As per case facts, the plaintiff, a public limited company, had a long-standing banking relationship with the defendant bank since 1963, availing working capital facilities. In 2018, the bank unilaterally ...
Appeal (CAD) (MD).No.2 of 2025
BEFORE THE MADURAI BENCH OF MADRAS HIGH COURT
Reserved on : 28.04.2026Pronounced on : 23.06.2026
CORAM:
THE HONOURABLE MR.JUSTICE N.ANAND VENKATESH
and
THE HONOURABLE MR.JUSTICE K.K.RAMAKRISHNAN
Appeal (CAD) (MD).No.2 of 2025
M/s.Kovilpatti Lakshmi Roller,
Flour Mills Limited,
Registered Office at 75/8,
Benares Cape Road,
Gangaikondan – 627352,
Tirunelveli,
Represented by its Company Secretary,
S.Piramuthu. ... Appellant / Plaintiff
Vs.
M/s.Canara Bank,
having its Head Office at
112, JC Road, Bengaluru,
Karnataka – 560002 and its Branch at
52C/41/13,
Ettayapuram Rajah Building,
Page 1 of 57 https://www.mhc.tn.gov.in/judis
Appeal (CAD) (MD).No.2 of 2025
Tirunelveli Junction,
Tirunelveli – 627001,
through its Chief Manager. ... Respondent / Defendant
PRAYER: Appeal – Commercial Appellate Division has been filed under
Section 13 of the Commercial Courts Act, to set aside the judgment and
decree dated 05.11.2024 made in O.S.No.148 of 2021 (Commercial Original
Suit) on the file of the learned Principal District Judge, Tirunelveli and to
allow the above appeal.
For Appellant : M/s.N.Krishnaveni,
Senior Counsel
for Mr.P.Thiyagarajan
For Respondent : Mr.N.Dilip Kumar
J U D G M E N T
(Judgment of the Court was made by K.K.RAMAKRISHNAN,J. )
The Appeal – Commercial Appellate Division has been filed by the
appellant/plaintiff to set aside the judgment and decree dated 05.11.2024
made in O.S.No.148 of 2021 (Commercial Original Suit) on the file of the
learned Principal District Judge, Tirunelveli and to allow the above appeal.
Page 2 of 57 https://www.mhc.tn.gov.in/judis
Appeal (CAD) (MD).No.2 of 2025
2. For the sake of convenience and better appreciation of the facts, the
parties are referred to according to their rank before the Trial Court.
3. The brief averments of the plaint are as follows:
3.1. The plaintiff is a public limited company having two distinct
business divisions, namely, the flour mill division and the engineering
division. The plaintiff had availed working capital facilities from the
defendant bank in the year 1963 to the tune of Rs.29.70 crores. The said
working capital limit was being renewed periodically every year. Out of the
said limit of Rs.29.70 crores, a sum of Rs.28.70 crores was availed for the
flour mill division and a sum of Rs.1 crore was availed for the sheet metal
division.
3.2. In the year 2018, the defendant bank unilaterally increased the rate
of interest on the working capital loan from 11.10% to 13.70% with effect
from 02.05.2018 through the sanction memorandum dated 13.04.2018.
Since the other banks, particularly HDFC Bank, were charging only 10.30%
interest, the plaintiff, by communications dated 28.05.2018 and 10.01.2019,
Page 3 of 57 https://www.mhc.tn.gov.in/judis
Appeal (CAD) (MD).No.2 of 2025
requested the defendant bank to reduce the rate of interest. However, the
defendant failed to consider the said request.
3.3. According to the plaint, the respondent bank neither responded to
the plaintiff's request nor reduced the rate of interest. In the meantime, the
validity period of the sanction memorandum dated 13.04.2018 expired and
the process for renewal of the working capital facilities for the financial
year 2019–2020 commenced. The plaintiff once again requested the
respondent bank to reduce the rate of interest.
3.4. The plaintiff would further aver that, although the respondent
bank had expressed its willingness to consider a reduction in the rate of
interest through its communications, no reduction was granted.
Consequently, the plaintiff submitted a further representation seeking
reduction of the interest rate. In the said communication dated 20.12.2018
the plaintiff also expressed its intention to adopt a multiple banking
arrangement involving other banks, including HDFC Bank and Axis Bank,
and proposed a reduction of its working capital exposure with the
Page 4 of 57 https://www.mhc.tn.gov.in/judis
Appeal (CAD) (MD).No.2 of 2025
respondent bank from 29.70 crores to approximately 13.50–14.50 crores.
3.5. Thereafter, the respondent bank issued a sanction memorandum
dated 06.05.2019, valid up to 09.04.2020, whereby the rate of interest for
the working capital facilities was reduced to 11.50%, broadly in line with
the rates prevailing in the earlier years. However, the said sanction
memorandum contained a specific condition that, in the event of the credit
facilities being taken over by another bank, the concession in the rate of
interest extended during the preceding year would be recovered from the
borrower before closure of the account. The said condition formed part of
the sanction terms conveyed to the plaintiff.
3.6. The plaintiff never accepted the Sanction Memorandum and sent a
communication dated 03.06.2019 requesting deletion of the aforesaid
clause. According to the plaintiff, although the Sanction Memorandum bore
the date 06.05.2019, the acceptance containing the endorsement “accepted
subject to the offer letter dated 03.06.2019” was obtained only after June
2019. The plaintiff thereafter addressed further communications requesting
Page 5 of 57 https://www.mhc.tn.gov.in/judis
Appeal (CAD) (MD).No.2 of 2025
deletion of the aforesaid condition relating to recovery of the interest
concession upon transfer of the account to another bank. Simultaneously,
the plaintiff continued to seek reduction of the rate of interest.
3.7. While matters stood thus, the subsequent renewal period
approached. During the outbreak of the COVID-19 pandemic, the
respondent bank sanctioned additional facilities to the plaintiff, including a
term loan and ad hoc working capital assistance. The plaintiff also decided
to discontinue its Sheet Metal Division and requested the respondent bank
to release the collateral securities proportionate to the liabilities pertaining
to the said division.
3.8. According to the plaint, discussions continued between the
parties concerning reduction of the rate of interest, release of securities,
restructuring of banking arrangements and other related issues. During this
period, the respondent bank sanctioned a term loan of 2.77 crores and ad
hoc temporary working capital facilities of 2.95 crores under a sanction
dated 22.04.2020.
Page 6 of 57 https://www.mhc.tn.gov.in/judis
Appeal (CAD) (MD).No.2 of 2025
3.9. The plaintiff would further contend that, since the respondent
bank did not favorably consider its requests regarding release of a portion of
the collateral securities and reduction of the rate of interest, it ultimately
decided to close its loan accounts with the respondent bank. Accordingly, on
08.09.2020, the plaintiff settled the outstanding liabilities and sought
closure of the accounts. However, the respondent bank allegedly declined to
release the title deeds and issue the closure certificate insisting the plaintiff
to pay the differential interest amount claimed under the condition
incorporated in the sanction memorandum dated 06.05.2019. The bank also
demanded commitment charges in respect of certain facilities that had been
sanctioned but not availed by the plaintiff.
3.10. The plaintiff requested waiver of the differential interest and
commitment charges on the ground that the facilities had not been utilized
and also that the demands were otherwise unjustified. The respondent bank,
however, declined the request. Due to the necessity of obtaining the title
deeds and closure certificate in order to secure credit facilities from other
banks offering finance at substantially lower rates of interest, the plaintiff
Page 7 of 57 https://www.mhc.tn.gov.in/judis
Appeal (CAD) (MD).No.2 of 2025
paid the amounts demanded under protest. After obtaining the discharge
documents, release of securities and closure certificate, the plaintiff shifted
its banking arrangements to another financial institution. Thereafter,
claiming that the amounts collected towards differential interest pursuant to
the condition contained in the sanction memorandum dated 06.05.2019 and
the commitment charges were illegal and not recoverable in law, the
plaintiff instituted the present suit seeking recovery of the said amounts
together with consequential reliefs.
