0  23 Sep, 2021
Listen in 2:00 mins | Read in 52:05 mins
EN
HI

M/s Yashnand Engineers and Contractors Pvt. Ltd. Vs The State of Assam

  Gauhati High Court WP(C) No. 1242/2021
Link copied!

Case Background

The writ petition under Article 226 of the Constitution of India has been preferred by the petitioner, a company registered under the provisions of the Companies Act, 2013, assailing the decision of ...

Bench

Applied Acts & Sections

No Acts & Articles mentioned in this case

Hello! How can I help you? 😊
Disclaimer: We do not store your data.
Document Text Version

Page 1 of 35

THE GAUHATI HIGH COURT

(THE HIGH COURT OF ASSAM, NAGALAND, MIZORAM & ARUNACHAL PRADESH )

WP(C) No. 1242/2021

M/s Yashnand Engineers and Contractors Pvt. Ltd.

A Company duly incorporated under the provisions

of the Companies Act, 2013 as amended,

having its registered office at 214/5, Khyati Complex,

Near Mithakhali Garden, Ellisbridge, Ahmedabad,

Gujarat - 380006 and represented by Shri Devang Shah.

………………Petitioner

-Versus-

1. The State of Assam,

represented by the Commissioner and Secretary to the

Government of Assam, Public Works (Building and NH )

Department, Dispur, Guwahati - 781006, Assam.

2. The Chief Engineer, PWD (Building), Assam,

Chandmari, Guwahati – 781003.

3. The Executive Engineer, GMC Branch Office of the Chief Engineer

PWD (Building), Assam, Chandmari, Guwahati – 781003.

4. The Senior Architect (B/M), office of the PWD (Building), Assam,

Chandmari, Guwahati - 781003.

.….……….Respondents

Advocates :

For the petitioner : Mr. G.N. Sahewalla, Senior Advocate,

GAHC010035172021

Page 1 of 35

THE GAUHATI HIGH COURT

(THE HIGH COURT OF ASSAM, NAGALAND, MIZORAM & ARUNACHAL PRADESH )

WP(C) No. 1242/2021

M/s Yashnand Engineers and Contractors Pvt. Ltd.

A Company duly incorporated under the provisions

of the Companies Act, 2013 as amended,

having its registered office at 214/5, Khyati Complex,

Near Mithakhali Garden, Ellisbridge, Ahmedabad,

Gujarat - 380006 and represented by Shri Devang Shah.

………………Petitioner

-Versus-

1. The State of Assam,

represented by the Commissioner and Secretary to the

Government of Assam, Public Works (Building and NH )

Department, Dispur, Guwahati - 781006, Assam.

2. The Chief Engineer, PWD (Building), Assam,

Chandmari, Guwahati – 781003.

3. The Executive Engineer, GMC Branch Office of the Chief Engineer

PWD (Building), Assam, Chandmari, Guwahati – 781003.

4. The Senior Architect (B/M), office of the PWD (Building), Assam,

Chandmari, Guwahati - 781003.

.….……….Respondents

Advocates :

For the petitioner : Mr. G.N. Sahewalla, Senior Advocate,

GAHC010035172021

Page 2 of 35

: Mr. D. Senapati, Advocate

For the State Respondents : Mr. D. Saikia, Advocate General, Assam

: Sri. B. Gogoi, Standing Counsel, P.W.D.

Date of Hearing : 13.08.2021

Date of Judgment : 23.09.2021

BEFORE

HON’BLE MR. JUSTICE MANISH CHOUDHURY

JUDGMENT & ORDER

The writ petition under Article 226 of the Constitution of India has been

preferred by the petitioner, a company registered under the provisions of the

Companies Act, 2013, assailing the decision of the Technical Bid Evaluation Committee

taken in a meeting held on 16.02.2021 wherein the technical bid submitted by the

petitioner in response to a Press Notice bearing no. GMC.81/2020/5 dated 02.01.2021

had been declared to be non-responsive. A further direction to the State respondent

authorities is sought for to consider the technical bid submitted by the petitioner and

to open its financial bid.

2. The impugned decision of the Technical Bid Evaluation Committee dated

16.02.2021 is relatable to a competitive bidding process initiated for the contract work

– “Construction of New Medical College centering MMCH and Kalapahar campus along

with 800 Bedded General Hospital at MMCH Campus in Guwahati” [hereinafter referred

to as ‘the Contract Work’, for easy reference].

3. A Press Notice bearing no. GMC.81/2020/5 was published by the Chief Engineer,

Public Works Department [P.W.D.] [Building], Assam [hereinafter also referred to as

‘the tendering authority’, at places for convenience] on 02.01.2021 inviting bids from

eligible registered contractors/firms/private limited company having experience of

similar nature of work for the Contract Work. In continuation of the Press Notice dated

02.01.2021, a Detail Notice Inviting Bid [‘the NIT’, for short] was published on

Page 3 of 35

18.01.2021 inviting bids for the Contract Work from contractors having eligibility

criteria as laid down in the Standard Bidding Document [‘the SBD’/’the bidding

document’, for short]. In the NIT, the approx. value of the work has been mentioned

as Rs. 666.1351 crores and the time of completion as 36 months. The details of the

bid was made available at the e -procurement portal website,

www.assamtenders.gov.in and it was made mandatory for the participating bidders to

enroll therein.

4. As per the original NIT, downloading of bidding document was open from

18.01.2021 to 08.02.2021. The last date of submission of bid was mentioned as upto

12-30 p.m., 08.02.2021. Online submissions of technical bid and financial bid were

made mandatory. A pre-bid meeting was scheduled at 11-00 a.m. on 21.01.2021 at

the office of the Chief Engineer, P.W.D.[Building], Assam. After the pre-bid meeting,

held on 21.01.2021, a Corrigendum dated 06.02.2021 with a revised activity schedule,

came to be published. By the revised activity schedule, the last date of submission of

bid was extended upto 12-30 p.m. on 10.02.2021. The time and date of technical bid

opening were mentioned as 04-30 p.m. and 10.02.2021 respectively.

5. In response to the NIT dated 18.01.2021, the petitioner participated in the said

competitive bidding process considering itself to be eligible, experienced and qualified

in terms of the NIT dated 18.01.2021 by submitting its bid along with all the documents

asked for, within the notified time.

6. As per the activity schedule, the technical bids of the participating bidders were

opened on 10.02.2021 and it was found that three nos. of bids including that of the

petitioner, were received by the tendering authority for the Contract Work. The

technical bids of all the three bidders were thereafter, evaluated and an evaluation

report was presented before a Technical Bid Evaluation Committee headed by the Chief

Engineer, P.W.D.[Building], Assam constituted for the purpose of considering the bids

on merit.

Page 4 of 35

7. It is the case of the petitioner that when the petitioner was waiting and expecting

for a positive outcome of its technical bid, it came to learn from the official website of

the respondent authorities that its technical bid had been found non-responsive. The

reasons assigned for such non-responsiveness are, firstly, non-receipt of confirmation

from the concerned authority as regards genuineness of completion certificate for

single similar nature of work, and secondly, non-submission of necessary documentary

evidence in support of the single similar nature of work as per Clause 4.5A. On

16.02.2021 itself, an Office Order of even date came to be issued by the Chief

Engineer, P.W.D.[Building], Assam whereby it was informed that the financial bids for

the Contract Work would be opened at 11-30 a.m. on 16.02.2021 in his office. All the

members of the Technical Bid Evaluation Committee and the successful bidders in the

technical bid evaluation were requested to attend the opening of the financial bids at

the scheduled time.

8. Heard Mr. G.N. Sahewalla, learned Senior Counsel assisted by Mr. D. Senapati,

learned counsel for the petitioner and Mr. D. Saikia, learned Advocate General, Assam

assisted by Sri. B. Gogoi, learned Standing Counsel, P.W.D. for all the respondents.

9. Mr. Sahewalla has submitted that the impugned decision on the part of the

Tender Bid Evaluation Committee in rejecting the bid submitted by the petitioner on

16.02.2021 is bad and arbitrary being contrary to the clauses of the bidding document

[SBD]. The decision assigned as regards non-receipt of confirmation of genuineness

of completion certificate for single similar nature of work from the concerned authority

cannot be termed to be in conformity of the terms and conditions set forth in the

bidding document. It is his submission that by no stretch, the impugned decision can

be made relatable to Clause 4.5A of the bidding document.

