IN THE HIGH COURT OF ANDHRA PRADESH AT AMARAVATI
****
WRIT PETITION No.22568 of 2020
And
CONTEMPT CASE No.1580 of 2021
Between:
M/s. Sunshine Electricals,
Rep. by its Proprietor, Mr. K.V.R. Babu,
S/o. Venku Naidu, Aged about 51 years,
Office at :D.No.12-1-25, GNT Road,
Nehru Chowk,
Anakapalli, Visakhapatnam-531001,
R/o. H.No.12-4-36/8, Lokesh Vari Veedhi,
Near RTC Complex, Anakapalle,
Visakhapatnam District
--- Petitioner
And
The State of A.P.,
Rep. by its Principal Secretary,
Panchayat Raj and Rural Development,
(RWS & S) Department,
Secretariat Buildings,
Velagapudi, Amaravathi,
Guntur District
and others
--- Respondents
DATE OF JUDGMENT PRONOUNCED : 06.09.2022
SUBMITTED FOR APPROVAL :
2
NV, J
wp_22568_2020 & cc_1580_2021
HON'BLE SRI JUSTICE VENKATESWARLU NIMMAGADDA
1. Whether Reporters of Local Newspapers
may be allowed to see the judgment? Yes/No
2. Whether the copy of judgment may be
marked to Law Reporters/Journals? Yes/No
3. Whether His Lordship wish to
see the fair copy of the judgment? Yes/No
_________________________________________
VENKATESWARLU NIMMAGADDA, J
3
NV, J
wp_22568_2020 & cc_1580_2021
* HON'BLE SRI JUSTICE VENKATESWARLU NIMMAGADDA
+ WRIT PETITION No.22568 of 2020
And
CONTEMPT CASE No.1580 of 2021
% 06.09.2022
# Between:
M/s. Sunshine Electricals,
Rep. by its Proprietor, Mr. K.V.R. Babu,
S/o. Venku Naidu, Aged about 51 years,
Office at :D.No.12-1-25, GNT Road,
Nehru Chowk,
Anakapalli, Visakhapatnam-531001,
R/o. H.No.12-4-36/8, Lokesh Vari Veedhi,
Near RTC Complex, Anakapalle,
Visakhapatnam District
--- Petitioner
And
The State of A.P.,
Rep. by its Principal Secretary,
Panchayat Raj and Rural Development,
(RWS & S) Department,
Secretariat Buildings,
Velagapudi, Amaravathi,
Guntur District
and others
--- Respondents
! Counsel for the petitioner : Sri Subba Rao Korrapati
^Counsel for Respondent Nos.: Learned Government Pleader
1 and 2 for Panchayat Raj
^ Counsel for Respondent No.3: Sri Alapati Vivekananda,
Learned Standing Counsel
for NREDCAP
4
NV, J
wp_22568_2020 & cc_1580_2021
< Gist:
> Head Note:
? Cases referred:
1. 2011 (5) SCC 697
2. 2015 (14) SCC 685
3. (2004) 3 SCC 553
4. (1981) 3 SCC 238
5. (1989) 2 SCC 116
6. (1996) 6 SCC 22
7. (2000) 6 SCC 293
8. (2015) 7 SCC 728
9. 2019 SCC Online All 2244
10. (2019) 16 SCC 794
This Court made the following :
5
NV, J
wp_22568_2020 & cc_1580_2021
THE HON’BLE SRI JUSTICE VENKATESWARLU NIMMAGADDA
WRIT PETITION No.22568 of 2020
And
CONTEMPT CASE No.1580 of 2021
COMMON ORDER :
Learned counsel for the petitioner as well as learned
counsel for the respondents agreed to pass a common order in
both the writ petition as well as in contempt case. Accordingly,
this Court is inclined to pass a common order in both the writ
petition as well as in contempt case.
2. The present writ petition is filed declaring the inaction of
the respondents in releasing the payments due to the petitioner
concern, as per the directions of the 2
nd
respondent herein, vide
Memo No.24/CPR & RD/LED/2018, dated 19.05.2020 and
subsequent letter of the 1
st
respondent vide Letter No.PRR01-
PROPPAN(STLT)/5/Pts.III/A2/2020, dated 19.08.2020 in
respect of the work executed by the petitioner for conversion of
existing conventional streetlights into energy efficient LED street
lighting system for conservation of energy in Gram Panchayats
in Visakhapatnam District, as per agreement dated 30.10.2017
with the 3
rd respondent-Corporation herein, as illegal and
arbitrary.
6
NV, J
wp_22568_2020 & cc_1580_2021
3. Heard learned counsel for the petitioner, learned
Government Pleader for Panchayat Raj and learned Standing
Counsel for 3
rd respondent-Corporation.
4. Learned counsel for the petitioner submits that the 1
st
respondent took a policy decision and decided to convert the
existing conventional streetlights into energy efficient LED street
lighting system for conservation of energy and for minimizing
the maintenance expenditure incurring under street lighting
head in various Gram Panchayats in Andhra Pradesh.
