As per case facts, an objection was raised under Section 16 of the Arbitration and Conciliation Act, 1996, stating that various agreements between the parties were insufficiently stamped. The Arbitrator ...
2026 INSC 566
Civil Appeal arising out of SLP (C) No.27534 of 2025 Page 1 of 39
REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO. OF 2026
(@ SLP (C) NO.27534 OF 2025)
M/S TARINI PRASAD MOHANTY APPELLANT
VERSUS
M/S SUNFLAG IRON AND STEEL RESPONDENT
COMPANY LIMITED
J U D G M E N T
ATUL S. CHANDURKAR, J
1. An objection raised under Section 16 of the Arbitration
and Conciliation Act, 1996
1 that various agreements executed
between the parties were insufficiently stamped was turned
down by the learned Arbitrator. A challenge was raised to the
said order by the objector through a writ petition preferred
under Articles 226 and 227 of the Constitution of India
2. A
learned Single Judge of the High Court entertained the writ
1
For short, ‘the A and C Act’
2
For short, ‘the Constitution’
Civil Appeal arising out of SLP (C) No.27534 of 2025 Page 2 of 39
petition and upheld the objection raised under Section 16 of
the A and C Act. Impounding of the said agreements was
directed. The other party challenged this decision in a writ
appeal that was allowed by the Division Bench of the High
Court. The objector, being aggrieved, has approached this
Court.
2. Leave granted.
3. Two issues arise for consideration in the present appeal,
namely (a) whether in the exercise of jurisdiction under
Articles 226 and 227 of the Constitution, a challenge to an
order passed under Section 16 of the A and C Act ought to
have been entertained, especially when the Arbitrator was
seized of the arbitration proceedings? and (b) the learned
Single Judge having upheld the challenge to an order passed
under Section 16 of the A and C Act, whether the Division
Bench was right in interfering with such exercise of
jurisdiction and setting aside that order?
4. It is not necessary to refer to the facts in great detail.
Suffice it to observe that an agreement for sale of iron ore
came to be executed on 12.02.2004 between the appellant-
Civil Appeal arising out of SLP (C) No.27534 of 2025 Page 3 of 39
M/s Tarini Prasad Mohanty
3 and the respondent-M/s Sunflag
Iron and Steel Company Limited
4. Supplementary agreements
were also entered into between the parties thereafter. During
the course of their contractual engagement, disputes arose
between the parties. In accordance with the arbitration clause
contained in the agreement for sale, these disputes were
referred to a Sole Arbitrator. SISCO as claimant made various
claims against the mine owner, who in turn filed a counter
claim against SISCO. On 05.02.2024 during the course of the
arbitration proceedings, the mine owner filed an application
under Section 16 of the A and C Act. It was stated therein that
the agreement for sale dated 12.02.2004 alongwith various
supplementary agreements had been insufficiently stamped.
According to the mine owner, the contract between the parties
was in the nature of ‘conveyance’ and, hence, it was necessary
that the agreements had to be stamped in accordance with
Article 23 of Schedule I to the Indian Stamp Act, 1899
5. It was,
thus, stated that unless the agreements were impounded and
3
For short, ‘the mine owner’
4
For short, ‘SISCO’
5
For short, ‘the Stamp Act’
Civil Appeal arising out of SLP (C) No.27534 of 2025 Page 4 of 39
properly stamped, the arbitration proceedings could not
continue.
5. The claimant filed its reply to the aforesaid objection and
took the stand that the agreements between the parties had
been duly stamped and there was no need to impound the
same. It was further stated that such objection had not been
raised when the counter claim was filed and it was not liable
to be entertained as having been raised belatedly.
The learned Arbitrator after hearing both sides by his
order dated 30.05.2024 turned down the said objection and
held that the agreement between the parties was “ an
agreement to sell” and not “conveyance” or sale. Since the
agreement had been properly stamped in accordance with
Article 5(c) of Schedule I to the Stamp Act, the objection was
rejected.
6. The mine owner being aggrieved by the aforesaid order
challenged the same by filing a writ petition under Articles
226 and 227 of the Constitution of India before the High Court
Civil Appeal arising out of SLP (C) No.27534 of 2025 Page 5 of 39
of Orissa
6. The prayers made in the writ petition read as
under:
“A) Why the Impugned Order dated 30.05.2024 vide Annexure 1,
passed by the Ld. Arbitral Tribunal shall not be quashed, being
illegal, arbitrary and contrary to settled principles of law;
B) Why directions shall not be issued to the Ld. Sole Arbitrator
directing the Respondent to produce the original Sale Agreement
before the concerned Collector for impounding the same for the
determination of the deficit stamp duty and payment of the same
by the Respondent;
C) Why the arbitral proceedings in the matter of arbitration
between “Sunflag Iron and Steel Co. Ltd. Vs. Tarini Prasad
Mohanty” shall not be kept in abeyance until the Respondent
rectifies the defect as per the law prescribed procedure in law;
D) Why such other appropriate order/orders as this Hon’ble Court
may deem fit and proper shall not be passed;”
7. SISCO opposed the writ petition by urging that the order
passed by the learned Arbitrator under Section 16 of the A
and C Act during pendency of the arbitration proceedings
could not be challenged in writ jurisdiction. It stated that at
the conclusion of the arbitration proceedings, the remedy
provided under Section 34 of the A and C Act could be availed.
It was further stated that the conclusion arrived at by the
learned Arbitrator that the agreements had been properly
stamped was correct and this did not call for any interference.
6
For short, ‘the High Court’
Civil Appeal arising out of SLP (C) No.27534 of 2025 Page 6 of 39
8. A learned Single Judge of the High Court by the
judgment dated 25.02.2025 considered the question as to the
maintainability of a writ petition wherein a challenge was
raised to an interlocutory order passed by the Arbitral
Tribunal. He, thereafter, examined the situations in which an
order passed under Section 16 of the A and C Act could be
interfered with in exercise of writ jurisdiction. After finding
that an ‘exceptional’ case for interference had been made out,
the learned Single Judge proceeded to hold that unless proper
stamp duty was paid on the sale agreement, the learned
Arbitrator did not have jurisdiction to arbitrate the disputes.
On that basis, the order passed under Section 16 of the A and
C Act came to be set aside and the Arbitral Tribunal was
directed to impound the agreements to enable them to be duly
stamped in accordance with Article 23, Schedule I(b) to the
Stamp Act. Various directions indicating the manner in which
such impounding was to be undertaken were also given. The
writ petition preferred by the mine owner, thus, came to be
allowed.