9.1. It is also his submission that though in terms of Clause 4.3.(iii) of the bidding

document the respondent authorities can seek further information on the contract

works in relation to which experience certificates had been submitted by the bidder

but non-receipt or delayed receipt of information from the concerned authorities have

Page 5 of 35

not empowered the respondent authorities to declare a bid as non-responsive. In the

case in hand, the respondent authorities had sought information from the M.P. Road

Development Corporation Limited [MPRDCL], a Government of Madhya Pradesh

Undertaking, without the knowledge of the petitioner after opening of the technical

bids. The respondent authorities had taken the pretext of non-receipt of response by

the MPRDCL to invalidate the otherwise valid bid of the petitioner. As it was not within

the knowledge and control of the petitioner to persuade the MPRDCL which entity is

not connected with the competitive bidding process under reference, the petitioner

could not have been penalized without bringing the fact of non-receipt of response to

the notice of the petitioner. There was no doubt about the genuineness of the

experience certificate and in such situation, it was not open for the respondent

authorities to declare the petitioner’s technical bid as non-responsive.

9.2. He has further submitted that the impugned action on the part of the respondent

authorities is based on extraneous considerations and an action other than bona fide.

Even if an irregularity is assumed to have occurred it cannot be comprehended to have

fallen within the category of essential conditions of eligibility. Submitting as above, Mr.

Sahewalla has submitted that the observation that the petitioner did not submit the

necessary documentary evidence in support of the single similar nature of work as per

Clause 4.5A of the bidding document is clearly arbitrary and unjustified.

9.3. Elaborating on the point, Mr. Sahewalla has submitted that the respondent

authorities had sought for information from the MPRDCL by a communication dated

10.02.2021 and two reminder e-mails dated 11.02.2021 and dated 12.02.2021 and the

said communications neither revealed the time period by which the MPRDCL was

required to furnish the information sought for nor the consequence in the event of

default in furnishing the information. According to him, the date of technical

evaluation, 16.02.2021 was fixed by the respondent authorities without any

information to the bidders. Effectively, there was only two working days in between

11.02.2021 and 16.02.2021 for the MPRDCL to furnish the information, with

13.02.2021 and 14.02.2021 being Saturday and Sunday respectively. Giving only two

Page 6 of 35

days’ time to furnish information without disclosing the consequence of non-furnishing

the information, is clearly arbitrary and irrational.

9.4. It is his further submission that the contention of the State respondents to the

effect that the petitioner did not submit the necessary documentary evidence in

support of the single similar nature of work as per Clause 4.5A is incorrect, perverse

and misstatement. By referring to the experience certificates annexed to the case

papers, he has submitted that the petitioner had submitted all the necessary

documents along with its bid including the details about scope of work as regards civil,

sanitary and water supply works and electrical works, more particularly, vide

performance certificate dated 04.02.2021. He has submitted that in the said

performance certificate dated 04.02.2021 issued by the MPRDCL, the details of the

individual components of the works are mentioned. As per the said performance

certificate dated 04.02.2021, the combined value of completed contract work was Rs.

334.98 crores, meaning thereby, the petitioner had fulfilled the qualification criterion

enjoined by Clause 4.5A.(c) of the bidding document which was at Rs. 266.45 crores.

It is his contention that it is not open for the respondent authorities to give a different

meaning to the term ‘contract value’ in order to brace themselves to disqualify the

petitioner’s technical bid in order to eliminate it from the stage of financial bid

evaluation so as to award the contract to a bidder of their choice.

9.5. It has been pleaded and submitted that in the meantime, the financial bids of the

remaining two bidders were opened after rejection of the petitioner’s technical bid and

both of them had quoted substantially higher bid values than the petitioner. It has

been contended that the impugned action has been undertaken by the respondent

authorities to somehow oust the petitioner from the competition so as to facilitate the

respondent authorities to award the Contract Work to one of the other two bidders at

a higher price, which is against the public interest.

9.6. In support of his submissions, Mr. Sahewalla has referred to the decisions in Asia

Foundation & Construction Ltd. vs. Trafalgar House Construction (I) Ltd. and others,

Page 7 of 35

reported in (1997) 1 SCC 732; Bharat Sanchar Nigam Limited vs. Bhupender Minhas

and others, reported in (2008) 11 SCC 273; Afcons Infrastructure Limited vs. Nagpur

Metro Rail Corporation Limited and another, reported in (2016) 16 SCC 818; and

Consortium of Titagarh Firema Adler S.P.A. vs. Nagpur Metro Rail Corporation Limited,

reported in (2017) 7 SCC 486.

10. Mr. Saikia, learned Advocate General has, on the other hand, raised a preliminary

objection regarding maintainability of the writ petition on the ground of non-joinder of

necessary parties. It is submitted by him that in the bidding process, three bidders

including the petitioner, submitted their bids. The technical bids of the three

participating bidders were opened on 10.02.2021. The technical bids were thereafter,

evaluated and an evaluation report was prepared and presented on 16.02.2021. The

Technical Bid Evaluation Committee held its meeting on 16.02.2021 and after

evaluation, the technical bid of the petitioner was found non-responsive. At the same

time, the technical bids of the other two participating bidders were found responsive

and a decision was also taken on that day itself i.e. on 16.02.2021 to open their

financial bids. The financial bids of the two technically responsive bidders were opened

on 16.02.2021 and one of the said two bidders was declared as L-1 bidder. He has,

thus, contended that a third party right had accrued in favour of the L-1 bidder on

16.02.2021 for having the Contract Work in its favour and, as such, both the L-1 bidder

and L-2 bidder are necessary parties in the instant proceeding as it is likely to be

adversely affected in the event the writ petition, with the prayers above, is allowed.

Non-impleadment of the L-1 bidder and L-2 bidder as a party-respondents in the

instant writ petition has made the writ petition not maintainable and the writ petition

is to be dismissed on the ground of non-joinder of the necessary parties, he submits.

The writ petition was filed on 22.02.2021 and in the writ petition, the petitioner has

made mention about the bid values of the other two bidders and their names. It is,

thus, evident that the petitioner was well aware about the successful bidder at the

time of preferring the writ petition and yet, it has not brought in the successful bidder

as a party-respondent.

Page 8 of 35

10.1. In the above context, he has referred to the decisions in Udit Narain Singh

Malpaharia vs. Additional Member Board of Revenue, Bihar and another, reported in

AIR 1963 SC 786; Prabodh Verma and others vs. State of Uttar Pradesh and others,

reported in (1984) 4 SCC 251; Ranjan Kumar and others vs. State of Bihar and others,

reported in (2014) 16 SCC 187; and Afcons Infrastructure Limited (supra).

10.2. After raising the above preliminary issue regarding maintainability, Mr. Saikia has

referred to the relevant clauses in the bidding document. He has submitted that Clause

4.5 of the bidding document has prescribed the Qualification Criteria. Laying stress on

Clause 4.5A.(c) of the bidding document, he has submitted that a bidder has to satisfy

the qualification criterion prescribed therein. A bidder in order to satisfy the

qualification criterion mentioned in Clause 4.5A.(c), was to submit requisite

documentary evidence regarding satisfactory completion [not less than 90% of

contract value] of at least one similar work of multi-storied RCC Hospital and Medical

College Project of value not less than amounting to Rs. 266.45 crores. Though the

petitioner had submitted a number of documents regarding work experience along

with its bid, none of them except one contract work executed under the MPRDCL had

been projected to have fulfilled the said qualification criterion. In support of the said

contract work under the MPRDCL the petitioner had submitted a performance

certificate dated 04.02.2021. On perusal of the same after opening of the technical bid

on 10.02.2021, the Technical Bid Evaluation Committee found a number of deficiencies

in the said performance certificate and accordingly, it was decided by the Committee

to request the MPRDCL to confirm as regards its genuineness and also to provide the

detailed scope of work in terms of Clause 4.3.(iii) of the bidding document. To that

effect, a letter dated 10.02.2021 and two e-mails dated 11.02.2021 and 12.02.2021

were sent to the MPRDCL with the request to furnish the reply urgently. When no reply

was received till 16.02.2021, that is, the date of sitting of the Technical Bid Evaluation

Committee, the Committee after threadbare discussion, had got no option but to reject

the technical bid of the petitioner for lack of satisfactory documents/information

relating to single similar nature of work to be compliant of the qualification criterion

laid down in Clause 4.5A.(c). It is his submission that the decision to declare the bid

Page 9 of 35

as a non-responsive one was taken in consonance with the terms and conditions of

the bidding document.