Presently, the street lighting system prevailing in the Gram
Panchayats of State of Andhra Pradesh is conventional lighting
systems based on High Pressure Sodium Vapor lamps, Metal
Halide lamps, Florescent Tube Lights and CFL etc. In fact, the
LED based street lighting systems offers higher efficiency, better
illumination and life expectancy, apart from being
environmentally benign. While so, to achieve this object, the 1
st
respondent has entered into MOU with the 3
rd
respondent on
26.03.2016 for survey, supply and installation of LED Fixtures
and CCMS through SMART Centre Connectivity including their
post installation maintenance over the project for a period of 10
years at specified Gram Panchayats in Andhra Pradesh. The 3
rd
respondent-Corporation is created by the 1
st respondent.
7
NV, J
wp_22568_2020 & cc_1580_2021
Hence, it is classified as Government Company and owned by
the 1
st respondent.
5. Pursuant to achieving the proposed object of the 1
st
respondent, the 3
rd
respondent-Corporation was permitted to
act as Nodal Agency on behalf of the 2
nd
respondent herein for
conversion of conventional street lighting. Similarly, the 2
nd
respondent also indentified another agency i.e., EESL and
entered into an agreement dated 17.07.2017, which is
subsequent to the agreement entered by the 3
rd respondent
herein. It is a fact that the agreement between the 1
st
respondent and EESL is allowing payments for installation
charges apart from other charges, which are common in respect
of the 3
rd respondent and EESL. Then, the vendors, who were
entered into agreements with the 3
rd respondent to achieve the
above said object, have requested vide affidavits dated
03.10.2017 to enlarge the benefit of payment of installation
charges in accordance with the terms of agreement entered into
between the 1
st
respondent and EESL. The said request was
forwarded and to see that it is acceptable to the 1
st
respondent
by the 3
rd
respondent herein. Accordingly, the 1
st
respondent
issued a Memo dated 18.10.2017 permitting the 2
nd respondent
to enter into a separate agreement with the 3
rd respondent with
8
NV, J
wp_22568_2020 & cc_1580_2021
conditions same as that of conditions of agreement with EESL
dated 17.07.2017. In view of the same, the agreements with
the 3
rd respondent as well as EESL entered into by the 2
nd
respondent are one and the same.
6. In pursuance of the object, the 1
st
respondent identified
the Gram Panchayats in Visakhapatnam and West Godavari
Districts in Phase-I and entrusted the same for such conversion
to the 3
rd
respondent herein. The 3
rd
respondent issued tender
notice dated 01.06.2017 and after completion of entire tender
procedure, the 3
rd respondent-Corporation and petitioner
entered into an agreement dated 30.10.2017. As per the
agreement, the total value of the work is about Rs.75 Crores in
respect of 925 villages. He further submits that as per the
terms and conditions of the agreement and with the help of the
agencies, the petitioner completed the execution of work in
respect of Visakhapatnam District. Then the 5
th
respondent
also issued satisfaction letter about the work of the petitioner to
the 3
rd
respondent-Corporation and specified Rs.7,56,04, 379/-
to be payable out of that only Rs.1,92,01,513/- paid so far.
Then the petitioner submitted a representation dated
30.06.2020 to the 2
nd respondent and another representation
dated 30.09.2019 to the 3
rd respondent seeking payment of due
9
NV, J
wp_22568_2020 & cc_1580_2021
amount of Rs.9,33,90,066/- but there is no response. Learned
counsel for the petitioner also submitted the documents issued
by the respondent authorities under which the respondents
admitted the amounts and agreement on par of EESL. The 3
rd
respondent addressed a letter to the 2
nd
respondent for entering
into an agreement as per the directions of the 1
st
respondent
regarding infrastructure development authorities with the 2
nd
respondent dated 23.10.2017. On 19.05.2020 the 2
nd
respondent issued a memo directing respondent Nos.5 to 7 to
release of the funds for payment of the dues to the petitioner.
Even after specific memo no payments were released, the
petitioner having waited for considerable time, then made
representations to the concerned authorities and also National
Commission for Backward Classes. Pursuant to the letter
addressed by the National Commission for Backward Classes,
respondent Nos.1 and 2 replied that the 3
rd
respondent
submitted bills for an amount of Rs.14.19 Crores towards
installation of LED Lights in respect of Visakhapatnam, West
Godavari and Krishna Districts. Out of an amount of Rs.14.19
Crores, an amount of Rs.3.60 Crores was already paid to the 3
rd
respondent. So, the total remaining bill to be payable is
approximately Rs.11.00 Crores. While so, the 2
nd respondent
10
NV, J
wp_22568_2020 & cc_1580_2021
vide Memo dated 19.05.2020 admitted the amount payable to
the petitioner in respect of Visakhapatnam District is
Rs.6,84,69,937/- as on that date and the same was also
confirmed by the 1
st
respondent vide letter dated 19.08.2020.