4. The brief averments of the written statement filed by the
defendants are as follows:-
4.1. The defendant bank filed a written statement denying the
allegations made in the plaint and contended that the plaintiff was liable to
pay the commitment charges as well as the differential interest in view of
the specific clauses contained in the sanction memorandum dated
06.05.2019, which had been accepted by the plaintiff. According to the
defendant, the reduction in the rate of interest was granted subject to the
condition that, in the event of takeover of the loan account by another bank,
Page 8 of 57 https://www.mhc.tn.gov.in/judis
Appeal (CAD) (MD).No.2 of 2025
the plaintiff would be liable to pay the said charges.
4.2. The defendant further contended that, since the loan facilities had
been sanctioned and enjoyed by the plaintiff, the commitment charges were
legally recoverable. It was also stated that the defendant had made the claim
strictly in accordance with the contractual terms agreed upon between the
parties. Hence, the defendant prayed for dismissal of the suit. On the basis
of the pleadings, the learned Trial Judge framed necessary issues and
proceeded the trial.
5. On the side of the plaintiff, one witness was examined as P.W.1 and
documents were marked as Exhibits A1 to A13. On the side of the defendant
bank, the Branch Manager was examined as D.W.1. However, no document
was marked on the side of the defendant.
6. The learned Trial Judge, upon consideration of the oral and
documentary evidence available on record, dismissed the suit filed by the
plaintiff/appellant holding that, in terms of the contractual conditions, the
Page 9 of 57 https://www.mhc.tn.gov.in/judis
Appeal (CAD) (MD).No.2 of 2025
defendant bank was entitled to recover the differential interest as well as the
commitment charges. The learned Trial Judge further held that, since the
loan facilities had been availed and enjoyed by the plaintiff, the levy of
commitment charges was justified. Aggrieved by the said judgment and
decree dated 05.11.2024, the plaintiff has preferred the present appeal
before this Court.
7. Submission of the learned Senior Counsel appearing for the
appellant:
7.1. The learned Senior Counsel for the appellant/plaintiff would
submit that the Court below failed to properly appreciate the specific and
consistent case of the plaintiff. According to the plaintiff, the respondent
bank had no legal authority to demand the differential interest on the basis
of the sanction memorandum dated 06.05.2019, since the said condition was
never unconditionally accepted by the plaintiff. The learned Senior Counsel
appearing for the plaintiff/appellant would submit that the rider clause
incorporated in the sanction memorandum dated 06.05.2019 is contrary to
the fundamental principles governing the law of contracts and is also
Page 10 of 57 https://www.mhc.tn.gov.in/judis
Appeal (CAD) (MD).No.2 of 2025
opposed to public policy. According to the learned Senior Counsel, the said
rider clause is, therefore, void and unenforceable in law. immediately upon
receipt of the sanction memorandum, the plaintiff, by letter dated
03.06.2019, specifically objected to the disputed condition and requested
deletion of the same. the signature also obtained in the sanction
memorandum dated 06.05.2019 after the receipt of communication dated
03.06.2019 and therefore, according to the learned Senior Counsel
appearing for the appellant, it cannot be construed as unconditional
acceptance of the disputed clause, particularly when the plaintiff had
already recorded his protest and reservation through the communication
dated 03.06.2019.
7.2. The learned Senior Counsel would further submit that under
Section 7 of the Indian Contract Act, 1872, acceptance must be absolute and
unqualified in order to result in a concluded contract. In the present case,
the plaintiff never accepted the disputed condition relating to recovery of
the differential interest. On the contrary, the communications placed on
record clearly establish that the plaintiff consistently opposed the said
Page 11 of 57 https://www.mhc.tn.gov.in/judis
Appeal (CAD) (MD).No.2 of 2025
condition. Therefore, the alleged acceptance amounted only to a counter-
offer which, in law, would not result in a concluded acceptance. It is further
submitted that even in the earlier sanction communication issued prior to the
sanction memorandum dated 06.05.2019, no such condition regarding
recovery of differential interest was incorporated and the rate of interest was
prescribed only at 11.70%. Subsequently, the respondent bank unilaterally
introduced the disputed clause in the sanction memorandum dated
06.05.2019. Even thereafter, the plaintiff, through subsequent
communications, reiterated that he can never agree to such a condition.
7.3. The learned Senior Counsel would submit that such unilateral
recovery, without lawful consensus ad idem between the parties, is opposed
to the fundamental principles governing contracts and is also against public
policy. Hence, the disputed clause itself is unenforceable in law.
Accordingly, it is contended that the claim made by the respondent bank
towards the alleged differential interest is legally unsustainable and the
learned trial Judge failed to properly consider the above vital aspects in the
correct perspective.
Page 12 of 57 https://www.mhc.tn.gov.in/judis
Appeal (CAD) (MD).No.2 of 2025
7.4.The learned Senior Counsel appearing for the plaintiff further
submitted that the finding of the learned trial Judge that there existed a
binding contract between the plaintiff and the defendant bank merely on the
basis of continuation of banking transactions from May 2019 to September
2020 is legally unsustainable. According to the learned Senior Counsel for
the plaintiff, in terms of Section 7 of the Indian Contract Act, it was
incumbent upon the defendant Bank to respond to the plaintiff's various
communications seeking deletion of the clauses contained in the Sanction
Memorandum dated 06.05.2019. It is contended that, in the absence of any
such response, there was an implied acceptance of the plaintiff's request for
deletion of the said clauses. The learned Senior Counsel further submitted
that, notwithstanding the plaintiff's communications, the defendant Bank
continued the existing credit facilities and sanctioned the further term loan
and working capital loan extension without insisting upon an unconditional
acceptance of the subsequent Sanction Memorandums. Such conduct,
according to the learned Senior Counsel, amounts to acceptance by conduct
of the plaintiff's counter-offer. Consequently, the parties stood governed by
the modified terms proposed by the plaintiff and not by the original terms
Page 13 of 57 https://www.mhc.tn.gov.in/judis
Appeal (CAD) (MD).No.2 of 2025
contained in the Sanction Memorandum dated 06.05.2019. Therefore, the
defendant Bank has no cause of action to recover commitment charges,
interest, or any other amount founded upon the clauses contained in the
Sanction Memorandum dated 06.05.2019.
7.5. Subsequently, a different term loan proposal was processed by the
bank. However, the plaintiff never accepted nor appropriated the said loan.
On account of the conditions imposed by the bank, including refusal to
release the collateral securities and refusal to reduce the rate of interest, the
plaintiff did not proceed with the said transaction. Therefore, according to
the learned Senior Counsel, the finding of the learned trial Judge runs
contrary to the pleadings and evidence adduced by the bank. The learned
trial Judge erroneously shifted the burden of proof upon the plaintiff by
holding that, unless the plaintiff expressly refused to accept the loan, the
subsequent transactions amounted to acceptance of the terms of the
Sanction Memorandum. The learned Senior Counsel would further contend
that, under Section 7 of the Indian Contract Act, 1872, an acceptance must
be absolute and unqualified in order to result in a concluded contract. If the
Page 14 of 57 https://www.mhc.tn.gov.in/judis
Appeal (CAD) (MD).No.2 of 2025
offeree varies the terms of the proposal or expressly refuses to accept any of
its conditions, such response amounts to a counter-offer and not an
acceptance. In such circumstances, it is for the proposer, namely the
respondent Bank, either to accept or reject the counter-offer. Where the
proposer acts upon the counter-offer without rejecting it, there is an implied
acceptance of the modified terms, thereby resulting in a concluded contract
on the basis of the counter-offer.Developing the above submission, the
learned Senior Counsel would argue that the Bank, by its subsequent
conduct, accepted the counter-proposal made by the plaintiff/appellant. The
subsequent sanction memoranda did not reiterate or insist upon the disputed
rider clause. On the contrary, the Bank proceeded to sanction and disburse
the loan facilities, thereby clearly evincing its intention to act upon the
modified terms. Consequently, the original rider clause contained in the
sanction memorandum dated 06.05.2019 stood waived or abandoned by
conduct. The learned trial Judge failed to appreciate that the plaintiff had
already furnished substantial securities, the value of which exceeded the
working capital limits sanctioned by the defendant Bank. In such
circumstances, the mere continuation of banking transactions could not be
Page 15 of 57 https://www.mhc.tn.gov.in/judis
Appeal (CAD) (MD).No.2 of 2025
construed as an unconditional acceptance of the disputed terms of the
Sanction Memorandum.