9. The claimant being aggrieved by the exercise of
jurisdiction by the learned Single Judge preferred writ appeal
Civil Appeal arising out of SLP (C) No.27534 of 2025 Page 7 of 39
under Clause 10 of the Letters Patent Act, 1992. The Division
Bench of the High Court after referring to various decisions of
this Court was of the view that the power of judicial review
under Article 226 of the Constitution as well as the power
superintendence over courts and tribunals under Article 227
of the Constitution were integral parts of the basic structure
which could not be curtailed and/or abridged under any
legislative fiat. It further held that an order upholding the
jurisdiction of the Arbitrator was capable of being challenged
under Section 34 of the A and C Act at the conclusion of the
arbitration proceedings. It found that the exercise of
determining whether the agreements were properly stamped
required an interpretation of the contract between the parties.
This was required to be done on the basis of evidence to be
adduced by the parties. It was therefore desirable that the writ
court ought not to go into the question involving
interpretation of the contract. On that basis, it held that the
view taken by the learned Arbitrator could not be said to be
perverse or that the Arbitral Tribunal lacked inherent
jurisdiction to entertain the arbitration proceedings. The
Division Bench, thus, set aside the judgment of the learned
Single Judge holding the same to be in excess of jurisdiction.
Civil Appeal arising out of SLP (C) No.27534 of 2025 Page 8 of 39
The mine owner being aggrieved by this adjudication has
preferred the present appeal.
10. Mr. Shashank Garg, learned Senior Advocate for the
appellant in support of the appeal made the following
submissions:
a) The writ appeal preferred by SISCO was not
maintainable:
It was urged that though the mine owner referred to
Articles 226 and 227 of the Constitution in the writ petition
preferred by him, the said writ petition was in fact one under
Article 227 of the Constitution alone. This was clear from the
tenor of the writ petition and the grounds raised therein. The
mine owner had invoked supervisory jurisdiction of the High
Court under Article 227 of Constitution and therefore, the writ
appeal preferred by SISCO was not maintainable. The
directions issued in the order passed by the learned Single
Judge as regards impounding of the documents in question
would not result in converting the proceedings into one under
Article 226 of the Constitution. In this regard, the learned
Senior Advocate placed reliance on the decisions in Umaji
Keshao Meshram and others Vs. Radhikabai w/o Anandrao
Civil Appeal arising out of SLP (C) No.27534 of 2025 Page 9 of 39
Banapurkar and another
7, Life Insurance Corporation of
India Vs. Nandini J. Shah and others
8 and Ram Kishan
Fauji Vs. State of Haryana and others
9.
b) The writ petition preferred by the mine owner for
challenging the order passed under Section 16 of the A and C
Act was maintainable:
It was submitted that in exceptional cases and on
grounds of perversity, an order passed by the Arbitral
Tribunal under Section 16 of the A and C Act would be
maintainable. The fact that the learned Single Judge set aside
the order passed under Section 16 of the A and C Act on the
ground that the same was ‘grossly erroneous and perverse’
justified the invocation of such jurisdiction by the mine
owner. Since an exceptional case had been made out by the
mine owner, jurisdiction under Article 227 of the Constitution
was rightly exercised by the learned Single Judge.
c) The agreement dated 12.02.2004 and the
supplementary agreements constituted ‘conveyance’:
It was submitted by referring to the provisions of Section
2(10) of the Stamp Act and Section 4(4) of the Sale of Goods
Act, 1930
10 that on a reading of the agreements in their
7
1986 INSC 41
8
2018 INSC 178
9
2017 INSC 238
10
For short, ‘SoG Act’
Civil Appeal arising out of SLP (C) No.27534 of 2025 Page 10 of 39
entirety, it was clear that the transaction envisaged therein
was one of sale. Reference was made to various clauses of the
agreement dated 12.02.2004 to substantiate this contention.
The nomenclature of the said document was not relevant but
its substance was required to be seen. The learned Arbitrator
having failed to determine the exact nature of the agreement
dated 12.02.2004 and the supplementary agreements , the
learned Single Judge was justified in concluding that the
transactions entered into amounted to ‘conveyance’. Reliance
was placed on the decision in State of Uttaranchal and
others Vs. M/s Khurana Brothers
11 in that regard.
d) Failure of the Arbitral Tribunal to impound the various
agreements resulted in a jurisdictional error:
It was submitted that unless the agreement for sale
between the parties was properly stamped, the learned
Arbitrator did not have jurisdiction to arbitrate the disputes.
For determining the true nature of the transaction, t he
agreement for sale dated 12.02.2004, various supplementary
agreements and the eighty-nine purchase orders ought to
have been taken into consideration. They all were relevant for
determining the issue of proper stamp duty being paid on the
11
2010 INSC 746
Civil Appeal arising out of SLP (C) No.27534 of 2025 Page 11 of 39
agreements. The Arbitral Tribunal erred in failing to take the
entire material into consideration before arriving at its
conclusion. The learned Single Judge rightly considered all
the relevant material in this regard and found that the
agreements were insufficiently stamped. Unless proper stamp
duty was duly paid, the learned Arbitrator could not have
proceeded with the arbitration proceedings. The Division
Bench, thus, erred in interfering with the well reasoned order
passed by the learned Single Judge.
e) The interest of revenue ought to be borne in mind while
adjudicating the present dispute:
It was submitted that non-payment of stamp duty or
insufficiency of stamp duty results in a loss to the public
exchequer. For an instrument to be admitted in evidence
and/or acted upon in law, the document ought to have been
correctly stamped. Reference was made to the judgment of the
Constitution Bench in Re: Interplay Between Arbitration
Agreements Under The Arbitration And Conciliation Act,
1996 and The Indian Stamp Act, 1899
12. Moreover, the
scope for interference under Section 34 of the A and C Act was
12
2023 INSC 1066
Civil Appeal arising out of SLP (C) No.27534 of 2025 Page 12 of 39
limited as reiterated in Gayatri Balasamy Vs. M/s ISG
Novasoft Technologies Limited
13.
It was, thus, submitted on the aforesaid grounds that
the judgment of the Division Bench impugned herein was
liable to be set aside and order passed by the learned Single
Judge impounding the agreement dated 12.02.2004 deserved
to be upheld.
11. Per contra, Mr. Gopal Subramanium, Mr. N.K.Mody and
Ms. Malvika Trivedi, learned Senior Advocates for the
respondent supported the judgment of the Division Bench and
urged as under:
a) The writ appeal filed by SISCO was maintainable:
It was submitted that the writ petition filed by the mine
owner was under Articles 226 and 227 of the Constitution.