In view of the said admission on the part of the respondents,
they are bound to release the payments to the petitioner. As
such, the petitioner can invoke the jurisdiction of this Court
since it is well settled that the alternative remedy is not effective
and efficacious except to invoke a writ jurisdiction when an
injustice is caused and rule of law is violated. He further
submits that it is also well settled that the writ petition is
maintainable in the matter of contracts, when the action of the
respondent statutory authorities is in violation of principles of
natural justice and is not in accordance with the procedure as
contemplated and in the public interest as held by the Hon’ble
Apex Court in Union of India and others v. Tantia
Constructions Private Limited
1
and similarly the Hon’ble
Apex Court also in Naseem Ahmed v. State of Uttar Pradesh
2
held that “in view of the fact that the amount had been admitted
by the respondent Government, we feel that said amount should
1
2011 (5) SCC 697
2
2015 (14) SCC 685
11
NV, J
wp_22568_2020 & cc_1580_2021
be paid without entering into any arbitration, etc. and therefore
the amount shall be paid to the appellant within four months
from today after deducting taxes etc.” In support of his case, he
also relied upon the judgment of the Hon’ble Apex Court in ABL
International Ltd. v. Export Credit Guarantee Corporation
of India Ltd.
3
. He also submits that apart from the judgments
of the Hon’ble Apex Court, this Court also granted reliefs
together with interest in W.P.No.2369 of 2018 dated 23.09.2019
and another W.P.No.496 of 2020 dated 13.08.2020. Therefore,
the respondents are liable to pay the amounts as admitted by
them as stated above.
7. Learned counsel for the petitioner further submits that as
per the counter affidavit of the 3
rd respondent, the 3
rd
respondent specifically and categorically admitted that the
amount payable to the petitioner upto 30.06.2020 is
Rs.8,42,61,256.56 out of which, an amount of Rs.3,03,79,110/-
was paid and balance quarterly bill amount of Rs.5,38,82,146/-
is to be received from respondent Nos.1 and 2. But the 2
nd
respondent in his counter affidavit admitted total amount
payable in respect of Visakhapatnam District upto December,
3
(2004) 3 SCC 553
12
NV, J
wp_22568_2020 & cc_1580_2021
2019 is Rs.6,62,00,643/- to the 3
rd respondent herein and out
of the said amount upto December, 2019, Rs.3,04,13,963/- was
paid and remaining Rs.3,57,88,868/- was paid after the orders
of this Court and pleaded the entire amount due to the
petitioner as per Memo dated 19.05.2020 has been paid. He
also submits that the difference of amount between the 3
rd
respondent as well as the 2
nd
respondent is Rs.2,83,02,463.41
ps. towards infrastructural developmental costs/installation of
lights, which was admitted by the 1
st respondent vide Memo
dated 18.10.2017. Pursuant to said memo, respondent Nos.2
and 3 are entered into an agreement for such payment on
23.10.2017. Therefore, the respondents are liable to pay an
amount of Rs.4,83,86,491/- upto June, 2020. In view of the
categorical admission on the part of the 3
rd respondent in its
counter affidavit, the contention of the respondents that the writ
petition is not maintainable since alternative remedy is available
as per clauses of the agreement entered into between the 3
rd
respondent and the petitioner dated 30.10.2017 are cannot be
sustained as held by the Hon’ble Apex Court as well as this
Court that wherever there is an admission of amounts or
admission of facts on the part of official respondents the writ
13
NV, J
wp_22568_2020 & cc_1580_2021
jurisdiction is always available to the aggrieved party. In view of
the settled law, this writ petition is liable to be allowed.
8. Learned Government Pleader for Panchayat Raj appearing
for respondent Nos.1 and 2 submits that the present writ
petition is not maintainable since the petitioner is available
effective alternative remedy by way of initiation of arbitration
proceedings as per Clauses 19(1), 19(2) and 19(3) of the
agreement dated 30.10.2017 entered into between the petitioner
as well as the 3
rd respondent herein. Moreover, there is no
privity of contract between the petitioner and respondent Nos.1
and 2. Even though there is no privity of contract between the
petitioner and respondent Nos.1 and 2, but wantonly
respondent Nos.1 and 2 arrayed as party respondents in the
writ petition. The other contention of learned Government
Pleader is that the prayer of the petitioner in the writ petition is
only declaring the inaction of the respondents in releasing the
payments due to the petitioner as per the directions of the 2
nd
respondent vide memo dated 19.05.2020 and subsequent letter
of the 1
st
respondent dated 19.08.2020, as illegal and arbitrary.