7.6. It was further contended that the bank sought to recover only the
differential interest on the strength of the sanction memorandum dated
06.05.2019 and the conditions incorporated therein. The Court below erred
in extending the applicability of the said sanction memorandum to the
subsequent continuation of the account till September 2020, despite the
absence of signature of the plaintiff in the said sanction memorandums.
7.7. The learned Senior Counsel also assailed the further finding of the
trial Court that the continuance of banking transactions for about sixteen
months itself established acceptance of the contractual terms. According to
him, several communications had been addressed by the plaintiff objecting
to the conditions imposed by the bank and at no point of time did the
plaintiff agree to the revised terms. The transaction in question related to the
2020 term loan, which was never accepted by the plaintiff. The bank
unilaterally sanctioned the loan and credited the amount into the plaintiff’s
Page 16 of 57 https://www.mhc.tn.gov.in/judis
Appeal (CAD) (MD).No.2 of 2025
account. However, the plaintiff never utilized the said amount in view of the
onerous conditions imposed by the bank.
7.8. The learned Senior Counsel would therefore submit that, in the
absence of any concluded acceptance of the original sanction memorandum
containing the disputed rider clause, the respondent Bank cannot
subsequently seek to enforce the said clause or claim the differential rate of
interest on its basis. It is further submitted that, notwithstanding the
plaintiff's repeated communications, the Bank sanctioned and disbursed
additional loan facilities without obtaining the plaintiff's consent. According
to the learned Senior Counsel, the plaintiff had specifically requested the
Bank to release the securities furnished in respect of Metal Sheet Company
and to issue the necessary permission to enable the plaintiff to avail
additional credit facilities from a third-party bank. However, the respondent
Bank neither acceded to those requests nor resolved the disputes that had
arisen between the parties.
7.9. The learned Senior Counsel would also point out that, in several
Page 17 of 57 https://www.mhc.tn.gov.in/judis
Appeal (CAD) (MD).No.2 of 2025
instances, the Bank sanctioned and disbursed loan facilities without
obtaining the plaintiff's signature on the relevant sanction memoranda. In
certain cases, the signatures were obtained only after a considerable lapse of
time, while in other cases no signatures were obtained at all. According to
the learned Senior Counsel, this conduct was attributable to the strained
relationship that had developed between the parties, particularly after the
plaintiff requested closure of the loan accounts and objected to the Bank's
refusal to release the securities. On the above submissions, the learned
Senior Counsel prayed that the appeal be allowed by setting aside the
judgment and decree of the learned Trial Judge.
7.10. To substantiate his submissions, the learned Senior Counsel
appearing for the plaintiff relied upon number of precedents.
8. Submission of the learned Counsel appearing for the bank:
8.1. Per contra, the learned counsel appearing for the bank submitted
that the learned trial Judge had correctly appreciated the entire sequence of
events between the parties. According to the learned counsel, the plaintiff
Page 18 of 57 https://www.mhc.tn.gov.in/judis
Appeal (CAD) (MD).No.2 of 2025
had continuously transacted with the respondent bank from 2019 till
September 2020 and had maintained customer relationship with the bank for
more than sixteen years. Having continued such business relationship, the
plaintiff cannot now contend that there was no agreement between the
parties.
8.2. The learned counsel further submitted that the conduct of the
plaintiff amounted to acceptance and appropriation of the facilities extended
by the bank and that the plaintiff cannot subsequently reprobate the same. It
was also contended that once the conditions were incorporated in the
sanction memorandum dated 06.05.2019, the bank became entitled to
recover the differential rate of interest.
8.3. The learned counsel for the bank further submitted that though
the plaintiff had purportedly accepted the sanction subject to the letter dated
06.06.2019, the said conditional acceptance was never accepted by the
bank. At the same time, the plaintiff never expressly declined the sanction
granted under the memorandum dated 06.05.2019. Hence, according to the
Page 19 of 57 https://www.mhc.tn.gov.in/judis
Appeal (CAD) (MD).No.2 of 2025
bank, the plaintiff remained liable to pay the differential interest consequent
upon closure of the change -over account and transfer of dealings to another
bank.
8.4. Insofar as the claim for commitment charges is concerned, the
learned counsel submitted that the loan had already been sanctioned and the
sanctioned amount remained in the plaintiff’s account till September 2020.
Therefore, according to the bank, the facility stood duly sanctioned and kept
available to the plaintiff, thereby entitling the bank to recover commitment
charges.
8.5. The learned counsel for the bank finally submitted that the
conditions imposed under the sanction memorandum were not opposed to
public policy, as they were in consonance with the guidelines issued by the
Reserve Bank of India. Hence, there was no legal basis to hold the said
conditions to be void on the ground of public policy. On the above
submissions, the learned counsel prayed for confirmation of the judgment
and decree passed by the trial Court.
Page 20 of 57 https://www.mhc.tn.gov.in/judis
Appeal (CAD) (MD).No.2 of 2025
8.6. The learned counsel for the bank mainly advanced his
submissions on two grounds. Firstly, he contended that the judgments relied
upon by the bank have consistently held that where acceptance of a contract
is clear, unequivocal, and reflected through conduct, there is no necessity
for independent proof that the acceptance was qualified and absolute.
According to the learned counsel, Section 7 of the Indian Contract Act
contemplates that acceptance may be expressed in a usual and reasonable
manner. In the present case, following the ordinary banking procedure, the
loan was sanctioned at the concessional rate of interest of 11.5%, subject to
the conditions incorporated in the sanction memorandum dated 06.05.2019.
8.7. According to the learned counsel, despite receipt of the sanction
memorandum and continuance of banking transactions thereafter, the
plaintiff never unequivocally repudiated the said conditions. Hence, the
plaintiff cannot subsequently contend that there was no concluded contract
between the parties. In this regard, the learned counsel relied upon several
precedents to contend that acceptance may be inferred from the conduct of
Page 21 of 57 https://www.mhc.tn.gov.in/judis
Appeal (CAD) (MD).No.2 of 2025
the parties and surrounding circumstances.
8.8. The learned counsel further submitted that the second limb of
Section 7(2) of the Indian Contract Act has no application to the facts of the
present case and that only the first limb governing absolute and unqualified
acceptance would apply. According to him, once the plaintiff accepted the
benefit of concessional interest without rejecting the facility itself, the
plaintiff cannot selectively repudiate the conditions subject to which such
concessional rate had been granted. Therefore, according to the learned
counsel, the learned trial Judge rightly dismissed the suit, for which reliance
was also placed on several judicial precedents.
8.9. The learned counsel for the bank further submitted that the bank
was fully justified in levying commitment charges once the loan amount had
been sanctioned and earmarked in favour of the plaintiff. Merely because
the plaintiff did not ultimately utilize the sanctioned amount, the same
cannot disentitle the bank from claiming commitment charges. According to
the learned counsel, once an application was made by the plaintiff and the
Page 22 of 57 https://www.mhc.tn.gov.in/judis
Appeal (CAD) (MD).No.2 of 2025
loan was sanctioned by the bank, the liability to pay commitment charges
automatically arose. The subsequent refusal of the plaintiff to avail the
facility on account of disagreement with certain conditions would not
absolve the plaintiff from such liability. In support of the said contention,
the learned counsel also relied upon several documents and precedents.