10.3. Objecting to the allegations of arbitrariness and irrationality, learned Advocate

General has submitted that Clause 4.5A.(c) is specific to the point that to qualify, a

bidder must have satisfactorily completed [not less than 90% of contract value] as a

prime contractor or as a permitted sub-contractor at least one similar work of multi-

storied RCC Hospital and Medical College Project of value not less than amounting to

Rs. 266.45 crores. But the petitioner appears to have completed its largest single

similar work where the Tendered Cost was Rs. 234.62 crores and the Project Allocated

Cost [PAC] was Rs. 248.01 crores, which were much lesser than Rs. 266.45 crores.

10.4. In response to the above letter dated 10.02.2021 and e-mails dated 11.02.2021

and 12.02.2021, a reply was received from the MPRDCL only on 26.02.2021 along with

a modified performance certificate dated 25.02.2021. On receipt of the modified

performance certificate dated 25.02.2021, the same was compared with the previous

performance certificate dated 04.02.2021. Upon comparison of the said two

performance certificates for the same contract work, a number of discrepancies were

again found by the respondent authorities and in that connection, he has referred to

the statements made in paragraph 12 of the affidavit-in-opposition filed on behalf of

the respondent no. 2. According to him, the discrepancies had further vindicated the

stand of the tendering authority taken with regard to disqualification of the petitioner’s

technical bid.

10.5. It is the further contention on behalf of the State respondents that the documents

annexed with the bid of the petitioner reflected that there were delays and in some

cases, inordinate delays on the part of the petitioner to execute even smaller contract

works of different sizes or values. By referring to the documents annexed to the writ

petition, he has submitted that it is a pointer towards not satisfactory performance

with regard to the periods of completion on the part of the petitioner in executing

contract works and the said aspect can be taken note of by the tendering authority at

Page 10 of 35

the time of taking a decision with regard to qualification or disqualification of a bid

submitted by a bidder. It is his submission that in view of Clause 4.9 of the bidding

document, it was well within the ambit and authority of the tendering authority to

disqualify the technical bid of the petitioner to take note of such facts, which are very

relevant from the point of view of the tendering authority.

10.6. Learned Advocate General has contended that the decision-making process of

the tendering authority as regards acceptance or rejection of a bid taken in respect of

a contract work pursuant to a competitive bidding process undertaken is not to be

lightly interfered with as the law is settled that interference is permissible only if the

decision-making process is found to be arbitrary or irrational or mala fide. The bidding

document is prepared by the tendering authority with the help of experts by taking

into accounts the requirements of the contract work/project in question. In the case

in hand, it is a specialized project for construction of a Medical College and Hospital

with 800 bed capacity and the past performance of a bidder in similar nature of work

is the most vital and relevant aspect. The element of public interest is very much

present behind the decision and any interference at the instance of an unsuccessful

bidder regarding interpretation of the terms and conditions of the bidding document is

not called for except in exceptional circumstances. As no exceptional circumstances

have been made out by the petitioner here, this writ petition deserves to be dismissed

also on merits, if not on the preliminary issue.

10.7. To buttress his submissions, learned Advocate General has referred to the

decisions in Central Coalfields Limited and another vs. SLL-SML (Joint Venture

Consortium and others), reported in (2016) 8 SCC 622; Afcons Infrastructure Limited

(supra); Caretel Infotech Limited vs. Hindustan Petroleum Corporation Limited and

others, reported in (2019) 14 SCC 81; and Silppi Constructions Contractors vs. Union

of India and another, reported in (2020) 16 SCC 489.

11. In reply, Mr. Sahewalla has submitted that the aspect of alleged delay in

executing the contract works, as contended on behalf of the State respondents, is not

Page 11 of 35

a ground taken earlier. By referring to the documents annexed to the writ petition to

which the learned Advocate General has referred to, he has submitted that there was

nothing to indicate in those documents that there was any remark of poor performance

by the employers of those works. Rather the performance reports indicated about

good/very good/outstanding performance. The delay, if any, in absence of any remark

cannot be attributed to the petitioner merely for the reason that in some of the cases,

the dates of completion of the contract works were beyond the stipulated dates of

completion. No penalty was levied in any of the cases, he submits. It is not open for

the State respondents to make addition of grounds of rejection to supplement its

previous grounds. In this connection, he has referred to the decisions in Hindustan

Petroleum Corpn. Ltd. vs. Darius Shapur Chennai and others, reported in (2005) 7 SCC

627; Rashmi Metaliks Limited and another vs. Kolkata Metropolitan Development

Authority and others, reported in (2013) 10 SCC 95; State of Punjab vs. Bandeep Singh

and others, reported in (2016) 1 SCC 724; and T.P. Senkumar, IPS vs. Union of India

and others, reported in (2017) 6 SCC 801. In all these decisions, it has been observed

that every decision of an administrative or executive nature must contain the reasons

which led the authority in taking such decision and it is not permissible for the authority

thereafter to take resort to any other additional reasons.

11.1. With regard to the preliminary issue raised on the ground of non-joinder of

parties, he has referred to the decision in Silppi Constructions Contractors (supra). It

is his submission that in the present writ petition, the petitioner has challenged the

decision of the tendering authority in declaring the petitioner’s technical bid as non-

responsive and as such, there is no requirement to make the other bidders party-

respondents in the instant writ proceeding. He has contended that the writ petition is

maintainable in the absence of the other two participating bidders.

12. I have considered the rival submissions advanced by the learned counsel for the

parties and also perused the materials brought on record by the parties through their

respective pleadings. I have also considered the decisions cited by the learned counsel

Page 12 of 35

for the parties in support of their contentions and the written submissions submitted

by them.

13. The competitive bidding process has been initiated by the Press Notice dated

02.01.2021, followed by a Detail Notice Inviting Bid [the NIT], for the contract work –

‘Construction of New Medical College Centering MMCH and Kalapahar campus along

with 800 Bedded General Hospital at MMCH Campus in Guwahati’ [the Contract Work].

The approximate value of the Contract Work is Rs. 666.1351 crores and the time of

completion is 36 months. Bids were invited for the Contract Work from contractors

having qualification criteria as laid down in the Standard Bidding Document [SBD]. As

per the NIT, contractors/bidders had to submit the technical bid and the financial bid

online. Initially, the last date of submission of bid was mentioned as up to 12-30 p.m.,

08.02.2021. Apart from the above, a hard copy of the technical bid submitted online,

was also to be submitted on 08.02.2021 up to 12-30 p.m. for evaluation purpose. As

per the activity schedule provided in the NIT, a pre-bid meeting was scheduled on

21.01.2021.

14. The pre-bid meeting was held, as scheduled, on 21.01.2021 in the office of the

respondent no. 2 i.e. the Chief Engineer, P.W.D. [Building], Assam. Queries from the

intending bidders were received both through e-mail and in person. The queries were

discussed and deliberated upon and resolutions were worked out. Clause 4.5A of the

SBD/bidding document had been modified. The minutes of the pre-bid meeting were

accordingly uploaded in the concerned website. On 06.02.2021, a Corrigendum came

to be issued by publishing the modification made in the SBD/bidding document and

Bill of Quantities [BOQ]. By the said Corrigendum, the last date of submission of bid

was extended up to 12-30 p.m., 10.02.2021. It was further notified that the technical

bids would be opened at 04-30 p.m. on 10.02.2021 and the date of opening of financial

bids would be notified later.

15. In response to the NIT, three bidders submitted their bids viz. (a) M/s Yashnand

Engineers and Contractors Pvt. Ltd. – the petitioner; (b) M/s Larsen & Toubro Ltd.;

Page 13 of 35

and (c) M/s NCC Ltd. The technical bids were opened at 04-45 p.m. on 10.02.2021 in

the office of respondent no. 2. Thereafter, the technical bids of all the three bidders

were evaluated in reference to the requisite documents/information furnished by the

bidders for fulfilment of the qualification criteria. After completion of the evaluation

process of the technical bids for the Contract Work, an evaluation report was prepared

and presented before the Technical Bid Evaluation Committee for consideration of the

technical bids on merits.

16. A meeting of the Technical Bid Evaluation Committee was held on 16.02.2021.

The Committee after scrutiny of the bids and discussion, had declared the bid of the

petitioner to be non-responsive. As per the minutes of the Technical Bid Evaluation

Committee, the bid was non-responsive as confirmation of genuineness of the

completion certificate for single similar nature of work from the concerned authority

was not received till that date and the petitioner had not submitted the necessary

documentary evidence in support of the single similar nature of work as per Clause

4.5A of the bidding document. The minutes of the Technical Bid Evaluation Committee

had further recorded that the technical bids of the other two bidders i.e. M/s Larsen &

Toubro Ltd. and M/s NCC Ltd. had been found responsive for opening of their financial

bids for the Contract Work. An office order came to be issued by the respondent no. 2

on 16.02.2021 whereby it was informed that the financial bids for the Contract Work

would be opened at 11-30 hours on 16.02.2021 in the office of the respondent no. 2.