As per the said memo, the 2
nd
respondent instructed the 5
th
respondent to take steps for payment of bills due in favour of
the petitioner as well as others. As per the said memo, the
14
NV, J
wp_22568_2020 & cc_1580_2021
amount due as on December, 2019 is Rs.6,84,69,937/- out of
the said admitted amount, an amount of Rs.3,04,13,963/- was
paid prior to the writ petition and an amount of
Rs.3,57,88,868/- was paid to the 3
rd
respondent after filing of
the present writ petition. Therefore, the entire amount as
admitted vide Memo dated 19.05.2020 as prayed by the
petitioner and the same was complied with and for further dues,
which may arise after filing of the writ petition, are not admitted
by the 2
nd respondent and regarding infrastructural
developmental charges, which are claiming by the petitioner, is
never admitted by respondent Nos.1 and 2 and there is no
privity of contract even between the petitioner and 3
rd
respondent. Therefore, the extraordinary jurisdiction of this
Court is not amenable regarding disputed facts between the
parties. In support of his case, he relied upon the judgments
rendered by the Hon’ble Apex Court, which are as under:
1. In Divl. Forest Officer v. Bishwanath Tea Co. Ltd.
4
,
the Hon’ble Apex Court held at para No.9 as under:
“9. Ordinarily, where a breach of contract is complained
of, a party complaining of such breach may sue for specific
performance of the contract, if contract is capable of being
4
(1981) 3 SCC 238
15
NV, J
wp_22568_2020 & cc_1580_2021
specifically performed, or the party may sue for damages.
Such a suit would ordinarily be cognizable by the civil court.
The High Court in its extraordinary jurisdiction would not
entertain a petition either for specific performance of
contract or for recovering damages. A right to relief flowing
from a contract has to be claimed in a civil court where a
suit for specific performance of contract or for damages
could be filed. This is so well-settled that no authority is
needed. However, we may refer to a recent decision bearing
on the subject. In Har Shankar v. Deputy Excise & Taxation
Commissioner [(1975) 1 SCC 737] the petitioners offered
their bids in the auctions held for granting licences for the
sale of liquor. Subsequently, the petitioners moved to
invalidate the auctions challenging the power of the
Financial Commissioner to grant liquor licences. Rejecting
this contention, Chandrachud, J. (as he then was), speaking
for the Constitution Bench at p. 263 observed as under:
(SCC p. 746, para 16)
“Those who contract with open eyes must accept
the burdens of the contract along with its benefits.
The powers of the Financial Commissioner to grant
liquor licences by auction and to collect licence fees
through the medium of auctions cannot by writ
petitions be questioned by those who, had their
venture succeeded, would have relied upon those very
powers to found a legal claim. Reciprocal rights and
obligations arising out of contract do not depend for
their enforceability upon whether a contracting party
finds it prudent to abide by the terms of the contract.
By such a test no contract could ever have a binding
force.”
16
NV, J
wp_22568_2020 & cc_1580_2021
Again at p. 265 there is a pertinent observation which may
be extracted: (SCC p.747, para 21)
“Analysing the situation here, a concluded contract
must be held to have come into existence between the
parties. The appellants have displayed ingenuity in
their search for invalidating circumstances but a writ
petition is not an appropriate remedy for impeaching
contractual obligations.”
This apart, it also appears that in a later decision, the
Assam High Court itself took an exactly opposite view in
almost identical circumstances. In Woodcrafts
Assam v. Chief Conservator of Forests [AIR 1971 Ass 92] a
writ petition was filed challenging the revision of rates of
royalty for two different periods. Rejecting this petition as
not maintainable, a Division Bench of the High Court held
that the complaint of the petitioner is that there is violation
of his rights under the contract and that such violation of
contractual obligation cannot be remedied by a writ petition.
That exactly is the position in the case before us. Therefore,
the High Court was in error in entertaining the writ petition
and it should have been dismissed at the threshold.”
2. In Bareilly Development Authority v. Ajai Pal Singh
5
,
the Hon’ble Apex Court held at para No.22 as under:
“22. There is a line of decisions where the contract
entered into between the State and the persons aggrieved is
non-statutory and purely contractual and the rights are
governed only by the terms of the contract, no writ or order
can be issued under Article 226 of the Constitution of India
5
(1989) 2 SCC 116
17
NV, J
wp_22568_2020 & cc_1580_2021
so as to compel the authorities to remedy a breach of
contract pure and simple — Radhakrishna Agarwal v. State
of Bihar [(1977) 3 SCC 457], Premji Bhai Parmar v. Delhi
Development Authority [(1980) 2 SCC 129]
and DFO v. Biswanath Tea Company Ltd. [(1981) 3 SCC
238]”
3. In State of U.P. v. Bridge & Roof Co. (India) Ltd.
6, the
Hon’ble Apex Court held at para Nos.15, 16, 18 and 21 as
under:
“15. In our opinion, the very remedy adopted by the
respondent is misconceived. It is not entitled to any relief in
these proceedings, i.e., in the writ petition filed by it. The
High Court appears to be right in not pronouncing upon any
of the several contentions raised in the writ petition by both
the parties and in merely reiterating the effect of the order of
the Deputy Commissioner made under the proviso to
Section 8-D(1).