8.10. The learned counsel appearing for the respondent bank also cited
several judgments of the Hon’ble Supreme Court and various High Courts,
including this Court:
9. This Court shall now consider the rival submissions advanced on
either side, the materials placed on record, and the precedents relied upon by
the respective parties.
10. In this appeal, the following points arise for determination:
i) Whether the clause incorporated in the Sanction
Memorandum dated 06.05.2019 is valid, binding, and
enforceable against the plaintiff?
ii) Whether there was a valid acceptance of the terms
Page 23 of 57 https://www.mhc.tn.gov.in/judis
Appeal (CAD) (MD).No.2 of 2025
and conditions contained in the Sanction Memorandum
dated 06.05.2019, and consequently, whether the
defendant Bank is entitled to claim the differential rate
of interest on the basis of the said memorandum?
11. Discussion on the question “Whether the clause incorporated in
the Sanction Memorandum dated 06.05.2019 is valid, binding, and
enforceable against the plaintiff?”:
11.1. This is a classic case of oppression and commercial coercion
employed by a nationalized bank under the guise of its absolute supervisory
powers over a helpless borrower. The appellant had been maintaining
banking relations with the respondent bank since 1963 and had been
availing working capital facilities on a yearly basis without committing even
a single default. Even according to the bank, the appellant was one of its
most valued customers. However, the appellant’s entire business came to a
standstill because of the arm-twisting methods adopted by the banking
authorities by imposing conditions opposed to public policy, thereby
Page 24 of 57 https://www.mhc.tn.gov.in/judis
Appeal (CAD) (MD).No.2 of 2025
destroying a banking relationship that had subsisted smoothly for more than
fifty years.
11.2. Since the entire claim of the respondent bank is founded upon
the rider clause incorporated in the sanction memorandum dated
06.05.2019, marked as Exhibit A10, it is necessary to briefly examine the
plaintiff's case. The plaintiff has specifically pleaded in para 8 of the plaint
that the rider clause had no legal effect. Hence ,this Court is required to
examine the plaintiff's contention regarding the validity of the rider clause
and for proper appreciation of the controversy, this Court has extracted
rider clause in the sanction memorandum dated 06-05-2019 which reads as
“HO cir 133/2019: In case where the account is taken over by
other banks/FIs, concessions in Rol/ Charges extended for the
last one year to be recovered before closure. (This shall be part
of the sanction conveying letter and accepted by the
borrower.)”
11.3. In the present case, the rate of interest charged by the respondent
Page 25 of 57 https://www.mhc.tn.gov.in/judis
Appeal (CAD) (MD).No.2 of 2025
bank was abnormal and exorbitant in comparison with other Banks .
Therefore,the borrower, who had not committed even a single default for
several decades, was constrained to shift his account to another bank solely
because the other bank offered credit facilities at a substantially lower rate
of interest and he made frequent request to allow multiple banking
operations with Axis bank etc on the account of sufficiency of security.
Despite holding valuable title deeds and securities the value of which was
several times more than the working capital loan facilities , the bank
authorities adopted unfair and oppressive practices to enforce a condition
which is ex facie opposed to public policy.
11.4. It is always open to a borrower to approach any financial
institution or bank of his choice for availing credit facilities. The right to
carry on occupation, trade, and business under Article 19(1)(g) of the
Constitution of India includes the freedom to choose a financial institution
of one’s choice for availing credit facilities. Significantly, the penal clause
imposing prepayment charges for shifting the account to another bank did
not find place in the earlier sanction memoranda issued to the borrower
Page 26 of 57 https://www.mhc.tn.gov.in/judis
Appeal (CAD) (MD).No.2 of 2025
during the longstanding banking relationship prior to the sanction
communications issued during January 2018 and January 2019 and the same
was introduced only after the plaintiff had expressed their intention to
switch over to other bank on the account of exorbitant interest.
11.5.The penal condition imposing 2% prepayment charges merely
because the borrower intended to shift the account to another bank is not
only unconscionable, but also opposed to public policy. A borrower cannot
be compelled to continue with a particular bank against his commercial
interest, particularly when other financial institutions are willing to extend
credit facilities at substantially lower rates of interest. The right of a
borrower to approach another bank for better financial terms forms part of
legitimate commercial freedom and cannot be curtailed by oppressive
contractual stipulations. Furthermore, this court takes judicial notice of the
RBI Fair Practices Code adopted by the respondent Canara Bank, which
mandates transparency, fairness, and non-coercive banking practices in
dealing with borrowers.which also insists to treat the customers as guests.
Page 27 of 57 https://www.mhc.tn.gov.in/judis
Appeal (CAD) (MD).No.2 of 2025
11.6.Further, the conduct of the respondent bank in withholding the
original title deeds and other valuable documents, despite the borrower not
having committed any wilful default, amounts to an unfair banking practice.
The retention of documents solely to prevent the borrower from shifting the
account to another bank clearly reflects arbitrary and coercive conduct
contrary to the RBI Fair Practices Code and established banking norms.
11.7.Therefore, in the above circumstances, the imposition of a
condition restraining the borrower from shifting the account, coupled with a
penal clause demanding 2% prepayment charges, despite repeated
objections raised by the borrower through emails and communications
acknowledged by the bank officials, amounts to imposition of an
unconscionable condition opposed to public policy, violative of the RBI
Fair Practices Code adopted by the respondent Canara Bank and contrary to
the constitutional guarantee under Article 19(1)(g) of the Constitution of
India, namely the right to carry on occupation, trade, and business, which
includes the freedom to choose a financial institution of one’s choice for
availing credit facilities. Therefore, the claim made by the respondent bank
Page 28 of 57 https://www.mhc.tn.gov.in/judis
Appeal (CAD) (MD).No.2 of 2025
on the basis of such a condition is wholly unsustainable and unenforceable
in law. Accordingly, this Court is inclined to set aside the said demand and
constrained to hold that the respondent bank is not entitled to enforce the
penal clause and recover difference of interest as stated in their claim dated
25.09.2020 as in EX.A.21.
12. Discusion on the question “Whether there was a valid acceptance
of the terms and conditions contained in the Sanction Memorandum dated
06.05.2019, and consequently, whether the defendant Bank is entitled to
claim the differential rate of interest on the basis of the said
memorandum”?
12.1. Now the next controversy which revolves around Exhibit A10,
namely, the sanction memorandum dated 06.05.2019 is the question
whether the plaintiff had accepted the rider clause so as to constitute a
concluded and binding contract between the parties and for proper
appreciation of the controversy, this Court has extracted the relevant portion
of the communication of plaintiff dated 06-06-2019 and rider clause as well
Page 29 of 57 https://www.mhc.tn.gov.in/judis
Appeal (CAD) (MD).No.2 of 2025
as the endorsement made by the plaintiff while accepting the sanction
memorandum dated 06-05-2019:
Page 30 of 57 https://www.mhc.tn.gov.in/judis
Appeal (CAD) (MD).No.2 of 2025
Page 31 of 57 https://www.mhc.tn.gov.in/judis
Appeal (CAD) (MD).No.2 of 2025
The material content of the letter dated 03.06.2019 which reads as follows:
Reply from the plaintiff dated 3
rd
June, 2019:
Sl.
No.
Page
No.
Particulars Corrections / Deletion / Remarks
43
HO Cir 133/2019: In case where
the account is taken over by other
Banks/FIs, concessions in
ROI/Charges extended for the last
one year to be recovered before
closure
KLRF does not agree for this
condition. Please delete this clause
We request you to kindly consider our request and accord your approval at
the earliest.