Substantive reliefs in the nature of writs had been prayed for
and no supervisory direction had been sought. The learned
Single Judge after setting aside the order passed under
Section 16 of the A and C Act issued a direction to the
Collector to determine the deficient stamp duty. Even
otherwise, the writ petition having been filed invoking Articles
13
2025 INSC 605
Civil Appeal arising out of SLP (C) No.27534 of 2025 Page 13 of 39
226 and 227 of the Constitution, the writ appeal would be
maintainable by treating the writ petition as filed under Article
226 of the Constitution. Reliance was placed on the decision
in Umaji Keshao Meshram (supra) to support this submission.
b) The order passed by the learned Arbitrator under
Section 16 of the A and C Act was not liable to be interfered
with:
The learned Single Judge erred in interfering with the
order passed by the learned Arbitrator under Section 16 of the
A and C Act. It was not a case of complete lack of inherent
jurisdiction on the part of the learned Arbitrator so as to
enable writ jurisdiction being invoked. The Constitution
Bench in Re: Interplay (supra) having held that the issue as to
stamping of a document was one that fell within the ambit of
the Arbitral Tribunal, the decision taken by the learned
Arbitrator under Section 16 of the A and C Act was thus
within its jurisdiction. Merely by stating that the
circumstances were ‘exceptional’, writ jurisdiction could not
have been exercised. Assuming that the order passed by the
learned Arbitrator under Section 16 of the A and C Act was
erroneous in law, the same could have been challenged under
Section 34 of the A and C Act at the conclusion of the
proceedings as provided under Section 16(6).
Civil Appeal arising out of SLP (C) No.27534 of 2025 Page 14 of 39
c) The agreement dated 12.0 2.2004 and the
supplementary agreements did not amount to ‘conveyance’
under Section 2(10) of the Stamp Act:
It was submitted that on a complete reading of the entire
agreement dated 12.0 2.2004 and the supplementary
agreements, it was clear that it envisaged a future sale of iron
ore by the mine owner to SISCO. Under the said agreements,
the goods were neither ascertained nor were they in a
deliverable state. Reference was made to various clauses in
the agreements to substantiate this contention. It was further
urged that the aspect of interpretation of a document touched
the merits of the dispute, consideration of which was yet to be
undertaken by the learned Arbitrator. This Court, therefore,
would not undertake that exercise at this stage. The decision
in M/s Khurana Brothers (supra) relied upon before the
learned Single Judge was sought to be distinguished. It was
also submitted that various purchase orders were sought to
be relied upon by the mine owner for the first time in the writ
petition before the learned Single Judge. In any event, the
transaction in question could not be treated to be
‘conveyance’.
It was, thus, submitted that the Division Bench of the
High Court having rightly set aside the order passed by the
Civil Appeal arising out of SLP (C) No.27534 of 2025 Page 15 of 39
learned Single Judge, no interference was called for and the
appeal was liable to be dismissed.
12. We have heard the learned Senior Advocates for the
parties at length and with their assistance, we have also
perused the relevant documentary material placed on record.
At the outset, it would be necessary to consider the objection
raised on behalf of the mine owner that the writ appeal
preferred by SISCO was not maintainable as the learned
Single Judge had merely exercised jurisdiction under Article
227 of the Constitution while setting aside the order passed
under Section 16 of the A and C Act. According to the mine
owner, since a challenge was raised to an order passed by the
learned Arbitrator under Section 16 of the A and C Act,
notwithstanding the invocation of Articles 226 and 227 of the
Constitution in the writ petition, the jurisdiction exercised by
the learned Single Judge was only under Article 227 of the
Constitution.
We are not in a position to accept this submission for
more than one reason. Perusal of the writ petition as preferred
by the mine owner including the prayers made therein makes
it clear that the writ petition was preferred under Articles 226
Civil Appeal arising out of SLP (C) No.27534 of 2025 Page 16 of 39
and 227 of the Constitution. Besides the cause title of the said
writ petition, the pleadings therein, especially paragraph 27
indicates that the mine owner sought to invoke the
extraordinary jurisdiction of the High Court under Article 226
of the Constitution. Further, the learned Single Judge after
referring to various decisions cited before him by the parties
observed in paragraph 60 as under:
“60. A perusal of the above-mentioned decisions, shows that
the following principles are well settled, in respect of the scope
of interference under Article 226/227 in challenges to orders by
an arbitral tribunal including orders passed under Section 16
of the Act:
(i). An arbitral tribunal is a 'tribunal’ against which a petition
under Article 226/227 would be maintainable;
(ii). The non-obstante clause in section 5 of the Act does not
apply in respect of exercise of powers under Article 227 which
is a Constitutional provision;
(iii). For interference under Article 226/227, there have to be
'exceptional circumstances';
(iv). Though interference is permissible, unless and until the
order is so perverse that it is patently lacking in inherent
jurisdiction, the writ court would not interfere;
(v). Interference is permissible only if the order is completely
perverse i.e., that the perversity must stare in the face;
(vi). High Courts ought to discourage litigation which
necessarily interfere with the arbitral process;
(vii). Excessive judicial interference in the arbitral process is not
encouraged;
(viii). It is prudent not to exercise jurisdiction under Article
226/227;
(ix). The power should be exercised in 'exceptional rarity' or if
there is 'bad faith' which is shown;
Civil Appeal arising out of SLP (C) No.27534 of 2025 Page 17 of 39
(x). Efficiency of the arbitral process ought not to be allowed to
diminish and hence interdicting the arbitral process should be
completely avoided.”
Thereafter, on examining the agreement for sale dated
12.02.2004 as well as the second agreement dated
09.01.2011, the learned Single Judge was of the view that the
challenge raised by the mine owner could be treated to be
‘exceptional’ and writ jurisdiction ought to be exercised in the
matter.
13. In this regard, we may refer to the decision of this Court
in Lokmat Newspapers Pvt. Ltd . Vs. Shankar Prasad
14
wherein after referring to the decision in Umaji Keshao
Meshram and others (supra), it was observed as under:-
“It is, therefore, obvious that the Writ Petition invoking
jurisdiction of the High Court both under Articles
226 and 227 of the Constitution had tried to make out a case
for High Court's interference seeking issuance of an appropriate
Writ of Certiorari under Article 226 of the Constitution of India.
