As per case facts, the Petitioner and Respondent had an agreement for a foot over bridge project. Despite extensions, the work was not completed, leading to a termination notice issued ...
Arb.OP(Com.Div).No.630 of 2022
IN THE HIGH COURT OF JUDICATURE AT MADRAS
RESERVED ON : 10.02.2026
PRONOUNCED ON : 13.02.2026
CORAM
THE HONOURABLE MR.JUSTICE N.ANAND VENKATESH
Arb.OP(Com.Div).No.630 of 2022
M/s. Sivashankar & Co
Rep.by its Proprietor D.Sivashankar
Having Office at 303, EBONY Apartment
110/2, River View Link Road
IAS/IPS Colony, Manapakkam
Chennai-600125.
..Petitioner
Vs.
The Divisional Railway Manager
Chennai Division ,Southern Railway
Chennai. ..Respondent
Prayer: Arbitration Original Petition filed under Section 34(2) of the
Arbitration and Conciliation Act, 1996, to set aside the award of the
Arbitral Tribunal dated 27.3.2022 and received on 17.05.2022 and to
direct the respondents to pay the costs.
For Petitioner : Mr.J.Srinivasa Mohan
for M/s.TVJ Associates
For Respondents : Mr.K.S.Jayaganesan
Senior Counsel
1/22 https://www.mhc.tn.gov.in/judis
Arb.OP(Com.Div).No.630 of 2022
O R D E R
This Arbitration Original Petition has been filed challenging the
award dated 27.3.2022 passed by the Arbitral Tribunal under Section
34(1) of the Arbitration and Conciliation Act, 1996, [hereinafter referred
to as 'the Act'] .
2.The petitioner and the respondent entered into an agreement
dated 27.3.2017 for work relating to provision of new foot over bridge at
Chennai, Egmore. This was for platforms 2 to 11. The Letter of
Acceptance was issued on 7.11.2016 and the duration of work was fixed
as 12 months. However, extensions were granted till June 2020.
Ultimately, a notice of termination dated 30.09.2020 was issued by the
respondent under the General Conditions of Contract (GCC) 62(1) and
16(4)(f). Pursuant to the same, the Earnest Money Deposit (EMD),
Performance Guarantee (PG) and Security Deposit (SD) were forfeited
and certain claims made by the petitioner was rejected. The dispute was
referred to the Arbitral Tribunal and the claimant made the following
claims:
(a) To declare that the termination order dated
30-09-2020 is unlawful and also the termination has
been done without currency.
2/22 https://www.mhc.tn.gov.in/judis
Arb.OP(Com.Div).No.630 of 2022
(b) Direct the Respondent to release the
Performance Guarantee amount of a sum Rs.
16,62,557/- .
(c) Direct the Respondent to Refund the EMD of
Rs. 2,82,400/-.
(d) Direct the Respondent to Refund the Security
Deposit of Rs. 13,45,026/-.
(e) Direct the Respondent to pay the Price
Variation Clause Amount of a sum of Rs. 17,63,411/-.
(f) Direct the Respondent to pay the GST
Amount of a sum of Rs. 14,26,327/-.
(g) The Claimant is entitled to cost of Stock at
site of a sum o Rs.4,50,000/-.
(h) The Claimant is entitled to loss of amount
incurred in Idling of men and Machinery of sum of Rs.
1,40,000/-.
(i) The Claimant is entitled to overhead charges
and establishment charges incurred of a sum of
Rs.6,76,000/-.
(j) The Claimant is entitled to cost of 2.5 MT
Finished steel structure of a sum of Rs.2,96,000/-.
(k) The Claimant is entitled to loss of profit at
10% on the balance work of Rs. 2,89,54,459/-
amounting to Rs.28,95,446/-.
3/22 https://www.mhc.tn.gov.in/judis
Arb.OP(Com.Div).No.630 of 2022
(l) The Claimant is entitled to Rs. 15,06,047/-
payable towards the Interest and charges paid by the
Claimant to banks and others.