All the members of the Evaluation Committee as well as the successful bidders in the

technical bid evaluation stage were requested to attend the meeting for opening of

the financial bids at the scheduled time. By the said office order, the two bidders viz.

M/s Larsen & Toubro Ltd. and M/s NCC Ltd. were notified to be present at the time of

opening of the financial bids.

17. Aggrieved by and dissatisfied with such declaration of non-responsiveness of its

technical bid the petitioner submitted a letter to the respondent no. 1 i.e. the

Commissioner and Special Secretary to the Government of Assam, P.W.D. [Building &

NH] on 16.02.2021 ventilating its grievances. It was contended that the procedure

Page 14 of 35

adopted by the Technical Bid Evaluation Committee was arbitrary and the technical bid

of the petitioner was rejected on flimsy and frivolous grounds. It was further contended

that the necessary documentary evidence as required under Clause 4.5A had been

duly submitted for single similar nature of work. The petitioner was also aggrieved by

the immediate opening of the financial bids on 16.02.2021 and the consequent

declaration of L-1 bidder and L-2 bidder on the portal. The petitioner had, thereby,

called for necessary and immediate direction to the Technical Bid Evaluation

Committee to review their evaluation of the petitioner’s technical bid after receipt of

confirmation of the completion certificate. On 17.02.2021, a legal notice was also

served upon the respondent authorities in that regard.

18. From the rival submissions of the parties, it appears that the qualification criterion

with regard to single similar nature of work is the prime bone of contention. As per

Clause 4.3 of the SBD, a bidder with its bid had to submit, inter-alia, the information

and documents in relation to experience in works of a similar nature and size for each

of the last five years, and details of works underway or contractually committed; and

clients who can be contacted for further information on those contracts. Clause 4.5

has catalogued ‘the Qualification Criteria’. Clause 4.5A thereof has prescribed that each

bidder in its name should have the qualification in the last five years as referred to in

the Appendix to qualify for award of the Contract Work. The qualification criterion

contained in Clause 4.5A.(c) in the original SBD is extracted herein below for ready

reference :-

4.5A.(c) :- Satisfactorily completed (not less than 90% of contract value), as a

prime contractor (or as a nominated sub-contractor, where the sub-

contractor involved in execution of all main items of work described

in the bid document, provided further that all other qualification

criteria, are satisfied) at least one similar work of multi-storied RCC

Hospital and Medical College Project of value not less than

amounting to (1) Civil, Sanitary & Water supply work and Electrical

works including all ancillary works of Rs. 266.45 Crore (Rupees two

Page 15 of 35

hundred sixty six crore and forty five lakh) only which is

approximately 40% of the bid value (updated value) during last 5

years i.e. upto 31.03.2020 under Central Govt./State Govt.

Organization/Semi Govt./PSU within the country.

The qualification criterion contained in modified Clause 4.5A.(c), as per the minutes of

the pre-bid meeting, is also extracted herein below for ready reference :-

4.5A.(c) :- Satisfactorily completed (not less than 90% of contract value), as a

prime contractor (or as a nominated sub-contractor, where the sub-

contractor involved in execution of all main items of work described

in the bid document, provided further that all other qualification

criteria, are satisfied) at least one similar work of multi-storied RCC

Hospital and/or Medical College Project of value not less than

amounting to (1) Civil, Sanitary & Water supply work and Electrical

works including all ancillary works of Rs. 266.45 Crore (Rupees two

hundred sixty six crore and forty five lakh) only which is

approximately 40% of the bid value (updated value) during last 5

years i.e. upto 31-03-2020 under Central Govt./State Govt.

Organization/Semi Govt./PSU within the country.

19. In order to show fulfillment of the ‘Qualification Criteria’ laid down in Clause 4.5

of the SBD/bidding document, the petitioner has stated that it had submitted the

details of the experience in executing similar works over the last five years along with

the necessary documents/certificates with its bid, along with a chart. The said chart is

also appended as Annexure–V to the writ petition. From the said chart, it is noticed

that the petitioner has identified 10 (ten) nos. of contract works executed for different

authorities during the last five years. It is further noticed that out of the said 10 (ten)

nos. of contract works, the contract values of 9 (nine) nos. of contract works are

mentioned as Rs. 52.98 crores, Rs. 58.13 crores, Rs. 73.36 crores, Rs. 76.62 crores,

Rs. 89.95 crores, Rs. 99.84 crores, Rs. 111.16 crores, Rs. 155.32 crores and Rs. 183.90

Page 16 of 35

crores respectively. Prima facie none of these 9 (nine) contract works meets the

eligibility criterion laid down in Clause 4.5A.(c). It is the work executed for the M.P.

Road Development Corporation Ltd. [MPRDCL] which the petitioner has emphasized in

relation to the qualification criterion mentioned in Clause 4.5A.(c) of the bidding

document. The said work executed for the MPRDCL was in respect of the contract

work of ‘Construction of New Medical Colleges and up-gradation of Hospitals at Vidisha,

[M.P.] 1. Civil, Sanitary, Plumbing, Internal Electrical, Electric Low Voltage Systems,

Fire Fighting, Fire Alarm System, External Water Supply, External Drainage, STP, PTP,

Road, Horticulture, Street Light, Electric Sub-station, HVAC including IBMS, Lift,

Medical Gas Pipeline System, Solar Water Heating System, etc.’ [hereinafter referred

to as ‘the subject-work’, for easy reference]. According to the petitioner, the

experience it has gained by executing the subject-work has made it eligible and

qualified for the Contract Work, which the tendering authority has disputed by

contending that the qualification criterion set forth in Clause 4.5A.(c) is not satisfied

by the petitioner with the experience gained from the subject-work.

20. In view of such rival contentions, it has become necessary to have a closer look

at the performance certificate dated 04.02.2021, issued by the MPRDCL, in relation to

the subject-work. The performance certificate dated 04.02.2021 has been annexed to

the writ petition and the same is available at page nos. 70-71 of the case papers. For

ready reference, the said performance certificate dated 04.02.2021 is quoted herein

below :-

CIN : U45203MP2004SGC016758

M.P. Road Development Corporation Ltd.

(M.P. State Highway Authority)

(Govt. of M.P. Undertaking)

45-A, Arera Hills, Bhopal-462011

Phone : 0755-2597290/2765205 Fax : 0755-2572643, Website : mprdc.gov.in

Letter no. 13265/Build/Vidisha Medical College/2021 Bhopal dated 04.02.2021

PERFORMANCE CERTIFICATE

Page 17 of 35

This Certificate is issued on the request of M/s Yashnand Engineers & Contractors Pvt. Ltd. for

Tender purpose only.

(Yogendra Gahole)

Chief Engineer (Building)

1.

Name of work/Project & Location Construction of New Medical

Colleges and up-gradation of

Hospitals at Vidisha, Madhya

Pradesh

2. Agreement No. Agreement No. – 214/2016

3.

Name of Contractor YASHNAND ENGINEERS &

CONTRACTORS PVT. LTD.

4. PAC Rs. 248.01 Cr.

5. Tendered Cost Rs. 234.62 Cr.

6.

Gross Amount up to date payment done Rs.

(Final Bill in under payment processes.)

334.98 Cr.

7. Gross Amount of work done up to 31.03.2020 Rs. 313.69 Cr.

8. Total Work done up to 31.03.2020 (in %) 92.80%

9. Date of Start 18/01/2016

10. Date of Completion 25/08/2020

11.

i) Stipulated Date of Completion

(as mentioned in work order)

17/01/2018

ii) Actual Date of Completion 25/08/2020

iii) Whether case of levy of compensation for

delay has been decided or not

Decided

iv) If decided, amount of compensation levied

for delayed completion, if any.

No.

12. Work Components [Please tick (√) in relevant box]

a) RCC Framed Structure √

b) Finishing Works √

c) Water Supply and sanitary installation works √

d) External development and Drainage √

e)

Internal & External Electrification, Electrical Sub

Station, HT Line, LT Line, Transformer and DG set

Works.

f) Firefighting & Fire Alarm Works √

g) LV Works √

h) Lifts √

i) Medical Gas Pipe Line (MGPS) Works √

j) ETP, STP, WTP, RO and Pump Works √

k) CCTV Works √

l) Dedicated PA Systems √

13. No. of Storeys (Basement + G.F. + 6 Floor) 8

14. Performance Report*

1) Quality of Work Very Good

2) Financial Soundness Very Good

3) Technical Proficiency Very Good

4) Resourcefulness Very Good

5) General Behaviour Outstanding

Page 18 of 35

MPRDC, Bhopal

It is submitted by the parties at the bar that PAC stands for Project Allocated Cost.

