No Acts & Articles mentioned in this case
In the High Court at Calcutta
Original Civil Jurisdiction
Commercial Division
The Hon’ble Justice Sabyasachi Bhattacharyya
AP-COM No. 77 of 2024
M/s Zillion Infraprojects Pvt Ltd
Vs
Bridge and Roof Co India Ltd
With
AP No. 407 of 2022
Zillion Infraprojects Pvt Ltd
VS
Bride and Roof Co (India) Ltd
For the petitioner : Mr. Kishore Datta, Sr. Adv.
Mr. Soumen Das, Adv.
Mr. Altamash Alim, Adv.
Ms. Promita Ghose, Adv.
For the respondent : Mr. Amitabh Shukla, Adv.
Mr. Mohit Gupta, Adv.
Mr. Prakash Ch. Pandey, Adv.
Hearing concluded on : 27.06.2024
Judgment on : 08.07.2024
Sabyasachi Bhattacharyya, J:-
1. Both the applications under Section 11 of the Arbitration and
Conciliation Act, 1996 (hereinafter referred to as, “the 1996 Act”) arise
from arbitration clauses embodied in two similar contracts between
the parties. The issues involved being the same, the matters are taken
up together for hearing. 2024:CHC-OS:189
2
2. Both the agreements are works contracts issued to the petitioner by
the respondent Bridge and Roof Company (India) Limited (in short,
“the B&R”). The principal contract was executed between Indian Oil
Corporation of India Limited (IOCL) and the respondent in respect of
work regarding mechanical equipments, erection and pending works
by VGO-DHT Units of Paradwip Refinery Project of M/s. IOCLO,
Paradwip, Orissa. The work was sub -contracted to the petitioner.
Disputes and differences having arisen between the petitioner and the
respondent, the present applications have been filed.
3. The relevant clause in both the works contracts is Clause 14.0.
4. Learned senior counsel for the petitioner argues that the said Clause
provides for resolution of disputes between the petitioner/sub-
contractor and B&R. However, in case of the petitioner desires to refer
the matter to arbitration, it has to approach B&R with such request
substantiating its claim and only if B&R feels justified to initiate an
arbitration, it will invoke the arbitration clause with M/s. IOCL. The
decision of the Arbitrator will be final an d binding on the
petitioner/sub-contractor. The sub-contractor has to bear pro rata
cost of the arbitration expenses in respect of its portion of the claim.
5. Learned senior counsel highlights the inherent lopsidedness of the
clause. Even if the petitioner seeks to raise a dispute by invoking the
Arbitration clause, it has to approach B&R, despite the dispute being
against B&R itself. In such case, the petitioner has to depend on the
decision of B&R to invoke the arbitration clause. Even then, the
petitioner cannot itself participate independently in the arbitral 2024:CHC-OS:189
3
proceedings but, on the other hand, would be bound by the award
passed by the Arbitrator.
6. The other injustice implicit in the clause is that the petitioner is to
bear its portion of expenses regarding its claim, without having any
participation in the arbitral process.
7. It is argued that the said conditions of the arbitration clause are
unreasonable and violative of Article 14 of the Constitution of India
and ought to be set aside. It is argued that such question can be
entered into by the Court while taking up an application under
Section 11 of the 1996 Act and such challenge need not be restricted
to applications under Article 226 of the Constitution. In support of
such contention, learned senior counsel cites Lombardi Engineering
Ltd. v. Uttarakhand Jal Vidyut Nigam Ltd., reported at 2023 SCC
OnLine SC 1422.
8. It is further argued that since the expression of intention to refer the
disputes to arbitration finds place in the clause, the portion of the said
clause which is violative of Article 14 of the Constitution ought to be
struck down and the petitioner ought to be permitted to independently
refer the matter to arbitration in disputes between the petitioner and
the B&R.
9. For such proposition, the petitioner relies on Jagdish Chander v.
Ramesh Chander, reported at (2007) 5 SCC 719, which lays down the
well-settled principle of law that if arbitration is expressly or impliedly
provided, the matter ought to be referred to arbitration. 2024:CHC-OS:189
4
10. Learned senior counsel appearing for the petitioner further argues
that even if the petitioner consented to the arbitration clause, there
can no waiver of fundamental rights embodied in Article 14.
11. The arbitration agreement, it is argued, does not comply with and falls
fowl of Section 7 of the 1996 Act as well as the Constitution of India
and militates against the concept of party autonomy, which is
inherent in arbitration.