Basic averments for invoking such jurisdiction were already
pleaded in the Writ Petition for High Court's consideration. It is
true, as submitted by learned counsel for the appellant, that the
order of the learned Single Judge nowhere stated that the Court
was considering the Writ Petition under Article 226 of the
Constitution of India. It is equally true that the learned Single
Judge dismissed the Writ Petition by observing that the Courts
below had appreciated the contentions and rejected the
complaint. But the said observation of the learned Single Judge
did not necessarily mean that the learned Judge did not inclined
to interfere under article 227 of the Constitution of India only.
The said observation equally supports the conclusion that the
14
1999 INSC 279
Civil Appeal arising out of SLP (C) No.27534 of 2025 Page 18 of 39
learned Judge was not inclined to interfere under Articles
226 and 227. As seen earlier, that he was considering the
aforesaid Writ Petition moved under Articles 226 as well as 227
of the Constitution of India. Under these circumstances, it is not
possible to agree with the contention of learned counsel for the
appellant that the learned Single Judge had refused to interfere
only under Article 227 of the Constitution of India when he
dismissed the Writ Petition of the respondent. In this
connection, it is profitable to have a look at the decision of this
Court in the case of Umaji Keshao Meshram and Others vs.
Radhikabai, widow of Anandrao Banapurkar and Anr., [(1986)
Supp SCC 401]. In that case O.Chinnappa Reddy and
D.P.Madon, JJ., considered the very same question in the light
of clause 15 of the Letters Patent Appeal of the Bombay High
Court. Madon J., speaking for the Court in para 107 of the
Report at page 473, made the following pertinent observations :
“Petitions are at times filed both under Articles
226 and 227 of the Constitution. The case of Hari Vishnu
Kamath v. Syed Ahmad Ishaque before this Court was of
such a type. Rule 18 provides that where such petitions
are filed against orders of the tribunals or authorities
specified in Rule 18 of Chapter XVII of the Appellate Side
Rules or against decrees or orders of courts specified in
that rule, they shall be heard and finally disposed of by a
Single Judge. The question is whether an appeal would lie
from the decision of the Single Judge in such a case. In
our opinion, where the facts justify a party in filing an
application either under Article 226 or 227 of the
Constitution, and the party chooses to file his application
under both these articles, in fairness and justice to such
party and in order not to deprive him of the valuable right
of appeal the court ought to treat the application as being
made under Article 226, and if in deciding the matter, in
the final order the court gives ancillary directions which
may pertain to Article 227, this ought not to be held to
deprive a party of the right of appeal under Clause 15 of
the Letters Patent where the substantial part of the order
sought to be appealed against is under Article 226. Such
was the view taken by the Allahabad High court in Aidal
Singh v. Karan Singh and by the Punjab High Court in Raj
Kishan Jain v. Tulsi Dass and Barham Dutt v. Peoples' Co-
operative Transport Society Ltd., New Delhi and we are in
agreement with it.”
The aforesaid decision squarely gets attracted on the facts of
the present case. It was open to the respondent to invoke
jurisdiction of the High Court both under Articles
Civil Appeal arising out of SLP (C) No.27534 of 2025 Page 19 of 39
226 and 227 of the Constitution of India. Once such
jurisdiction was invoked and when his Writ Petition was
dismissed on merits, it cannot be said that the learned Single
Judge had exercised his jurisdiction only under Article 226 of
the Constitution of India. This conclusion directly flows from the
relevant averments made in the Writ Petition and the nature of
jurisdiction invoked by the respondent as noted by the learned
Single Judge in his judgment, as seen earlier. Consequently, it
could not be said that Clause 15 of the Letters Patent was not
attracted for preferring appeal against the judgment of learned
Single Judge…..”
[emphasis supplied by us]
14. In our view, the observations referred to above are
clearly applicable to the facts of the present case. The mine
owner having invoked jurisdiction under Articles 226 and 227
of the Constitution and the learned Single Judge having
exercised jurisdiction without clearly specifying any
particular Article, it cannot be said that what was exercised
by the learned Single Judge was jurisdiction only under
Article 227 of the Constitution and not under Article 226 of
the Constitution. Moreover, the mine owner himself having
invoked both Articles and having succeeded before the
learned Single Judge, in fairness, he ought not now contend
that the writ petition preferred by him was only under Article
227 of the Constitution so as to question the maintainability
of the writ appeal.
Civil Appeal arising out of SLP (C) No.27534 of 2025 Page 20 of 39
We would reiterate what was held by this Court in Sh
Jogendrasinhji Vijaysinghji Vs. State of Gujarat and
others
15 in paragraph 25:
“25. From the aforesaid pronouncements, it is graphically clear
that maintainability of a letters patent appeal would depend upon
the pleadings in the writ petition, the nature and character of the
order passed by the learned Single Judge, the type of directions
issued regard being had to the jurisdictional perspectives in the
constitutional context. Barring the civil court, from which order
as held by the three-Judge Bench in Radhey Shyam (supra) that
a writ petition can lie only under Article 227 of the Constitution,
orders from tribunals cannot always be regarded for all purposes
to be under Article 227 of the Constitution. Whether the learned
Single Judge has exercised the jurisdiction under Article 226 or
under Article 227 or both, needless to emphasise, would depend
upon various aspects that have been emphasised in the
aforestated authorities of this Court. There can be orders passed
by the learned Single Judge which can be construed as an order
under both the articles in a composite manner, for they can co-
exist, coincide and imbricate. We reiterate it would depend upon
the nature, contour and character of the order and it will be the
obligation of the Division Bench hearing the letters patent appeal
to discern and decide whether the order has been passed by the
learned Single Judge in exercise of jurisdiction under Article
226 or 227 of the Constitution or both. The Division Bench would
also be required to scrutinize whether the facts of the case justify
the assertions made in the petition to invoke the jurisdiction
under both the articles and the relief prayed on that
foundation….”
We are, therefore, of the view that the learned Single
Judge having entertained the writ petition that was preferred
under Articles 226 and 227 of the Constitution and having
granted relief to the mine owner, the writ appeal preferred by
15
2015 INSC 485
Civil Appeal arising out of SLP (C) No.27534 of 2025 Page 21 of 39
SISCO was maintainable. SISCO, therefore, cannot be non-
suited on this count.