(m) The respondent is liable to pay compensation
20,00,000/-for the agony endured and which continues
till date due to the wrongful termination of the contract.
(n) The claimant is entitled to interest on the
claims.
(o)The respondent is liable to bear the cost of
arbitration.
3.The respondent filed statement of defence and justified the
termination of contract and forfeiture of EMD, PG and SD. The
respondent sought for counter claims to the total tune of Rs.2.44 Crores.
The respondent also sought for the rejection of the claim made by the
petitioner.
4.The Arbitral Tribunal instead of framing issues thought it fit to
deal with each claim made by the petitioner and the counter claim made
by the respondent. On considering the facts and circumstances of the
case and the documents relied upon by both sides, Claim Nos.5 and 6
alone were awarded. Insofar as the counter claims are concerned, the
majority members held that the respondent is entitled for Counter Claim
4/22 https://www.mhc.tn.gov.in/judis
Arb.OP(Com.Div).No.630 of 2022
Nos.1 and 2 and rejected Counter Claim Nos. 3 to 5. The summary of the
award is tabulated hereunder:
48.1 Claims of Claimant :
ClaimGist of claimAmount of
Claim
(in Rs.)
Award given by
presiding Arbitrator
(in Rs.)
Award given by
other two
Arbitrators
(in Rs.)
(1)To declare
termination of
contract not
valid
DeclaratoryClaimant as well as
respondent are
responsible for
termination.
Termination letter
with retrospective
effect is legally valid
and justified.
(2)Release of
Performance
guarantee
amount
16,62,557/-
Half of each totalling
16,44,991/- in
favour of the
Nil
(3) Refund of
EMD
2,82,400/- Nil
(4) Refund of
security
deposit
13,45,026/- Claimant Nil
(5)Payment of
price variation
as per
agreement
17,63,411/-
increased to
26,20,140/-
25,94,300/- in favour
of the claimant
25,94,300/-
(6)Reimburse
eligible GST
neutralization
14,26,327/-
increased to*
15,22,402/-
15,22,402/- in favour
of the claimant
Rs.15,22,402/- in
favour of the
claimant
(7)Payment of
stock at site
4,50,000/- Nil Nil
5/22 https://www.mhc.tn.gov.in/judis
Arb.OP(Com.Div).No.630 of 2022
ClaimGist of claimAmount of
claimant
(in Rs.)
Award given by
presiding
Arbitrator (In
Rs.)
Award given by
other two
Arbitrators (in Rs.)
(8)Payment for
idling of men
and machinery
1,40,000/- Nil Nil
(9) Payment
towards
overhead and
establishment
charges
6,76,000/- Nil Nil
(10)Payment for
fabricated steel
structure
2,96,000/- Nil Nil
(11)Loss of profit28,95,446/- Nil Nil
(12)Reimbursement
of interest paid
to Bank
15,06,047/- Nil Nil
(13)Compensation
for damage of
reputation etc,
20,00,000/- Nil Nil
(14)Payment of
interest charges
at 12%
TO BE
DECIDED
Nil Nil
(15)Legal expenses
and cost of
Arbitration
9,00,000/- Nil Nil
(16)TOTAL OF
ALL CLAIMS
1,53,43,214/-
(INCREASED
TO
1,62,96,018/-)
+ to be decided
57,61,693/- in
favour of the
claimant
41,16,702/- in
favour of the
claimant
*Increased by the claimant through his submission at CD-4.
6/22 https://www.mhc.tn.gov.in/judis
Arb.OP(Com.Div).No.630 of 2022
49.COUNTER CLAIMS OF RESPONDENT:
C/
Claim
Gist of
Counter Claim
Amount of
claim
(in Rs.)
Award given by
presiding
Arbitrator
(In Rs.)
Award given by
other two
Arbitrators
(in Rs.)