16. Firstly, the contract between the parties is a contract
in the realm of private law. It is not a statutory contract. It is
governed by the provisions of the Contract Act or, maybe,
also by certain provisions of the Sale of Goods Act. Any
dispute relating to interpretation of the terms and conditions
of such a contract cannot be agitated, and could not have
been agitated, in a writ petition. That is a matter either for
arbitration as provided by the contract or for the civil court,
as the case may be. Whether any amount is due to the
respondent from the appellant-Government under the
contract and, if so, how much and the further question
6
(1996) 6 SCC 22
18
NV, J
wp_22568_2020 & cc_1580_2021
whether retention or refusal to pay any amount by the
Government is justified, or not, are all matters which cannot
be agitated in or adjudicated upon in a writ petition. The
prayer in the writ petition, viz., to restrain the Government
from deducting a particular amount from the writ
petitioner's bill(s) was not a prayer which could be granted
by the High Court under Article 226. Indeed, the High Court
has not granted the said prayer.
18. Accordingly, it must be held that the writ petition
filed by the respondent for the issuance of a writ of
mandamus restraining the Government from deducting or
withholding a particular sum, which according to the
respondent is payable to it under the contract, was wholly
misconceived and was not maintainable in law. (See the
decision of this Court in Asstt. Excise Commr. v. Issac
Peter [(1994) 4 SCC 104] where the law on the subject has
been discussed fully.) The writ petition ought to have been
dismissed on this ground alone.
21. There is yet another substantial reason for not
entertaining the writ petition. The contract in question
contains a clause providing inter alia for settlement of
disputes by reference to arbitration (clause 67 of the
contract). The arbitrators can decide both questions of fact
as well as questions of law. When the contract itself provides
for a mode of settlement of disputes arising from the
contract, there is no reason why the parties should not
follow and adopt that remedy and invoke the extraordinary
jurisdiction of the High Court under Article 226. The
existence of an effective alternative remedy — in this case,
provided in the contract itself — is a good ground for the
court to decline to exercise its extraordinary jurisdiction
under Article 226. The said article was not meant to
19
NV, J
wp_22568_2020 & cc_1580_2021
supplant the existing remedies at law but only to
supplement them in certain well-recognised situations. As
pointed out above, the prayer for issuance of a writ of
mandamus was wholly misconceived in this case since the
respondent was not seeking to enforce any statutory right of
theirs nor was it seeking to enforce any statutory obligation
cast upon the appellants. Indeed, the very resort to Article
226 — whether for issuance of mandamus or any other writ,
order or direction — was misconceived for the reasons
mentioned supra.”
4. In Kerala State Electricity Board v. Kurien E.
Kalathil
7, the Hon’ble Apex Court held at para No.11 as under:
“11. A statute may expressly or impliedly confer power
on a statutory body to enter into contracts in order to enable
it to discharge its functions. Dispute arising out of the terms
of such contracts or alleged breaches have to be settled by
the ordinary principles of law of contract. The fact that one
of the parties to the agreement is a statutory or public body
will not by itself affect the principles to be applied. The
disputes about the meaning of a covenant in a contract or
its enforceability have to be determined according to the
usual principles of the Contract Act. Every act of a statutory
body need not necessarily involve an exercise of statutory
power. Statutory bodies, like private parties, have power to
contract or deal with property. Such activities may not raise
any issue of public law. In the present case, it has not been
shown how the contract is statutory. The contract between
the parties is in the realm of private law. It is not a statutory
7
(2000) 6 SCC 293
20
NV, J
wp_22568_2020 & cc_1580_2021
contract. The disputes relating to interpretation of the terms
and conditions of such a contract could not have been
agitated in a petition under Article 226 of the Constitution of
India. That is a matter for adjudication by a civil court or in
arbitration if provided for in the contract. Whether any
amount is due and if so, how much and refusal of the
appellant to pay it is justified or not, are not the matters
which could have been agitated and decided in a writ
petition. The contractor should have relegated to other
remedies.”
5. In Joshi Technologies International Inc. v. Union of
India
8, the Hon’ble Apex Court held at para Nos.69.4. 70.4,
70.6, 70.8 and 71 held as under:
“69.4. Money claims per se particularly arising out of
contractual obligations are normally not to be entertained
except in exceptional circumstances.
70.4. Writ jurisdiction of the High Court under Article
226 of the Constitution was not intended to facilitate
avoidance of obligation voluntarily incurred.
70.6. Ordinarily, where a breach of contract is
complained of, the party complaining of such breach may
sue for specific performance of the contract, if contract is
capable of being specifically performed. Otherwise, the party
may sue for damages.
70.8. If the contract between private party and the
State/instrumentality and/or agency of the State is under
the realm of a private law and there is no element of public
law, the normal course for the aggrieved party, is to invoke
21
NV, J
wp_22568_2020 & cc_1580_2021
the remedies provided under ordinary civil law rather than
approaching the High Court under Article 226 of the
Constitution of India and invoking its extraordinary
jurisdiction.
71. Keeping in mind the aforesaid principles and after
considering the arguments of the respective parties, we are
of the view that on the facts of the present case, it is not a fit
case where the High Court should have exercised
discretionary jurisdiction under Article 226 of the
Constitution. First, the matter is in the realm of pure
contract. It is not a case where any statutory contract is
awarded.”