12. The court, it is contended, has jurisdiction to sever the
unconscionable part of the clause, retaining the intention to refer to
arbitration.
13. As such, it is argued that the matter ought to be referred to arbitration
and in view of lack of consensus between the parties in that regard,
this Court ought to appoint an Arbitrator for such purpose under
Section 11 of the 1996 Act.
14. Learned counsel for the respondent takes a preliminary objection in
that the arbitration clause specifically bars reference to arbitration in
respect of disputes exclusively between the petitioner/sub-contractor
and the respondent (B&R). In view of such negative clause, the matter
cannot be referred to arbitration, since the present dispute is between
the petitioner and B&R, and IOCL is not involved at all.
15. The respondent, in such context, relies on M.R. Engineers &
Contractors Private Ltd. v. Som Datt Builders Ltd., reported at (2009) 7
SCC 696, where the applicability of Section 7(5) of the 1996 Act was
considered and it was held that wording of the said sub-section makes
it clear that mere reference to a document in a contract would not 2024:CHC-OS:189
5
have the effect of making the arbitration clause in that document a
part of the contract. Thus, the GCC, SCC, technical specification, etc.
between the IOCL and B&R cannot be looked into to find out an
arbitration clause therein, as the petitioner is not a party in any of
such documents. Section 7(5) requires a conscious acceptance of the
arbitration clause from another document by the parties as a part of
their contract. In the absence of the same, the petitioner cannot take
advantage of the arbitration clause in the agreement between IOCL
and B&R.
16. A general reference to another contract would not suffice to import the
arbitration clause in such contract between the parties to a different
contract.
17. In the case of NBCC (India) Ltd. v. Zillion Infraprojects Pvt. Ltd.,
reported at 2024 SCC OnLine SC 323, the Supreme Court relied on the
judgment of M.R. Engineering (supra) and set aside the order of the
Delhi High Court whereby an Arbitrator was appointed for
adjudication of disputes between NBCC and Zillion, the present
petitioner. There, the Supreme Court was considering similar facts as
in the present case. As such, the ratio of the said judgment is binding
in the present case as well.
18. In the instant case, there is only a general reference to GCC, SCC,
technical specification, etc. issued by IOCL to the respondent in the
contract between the parties. The arbitration clause contained in the
GCC issued by IOCL is not incorporated in the agreement between the
petitioner and the B&R. On the contrary, the condition s of this 2024:CHC-OS:189
6
particular agreement provide that the disputes between the parties
herein shall not be referred to arbitration or to any similar Alternative
Dispute Resolution forum.
19. It is next argued that the respondent is not relying on the restrictive
part of Clause 14.0, which is the arbitration clause. Even if such part
of Clause 14.0 is severed, the other part still remains which states
that the disputes between the parties shall not be adjudicated through
arbitration or similar disputes resolution system, which means that
there cannot be a reference of such disputes to arbitration or to other
similar Alternative Dispute Resolution forums. Thus, the proposition
in Lombardi Engineers Ltd. (supra) does not apply. Hence, it is argued
that the applications under Section 11 of the 1996 Act ought to be
dismissed.
20. The moot question which falls for consideration in the present case is
whether there is a valid arbitration clause in the agreement between
the parties which covers the disputes raised by the petitioner.
21. For deciding such issue, the relevant arbitration clause in the
agreement between the present parties is required to be gone into and
is set out below:
“14.0 The Arbitration of disputes if any between IOCL & B&R will be
final & binding upon the subcontractor. No dispute can be
adjudicated separately through arbitration or any other similar
forum for any disputes between subcontractor & B&R. However
incase subcontractor desires B&R to raise certain disput es
pertaining to its claim for reference to arbitration, the
subcontractor shall approach B&R with such request
substantiating its claim and incase B&R feels justified to initiate
an arbitration (decision of concerned General Manager of B&R in
this regard will be final & binding), the arbitration may be 2024:CHC-OS:189
7
invoked by B&R with M/s. IOCL and decision of the arbitrator
will be final and binding upon the subcontractor for all disputes.
However the subcontractor has to bear prorata cost of its portion
of claim of arbitration expenses. The jurisdiction of Court, if
situation so arises, in any circumstances shall be at Kolkata.
22. A perusal of the clause shows that there are primarily two components
of the same. The first part, apart from lending finality to the decision
of the Arbitrator, provides that any dispute between the sub-
contractor/petitioner and the contractor/B&R is not to be adjudicated
separately through arbitration or in other similar forum.
