Competent Authority,
CPCB”.
(Emphasis supplied)
20. After the UP SEIAA had revoked the appellant’s first EC in
accordance with the Tribunal’s judgment in Aniruda Panwar (supra),
on 17.10.2023, the appellant had submitted a fresh proposal to the UP
SEIAA for the grant of prior EC.
21. Vide its e-mail communication dated 17.11.2023, the respondent no. 1
addressed a complaint against the appellant to the UP SEAC
highlighting the following aspects: (i) that plot no. E-27 had not yet
been allotted to the appellant, (ii) that since plot nos. E-25 and E-26
respectively were originally allotted to the appellant for the
establishment of a ‘green category’ industry i.e., the fabrication of
industrial equipment, the process of allotment should not have been
revisited by the UPSIDA to entitle the appellant to establish a ‘red
category’ industry in the same plot, and (iii) that the GAP Analysis
for the entire State as mandated by the RG, 2016 had not been
conducted and therefore, the appellant’s case must not be considered
for the issuance of CTE.
22. Since relaxation was granted by the CPCB and it was no longer
necessary to procure plot E-27, vide letter dated 21.11.2023, the
appellant applied to withdraw the second ToR issued in its favour.
23. Despite the aforesaid allegations levelled by the respondent no. 1, on
20.11.2023, the UP SEAC in its 810
th meeting recommended the grant
Civil Appeal No. 7367 of 2024 Page 11 of 78
of EC to the appellant. It must be noted that it was the first ToR and
its consequent EIA study, not the second ToR, which was taken into
consideration during its decision-making process. The UP SEIAA
also concurred with the said decision and therefore, the EC dated
20.12.2023 (“hereinafter, the “second EC”) was granted.
24. Further, on the same date i.e., on 20.12.2023, the UPPCB also granted
the CTE (hereinafter, the “second CTE”) to the appellant.
25. Aggrieved, on 16.01.2024, the appellant preferred an Appeal bearing
Appeal No. 4 of 2024 under Sections 16(g) and (h) of the National
Green Tribunal Act, 2010 (“NGT Act”) before the Tribunal
challenging the second EC and the second CTE respectively.
26. In the meantime, on 19.02.2024, a Consent to Operate (“CTO”) was
also granted to the appellant by the UPPCB.
27. Vide the impugned decision dated 05.07.2024, the Tribunal decided
to set-aside the second EC and second CTE respectively for being
illegal and held as under:
i. First, that the RG, 2016 have been framed in exercise of statutory
power and are mandatory, enforceable and binding in nature.
ii. Secondly, Clause 7(b) of the RG, 2016 which allows a deviation
from the one acre plot size requirement is anchored on the
fulfilment of a crucial precondition i.e., the CBWTF must be
established within municipal limits with population of more
than 25 lakhs or be established in a rural area. Babrala does not
Civil Appeal No. 7367 of 2024 Page 12 of 78
fulfil either criteria and the authorities failed to look further into
this aspect. Therefore, the UP SEAC, UP SEIAA, UPPCB and the
CPCB respectively have acted in a very mechanical and
unmindful manner insofar as applying Clause 7(b) to the instant
project was concerned.
iii. Thirdly, that this Tribunal in Aniruda Panwar (supra) did not
strictly lay down that the appellant’s application for land
relaxation must be allowed. It was clear that the process shall be
undertaken in accordance with law and not in an illegal or
arbitrary manner. Hence, it cannot be suggested that there was
any direction in this regard made by the Tribunal in Aniruda
Panwar (supra).
iv. Lastly, that in granting such land relaxation, the UPPCB and
CPCB respectively have paid undue weight to irrelevant factors
like the investment made by the appellant and the GAP analysis
report. Moreover, the UPPCB had either deliberately or
unintentionally projected that the first EC and first CTE
respectively were only declared null and void and not illegal. No
heed was paid to the multivarious factors relevant to operational
effectiveness of the plant in a smaller area. Therefore, when
considerations which were either untrue or irrelevant had been
relied upon by the authorities, it undoubtedly showed that there
was no real application of mind and as a result, the entire
exercise of grant of land relaxation was vitiated on account of
malice in law.
Civil Appeal No. 7367 of 2024 Page 13 of 78
The relevant observations made by the Tribunal in the impugned
decision are reproduced thus:
“140. A perusal of para 7(a) shows that it requires setting up of
CBWTF preferably on a plot size of not less than one acre in all
the areas. However, CBWTF can be developed in adjacent plots
to cover up requirement of the area but cannot be set up in two
or more different plots located in different areas.
141. Para 7(b) contemplates a deviation from the requirement
of not less than one acre land and says that if there is a new
CBWTF to be established in a municipal limit with population
of more than 25 lakhs or rural areas, the land area requirement
may be relaxed but not in any case less than 0.5 acres by
SPCB/SPCC with additional control measures such as zero
liquid discharge, increase in stack height, stringent emission
norms, odour control measures or any other measures felt
necessary by the prescribed authority on case to case basis, only
in consultation with CPCB
142 One of the conditions for relaxation or deviation in the
requirement of not less than one acre of land is that the
municipal limit wherein a new CBWTF is proposed, should
have a population of more than 25 lakhs or CBWTF is proposed
to be established in a rural area. It is not disputed before us that
Babrala is a Nagar Panchayat. It is thus, not a rural area.
143. A Nagar Panchayat is an urban local body i.e.,
Municipality. […]
-xxx-
145. Article 243Q refers to three kinds of municipalities i.e., (a)
Nagar Panchayat (by whatever name called) for a transitional
area, that is to say, an area in transition from a rural area to an
urban area, (b) a Municipal Council for a smaller urban area;
and (c) a Municipal Corporation for a larger urban area.
Civil Appeal No. 7367 of 2024 Page 14 of 78
147 The population of Babrala Nagar Panchayat whether taking
as per 2011 census or as per any subsequent estimation is not
even one lakh, what to say of more than 25 lakhs. Para 7(b) of
RG 2016, therefore, was outrightly inapplicable for exercising
the power of relaxation in respect of the proposed CBWTF of
respondent 7 It is really surprising and very astonishing that
neither SEIAA UP nor CPCB have looked into this aspect of
the matter at all and acted in a very mechanical and unmindful
manner,
148. Suggestions has been made that since there was a direction
by this Tribunal in Aniruda Panwar vs. Ministry of
Environment, Forest and Climate Change & Others (supra)
that application for grant of EC may be considered by exercising
the power of relaxation in respect of requirement of area but
authorities have totally misled themselves by ignoring that
Tribunal clearly said that such consideration shall be in
accordance with law and not in an arbitrary and illegal manner.
149. We also notice that the then Member Secretary, UPPCB
by seeking clarification from CPCB regarding relaxation in land
requirement for CBWTF vide letter dated 16.10.2023 has only
stressed upon the fact that proponent has made investment of
132 lakhs which include cost of land, building, plant and
machinery; as per Gap Analysis, there was requirement of
CBWTF to be established and that respondent 7 was already
granted CTE and EC but due to gap in certain procedure and
formalities, earlier CTE and EC became null and void and not
illegal. This is clear misreading and appears to be a deliberate
attempt on the part of the then Member Secretary, UPPCB to
suggest that earlier CTE and EC was only null and void and
not illegal though judgment of Tribunal in Aniruda Panwar vs.
Ministry of Environment, Forest and Climate Change & Others
(supra) clearly declares that CTE and EC, not in conformity
with the RG 2016 in respect of requirement of area is null, void
and illegal and nullity for all purposes […]
-xxx-
Civil Appeal No. 7367 of 2024 Page 15 of 78
151. We further find that CPCB in its letter dated 17.11.2023,
instead of applying mind on this aspect directing SEIAA UP
to look into the question whether any relaxation is admissible or
permissible in accordance with provisions of RG 2016 in the
case in hand, has simply observed that the area criteria may be
relaxed from one acre to 0.89 acres by adopting certain measures
which relates to additional conditions necessary for prevention
of pollution of air. There is no reference to the question as to
whether the area where CBWTF is proposed qualify the
requirement of population for the purpose of attracting the
provisions of para 7(b) or not.
152 In the ultimate order granting relaxation, again the same
considerations, as are mentioned in the letter dated 16.10.2023,
have been reiterated which in our view, were irrelevant since it
is not investment made by respondent 7 which was relevant but
the operational effectiveness of the plant in a smaller area ought
to have been considered. There is no application of mind on this
aspect. There is no consideration whether sufficient space for
storage of BMW generated by health care facilities collected by
CBWTF for processing and also for storage of inert/residual
matter etc., and for other operational purposes was available.
-xxx-
154. We also do not find any hesitation in observing that the
officer concerned who has issued EC and CTE to respondent 7
after judgment of Tribunal in Aniruda Panwar vs. Ministry of
Environment, Forest and Climate Change & Others (supra) has
acted for reasons other than bonafide and clearly it is malicious
in law.There was/is no extraordinary urgency in proceeding to
grant the requisite clearance to respondent 7 instead of
considering the matter in the light of relevant provisions and by
application of mind to the relevant factors. The entire exercise
is clearly malicious in law. It is well settled that even if there is
no malice in fact but if there is something malicious m law, it is
vitiated in law.
-xxx-
Civil Appeal No. 7367 of 2024 Page 16 of 78
164. In brief the malice in law can be said when a power is
exercised for an unauthorized purpose or on a fact which is
claimed to exist but in fact, is non-est or for the purpose for
which it is not meant though apparently it is shown that the
same is being exercised for the purpose the power is supposed to
be exercised […]
-xxx-
166. In view of the above discussion, we have no hesitation but
to hold that EC and CTE granted in the case in hand, cannot be
sustained. They are contrary to law, illegal and are liable to be
set aside.
167 The Appeal is accordingly allowed. Impugned EC dated
20.12 2023 and CTE dated 20 12.2023 are hereby set aside.”
(Emphasis supplied)
28. In such circumstances referred to above, the appellant has preferred
the present appeal.
29. This Court vide its order dated 15.07.2024 directed that a report be
furnished by the District Magistrate, Sambhal regarding the location
of the CBWTF established by the appellant and the population of the
Babrala Nagar Panchayat. The relevant portions of the said order of
this Court is reproduced thus:
“4. According to the appellant, its CBWTF is situated in a rural
area. However, this is contested by the respondent who contends
that the Facility is not situated in a rural area, but is situated
within the limits of Babrala Nagar Panchayat with a population
much less than twenty-five lacs.
Civil Appeal No. 7367 of 2024 Page 17 of 78
5. We have heard Mr Shyam Divan, senior counsel appearing
for the appellant and Mr Pinaki Misra, senior counsel for the
respondent.
6. Certain documents have been produced by the appellants in
the course of the hearing, in interlocutory applications, but it
has been fairly accepted that these were not part of the record
before the NGT. In order to obviate any controversy on the
factual aspect so as to allow this Court to have a clear indication
in regard to the location of the Bio-medical Waste Treatment
Facility which has been conducted by the appellant, we are of
the view that a report should be called for from the District
Magistrate, Sambhal, Uttar Pradesh.
7. The CBWTF of the appellant is situated on plot No E-25/26,
UPSIDC Industrial Area, Babrala – 243751, District Sambhal.
The District Magistrate, Sambhal shall submit a report to this
Court on the following aspects:
(i). Whether the CBWTF of the appellant is situated within the
limits of Babrala Nagar Panchayat;
(ii). In the event, that the answer to (i) above is in the
affirmative, the population of the Babrala Nagar Panchayat; and
(iii). In the event, that the answer to (i) above is in the negative,
whether the CBWTF is situated in a rural area.
8 The report to be submitted by the District Magistrate shall be
based on the official records as available. The report shall be
submitted within a period of one week.”