21. From the performance certificate dated 04.02.2021, it transpires that the PAC for

the subject-work was Rs. 248.01 crores and the Tendered Cost was Rs. 234.62 crores.

It further transpires that the gross amount upto date payment done was Rs. 334.98

crores and as on 04.02.2021, the final bill was in the process for payment. The gross

amount of work done upto 31.03.2020 was Rs. 313.69 crores and it amounted to

92.80% of the total work. It is noticed that the date of start of the subject-work was

18.01.2016 and the date of completion was 25.08.2020. As per the work order issued

for the subject-work, the stipulated date of completion was 17.01.2018.

22. It can be iterated that the submissions of the parties have centered around the

above figures and parameters of the subject-work vis-à-vis Clause 4.5A.(c) of the SBD.

Admittedly, the subject-work is reflected as new medical colleges and up-gradation of

hospitals and the MPRDCL is a Government of Madhya Pradesh Undertaking. After

opening of the technical bid of the petitioner on 10.02.2021 and upon perusal of the

performance certificate dated 04.02.2021, the tendering authority was stated to be of

the view that the detailed scope of the subject-work was not mentioned therein. The

tendering authority appeared to have taken a view that in order to ascertain the

credentials of the petitioner as the contractor as regards its ability and capacity to

perform such similar work under the P.W.D. a confirmation about the genuineness of

the performance certificate and the detailed scope of the subject-work would be

necessary from the MPRDCL which was the employer for the subject-work. It was in

such situation, the tendering authority stated to have written to the MPRDCL on

10.02.2021 as well as by e-mails on 11.02.2021 and 12.02.2021. Though no time

period was mentioned in those communications, it was, however, asserted that the

confirmation and supply of the detailed scope of the subject-work were urgently

required at an early date by e-mail, followed by a post copy. The MPRDCL was

requested to sent its reply to two e-mail accounts, mentioned in those communications,

Page 19 of 35

of the respondent no. 2. As has been mentioned above, the evaluation report was

prepared by 16.02.2021 on the basis of the tender papers received from the

participating bidders after opening of the technical bids on 10.02.2021 and the same

was placed before the Tender Bid Evaluation Committee on 16.02.2021. Admittedly,

no response from the MPRDCL was received till 16.02.2021. It is not the case of the

petitioner that the MPRDCL did not receive the above three communications (supra)

during the period from 10.02.2021 to 16.02.2021. It is the contention of the petitioner

that during the period from 10.02.2021 to 16.02.2021, there were only two working

days and such short duration is wholly inadequate to forward a reply.

23. On reverting back to the performance certificate dated 04.02.2021, it is found

that the MPRDCL had mentioned the name of the subject-work as ‘Construction of New

Medical Colleges and Up-gradation of Hospitals at Vidisha, Madhya Pradesh’. The

Tendered Cost was Rs. 234.62 crores. The work components at serial no. 12 of the

performance certificate were marked with tick [√] marks in the relevant boxes. For

example, there is a tick [√] mark against RCC Framed Structure. One could reasonably

guess therefrom that the subject-work included the work component of RCC Framed

Structure, without any further details.

24. In paragraph 8 of the affidavit-in-opposition, the respondent no. 2 has contended

that during evaluation when it examined the performance certificate dated 04.02.2021

concomitantly with Clause 4.5A of the SBD, it noticed the following discrepancies :-

(i) Name of the project is Plural such as “Medical Colleges”, “Upgradation

of Hospitals” that does indicate there may be more than one no. of

projects.

(ii) Tendered cost mentioned for the project was Rs. 234.62 crore & Project

Allocated Cost (PAC) value mentioned in the certificate was Rs. 248.01

crore, whereas as per bid requirement, the same should be of value of

Rs. 266.45 crore.

Page 20 of 35

(iii) But, as mentioned in the completion certificate, the gross amount up-

to-date payment done was Rs. 334.98 crore & final bill was still under

process with gross amount of work done upto 31

st

March, 2020 as Rs.

313.69 crore, with percentage of progress 92.8%. But, arithmetically

92.8% of Rs. 334.98 crore comes to 310.86 crore instead of Rs. 313.69.

Further, the certificate was neither authenticated by any statutory

auditor nor supported by documents like certified copy of passed bill.

The Performance Certificate indicated that there was a probable

enhancement of the project cost; for which the documentary evidence

like project enhancement document in favour of the bidder was not

attached with the bid.”

25. It has been averred that observing such discrepancies in the performance

certificate dated 04.02.2021, the communications dated 10.02.2021, 11.02.2021 and

12.02.2021 were made to the MPRDCL. According to the Technical Bid Evaluation

Committee, the documentary evidence in the form of the said performance certificate

dated 04.02.2021, furnished by the petitioner, in support of ‘similar nature of work’

lacked in vital information and, thus, could not be considered as sufficient evidence for

the purpose of establishing responsiveness of the technical bid. They also doubted the

genuineness of the information contained therein in view of deficiencies in respect of

vital information and it was well within their authority to ask for confirmation and to

call for further information in terms of Clause 4.3.(iii) of the SBD/bidding document. It

has been contended by the petitioner that a perusal of the performance certificate

dated 04.02.2021 clearly indicates that the same is a single work and not multiple

works, as alleged. Moreover, it was not assigned as a specific ground of rejection in

the impugned decision dated 16.02.2021. It is further contended by the petitioner that

the eligibility criterion contained in Clause 4.5A.(c) has not stipulated that the value

should be ‘Tendered Cost’ or it should be ‘actual contract value’, which is the cost at

which the work had been executed. It is the contention of the petitioner that it is the

actual executed contract value which is to be considered, not the initial bid value at

which the contract-work was awarded. Regarding the allegation about percentage of

progress to the extent of 92.8%, the petitioner has asserted that the said calculation

Page 21 of 35

is incorrect and its calculation adopted for work done percentage-wise as 92.8%

[=313.69/337.99*100] is correct. It is also contended that since confirmation and

information were sought from the MPRDCL by the tendering authority it was not open

for the tendering authority to penalize the petitioner for non-receipt of confirmation

and information by rejecting its technical bid.

26. During the course of hearing, learned Advocate General has, by referring to the

other performance/completion certificates submitted with the technical bid of the

petitioner which are annexed to the writ petition at page nos. 72-91, submitted that

from a bare perusal of those it is evident that the petitioner had failed to complete

those contract works within the stipulated dates of completion and invariably, the

actual dates of completion were much after the stipulated dates of completion. It has

been contended on the basis of Clause 4.9 of the SBD/bidding document that even if

a bidder meets the qualifying criteria, he can be disqualified if record of poor

performance such as improper completion of contract, inordinate delays in completion,

etc. are noticed. The said contention has been objected by the learned Senior Counsel

for the petitioner by submitting that the same was not a ground for rejection of the

petitioner’s technical bid nor it was pleaded in the pleadings. It is his contention that

a new ground cannot be taken afterwards and has referred to the decisions mentioned

above.

27. At this stage, it would be apposite to refer to the scope of judicial review in

respect of a tender process which has been laid down by the Hon’ble Supreme Court

of India in some of the decisions, mentioned above, cited by the learned counsel for

the parties.

27.1. In Asia Foundation & Construction Ltd. (supra), referred by the petitioner, it has

been observed that though the judicial review cannot be denied so far as exercise of

contractual powers of Government bodies are concerned, but it is intended to prevent

arbitrariness or favouritism and it is exercised in the larger public interest or if it is

brought to the notice of the Court that in the matter of award of a contract power has

Page 22 of 35

been exercised for any collateral purpose. It is also observed that it is not justified in

interfering with the award by going into different clauses of the bid document. The

fact of escalation of cost on account of delay in executing a project is a relevant factor.