23. The second component deals with issues pertaining to disputes
between the contractor (B&R) and/or the sub-contractor (petitioner)
on the one hand and M/s IOCL on the other.
24. According to the second limb of the arbitration clause, in case the
subcontractor desires B&R to raise a dispute pertaining to its claim
for reference to arbitration, the sub-contractor shall approach B&R
with such request. If the B&R feels it justified to initiate an arbitration
on the said claim, regarding which the decision of the General Manger
of B&R will be final, arbitration may be invoked by B&R with M/s
IOCL, in which case the sub-contractor has to bear pro rata cost of its
portion of the claim of arbitration expenses. The jurisdiction of the
court has been fixed at Kolkata.
25. Hence, there are two distinct sub-divisions in the clause. The first part
deals with disputes arising between the subcontractor (petitioner) and
the respondent/ B&R. Regarding such dispute s, it is specifically
provided that such dispute cannot be adjudicated through arbitration 2024:CHC-OS:189
8
or any similar forum. The obvious meaning of “similar’’ is any other
Alternative Dispute Redressal forum.
26. Although in the succeeding sentence, being the second limb of the
clause, it is not made clear as the whether the disputes sought to be
raised by the sub-contractor pertaining to its claim has to be against
IOCL or can be exclusively against B&R only, the rest of the provision,
read harmoniously, leaves no manner of doubt that such dispute has
to be against the IOCL. Otherwise, an absurdity would arise inasmuch
as the subcontractor has to approach the respondent/contractor, the
very entity against which the dispute is raised, for deciding even
whether to initiate an arbitration proceeding. Further, in such event
there would be no scope of the petitioner paying its portion of the
arbitration expenses, as in such cases the entire dispute would be
between the petitioner and the respondent/contractor and there
would not be any occasion to calculate any pro rata portion of the
petitioner’s costs. A cardinal rule of construction of documents is that
any interpretation which leads to absurdity or unworkability is to be
avoided. Since the provisions of the present arbitration clause can be
read harmoniously without imputing any such absurdity, such
harmonious construction is to be adopted by the court.
27. Hence, it is inevitable that the claim which is proposed by the
petitioner to the respondent for being taken up in arbitration has to be
a component of the primary dispute raised by the respondent against
the IOCL where the petitioner may also have a say since it will also be
affected, being bound by the arbitration between B&R and IOCL. In 2024:CHC-OS:189
9
such cases, the petitioner has to approach the respondent with the
petitioner’s claim against the IOCL, the respondent deciding whether
to incorporate such component in its arbitration with IOCL or
independently raise it with IOCL.
28. The cardinal challenge by the petitioner is on the footing of violation of
Article 14 of the Constitution. A perusal of the arbitration clause
shows that it is segregable into two parts – the first part dealing with
disputes between the petitioner and the respondent, which is non-
arbitrable, and the second dealing with disputes between the B&R and
the IOCL, in which case the petitioner can side with the B&R and seek
to raise its sub-claim against the IOCL through the respondent, in the
arbitral proceedings initiated between the respondent and the IOCL.
29. It is evident that the second part is unjust and violative of party
autonomy, since the petitioner would not, in such case, have any
participation in the arbitral process with IOCL, although it has a stake
in the outcome of the same. Moreover, the decision whether to take
the claim of the petitioner to arbitration also lies within the exclusive
discretion of the respondent, which is also unjust and lopsided. The
petitioner, in such case, has to pay according to its portion of the
claim but have no participation in the arbitration, which definitely is
violative of Article 14 of the Constitution of India and ought to be
struck down.
30. However, as discussed above, the second limb being segregable,
striking down the same does not affect the first limb which clearly 2024:CHC-OS:189
10
debars any exclusive dispute between the petitioner and the
respondent from being referred to arbitration.
31. The petitioner has argued that the arbitration clause does not comply
with and falls fowl of Section 7 of the 1996 Act. Section 2(1)(b) of the
1996 Act defines “arbitration agreement” to mean an agreement
referred to in Section 7. Section 7 provides that an arbitration
agreement means an agreement by the parties to submit to arbitration
all or certain disputes which have arisen or which may arise between
them in respect of a defined legal relationship, whether contractual or
not.
32. In the present case, the arbitration clause, insofar as it relates to
disputes between the petitioner/sub -contractor and the
respondent/contractor is concerned, which is a defined legal
relationship, provides in clear terms that no such dispute can be
adjudicated separately through arbitration or any other similar forum.
In view of the negative language used in the said provision, there is a
clear bar to disputes between the petitioner and the respondent to be
referred to arbitration.