(Emphasis supplied)
II. SUBMISSIONS OF THE PARTIES
A. Submissions on behalf of the Appellant
30. Mr. Shyam Divan, the learned Senior Counsel appearing on behalf of
the appellant canvassed the following submissions:
Civil Appeal No. 7367 of 2024 Page 18 of 78
i. The CBWTF plant established by the appellant is located in a
rural area, more specifically under Village Noorpur. The same is
brought forth by the report dated 24.07.2024 furnished by the
District Magistrate, Sambhal in compliance with the order of this
Court dated 15.07.2024 as also the letter dated 10.07.2024
addressed by the Revenue Inspector, Sambhal respectively. The
location of the appellant’s facility does not fall within the limits
of the Babrala Nagar Panchayat. In fact, the distance between the
plant and the border of the Babrala Nagar Panchayat is about 2.6
km.
ii. It must be further noted that the Governor of the State of Uttar
Pradesh, vide notification dated 05.09.2001, in exercise of the
power under Section 2(d) of the Uttar Pradesh Industrial Area
Development Act, 1976 (“UP Industrial Area Act”) notified the
Industrial Area, Babrala (at serial no.78 of the Gazette
Notification) wherein, it has been categorically mentioned that it
is situated in Village Noorpur.
iii. Therefore, the pre-condition under Clause 7(b) of the RG, 2016
as regards the relaxation of land requirement for a CBWTF
stands fulfilled and the grant of such relaxation with additional
control measures by the CPCB on 17.11.2023 cannot be faulted
with. As a result, the impugned decision setting aside the second
EC and second CTE respectively on this ground was completely
erroneous.
Civil Appeal No. 7367 of 2024 Page 19 of 78
iv. The first ToR granted to the appellant was never set-aside by the
Tribunal vide its decision in Aniruda Panwar (supra). Moreover,
the Office Memorandums (“O.M.”) dated 29.08.2017 and
08.06.2022 respectively issued by the MoEF&CC explicitly state
that the validity of a ToR is for a period of four years. Therefore,
there was no requirement for the appellant to obtain a fresh ToR.
v. The second ToR which was issued to the appellant on 10.08.2023
was subsequently withdrawn vide letter dated 21.11.2023.
Therefore, it can neither be said that the appellant provided any
false or misleading information to the authorities, nor can it be
said that the authorities were wrong in considering the first ToR
while issuing the second EC and second CTE respectively.
vi. The relevant authorities had duly applied their mind during the
process of granting the second EC and second CTE respectively,
and the same can be independently demonstrated by the
chronology of events placed on record. As such, it cannot be
stated that the decision(s) of the UP SEAC, UP SEIAA, UPPCB
and the CPCB respectively lacked application of mind or was
malicious in law.
B. Submissions on behalf of the Respondent No. 1
31. Mr. Pinaki Misra, the learned Senior Counsel appearing on behalf of
the respondent no. 1 canvassed the following submissions:
Civil Appeal No. 7367 of 2024 Page 20 of 78
i. The information furnished by the project proponent in Form
1/1A along with the proposed ToR form the basis and soul of
the grant of EC for any project. Providing missing or misleading
information in Form 1/1A significantly impedes the functioning
of the authorities and the conduct of the EIA study. It is for this
reason that Clause 8(vi) of the EIA, 2006 provides that “Deliberate
concealment and/or submission of false or misleading information or
data which is material to screening or scoping or appraisal or decision
on the application shall make the application liable for rejection, and
cancellation of prior environmental clearance granted on that basis.”
In the present case, both the first and the second ToR were
granted on deliberate concealment and/or the submission of
false/misleading data. Reliance was placed on the decision of
this Court in Hanuman Laxman Aroskar v. Union of India
reported in (2019) 15 SCC 401 to submit that such lapses must
vitiate the whole process and the appellant must recommence
from the Form 1 stage.
ii. The issue whether allocation or procurement of land is a
condition precedent for filing an application for grant of EC and
CTE respectively to a CBWTF was considered by the Tribunal in
Aniruda Panwar (supra) and was answered in the affirmative in
light of Clause 2 of the RG, 2016. In consonance with such a
finding, the decision in Aniruda Panwar (supra) held the first
ToR granted in favour of the appellant to be illegal and void.
Naturally, the second EC and second CTE respectively which
Civil Appeal No. 7367 of 2024 Page 21 of 78
were granted on the basis of the defunct first ToR cannot have
any validity under law. Therefore, the impugned decision
rightly set-aside the second set of permissions.
iii. Even the second ToR granted in favour of the appellant would
be hit by the decision of the Tribunal in Aniruda Panwar (supra)
since it mentions plot E-27 without the appellant having actually
procured the said plot from the UPSIDA.
iv. Moreover, the very issuance of the second ToR clearly evinces
that the first ToR could no longer be put to use.
v. The relaxation in land requirement granted by the CPCB cannot
be sustained for three reasons: First, the letter dated 16.10.2023
addressed by the Member Secretary, UPPCB to the CPCB had
observed that the first EC and first CTE granted to the appellant
were declared null and void ‘but not illegal’ by the Tribunal in
Aniruda Panwar (supra). This false premise contributed to the
decision granting relaxation and hence, such a decision is
vitiated by malice in law. Secondly, relaxation cannot be given as
a matter of right and must be reserved only for exceptional
circumstances. Such an exception must seldom be used
especially when the project in question is located in an industrial
area and the same was emphasized by the Tribunal in Aniruda
Panwar (supra). Lastly, the UPPCB and CPCB respectively were
preoccupied with irrelevant considerations like the investment
made by the appellant and ignored the crucial question as
Civil Appeal No. 7367 of 2024 Page 22 of 78
regards the operational effectiveness of the CBWTF in a smaller
area. Therefore, their decision suffers from due application of
mind.
vi. The decisions of this Court in Indian Railway Construction Co.
Ltd. v. Ajay Kumar reported in (2003) 4 SCC 579 and State of
NCT of Delhi v. Sanjeev reported in (2005) 5 SCC 181
respectively lay down the criteria for judicial review of
discretionary administrative action and the present case was a
fit one for interference by the Tribunal.
III. ISSUES FOR CONSIDERATION
32. Having heard the learned counsel for the parties and having gone
through the materials on record, the question which falls for our
consideration is whether the NGT vide the impugned judgment and
order dated 05.07.2024 was right in setting aside the second EC and
second CTE respectively granted to the appellant by the UP SEIAA
and UPPCB respectively.
33. In order to arrive at a finding on the aforesaid, the following legal
issues need to be dealt with:
i. Whether the RG, 2016 is mandatory or directory in nature?
ii. Whether the grant of relaxation in land requirement in favour
the appellant for the establishment of a CBWTF by the CPCB was
permissible?
Civil Appeal No. 7367 of 2024 Page 23 of 78
iii. On a combined reading of the EIA, 2006 and the RG, 2016
respectively, what is the status of land acquisition required for
establishing a CBWTF at the time of making a Form 1
application, at the stage of Appraisal of the EC and at the time of
making an application for the issuance of CTE respectively?
iv. Whether the UP SEAC and the UP SEIAA respectively could
have proceeded with the grant of the second EC on the basis of
the first ToR?
IV. ANALYSIS
A. Mandatory nature of the RG, 2016 and the decision of this
Court in Gulf Goans
34. Before we proceed to the other issues raised in this appeal, it is
imperative that we deal with the question pertaining to the
mandatory nature of the RG, 2016. This is especially because there
seems to be a repeated trend of submissions being made before the
Tribunal that in light of the decision of this Court in Gulf Goans
Hotels Company Limited and Another v. Union of India and Others
reported in (2014) 10 SCC 673, the guidelines may not have the ‘force
of law’. The impugned decision has held that the RG, 2016 is binding,
however, in doing so it has not made any specific reference to the
ratio in Gulf Goans (supra) or the line of argument referenced
hereinabove.
Civil Appeal No. 7367 of 2024 Page 24 of 78
35. Gulf Goans (supra) was concerned with a set of guidelines pertaining
to permissible construction activity in the coastal areas of Goa, more
specifically the distance that has to be maintained from the high tide
line. It is to be noted that these guidelines were issued before the
enactment of the Environment (Protection) Act, 1986 (“EP Act”)
which penalized environmental violations through statutory power.
In this background, it was held that such executive guidelines cannot
be enforced to the prejudice of an individual unless shown to have
acquired the force of law. To acquire such character, the guidelines
were required to satisfy certain minimum elements i.e., they must
inter alia have (i) a certain form possessed by other laws in force; (ii)
encapsulate a clear mandate or explicit command which may be
prescriptive, permissive or penal; (iii) disclose the achievement of a
specific and identifiable purpose; (iv) have some authentication and
(v) be notified or published either in the mode prescribed by the
statute or in the Official Gazette. It was added that the first element
itself i.e., the form, or the absence thereof will not be determinative.
However, the second and third elements i.e., a clear mandate and
purpose, were indispensable.
36. In effect, Gulf Goans (supra) held that the impugned
guidelines/notifications therein had not acquired the force of law for
several reasons including the lack of an expressed or clearly defined
dicta which supported that they were not mere suggestions or
expressions of opinion, the government failing to discharge the
burden that the guidelines were authenticated in accordance with
Civil Appeal No. 7367 of 2024 Page 25 of 78
Article 77 of the Constitution, and the failure to notify or publish
them in the Official Gazette. The relevant observations are
reproduced below:
“17. […]However, we are unable to find in the said guidelines
any expressed or clearly defined dicta. In fact, having read and
considered the guidelines, we are left with a reasonable doubt as
to whether what has been spelt out therein are not mere
suggestions or opinions expressed in the process of a continuing
exploration to identify the correct parameters that would
effectuate the purpose i.e. safeguarding and protecting the
environment (sea beaches) from human exploitation and
degradation.
19. Article 77 of the Constitution provides the form in which
the Executive must make and authenticate its orders and
decisions. Clause (1) of Article 77 provides that all executive
action of the Government must be expressed to be taken in the
name of the President. The celebrated author H.M. Seervai in
Constitutional Law of India, 4th Edn., Vol. 2, 1999 describes
the consequences of government orders or instructions not
being in accordance with clauses (1) or (2) of Article 77 by
opining that the same would deprive the orders of the immunity
conferred by the aforesaid clauses and they may be open to
challenge on the ground that they have not been made by or
under the authority of the President in which case the burden
would be on the Government to show that they were, in fact, so
made. In the present case, the said burden has not been
discharged in any manner whatsoever. […]
20. Clause (2) of Article 77 also provides for the authentication
of orders and instruments in a manner as may be prescribed by
the Rules. In this regard, vide S.O. No. 2297 dated 3-11-1958
published in the Gazette of India, the President has issued the
Authentication (Orders and Other Instruments) Rules, 1958.
The said Rules have been superseded subsequently in 2002.
Admittedly, the provisions of the said 1958 Rules had not been
Civil Appeal No. 7367 of 2024 Page 26 of 78
followed in the present case insofar as the promulgation of the
guidelines is concerned.
21. In the absence of due authentication and promulgation of
the guidelines, the contents thereof cannot be treated as an order
of the Government and would really represent an expression of
opinion.[…]
22. It is also essential that what is claimed to be a law must be
notified or made public in order to bind the citizen. […]
24. It will not be necessary to notice the long line of decisions
reiterating the aforesaid view. So far as the mode of publication
is concerned, it has been consistently held by this Court that
such mode must be as prescribed by the statute. In the event the
statute does not contain any prescription and even under the
subordinate legislation there is silence in the matter, the
legislation will take effect only when it is published through the
customarily recognised official channel, namely, the Official
Gazette (B.K. Srinivasan v. State of Karnataka) [(1987) 1 SCC
658] . Admittedly, the “guidelines” were not gazetted.
25. If the guidelines relied upon by the Union of India in the
present case fail to satisfy the essential and vital
parameters/requirements of law as the trend of the above
discussion would go to show, the same cannot be enforced to the
prejudice of the appellants as has been done in the present
case.[…]”
(Emphasis supplied)
i. The genesis, scope and nature of the RG, 2016
37. At this juncture, it would be appropriate for us to pause and look into
how the RG, 2016 came into existence. Section 8 of the EP Act
mandates that no person shall handle or cause to be handled any
Civil Appeal No. 7367 of 2024 Page 27 of 78
hazardous substance except in accordance with such procedure and
after complying with such safeguards as may be prescribed. Sections
6 and 25 of the EP Act respectively, grant powers to the Central
Government to make rules in respect of the aforesaid and requires
the publication of these rules in the Official Gazette. In exercise of the
powers conferred under the aforementioned provisions of the EP
Act, the Bio-Medical Waste Management Rules, 2016 (“BMWM
Rules”) came into existence through publication in the Official
Gazette.