(1)Forfeiture of
Performance
guarantee
16,62,557/-Same as award
against claims
nos.2,
3 & 4
Rs.16,44,991/- in
favour of
respondent
16,62,557/- in
favour of
respondent
(2)Forfeiture of
EMD and SD
16,62,557/- 16,62,557/- in
favour of
respondent
(3) Cost of
supervision
58,56,339/- Nil Nil
(4)Difference in
cost due to
escalation
1,66,11,249/- Nil Nil
(5) Cost of
Arbitration
To be
quantified
Nil Nil
(6) Total 2,44,68,417/-
(actual total
comes to
2,57,92,702/-)
plus amount
to be
quantified
Rs.16,44,991/-
in favour of
respondent
Rs.33,25,114/-
in favour of
respondent
5.Aggrieved by the above award passed by the Tribunal, the
present petition has been filed before this Court.
7/22 https://www.mhc.tn.gov.in/judis
Arb.OP(Com.Div).No.630 of 2022
6.The learned counsel for the petitioner mainly focused his
arguments with respect to Claim Nos.1 to 4, 7 and 11 and it will suffice to
deal with these claims while testing the award passed by the Arbitral
Tribunal.
7.This Court heard the learned counsel for the petitioner and the
learned counsel for the respondents and has carefully considered the
submissions of the learned counsel on either side and perused the
materials available on record and the award passed by the Arbitral
Tribunal.
8.Claim Nos. 1 to 4 are interconnected since the forfeiture of
EMD, PG and SD was done pursuant to the termination of the contract.
Therefore, if the termination of the contract is upheld, the forfeiture of
EMD, PG and SD will be justified. If the termination is held to be bad,
the forfeited amount will have to be refunded to the petitioner.
9.The time was fixed for the completion of work as 12 months.
However, three extensions were granted. The first extension was granted
on 26.6.2018 upto 31.12.2018 and this extension was granted under
8/22 https://www.mhc.tn.gov.in/judis
Arb.OP(Com.Div).No.630 of 2022
Clause 17A(ii) of the GCC. The second extension was granted on
6.3.2019 once again by relying upon the same Clause upto 31.12.2019.
The third extension was granted on 21.01.2020 again by relying upon the
same clause upto 30.06.2020. It is an admitted case that no further
extension of time was granted and the period came to an end on
30.06.2020.
10.In the light of the above admitted facts, two issues that falls for
consideration is as to whether after the expiry of the period a contract can
be cancelled and whether extension of the period under Clause 17A(ii) of
the GCC can result in breach of contract for not completing the work
within the time stipulated.
11.The reasons for the extension of time are (a) GAD revised and
approved only on 2.11.2018 (b) Alignment of FOB changed “Z” shape to
a straight line (c ) Site was not handed over for platforms 3 to 6, 10 and
11 and; (d) G1/A2B site – additional work.
12.Apart from the above, there were other reasons like certain third
parties who had to vacate and hand over possession and which was
protracting due to litigation.
9/22 https://www.mhc.tn.gov.in/judis
Arb.OP(Com.Div).No.630 of 2022
13.As stated supra, extension of time was granted under Clause
17A(ii) of the GCC. For proper appreciation, the relevant Clause is
extracted hereunder:
17- A Extension of Time in Contracts:
(ii) Extension for Delay not due to Railway or
Contractor: If in the opinion of the Engineer, the progress
of work has any time been delayed by any act or neglect
of Railway's employees or by other Contractor employed
by the Railway under Sub-Clause (4) of Clause 20 of
these Conditions or in executing the work not forming part
of the contract but on which Contractor's performance
necessarily depends or by reason of proceeding taken or
threatened by or dispute with adjoining or to neighbouring
owners or public authority arising otherwise through the
Contractor's own default etc. or by the delay authorized by
the Engineer pending arbitration or in consequences of the
Contractor not having received in due time necessary
instructions from the Railway for which he shall have
specially applied in writing to the Engineer or his
authorized representative then upon happening of any
such event causing delay, the Contractor shall immediately
give notice thereof in writing to the Engineer within 15
days of such happening, but shall nevertheless make
constantly his best endeavours to bring down or make
good the delay and shall do all that may be reasonably
required of him to the satisfaction of the Engineer to
proceed with the works. The Contractor may also indicate
the period for which the work is likely to be delayed and
shall be bound to ask for necessary extension of time. The
Engineer on receipt of such request from the Contractor
10/22 https://www.mhc.tn.gov.in/judis
Arb.OP(Com.Div).No.630 of 2022
shall consider the same and shall grant such extension of
time as in his opinion is reasonable having regard to the
nature and period of delay and the type and quantum of
work affected thereby. No other compensation shall be
payable for works so carried forward to the extended
period of time; the same rates, terms and conditions of
contract being applicable as if such extended period of
time was originally provided in the original contract itself.