33. There is nothing in the other part of the said clause to create such
right of reference of exclusive disputes between the petitioner and the
respondent to arbitration. The rest of the clause deals with disputes
against the IOCL. Such dispute may be solely between the respondent
and the IOCL or might have some components of challenge by the
petitioner as well. Clause 14.0, the arbitration clause in the
agreement between the petitioner and the respondent, provides that in 2024:CHC-OS:189
11
case of such disputes between the respondent and the IOCL, t he
petitioner may add its own component, subject to the discretion of the
respondent, in which case, the petitioner would not have participatory
right but would be liable to pay its portion of the expenses.
34. Hence, there is no violation of Section 7 of the 1996 Act, at least
insofar as the petitioner and the respondent are concerned.
35. Admittedly, the present dispute has arisen exclusively between the
petitioner and the respondent, the IOCL having no part to play in it.
36. Although the agreement between the petitioner and the respondent, in
certain places, refers to the GCC, SCC, technical specification,
drawings, addendums and other clauses to which the IOCL is also a
party, there is no specific provision in the agreement between the
present parties incorporating the arbitration clause therein in the
contract between the present parties. As held in NBCC (India) Ltd.
(supra), Section 7(5) of the 1996 Act provides for a conscious
acceptance of the arbitration clause from any document by the parties
as a part of their contract, before such arbitration clause could be
read as a part of the contract between the parties.
37. Section 7(5) stipulates that the reference in a contract to a document
containing an arbitration clause constitutes an arbitration agreement
if the contract is in writing and the reference is such as to make that
arbitration clause part of the contract.
38. In the present case, however, there is not a single sentence in the
agreement between the petitioner and the respondent to indicate that
the arbitration clause in the agreements between the IOCL and the 2024:CHC-OS:189
12
respondent have been made a part of the contract between the
petitioner and the respondent.
39. Again, in M.R. Engineers (supra), Section 7(5) was discussed and it
was held in categorical terms that the arbitration clause from another
contract can be incorporated into the contract only by specific
reference to the arbitration clause in the other contract.
40. In the present case, such specific incorporation being absent, it
cannot be said that the petitioner can take advantage of the
arbitration clause in the agreements between the IOCL and the
respondent.
41. The only clause relating to arbitration which is operative insofar as the
petitioner is concerned, is Clause 14.0 in the agreement between the
petitioner and the respondent which, in specific terms, debars any
arbitration regarding disputes arising exclusively between the
petitioner and the respondent.
42. The petitioner further alleges violation of Artic le 14 of the
Constitution. The restriction to refer matters between the petitioners
and respondent to arbitration merely restricts the forum to civil courts
and other forums under general law, precluding any reference to
arbitration or other Alternative Dispute Resolution forum. Clause 14.0
merely states in that regard that such disputes cannot be adjudicated
through arbitration or any other “similar forum”, meaning thereby any
other Alternative Dispute Resolution Forum, and does not take away
the remedy of the petitioner under general law to move the civil court
or any other forum, if available under any other law. Hence, it cannot 2024:CHC-OS:189
13
be said that the right of the petitioner to have access to justice has
been curtailed in any manner.
43. Arbitration is a choice to be exercised on consensus by the parties.
The petitioner entered into the contract with the respondent with open
eyes and nothing prejudicial to the petitioner has been incorporated in
the said agreement by precluding arbitratio n regarding disputes
between the present parties which could be said to take away the
party autonomy of the petitioner. The petitioner cannot selectively
pick and choose particular terms of the agreement and shut its eyes
or assail the others. The ground of unequal bargaining power is not
applicable, since the petitioner took full advantage of the contract and
did the work envisaged therein.
44. The petitioner places reliance on Lombardi Engineering Ltd. (supra)
where it was held that the court, while considering an application
under Section 11(6) of the said 1996 Act, can test the validity or
reasonableness of the condition stipulated in the arbitration clause at
the touch-stone or anvil of Article 14 of the Constitution.
45. Again, in Jagdish Chander’s case, the Supreme Court observed that
the court may sever and declare unenforceable a provision of the
arbitration clause that is violative of law or fundamental rights.
46. In the present case, there are two clearly segregable parts of the
arbitration clause. The first part deals with a specific bar to
arbitration in respect of disputes arising exclusively between the
petitioner and the respondent. On the other hand, the second limb of 2024:CHC-OS:189
14
the clause deals with disputes between the respondent and the IOCL
where the petitioner may also stake a claim.