15. We further find from the proceedings in the writ appeal
before the Division Bench that the parties did not join issue
on the maintainability of the writ appeal. Rather the contest
was on the scope of jurisdiction under Articles 226 and 227
of the Constitution and the legal propriety of the learned
Single Judge exercising such jurisdiction. In paragraphs 1, 4
and 5 of the ‘Note for Writ Appeal’ submitted by the mine
owner, it has been stated as under:
“I. Whether a writ court can interfere with the order passed
by the arbitral tribunal in exercise of its powers under Section
16 of the Arbitration and Conciliation Act
1. The test propounded by the court for a challenge of an
order of the arbitral tribunal (section 16 of the Arbitration and
Conciliation Act 1996) by way of a writ petition under Article
226/227 is perverse/exceptional circumstance namely: patent
lack of inherent jurisdiction.”
4. In relation to jurisdiction of a writ court challenging a
Section 16 order of an arbitral tribunal, the Hon’ble Supreme
Court has upheld the position in Deep Industries, in the case of
Punjab State Power Corporation Limited V. EMTA Coal Limited
and anr. (2020) 17 SCC 93, in paragraph 4 as follows:
“4. We are of the view that a foray to the writ court from
a Section 16 application being dismissed by the
arbitrator can only be if the order passed is so
perverse that the only possible conclusion is that
there is a patent lack in inherent jurisdiction. A patent
lack of inherent jurisdiction requires no argument
whatsoever – it must be the perversity of the order that
must stare one in the face.”
Civil Appeal arising out of SLP (C) No.27534 of 2025 Page 22 of 39
5. The order passed by the single judge squarely falls within
the parameters.”
16
The Division Bench, therefore, observed in paragraph 8
of the impugned judgment as under:
“8. Learned Counsels appearing for the respective parties
made extensive arguments not only on the nature of an
agreement for the purpose of stamp duty leviable thereupon but
also on the scope and jurisdiction of the High Court conferred
under Article 226/227 of the Constitution of India.”
It, thus, becomes clear that maintainability of the writ
appeal was not specifically questioned by the mine owner
before the Division Bench.
16. Having found that the writ appeal preferred by SISCO
was maintainable, it would now be necessary to consider
whether the Division Bench was justified in entertaining the
same and setting aside the order passed by the learned Single
Judge. For doing so, a brief reference to the adjudication by
the learned Arbitrator under Section 16 of the A and C Act
would be necessary. During the course of arbitration
proceedings, an objection was raised by the mine owner on
05.02.2024 that the agreement for sale dated 12.02.2004 as
16
(See pages 299 and 300, Annexure R-7 of counter affidavit by SISCO)
Civil Appeal arising out of SLP (C) No.27534 of 2025 Page 23 of 39
well as the supplementary agreements executed between the
parties were insufficiently stamped. Unless the said
instruments were impounded and adequate stamp duty was
paid, the arbitration proceedings could not proceed. The
learned Arbitrator considered the said objection. After
referring to the agreements in question including its relevant
clauses, he came to the conclusion that the agreements could
not be treated to be ‘conveyance’ or sale of movable property.
The application under Section 16 of the A and C Act was,
thus, dismissed on 30.05.2024.
17. A perusal of the aforesaid adjudication would prima facie
indicate that on consideration of various agreements between
the parties and the relevant clauses therein, the learned
Arbitrator concluded that the same were merely in the nature
of an agreement to sell and not ‘conveyance’. This decision
was arrived at after examining and prima facie interpreting
the agreements in question. The learned Single Judge while
considering the challenge to the said order re-examined the
said agreements and clauses therein. He undertook the
exercise of determining the true intention of the parties
Civil Appeal arising out of SLP (C) No.27534 of 2025 Page 24 of 39
behind executing the said agreements. In fact, in paragraph
70 of his judgment, it has been observed as under:
“70. Now, this court shall embark on a perusal of the true
intention of the Parties by examining the Agreement itself as it
is settled in law, that the mere title of the document would not
be indicative of the true nature of the document itself…..”
Thereafter, he concluded in paragraph in 75 of his
judgment that the intention of the parties made it clear that
the minerals excavated from the mines of SISCO would stand
vested in the mine owner for a period of ten years for which
the consideration had already been fixed and paid. He,
therefore, concluded that there was indeed conveyance of the
goods in question. The conclusion of the learned Arbitrator as
recorded in paragraphs 38 to 40 of his order was held to be
grossly erroneous and perverse.
It is, thus, evident that while considering the challenge
raised by the mine owner to the order passed by the learned
Arbitrator under Section 16 of the A and C Act, the learned
Single Judge entered into the merits of the dispute and
thereafter concluded that the transactions were in the nature
of ‘conveyance’.
Civil Appeal arising out of SLP (C) No.27534 of 2025 Page 25 of 39
18. At this stage, it would be necessary to refer to the
decision of the Constitution Bench in M/s S.B.P. and
Company Vs. M/s Patel Engineering Ltd. and another
17
. In
paragraphs 6, 44 and 45 of the majority judgment, it has been
held as under:
“6. …….Chapter IV deals with the jurisdiction of Arbitral
Tribunals. Section 16 deals with the competence of an Arbitral
Tribunal, to rule on its jurisdiction. The Arbitral Tribunal may rule
on its own jurisdiction, including ruling on any objection with
respect to the existence or validity of the arbitration agreement. A
person aggrieved by the rejection of his objection by the Tribunal
on its jurisdiction or the other matters referred to in that Section,
has to wait until the award is made to challenge that decision in
an appeal against the arbitral award itself in accordance with
Section 34 of the Act. But an acceptance of the objection to
jurisdiction or authority, could be challenged then and there,
under Section 37 of the Act.”
xxxxxxxx
“44. It is seen that some High Courts have proceeded on the
basis that any order passed by an arbitral tribunal during
arbitration, would be capable of being challenged under Article 226
or 227 of the Constitution of India. We see no warrant for such an
approach. Section 37 makes certain orders of the arbitral tribunal
appealable. Under Section 34, the aggrieved party has an avenue
for ventilating his grievances against the award including any in-
between orders that might have been passed by the arbitral
tribunal acting under Section 16 of the Act. The party aggrieved by
any order of the arbitral tribunal, unless has a right of appeal
under Section 37 of the Act, has to wait until the award is passed
by the Tribunal. This appears to be the scheme of the Act. The
arbitral tribunal is after all, the creature of a contract between the
parties, the arbitration agreement, even though if the occasion
arises, the Chief Justice may constitute it based on the contract
between the parties. But that would not alter the status of the
arbitral tribunal. It will still be a forum chosen by the parties by
agreement. We, therefore, disapprove of the stand adopted by some
of the High Courts that any order passed by the arbitral tribunal
is capable of being corrected by the High Court under Article 226
17
2005 INSC 526
Civil Appeal arising out of SLP (C) No.27534 of 2025 Page 26 of 39
or 227 of the Constitution of India. Such an intervention by the
High Courts is not permissible.