Kindly note that the company has accepted your sanction letter subject to
aforesaid corrections/deletions required to be made therein. This letter is
also part and parcel of the documents be executed by the Company to avail
the working capital facilities.”
12.2. Even prior to the communication of the plaintiff dated
06.16.2019, the plaintiff sent request on 10.01.2019 which reads as follows:
“ We wish to thank you for the revised sanction
memorandum dated 5
th
January 2019 reducing the interest rate
Page 32 of 57 https://www.mhc.tn.gov.in/judis
Appeal (CAD) (MD).No.2 of 2025
from 13.70% to 11.45% per annum.
We refer our letter dated 25
th
Jun 2018, 20
th
Dec 2018 and 3
rd
January 2019 requesting for NOC from Canara Bank for
introducing Axis Bank as a third banker.
We have requested for the interest rate reduction with effect
from 2
nd
May 2018 but we have received the approval for
revised interest on 5th January 2019. Such inordinate delays
have seriously impacted our operations adversely.
As mentioned in our earlier letters HDFC is charging 10.45%
p.a. on our OCC account. We have received an offer from Axis
bank at 10.05% per annum.
We have been instructed by our board of directors to avail the
most competitive rates and hence we would like to bring in Axis
Bank as a third banker and avail Rs.15 Crores working capital
facilities from them. But we will continue to avail Rs. 14.50
Crores (Flour mill division Rs.13.50 Crs and Sheet Metal
division Rs.1.00 Cr) from Canara Bank.
Page 33 of 57 https://www.mhc.tn.gov.in/judis
Appeal (CAD) (MD).No.2 of 2025
Hence, we request you to kindly issue a No Objection
Certificate for the new multiple banking arrangement including
Axis Bank and HDFC Bank.”
12.3. To consider whether the above terms constitute a valid
acceptance in terms of Section 7 of the Indian Contract Act, 1872, the
provisions of Section 7 of the contract extracted hereunder:
“In order to convert a proposal into a promise the
acceptance must—
(1)be absolute and unqualified;
(2)be expressed in some usual and reasonable manner,
unless the proposal prescribes the manner in which it is
to be accepted.
If the proposal prescribes a manner in which it is to be
accepted, and the acceptance is not made in such manner,
the proposer may, within a reasonable time after the
acceptance is communicated to him, insist that his
proposal shall be accepted in the prescribed manner, and
not otherwise; but, if he fails to do so, he accepts the
acceptance”
Page 34 of 57 https://www.mhc.tn.gov.in/judis
Appeal (CAD) (MD).No.2 of 2025
12.4. A reading of Section 7 makes it clear that, in order to convert a
proposal into a promise, the acceptance must be absolute and unqualified. In
the present case, the materials on record indicate that right from the stage
when the respondent bank enhanced the rate of interest, the plaintiff was
exploring the possibility of shifting its banking arrangements to other
institutions offering credit at lower rate of interest. The bank unilaterally
sanctioned the loan vide sanction memorandum dated 6th May 2019
subject to the Rider Clause . However, immediately upon receipt of the
sanction memorandum, the borrower/plaintiff addressed a communication
dated 03.06.2019 seeking deletion of the said Rider Clause. Significantly,
the plaintiff's signature was not obtained on the date of issuance of the
sanction memorandum. The signature was obtained only subsequently, after
the plaintiff had already communicated its objections to the rider clause vide
the communication dated 03.06.2019 with the following response:
“accepted subject to our letter June 3,2019”. In such circumstances, it
cannot be conveniently presumed that there was an unconditional
acceptance of all the terms contained in the sanction memorandum and it is
abundantly clear that his acceptance was conditional upon deletion of the
Page 35 of 57 https://www.mhc.tn.gov.in/judis
Appeal (CAD) (MD).No.2 of 2025
Rider Clause. Such a response cannot prima facie be construed as an
unconditional acceptance; rather, it partakes the character of a counter-offer.
In commercial transactions, once a counter-offer is made, the original offer
does not attain finality unless the counter-offer is accepted or otherwise
dealt with by the offeror.
12.5. In this regard, it is relevant to extract the following principles
of Hon'ble Supreme Court Deokar Exports Private Limited -vs- New India
Assurance Company Limited reported in (2008) 14 SCC 598 relating to
counterproposal and the legal consequences flowing from a counterproposal
and the modes by which such a proposal may be accepted or rejected:
“13. A policy of insurance is a contract based on an offer (proposal)
and an acceptance. The appellant made a proposal. The respondent
accepted the proposal with a modification. Therefore, it was a counter-
proposal. The appellant had three choices. The first was to refuse to accept
the counter-proposal, in which event there would have been no contract.
The second was to accept either expressly or impliedly, the counter-
proposal of the respondent (that is, the respondent's acceptance with
Page 36 of 57 https://www.mhc.tn.gov.in/judis
Appeal (CAD) (MD).No.2 of 2025
modification) which would result in a concluded contract in terms of the
counter-proposal. The third was to make a counter-proposal to the counter-
proposal of the respondent in which event there would have been no
concluded contract unless the respondent agreed to such counter-counter-
proposal.
12.6. From the above, it is clear that in the case of a counterproposal,
three possible courses are available to the original proposer First, the
proposer may reject to the counterproposal. In such an event, no consensus
ad idem arises between the parties and consequently no concluded contract
comes into existence.
Secondly, the proposer may expressly or impliedly accept the
counterproposal. Upon such acceptance, the original proposal stands
superseded and a concluded contract emerges on the terms contained in the
counterproposal.
Thirdly, where a counterproposal is made to the counter proposal
and it has not been accepted by the party, then again, the original proposer
can not say that concluded contract exists.
Page 37 of 57 https://www.mhc.tn.gov.in/judis
Appeal (CAD) (MD).No.2 of 2025
12.7. Applying the above principles to the present case, once the
borrower expressly communicated its unwillingness to accept the rider
clause and sought its deletion, the Bank was required either to reject the
counterproposal or to communicate its insistence upon the rider clause.
However, the Bank did neither. Any response varying the terms of the
proposal or imposing further conditions would amount only to a counter-
offer. The conduct of the parties requires examination in the light of the
principles governing offer, acceptance and counter-offer.
12.8. The communications exchanged between the parties
demonstrate that the borrower had specifically conveyed through repeated
email communications that he was willing to continue the banking
relationship only upon reduction of the rate of interest and removal of the
penal clause relating to shifting of the account to another financial
institution. The sanction letter itself clearly disclosed that the sanction was
“subject to” the borrower’s request made in the letter dated June, 2019.
Page 38 of 57 https://www.mhc.tn.gov.in/judis
Appeal (CAD) (MD).No.2 of 2025
12.9. The usage of the expression “subject to” creates a strong
presumption that the parties never intended to enter into an immediately
binding and concluded contract without the pending issues between them
being expressly resolved. In view of above circumstances, a duty was cast
upon the respondent Canara Bank either to expressly reject the counter-offer
made by the borrower or to refuse continuation of the facility unless the
borrower unequivocally accepted the disputed conditions.
12.10. Thereafter, the Bank neither rejected the said condition nor
reiterated the applicability of the rider clause while extending and operating
the loan facility. A reading of the rider clause in the sanction memorandum
bears the date 06.05.2019, the endorsement made by the plaintiff, and the
subsequent events, particularly the ad hoc extension of working capital
facilities granted under the sanction memorandum dated 22.04.2020 and
sanctioning of two more terms loans without reiterating the said rider
condition amounts “to implied acceptance of the counterproposal”.
12.11. The subsequent conduct of the parties clearly demonstrates that
Page 39 of 57 https://www.mhc.tn.gov.in/judis
Appeal (CAD) (MD).No.2 of 2025
the bank acted upon the plaintiff's conditional acceptance. The continued
conduct of the parties, coupled with the silence of the bank authorities in
not expressly rejecting the borrower’s objections and counter-offer, gives
rise to a deemed acceptance of the modified terms proposed by the
borrower. Therefore, this Court finds that the principle of sub silentio
squarely applies to the facts of the present case. By their conduct and
silence, the bank authorities must be deemed to have accepted the counter-
offer made by the borrower seeking deletion of the oppressive penal clause.