47. Thus, the segregation is complete in the clause between the disputes
arising exclusively between the petitioner and the respondent and
those arising between the IOCL and the one hand and the respondent
and, in certain cases the petitioner, on the other.
48. Insofar as the first part is concerned, there is a specific bar to
arbitration. The petitioner tends to argue that if there is an intention
of the parties to refer matters to arbitration, the same has to be
honoured unless the provision is totally unworkable.
49. In the present case, there is no dichotomy or unworkability, nor is
there any absurdity or violation of Article 14 of the Constitution of
India insofar as the portion of the arbitration clause dealing with
disputes between the petitioner and the respondent is concerned. The
clause clearly provides a bar to reference of such disputes to
arbitration. Thus, the intention to refer to arbitration of disputes
arising exclusively between the petitioner and the respondent, which a
sine qua non for such reference in the first place, is completely absent
in the said clause. It is not for the Court, sitting in jurisdiction under
Section 11 of the 1996 Act, to modify the contract and carve out such
right for the parties where the parties themselves choose not to confer
upon themselves the same.
50. Hence, Clause 14.0 does not, in any manner, clothe the petitioner or
the respondent with any right to refer the disputes which arise inter se
between them to arbitration. 2024:CHC-OS:189
15
51. However, insofar as the other part of the said clause is concerned, the
same imposes unreasonable fetters on the petitioner in respect of
disputes with the IOCL. In such cases, the petitioner is given a right
to raise the issue with the respondent and join in an arbitration
initiated by the respondent against the IOCL.
52. There are two components of such provision which militate against
Article 14 of the Constitution. First, the petitioner is not allowed to
participate in the proceedings, although mandated to bear the
expenses regarding its portion of the claim. Secondly, even the
reference of the dispute to the adjudicatory forum is left entirely to the
discretion of the respondent, thereby denuding the petitioner of its
independent right to raise a dispute before the appropriate
adjudicatory authority. Such curtailment of right tantamounts to
contravention of the right to access to justice, which is a fundamental
component of the right to equality enshrined in Article 14 of the
Constitution.
53. Hence, such second limb of the arbitration clause, being violative of
Article 14 of the Constitution of India, is hereby struck down insofar
as the petitioner is concerned. The effect of such striking down is that
the petitioner will be at liberty to raise any dispute against the IOCL
alone or against the IOCL as well as the respondent, if the petitioner
so chooses, before the competent civil court having jurisdiction and/or
any other authority if vested with such adjudicatory power under any
other statute. However, there is no scope of the petitioner joining in
an arbitration proceeding between the respondent and the IOCL, since 2024:CHC-OS:189
16
the petitioner is not a party to the other agreements between the IOCL
and the respondent which contemplate arbitration between them.
54. Thus, in view of the above discussions, this Court c omes to the
following conclusions:
(i) Disputes arising out of or in respect of the agreement between
the petitioner and the respondent exclusively are not amenable
to arbitration due to the specific bar in the arbitration clause.
(ii) In the event the petitioner has a dispute against IOCL where the
respondent may or may not be a party, it will be open to the
petitioner to ignore the arbitration clause, that is, Clause 14.0
and the restrictions imposed therein and to independently file a
legal action before the competent civil court and/or any other
authority, if vested with such power under any other statute
than the Arbitration and Conciliation Act, 1996.
(iii) As a result, the petitioner is not entitled to invoke the
arbitration clause in the present dispute, which arises
exclusively between the petitioner and the respondent, in view of
the specific bar in Clause 14.0 of the agreement between the
parties.
(iv) However, the petitioner will be at liberty to file a regular civil
suit before the competent civil court and/or move any other
forum if the petitioner has such right under any other statute
than the Arbitration and Conciliation Act, 1996.
55. In view of the above, there is no occasion for this Court to appoint an
Arbitrator in respect of the present dispute. As such, the applications 2024:CHC-OS:189
17
under Section 11 of the Arbitration and Conciliation Act, 1996 are not
maintainable in law.
56. Hence, AP-COM No. 77 of 2024 and AP No. 407 of 2022 are dismissed
on contest without any order as to costs, leaving it open for the
petitioner to approach the competent civil court or any other statutory
forum with the disputes raised by the petitioner with the respondent.
57. There will be no order as to costs.
58. Urgent certified server copies, if applied for, be issued to the parties
upon compliance of due formalities.
( Sabyasachi Bhattacharyya, J. ) 2024:CHC-OS:189
Legal Notes
Add a Note....