6. In Ipjacket Technology India Private Limited v. M. D.
Uttar Pradesh Rajakiya Nirman Nigam Ltd .
9
, the Hon’ble Apex
Court held at para No.24 as under:
“24. We may gainfully refer to the judgment in the case
of Joshi Technologies International Inc. (supra) wherein the
entire legal position in this regard has been taken note of
and summarized in the following terms:—
“69. The position thus summarised in the aforesaid
principles has to be understood in the context of discussion
that preceded which we have pointed out above. As per
this, no doubt, there is no absolute bar to the
maintainability of the writ petition even in contractual
matters or where there are disputed questions of fact or
even when monetary claim is raised. At the same time,
discretion lies with the High Court which under certain
circumstances, it can refuse to exercise. It also follows that
8
(2015) 7 SCC 728
9
2019 SCC OnLine All 2244
22
NV, J
wp_22568_2020 & cc_1580_2021
under the following circumstances, “normally”, the Court
would not exercise such a discretion:
69.1. The Court may not examine the issue unless the
action has some public law character attached to it.
69.2. Whenever a particular mode of settlement of
dispute is provided in the contract, the High Court would
refuse to exercise its discretion under Article 226 of the
Constitution and relegate the party to the said mode of
settlement, particularly when settlement of disputes is to be
resorted to through the means of arbitration.
69.3. If there are very serious disputed questions of fact
which are of complex nature and require oral evidence for
their determination.
69.4. Money claims per se particularly arising out of
contractual obligations are normally not to be entertained
except in exceptional circumstances.””
9. Learned Standing Counsel for respondent No.3 submits
that he adopted the arguments of learned Government Pleader
for Panchayat Raj and contended that the amount, which was
claimed by the petitioner as per Memo dated 19.05.2020, is paid
and the claim of the petitioner regarding infrastructural
developmental charges so far not finalized and it is only a
disputed fact between the parties. He further submits that the
contention of the petitioner that the 6
th respondent is admitted
the amount payable to the petitioner is Rs.8,42,61,256.56 ps.,
which includes Rs.2,83,02,463/-, is towards infrastructural
developmental charges/for installation of lights is not received
23
NV, J
wp_22568_2020 & cc_1580_2021
by this respondent. Even though it was admitted in counter
affidavit but this respondent clarified in its additional counter
affidavit that the petitioner is due to the Corporation an amount
of Rs.1,56,68,405/- towards CCMS Boxes out of that they have
not deducted an amount of Rs.29,33,296/- deposited by
respondent Nos.1 and 2 and therefore, the amount admitted by
the 2
nd
respondent in its Memo dated 19.05.2020 i.e.,
Rs.6,64,46,338/- was paid to the petitioner after deduction of
service charges to this Corporation in 14 installments. As such,
the present writ petition is liable to be dismissed.
10. Having regard to the contentions made by learned counsel
for the petitioner as well as learned counsel for the respondents
and the material placed before this Court, this Court is of the
considered view that the contention of the petitioner that once
the 3
rd
respondent-Corporation admitted by sworn affidavit
before the Court regarding payments to be payable to the
petitioner is amounts to admission on the part of the 3
rd
respondent and the extraordinary jurisdiction of this Court can
be exercised in view of such admission made by the 3
rd
respondent is sustainable. The another contention of the
petitioner that for payment of infrastructural developmental
charges is accepted by respondent Nos.1 and 2 and issued a
24
NV, J
wp_22568_2020 & cc_1580_2021
memo directing the 2
nd respondent to enter into an agreement to
that effect with the 3
rd respondent is complied with and
accordingly, an agreement was entered on 23.10.2017. In view
of the agreement entered into between respondent Nos.2 and 3,
the 3
rd
respondent admitted such amount in its counter
affidavit regarding infrastructural developmental charges to be
payable to the petitioner. Therefore, such contention of the
petitioner is sustainable. The other contention of the petitioner
that when there is an admission on the part of the respondents
regarding any contract and its payment, the extraordinary
jurisdiction of this Court is very much available is also
sustainable as held by the Hon’ble Apex Court in the following
judgments:
1. In Naseem Ahmad ’s case (2 supra), the Hon’ble Apex
Court held at para Nos.3 and 4 as under:
“3. It is an admitted fact that Rs 8,81,085 (Rupees eight-
lakhs eighty-one thousand and eighty-five only) were
payable to the appellant by the respondent Government and
the said fact is very clearly admitted in the Letter dated 14-
7-2010, written by the Executive Engineer, Lower Division,
East Yamuna Canal, Muzaffarnagar. From the said amount
certain deductions are to be made, which are in the nature
of certain taxes including business tax, etc.
25
NV, J
wp_22568_2020 & cc_1580_2021
4. In view of the fact that the amount had been admitted
by the respondent Government, we feel that the said amount
should be paid without entering into any arbitration, etc.
and therefore, the said amount shall be paid to the appellant
within four months from today after deducting taxes, etc.
and along with the payment, details with regard to the
deductions made shall also be given to the appellant by the
respondent.”