45. The object of minimising judicial intervention while the
matter is in the process of being arbitrated upon, will certainly be
defeated if the High Court could be approached under Article 227
or under Article 226 of the Constitution against every order made
by the Arbitral Tribunal. Therefore, it is necessary to indicate that
once the arbitration has commenced in the Arbitral Tribunal,
parties have to wait until the award is pronounced unless, of
course, a right of appeal is available to them under Section 37 of
the Act even at an earlier stage.”
[emphasis supplied by us]
The object of minimal judicial intervention and
availability of a remedy under Section 34 of the A and C Act
has been highlighted.
19. As regards challenge to the rejection of an objection
raised under Section 16 of the A and C Act is concerned, this
Court in M/s Deep Industries Ltd. Vs. Oil and Natural Gas
Corporation Limited and another
18 held in paragraph 16 as
under:
“16. …….The drill of Section 16 of the Act is that where a
Section 16 application is dismissed, no appeal is provided and the
challenge to the Section 16 application being dismissed must await
the passing of a final award at which stage it may be raised under
Section 34. What the High Court has done in the present case is
to invert this statutory scheme by going into exactly the same
matter as was gone into by the arbitrator in the Section 16
application, and then decided that the two-year ban/blacklisting
was no part of the notice for arbitration issued on 2-11-2017, a
finding which is directly contrary to the finding of the learned
18
2019 INSC 1299
Civil Appeal arising out of SLP (C) No.27534 of 2025 Page 27 of 39
arbitrator dismissing the Section 16 application. For this reason
alone, the judgment under appeal needs to be set aside.”
Yet again in Bhaven Construction through Authorised
Signatory Premjibhai K. Shah Vs. Executive Engineer,
Sardar Sarovar Narmada Nigam Limited and another
19, it
was held in paragraphs 11, 15, 16 and 25 as under:-
“11. We need to note that the Arbitration Act is a code in itself.
This phrase is not merely perfunctory, but has definite legal
consequences. One such consequence is spelled out under
Section 5 of the Arbitration Act, which reads as under
“Notwithstanding anything contained in any other law for the
time being in force, in matters governed by this Part, no judicial
authority shall intervene except where so provided in this Part.”
The non-obstante clause is provided to uphold the intention of
the legislature as provided in the Preamble to adopt UNCITRAL
Model Law and Rules, to reduce excessive judicial interference
which is not contemplated under the Arbitration Act.”
xxxxxxxx
“15. In this context, we may state that the appellant acted in
accordance with the procedure laid down under the agreement
to unilaterally appoint a sole arbitrator, without Respondent 1
mounting a judicial challenge at that stage. Respondent 1 then
appeared before the sole arbitrator and challenged the
jurisdiction of the sole arbitrator, in terms of Section 16(2) of
the Arbitration Act.
16. Thereafter, Respondent 1 chose to impugn the order
passed by the arbitrator under Section 16(2) of the Arbitration
Act through a petition under Articles 226/227 of the Indian
Constitution. In the usual course, the Arbitration Act provides
for a mechanism of challenge under Section 34. The opening
phase of Section 34 reads as ‘Recourse to a Court against an
arbitral award may be made only by an application for setting
aside such award in accordance with sub-section (2) and sub-
section (3)’. The use of term ‘only’ as occurring under the
provision serves two purposes of making the enactment a
complete code and lay down the procedure.”
19
2021 INSC 9
Civil Appeal arising out of SLP (C) No.27534 of 2025 Page 28 of 39
xxxxxxxxxx
“25. It must be noted that Section 16 of the Arbitration Act,
necessarily mandates that the issue of jurisdiction must be
dealt first by the tribunal, before the court examines the same
under Section 34. Respondent 1 is therefore not left remediless,
and has statutorily been provided a chance of appeal. In Deep
Industries case (supra) this Court observed as follows:
“22. One other feature of this case is of some importance.
As stated hereinabove, on 9 -5-2018, a Section 16
application had been dismissed by the learned arbitrator
in which substantially the same contention which found
favour with the High Court was taken up. The drill of
Section 16 of the Act is that where a Section 16 application
is dismissed, no appeal is provided and the challenge to the
Section 16 application being dismissed must await the
passing of a final award at which stage it may be raised
under Section 34.”
(emphasis supplied)
20. Recently, the Constitution Bench in Re: Interplay (supra)
considered the scheme of the A and C Act including Section
16 thereof as well as the question whether the rejection of an
objection raised under Section 16 could be subjected to
challenge in the midst of the arbitral proceedings. In
paragraphs 120 and 122, it was held as under:
“120. …..Section 16 empowers the Arbitral Tribunal to rule on
its own jurisdiction, including ruling on any objections with
respect to the existence or validity of arbitration agreement.
Importantly, the parties have a right under Sections 16(2) and
16(3) to challenge the jurisdiction of the Arbitral Tribunal on
grounds such as the non-existence or invalidity of the arbitration
agreement. The Arbitral Tribunal is obligated to decide on the
challenge to its jurisdiction, and where it rejects the challenge, it
can proceed with the arbitral proceedings and make an arbitral
award. It is the principle of procedural competence-competence
which recognises the power of an Arbitral Tribunal to hear and
decide challenges to its jurisdiction. Once the Arbitral Tribunal
Civil Appeal arising out of SLP (C) No.27534 of 2025 Page 29 of 39
makes an arbitral award, Section 16(6) allows the aggrieved party
to make an application for setting aside the award under Section
34. Sections 16(5) and 16(6) further show that Parliament has
completely ousted the jurisdiction of Courts to interfere during the
arbitral proceedings - courts can intervene only after the tribunal
has made an award. Thus, Section 16 is intended to give full effect
to the procedural and substantive aspects of the doctrine of
competence-competence.”
xxxxxxxxx
“122. Under Section 34, the grounds for setting aside an arbitral
award are specific. The provision requires a party challenging an
award to plead and prove the existence of one or more such
grounds.
20 The scheme of the Arbitration Act shows that although
an Arbitral Tribunal is given priority to determine all issues
pertaining to its jurisdiction based on the principle of competence-
competence, the tribunal's decision is subject to judicial review at
the stage when an award is challenged. Moreover, one of the
grounds on which an arbitral award can be set aside is that the
arbitration agreement is not valid under law. This indicates that
the Arbitration Act does not contemplate the Court determining
the validity of an arbitration agreement at a pre-arbitral stage.”