38. The BMWM Rules, in turn, under several provisions, refer to certain
guidelines which are to be issued by the CPCB that would further
regulate the standards and procedures to be followed by operators of
CBWTFs i.e., the RG, 2016. As per Rule 3(c), the authorisation granted
by the prescribed authority must itself be in accordance with the RG,
2016. Rule 5 relating to the duties of a CBWTF operator also relies on
the RG, 2016 for prescribing detailed responsibilities. Rule 17, which
is of some relevance to the broad issue canvassed under the present
appeal, also states that site selection for setting up a CBWTF shall be
made in accordance with the RG, 2016. For better context, the
relevant provisions of the BMWM Rules are reproduced
hereinbelow:
“3. Definitions -
[…]
(c) "authorisation" means permission granted by the prescribed
authority for the generation, collection, reception, storage,
Civil Appeal No. 7367 of 2024 Page 28 of 78
transportation, treatment, processing, disposal or any other
form of handling of bio-medical waste in accordance with these
rules and guidelines issued by the Central Government or
Central Pollution Control Board as the case may be;
(d) "authorised person" means an occupier or operator
authorised by the prescribed authority to generate, collect,
receive, store, transport, treat, process, dispose or handle bio-
medical waste in accordance with these rules and the guidelines
issued by the Central Government or the Central Pollution
Control Board, as the case may be;
5. Duties of the operator of a common bio-medical waste
treatment and disposal facility.-It shall be the duty of every
operator to -
(a) take all necessary steps to ensure that the bio-medical waste
collected from the occupier is transported, handled, stored,
treated and disposed of, without any adverse effect to the human
health and the environment, in accordance with these rules and
guidelines issued by the Central Government or, as the case may
be, the central pollution control board from time to time;
14. Maintenance of records.- (1) Every authorised person
shall maintain records related to the generation, collection,
reception, storage, transportation, treatment, disposal or any
other form of handling of bio-medical waste, for a period of five
years, in accordance with these rules and guidelines issued by
the Central Government or the Central Pollution Control Board
or the prescribed authority as the case may be.
17. Site for common bio-medical waste treatment and
disposal facility.-(1) Without prejudice to rule 5 of these
rules, the department in the business allocation of land
assignment shall be responsible for providing suitable site for
setting up of common biomedical waste treatment and disposal
facility in the State Government or Union territory
Administration.
Civil Appeal No. 7367 of 2024 Page 29 of 78
(2) The selection of site for setting up of such facility shall be
made in consultation with the prescribed authority, other
stakeholders and in accordance with guidelines published by the
Ministry of Environment, Forest and Climate Change or
Central Pollution Control Board.”
(Emphasis supplied)
39. In addition to the above, Schedule III to the BMWM Rules which lists
out every prescribed authority and the corresponding duties
entrusted to them, require the CPCB to “prepare Guidelines on bio-
medical waste management” and “lay down criteria for establishing
common bio-medical waste treatment facilities in the country”, amongst
other things. Additionally, the Schedule also requires Municipalities
or Corporations, Urban Local Bodies and Gram Panchayats to
provide or allocate suitable land for development of common bio-
medical waste treatment facilities in their respective jurisdictions “as
per the guidelines of the Central Pollution Control Board”.
40. What can be gathered from all these different provisions under the
BMWM Rules is that the rules themselves require the RG, 2016 to be
made and scrupulously followed for its effective implementation.
This aspect could not have been conveyed with better clarity. In such
circumstances, there must arise no doubt as regards the mandatory
nature of the RG, 2016. To alleviate any residual uncertainty, the RG,
2016 itself in its introductory paragraph reads thus:
“Also, the Bio-medical Waste Management Rules, 2016
mandates that the operator of a CBWTF authorised by the
prescribed authority is required to take all necessary steps to
ensure that the bio-medical waste collected from the occupier is
Civil Appeal No. 7367 of 2024 Page 30 of 78
transported, handled, stored, treated and disposed of, without
any adverse effect to the human health and the environment, in
accordance with the BMWM Rules and the guidelines issued by
the Central Government or the Central Pollution Control
Board (CPCB) from time to time. Therefore, these guidelines
have been prepared with an aim to have uniformity in ensuring
site selection, allowing and establishment of a state-of-the-art
CBWTF, operation as well as verification of compliance to the
BMWM Rules, 2016 throughout the country. However, any
other aspects which are not been covered under these guidelines
and needs attention, in such a case, the prescribed authority
may take suitable action in the interest of protection of the
environment in consultation with MoEF & CC/CPCB. Also, it
is pertinent to mention here that these guidelines are mandatory
henceforth under the Bio-medical Waste Management Rules,
2016.”
(Emphasis supplied)
41. Moreover, observing alleged non-compliance to the BMWM Rules
and the RG, 2016 in the State of Uttar Pradesh by the UP SEIAA and
UP SEAC respectively in the process of grant of EC to CBWTFs, the
MoEF&CC thought fit to issue an OM dated 01.04.2022, the relevant
parts of which reads thus:
“2. The communications highlights that the SEIAA abd SEAC
of Uttar Pradesh is not taking into consideration the Biomedical
Waste Management Rules, 2016 and Revised CPCB Guideline
provisions while according Environmental Clearance for
CBWTFs.
3. In view of the above, it is requested to kindly examine the
matter as per provisions stipulated under Biomedical Waste
Management Rules, 2016 and respective CPCB Guidelines. It
is to emphasize here that the provisions contained in guidelines
may be strictly followed while giving clearance to new facilities
through Gap-Analysis. Further, CPCB may ensure the
Civil Appeal No. 7367 of 2024 Page 31 of 78
compliance through regular monitoring. An Action taken
Report may also kindly be provided to the Ministry.”
(Emphasis supplied)
42. Therefore, the intention behind bringing in the RG, 2016 and making
it a binding mandate on all the stakeholders is as clear as a noon day.
However, it seems as though the ratio in Gulf Goans (supra) is still
blindly being resorted to, as one final attempt, by project proponents
and surprisingly, State SEIAAs/SEACs alike, to avoid compliance
with RG, 2016. To thwart such devious attempts, we must take a
closer look at necessary elements laid down in Gulf Goans (supra)
and contextualise them with the RG, 2016. No doubt, the first three
i.e., a form, a clear mandate and an identifiable purpose, don’t
require much debate insofar as the RG, 2016 is concerned.
ii. The requirement of authentication under Article 77 of the Constitution
43. As regards the question of authentication under Article 77 of the
Constitution, this Court in Air India Cabin Crew Assn. v.
Yeshaswinee Merchant and Others reported in (2003) 6 SCC 277 held
that the object and effect of Article 77 is to insulate the executive
action of the government which is formally taken in the name of the
President from challenge on the ground that it is not an order or
instrument made or executed by the President. However, this cannot
be read to mean that all other executive action which is not formally
expressed to have been taken in the name of the President, ipso facto
becomes invalid. In other words, any alleged non-compliance with
Article 77 only precludes the drawing of an irrebuttable presumption
Civil Appeal No. 7367 of 2024 Page 32 of 78
that it is an order or instrument made in the name of the President
and by no stretch of imagination, invalidates the order itself. It can
always be established by evidence aliunde that the order was made
by the competent authority of the Central Government in the name
of the President [See also, Major E.G. Barsay v. State of Bombay
reported in 1961 SCC OnLine SC 30]. The relevant observations
made in Air India Cabin Crew Assn (supra)are thus:
“72. In our opinion, reference to Article 77 is wholly
inappropriate. The exercise of statutory power under Section 34
by the Central Government, even though not expressed to have
been taken in the name of President, does not render it invalid.
Clause (2) of Article 77 insulates an executive action of the
Government formally taken in the name of President from
challenge on the ground that it is not an order or instrument
made or executed by President. Even if an executive action of
the Central Government is not formally expressed to have been
taken in the name of President, Article 77 does not provide that
it would, therefore, be rendered void or invalid.[…]”
(Emphasis supplied)
44. Keeping in mind the clarification made by Air India Cabin Crew
Assn (supra), it would be even more absurd to assert that executive
guidelines issued in exercise of statutory power would be
automatically invalid if not authenticated. We say so because, it
cannot be disputed that the RG, 2016 has been, in fact, made by the
appropriate authority i.e., the CPCB, in pursuance of a clear mandate
outlined by the EP Act and the BMWM Rules respectively.
Furthermore, what is of particular note is that Gulf Goans (supra) was
Civil Appeal No. 7367 of 2024 Page 33 of 78
concerned with guidelines which did not have statutory backing. As
a matter of fact, Gulf Goans (supra) itself, while differentiating Air
India Cabin Crew Assn (supra) recognised that when executive
guidelines or directions are issued pursuant to a statute, it may not
be necessary that the burden of proof of authentication under Article
77 be discharged and observed thus:
“19. […] The decision in Air India Cabin Crew Assn. v.
Yeshaswinee Merchant [(2003) 6 SCC 277, p. 311, para 72 :
2003 SCC (L&S) 840] , taking a somewhat different view can,
perhaps, be explained by the fact that in the said case the
impugned directions contained in the government letter (not
expressed in the name of the President) was in exercise of the
statutory power under Section 34 of the Air Corporations Act,
1953. In the present case, the impugned guidelines have not
been issued under any existing statute.”
45. As a result, the only element that now requires some explanation is
that of publication, that too, whether it must be made in the Official
Gazette.
iii. Whether the non-publication of the RG, 2016 in the Official Gazette
could be said to affect its mandatory nature
46. While it would have been possible for us to differentiate Gulf Goans
(supra) from the present case by stating that the RG, 2016 came to be
issued in furtherance of several statutory provisions and thereby
dispense with the requirement of publication in the Official Gazette,
we are afraid that doing so may lead to an oversimplified and
fallacious misinterpretation that all statutory guidelines need not be
Civil Appeal No. 7367 of 2024 Page 34 of 78
published in the Official Gazette. The answer is, rather, slightly more
layered.
47. This Court in B.K. Srinivasan and Others v. State of Karnataka and
Others reported in (1987) 1 SCC 658 largely dealt with a similar issue
wherein the consequences of a failure to publish the Outline
Development Plan and the Regulations therein in the Official Gazette
was being ascertained to see if the violations committed by the
appellants deserved commensurate action. Holding that the non-
publication in the Official Gazette was not detrimental, this Court
observed that:
i. First, a law along with all the changes and/or additions made to
it by various processes, whether permanent or subordinate,
must be notified ‘directly and reliably’ to those from whom it
seeks compliance. To put it simply, that law must be so made
that it can be known.
ii. Secondly, the question whether non-publication of something in
the Official Gazette is fatal must be viewed from three
perspectives or angles: (a) the first angle wherein a specific mode
is prescribed for its publication by the parent statute. In such
cases, the said mode must be followed; (b) the second type
wherein there is a silence in the parent statute but the
subordinate legislation prescribes a mode for its publication. In
such cases, the prescribed mode may be sufficient, if reasonable.
(c) The third-type wherein both the parent and subordinate
legislation are silent, or where the subordinate legislation
Civil Appeal No. 7367 of 2024 Page 35 of 78
prescribes a plainly unreasonable mode. In such cases, effect can
be given only if it is published through the customarily
recognised official channel i.e., the Official Gazette or “some other
reasonable mode”.
The relevant observations are thus:
“15. There can be no doubt about the proposition that where a
law, whether parliamentary or subordinate, demands
compliance, those that are governed must be notified directly
and reliably of the law and all changes and additions made to it
by various processes. Whether law is viewed from the
standpoint of the “conscientious good man” seeking to abide by
the law or from the standpoint of Justice Holmes's
“unconscientious bad man” seeking to avoid the law, law must
be known, that is to say, it must be so made that it can be known.