2. In ABL International Ltd.’s case (3 supra), the Hon’ble Apex
Court held at para Nos.16, 17, 19, 27 and 55 as under:
“16. A perusal of this judgment though shows that a writ
petition involving serious disputed questions of facts which
requires consideration of evidence which is not on record,
will not normally be entertained by a court in the exercise of
its jurisdiction under Article 226 of the Constitution of India.
This decision again, in our opinion, does not lay down an
absolute rule that in all cases involving disputed questions
of fact the parties should be relegated to a civil suit. In this
view of ours, we are supported by a judgment of this Court
in the case of Gunwant Kaur v. Municipal Committee,
Bhatinda [(1969) 3 SCC 769] where dealing with such a
situation of disputed questions of fact in a writ petition this
Court held: (SCC p. 774, paras 14-16)
“14. The High Court observed that they will not
determine disputed question of fact in a writ petition. But
what facts were in dispute and what were admitted could
only be determined after an affidavit-in-reply was filed by
the State. The High Court, however, proceeded to dismiss
the petition in limine. The High Court is not deprived of its
jurisdiction to entertain a petition under Article 226 merely
because in considering the petitioner's right to relief
26
NV, J
wp_22568_2020 & cc_1580_2021
questions of fact may fall to be determined. In a petition
under Article 226 the High Court has jurisdiction to try
issues both of fact and law. Exercise of the jurisdiction is, it
is true, discretionary, but the discretion must be exercised
on sound judicial principles. When the petition raises
questions of fact of a complex nature, which may for their
determination require oral evidence to be taken, and on
that account the High Court is of the view that the dispute
may not appropriately be tried in a writ petition, the High
Court may decline to try a petition. Rejection of a petition in
limine will normally be justified, where the High Court is of
the view that the petition is frivolous or because of the
nature of the claim made dispute sought to be agitated, or
that the petition against the party against whom relief is
claimed is not maintainable or that the dispute raised
thereby is such that it would be inappropriate to try it in
the writ jurisdiction, or for analogous reasons.
15. From the averments made in the petition filed by
the appellants it is clear that in proof of a large number of
allegations the appellants relied upon documentary
evidence and the only matter in respect of which conflict of
facts may possibly arise related to the due publication of
the notification under Section 4 by the Collector.
16. In the present case, in our judgment, the High
Court was not justified in dismissing the petition on the
ground that it will not determine disputed question of fact.
The High Court has jurisdiction to determine questions of
fact, even if they are in dispute and the present, in our
judgment, is a case in which in the interests of both the
parties the High Court should have entertained the petition
and called for an affidavit-in-reply from the respondents,
and should have proceeded to try the petition instead of
relegating the appellants to a separate suit.”
27
NV, J
wp_22568_2020 & cc_1580_2021
17. The above judgment of Gunwant Kaur [(1969) 3 SCC
769] finds support from another judgment of this Court in
the case of Century Spg. and Mfg. Co. Ltd. v. Ulhasnagar
Municipal Council [(1970) 1 SCC 582] wherein this Court
held: (SCC p. 587, para 13)
“Merely because a question of fact is raised, the High
Court will not be justified in requiring the party to seek
relief by the somewhat lengthy, dilatory and expensive
process by a civil suit against a public body. The questions
of fact raised by the petition in this case are elementary.”
19. Therefore, it is clear from the above enunciation of
law that merely because one of the parties to the litigation
raises a dispute in regard to the facts of the case, the court
entertaining such petition under Article 226 of the
Constitution is not always bound to relegate the parties to a
suit. In the above case of Gunwant Kaur [(1969) 3 SCC 769]
this Court even went to the extent of holding that in a writ
petition, if the facts require, even oral evidence can be taken.
This clearly shows that in an appropriate case, the writ
court has the jurisdiction to entertain a writ petition
involving disputed questions of fact and there is no absolute
bar for entertaining a writ petition even if the same arises
out of a contractual obligation and/or involves some
disputed questions of fact.
27. From the above discussion of ours, the following legal
principles emerge as to the maintainability of a writ petition:
(a) In an appropriate case, a writ petition as against a
State or an instrumentality of a State arising out of a
contractual obligation is maintainable.
(b) Merely because some disputed questions of fact arise
for consideration, same cannot be a ground to refuse to
entertain a writ petition in all cases as a matter of rule.
28
NV, J
wp_22568_2020 & cc_1580_2021
(c) A writ petition involving a consequential relief of
monetary claim is also maintainable.
55. In Bal Krishna Agarwal (Dr) v. State of U.P. [(1995) 1
SCC 614 this Court held: (SCC p. 618, para 10)
“10. Having regard to the aforesaid facts and
circumstances, we are of the view that the High Court was
not right in dismissing the writ petition of the appellant on
the ground of availability of an alternate remedy under
Section 68 of the Act especially when the writ petition that
was filed in 1988 had already been admitted and was
pending in the High Court for the past more than 5 years.