Thereafter, the Constitution Bench recorded its
conclusions in paragraph 224 as under:
“224. The conclusions reached in this judgment are summarised
below:
a. Agreements which are not stamped or are inadequately stamped
are inadmissible in evidence under Section 35 of the Stamp Act.
Such agreements are not rendered void or void ab initio or
unenforceable;
b. Non-stamping or inadequate stamping is a curable defect;
c. An objection as to stamping does not fall for determination
under Sections 8 or 11 of the Arbitration Act. The Court concerned
must examine whether the arbitration agreement prima facie
exists;
d. Any objections in relation to the stamping of the agreement fall
within the ambit of the Arbitral Tribunal; and
20
Fiza Developers & Inter-Trade (P) Ltd. v. Amci (I) (P) Ltd., (2009) 17 SCC 796 : (2011) 2 SCC (Civ)
637
Civil Appeal arising out of SLP (C) No.27534 of 2025 Page 30 of 39
e. The decision in N.N. Global (2)
21 and SMS Tea Estates
22 are
overruled. Paras 22 and 29 of Garware Wall Ropes
23 are overruled
to that extent.”
21. The learned Senior Advocate for the mine owner also
urged that relegating the stamping objection to the post-
award stage under Section 34 of the A and C Act would
compel the mine owner to endure prolonged and expensive
arbitral proceedings merely to vindicate what he characterises
as a mandatory fiscal objection going to the root of the
agreement, while the remedy available under Section 34 is too
circumscribed to adequately address such a fundamental
defect. This Court is unable to accept this submission, as it
derives its force only if non-stamping or inadequate stamping
of an agreement is treated as a fatal, jurisdictional infirmity
that vitiates the agreement at its inception. That premise,
however, no longer holds good in law. The Constitution Bench
in Re: Interplay (supra), has unequivocally held that non-
stamping or inadequate stamping of an arbitration agreement
is merely a curable defect. In paragraph 48, it was held as
under:
21
N.N. Global Mercantile (P) Ltd. v. Indo Unique Flame Ltd., (2023) 7 SCC 1 : (2023) 3 SCC (Civ)
564
22
SMS Tea Estates (P) Ltd. v. Chandmari Tea Co. (P) Ltd., (2011) 14 SCC 66 : (2012) 4 SCC (Civ) 777
23
Garware Wall Ropes Ltd. v. Coastal Marine constructions & Engg. Ltd., (2019) 9 SCC 209 :
(2019) 4 SCC (Civ) 324
Civil Appeal arising out of SLP (C) No.27534 of 2025 Page 31 of 39
“48. Section 35 of the Stamp Act is unambiguous. It stipulates,
“No instrument chargeable with duty shall be admitted in
evidence…” The term “admitted in evidence” refers to the
admissibility of the instrument. Sub- section (2) of Section 42, too,
states that an instrument in respect of which stamp-duty is paid
and which is endorsed as such will be “admissible in evidence.”
The effect of not paying duty or paying an inadequate amount
renders an instrument inadmissible and not void. Non-stamping
or improper stamping does not result in the instrument becoming
invalid. The Stamp Act does not render such an instrument void.
The non-payment of stamp duty is accurately characterised as a
curable defect. The Stamp Act itself provides for the manner in
which the defect may be cured and sets out a detailed procedure
for it. It bears mentioning that there is no procedure by which a
void agreement can be ‘cured’.”
Hence, this Court drew a careful and fundamental
distinction between the admissibility of an instrument in
evidence and its validity and enforceability in law, holding
that the scheme of the Stamp Act is concerned only with
admissibility and mere non-stamping or inadequate stamping
does not render an agreement void. The agreement survives
non-stamping or insufficient stamping, and the defect can be
cured by getting the agreement sufficiently stamped at any
stage, whereupon it becomes admissible in the eyes of law. It
is the arbitral tribunal that is empowered to deal with this
issue in the first instance. The remedy of having the Tribunal
satisfy itself on the question of stamping under Section 16,
with the award remaining open to challenge under Section 34
at a later stage, is not inadequate. The apprehension of the
Civil Appeal arising out of SLP (C) No.27534 of 2025 Page 32 of 39
mine owner, therefore, rests on a legal position that stands
overruled.
22. Besides the well settled parameters to be borne in mind
while exercising jurisdiction under Articles 226 and 227 of the
Constitution, it is also necessary to be mindful of the
statutory scheme of the concerned enactment from which the
impugned order arises. If the enactment besides providing for
a statutory remedy [herein, Section 34] also expects minimal
judicial interference prior to the culmination of the arbitral
proceedings [herein, Section 5], the said factor would be of
relevance while considering the exercise of jurisdiction. In
other words, the threshold to be satisfied before exercising
discretion under Articles 226 and 227 of the Constitution in
the light of such legislative intent would be higher. As held in
Re: Interplay (supra), the non-obstante clause in Section 5 of
the A and C Act must take precedence over any other law for
the time being in force. It would have to be demonstrated that
notwithstanding the availability of an alternate remedy at the
conclusion of the proceedings, such challenge cannot await
the final adjudication of the proceedings and despite the
Civil Appeal arising out of SLP (C) No.27534 of 2025 Page 33 of 39
statutory expectation of minimal interference, intervention in
exercise of writ jurisdiction at an interim stage is imperative.
We may clarify that our observations are as regards the
‘entertainability’ of a writ petition under Articles 226 and 227
of the Constitution and not with regard to its ‘maintainability’.
This Court in M/s Godrej Sara Lee Ltd. Vs. The Excise and
Taxation Officer-cum-Assessing Authority and others
24
has succinctly explained these concepts as under :-
“4 …In a long line of decisions, this Court has made it
clear that availability of an alternative remedy does not
operate as an absolute bar to the “maintainability” of a writ
petition and that the rule, which requires a party to pursue
the alternative remedy provided by a statute, is a rule of
policy, convenience and discretion rather than a rule of
law. Though elementary, it needs to be restated that
“entertainability” and “maintainability” of a writ petition
are distinct concepts. The fine but real distinction between
the two ought not to be lost sight of. The objection as to
“maintainability” goes to the root of the matter and if such
objection were found to be of substance, the courts would
be rendered incapable of even receiving the lis for
adjudication. On the other hand, the question of
“entertainability” is entirely within the realm of discretion
of the high courts, writ remedy being discretionary. A writ
petition despite being maintainable may not be entertained
by a high court for very many reasons or relief could even
be refused to the petitioner, despite setting up a sound
legal point, if grant of the claimed relief would not further
public interest….”