[…] Where the parent statute prescribes the mode of publication
or promulgation that mode must be followed. Where the parent
statute is silent, but the subordinate legislation itself prescribes
the manner of publication, such a mode of publication may be
sufficient, if reasonable. If the subordinate legislation does not
prescribe the mode of publication or if the subordinate
legislation prescribes a plainly unreasonable mode of
publication, it will take effect only when it is published through
the customarily recognised official channel, namely, the Official
Gazette or some other reasonable mode of publication. There
may be subordinate legislation which is concerned with a few
individuals or is confined to small local areas. In such cases
publication or promulgation by other means may be sufficient
[Narayana Reddy v. State of A.P., (1969) 1 Andh WR 77]”
(Emphasis supplied)
48. In B.K. Srinivasan (supra), it was not the parent statute but the rules
which prescribed a mode by stating that “The Outline Development
Plan and the Regulations as approved by the State Government under sub-
section (4) of Section 13 shall be published in the Official Gazette”.
Civil Appeal No. 7367 of 2024 Page 36 of 78
Therefore, the factual circumstances fell under the second-type
aforementioned. Hence, in an attempt to discover whether the mode
prescribed by the rules was ‘reasonable’, this Court probed into what
was, in essence, required as a consequence of the publication and
attempted at a holistic reading of the entire scheme of the Act and
rules thereunder. In doing so, it was held that the plan and the
regulations themselves need not have been ‘bodily published’ or
reproduced in the Official Gazette. For better clarity, we deem it
necessary to reproduce the relevant observations:
“16. In the present case Section 13(4) has prescribed the mode
of publication of the Outline Development Plan and the
Regulations. It requires the Outline Development Plan and the
Regulations to be published in the prescribed manner and the
Plan and particulars to be permanently displayed in the offices
of the Director and the Planning Authority and a copy to be
kept available for the inspection of the public at the office of the
Planning Authority. The particulars referred to, we presume,
are the particulars mentioned in Section 12(2) of the Act
consisting of various reports, including the Regulations. “The
prescribed manner” is what is prescribed by Rule 33, that is,
publication in the Official Gazette. If we now turn to Section
9(1) and 9(2), we find that there too the Outline Development
Plan is required to be published in “the prescribed manner”. The
prescribed manner for the purposes of sub-sections (1) and (2)
of Section 9 is that prescribed by Rule 32. Rule 32 we have seen
prescribes making a copy of the Plan available for inspection,
publishing a notice in Form II in the Official Gazette and in one
or more newspapers and displaying a notice in Form II at the
office of Planning Authority and at other specified places. It is
true that Rule 33 speaks of publication of approved Outline
Development Plan and Regulations in the Official Gazette,
suggestive of a requirement that the Outline Development Plan
Civil Appeal No. 7367 of 2024 Page 37 of 78
and Regulations should bodily be incorporated in the Official
Gazette. But if the entire scheme of the Act and the rules is
considered as an integral whole it becomes obvious that what
Section 13(4) contemplates besides permanently displaying the
Plan and the particulars in the offices of Director and Planning
Authority and keeping available a copy for the inspection of the
public at the office of Planning Authority is a public notice to
the general public that the Plan and Regulations are
permanently displayed and are available for inspection by the
public. Such public notice is required to be given by a
publication in the Official Gazette. This is how it was
understood by the authorities and everyone else concerned and
this is how it was done in the present case. This appears to be a
reasonable and a rational interpretation on Section 13(4) and
Rule 33 in the setting and the scheme. We are of the view that
there was compliance with the requirements of Section 13(4)
and Rule 33. We have earlier mentioned that Section 13(1)
requires the provisional Outline Development Plan and
particulars to be published by notification in the Official
Gazette, with a view to invite comments from the public. What
was published in the present case under Section 13(1) was also
a notice in Form II and not the whole of the Plan and
particulars. Such publication evoked considerable public
response. As many as 600 representations from individuals and
institutions were received. That is why we said that everyone
concerned, that is, the Government, the Director, the Planning
Authority and the public, individual and institution alike,
thought that publication of a notice in the Gazette inviting the
attention of the public to the display and the availability for
inspection of the Plan and particulars was all that was
contemplated by the provisions providing for publication. We
do not think that there is any reason or justification for us to
adopt an interpretation which departs from common
understanding of the Act and the Rules.”
(Emphasis supplied)
Civil Appeal No. 7367 of 2024 Page 38 of 78
49. There was also an omnibus curative clause in the parent Act in B.K.
Srinivasan (supra) which protected a publication defect when
sufficient knowledge of the requirements in the plan and regulation
existed with the violating individual. While the presence of this
clause added another layer of reasoning, it did not materially affect
the conclusion already arrived at. What we are trying to convey is
that even when the publication of something in the Official Gazette
is required by the plain words of the subordinate legislation (rules),
there is some scope, albeit narrow, for the interpretation that its non-
publication in the Gazette was not detrimental to its legality or
binding nature based on an examination of whether the prescribed
mode was reasonable or not.
50. In the present litigation, we are concerned with a situation fitting
within the third type i.e., when there is silence both in the parent
statute and the rules as regards what mode of publication must be
followed. As a general rule, even in such scenarios, publication must
ideally be made in the Official Gazette. After all, it is the customarily
recognised official channel of the government. But, of course, the
natural corollary to any general rule is the possibility of it having one
or more exceptions. B.K. Srinivasan (supra) too referred to such
outliers when it clearly stated that “some other reasonable mode of
publication” may also be acceptable apart from publication in the
Official Gazette. It is tacit that to take benefit of this exception, the
court must be satisfied that such an alternate mode or manner of
publication was indeed reasonable.
Civil Appeal No. 7367 of 2024 Page 39 of 78
51. At this juncture, we must point out that Gulf Goans (supra) itself laid
down the requirement of publication in the Official Gazette as a pre-
requisite by placing reliance upon B.K. Srinivasan (supra). However,
in the larger background of the facts in Gulf Goans (supra), this Court
did not find it necessary to delve further into whether the mode of
publication undertaken was reasonable or not.
52. A handful of decisions of this Court have held that publication in the
Official Gazette is required. However, on a closer examination, all of
them can be differentiated. In Pankaj Jain Agencies v. Union of India
and others reported in (1994) 5 SCC 198, I.T.C. Bhadrachalam
Paperboards and Another v. Mandal Revenue Officer, A.P. and
Others reported in (1996) 6 SCC 634, Union of India and Others v.
Ganesh Das Bhojraj reported in (2000) 9 SCC 461 and Nabha Power
Limited and Another v. Punjab State Power Corporation and
Another reported in (2025) 5 SCC 353 respectively, the exemption
order/notification was required to be published in the Official
Gazette by the parent statute itself. Such was the case in Sammbhu
Nath Jha v. Kedar Prasad Sinha and Others reported (1972) 1 SCC
573 as well where the notification of appointment of the Commission
of Inquiry needed to be published in the Official Gazette by the
statute. In State of Kerala and Others v. P.J. Joseph reported in (1957)
3 SCC 638, the alleged statutory order varying an existing rule was,
again, required to be published in the Official Gazette under the
relevant provisions of the statute. The most recent decision in Viraj
Impex Pvt. Ltd. v. Union of India and Another reported in 2026 SCC
Civil Appeal No. 7367 of 2024 Page 40 of 78
OnLine 101 also related to an order which was expressly required to
be published in the Official Gazette by the statute and it was
observed that “The Legislature in its wisdom, has not left the mode of
promulgation to executive discretion”. All the aforesaid are instances
where this Court has given effect to a clear stipulation in the parent
Act which prescribed a set mode of publication or in other words,
cases which fell under the first type set out in B.K. Srinivasan (supra).
53. Harla v. State of Rajasthan reported in 1951 SCC OnLine SC 54 was
concerned with a situation wherein the Jaipur Opium Act, 1924 i.e.,
offence creating parent statute itself had not been promulgated and
published appropriately. Similarly, in Rajendra Agricultural
University v. Ashok Kumar Prasad and Others reported in (2010) 1
SCC 730, the issue was with regard to the non-publication of the
statute in the Official Gazette. In Ramakrishna Vivekananda Mission
v. State of W.B. and Others reported in (2005) 9 SCC 53, it was the
special rules i.e., a subordinate legislation, which was required to be
previously published according to the statute and in ascertaining the
import of the words ‘previously published’, recourse was taken to
the Bengal General Clauses Act, 1899 which mandated publication in
the Official Gazette. These set of decisions deal with the Act or the
Rules themselves not being published in the Official Gazette and
therefore, again, have little to do with the specific question we are
faced with.
Civil Appeal No. 7367 of 2024 Page 41 of 78
54. Now, turning to our facts; neither the EP Act nor the BMWM Rules
prescribe a strict mode of publication for the RG, 2016. Undeniably,
we would fall under the third-type of scenario as per the decision in
B.K. Srinivasan (supra). Therefore, publication in the Official Gazette,
although the general rule, cannot be said to be a sine qua non. We are
of the view that publication of such technical guidelines i.e. the RG,
2016, on the official website of the CPCB was reasonably sufficient.
Moreover, the RG, 2016 lays down crucial standards which form the
foundation for the grant of EC and CTE/CTO respectively to a
CBWTF. They are so deeply embedded in the authorisation
mechanism and all project proponents are sufficiently made aware of
its existence whilst commencing the process for obtaining different
clearances. Therefore, it cannot be argued that they do not constitute
enforceable standards for the grant as well as revocation of
permissions. Consequently, falling back on the ratio in Gulf Goans
(supra) would be of no help.
B. Permissibility of the grant of relaxation in land requirement
55. The RG, 2016 under Clause 7 provides for the “Land Requirement” of
a CBWTF and reads thus:
“7) Land requirement
Sufficient land shall be allocated to the CBWTF to provide all
requisite systems which include dedicated space for storage of
waste (both treated and untreated), waste treatment equipment,
vehicle washing bay, vehicle parking space, ETP, incineration
Civil Appeal No. 7367 of 2024 Page 42 of 78
ash storage provision, administrative room, space for DG Set
etc.,.
(a) Preferably, a CBWTF shall be set up on a plot size of not less
than one acre in all the areas. However, a CBWTF can be
developed in adjacent plots but cannot be set up in two or more
different plots located in different areas. Separate plots can be
permitted only for vehicle parking if located in the close vicinity
of the proposed CBWTFs or the existing CBWTFs.
(b) In case of upcoming or new CBWTFs (both in municipal
limits with population more than 25 lakhs or in rural areas),
the land area requirement may be relaxed (but in any case not
less than 0.5 acre) by the SPCB/PCC, with additional control
measures such as zero liquid discharge, increase in stack height,
stringent emission norms, odour control measures or any other
measures felt necessary by the prescribed authority on case-to-
case basis, only in consultation with CPCB.”
(Emphasis supplied)
56. Clause 7 begins with a short prelude explaining that sufficient land
shall be allocated to the CBWTF so that all requisite systems will have
adequate space. It goes on to state that a CBWTF shall preferably be
set up on a plot size of not less than one acre in all areas. The use of
the word “preferably” here must not be read to mean that the one acre
standard is not compulsory. Instead, the word is used to signify that
a single plot need not admeasure one acre and that multiple but
adjacent plots can be combined to fulfil this requirement. While
different plots which are separate cannot be used for the CBWTF as
a general rule, a deviation from this may be allowed if the separate
plot is in the close vicinity and is solely for the purpose of vehicle
parking. That the one-acre requirement is a strict rule is further
Civil Appeal No. 7367 of 2024 Page 43 of 78
substantiated by the fact that land area relaxation may be allowed in
certain cases i.e., for upcoming or new CBWTFs which are either in
municipal limits with a population of more than 25 lakh or in rural
areas. However, such relaxation cannot exceed 0.5 acre under any
circumstance. The State Pollution Control Board (“SPCB”) or the
Union Territory Pollution Control Committee (“PCC”) would be the
authority which would decide whether relaxation could be granted
or not. In all eligible cases, relaxation would be accompanied with
additional control measures including inter-alia zero liquid
discharge, increase in stack height, stringent emission norms, odour
control measures or any other measures considered necessary and
the matter shall be consulted with the CPCB.
57. It could, therefore, be said that the grant of relaxation has a pre-
condition and is also subject to certain mandatory accompanying
conditions. The pre-condition relates to the location of the proposed
site(s) i.e., it must be within municipal limits having more than 25
lakh population or within rural limits. The accompanying conditions
are that: (i) consultation with the CPCB is mandatory and, (ii)
additional control measures must be imposed.