27.2. In Bharat Sanchar Nigam Limited (supra), referred to by the petitioner, the

decisions in Directorate of Education vs. Educomp Datamatics Ltd., (2004) 4 SCC 19

and Tata Cellular vs. Union of India, (1994) 6 SCC 651, have been referred wherein it

has been held that the Courts can scrutinize the award of the contracts by the

Government or its agencies in exercise of their powers of judicial review to prevent

arbitrariness or favouritism but there are inherent limitations on the exercise of the

power of judicial review in such matters. The terms of the invitation to tender cannot

be opened to judicial scrutiny because the invitation to tender is in the realm of

contract. The Court does not sit as a court of appeal but merely reviews the manner

in which the decision was made because the Court does not have the expertise to

correct the administrative decision. If a review of the administrative decision is

permitted it will be substituting its own decision, without the necessary expertise which

itself may be fallible. The Government must have a free hand in setting the terms of

the tender and must have reasonable play in its joints as a necessary concomitant for

an administrative body in an administrative sphere. It is entitled to pragmatic

adjustments which may be called for by the particular circumstances. The Courts

cannot strike down the terms of the tender prescribed by the Government because it

feels that some other terms in the tender would have been fair, wiser or logical. The

Courts can interfere only if the policy decision is arbitrary, discriminatory or mala fide.

27.3. In Consortium of Titagarh Firema Adler S.P.A. (supra), referred by the petitioner,

the decision in Tata Cellular (supra) has been referred to apart from other decisions to

observe that the modern trend is judicial restraint on administrative action and the role

of the Court is only to review the manner in which the decision has been taken. An

administrative decision can be tested by the application of Wednesbury principle of

reasonableness to see whether it is free from arbitrariness not affected by bias or

actuated by mala fides. If the decision relating to award of contract is bona fide and is

Page 23 of 35

in public interest, the Court will not, in exercise of power of judicial review, interfere

even if a procedural aberration or error in assessment or prejudice to a tenderer is

made out.

27.4. In Central Coalfields Limited (supra), the Hon’ble Supreme Court of India by

quoting from the decisions in Ramana Dayaram Shetty vs. International Airport

Authority of India, (1979) 3 SCC 489 and G.J. Fernandez vs. State of Karnataka, (1990)

2 SCC 480, has gone to observe that the Court must, as far as possible, avoid a

construction which would render the words used by the author of the document

meaningless and futile or reduced to silence any part of the document and make it all

together inapplicable. It has reaffirmed that the tendering authority issuing the tender,

has the right to enforce the terms of the tender. If a party approaches a Court for an

order restraining the employer from strict enforcement of the terms of the tender, the

Court would decline to do so. The Court will not countenance interference with the

decision of the employer at the behest of an unsuccessful bidder in respect of a

technical or procedural violation. After considering a host of decisions as regards

contours of judicial review in relation to tender process, it has been held that the issue

of acceptance or rejection of a bid or a bidder should be looked at not only from the

point of view of the unsuccessful party but also from the point of view of the employer.

Ordinarily, the soundness of the decision taken by the employer ought not to be

questioned. However, the decision-making process can be subject to judicial review.

The decision may be questioned if it is irrational or mala fide or intended to favour

someone or a decision that no responsible authority acting reasonably and in

accordance with relevant law could have reached.

27.5. The decisions in Afcons Infrastructure Limited (supra) and Silppi Constructions

Contractors (supra) have been referred to and relied on by both the parties.

27.6. In Afcons Infrastructure Limited (supra), bids were invited for a contract work by

the Nagpur Metro Rail Corporation Limited [the NMRCL] for the Nagpur Metro Rail

Project. The decision in Central Coalfields Limited (supra) has been referred to observe

Page 24 of 35

that in relation to a tender process, the Constitutional Courts can interfere a decision

as regards acceptance or rejection of the bid of a bidder if the decision is perverse.

The Constitutional Courts are expected to exercise restraint in interfering with the

administrative decision and ought not to substitute its view for that of the

administrative authority. A mere disagreement with the decision-making process or

the decision of the administrative authority is not a reason for a Constitutional Court

to interfere. The owner or the employer of a project, having authored the tender

documents, is the best person to understand and appreciate its requirements and

interpret its documents. The Constitutional Courts must defer to this understanding

and appreciation of the tender documents, unless there is mala fide or perversity in

the understanding or appreciation or in the application of the terms of the tender

conditions. It is possible that the owner or employer of a project may give an

interpretation to the tender documents that is not acceptable to the Constitutional

Courts but that by itself is not a reason for interfering with the interpretation given.

27.7. In Silppi Constructions Contractors (supra), the respondents issued notice

inviting tenders for two works. The technical bids of the petitioner therein i.e. Silppi

Constructors Contractors were rejected by the tendering authorities. The petitioner

filed a writ petition challenging the same. The main ground raised was that no reasons

were given either while rejecting its tender or the appeals. In the counter filed to the

writ petition the stand taken by the respondents was that the petitioner’s tenders were

rejected since the petitioner did not satisfy the eligibility criteria for submission of the

bid. It has been held therein that the Court should normally refrain from interfering in

contractual matters unless a clear-cut case of arbitrariness or mala fides or bias or

irrationality is made out. The Court does not sit like a court of appeal over the

appropriate authority. The authority which floats the contract of tender and has

authored the tender documents is the best judge as to how the documents have to be

interpreted. If two interpretations are possible then the interpretation of the author

must be accepted. It has been reiterated that the decisions taken with regard to tender

processes are administrative decisions and such decisions are in the realm of contract.

While rejecting the tender a person or authority inviting the tenders is not required to

Page 25 of 35

give reasons even if it be a State within the meaning of Article 12 of the Constitution

of India. These decisions are neither judicial nor quasi-judicial. If reasons are to be

given at every stage, then the commercial activities of the State could come to a

grinding halt. The State must be given sufficient leeway in this regard. The tendering

authority is entitled to give reasons in the counter to the writ petition.

27.8. The decision in Caretel Infotech Limited (supra) has been referred to by the

respondents’ side to emphasize as regards the extent to which scrutiny of tenders in

writ proceedings under Article 226 of the Constitution of India is permissible. It has

been held therein to the effect that normally, the parties would be governed by their

contracts and the tender terms. In view of Government and public sector enterprises

venturing into economic activities, the Supreme Court of India has found it appropriate

to build in certain checks and balances of fairness in procedure. Observing that the

window has been opened too wide by challenging every small or big tender nowadays

in writ proceedings almost as a matter of routine, it has been cautioned that an

unnecessary and close scrutiny of minute details, contrary to the view of the tendering

authority, has made awarding of contracts by Government and public sector enterprise

a cumbersome exercise, with long drawn out litigation at the threshold. By making a

comparison with the promptness and efficiency levels in respect of private contracts it

has been observed that such close scrutiny has tended to make the tenders of the

public sector a non-competitive exercise to the great disadvantage to the Government

and the public sector. The object cannot be that in every contract, where some parties

would lose out, they should get the opportunity to somehow pick holes, to disqualify

the successful parties, on grounds on which even the party floating the tender finds

no merit.

28. Reverting back once again to the facts of the case in hand, it could be seen that

opportunity was provided to a prospective bidder to seek any clarification on the

bidding document by writing to the respondent no. 2 prior to the scheduled pre-bid

meeting. The respondent no. 2 was to respond to any such request for clarification

and such clarification was required to be intimated to all purchasers of the bidding

Page 26 of 35

document. The purpose of the pre-bid meeting was to clarify issues and to answer

questions on any matter that might be raised at that stage. In the minutes of the pre-

bid meeting held on 21.01.2021 for the Contract Work, the tendering authority

mentioned that a lot of queries were received from the prospective bidders and all

those queries were deliberated upon in the pre-bid meeting and thereafter, resolutions

taken were intimated to all the prospective bidders by uploading the same in the

website. It is not the case of the petitioner that they had sought any clarification with

regard to any of the clauses of the bidding document and clarifications were not given.

In such view of the matter, one has to proceed on the premise that the petitioner had

accepted all the terms and conditions of the bidding document and proceeded to

submit its bid. It is not also the case of the petitioner, that the terms and conditions

set in the bidding document/SBD were made keeping in mind the qualifications of

certain other bidders and in order to deprive the petitioner. The petitioner has not

alleged about any discriminatory treatment qua the terms and conditions specified in

the bidding document.