12.12.Therefore, the bank is legally deemed to have accepted the
plaintiff's request for deletion of the Rider Clause. Accordingly, this Court
holds that there was an implied acceptance of the borrower's
counterproposal and a concluded contract came into existence without the
rider clause. Accordingly, this Court holds that the Rider Clause was never
intended to be operative between the parties and was not acted upon. The
borrower had never unconditionally accepted the said condition. The
principle of acquiescence and implied acceptance of borrower's
communication dated 3-6-2019 to delete the rider clause would operate
Page 40 of 57 https://www.mhc.tn.gov.in/judis
Appeal (CAD) (MD).No.2 of 2025
against the bank in the facts of the present case Consequently, the bank is
not entitled to rely upon the said Rider Clause for claiming differential
interest. Any demand founded solely upon the Rider Clause is legally
unsustainable. Hence, the bank has no right to recover the difference in
interest on the basis of the said Rider Clause.
12.13. Once the borrower had discharged the liability and closed the
transaction, the respondent bank could not thereafter invoke a disputed and
unconcluded condition to retain amounts or claim additional charges.
Therefore, the dismissal of the suit filed by the borrower seeking refund of
the excess interest and penal charges suffered from serious legal infirmity.
Consequently, this Court is inclined to set aside the findings of the Court
below and grant appropriate relief in favour of the borrower.
13. Discussion on the question of “Whether the defendant Bank is
entitled to recover commitment charges when the loan amount was
unilaterally credited to the plaintiff's account without obtaining the
plaintiff's signature in token of acceptance of the Sanction Memorandum
Page 41 of 57 https://www.mhc.tn.gov.in/judis
Appeal (CAD) (MD).No.2 of 2025
dated 22.04.2020, 09.09.2020, etc.?”:
13.1. So far as the commitment charges are concerned, the materials
available on record clearly establish that, even prior to the issuance of the
Sanction Memorandum and also subsequent to the Sanction Memoranda
dated 22.04.2020, 09.09.2020 and other relevant dates, the borrower had
specifically communicated to the respondent Canara Bank that he would
avail the proposed loan facility only on the condition that the land and
building pertaining to the sheet metal division is released from the list of
collateral securities. The relevant communications are as follows:
13.1.1. The relevant portions of Ex.A12, being the copy of the
information communicated by the plaintiff to the defendant Bank through e-
mail regarding the resolutions passed on 14.02.2020, read as follows:
“ 8.The board of directors of Kovilpatti Lakshmi Roller
Flour Mills limited has taken policy decision to give only the
respective division's property as collateral security for the
facilities provided. Hence, we request you to release the sheet
metal division's land & buildings situated at
Page 42 of 57 https://www.mhc.tn.gov.in/judis
Appeal (CAD) (MD).No.2 of 2025
Periyanaickenpalayam, total extent of 7.45 acres, given as
collateral security for the working capital facilities.”
13.1.2. The relevant portions of Ex.A17 dated 22.05.2020, being the
copy of the e-mail sent by the plaintiff to the General Manager, Canara
Bank, Madurai, requesting the Bank to take up the matter with the
appropriate authority, read as follows:
“As explained in our various letters and meetings we
would like to request you to reduce the interest rates in line with
the market rates. Presently we have been charged 11.70% p.a.
which is very high as compared to market rates. We understand
that other companies are availing loans at 9.00% p.a for their
facilities.
Canara Bank has sanctioned a term loan of Rs.77 Lakhs
to KLRF for the office modernization at Gangaikondan. Also,
we have received the sanction letter for WCDL of Rs.2.95 crores
from Canara Bank, Sheet metal division's land has been
included as a collateral security in both these sanction letters.
As already communicated, we would like to avail both these
loans subject to removal of Sheet Metal Division's land as
collateral security.
Page 43 of 57 https://www.mhc.tn.gov.in/judis
Appeal (CAD) (MD).No.2 of 2025
Sheet metal unit of the company will be leased and hence
we do not want to renew the sanctioned limit of Rs. 100 Lakhs
for this unit. Hence, we request you to release the sheet metal
property as collateral security.”
13.1.3. The relevant portions of Ex.A19 dated 09.06.2020, being the
copy of the e-mail addressed by the plaintiff to the General Manager,
Canara Bank, Madurai, reiterating its earlier request, read as follows:
“ As explained in our various letters and meetings we
would like to request you to reduce the interest rates in line
with the market rates. Presently we have been charged 11.70%
p.a. which is very high as compared to market rates: We
understand that other companies are availing loans at 9.00%
p.a. for their facilities.
Canara Bank has sanctioned a term loan of Rs.77 Lakhs
to KLRF for the office modernization, at Gangaikondan. Also,
we have received the sanction letter for WCDL of Rs.2.95
crores from Canara Bank. Sheet metal division's land has been
included as a collateral security in both these sanction letters.
As already communicated, we would like to avail both these
Page 44 of 57 https://www.mhc.tn.gov.in/judis
Appeal (CAD) (MD).No.2 of 2025
loans subject to removal of Sheet Metal Division's land as
collateral security.
Sheet metal unit of the company will be leased and hence
we do not want to renew the sanctioned limit of Rs. 100 Lakhs
for this unit. Hence, we request you to release the sheet metal
property as collateral security.
KLRF's cash credit limit was due for renewal on 4th
April 2020 for which we have received temporary extension till
30th June 2020. We would like request you to send us the
renewal for the year 2020-21 with the reduced interest rates
after excluding sheet metal division's land as collateral
security.
Considering our long relationship with Canara bank, we
hope you will consider our requests and approve. If you need
further clarifications, we may have the conference call.”
The borrower had insisted upon such release in view of the fact that the
earlier dues had already been settled without any default and that the yearly
working capital facilities had been regularly serviced for several decades.
Page 45 of 57 https://www.mhc.tn.gov.in/judis
Appeal (CAD) (MD).No.2 of 2025
13.2.The respondent bank, however, did not agree to the said
condition. On the contrary, without obtaining unequivocal and
unconditional acceptance from the borrower, the bank proceeded to
unilaterally sanction and temporarily extend the loan facilities. The
borrower, consistently voicing his objection, ultimately remitted and closed
the entire liability without availing the facility.
13.3. In this case, it is an admitted case of the bank and also finding
of learned trial judge that the Bank sanctioned all the loans unilaterally vide
sanction memorandums without obtaining consent signature of plaintiff and
hence the transactions without signature did not confer any cause of action
to claim Commitment charges. Therefore, the very foundation for levy of
commitment charges is absent in the present case. Commitment charges can
arise only when there exists a concluded contract and when the borrower,
after accepting the sanctioned facility, fails to utilise the same in accordance
with the agreed terms. In the absence of unconditional acceptance by the
borrower, no binding contractual obligation arose so as to enable the
respondent bank to levy commitment charges.
Page 46 of 57 https://www.mhc.tn.gov.in/judis
Appeal (CAD) (MD).No.2 of 2025
14. Discussion on the concept of approbate and reprobate:
The learned Counsel appearing for the bank contended that once the
plaintiff had availed the loan at a concessional rate of interest subject to the
condition that, in the event of transfer of the account to another bank, the
concessional benefit would stand withdrawn and differential interest would
become recoverable, the plaintiff cannot subsequently protest that condition.
According to the learned counsel, such a contention would amount to
rewriting a concluded bilateral contract. He further submitted that a party
cannot approbate and reprobate, namely, accept the beneficial portion of the
contract while rejecting the burdensome portion. Hence, he prayed for
confirmation of the judgment of the court below.