58. It is this issue pertaining to Clause 7 of the RG, 2016 which weighed
heavily with the impugned decision and it reached the conclusion
that the pre-condition was not fulfilled in the instant case. There was
some confusion as regards whether the UPSIDC Industrial Area was
situated within Nagar Panchayat limits or rural limits, and if it was
Civil Appeal No. 7367 of 2024 Page 44 of 78
situated in the former whether the population of the Nagar
Panchayat was more than 25 lakh or not.
59. The impugned decision upon finding that the industrial area was
located within the Babrala Nagar Panchayat, proceeded to observe
that its population was not even one lakh as per the 2011 census.
Therefore, it was sure that Clause 7 was outrightly inapplicable and
the authorities including the CPCB and the UP SEIAA respectively,
had misdirected themselves in exercising their powers for the grant
of relaxation.
60. This Court vide order dated 15.07.2024 directed that a report be
furnished by the District Magistrate, Sambhal regarding the location
of the CBWTF established by the appellant and the population of the
Babrala Nagar Panchayat. We have been apprised that the UPSIDC
Industrial Area has been formed in village Noorpur, Pargana
Asadpur, Tehsil Gunnaur, District Sambhal. It is not situated within
the limits of the Babrala Nagar Panchayat but falls within the
Noorpur Gram Panchayat. In fact, the distance of the said industrial
area from the border of the Babrala Nagar Panchayat is about 2.6 km.
Several other authorities including the Executive Officer of the
Babrala Nagar Panchayat, the Tehsildar at Gunnaur and the Regional
Manager, UPSIDA, all confirm that the plots fall within rural limits.
61. Moreover, in exercise of the powers under Section 2(d) of the UP
Industrial Area Act, a Gazette notification was issued by the State of
Uttar Pradesh declaring the areas mentioned in the Schedule
Civil Appeal No. 7367 of 2024 Page 45 of 78
annexed thereto as Industrial Development Areas. Sl. No. 78 of the
Schedule pertains to the Industrial Area that we are concerned with
and it is declared to be located at Village Noorpur. Therefore, it
cannot be argued that plot nos. E-25 and E-26 respectively situated
within the limits of a rural area did not fulfil the precondition under
Clause 7(b) of the RG, 2016.
62. Aniruda Panwar (supra) emphasized that setting up a CBWTF on
land admeasuring one acre was the rule and relaxation of this land
requirement was the exception. Relaxation must not be granted as a
matter of right and in a casual manner. On this, we are in agreement.
However, in the present case, relaxation was granted after due
consultation with the CPCB and the prescription of additional
control measures which took into account the operational
effectiveness of the appellant’s plant in a smaller area. Therefore, the
fact that the investment already made by the appellant was also a
factor which was considered by the UPPCB and the CPCB
respectively, would not be sufficient to indicate that there was malice
in law. Similarly, while we agree that the representation made by the
UPPCB vide letter dated 16.10.2023 to the CPCB was wrong in stating
that the first EC and first CTE respectively were only null and void
and not illegal, this does not seem to have affected the actual grant of
relaxation by the CPCB in any manner. The mandate under Clause 7
of the RG, 2016 was strictly followed and the CPCB has not acted in
ignorance of the law. It is not the respondent no. 1’s case that the
Civil Appeal No. 7367 of 2024 Page 46 of 78
additional control measures which ultimately came to be imposed
were not sufficient or adequate in some way.
63. In view of the aforesaid, on the issue of relaxation in land
requirement, the second EC or the second CTE could not have been
quashed by the impugned decision.
C. Status of land acquisition required from a project proponent
seeking to establish a CBWTF at the time of making the Form
1 application, at the stage of appraisal of the EC and at the time
of applying for a CTE respectively.
64. The answer to this issue hinges on a careful reading of Clause 6 of the
EIA, 2006, Clause 2 of the RG, 2016, Section 25 of the Water Act and
Section 21 of the Air Act respectively along with some O.M.’s/orders
issued by the MoEF&CC.
i. Clause 6 of the EIA, 2006 read with the O.M. dated 07.10.2014
65. Clause 6 of the EIA, 2006 deals with the application to be made for
obtaining a prior EC. It reads thus:
“An application seeking prior environmental clearance in all
cases shall be made in the prescribed Form 1 annexed herewith
and Supplementary Form 1A, if applicable, as given in
Appendix II, after the identification of prospective site(s) for the
project and/or activities to which the application relates, before
commencing any construction activity, or preparation of land,
at the site by the applicant. The applicant shall furnish, along
with the application, a copy of the pre-feasibility project report
except that, in case of construction projects or activities (item 8
of the Schedule) in addition to Form 1 and the Supplementary
Civil Appeal No. 7367 of 2024 Page 47 of 78
Form 1A, a copy of the conceptual plan shall be provided,
instead of the pre-feasibility report.”
(Emphasis supplied)
66. Basically, it states that the application for prior EC must be made in
the prescribed Form 1/supplementary Form 1A after the identification
of prospective site(s) but before commencing any construction activity
or preparing the land. It also indicates that such identification must
be for the specific project or purpose for which the EC is sought and
this is brought forth by the expression “to which the application relates”.
Therefore, land which is identified as a prospective site for a different
purpose, cannot pass the muster of Clause 6 when the EC is being
sought for establishing some other project/facility.
67. The submission of Mr. Divan is that the words “identification of
prospective site(s)” clearly indicate that a successful allotment of land
for the purpose of establishing of a CBWTF in the appellant’s favour
was not necessitated by the EIA, 2016. He would state that it may be
sufficient if the project proponent has simply identified the land
concerned. In our opinion, while his submission would be right for
when the Form 1 application is made, the threshold would shift when
the EC process progresses to the appraisal stage i.e., Stage 4.
68. The O.M. dated 07.10.2014 issued by the MoEF&CC would shed
some further light. It states that an EC is always site-specific, meaning
that if the project comes to be set-up in a land different than that for
which EC was given, then such EC would automatically become
Civil Appeal No. 7367 of 2024 Page 48 of 78
invalid. The O.M. also adds that full acquisition of land may not be a
pre-requisite for considering an EC application. However, there must
be some credible document showing the status of land acquisition
with respect to the project site when the case is brought before the
concerned EAC/SEAC for appraisal. The relevant portions of the
said O.M. are reproduced thus:
2. The matter has been examined in the Ministry. The EC
granted for a project or activity under the EIA Notification
2006, as amended, is site specific. While full acquisition of land
may not be a pre-requisite for the consideration of the case for
EC, there should be some credible document to show the status
of land acquisition w.r.t. project site when the case is brought
before the concerned EAC/SEAC for appraisal. It has been
accordingly decided that the following documents relating to
acquisition of land w.r.t the project site may be considered as
adequate by EACs/SEACs at the time of appraisal of the case for
EC.
[…]
(ii) In case the land is being acquired through private
negotiations with the land owners, credible document showing
intent of the land owners to sell the land for the proposed project.
3. It may, however, be noted that the EC granted for a project
on the basis of aforesaid documents shall become invalid in case
the actual land for the project site turns out to be different from
the land considered at the time of appraisal of project and
mentioned in the EC.”
(Emphasis supplied)
69. If noticed closely, it states that some credible document showing the
intent of the land owners to sell the land for the proposed project
Civil Appeal No. 7367 of 2024 Page 49 of 78
would be sufficient at the appraisal stage. The stages involved in the
process of obtaining a prior EC are four: Screening, Scoping, Public
Consultation and Appraisal respectively. According to the O.M., the
need for such a credible document only arises at the fourth stage. So,
although the application in Form 1 can be made by a project
proponent before such a credible document is obtained, yet this
document must be available for scrutiny when the SEAC and SEIAA
respectively, ‘finally appraise’ the EC application.
70. This brings us to our first take-away i.e., land allotment for the
particular purpose/project is not necessary before the application
under Form 1 can be made, i.e., before the first stage of screening.
Identification is enough. Such a view is further substantiated by two
things: (i) when the EC is inherently site-specific there arises no
reason for placing such a high burden at the Form 1 stage itself, and
(ii) a reading of the prescribed Form 1 enclosed as Annexure-I to the
EIA, 2006, under the head ‘Basic Information’, requires the applicant
to provide details of the “Location/site alternatives under consideration”,
meaning thereby that the applicant is only to provide details of the
site(s) in which he intends to setup the project/activity concerned.
71. How can a Form 1 applicant then satisfy that it has identified
prospective site(s) or that some site is under consideration for the
purpose for which EC is sought? While we are not inclined to lay
down a general standard, we can say without doubt that, in the
present case, the applications dated 06.07.2021 made to the UPSIDA
Civil Appeal No. 7367 of 2024 Page 50 of 78
seeking allotment of plots E-25 and E-26 respectively, for establishing
a CBWTF, was sufficient to prove that the plots were identified or
were being considered by the appellant.
72. The second take-away is that, when the stage of appraisal arrives, a
credible document becomes crucial. What could be this credible
document in the context of the present matter? Undoubtedly, it
would either be a successful allotment in favour of the appellant or,
if the allotment is not in vogue, then a provisional allotment/
acknowledgment issued by the UPSIDA.
73. Clause 6 of the EIA, 2006 and the O.M. dated 07.10.2014 respectively
clarify that legal possession by way of a sale deed, lease deed etc.,
may not necessarily be obtained, both before making the Form 1
application and at the stage of appraisal, respectively.
74. Let us see if the RG, 2016 says anything different. The Tribunal in
Aniruda Panwar (supra) was of the opinion that it did.
ii. Clause 2 of the RG, 2016
75. Clause 2 of the RG, 2016 lays down the criteria for the development
of a new CBWTF. Amongst other things, it states thus:
“c) SPCB/PCC shall identify the coverage area, which require
additional treatment facility and bring it to the notice of the
concerned department in the business allocation of land
assignment in the respective State Government or UT
Administration. The department in the business allocation of
land assignment shall be responsible for providing suitable site
Civil Appeal No. 7367 of 2024 Page 51 of 78
in the identified coverage area for setting up of a CBWTF, in
consultation with the prescribed authority (i.e., SPCB/PCC),
other stakeholders and in accordance with these guidelines
issued by CPCB from time to time.
d) Alternately, a CBWTF may also be allowed to be established
on a land procured by an entrepreneur in accordance with the
location criteria suggested under these guidelines.
e) The SPCB/PCC or concerned department in the business
allocation of land assignment in the respective State
Government or UT Administration may seek expression of
interest from the proponents for development of new CBWTF
(s) in the identified coverage area. Upon allocation of site to the
proponent, the proponent is required to take necessary
approvals as required under the Environment (Protection)
Act, 1986 for development of the new CBWTF in accordance
with these guidelines.”
76. According to the above, in the normal course of things, it would be
the SPCB or the PCC which shall identify the requirement of new
CBWTFs in each coverage area. The department entrusted with the
business allocation of land assignment in the State/UT
administration would then provide suitable sites. Thereafter,
expressions of interest (“EoIs”) may be sought for the establishment
of a CBWTF. Upon allocation of the site to the successful project
proponent, it would be upon such proponent to obtain the necessary
approvals. Alternatively, an entrepreneur may also seek to establish
a CBWTF on land procured by himself in accordance with the
location criteria under the RG, 2016.
77. The use of the words “land procured” in the context of an entrepreneur
in Clause 2(d) and “upon allocation of site” in the context of the
Civil Appeal No. 7367 of 2024 Page 52 of 78
SPCB/PCC/administration’s initiative in Clause 2(e), is of particular
note. We are of the opinion that, fundamentally, these words do not
convey a message different from that of the EIA, 2006. In other words,
there is no conflict as such between the relevant provisions of the
EIA, 2006 and the RG, 2016 respectively as highlighted in Aniruda
Panwar (supra).
78. According to the RG, 2016, there are two ways through which the
process of establishing a CBWTF can be commenced: One, by the
SPCB/PCC/administration via Clauses 2(c) and 2(e) respectively,
and two, by the entrepreneur via Clause 2(d).