29. There is no ambiguity in Clause 4.5A.(c) that the bidder has to fulfill the

qualification criterion of executing ‘one similar work of multi-storied RCC Hospital

and/or Medical College Project’. A look in the performance certificate dated 04.02.2021

has demonstrated that the MPRDCL had mentioned the name of the work/project and

location as ‘Construction of New Medical Colleges and Up-gradation of Hospitals at

Vidisha, Madhya Pradesh’. Thus, it cannot be said that the contention raised in

paragraph 8 (i) of the affidavit-in-opposition to the effect that there was no indication

about a single project of Medical College and Up-gradation of Hospital or multiple

projects of medical colleges and up-gradation of hospitals or in multiples is irrelevant,

far fetched and out of context. The tendering authority has insisted in Clause 4.5A.(c)

from the bidder, either as a prime contractor or as a sub-contractor, satisfactory

completion [not less than 90% of contract value] of at least ‘one similar work of multi-

storied RCC Hospital and/or Medical College Project’ of Rs. 266.45 crores which is

approximately 40% of the bid value i.e. Rs. 666.1351 crores during last five years i.e.

up to 31.03.2020. It, thus, means that such similar work had to be executed between

Page 27 of 35

the period from 01.04.2015 to 31.03.2020. The subject-work is found to have been

completed during the period from 18.01.2016 to 25.08.2020. Considering the fact that

the approximate value of the Contract Work has been fixed at Rs. 666.1351 crores the

tendering authority has set the benchmark at Rs. 266.45 crores, which is approximately

40% of Rs. 666.1351 crores, so that it can assure itself about the past performance,

experience and credentials of the bidder to execute a public project of such nature

where money from the coffers of the State are to be spent.

30. It is the stand of the tendering authority, through its affidavit-in-opposition, that

the tendered cost for the subject-work was Rs. 234.62 crores which is lesser than the

figure set forth in the qualification criterion in Clause 4.5A.(c) at Rs. 266.45 crores.

The tendering authority has insisted that the meaning ascribed by the term ‘contract

value’ in Clause 4.5A.(c) in the SBD/bidding document can only be equated with the

term ‘tendered cost’ appearing in the performance certificate dated 04.02.2021 and

no other meaning can be comprehended for the term ‘contract value’. While the

petitioner has sought to contend that the term ‘contract value’ has to be the value/cost

at which the subject-work was executed the same has been vehemently objected by

the State respondents. It prima facie appears from the performance certificate dated

04.02.2021 that the gross amount of work done up to Rs. 313.69 crores is greater

than the tendered cost of Rs. 234.62 crores. As per the version of the tendering

authority the performance certificate indicated about enhancement of the project cost.

The communication dated 12.06.2018, annexed as Annexure-C to the additional

affidavit of the petitioner, goes to indicate that there was enhancement in the project

cost for the subject-work i.e. the construction of Vidisha Medical College, with no

corresponding enhancement in the scope of work and the same is clearly indicative of

escalation in the cost with time. The said fact is also apparent from a communication

dated 18.01.2016 of the MPRDCL made to the petitioner and the relevant part of the

said communication is extracted herein below :-

MADHYA PRADESH ROAD DEVELOPMENT CORPORATION LTD.

(Govt. of M.P. Undertaking)

45-A, Arera Hills, Bhopal - 462 011, Madhya Pradesh

Page 28 of 35

Tel.: (O) 0755-2765205, 2527202 - 299 (PRL Line) Fax: +91-755-2572643

Website: www.mprdc.nic.in

No. 16053/MPRDC/Procu./WO/Medical College/272/2015 Date 18.01.2016

To,

M/s Yashnand Engineers & Contractors

214/5, Khyati Complex, Mithakhali, Ellisbridge,

Ahmedabad – 382006 Gujarat

Tel: 079 – 23240202, Mob: 09824001024

E-mail: yashnandengineer@yahoo.co.in

Fax No: 079-23244186

Sub: Agreement for Construction of New Medical College and up-gradation

of Hospital at Vidisha {PAC Rs. 248.01 Crores} (Online Tender No. 379).

Ref: LoA No. 14760/MPRDC/Procu./LoA/Medical College/272/2015, Date

26/12/2015.

Your tender for the aforesaid work has been accepted by MPRDC vide

letter under reference. The agreement has been signed on 18

th

January, 2016. The

details of Agreement are as follows:

1. Agreement No. : 214/2016

2. PAC : Rs. 248.01 Crores

3. Quoted Rate : @5.40% (Five point four zero percent)

below PAC

4. Stipulated Period of Contract : 24 (Twenty Four) Months (including rainy

season)

(Narendra Kumar)

Chief Engineer

(Procurement)

31. By Clause 8 of the bidding documents, a bidder has been asked to examine

carefully all instructions, conditions of contract, contract data, forms, terms and

technical specifications, bill of quantities, forms Appendix and drawings. It has been

mentioned that failure to comply with the requirements of the bidding document shall

be at the bidder’s own risk. It has been made clear that pursuant to Clause 26 thereof,

bids which are not substantially responsive to the requirements of the bidding

documents shall be rejected. Clause 26 has provided the provision regarding

examination of bids and determination of responsiveness. It is the tendering authority

who, during the detailed evaluation of the technical bids, was to determine whether

each bid met the eligibility criteria. A bid had to be substantially responsive to the

requirements regarding qualification criteria as laid down in Clause 3 and Clause 4 of

Page 29 of 35

the bidding document. In a competitive bidding process, it is the terms and conditions

of the bidding document which decide the outcome of a bid in the bidding process.

32. The parties have not pointed out any definition of the term ‘contract value’ from

the bidding document so as to facilitate this Court in arriving at a clear view. It is the

tendering authority who has authored the bidding document and, as such, it is in the

best position to interpret and define the term ‘contract value’ in reference to which the

qualification criterion set forth in Clause 4.5A.(c) of the bidding document/SBD is to be

understood. It has become a settled position of law, more particularly, with regard to

a tender process that if two interpretations with regard to a term appearing in the

bidding document which is technical in nature, are possible then the interpretation of

the author of the bidding document/tendering authority is to be respected. The Court

is to refrain from making its own interpretation of such term and thereafter, substitute

its interpretation for such term with the interpretation given by the author of the

bidding document/tendering authority with the assumption as if it is exercising any

appellate jurisdiction, unless the interpretation given by the author of the bidding

document/tendering authority is so absurd and irrational that no prudent and

reasonable person is likely to arrive at such an interpretation.

33. What has emerged from the document dated 18.01.2016, extracted in paragraph

30 above, the Project Allocated Cost [PAC] for the subject-work i.e. ‘Construction of

New Medical Colleges and Up-gradation of Hospital at Vidisha’ was Rs. 248.01 crores.

The petitioner submitted its bid for the subject-work at a bid value below 5.40% of

the PAC. The subject-work was awarded to the petitioner at its said quoted bid value

which was Rs. 234.62 crores, meaning thereby, it had tendered to execute the subject-

work at Rs. 234.62 crores. Both these two figures for the subject-work, that is, PAC at

Rs. 248.01 crores and the tendered cost at Rs. 234.62 crores were lesser than Rs.

266.45 crores, which is approximately 40% of the bid value for the Contract Work,

that is, “Construction of New Medical College centering MMCH and Kalapahar campus

along with 800 bedded General Hospital at MMCH Campus in Guwahati”. Though the

petitioner herein has sought to interpret and equate the term ‘contract value’ with the

Page 30 of 35

final value at which the subject-work which has been executed sans the escalation

made therein and the final bill for the subject-work which has been raised, this Court

is not persuaded to reach such a view as it has found that the term ‘contract value’ is

more synonymous with the term ‘tendered cost’, as has been insisted by the author of

the bidding document/tendering authority. This Court has not found such

interpretation of the term made by the author of the bidding document/tendering

authority arbitrary, irrational and unreasonable in any manner.

34. In the considered view of this Court, a bidder like the petitioner cannot compel

its own interpretation of the term ‘contract value’ to be foisted unilaterally on the

author of the bidding document/tendering authority. It is also not open for a bidder to

demand before the Court to compel the author of the bidding document/tendering

authority to accept its interpretation of the term ‘contract value’. This Court has, thus,

refrained itself to make any endeavour to give its own interpretation to the term

‘contract value’, appearing in Clause 4.5A(c), especially not at the instance of a bidder

participating in the competitive bidding process, giving a go-by the interpretation

ascribed to the term by the author of the bidding document/tendering authority who

has authored it with the assistance of the experts in the field, by taking into purview

its requirements and its experience in the field. In such view of the matter, the prime

contention advanced on behalf of the petitioner is found not acceptable by this Court.

The ground of rejection regarding lack of necessary documentary evidence in support

of single similar nature of work is not found arbitrary, unlawful, irrational or mala fide

on the touchstone of Article 14 of the Constitution of India.