14.1. Per contra, the learned Senior counsel appearing for the
plaintiff submitted that the impugned stipulation was obtained by force,
coercion, and economic duress, and therefore the plaintiff is legally entitled
to challenge the offending clause without repudiating the entire transaction.
According to her, the bank occupied a dominant and advantageous
Page 47 of 57 https://www.mhc.tn.gov.in/judis
Appeal (CAD) (MD).No.2 of 2025
bargaining position, whereas the plaintiff, being financially dependent upon
the working capital facilities for continuation of business, was placed in an
utter disadvantageous position. The bank was also keeping custody of all
original title deeds and security documents of the plaintiff. In such
circumstances, the plaintiff had no other alternative except to submit
unwillingly to the unilateral demand imposed by the bank and make
payment under protest.
14.2.The learned counsel further submitted that the apparent consent
of the plaintiff was not free consent within the meaning of the Indian
Contract Act, but consent was obtained under commercial compulsion and
economic coercion. The bank, taking advantage of its dominant position,
allegedly exerted illegitimate commercial pressure and threatened unlawful
injury to the plaintiff’s economic interests by withholding the release of
securities and denying continuation of essential banking facilities.
Therefore, the consent obtained for incorporation of the disputed clause
stood vitiated by economic duress and undue influence. Such acceptance,
according to the learned counsel, cannot be construed as voluntary assent in
Page 48 of 57 https://www.mhc.tn.gov.in/judis
Appeal (CAD) (MD).No.2 of 2025
the eye of law.
14.3. This Court finds considerable force in the said submission. When
consent to a contractual stipulation is procured by economic coercion,
commercial compulsion, or abuse of dominant bargaining position, the
resultant consent ceases to be free consent. In such cases, it is always open
to the aggrieved party to impeach that particular stipulation which was
incorporated by use of duress, without necessarily repudiating the entire
contract.
14.4. The said principle has been recognized by the Hon’ble Supreme
Court in Central Inland Water Transport Corporation Ltd. v. Brojo Nath
Ganguly reported in AIR 1986 SC 1571, wherein the Apex Court held that
unfair and unreasonable contractual terms imposed by a party enjoying
superior bargaining power are liable to be struck down. The same principle
was elaborately considered by the Bombay High Court in the judgment
reported in AIR 1992 Bombay 309, wherein it was observed that it is open
Page 49 of 57 https://www.mhc.tn.gov.in/judis
Appeal (CAD) (MD).No.2 of 2025
to the victim of duress to impugn that part of the transaction or stipulation
which had been incorporated by use of coercive pressure.
14.5. Therefore, the contention of the learned counsel for the bank that
the plaintiff cannot selectively challenge a clause in a concluded bilateral
contract cannot be accepted in the peculiar facts and circumstances of the
present case. If a particular stipulation has been imposed by exerting
economic duress, undue influence, or coercive commercial pressure, the
affected party is legally entitled to repudiate that offending portion and seek
recovery of the amount wrongfully recovered by the bank.
15. Discussion on the trial court finding:
15.1.Since the plaintiff's response amounted to a counter-offer, a
corresponding duty arose on the part of the respondent bank either to reject
the counter-offer and decline the facility or to expressly communicate its
acceptance of the modified terms. The learned Trial Judge, however, appears
to have proceeded on the premise that the burden was upon the plaintiff to
reject the facility altogether. Such an approach, in the considered view of
Page 50 of 57 https://www.mhc.tn.gov.in/judis
Appeal (CAD) (MD).No.2 of 2025
this Court, overlooks the legal consequences flowing from a qualified
acceptance under Section 7 of the Contract Act. Without considering the
principles governing acceptance under Section 7 of the Indian Contract Act,
the learned Judge proceeded solely on the basis that there existed a
continuing lender–borrower relationship between the parties pursuant to the
sanction memorandum dated 06.05.2019. On that basis, the learned Judge
held that there was an implied acceptance of the terms contained in the
sanction memorandum. Such a finding was rendered without identifying any
positive act on the part of the plaintiff either accepting the rider clause or
otherwise signifying assent to the modified terms. Mere continuation of the
loan relationship or availing of the facility, in the facts and circumstances of
the present case, cannot by itself constitute implied acceptance, particularly
when the plaintiff had specifically communicated his objection to the rider
clause and had accepted the sanction memorandum only subject to the
conditions contained in his letter dated 03.06.2019.
15.2.The said finding is fundamentally contrary to the settled
principles governing acceptance and counter-offer under Section 7 of the
Page 51 of 57 https://www.mhc.tn.gov.in/judis
Appeal (CAD) (MD).No.2 of 2025
Indian Contract Act. Once the plaintiff had proposed a variation to the rider
clause, the original proposal could not be treated as accepted unless the
bank expressly or impliedly assented to such variation. In the absence of
such assent, no concluded contract incorporating the disputed rider clause
could have legally come into force Therefore, this Court is unable to concur
with the finding of the learned Judge that there was an implied acceptance
of the rider clause. Consequently, the finding of the learned Judge on this
aspect is liable to be set aside.
15.3.Furthermore, the learned Judge failed to appreciate that the
subsequent conduct of the parties clearly indicates an unequivocal
acceptance of the plaintiff's counter-proposal contained in the
communication dated 03.06.2019. Applying the principles of implied
acceptance and acceptance sub silentio, the conduct of the bank in
proceeding with the transaction without rejecting the plaintiff's stipulation
amounts to absolute assent to the modified terms proposed by the plaintiff.
Once the plaintiff had accepted the sanction memorandum subject to the
deletion or modification of the rider clause, the said communication legally
Page 52 of 57 https://www.mhc.tn.gov.in/judis
Appeal (CAD) (MD).No.2 of 2025
constituted a counter-proposal. The subsequent acts of the bank, viewed in
their entirety, demonstrate a clear acceptance of such counter-proposal. In
such circumstances, the contractual relationship between the parties could
only be governed by the terms emerging from the counter-proposal and its
subsequent acceptance. Therefore, this Court is unable to agree that the rider
clause continued to form part of the contract between the parties. On the
contrary, the materials available on record indicate that the rider clause
stood superseded by the plaintiff's counter-proposal, which was accepted by
the bank through its conduct and silence coupled with subsequent
performance.
15.4.The learned counsel appearing for the Bank would contend that
the case is covered under Section 7(2) of the Indian Contract Act, 1872,
which provides that where a proposal does not prescribe the manner in
which it is to be accepted, the acceptance may be expressed in some usual
and reasonable manner. According to the learned counsel, it is the routine
practice of the Bank to grant renewal and ad hoc facilities on the same terms
and conditions that existed earlier, and therefore the rider clause contained
Page 53 of 57 https://www.mhc.tn.gov.in/judis
Appeal (CAD) (MD).No.2 of 2025
in the sanction memorandum dated 06.05.2019 must be deemed to have
been accepted by the plaintiff.
15.5.This Court is unable to accept the said contention. Firstly, as
already discussed in the preceding paragraphs, the sanction memorandum
dated 06.05.2019 did not amount to a valid acceptance of the alleged rider
clause so as to constitute a concluded contract between the parties.
Secondly, except making a bald assertion that the subsequent credit facilities
were sanctioned on the same terms and conditions, the Bank has failed to
adduce any acceptable evidence to establish the existence of such a usual
and reasonable practice. On the contrary, the officials examined on behalf of
the Bank have categorically admitted in their evidence that the plaintiff had
not affixed his signature in any of the documents relating to the subsequent
ad hoc credit facilities or term loan transactions. No material has been
produced to show that the alleged condition was expressly carried forward
and accepted by the plaintiff on each subsequent occasion. In the absence of
any documentary evidence, this Court cannot presume the continuation of
such a condition merely on the basis of the Bank's bare assertion.