14.An extension made under Clause 17A(ii) is an extension given
where the delay is not attributable either to the Railways or to the
contractor. Thus, this Clause is invoked when there are justifiable reasons
to extend the period of contract. It also makes it clear that no further
compensation will be payable for the works carried out during the
extended period of time and the same rates and terms of conditions of
contract will be applicable even for the extended period as if such time
was provided in the original contract itself.
15.In the termination notice dated 30.09.2020, it has been stated
that the petitioner failed to complete the work and failed to apply for the
further extension of period upto 30.06.2020 and did not show any
progress even after the issuance of seven days notice and 48 hours notice
and therefore the contract stands terminated with effect from 30.06.2020.
11/22 https://www.mhc.tn.gov.in/judis
Arb.OP(Com.Div).No.630 of 2022
16.While going through the materials placed before this Court, it is
seen that various reasons have been given regarding poor progress shown
by the petitioner from 16.3.2020. On 15.9.2020, the SSE bridges writes
that the fabrication work for GI road side work is under progress but the
progress is not substantial. The next day the same SSE bridges writes
another letter stating that the work has not progressed for more than six
months inspite of repeated instructions. On 29.9.2020, yet another letter
was issued to the effect that the contractor has not even reported to the
SSE bridges.
17.In the seven days notice, it is mentioned that the work has not
restarted and that the claimant did not work from 16.3.2020.
18.On the side of the petitioner, certain documents were relied
upon to show that steel has been procured and fabrication was in progress
during September 2020 and during interregnum period between April and
July 2020, nothing was able to be done due to the Pandemic period.
19.The Arbitral Tribunal in more than one place renders a finding
that the contract has come to an end on 30.06.2020 and admittedly no
12/22 https://www.mhc.tn.gov.in/judis
Arb.OP(Com.Div).No.630 of 2022
extension of time was granted thereafter. At this juncture, it has to be
seen as to whether there can be a termination of contract that is not
subsisting.
20.Once a contract comes to an end by efflux of time and the
period is not extended, there is no question of issuing a termination
notice and thereafter terminating the contract. The very process of
termination pre-supposes that there is a subsisting contract. If there is no
subsisting contract, there is nothing to be terminated thereafter. Useful
reference can be made to the judgment of the Bombay High Court in
Union of India .V. M/s.Quick Communication Systems Pvt., Ltd.,
made in Arbitration Petition No.305 of 2009 dated 02.07.2012. It is
also relevant to take note of the judgment of this Court in The Chief
Engineer/CN/East, Construction Office, Southern Railway,
Chennai .Vs. 1.Mrs.V.kalyani and Others reported in 2018 SCC
Online Mad 2138.