35. The matter of responsiveness of a bid is to be determined on the basis of the bid

submitted by the bidder at the time of its submission and the tendering authority can

determine the bid’s responsiveness or otherwise on the basis of the

materials/documents submitted with the bid. There is no obligation cast on the

tendering authority to call for any further information or clarification or document from

any other source, though it may call for the same in its own discretion. In the case in

hand, the tendering authority finding certain discrepancies in respect of the

Page 31 of 35

performance certificate dated 04.02.2021 had asked for certain clarification or

information from the MPRDCL on an urgent basis. That fact of calling such clarification

or information by itself had not made it binding for the tendering authority to wait for

such clarification or information. The decision to proceed with the bidding process on

16.02.2021 cannot be held to be arbitrary or illegal when there are other bidders whose

technical bids were found responsive. It is pertinent to note that the petitioner has

neither raised any whisper as regards the eligibility, qualification or capacity of the

other two participating bidders nor has contended that their technical bids and/or

financial bids were not responsive to the bidding document in any manner. Considering

the nature of the Contract Work which is worth at least of Rs. 666.1351 crores, the

qualification criterion set forth in Clause 4.5A.(c) the bidding document is to be held

as an essential condition which is to be satisfied by a bidder at the time of submission

of bid. If the information/documents furnished by a bidder are found not sufficient to

arrive at a satisfactory conclusion with regard to fulfillment of the qualification

criterion/criteria by such bidder the tendering authority is not obligated to give any

further time to furnish additional information/documents to supplement the deficient

information/documents already provided at the time of submission of the bid.

Consequently, the contention of the petitioner that the tendering authority ought to

have waited for the response from the MPRDCL cannot be countenanced.

36. Ultimately, the clarification or information, sought for by the tendering authority,

came from the MPRDCL on 25.02.2021 which was too late in the day to walk the road

again from the stage of technical bid evaluation as by that time, there has been

emergence of the successful bidder. In such view of the matter, any further dilation

on the performance certificate dated 04.02.2021 vis-à-vis the performance certificate

dated 25.02.2021 is not necessary in which respect the contention has been advanced

by the State respondents that the facts and figures in the said two performance

certificates are found at variance with each other, as averred in paragraph 12 of the

affidavit-in-opposition.

Page 32 of 35

37. The petitioner has also raised absence of public interest behind the impugned

decision of the petitioner’s disqualification at the technical bid evaluation stage by

contending that the bid values quoted by the other two participating bidders were

higher than the bid value quoted by the petitioner for the Contract Work. The

contention is made without, however, impleading the other two participating bidders

as party-respondents in the writ petition. In this connection, it would be apposite to

refer to the decision in Raunaq International Ltd. vs. I.V.R. Construction Ltd. and

others, (1999) 1 SCC 492, wherein the elements of public interest have been discussed

in the following manner :-

“10. What are these elements of public interest ? (1) Public money would be

expended for the purposes of the contract; (2) The goods or services which

are being commissioned could be for a public purpose, such as, construction

of roads, public buildings, power plants or other public utilities. (3) The

public would be directly interested in the timely fulfilment of the contract

so that the services become available to the public expeditiously. (4) The

public would also be interested in the quality of the work undertaken or

goods supplied by the tenderer. Poor quality of work or goods can lead to

tremendous public hardship and substantial financial outlay either in

correcting mistakes or in rectifying defects or even at times in re-doing the

entire work - thus involving larger outlays or public money and delaying the

availability of services, facilities or goods, e.g. a delay in commissioning a

power project, as in the present case, could lead to power shortages,

retardation of industrial development, hardship to the general public and

substantial cost escalation.

The decision in Raunaq International Ltd. (supra) has further observed that a

mere difference in the prices offered by tenderers may or may not be decisive in

deciding whether any public interest is involved in intervening in a commercial

transaction. Before making any intervention in a commercial transaction involving a

project, the Court shall also require to take into consideration that by such intervention

the proposed project may considerably be delayed thus, escalating the cost far more

than any saving. Unless the Court is satisfied that there is a substantial amount of

Page 33 of 35

public interest, or the transaction is entered into mala fide, the Court should not

intervene under Article 226 of the Constitution of India in disputes between rival

tenderers. The decision has further gone to observe in the following manner :-

“16. It is also necessary to remember that price may not always be the

sole criterion for awarding a contract. Often when an evaluation

committee of experts is appointed to evaluate offers, the expert

committee’s special knowledge plays a decisive role in deciding which

is the best offer. Price offered is only one of the criteria. The past

record of the tenderers, the quality of the goods or services which are

offered, assessing such quality on the basis of the past performance

of the tenderer, its market reputation and so on, all play an important

role in deciding to whom the contract should be awarded. At times, a

higher price for a much better quality of work can be legitimately paid

in order to secure proper performance of the contract and good

quality of work – which is as much in public interest as a low price.

The court should not to substitute its own decision for the decision of

an expert evaluation committee.”

In view of non-compliant nature of its technical bid with regard to the essential

qualification criterion which is primarily in relation to past experience, for the reasons

discussed above, this Court, taking a cue from the above observations, has not found

any merit in the petitioner’s contention about public interest for the simple reason that

the said qualification criterion with regard to past experience is intricately connected

with public interest as the Contract Work is a public project of importance in the health-

care sector.

38. On the preliminary issue, a number of decisions have been referred to on the

issue of non-joinder of necessary party. The law is settled that a necessary party is

one without whom no order can be made effectively and as such, no further dilation

is required on that aspect. As the petitioner has not impleaded the other two

participating bidders as party-respondents in this writ petition it is not open for the

Page 34 of 35

petitioner to argue regarding price differences in the bid value quoted by the petitioner

vis-à-vis the bid values quoted by the other two participating bidders, in their absence

and behind their backs. Relying on the decision in Silppi Constructions Contractors

(supra), the petitioner has sought to advance its case by stating that it is only assailing

the rejection of its technical bid. In Silppi Constructions Contractors (supra) also, the

petitioner was only challenging the rejection of its technical bid. It has been held

therein that at that stage the other tenderers were not necessary parties. The Hon’ble

Supreme Court has held that the writ petition was maintainable even in the absence

of other tenderers because till that stage there was no successful tenderer. At the

same time, it has held that who are the necessary parties would depend upon the facts

of its case. It has also been held that the position might be otherwise if a tenderer

challenges a bid awarded to another or challenges the rejection of its bid at a later

stage. It, thus, appears that the observation regarding the other tenderers not being

necessary parties, was made with regard to the particular fact situation obtaining in

that case.

39. The competitive bidding process had begun in the case in hand with the

submission of the bids by the three participating bidders with two barriers - technical

bid evaluation stage and financial bid evaluation stage – to cross for them to emerge

as the successful bidder by one of them. The petitioner was stopped by the tendering

authority at the first barrier, that is, at the technical bid evaluation stage and the other

two participants were allowed to remain in the race who eventually also crossed the

next barrier, that is, the financial bid evaluation stage. After the stage of financial bid

evaluation was over, rankings L-1 and L-2 were given to them. It was the L-1 bidder

who had emerged as the successful bidder. The petitioner also had the knowledge

who had reached the last stage in the bidding process. After emergence of the

successful bidder the only thing left to be completed by the tendering authority is the

award of the Contract Work as per the terms of the bidding document. At that stage,

the petitioner decided to challenge by this writ petition his disqualification made by the

tendering authority at the stage of technical bid evaluation. In Afcons Infrastructure

Limited (supra), the original petitioner approached the High Court when its bid was

Order downloaded on 24-12-2024 07:13:29 PMPage 35 of 35

disqualified at the technical bid opening stage. The writ petition was allowed and the

High Court had the opinion that the eligible bidders were not entitled to be either

impleaded by the ineligible bidder or were not entitled to be heard. The Hon’ble

Supreme Court has observed that the view of the High Court was not appropriate view

to take in matters like that. One of the reasons is that there could be occasions where

an eligible bidder would bring to the notice of the owner or employer of the project

that the ineligible bidder was ineligible for additional reasons or reasons that were not

within the contemplation of the owner or employer of the project. Taking note of the

aforesaid views expressed in Afcons Infrastructure Limited (supra) and Silppi

Constructions Contractors (supra) and also of the fact situation obtaining in the case

in hand where there has been identification of the successful bidder when the writ

petition was filed, I find force in the submission made on behalf of the State

respondents that the petitioner ought to have made the successful bidder a party-

respondent in the writ petition. In such view of the matter, this Court is also of the

considered view that the writ petition has suffered for non-joinder of the necessary

party.

40. In view of the discussion made above and for the reasons stated therein, this

Court has found no reason to interfere with the decision taken by the Technical Bid

Evaluation Committee on 16.02.2021 with regard to disqualification of the technical

bid of the petitioner. Consequently, the writ petition being devoid of merit, stands

dismissed. The interim order stands recalled. The respondent authorities will be at

liberty to proceed further with the competitive bidding process under reference. There

shall, however, be no order as to cost.

JUDGE

Comparing Assistant

Reference cases

Description

Legal Notes

Add a Note....