Page 54 of 57 https://www.mhc.tn.gov.in/judis
Appeal (CAD) (MD).No.2 of 2025
15.6.Further, the records explicitly disclose that prior to the year
2018, no such condition was ever incorporated in any of the sanction
memoranda issued by the Bank. It is also relevant to note that another
financial institution, namely HDFC Bank, held a pari passu charge over the
assets along with Canara Bank. In such circumstances, the contention that
the alleged rider clause formed part of a usual and reasonable banking
practice, or that it stood automatically incorporated into the subsequent
transactions, is wholly unsustainable. Accordingly, the submission of the
learned counsel for the Bank that the case falls within the ambit of Section
7(2) of the Indian Contract Act is entirely misconceived.
16. Conclusion:
Accordingly, the Commercial Appellate Division stands allowed with
cost by setting aside the judgment and decree dated 05.11.2024 made in
O.S.No.148 of 2021 (Commercial Original Suit) on the file of the learned
Principal District Judge, Tirunelveli, and the plaintiff is entitled for decree
for the amount of Rs.46,75,422/- with interest at the rate of 7.5% from the
Page 55 of 57 https://www.mhc.tn.gov.in/judis
Appeal (CAD) (MD).No.2 of 2025
date of plaint till the date of recovery.
[N.A.V, J.] & [K.K.R.K,J.]
23.06.2026.
NCC : Yes/No
Index : Yes/No
Internet : Yes/No
pal
To
1.The Principal District Judge,
Tirunelveli.
2.The Record Keeper,
Vernacular Section,
Madurai Bench of Madras High Court,
Madurai.
Page 56 of 57 https://www.mhc.tn.gov.in/judis
Appeal (CAD) (MD).No.2 of 2025
N.ANAND VENKATESH, J.
and
K.K.RAMAKRISHNAN, J.
pal
PRE-DELIVERY JUDGMENT made in
Appeal (CAD) (MD).No.2 of 2025
Dated: 23.06.2026
Page 57 of 57 https://www.mhc.tn.gov.in/judis
In a significant judgment, the Madras High Court, Madurai Bench, recently delivered a ruling in Appeal (CAD) (MD).No.2 of 2025, shedding light on critical aspects of the Indian Contract Act Section 7 and Banking Law Disputes India. This case, now prominently featured on CaseOn, serves as a crucial precedent for understanding contractual obligations and the enforceability of banking terms. The court meticulously examined the concepts of conditional acceptance, implied contracts, and the impact of economic coercion in commercial lending, ultimately siding with the borrower against the bank's contested claims for differential interest and commitment charges.
CaseOn.in offers 2-minute audio briefs for rulings like this, helping legal professionals quickly grasp the essence and implications of complex judgments.
The core of this appeal revolved around two principal issues arising from a banking relationship between M/s. Kovilpatti Lakshmi Roller, Flour Mills Limited (the plaintiff/appellant), and M/s. Canara Bank (the defendant/respondent):
Was the rider clause incorporated into the Sanction Memorandum dated 06.05.2019 valid, binding, and enforceable against the plaintiff? Specifically, was the defendant bank entitled to claim differential interest based on this clause, which stipulated that concessions on the Rate of Interest (RoI) or charges would be recovered if the account was taken over by another bank?
Was the defendant bank entitled to recover commitment charges when the loan amount was unilaterally credited to the plaintiff's account without obtaining the plaintiff's signature as a token of acceptance of the Sanction Memorandum?
To address these issues, the court invoked several key legal principles and guidelines:
This fundamental section mandates that for a proposal to convert into a promise (i.e., a binding contract), the acceptance must be absolute and unqualified. Any acceptance that varies the terms of the original proposal constitutes a counter-offer, which then requires acceptance from the original proposer.
The court considered whether contractual conditions that are unconscionable, oppressive, or restrict a borrower's commercial freedom violate public policy. Specifically, the right to carry on occupation, trade, and business under Article 19(1)(g) of the Constitution of India includes the freedom to choose financial institutions for credit facilities. Penal clauses that force a borrower to remain with a bank or penalize them for shifting accounts might be struck down if they are found to be unfair and unreasonable, especially when imposed by a party with superior bargaining power.
While acceptance can sometimes be implied by conduct, it must be unequivocal. If a party makes a counter-offer and the other party acts upon it without expressly rejecting it, this can amount to an implied acceptance of the modified terms.
Consent obtained under commercial compulsion, economic duress, or abuse of a dominant bargaining position is not considered 'free consent' under the Indian Contract Act. Such stipulations, even if signed under protest, can be challenged.
The Reserve Bank of India's Fair Practices Code, adopted by banks like Canara Bank, mandates transparency, fairness, and non-coercive banking practices in dealing with borrowers. Practices contrary to these guidelines can be deemed illegal.
The plaintiff had a long-standing relationship with Canara Bank since 1963, consistently availing working capital facilities without default. However, in 2018, the bank unilaterally increased the interest rate, prompting the plaintiff to explore options with other banks offering lower rates. When the bank issued a sanction memorandum on 06.05.2019 with a reduced interest rate (11.50%), it included a rider clause (HO Cir 133/2019) allowing recovery of interest concessions if the account was taken over by another bank. This was a new condition, not present in earlier sanction memoranda.
Crucially, the plaintiff immediately responded on 03.06.2019, explicitly objecting to this clause and requesting its deletion. The plaintiff's subsequent acceptance of the sanction memorandum was qualified with the endorsement: "accepted subject to our letter June 3, 2019." This act, according to Section 7 of the Indian Contract Act, constituted a counter-offer, not an absolute acceptance.
The bank, however, neither expressly rejected this counter-offer nor insisted on the original rider clause. Instead, it continued to extend credit facilities and sanctioned new term loans without reiterating the disputed condition. The court found that this conduct by the bank, coupled with its silence, amounted to an implied acceptance of the plaintiff's counter-offer to delete the rider clause. Therefore, the rider clause was never operative between the parties.
Furthermore, the court deemed the rider clause itself unconscionable and opposed to public policy. It restricted the borrower's commercial freedom to seek better financial terms, violating Article 19(1)(g) of the Constitution and going against the spirit of the RBI Fair Practices Code. The bank's act of withholding original title deeds and documents to prevent the borrower from shifting accounts was also criticized as an unfair banking practice and an arbitrary, coercive conduct.
Regarding commitment charges, the plaintiff consistently communicated that it would avail proposed loan facilities only on the condition that the land and building pertaining to the sheet metal division be released from collateral securities. Despite this, the bank unilaterally sanctioned and temporarily extended loan facilities, even crediting amounts, without obtaining the plaintiff's consent signature for these transactions. The plaintiff ultimately remitted and closed the liability without availing the facility due to the bank's conditions.
The court ruled that commitment charges can only arise from a *concluded contract* where the borrower has accepted the sanctioned facility unconditionally and then failed to utilize it. In this case, the absence of the plaintiff's unconditional acceptance and signature on the relevant sanction memoranda meant that no binding contractual obligation for commitment charges arose. The bank failed to provide evidence of any 'usual and reasonable practice' that would automatically incorporate such conditions, especially when the plaintiff had explicitly made its acceptance conditional on the release of collateral. The Trial Court's finding that the plaintiff should have expressly refused the loan was deemed erroneous, as the burden was on the bank to respond to the counter-offer.
The Commercial Appellate Division unequivocally allowed the appeal, setting aside the judgment and decree of the Principal District Judge, Tirunelveli. The court concluded that:
Consequently, the plaintiff was awarded a decree for the amount of Rs.46,75,422/- with interest at the rate of 7.5% from the date of the plaint until the date of recovery.
This judgment is an essential read for legal professionals and students for several reasons:
Disclaimer: All information provided herein is for informational purposes only and does not constitute legal advice. Readers are advised to consult with a qualified legal professional for advice pertaining to their specific circumstances.
Legal Notes
Add a Note....