79. Clause 2(d) only states broadly that land must be procured by the
entrepreneur before establishing a CBWTF. It does not lay down
specifically that (i) allotment must be complete before the Form 1
application can be made under the EIA, 2006, or (ii) mere
identification is insufficient before the Form 1 application is made
under the EIA, 2006, or (iii) legal possession must be obtained prior
to the appraisal stage under the EIA, 2006.
80. Moving on, Clause 2(e) admittedly states that the project proponent
must proceed with obtaining approvals under the EP Act after the
site is allocated in its favour by the SPCB/PCC/administration. But
this aspect must be interpreted in the context of the entire process
that is envisaged under Clause 2 and not as laying down a rigid rule
that allocation is a pre-condition for seeking other approval(s). When
EoIs are sought from multiple persons for establishing a CBWTF, the
Civil Appeal No. 7367 of 2024 Page 53 of 78
RG, 2016 places a duty only upon the successful allocatee to
commence the necessary approval process, and not everyone who
responded to the EOIs. It is for this simple reason that the words
“upon allocation” is used. Moreover, what is plainly clarified is that
despite the land being allocated by the SPCB/PCC/administration,
such allocatees must independently obtain the necessary approvals
as per the EP Act and that this over-arching obligation cannot be
dispensed with. This intent behind the Clause 2(e) must not be
morphed or misconstrued as laying down a standard which requires
successful allotment before an application under Form 1 is made for
the EC.
81. We must not favour a hyper technical view of the words “land
procured” in Clause 2(d) and “upon allocation of site” in Clause 2(e) of
the RG, 2016 respectively, in a manner which is contrary to the
meaning evinced by the EIA, 2006. Clause 6 of the EIA, 2006 and the
O.M. dated 07.10.2014 communicate what is required from any
project proponent while making the Form 1 application and at the
appraisal stage, without any ambiguity. We do not see any reason,
either in law or by way of technical necessity, why a stricter condition
must be placed for a proponent seeking to establish CBWTF in
comparison to proponents undertaking other activities/projects.
iii. Applying for a CTE under the Water Act and Air Act respectively.
82. A project proponent seeking to set-up a CBWTF has to obtain
previous consent(s) from the SPCB/PCC by virtue of Section 25 of
Civil Appeal No. 7367 of 2024 Page 54 of 78
the Water Act and Section 21 of the Air Act respectively. These
previous consents are two in number i.e., the CTE and CTO
respectively.
83. Section 25 of the Water Act lays down restrictions on new outlets and
new discharges by stating that no person shall, without the previous
consent of the SPCB, establish or take any steps to establish any
industry, operation or process, or any treatment and disposal system
or any extension or addition thereto, which is likely to discharge
sewage or trade effluent into a stream or well or sewer or on land.
Section 26 covers those persons who were already operating an
industry, operation or process discharging any sewage or trade
effluent and brings them within the ambit of Section 25.
84. Section 21 of the Air Act states that no person shall establish or
operate any industrial plant in an air pollution control area unless the
previous consent of the SPCB has been obtained.
85. A cursory reading of the aforesaid provisions do not explicitly and
separately mention the CTE and CTO respectively. Nevertheless, a
two-stage regulatory process is followed by the CPCB/SPCB and
PCC. The two stages at which the consents are to be obtained signify
two distinct operational milestones vis-à-vis the project and require
separate applications as well as verifications. Broadly, a CTE is
required before the project/plant is built or set-up so that the layout,
location, proposed air pollution and water pollution control systems
etc., can be evaluated before the project takes further shape. A CTO,
Civil Appeal No. 7367 of 2024 Page 55 of 78
on the other hand, is required once construction is done and before
the commercial operations begin. Its object is to verify that the actual
infrastructure including the installed machinery, pollution control
mechanisms etc., abide by what was previously approved.
86. Therefore, as the CTE is concerned, what we can gauge is that the
project proponent must apply for it before establishing or taking steps
to establish or setting up such industry/operation. What actions
could potentially fall both within and outside the ambit of the
expressions “establish” or “take any steps to establish” or “setting up” is
difficult to conjure with certainty. But, undeniably, these expressions
are of wide import because they can include actions ranging from
finalising land, materials, infrastructure labour, obtaining parallel
approvals etc. Therefore, when both Sections 25 of the Water Act and
21 of the Air Act mandate that a CTE has to be obtained before
establishment or taking steps for such establishment, one cannot say,
that only the act of procurement of land must predate the application
for a CTE while the other acts which otherwise broadly constitute
‘establishment’ can be undertaken subsequent to the CTE being
applied for and/or obtained. There is no contrary indicia supporting
the view that land procurement or land allotment alone must occur
prior to the CTE application. We have already held that Clause 2 of
the RG, 2016 does not say otherwise. Meaning thereby that,
successful land allotment cannot strictly be a pre-condition to
obtaining a CTE.
Civil Appeal No. 7367 of 2024 Page 56 of 78
87. This can further be substantiated through the order dated 20.09.2021
issued by the MoEF&CC which reads thus:
“Whereas, prior Environmental Clearance is a statutory
requirement for project/activities covered in the schedule of the
EIA Notification 2006, issued under section 3 of the
Environment (Protection) Act, 1986.
2. And whereas, obtaining the consents under Water
(Prevention & Control of Pollution) Act, 1974 & Air
(Prevention& Control of Pollution) Act, 1981 is mandatory for
all industrial units in Red, Orange and Green categories.
3. And whereas, the grant of EC and Consents are requirements
under different statutes and are not inter-dependent and can be
carried out as a parallel process.
4. And whereas, many a times it has been observed that while
industrial units are in possession of valid 'Consent to Establish'
(CTE)/ 'Consent to Operate' (CTO) issued by State Pollution
Control Boards (SPCBs)/ UT Pollution Control Committees
(UTPCC), however, they have not obtained the Environmental
Clearance (EC), even though it was required as per provisions
of EIA Notification 2006.
5. And whereas, it has been observed that this situation is
arising because majority of the SPCBs/ UTPCCs are issuing
CTE/CTO to projects without ascertaining the applicability of
prior EC to projects/ activities, resulting in an avoidable
situation of closure for even those industries also who seek to
carry out their activities following due procedure.
6. Now therefore, in exercise of powers conferred by section 5 of
the Environment (Protection) Act, 1986(29 of 1986), the
Central Government, hereby directs that all SPCB/UTPCC
shall:
i. Ascertain the applicability of EIA Notification at the time
of grant/renewal of CTE and stipulate appropriate condition
for obtaining Environmental Clearance (EC), if applicable,
before construction/commencement of project/activity.
Civil Appeal No. 7367 of 2024 Page 57 of 78
ii. Ensure that the project proponent possesses a valid Prior
EC in terms of the extant EIA Notification, if applicable, at
the time of grant/renewal of CTO and no CTO shall be
granted or renewed unless EC, if applicable, has been
obtained
7. This is issued with the approval of the Competent Authority.”
(Emphasis supplied)
88. The aforesaid order was made to address those situations wherein
CTEs/CTOs were being issued to projects without ascertaining the
applicability of the EIA, 2006 owing to the fact that the EC and the
CTE/CTO process can be undertaken parallelly. As a direct
consequence, several projects did not apply for EC and were being
subjected to closure. Therefore, it was directed that the applicability
of the EIA, 2006 be ascertained by the SPCB at the time of grant of
CTE itself and that no CTO be granted unless prior EC was already
obtained.
89. When the order dated 20.09.2021 is read holistically with what we
have held in the previous sub-section i.e., that proof of land allotment
only needs to be furnished during appraisal of the EC, what becomes
clear is that although land allotment may be a precondition for
obtaining the CTO (because prior EC has to be mandatorily obtained
before the CTO), yet such a requirement may not restrict the making
of an application for CTE or even the grant of CTE for that matter.
90. In view of all the aforesaid, we are afraid that we are in disagreement
with the decision in Aniruda Panwar (supra) on the reasoning that,
owing to Clause 2 of the RG, 2016, a project proponent seeking to
Civil Appeal No. 7367 of 2024 Page 58 of 78
establish a CBWTF must have successfully procured or gotten land
allocated in his favour even before commencing the process of
obtaining prior EC and/or CTE.
91. Whilst we differ in the interpretation it afforded, we must
nevertheless clarify that the conclusion reached in Aniruda Panwar
(supra) cannot be assailed for being wrong. As discussed above,
identification of the prospective site(s) for the specific
project/activity is the threshold for when an application for EC is
made. Obtaining a credible document showing the status of land
acquisition is the pre-requisite for when the EC is being appraised by
the SEAC and SEIAA respectively. Prior to applying in Form 1, the
appellant had approached the UPSIDA vide application dated
06.07.2021 for land allotment to establish a CBWTF and had
therefore, identified prospective site(s) for the purpose for which the
EC was being sought. So, up until this point, there was no issue.
However, it failed to fulfil what was expected from it at the appraisal
stage. In other words, at the time when the UP SEAC and UP SEIAA
respectively, were appraising the appellant’s EC application for the
grant of the first EC, i.e., on 16.06.2022 and 05.07.2022 respectively,
the UPSIDA had rejected the appellant’s request for land allotment
for setting up a CBWTF. Thereafter, it only re-issued an allotment
letter in favour of the appellant for a different type of
industry/facility. Meaning thereby that, there was no credible
document indicating that a CBWTF could be established in the said
land when the UP SEAC and the UP SEIAA appraised the EC
Civil Appeal No. 7367 of 2024 Page 59 of 78
application. Only after the first EC was granted did the appellant
apply and obtain permission for change in land use. This could not
have retrospectively legalised the grant of the first EC.
92. As far as the first CTE is concerned, although it could not have been
faulted with for non-allotment of land prior to the date on which the
CTE was applied for i.e. prior to 27.09.2021, yet the UPPCB was under
an obligation to check whether the specifications of the land provided
by the appellant in its application for CTE fulfilled the land
requirements prescribed under Clause 7 of the RG, 2016. Since the
land identified by the appellant was of a size less than one acre, the
UPPCB must have directed the appellant to either identify additional
prospective plots or apply for a relaxation in land requirement before
granting the first CTE. Hence, for this reason, the first CTE was illegal
and void.
93. Now, we must look into whether the second EC or second CTE could
be said to have become vulnerable for any reason/ground discussed
hereinabove. Considering that the appellant was not required to
apply through a fresh Form 1 after the first EC and first CTE were
set-aside by Aniruda Panwar (supra) (an aspect which will be dealt
with in detail in the next sub-section), we only need to see whether
land acquisition requirements were met at the appraisal stage. When
the UP SEAC and UP SEIAA sat for appraisal on 20.11.2023 and
20.12.2023 respectively, the appellant obtained allotment of plots E-
25 and E-26 respectively for establishing a CBWTF from the UPSIDA
Civil Appeal No. 7367 of 2024 Page 60 of 78
on 19.09.2022, and relaxation in land requirement of 1 acre was also
allowed by the CPCB on 17.11.2023. The second CTE was also
granted by the UPPCB on 20.12.2023 after land relaxation was
already allowed by the CPCB. Therefore, the second EC and CTE
stood the test of the land acquisition requirements at each stage of the
process.
D. The grant of the second EC on the basis of the first ToR
94. Mr. Misra would argue that when the first EC and first CTE was set-
aside by Aniruda Panwar (supra) for the reasons stated therein, the
first ToR was also implicitly set-aside. Therefore, the second EC and
second CTE granted on the basis of such a defunct ToR cannot be said
to be valid under law. On the other hand, Mr. Divan would state that
the setting aside of the first EC and first CTE had no effect on the first
ToR. Moreover, the ToR was also valid for a period of four years.
i. Whether the decision in Aniruda Panwar could be said to have set-aside
the first ToR
95. It cannot always as a mechanical rule be said that when the EC is set-
aside, the ToR is also automatically rendered null and void for a
project proponent who is desirous of obtaining a fresh EC. The
answer depends on the grounds due to which the EC is vitiated and
what was found to be illegal or defective in the four stage EC process.
It also depends on how far back into the process the defect had crept
in. For example, if the illegality arose from the appraisal stage alone
i.e., due to non-application of mind by the SEAC/SEIAA, then there
Civil Appeal No. 7367 of 2024 Page 61 of 78
would be no use in relegating the project proponent back to the
absolute beginning. But, say, the illegality arose from an incomplete
or shoddy EIA report which did not abide by the prescribed ToR,
then the project proponent would have to prepare a fresh EIA report.