21.The Arbitral Tribunal renders a finding that the determination of
the contract three months after it came to an end is nothing but a
declaration of the end of the contract on account of breach of contract by
the claimant after the previous last day of validity of the contract. The
13/22 https://www.mhc.tn.gov.in/judis
Arb.OP(Com.Div).No.630 of 2022
Arbitral Tribunal further holds that repudiatory breach is one of the
underlying principles to terminate a contract validly where the party does
not intend to perform his part of the contract or acts inconsistent with the
terms of the contract. These justifications given by the Arbitral Tribunal
does not in any way justify the act of the respondent in terminating a
contract which is not subsisting and which had admittedly come to an end
on 30.06.2020.
22.The Tribunal also takes into consideration the order passed by
this Court under Section 9 of the Act. Such an application came to be
filed by the petitioner to ensure that the left out work is completed and it
did not touch upon the issue of termination of contract. The Arbitral
Tribunal holds that the termination of the contract was not challenged by
the petitioner under Section 9 of the Act and that was put as a ground
against the petitioner. The petitioner could not have challenged the
termination of contract under Section 9 of the Act since if the petitioner
has sought for injuncting the respondent from terminating, it would have
been rejected under Section 14 of the Specific Relief Act, 1963 since it is
capable of being compensated in terms of money.
14/22 https://www.mhc.tn.gov.in/judis
Arb.OP(Com.Div).No.630 of 2022
23.As stated supra, the extension of time was granted under Clause
17A(ii) of the GCC. Thus, the delay caused due to this extension is
neither attributable to the petitioner nor to the respondent and therefore
the same cannot lead to breach of contract for not completing the work
within the time stipulated.
24.The judgment that was relied upon by the Arbitral Tribunal in
the case of Air India Limited .Vs. Gati Limited will not apply to the
facts of the present case since that was a case where there was inaction or
delay on the part of one party and therefore the termination notice issued
without following the proper procedure was held not to vitiate such
termination.
25.In the light of the above discussion, this Court holds that the
finding rendered by the Arbitral Tribunal justifying the termination order
dated 30.09.2020 is clearly perverse and suffers from patent illegality.
26.The Arbitral Tribunal consisted of retired personnel who were
working with Railways and they were trying to come up with various
reasons to justify the termination of the contract and to justify the
consequent forfeiture of EMD, PG and SD. Such state of mind on the
15/22 https://www.mhc.tn.gov.in/judis
Arb.OP(Com.Div).No.630 of 2022
part of the Arbitral Tribunal is quite apparent on a careful reading of the
award.
27.In the light of the above finding, the forfeiture of EMD, PG and
SD is unsustainable. Only if there is a valid termination of contract in
line with GCC 62(1), it can lead to forfeiture of EMD, PG and SD under
Clause 16(4)(f). If the termination of contract is held to be unlawful, the
consequent forfeiture must also fall to the ground.
28.In the light of the above discussion, Claim Nos.1 to 4 which was
rejected by the Arbitral Tribunal and which is connected with counter
claim nos.1 and 2, is liable to be interfered with by this Court and the
findings are set aside.
29.The next issue pertains to Claim No.7. This claim was made for
payment of steel material purchased and stocked at the site. The Arbitral
Tribunal rejected this claim only on the ground that the claimant had
caused breach of contract by not completing the work and the termination
of contract was upheld and therefore the claimant is not entitled for any
award under this head. The only other reason that has been assigned is
that the respondent has not taken custody of the materials of the claimant
16/22 https://www.mhc.tn.gov.in/judis
Arb.OP(Com.Div).No.630 of 2022
from the work site. The finding rendered by the Arbitral Tribunal is liable
to be interfered by this Court since the claimant has established the fact
that the steel material purchased was stocked at the work site (platform 10
and 11) and it was never taken back by the claimant. Accordingly, claim
No.7 has to be awarded in favour of the claimant.
30.Claim No.11 pertains to loss of profit due to illegal termination
of the contract.
31.The specific case of the claimant is that the illegal and unlawful
termination of the contract resulted in the claimant not being able to
execute the balance work resulting in loss of money invested, loss of
manpower and damage caused to the reputation of the claimant. The
claimant was claiming for 10% on the balance work to the tune of
Rs.26,18,886/-.