24
2023 INSC 92
Civil Appeal arising out of SLP (C) No.27534 of 2025 Page 34 of 39
23. Yet another aspect that is required to be referred to is
that the learned Single Judge while referring to the scope of
interference under Articles 226 and 227 of the Constitution
was cognizant of the fact that such power needs to be
exercised in exceptional rarity wherein the illegality or
perversity in the order of the learned Arbitrator stares one in
the face. These observations can be found in paragraph 61 of
the judgment of the learned Single Judge. Despite noticing
the contours and the scope of jurisdiction under Articles 226
and 227 of the Constitution, the learned Single Judge
proceeded to go into the intention of the parties and thereafter
determine the true nature of the agreements between them. It
may be noted that the Constitution Bench in Re: Interplay
(supra) has held in clear terms that any objection in relation
to stamping of an agreement falls within the ambit of the
Arbitral Tribunal. It would, thus, be clear that the learned
Arbitrator was duly empowered to decide the objection raised
by the mine owner as regards insufficient stamping of the
agreement. The jurisdiction to decide cannot mean to decide
in a particular manner. While exercising such power, one may
err on merits. Such error may not be one beyond jurisdiction.
The learned Arbitrator was, thus, within his jurisdiction in
Civil Appeal arising out of SLP (C) No.27534 of 2025 Page 35 of 39
not upholding the objection raised by the mine owner. It
therefore cannot be said that there was any inherent lack of
jurisdiction with the learned Arbitrator. Once it is found that
the learned Arbitrator had the jurisdiction to decide the
objection in relation to stamping of the agreements, in our
view, it was impermissible for the learned Single Judge to
undertake the exercise of entertaining a challenge to the said
adjudication by proceeding to interpret the agreements.
Assuming that the learned Arbitrator erred in his conclusion
that the agreement between the parties was ‘an agreement to
sell’, that would not make the case ‘exceptional’ for being set
aside in exercise of writ jurisdiction. Even on this count, the
approach of the learned Single Judge is found to be incorrect.
24. In our view, there is another material aspect that
requires mention. It was not open for the learned Single Judge
in exercise of writ jurisdiction to enter into the merits of the
dispute while adjudicating the challenge to an order passed
under Section 16 of the A and C Act. It has to be noted that
learned Arbitrator is still seized of the arbitration proceedings
and the parties are yet to lead evidence therein. Determining
the nature of the agreements at such stage would definitely
Civil Appeal arising out of SLP (C) No.27534 of 2025 Page 36 of 39
result in prejudice to the parties. We may in this regard refer
to the decision in Bhaven Construction through Authorised
Signatory Premjibhai K. Shah (supra)
25 wherein a three Judge
Bench of this Court observed that it was settled law that
interpretation of contracts should not generally be
undertaken while exercising writ jurisdiction. Therein, the
question arose as to whether the contract between the parties
was a contract for manufacture simpliciter or whether it was
a contract that was composite in nature and thus a works
contract. It was held that the said question required
contractual interpretation and was a matter of evidence,
especially when both parties had taken contradictory stands
in that regard.
We, therefore, find that that the learned Single Judge
was not justified in going into the merits of dispute between
the parties as regards the nature of the agreements while
exercising writ jurisdiction. An exercise requiring
interpretation of the various agreements ought not to have
been undertaken in exercise of extraordinary jurisdiction.
25
2021 INSC 9
Civil Appeal arising out of SLP (C) No.27534 of 2025 Page 37 of 39
25. We may state that Mr. Shashank Garg, learned Senior
Advocate for the mine owner sought to justify the finding
recorded by the learned Single Judge as regards the true
nature of the agreements and the conclusion that it was in
the nature of ‘conveyance’. Mr. Gopal Subramanium, learned
Senior Advocate for SISCO in his usual fairness sought to
dissuade the appellant from seeking an adjudication as
regards the true nature of the agreements at this stage.
According to him, undertaking such exercise now would be
premature as the arbitration proceedings were pending before
the learned Arbitrator and adjudication of the said issue
required interpretation of various terms of the agreements.
He, therefore, submitted that such adjudication could be
undertaken during the course of arbitration proceedings
before the learned Arbitrator after the evidence was led and
that the aggrieved party could thereafter avail the statutory
remedy, if aggrieved.
Since we have found that for the purposes of
determining the true nature of the agreement for sale dated
12.02.2004, it would be necessary to meaningfully interpret
the said agreement alongwith other supplementary
Civil Appeal arising out of SLP (C) No.27534 of 2025 Page 38 of 39
agreements, we are not inclined to undertake such exercise
as the same touches the merits of the dispute. Suffice it to
observe that the remedy available under Section 34 of the A
and C Act could be invoked by the party aggrieved and all
contentions could be raised at that stage. Section 16(6) read
with Section 34 of the A and C Act takes care of such
contingency. We, therefore, leave open the consideration of
the question as to whether the agreement for sale dated
12.02.2004 and the subsequent agreements between the
parties were in fact ‘conveyance’ as contended by the mine
owner or were merely agreements for sale as contended by
SISCO. We have, therefore, not dealt with the decisions cited
by learned counsel in this regard.
26. We would, thus, restrict ourselves to recording a
conclusion that the learned Single Judge was not justified in
exercising writ jurisdiction under Articles 226 and 227 of the
Constitution for examining and thereafter setting aside the
order passed by the learned Arbitrator under Section 16 of
the A and C Act. Consequently, the Division Bench was
justified in entertaining the writ appeal and setting aside the
Civil Appeal arising out of SLP (C) No.27534 of 2025 Page 39 of 39
order passed by the learned Single Judge after finding the
same to be in excess of jurisdiction.
27. To conclude, we do not find any reason whatsoever to
interfere with the order passed by the Division Bench of the
High Court. It is clarified that the issue with regard to
stamping of the agreement for sale dated 12.02.2004 and the
subsequent agreements is kept open for being raised by the
aggrieved party under Section 34 of the A and C Act, if the
need for the same arises. We place on record our deep
appreciation for the meaningful assistance rendered by all the
learned Senior Advocates as well as the learned counsel
assisting them in presenting before us the issues as raised in
a concise and clear manner.
The Civil Appeal is, accordingly, dismissed with no order
as to costs. Pending applications also stand disposed of.
…………………………..J.
[ J. K. MAHESHWARI ]
….…..………………………..J.
[ ATUL S. CHANDURKAR ]
NEW DELHI,
MAY 27, 2026.
Legal Notes
Add a Note....