Here again, there wouldn’t be any need to disturb the ToR itself.
However, say, the ToR itself was improperly issued because
necessary details in the Form 1 application were false, incomplete or
misleading, then the whole process would have to be recommenced
afresh. As a matter of practice, the stage at which the process must be
restarted is indicated with sufficient clarity in the order setting aside
the EC. However, admittedly, the decision in Aniruda Panwar
(supra) is not intelligible on this aspect.
96. Mr. Misra would submit that, once the first EC was set-aside, the
entire process was required to be started afresh because the appellant
had falsely claimed that plots E-25 and E-26 respectively, had been
procured in their Form 1 application. According to him, this would
amount to deliberate concealment and/or submission of misleading
and false information material to the screening, scoping and
appraisal stages under Clause 8(vi) of the EIA,2006, which tainted the
whole process. He would also place reliance on the decision of this
Court in Hanuman Laxman Aroskar (supra) to substantiate this
argument.
97. In Hanuman Laxman Aroskar (supra), the EC granted for
development of the greenfield airport project in Goa was called into
Civil Appeal No. 7367 of 2024 Page 62 of 78
question for several flaws in the EIA process including the failure of
the project proponent to disclose the name and identity of forests
within an aerial distance of 15km of the project despite the fact that
the Form 1 mandatorily required a clear disclosure of “areas which are
important or sensitive for ecological reasons — wetlands, water sources or
other water bodies, coastal zone, biospheres, mountains and forests”.
Deprecating such practice, this Court observed that non-disclosure
of vital information and suppression of material facts in Form 1 has
a cascading effect on the entire EC process: (i) It would impair the
ability of the EAC/SEAC to recommend a rejection of the application
for EC at the threshold under Clause 7 II.Stage(2)–Scoping(iii), (ii)
affect the functioning of the EAC/SEAC in the preparation of the
ToR, (ii) lead to a deficient EIA report, and (iii) influence the
EAC/SEAC’s appraisal of the EC application, amongst others. Since
Form 1 is the base upon which the whole process rests, it was
cautioned that the depth and accuracy of information provided in
Form 1 must not be compromised and the project proponent must be
held to the highest duty of transparency and rectitude. If the project
proponent did not abide by the same, then an EC already granted
could also be cancelled on the basis of Clause 8(vi) of the EIA,2006.
The relevant observations are thus:
“61. Under the 2006 Notification, EC process is based on the
information provided by the applicant in Form 1. That the
information provided in Form 1 is crucial can be borne from the
following circumstances:
Civil Appeal No. 7367 of 2024 Page 63 of 78
61.1. EAC or SEAC, as the case may be, formulates
comprehensive ToRs on the basis of the information furnished
in Form 1 which addresses all possible environmental concerns.
It is on the basis of ToR, that further studies and the EIA are
carried out on the impact of the proposed project on the
environment.
61.2. At the appraisal stage, the regulatory authority examines
the documents submitted by the applicant “strictly with
reference to ToR” and communicates any inadequacy to EAC
or SEAC.
61.3. Category B2 projects, which do not require scoping, are
evaluated by SEAC on the basis of the information furnished by
the applicant in Form 1 alone.
61.4. The appraisal of all projects or activities which are not
required to undergo public consultation, or submit an EIA
report, shall be carried out on the basis of the prescribed
application Form 1 and Form 1-A as applicable.
61.5. An application for extension of the validity of EC for
certain projects is to be made by submitting a revised Form 1
within the validity period.
62. The information provided in Form 1 serves as a base upon
which the process stipulated under the 2006 Notification rests.
An applicant is required to provide all material information
stipulated in the form to enable the authorities to formulate
comprehensive ToR and enable persons concerned to provide
comments and representations at the public consultation stage.
The depth of information sought in Form 1 is to enable the
authorities to evaluate all possible impacts of the proposed
project and provide the applicant an opportunity to address
these concerns in the subsequent study. Missing or misleading
information in Form 1 significantly impedes the functioning of
the authorities and the process stipulated under the notification.
For this reason, any application made or EC granted on the basis
Civil Appeal No. 7367 of 2024 Page 64 of 78
of a defective Form 1 is liable to be rejected immediately. Clause
(vi) of Para 8 of the notification provides thus[…]
70.1. Form 1, which was filed by the project proponent, did not
contain any disclosure of the name or identity of forests within
an aerial distance of 15 km. Item 2 under the heading of
“Environmental Sensitivity” requires a clear disclosure of
“areas which are important or sensitive for ecological reasons
— wetlands, water sources or other water bodies, coastal zone,
biospheres, mountains and forests”.
72. […] The project proponent is bound by the highest duty of
transparency and rectitude in making the disclosures in Form
1.
73. There can be no manner of doubt that Form 1 is an
important ingredient in the entire process envisaged under the
2006 Notification. Hence, clause (vi) of Para 8 of the 2006
Notification provides that deliberate concealment or submission
of false or misleading information or data which is material to
screening or scoping or appraisal or decision on the application
shall make the application liable for rejection and lead to the
cancellation of a prior EC granted on that basis. The declaration
which is required of the project proponent is to a similar effect.
80. […] There is an intrinsic link between the disclosures in
Form 1 which constitute the basis for formulating ToR and
between the ambit of the EIA report required by ToR and the
final EIA report. ToR guide the preparation of the EIA report.
A failure to disclose information in Form 1 impairs the
functioning of EAC in the preparation of ToR and in
consequence, leads to preparation of a deficient EIA report.”
(Emphasis supplied)
98. Coming back to the facts of our case, our finding on the previous
issue has already made clear that procurement or allotment of land
was not a pre-requisite for making an application under Form 1.
Civil Appeal No. 7367 of 2024 Page 65 of 78
Therefore, there arises no question of deliberate concealment or non-
disclosure which vitiated the first ToR. The respondent no. 1 has not
pointed any other aspect which, in their opinion, was false or
defective in the Form 1 application made on 11.08.2021 and which
may have made the ToR itself invalid/void/insufficient in any
manner.
99. Rather, what the appellant was actually guilty of in terms of Clause
8(vi) of the EIA,2006 was concealing the fact that UPSIDA had
thereafter allotted the plot for a difference purpose i.e., for fabrication
of industrial equipment. But this was a material concealment in
connection with the appraisal stage of the EC process and had nothing
to do with Form 1. The same comes across very clearly on a bare
reading of the following observations in Aniruda Panwar (supra):
“68. […] In the absence of such evidence Respondent No 7 must
be held to have suppressed material facts from UPPCB and
UPSEIAA UPPCB and UPSEIAA must also be held to have
ignored material facts in this regard that as on 26.04.2022 when
CTE was granted by UPPCB and on 13.07.2022 when EC was
granted by UPSEIAA to Respondent No.7 for establishment of
CBWTF, establishment of CBWTF was not permissible in plots
No. E-25 and E-26 situated in Babrala Industrial Area which
had been allotted by Respondent no. 6 UPSIDA to Respondent
No 7 for setting up Industrial Fabrication Equipment
(ETP/STP/WTP/C).
69. Concealment of material information by Respondent No 7
and impermissibility of land use for establishment of CBWTF
at the time of grant of CTE and EC cannot be casually brushed
aside […]”
Civil Appeal No. 7367 of 2024 Page 66 of 78
100. It was observed that “concealment of material information…at the time of
grant of EC…cannot usually be brushed aside”. Therefore, while the
appellant’s actions were hit by Clause 8(vi) of the EIA, 2006 and
affected the appraisal of the EC, such concealment did not render the
first ToR invalid.
101. Moreover, a careful reading of Hanuman Laxman Aroskar (supra)
also reveals that due attention must be paid to the nature of the non-
disclosure or concealment in Form 1 as well. We say so because
Hanuman Laxman Aroskar (supra) linked the significance of an
accurate and complete Form 1 with its potential to enable the
EAC/SEAC to reject the application at the threshold and/or, affect the
preparation of the ToR and/or, affect the ambit of the EIA report
and/or, influence the appraisal of the application by the EAC/SEAC.
Therefore, the information which is withheld or concealed in Form 1
must be such that it will push the fresh EC process off course, into
error or astray, in some manner, small or big, unless the entire
exercise is started from scratch. In other words, there must be some
impact that such a false disclosure or non-disclosure in Form 1 would
cause to the entirety of the EC process in order to direct the applicant
to go back to the starting line. This is also precisely why Clause 8(vi)
of the EIA, 2006 uses the words “information or data which is material
to” the screening, scoping, appraisal or decision on the application,
in the context of rejecting any application or cancelling the EC
already granted. For ease of reference, Clause 8(vi) is reproduced
thus:
Civil Appeal No. 7367 of 2024 Page 67 of 78
“Deliberate concealment and/or submission of false or
misleading information or data which is material to screening
or scoping or appraisal or decision on the application shall make
the application liable for rejection, and cancellation of prior
environmental clearance granted on that basis. Rejection of an
application or cancellation of a prior environmental clearance
already granted, on such ground, shall be decided by the
regulatory authority, after giving a personal hearing to the
applicant, and following the principles of natural justice.”
(Emphasis supplied)
102. When such material information has either been concealed or
falsified, then both reason and logic demands that the same be
remedied in the fresh EC which may be re-issued. Materiality has
nothing to do with whether the lapse or error was minor or not. In
matters concerning the environment, nothing must be casually
deemed minor. However, all we wish to convey is that, before
relegating the applicant way back to Form 1, there must be some
benefit that accrues from remand to a specific stage. Some cogent
reason must exist. Hence, along with assessing whether there was
deliberate concealment and/or submission of false/misleading
information or data, the material nature of the data/information and
an assessment of which all stages could be said to have been affected
must also be looked into, especially for deciding where the applicant
has to resume from after its EC is set-aside. Whether the ToR could
have become null/void directly depends on the stage from which
this restart has to occur.
Civil Appeal No. 7367 of 2024 Page 68 of 78
103. Considering that the appellant had successfully obtained a relaxation
in the land requirement for a CBWTF from the CPCB instead of
further pursuing the procurement of additional land from UPSIDA,
it would be pointless to direct the appellant to re-apply through a
fresh Form 1 application and obtain a fresh standard ToR. In opting
to proceed with the land relaxation, even if demoted back to the Form
1 stage, the appellant would have to provide the exact same details
on the Form 1 application, the fresh standard ToR would be identical
and the fresh EIA report prepared in pursuance of it would also be
no different. Hence, when the EC is set-aside in such cases, the
applicant must not be required to mechanically restart the process,
particularly when going to the starting line virtually adds nothing to
the procedure and is purely redundant. We must be alive to the costs
and delay that would accompany such a pointless restart.
104. On the contrary, if the appellant had been unsuccessful on the
relaxation front and proceeded to procure plot E-27, then it would
have had to apply through a fresh Form 1 application and a new ToR
would have been indispensable. This is because, as we had indicated
above, the EC process is site-specific and if the project or even a part
of the project comes to be established on different land, then the EC
would be invalidated. It naturally follows that if plot E-27 was sought
to be included in the project site, then the first ToR which only
mentioned plots E-25 and E-26 respectively would have created a
mis-match. A fresh Form 1 application, followed by a fresh ToR and
a EIA report which accounted for the additional land, would have
Civil Appeal No. 7367 of 2024 Page 69 of 78
been necessary. Anticipating this precise problem, the appellant
rightly obtained a second ToR through a fresh Form 1 application
which included plot E-27. However, once plot E-27 was out of the
picture, the appellant applied to cancel the second ToR and
proceeded with the first ToR whose validity was not affected by the
decision in Aniruda Panwar (supra).
ii. Validity period of the ToR
105. Responding to the submission that the first ToR was rendered
invalid, Mr. Divan also submitted that the first ToR remained valid
for a period of four years from the date of its issuance. To substantiate
the same, he would rely on two O.M’s issued by the MoEF&CC dated
29.08.2017 and 08.06.2022 respectively, which read thus:
O.M dated 29.08.2017
“Subject: Terms of Reference for EIA/EMP studies for the
projects/activities requiring Environmental Clearance
under the ElA Notification, 2006 - Extension of validity
period - regarding.