32.The Arbitral Tribunal had rejected this claim mainly on the
ground that the claimant had committed breach of contract and the
termination of the contract was also upheld and hence the claimant was
held to be not entitled for any compensation under this head.
17/22 https://www.mhc.tn.gov.in/judis
Arb.OP(Com.Div).No.630 of 2022
33.When it comes to loss of profit, certain amount of guesswork
and leeway is permitted and the Arbitral Tribunal can employ honest
guess work and a rough and ready method for quantifying the damage.
GCC61(3) provides that a contractor shall have no claim to any payment
of compensation or otherwise howsoever on account of any profit or
advantage which he might have derived from the execution of the work in
full but which he did not derive in consequence of determination of
contract.
34.The above Clause can be put against the petitioner if the
termination of the contract was legal. This Court has already held that the
termination of contract is illegal and unlawful. Under such
circumstances, the petitioner will be entitled for loss of profit. However,
there must be some basis for calculating this loss. The only basis on
which the petitioner is claiming for loss of profit is the balance work not
completed and out of which the petitioner is claiming for 10%. Such a
claim cannot be awarded mechanically without giving reasons on the
underlying facts which ultimately leads to adopting a formula to calculate
loss of profit. Just because the Arbitral Tribunal or the Court are given
the leeway or the scope for guesswork, that does not mean that an
arbitrary amount can be fixed without reasons. In the case in hand, the
18/22 https://www.mhc.tn.gov.in/judis
Arb.OP(Com.Div).No.630 of 2022
claimant is seeking for loss of profit at 10% on the balance work that was
not completed and that certainly cannot form the basis for awarding
compensation under the head of loss of profit. Hence, this Court is not
inclined to interfere with the finding of the Arbitral Tribunal insofar as
Claim No.11 is concerned.
35.The last issue that arises for consideration is as to whether the
petitioner will be entitled to claim for payment of interest towards the
EMD, PG and SD that has to be refunded by the respondent.
36.Under normal circumstances, these amounts will not carry any
interest and it has to be refunded as such. However, these amounts have
been retained by the respondent by forfeiting these amounts and such
forfeiture was held to be illegal by this Court. Therefore, the petitioner
will be certainly entitled for payment of interest on the EMD, PG and
SD.
37.In the result, Claim Nos.1 to 4 and 7 are awarded in favour of
the petitioner/claimant. Insofar Claim Nos. 2 to 4 are concerned, the
EMD, PG, and SD shall be refunded to the petitioner with interest at the
rate of 9% p.a., from 30.06.2020 till the date of actual payment.
19/22 https://www.mhc.tn.gov.in/judis
Arb.OP(Com.Div).No.630 of 2022
Similarly, the sum of Rs.4,50,000/- for Claim No.7 shall be paid to the
petitioner/claimant with interest at the rate of 9% p.a., from 30.06.2020,
till the date of actual payment. The counter claims 1 and 2 awarded by
the Arbitral Tribunal in favour of the respondent is set aside. The award
in all other respects stands confirmed.
38.In the result, this Arbitration Original Petition is allowed in the
above terms and there shall be a direction to the respondent to pay cost of
a sum of Rs.2,00,000/- to the petitioner.
13.02.2026
Index:Yes/No
Speaking order/Non Speaking Order
NCC:Yes/No
kp
20/22 https://www.mhc.tn.gov.in/judis
Arb.OP(Com.Div).No.630 of 2022
To
The Divisional Railway Manager
Chennai Division
Southern Railway
Chennai.
21/22 https://www.mhc.tn.gov.in/judis
Arb.OP(Com.Div).No.630 of 2022
N.ANAND VENKATESH, J
kp
Pre Delivery Order in
Arb.OP(Com.Div).No.630 of 2022
13.02.2026
.
22/22 https://www.mhc.tn.gov.in/judis
Legal Notes
Add a Note....