Since the question that is raised involves a pure question of
law and even if the matter is referred to the Chancellor
under Section 68 of the Act it is bound to be agitated in the
court by the party aggrieved by the order of the Chancellor,
we are of the view that this was not a case where the High
Court should have non-suited the appellant on the ground
of availability of an alternative remedy. We, therefore,
propose to go into the merits of the question regarding inter
se seniority of the appellant and Respondents 4 and 5. We
may, in this context, mention that Respondent 4 has
already retired in January 1994.””
3. In Surya Constructions v. State of Uttar Pradesh
10
,
the Hon’ble Apex Court held at para Nos.3 and 4 as under:
“3. It is clear, therefore, from the aforesaid order dated
22-3-2014 that there is no dispute as to the amount that
has to be paid to the appellant. Despite this, when the
appellant knocked at the doors of the High Court in a writ
petition being Writ Civil No. 25216 of 2014, the impugned
judgment dated 2-5-2014 [ Surya Construction v. State of
10
(2019) 16 SCC 794
29
NV, J
wp_22568_2020 & cc_1580_2021
U.P., (2014 SCC OnLine All 6071)] dismissed the writ
petition stating that disputed questions of fact arise and that
the amount due arises out of a contract. We are afraid the
High Court was wholly incorrect inasmuch as there was no
disputed question of fact. On the contrary, the amount
payable to the appellant is wholly undisputed. Equally, it is
well settled that where the State behaves arbitrarily, even in
the realm of contract, the High Court could interfere under
Article 226 of the Constitution of India (ABL International
Ltd. v. Export Credit Guarantee Corpn. of India Ltd. [(2004) 3
SCC 553])
4. This being the case and the work having been
completed long back in 2009, we direct Uttar Pradesh Jal
Nigam to make the necessary payment within a period of
four weeks from today. Given the long period of delay,
interest @ 6% p.a. may also be awarded.”
11. In view of the foregoing discussion, the Writ Petition is
disposed of with a direction to the respondents to pay the
remaining balance amount as per the counter affidavit of the 3
rd
respondent herein within a period of six (6) weeks from the date
of receipt of a copy of this order.
12. C.C.No.1580 of 2021 is filed by the petitioner complaining
that the order of this Court dated 16.08.2021 is not complied
with by the respondents. Hence, the respondents are liable for
punishment under Sections 10 and 12 of the Contempt of
Courts Act, whereas the respondents filed detailed counters,
30
NV, J
wp_22568_2020 & cc_1580_2021
wherein they specifically and categorically stated that the
interim order of this Court dated 16.08.2021 has been complied
with and therefore, the contempt case may be closed.
13. For better appreciation, it is appropriate to extract the
order of this Court dated 16.08.2021 hereunder:
“On instructions, the learned Government Pleader for
Panchayat Raj appearing for respondent Nos.1 and 2
submits that up to 04.08.2021, Rs.1,15,09,168/- was paid
to respondent No.3, which is payable to the petitioner in
turn by respondent No.3. Payment of remaining amount is
under process.
Sri Alapati Vivekananda, learned counsel for respondent
No.3, submits that no instructions with regard to the
payment received by respondent No.3 and sought time.
In view of the above, respondent No.3 is directed to
release the amounts in favour of the petitioner which they
have received from respondent Nos.1 and 2 forthwith.
Respondent Nos.1 and 2 are directed to take steps to
release the balance amount payable to the petitioner within
a reasonable period but not beyond two weeks from today.”
14. The counters filed by the 2
nd
respondent as well as the 3
rd
respondent which contended that as per the directions of this
Court that is to release the balance amount pursuant to the
Memo dated 19.05.2020 issued by the 2
nd respondent, under
which the 2
nd respondent directed the other respondents to take
steps for payment of Rs.6,64,46,338/-, the said amount has
31
NV, J
wp_22568_2020 & cc_1580_2021
been paid in two occasions before filing of the writ petition and
after filing of the writ petition.
15. In view of the payment of amount by the respondents as
prayed by the petitioner in his prayer, and the petitioner is not
quantified the amount payable other than the amount
mentioned by the 2
nd
respondent in its Memo dated 19.05.2020,
therefore, it cannot be said that the respondents did not comply
with the orders of this Court in the absence of quantifying of
amount to be received by the petitioner. Therefore, the interim
order of this Court dated 06.08.2021 has been complied with.
16. Accordingly, the Contempt Case is closed. There shall be
no order as to costs.
As a sequel, miscellaneous applications pending, if any,
shall stand closed.
______________________________________
VENKATESWARLU NIMMAGADDA, J
Date: 06.09.2022
Ivd
Note: L.R. copy to be marked
32
NV, J
wp_22568_2020 & cc_1580_2021
THE HON’BLE SRI JUSTICE VENKATESWARLU NIMMAGADDA
WRIT PETITION No.22568 of 2020
And
CONTEMPT CASE No.1580 of 2021
Date: 06.09.2022
Ivd
Legal Notes
Add a Note....