In order to streamline the process and provide greater clarity in
issuing Terms of Reference (ToRs) for undertaking EIA/EMP
studies for the projects/activities requiring Environmental
Clearance under the EIA Notification, 2006, the following
decisions have been taken with immediate effect:
(i) The validity of ToRs for projects/activities (except for River
Valley and HEP Projects), for submission of EIA/EMP reports
shall be three years.
(ii) The validity of ToRs for River Valley and HEP Projects, for
submission of EIA/EMP report shall be four years.
Civil Appeal No. 7367 of 2024 Page 70 of 78
(iii) The above validity period can be extended by the concerned
Regulatory Authority for a maximum period of one year
without referring the proposal to the EAC/SEAC concerned,
provided an application is made by the applicant before expiry
of the validity period, together with an updated Form-1 and
proper justification and there is no change in terms and
conditions of the ToRs. After the lapse of validity, such
extension will need EAC/SEAC consideration.
(iv) Thus, an outer limit of validity of ToRs shall be 4 years for
all the projects/activities and 5 years for River Valley and HEP
Projects.
(v) The ToRs will specifically mention the date of expiry of
validity.
(vi) Extension of validity of ToRs beyond the outer limit of four
years for all projects/activities, and five years for River Valley
and HEP projects, shall not be allowed/considered by the
Regulatory Authority.
[…]
(ix) In case the proposal for Environmental Clearance along
with EIA/EMP reports based on the ToRs prescribed, is not
submitted within the validity period of ToRs, and/or not
complying with the above conditions, the process shall be started
de novo. The already collected baseline data may be re-used,
provided it is not more than 3 years old and duly recommended
by EAC/SEAC in their due diligence.
(x) In case, any proposal for ToR is delisted for want of
additional information within the time period, as stipulated by
the Ministry, the same can be listed again after the requisite
information is submitted.”
(Emphasis supplied)
O.M. dated 08.06.2022
“Subject: Standardizing the validity of baseline data and
public consultation reports for submission of proposal
within the validity period of Terms of Reference (ToR)
Civil Appeal No. 7367 of 2024 Page 71 of 78
under the provisions of EIA Notification, 2006 –
regarding.
As per the provisions of EIA Notification, 2006, Terms of
References (ToR) are being accorded to the various
developmental projects listed in the schedule to the EIA
Notification, 2006 except schedule 8(a) for undertaking
EIA/EMP study. In this regard, Ministry issued Office
Memorandum No. J-11013/41/2006-IA-II (I) (Part) dated 29th
August 2017 stating that the validity period of ToR as three
years for all the projects/activities and four years for River
Valley and HEP Projects. This validity period could be further
extended by a maximum period of one year, thereby making the
outer limit for validity of ToR as four years for all
projects/activities and five years for River Valley and HEP
projects.
[…]
6. The aforesaid matter has been examined in the Ministry. In
order to address this issue in a practical manner and to bring
uniformity in handling such proposals, the following standard
procedures shall be followed with immediate effect:
[…]
(v). In case the proposal for EC along with EIA/EMP reports
based on the ToRs prescribed is not submitted within the
validity period of ToRs, and/or not complying with the above-
mentioned criteria, the concerned Member Secretary shall not
accept the proposal and process shall be initiated de novo by the
PP.”
(Emphasis supplied)
106. The aforesaid spell out that the validity of a ToR issued for a CBWTF
would be 3+1 years. In the event the project proponent does not place
its proposal for EC along with the EIA report and other necessary
particulars, if any, before the SEIAA within the validity period of the
prescribed ToR, only then the process would have to be started de
Civil Appeal No. 7367 of 2024 Page 72 of 78
novo. Here, de novo would mean right from the making of a Form 1
application for issuance of a fresh ToR.
107. The rationale behind tethering the ToR to a set time-limit was
elucidated upon in the decision of this Court in Bengaluru
Development Authority v. Sudhakar Hegde and Others reported in
(2020) 15 SCC 63. It was stated that every ToR relies upon
information furnished in the Form 1 application which, in turn,
comprises of data on an “as is” basis. However, the environment is in
a constant state of flux and therefore, after a point, the data forming
the basis of the ToR would become outdated and the EIA study
would pale into insignificance. For this reason, the MoEF&CC did
not want to indefinitely continue the validity of a ToR. It was to
account for such environmental dynamism that an outer limit was
laid down. The relevant observations are thus:
“48. Significantly, the process of obtaining an EC commences
from the production of the information stipulated in Form
1/Form 1-A. Information submitted in Form 1 relies on data
and information on an “as is” basis at the relevant time of
submitting information. Material information regarding the
particulars of the proposed project as well as the potential
impact on the environment is sought to enable the EAC or the
SEAC to prepare a comprehensive TOR on which basis the
applicant proceeds to prepare the EIA report.[…]
49. MoEFCC stated that it was clearly undesirable to
indefinitely continue a TOR. The environment is, by its very
nature, dynamic. Soil quality, air characteristics and
surrounding flora and fauna are among the characteristics of
the environment which are constantly in a state of flux. A
Civil Appeal No. 7367 of 2024 Page 73 of 78
robust framework of environmental governance accounts for the
dynamic nature of the environment. It is for this reason that
project proponents are also required to ensure the submission of
an Environmental Management Plan and compliance with the
monitoring procedures envisaged under the 2006 Notification.
An indefinite TOR defeats the very purpose which underlies the
2006 Notification for it may lead to situations where the state of
the environment has changed drastically, yet the EIA process is
carried out on the basis of outdated information.[…]”.
(Emphasis supplied)
108. In light of all the aforesaid, the first ToR could not be said to have
been invalidated when the first EC was set-aside by Aniruda Panwar
(supra), especially when it remained unimpacted by the reasons due
to which the first EC was quashed. It would be irrational for a ToR to
be allowed the full extent of its validity period solely when the EC
process is ongoing i.e., when the project proponent is yet to complete
the EIA study or the public consultation or submit his EC proposal
before the SEIAA. It is not the case of the respondent no. 1 that the
baseline data was outdated or faulty. Therefore, viewed from all
angles, the first ToR was still valid and the second EC could have
been granted on the basis of the first ToR.
109. It also cannot be said that the very factum of issuance of the second
ToR indicated that the first ToR could no longer be put to use. We
have explained why the second ToR may have been necessary if an
additional plot was sought to be acquired by the appellant. Based on
subsequent factual developments, the appellant ensured that the
same was duly withdrawn on 21.11.2023.
Civil Appeal No. 7367 of 2024 Page 74 of 78
V. CONCLUSION
110. A conspectus of the aforesaid discussion is as follows:
i. The RG, 2016 is mandatory in nature. It must be scrupulously
followed by the relevant authorities and the project proponents
alike during the process of obtaining/grant of permissions for
the establishment of a CBWTF. Its non-publication in the Official
Gazette could not be said to have affected its mandatory nature.
The decision of this Court in B.K. Srinivasan (supra) had clarified
that when a strict mode of publication has not been prescribed,
either by the parent statute or the subordinate legislation, a
reasonable mode of publication may be sufficient. Neither the EP
Act nor the BMWM Rules prescribe a strict mode of publication
for the RG, 2016. Therefore, publication in the Official Gazette,
although the general rule, cannot be said to be a sine qua non. The
publication of such technical guidelines on the official website of
the CPCB was reasonably sufficient.
ii. Moreover, the RG, 2016 lays down crucial standards which form
the foundation for the grant of EC and CTE/CTO respectively to
a CBWTF and are so deeply embedded in the existing
authorisation mechanism. All project proponents are sufficiently
made aware of its existence whilst commencing the process for
obtaining different clearances. Therefore, it cannot be argued
that they do not constitute enforceable standards for the grant as
Civil Appeal No. 7367 of 2024 Page 75 of 78
well as revocation of permissions. Any reliance on the ratio in
Gulf Goans (supra) would, therefore, be misplaced.
iii. As per Clause 7 of the RG, 2016, the land requirement of one acre
prescribed for setting up a CBWTF may be relaxed upon the
fulfilment of one of the two pre-conditions i.e., the land must be
situated either within municipal limits with a population of
more than 25 lakh or within a rural area. Additionally,
consultation with the CPCB and the imposition of additional
control measures is mandatory. The appellant’s CBWTF is
located within Village Noorpur and is therefore, in a rural area.
Relaxation was granted only after due consultation with the
CPCB and the imposition of additional control measures which
took into account the operational effectiveness of the CBWTF in
a smaller area. Therefore, the grant of relaxation cannot be
faulted.
iv. Clause 6 of the EIA, 2006 states that an application in Form 1 can
be made after the identification of prospective site(s). Therefore, land
allotment cannot be said to be a pre-condition for the making of
an application under Form 1.
v. The O.M. dated 07.10.2014 issued by the MoEF&CC clarifies
that, at the stage of appraisal of the EC i.e., at Stage IV, some
credible document showing the intent of the land owner(s) to
sell the land for the proposed project must be obtained in case
the land is being acquired through private negotiations. In the
Civil Appeal No. 7367 of 2024 Page 76 of 78
context of the present case, such a credible document would
either be a successful allotment in favour of the appellant for the
establishment of a CBWTF or, if the allotment is not in vogue,
then a provisional allotment/acknowledgment issued by the
UPSIDA for the establishment of a CBWTF.
vi. A perusal of the order dated 20.09.2021 issued by the MoEF&CC
as well as Section 25 of the Water Act and Section 21 of the Air
Act respectively, indicate that (a) the applicability of the EIA,
2006 and the necessity of obtaining prior EC must simply be
ascertained/identified by the SPCB/PCC at the time of grant of
CTE and, (b) prior EC must be obtained before a CTO can be
granted by the SPCB/PCC. Therefore, when the chronology is
rightly understood, a CTE can be issued before the issuance of a
prior EC upon a mere assessment of the applicability of the EIA,
2006. In that case, when the identification of prospective site(s) is the
land acquisition requirement for making a Form 1 application
under the EIA, 2006, then successful land allotment for the
CBWTF cannot be made a condition precedent, both for the
making of an application for CTE and the grant of CTE
respectively. Having said so, relaxation in land requirement, if
any, in accordance with Clause 7 of the RG, 2016 must be granted
by the SPCB/PCC in consultation with the CPCB before they can
issue a CTE for land admeasuring less than one acre.
Civil Appeal No. 7367 of 2024 Page 77 of 78
vii. Clause 2 of the RG, 2016 does not make land procurement or
land allocation a strict pre-requisite for initiating the process of
obtaining both the EC and CTE respectively.
viii. The second EC and second CTE were both granted in favour of
the appellant on 20.12.2023 after land was allotted to it by the
UPSIDA on 19.09.2022 and after relaxation was granted by the
CPCB on 17.11.2023. Therefore, as far as the fulfilment of land
acquisition conditions are concerned, the second EC and second
CTE was not vitiated.
ix. The setting aside of the first EC by the decision of the Tribunal
in Aniruda Panwar (supra) did not have the consequence of
rendering the first ToR invalid. There was no deliberate
concealment or non-disclosure of material information which
affected the Form 1 application or the issuance of the first ToR.
Therefore, the first ToR was intact. Considering that the first ToR
was also valid for a period of four years, the grant of the second
EC on the basis of the first ToR could not be said to be wrong.
111. In view of all the aforesaid, we have reached the conclusion that the
NGT committed an egregious error in passing the impugned
judgment quashing the second EC and second CTE respectively.
112. As a result, this appeal succeeds and is hereby, allowed. The
impugned judgment and order passed by the NGT, Principal Bench,
is hereby set-aside.
Civil Appeal No. 7367 of 2024 Page 78 of 78
113. Pending applications, if any, shall also stand disposed of.
114. Registry shall forward one copy of this judgment to the National Green
Tribunal, Principal Bench, New Delhi and the Principal Bench
thereafter shall circulate the judgment to all the circuit benches of the
Tribunal
… ................................. J.
(J.B. PARDIWALA)
New Delhi.
7
th September, 2026.
… ................................. J.
(MANOJ MISRA)
Legal Notes
Add a Note....